SlideShare ist ein Scribd-Unternehmen logo
1 von 27
Downloaden Sie, um offline zu lesen
Balance of Systems- Solar PV Project
Gensol Engineering Pvt Ltd
Balance of Systems (BOS)
• Inverters
• Mounting & Racking Systems
• Electrical Equipment and Installation
• Cabling-AC & DC
• Transformers & Breakers
• Combiner Boxes
• Earthing
• Transmission Line, etc
• Civil Work & Development
• Inverter Rooms, CMCS
• Roads, Boundary, Drainage, Cleaning Systems, etc
• Land
• Miscellaneous
All components of a photovoltaic system other the photovoltaic
panels
“
”
BOS Trends
-10.00
10.00
30.00
50.00
70.00
90.00
110.00
2010-11 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17
Normalized	Value
N ormalized	CERC	P V	Cost	Cu rves
Project	Cost Module	Cost BOS	Cost
0.00%
20.00%
40.00%
60.00%
80.00%
100.00%
2010-11 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17
Module-BOS	Cost	Breakup
Module	 BOS
• Module cost curve has
outrun BOS cost curve
• BOS optimization from
2013-14
• Module:BOS at 65:35
• Module CARR~ 9%
• BOS CARR ~8%
Cost Breakup
Head Components Trend
Inverters
Mounting	Structures MMS,	Fasteners, Installation
Civil Works	&	Development Rooms,	Roads,	Boundary,	Drainage,	Cleaning,	etc
Electrical	BOS Cabling,	Transformers, Breakers,	Combiner	Boxes,	Earthing,	etc
Land
Miscellaneous CCTV,	Monitoring,	etc
Module
65%
Inverters
4%
Mounting	
Structures
7%
Civil	Works	&	
Development
7%
Electrical	BOS
10% Land
6%
Miscellaneous
1%
Solar	Project	Cost	Breakup
BOS Reduction due to Module Efficiency
• Efficiency of average commercial wafer based silicon module has grown from
10% to 17% in last 10 years
• Best efficiency multi-crystalline module: 19.2%
Source: Fraunhofer ISE, 2016
BOS Reduction due to Module Efficiency
Impact of increase in module efficiency
Item Components Saving	Trend
Scalable DC	Cabling,	Structures, SCBs,	
Connectors,	Land
Semi-Scalable Roads,	Periphery,	Drains,	Lighting
Neutral AC	BOS,	Evacuation, etc
0.0%
2.0%
4.0%
6.0%
8.0%
10.0%
12.0%
14.0%
16.0%
18.0%
Efficiency DC	Works Structure Ass.	Civil	Work Land
0.0% 0.0% 0.0% 0.0% 0.0%
8.3% 8.0% 7.7%
6.0%
7.7%
16.7%
14.1%
16.7%
11.1%
14.2%
%	Cost	Savings
Cost	Savings- Efficiency	Increase
300W 325W 350W
For every 5W increase
in module wattage
• project costs
decrease by 0.27%
• BOS costs reduce
by 0.8%
BOS Reduction due to Overloading (DC:AC)
Impact of increase in overloading (DC:AC)
Item Components Saving	Trend
Neutral DC	Cabling,	Structures, SCBs,	Connectors,	
Land
Semi-Scalable Roads,	Periphery,	Drains,	Lighting
Scalable AC	BOS,	Evacuation, etc
BOS Reduction due to Overloading (DC:AC)
1.00	
0.96	
0.94	
0.92	
0.91	
0.90	
1.000	
0.984	 0.979	 0.972	 0.968	 0.962	
0.84	
0.86	
0.88	
0.90	
0.92	
0.94	
0.96	
0.98	
1.00	
1.02	
0 10% 15% 20% 25% 30%
Normalization	Factor
Overloading(%)
Effect	of	Overloading	on	Plant	Costs
Normalized	BOS	Cost/Wp Normalized	Cost/Wp
1.000	
1.083	
1.125	
1.167	
1.209	
1.251	
1.00	
1.10	
1.15	
1.20	
1.25	
1.30	
1.000	
1.050	
1.100	
1.150	
1.200	
1.250	
1.300	
0 10% 15% 20% 25% 30%
NORMALIZED	GAIN
OVERLOADING(5)
Cost	Benefit	Analysis	Of	Overloading
Normalized Normaized	Enegy	Gain
For every 10% increase in
overloading
• project costs decrease
by 1.25%
• BOS costs reduce by
3.5%
Cost Benefit Analysis
• Till Generation gain
surpasses increase in
cost
DC Cabling & Combiner Boxes
DC side cabling costs have decreased by about 40% due to efficient
design in the last few years
Smart DC Block Sizing
55:45 65:35 75:25
55:35 65:35 75:25
Cost(%) 100% 115% 124%
Loss(%) 100% 113% 120%
Overall	Cost(INR/Wp) 0.23 0.37
• Big Plant sizes allow DC block sizing optimization
DC Cabling & Combiner Boxes
String Fusing by Y-connectors-> Solar Cable & SCB Cost reduction by around
30%
String Monitoring removed, relying on inverter zone monitoring
Item Saving
Solar	Cable 32%
SCB 26%
Overall 28%
Leap Frogging saves 25% cable cost in the case of tracker
With effective design optimization on the DC side, a reduction
of 1.1% and 3.6% on project cost and BOS can be achieved“
Inverters & Transformers
Inverters
• Inverter costs have reduced by more than 70% from 2010-11
• Driven by
o Scale of Production (Inverter learning rates vary from 18-20%)1
o Technological advancements:
Ăź Material (SiC, GaN)
Ăź Block Size
Ăź Voltage Increase (1500V)
o Localization
• Inverters are predicted to see price reductions of 8-9% per annum upto 20202
Tranformers
• Have shown reduction in costs in recent years due to:
• Higher transformer capacities due to bigger block size
• Metal Prices
• Multi- winding transformer (5-winding, 7 winding) resulting in BOS optimization
Source: 1. Fraunhofer ISE, 2015
2 Greentech Media, 2015.
Case Study: Impact of Block Size on BOS
Case: 65MW Plant with 5 nos. Of 10MW
and 1 no. of 15MW Block Feeder
Comparison	for	use	of	various	Transformer	winding	options	
(5	Nos.	of	10MW	Feeders	&	1	No.	of	15MW	Feeder)
S.No Parameter Case	1 Case	3
Inverter	 Room	with	2	Inverters	&	3	
Winding	Transformer	(1No.)
Inverter	 Room	with	4	Inverters	&	5	
Winding	Transformer	(1No.)
1 Design	Type 2.5MVA	Block	with	3-winding	Xmer 5MVA	Block	with	5-winding	Xmer
3 No.	of	Inverter	Transformers 26	Nos.	(2.5	MVA	Capacity) 13	Nos.	(5MVA	Capacity)
4 No.	of	Aux.	Transformers
26	Nos.	(One	Aux	Trasf	for	each	
Inverter	 room)
13	Nos.	(One	Aux	Trasf	for	each	
Inverter	 room)
5 No.	of	UPS
26	Nos.	(One	UPS	for	each	Inverter	
room)
13	Nos.	(One	UPS	for	each	Inverter	
room,	but	size	of	UPS	will	be	almost	
twice	compared	to	Case	1)	
6 No.	of	VCBs
58	Nos.	VCB	(630A)	&	3Nos.	VCB	
(1600A)
32	Nos.	VCB	(630A)	&	3Nos.		VCB	
(1600A)
7
DC	Power	cable	(SMB	to	Inverter	
Cable)
45000	Mtrs	(150	Sqmm)	&	70000	
Mtrs	(185	Sqmm)
60000	Mtrs	(150	Sqmm)	&	90000	
Mtrs	(185Sqmm)
8 HT	Cable	
13650	Mtrs	(3Cx120	Sqmm),	3560	
Mtrs	(3Cx240	Sqmm),	600	Mtrs	
(3Cx300	sqmm)
3950	Mtrs	(3Cx240Sqmm),	4320	
Mtrs	(3Cx300	sqmm)
9
Aux	Power	Cable	(3Cx1.5	sqmm	
Cu.)
22815	Mtrs 31900	Mtrs
10 Communication	Cable	(RS	485) 18590	Mtrs 26050	Mtrs
11 Communication	Cable	(OFC) 31330	Mtrs 12560	Mtrs
12 HDPE	Pipes 49950	Mtrs 38610	Mtrs
13
No.	of	PEB	Inverter	Rooms	(Pre	
Engineered	 Building)
26 13
14
Size	of	each	Inverter	 Room	
(Approx)
8.5m	x	6m 14.5m	x	6m
15 Transformer	 foundation 26	Nos. 13	Nos.
16 CCTV
32	Nos.	of	HD	PTZ	type	&	7	Nos.	of	
HD	Fixed	type
19	Nos.	of	HD	PTZ	type	&	7	Nos.	of	
HD	Fixed	type
Item Savings	
(INR/W)
1. Tranformers +Aux.+	
UPS
0.06
2. Switchgear 0.25
3. Cables	(Power	+	Aux.	
+	Communication)
0.08
4. Civil	Work 0.06
Saving of INR 0.45/W due to
Block Size Increase and use
of 5-winding Transformer
“
”
1500V Inverter
Advantages
• Higher DC and AC voltage i.e. lesser current and lesser cabling
• Lesser current allows the increase in inverter block power, lesser BOS
• 50% longer strings, implying lesser strings, and 33% lesser junction boxes
• Lesser monitoring, and economical installation
• IEC certifications are in place
• Higher yield
Disadvantages
• Component availability limited at present, thus driving BOS costs higher
• Higher inverter costs due to 1500V components
1500V v/s 1000V
Comparison of 1500V v/s 1000V
Item Remarks Savings	(%) Savings	
(INR/Wp)
Saving	
Trend
PV	Modules 0.5	USD	cents	higher	for	1500V -1.15% -0.34
DC	Cables
Quantity Saving	~30%
Unit	Cost	considered	10%	extra	
for	1500V 22.22% 0.16
SCB
Quantity Saving	~32%
Unit	Cost	considered	25%	extra	
for	1500V 15.70% 0.05
AC	Subsystem
Inverter Trafo,	LT	Cable,	Aux.	
Trafo 11.44% 0.08
Inverter
25%	higher	cost
-25.00% -0.44
Civil	&	Labour
Inverter	Pad	for	1500V,	Room	
for	1000V.	Installation	Labour	
work	reduction	by	10%	assumed 31.08% 0.22
Overall -0.83% -0.28
1500V v/s 1000V
Comparison of 1500V v/s 1000V (Alternate Optimization)
• For same DC ohmic losses, a 7.5MW block can be formed in 1500V when
compared to 5MW block
• Bigger block size would mean optimization can be carried on AC side
1500V
7.5MW
1000V
5	MW
Land
• The cost of land for solar projects has risen about 6-10 times as compared to
2010-11
• Not only expensive, but difficulties in acquisition
• As the cost of PV modules decrease, land use optimization by decreasing the
tilt, and increasing the power density (kW/sqm)
East-West Mounting
• For places closer to equator, i.e. latitude <10°, solar modules can be mounted
in east west fashion at low tilt angles (around 3°)
• High land utilization, with GCR>80% can be achieved
• Wider peak
• Lesser structure and foundation cost
• Lesser BOS cost
• Marginal drop in generation
East-West Mounting
-11.98%
-14.47%
-11.55%
-12.15%
-11.08% -10.98% -11.12%
-7.68%
-4.22% -3.90% -4.31% -4.26%
-3.70% -3.81%
-4.81%
-3.72%
-2.62%
-1.73%
30.16 28.59 26.84 24.97 23.76 23.07 22.31 22.36 21.32 18.52 17.38 14.66 14.29 13.14 11.87 9.9 9.36 8.36
GENERATION	REDUCTION%
LATITUDE
East	West	 Mounting	v/s	South	 Facing
Shift from Fixed to Seasonal – How numbers work
• 20 X 315Wp modules in series = 6.3kWp = 1 Table
• 1MWp = 160 Tables (approx.)
• A team of 3 persons will take 15 minutes to change tilt of 1 table
(on an average), hence, 32 tables per day.
• Five such teams i.e 15 persons per day shall be able to change
tilt of 1MWp installation.
• At a labour rate of Rs. 350/- per day, it takes less than Rs. 6000
to change tilt of 1MWp installation.
• Assuming an increment of 3T / MWp between fixed and seasonal
tilt, additional capex comes out to be Rs. 2.4Lacs approx.
Structure Trend - Seasonal Tilt - Y 2014 – 60T
S.No Description Section Size
Length
(m)
Tot.
Quantity
Unit Weight
(kg/m)
Tot. Wt. (kg)
1) Column Post 130CU60x5 2.80 656 9.42 17302.66
2) Rafter 120CS50x18x3 3.375 656 5.74 12708.36
3) Purlin
130CS50x14x1.
5
4.97 1312 2.96 19301.09
4) Side Bracing-1 L-55x55x5 1.28 984 4.12 5189.222
5) Side Bracing-2 L-55x55x5 1.49 656 4.12 4027.053
6) Connection plate 0.265 656 1.04 682.24
6) Connection Cleat 0.167 2624 0.157 411.968
7) SQ. Washer 0.05 3936 0.0589 231.8304
Total Structural Steel Qty. (kg) 59854.42
Say 60 Ton
Structure Trend - Seasonal Tilt - Y 2015 – 40T
Module Mounting Structural Steel Qty.
Description
Sectional
Details
Quantity
/Table
Grade of
Steel
Finish
Length
(m)
Unit. Wt
(Kg/m)
Component
wt. (kg)
Quantity/
MW
Total Wt
(Kg)
Column 120CU50x3.15 5 350 Mpa GAL 2.390 5.10 12.189 835 10177.82
Washer Plate PLT 50x50x5 10 250 Mpa GAL 0.050 1.96 0.098 1670 163.87
Rafter 100CU50x2 5 350 Mpa GAL 2.910 3.00 8.730 835 7289.55
Purlin (A) 70CS40x15x1.2 4 350 Mpa GAL 3.460 1.61 5.576 668 3724.63
Purlin (B) 70CS40x15x1.2 4 350 Mpa GAL 5.195 1.61 8.372 668 5592.32
Purlin (C) 70CS40x15x1.2 4 350 Mpa GAL 3.460 1.61 5.576 668 3724.63
Side Bracing-1 40CU40x2 5 350 Mpa GAL 1.270 1.75 2.223 835 1855.79
Side Bracing-2 40CU40x2 5 350 Mpa GAL 1.470 1.75 2.573 835 2148.04
Connection
Plate-1 330x100x4
5
250 Mpa GAL
0.330 3.140
1.036 835 865.23
Connection
Plate-2 265x100x4
5
250 Mpa GAL
0.265 3.140
0.832 835 694.80
Connection angleL PLT 70x70x3 20 250 Mpa GAL 0.110 3.23 0.355 3340 1185.23
Tie Rod 12mm dia 8 250 Mpa GAL 0.965 0.889 0.858 1336 1145.99
Total Weight Per MW 38567.89
Spare 3 % 1157.04
Say 40 Ton
Pre Fab rooms and Decking Sheets
• Pre fab rooms offer significant time advantages in execution timelines
hence bring generation gains and more efficient supplies
• Instances where Pre fab buildings are not considered, decking sheets with
concrete layer on top can offer same benefits. It provides both required
strength, insulation and quicker installation benefits
Wind Shielding of Outer most structures
• Recent designs leverage on the density of array yard and consider lower
values of k2 factor in design calculations of structures.
• Outer rows are designed with higher sections as they have more impact of
wind speeds, however inner rows are designed 10-15% lighter to leverage
the shielding that outer structure provides
The 0.8mm Galvalume! In Sub 30 T structures!
One name that has echoed in procurement teams lately.
It’s a fine play and tight walk on the line between Optimization and Under design
Galvalume suits fixed tilt structures and can be very good for optimization
Use of galvalume in seasonal tilt structures has seen many failures recently and
resulted in loss of PV modules & of course generation
Extra caution to be exercised while tilting galvalume based structures and must
be done only using proper jacks. Manual tilting is a strict no, if not particularly
addressed during Engineering
Cost Saving by Internal Transmission Line
Site specific: If land is not highly constrained, and HT cables are running along
northern boundary
Pros:
• Cheaper compared to HT cable (30-40% lesser at full load evacuation)
• Maintenance friendly, and lesser probability of fault
• Higher current carrying capacity. New age AAAC panther conductors can carry
25MW on single circuit, whereas typical 33kV cables will take around15MW
Cons:
• Land wastage around poles due to shadow
• Land wastage can be minimized by planning TL along boundary, and suitably
oriented to north direction
Future Trends
Main Drives of BOS Cost Reduction in future
• Best practices assimilation across the industry
• Module efficiency
• Technological developments
• Incremental design improvements, such as higher overloading, mounting
structure, block size, etc
• Localization including streamlined logistics
• Increase in market volume
• Automation in production, development and installation
Based on the above factors and historical trends, we foresee a BOS cost
reduction of 30%-35% by 2020
About Gensol
Gensol, found in 2007 is India’s leading Advisory and System Integrator for Solar
PV Power Projects. Gensol is a channel partner to MNRE and enjoys
empanelmentwith most major Lending Institutions in India.
2,500+ MW 12,000+ kW
Gensol has an advisory portfolio of
more than 2.5 GW with every 5th
MW
in India developed with our expertise.
Being an MNRE Channel partner,
Gensol has executed more than 12
MW of Solar Rooftop Projects across
India.
Gensol is based out of Ahmedabad in
Gujarat but has operational solar
projects across 16 Indian States.
With a 130+ Employee Strength –
Gensol prides itself on having the
best technical talent in industry.
AWARDS
BusinessWorld – India’s largest
weekly business magazine awarded
Gensol with “Hottest Young
Entrepreneur” in 2009.
Economic Times – India’s largest
financial daily awarded Gensol in its
“Power of Ideas” series in 2010.
Gensol was the only non-UK based
firm to be nominated for Global
Consultancy of the Year at
BusinessGreen Leader Awards,
London in 2014.
Gensol Engineering Pvt Ltd | Gensol Consultants Pvt Ltd
Corporate Office
108, Pinnacle Business Park
Opp Royal Arcade, Prahladnagar
Ahmedabad, Gujarat
India - 380015
Email: solar@gensol.in
Website: www.gensol.in
Phone: +91 79 40068235
Fax: +91 79 40068239
Twitter: gensol_tweets
Gensol is one of the leading consultants and system integrators for Solar Power Plants. We boast of a portfolio of over
2500 MW of Solar Photovoltaic Plants. Gensol is also a channel partner to Ministry of New & Renewable Energy and
installs kW scale Solar Rooftop systems on a turnkey basis with more than 15 MW of cumulative installations across the
country.
The information contained herein is of a general nature and is not intended to address the circumstances of any particular
individual or entity.Although we endeavor to provide accurate and timely information,there can be no guarantee that such
information is accurate as of the date it is received or that it will continue to be accurate in the future. No one should act on
such information withoutappropriate professional advice after a thorough examination ofthe particular situation.

Weitere ähnliche Inhalte

Was ist angesagt?

How solar rooftop system works
How solar rooftop system worksHow solar rooftop system works
How solar rooftop system worksHardik Parmar
 
Study of Large Scale Grid interactive Solar PV power plant
Study of Large Scale Grid interactive Solar PV power plantStudy of Large Scale Grid interactive Solar PV power plant
Study of Large Scale Grid interactive Solar PV power plantShahbaz Makandar A.
 
Solar power plant presentation.pdf
Solar power plant presentation.pdfSolar power plant presentation.pdf
Solar power plant presentation.pdfAmarRajAnand
 
Design off grid solar PV system
Design off grid solar PV systemDesign off grid solar PV system
Design off grid solar PV systemRajesh Pindoriya
 
Engineering Drawings required for Solar Projects
Engineering Drawings required for Solar Projects Engineering Drawings required for Solar Projects
Engineering Drawings required for Solar Projects Gensol Engineering Limited
 
Photovoltaic Training - Session 1 - Design
Photovoltaic Training - Session 1 - DesignPhotovoltaic Training - Session 1 - Design
Photovoltaic Training - Session 1 - DesignLeonardo ENERGY
 
Indian Solar Rooftop PV - A Bright Investment (21.08.18)
Indian Solar Rooftop PV - A Bright Investment (21.08.18)Indian Solar Rooftop PV - A Bright Investment (21.08.18)
Indian Solar Rooftop PV - A Bright Investment (21.08.18)Gensol Engineering Limited
 
Webinar 02 demonstration of pv system design pvsyst
Webinar 02 demonstration of pv system design pvsystWebinar 02 demonstration of pv system design pvsyst
Webinar 02 demonstration of pv system design pvsystsolpowerpeople
 
Designing Solar PV Systems ( Utility Scale)
Designing Solar PV Systems ( Utility Scale)Designing Solar PV Systems ( Utility Scale)
Designing Solar PV Systems ( Utility Scale)Sunrator Technologies LLP
 
Photovoltaic(pv) module and transparent solar panels
Photovoltaic(pv) module and transparent solar panelsPhotovoltaic(pv) module and transparent solar panels
Photovoltaic(pv) module and transparent solar panelspadamatikona swapnika
 
Gensol Group Profile - Solar Advisory, Solar Rooftop EPC, Solar O&M (13.12.17)
Gensol Group Profile  - Solar Advisory, Solar Rooftop EPC, Solar O&M (13.12.17)Gensol Group Profile  - Solar Advisory, Solar Rooftop EPC, Solar O&M (13.12.17)
Gensol Group Profile - Solar Advisory, Solar Rooftop EPC, Solar O&M (13.12.17)Gensol Engineering Limited
 
Basic Introduction to solar PV System.
Basic Introduction to solar PV System.Basic Introduction to solar PV System.
Basic Introduction to solar PV System.Urval Chotalia
 
PPT OF SOLAR NAVEEN' `11
PPT OF SOLAR NAVEEN' `11PPT OF SOLAR NAVEEN' `11
PPT OF SOLAR NAVEEN' `11naveen bhati
 
Solar Panel Installation Proposal PowerPoint Presentation Slides
Solar Panel Installation Proposal PowerPoint Presentation SlidesSolar Panel Installation Proposal PowerPoint Presentation Slides
Solar Panel Installation Proposal PowerPoint Presentation SlidesSlideTeam
 
Design and performance analysis of 500 KWp on-grid solar PV system
Design and performance analysis of 500 KWp on-grid solar PV systemDesign and performance analysis of 500 KWp on-grid solar PV system
Design and performance analysis of 500 KWp on-grid solar PV systemAmroSadulQuddus
 
SOLAR SITE SURVEY ROOFTOP
SOLAR SITE SURVEY ROOFTOPSOLAR SITE SURVEY ROOFTOP
SOLAR SITE SURVEY ROOFTOPMurugappa Group
 
Drawings & Documents Required for Solar Projects
Drawings & Documents Required for Solar ProjectsDrawings & Documents Required for Solar Projects
Drawings & Documents Required for Solar ProjectsGensol Engineering Limited
 

Was ist angesagt? (20)

How solar rooftop system works
How solar rooftop system worksHow solar rooftop system works
How solar rooftop system works
 
Study of Large Scale Grid interactive Solar PV power plant
Study of Large Scale Grid interactive Solar PV power plantStudy of Large Scale Grid interactive Solar PV power plant
Study of Large Scale Grid interactive Solar PV power plant
 
Solar power plant presentation.pdf
Solar power plant presentation.pdfSolar power plant presentation.pdf
Solar power plant presentation.pdf
 
Phases of Construction - Solar Project
Phases of Construction - Solar ProjectPhases of Construction - Solar Project
Phases of Construction - Solar Project
 
Design off grid solar PV system
Design off grid solar PV systemDesign off grid solar PV system
Design off grid solar PV system
 
Engineering Drawings required for Solar Projects
Engineering Drawings required for Solar Projects Engineering Drawings required for Solar Projects
Engineering Drawings required for Solar Projects
 
Photovoltaic Training - Session 1 - Design
Photovoltaic Training - Session 1 - DesignPhotovoltaic Training - Session 1 - Design
Photovoltaic Training - Session 1 - Design
 
Indian Solar Rooftop PV - A Bright Investment (21.08.18)
Indian Solar Rooftop PV - A Bright Investment (21.08.18)Indian Solar Rooftop PV - A Bright Investment (21.08.18)
Indian Solar Rooftop PV - A Bright Investment (21.08.18)
 
Webinar 02 demonstration of pv system design pvsyst
Webinar 02 demonstration of pv system design pvsystWebinar 02 demonstration of pv system design pvsyst
Webinar 02 demonstration of pv system design pvsyst
 
Designing Solar PV Systems ( Utility Scale)
Designing Solar PV Systems ( Utility Scale)Designing Solar PV Systems ( Utility Scale)
Designing Solar PV Systems ( Utility Scale)
 
Economics of Solar Park
Economics of Solar ParkEconomics of Solar Park
Economics of Solar Park
 
Photovoltaic(pv) module and transparent solar panels
Photovoltaic(pv) module and transparent solar panelsPhotovoltaic(pv) module and transparent solar panels
Photovoltaic(pv) module and transparent solar panels
 
Gensol Group Profile - Solar Advisory, Solar Rooftop EPC, Solar O&M (13.12.17)
Gensol Group Profile  - Solar Advisory, Solar Rooftop EPC, Solar O&M (13.12.17)Gensol Group Profile  - Solar Advisory, Solar Rooftop EPC, Solar O&M (13.12.17)
Gensol Group Profile - Solar Advisory, Solar Rooftop EPC, Solar O&M (13.12.17)
 
Basic Introduction to solar PV System.
Basic Introduction to solar PV System.Basic Introduction to solar PV System.
Basic Introduction to solar PV System.
 
PPT OF SOLAR NAVEEN' `11
PPT OF SOLAR NAVEEN' `11PPT OF SOLAR NAVEEN' `11
PPT OF SOLAR NAVEEN' `11
 
Solar photo voltaics
Solar photo voltaics Solar photo voltaics
Solar photo voltaics
 
Solar Panel Installation Proposal PowerPoint Presentation Slides
Solar Panel Installation Proposal PowerPoint Presentation SlidesSolar Panel Installation Proposal PowerPoint Presentation Slides
Solar Panel Installation Proposal PowerPoint Presentation Slides
 
Design and performance analysis of 500 KWp on-grid solar PV system
Design and performance analysis of 500 KWp on-grid solar PV systemDesign and performance analysis of 500 KWp on-grid solar PV system
Design and performance analysis of 500 KWp on-grid solar PV system
 
SOLAR SITE SURVEY ROOFTOP
SOLAR SITE SURVEY ROOFTOPSOLAR SITE SURVEY ROOFTOP
SOLAR SITE SURVEY ROOFTOP
 
Drawings & Documents Required for Solar Projects
Drawings & Documents Required for Solar ProjectsDrawings & Documents Required for Solar Projects
Drawings & Documents Required for Solar Projects
 

Andere mochten auch

Fact Sheet - Solar Net Metering Regulations (India)
Fact Sheet - Solar Net Metering Regulations (India) Fact Sheet - Solar Net Metering Regulations (India)
Fact Sheet - Solar Net Metering Regulations (India) Gensol Engineering Limited
 
Financial Feasibility of Solar Power Plant in India
Financial Feasibility of Solar Power Plant in IndiaFinancial Feasibility of Solar Power Plant in India
Financial Feasibility of Solar Power Plant in IndiaAkash Jauhari
 
Pre-Commissioning Tests for AC Side of Solar Power Plant
Pre-Commissioning Tests for AC Side of Solar Power PlantPre-Commissioning Tests for AC Side of Solar Power Plant
Pre-Commissioning Tests for AC Side of Solar Power PlantGensol Engineering Limited
 
Market Outlook for Energy Storage in India
Market Outlook for Energy Storage in IndiaMarket Outlook for Energy Storage in India
Market Outlook for Energy Storage in IndiaGensol Engineering Limited
 
MS Projects - 10 MW Implementation Schedule
MS Projects - 10 MW Implementation ScheduleMS Projects - 10 MW Implementation Schedule
MS Projects - 10 MW Implementation ScheduleGensol Engineering Limited
 
Gensol Rooftop EPC - Steps & Quality Management
Gensol Rooftop EPC - Steps & Quality ManagementGensol Rooftop EPC - Steps & Quality Management
Gensol Rooftop EPC - Steps & Quality ManagementGensol Engineering Limited
 
10 MW Solar PV power Plant - CPM & PERT, Design
10 MW Solar PV power Plant - CPM & PERT, Design10 MW Solar PV power Plant - CPM & PERT, Design
10 MW Solar PV power Plant - CPM & PERT, DesignVignesh Sekar
 
Solar Cell & Module Supplier - India (01.02.17)
Solar Cell & Module Supplier - India (01.02.17)Solar Cell & Module Supplier - India (01.02.17)
Solar Cell & Module Supplier - India (01.02.17)Gensol Engineering Limited
 
3 Common Solar Module Quality Issues to Understand & Act On
3 Common Solar Module Quality Issues to Understand & Act On3 Common Solar Module Quality Issues to Understand & Act On
3 Common Solar Module Quality Issues to Understand & Act OnGensol Engineering Limited
 
Comparison between different Li Ion Cells Type
Comparison between different Li Ion Cells TypeComparison between different Li Ion Cells Type
Comparison between different Li Ion Cells TypeGensol Engineering Limited
 
Transmission Loss Calculation on 33 / 66 / 132 KV Lines for Solar Power Plant
Transmission Loss Calculation on 33 / 66 / 132 KV  Lines for Solar Power PlantTransmission Loss Calculation on 33 / 66 / 132 KV  Lines for Solar Power Plant
Transmission Loss Calculation on 33 / 66 / 132 KV Lines for Solar Power PlantGensol Engineering Limited
 
Solar Power - Grid Connected Ground Mounted and Solar Rooftop and Metering Re...
Solar Power - Grid Connected Ground Mounted and Solar Rooftop and Metering Re...Solar Power - Grid Connected Ground Mounted and Solar Rooftop and Metering Re...
Solar Power - Grid Connected Ground Mounted and Solar Rooftop and Metering Re...Headway Solar
 
Products and components of a Photovoltaic solar power project
Products and components of a Photovoltaic solar power projectProducts and components of a Photovoltaic solar power project
Products and components of a Photovoltaic solar power projectRavi shankar
 

Andere mochten auch (18)

Fact Sheet - Solar Net Metering Regulations (India)
Fact Sheet - Solar Net Metering Regulations (India) Fact Sheet - Solar Net Metering Regulations (India)
Fact Sheet - Solar Net Metering Regulations (India)
 
Gensol Lender's Engineer Services
Gensol Lender's Engineer ServicesGensol Lender's Engineer Services
Gensol Lender's Engineer Services
 
Financial Feasibility of Solar Power Plant in India
Financial Feasibility of Solar Power Plant in IndiaFinancial Feasibility of Solar Power Plant in India
Financial Feasibility of Solar Power Plant in India
 
Pre-Commissioning Tests for AC Side of Solar Power Plant
Pre-Commissioning Tests for AC Side of Solar Power PlantPre-Commissioning Tests for AC Side of Solar Power Plant
Pre-Commissioning Tests for AC Side of Solar Power Plant
 
Solarig Gensol 'An Overview'
Solarig Gensol 'An Overview' Solarig Gensol 'An Overview'
Solarig Gensol 'An Overview'
 
Market Outlook for Energy Storage in India
Market Outlook for Energy Storage in IndiaMarket Outlook for Energy Storage in India
Market Outlook for Energy Storage in India
 
MS Projects - 10 MW Implementation Schedule
MS Projects - 10 MW Implementation ScheduleMS Projects - 10 MW Implementation Schedule
MS Projects - 10 MW Implementation Schedule
 
Gensol Rooftop EPC - Steps & Quality Management
Gensol Rooftop EPC - Steps & Quality ManagementGensol Rooftop EPC - Steps & Quality Management
Gensol Rooftop EPC - Steps & Quality Management
 
List of Clearances for Solar Project
List of Clearances for Solar ProjectList of Clearances for Solar Project
List of Clearances for Solar Project
 
10 MW Solar PV power Plant - CPM & PERT, Design
10 MW Solar PV power Plant - CPM & PERT, Design10 MW Solar PV power Plant - CPM & PERT, Design
10 MW Solar PV power Plant - CPM & PERT, Design
 
Gensol detailed engineering services
Gensol detailed engineering servicesGensol detailed engineering services
Gensol detailed engineering services
 
Presentation by MNRE on Solar Parks
Presentation by MNRE on Solar ParksPresentation by MNRE on Solar Parks
Presentation by MNRE on Solar Parks
 
Solar Cell & Module Supplier - India (01.02.17)
Solar Cell & Module Supplier - India (01.02.17)Solar Cell & Module Supplier - India (01.02.17)
Solar Cell & Module Supplier - India (01.02.17)
 
3 Common Solar Module Quality Issues to Understand & Act On
3 Common Solar Module Quality Issues to Understand & Act On3 Common Solar Module Quality Issues to Understand & Act On
3 Common Solar Module Quality Issues to Understand & Act On
 
Comparison between different Li Ion Cells Type
Comparison between different Li Ion Cells TypeComparison between different Li Ion Cells Type
Comparison between different Li Ion Cells Type
 
Transmission Loss Calculation on 33 / 66 / 132 KV Lines for Solar Power Plant
Transmission Loss Calculation on 33 / 66 / 132 KV  Lines for Solar Power PlantTransmission Loss Calculation on 33 / 66 / 132 KV  Lines for Solar Power Plant
Transmission Loss Calculation on 33 / 66 / 132 KV Lines for Solar Power Plant
 
Solar Power - Grid Connected Ground Mounted and Solar Rooftop and Metering Re...
Solar Power - Grid Connected Ground Mounted and Solar Rooftop and Metering Re...Solar Power - Grid Connected Ground Mounted and Solar Rooftop and Metering Re...
Solar Power - Grid Connected Ground Mounted and Solar Rooftop and Metering Re...
 
Products and components of a Photovoltaic solar power project
Products and components of a Photovoltaic solar power projectProducts and components of a Photovoltaic solar power project
Products and components of a Photovoltaic solar power project
 

Ähnlich wie Optimisation of Balance of System (BOS) for Solar Projects

Solar power sector: Technology, BoS, Pre Feasbility and phase of project dev...
Solar power sector: Technology, BoS, Pre Feasbility and  phase of project dev...Solar power sector: Technology, BoS, Pre Feasbility and  phase of project dev...
Solar power sector: Technology, BoS, Pre Feasbility and phase of project dev...Ashish Verma
 
Solar street lights using solar tracker and
Solar street lights using solar tracker and Solar street lights using solar tracker and
Solar street lights using solar tracker and GITESHRMHATRE
 
Energy conservation sachivalaya part 2
Energy conservation sachivalaya part 2Energy conservation sachivalaya part 2
Energy conservation sachivalaya part 2IEI GSC
 
Next105 Ases Power Point Presentation Internal Final
Next105 Ases Power Point Presentation Internal FinalNext105 Ases Power Point Presentation Internal Final
Next105 Ases Power Point Presentation Internal FinalNextronex Inc
 
Solar Energy Generation Potential on National Highways
Solar Energy Generation Potential on National HighwaysSolar Energy Generation Potential on National Highways
Solar Energy Generation Potential on National HighwaysIRJET Journal
 
Low power in vlsi with upf basics part 1
Low power in vlsi with upf basics part 1Low power in vlsi with upf basics part 1
Low power in vlsi with upf basics part 1SUNODH GARLAPATI
 
Michel Sacotte - Schneider Electric
Michel Sacotte - Schneider ElectricMichel Sacotte - Schneider Electric
Michel Sacotte - Schneider Electriccwiemeexpo
 
March9 2009-workshop-slides
March9 2009-workshop-slidesMarch9 2009-workshop-slides
March9 2009-workshop-slidesSWITCHOntario
 
Proposal Wide Blower No.1 & 2 with inverter
Proposal Wide Blower No.1 & 2  with inverterProposal Wide Blower No.1 & 2  with inverter
Proposal Wide Blower No.1 & 2 with inverterRidhoIrawan12
 
Slideshare presentation
Slideshare presentationSlideshare presentation
Slideshare presentationNextronex Inc
 
CARBON FOOTPRINTING AND DESIGN OF SOLAR POWER PLANT
CARBON FOOTPRINTING AND DESIGN OF SOLAR POWER PLANTCARBON FOOTPRINTING AND DESIGN OF SOLAR POWER PLANT
CARBON FOOTPRINTING AND DESIGN OF SOLAR POWER PLANTAnkit Singh
 
Solar Power Plant cash flow model
Solar Power Plant cash flow model Solar Power Plant cash flow model
Solar Power Plant cash flow model Vijay Kannan
 
Anu Solar Power - Photovoltaics Basics
Anu Solar Power - Photovoltaics BasicsAnu Solar Power - Photovoltaics Basics
Anu Solar Power - Photovoltaics BasicsChetankumar Morey
 
Mark Wilkinson - Company presentation
Mark Wilkinson - Company presentationMark Wilkinson - Company presentation
Mark Wilkinson - Company presentationDutch Power
 
Electrical & MEP Design - Study material.pdf
Electrical & MEP Design - Study material.pdfElectrical & MEP Design - Study material.pdf
Electrical & MEP Design - Study material.pdfsureshrajan38
 
Voltage Optimisation and Stabilisation
Voltage Optimisation and StabilisationVoltage Optimisation and Stabilisation
Voltage Optimisation and StabilisationDeane Gudsell
 
Three phase BLDC motor
Three phase BLDC motorThree phase BLDC motor
Three phase BLDC motorAnoop S
 
Voltage stabilisation and optimisation by Captech - The facts
Voltage stabilisation and optimisation by Captech - The factsVoltage stabilisation and optimisation by Captech - The facts
Voltage stabilisation and optimisation by Captech - The factsEddie Hoade
 

Ähnlich wie Optimisation of Balance of System (BOS) for Solar Projects (20)

Solar power sector: Technology, BoS, Pre Feasbility and phase of project dev...
Solar power sector: Technology, BoS, Pre Feasbility and  phase of project dev...Solar power sector: Technology, BoS, Pre Feasbility and  phase of project dev...
Solar power sector: Technology, BoS, Pre Feasbility and phase of project dev...
 
Solar street lights using solar tracker and
Solar street lights using solar tracker and Solar street lights using solar tracker and
Solar street lights using solar tracker and
 
Energy conservation sachivalaya part 2
Energy conservation sachivalaya part 2Energy conservation sachivalaya part 2
Energy conservation sachivalaya part 2
 
Next105 Ases Power Point Presentation Internal Final
Next105 Ases Power Point Presentation Internal FinalNext105 Ases Power Point Presentation Internal Final
Next105 Ases Power Point Presentation Internal Final
 
Solar pv plant and india
Solar pv plant and indiaSolar pv plant and india
Solar pv plant and india
 
Solar Energy Generation Potential on National Highways
Solar Energy Generation Potential on National HighwaysSolar Energy Generation Potential on National Highways
Solar Energy Generation Potential on National Highways
 
Low power in vlsi with upf basics part 1
Low power in vlsi with upf basics part 1Low power in vlsi with upf basics part 1
Low power in vlsi with upf basics part 1
 
Michel Sacotte - Schneider Electric
Michel Sacotte - Schneider ElectricMichel Sacotte - Schneider Electric
Michel Sacotte - Schneider Electric
 
March9 2009-workshop-slides
March9 2009-workshop-slidesMarch9 2009-workshop-slides
March9 2009-workshop-slides
 
Proposal Wide Blower No.1 & 2 with inverter
Proposal Wide Blower No.1 & 2  with inverterProposal Wide Blower No.1 & 2  with inverter
Proposal Wide Blower No.1 & 2 with inverter
 
Slideshare presentation
Slideshare presentationSlideshare presentation
Slideshare presentation
 
CARBON FOOTPRINTING AND DESIGN OF SOLAR POWER PLANT
CARBON FOOTPRINTING AND DESIGN OF SOLAR POWER PLANTCARBON FOOTPRINTING AND DESIGN OF SOLAR POWER PLANT
CARBON FOOTPRINTING AND DESIGN OF SOLAR POWER PLANT
 
slup343.pdf
slup343.pdfslup343.pdf
slup343.pdf
 
Solar Power Plant cash flow model
Solar Power Plant cash flow model Solar Power Plant cash flow model
Solar Power Plant cash flow model
 
Anu Solar Power - Photovoltaics Basics
Anu Solar Power - Photovoltaics BasicsAnu Solar Power - Photovoltaics Basics
Anu Solar Power - Photovoltaics Basics
 
Mark Wilkinson - Company presentation
Mark Wilkinson - Company presentationMark Wilkinson - Company presentation
Mark Wilkinson - Company presentation
 
Electrical & MEP Design - Study material.pdf
Electrical & MEP Design - Study material.pdfElectrical & MEP Design - Study material.pdf
Electrical & MEP Design - Study material.pdf
 
Voltage Optimisation and Stabilisation
Voltage Optimisation and StabilisationVoltage Optimisation and Stabilisation
Voltage Optimisation and Stabilisation
 
Three phase BLDC motor
Three phase BLDC motorThree phase BLDC motor
Three phase BLDC motor
 
Voltage stabilisation and optimisation by Captech - The facts
Voltage stabilisation and optimisation by Captech - The factsVoltage stabilisation and optimisation by Captech - The facts
Voltage stabilisation and optimisation by Captech - The facts
 

Mehr von Gensol Engineering Limited

Factors Enhancing Bifacial Gain in India & Middle East_06.03.2020
Factors Enhancing Bifacial Gain in India & Middle East_06.03.2020Factors Enhancing Bifacial Gain in India & Middle East_06.03.2020
Factors Enhancing Bifacial Gain in India & Middle East_06.03.2020Gensol Engineering Limited
 
Ground measured data vs meteo data sets:57 locations in India_01.01.2020
Ground measured data vs meteo data sets:57 locations in India_01.01.2020Ground measured data vs meteo data sets:57 locations in India_01.01.2020
Ground measured data vs meteo data sets:57 locations in India_01.01.2020Gensol Engineering Limited
 
Gensol Engineering Limited - Investor Deck_26.09.2019
Gensol Engineering Limited - Investor Deck_26.09.2019Gensol Engineering Limited - Investor Deck_26.09.2019
Gensol Engineering Limited - Investor Deck_26.09.2019Gensol Engineering Limited
 
Electric Vehicles - Tax Benefits & Incentives_20.09.19
Electric Vehicles - Tax Benefits & Incentives_20.09.19Electric Vehicles - Tax Benefits & Incentives_20.09.19
Electric Vehicles - Tax Benefits & Incentives_20.09.19Gensol Engineering Limited
 
Phases of Construction & Erection for Wind Power Project_03 09 2019
Phases of Construction & Erection for Wind Power Project_03 09 2019Phases of Construction & Erection for Wind Power Project_03 09 2019
Phases of Construction & Erection for Wind Power Project_03 09 2019Gensol Engineering Limited
 
Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019
Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019
Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019Gensol Engineering Limited
 
Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)
Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)
Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)Gensol Engineering Limited
 
List of Solar PV Tenders Floated in India - 11.03.2019
List of Solar PV Tenders Floated in India - 11.03.2019List of Solar PV Tenders Floated in India - 11.03.2019
List of Solar PV Tenders Floated in India - 11.03.2019Gensol Engineering Limited
 
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19Gensol Engineering Limited
 
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019Gensol Engineering Limited
 
Comparison of Solar-Wind Hybrid Policies-07.02.2019
Comparison of Solar-Wind Hybrid Policies-07.02.2019Comparison of Solar-Wind Hybrid Policies-07.02.2019
Comparison of Solar-Wind Hybrid Policies-07.02.2019Gensol Engineering Limited
 
Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid TenderTender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid TenderGensol Engineering Limited
 
Emerging Opportunities - Wind Solar Hybrid System
Emerging Opportunities - Wind Solar Hybrid System Emerging Opportunities - Wind Solar Hybrid System
Emerging Opportunities - Wind Solar Hybrid System Gensol Engineering Limited
 
Wind Turbine Generator (WTG) Audit Checklist by Gensol - 16.06.18
Wind Turbine Generator (WTG) Audit Checklist by Gensol - 16.06.18Wind Turbine Generator (WTG) Audit Checklist by Gensol - 16.06.18
Wind Turbine Generator (WTG) Audit Checklist by Gensol - 16.06.18Gensol Engineering Limited
 
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018Gensol Engineering Limited
 
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...Gensol Engineering Limited
 
Technical Risks in Solar PV Projects 18.03.18
Technical Risks in Solar PV Projects 18.03.18Technical Risks in Solar PV Projects 18.03.18
Technical Risks in Solar PV Projects 18.03.18Gensol Engineering Limited
 
Gensol's Lender Engineer Credentials - 20.03.18
Gensol's Lender Engineer Credentials - 20.03.18Gensol's Lender Engineer Credentials - 20.03.18
Gensol's Lender Engineer Credentials - 20.03.18Gensol Engineering Limited
 

Mehr von Gensol Engineering Limited (20)

Factors Enhancing Bifacial Gain in India & Middle East_06.03.2020
Factors Enhancing Bifacial Gain in India & Middle East_06.03.2020Factors Enhancing Bifacial Gain in India & Middle East_06.03.2020
Factors Enhancing Bifacial Gain in India & Middle East_06.03.2020
 
Ground measured data vs meteo data sets:57 locations in India_01.01.2020
Ground measured data vs meteo data sets:57 locations in India_01.01.2020Ground measured data vs meteo data sets:57 locations in India_01.01.2020
Ground measured data vs meteo data sets:57 locations in India_01.01.2020
 
Gensol Engineering Limited - Investor Deck_26.09.2019
Gensol Engineering Limited - Investor Deck_26.09.2019Gensol Engineering Limited - Investor Deck_26.09.2019
Gensol Engineering Limited - Investor Deck_26.09.2019
 
Electric Vehicles - Tax Benefits & Incentives_20.09.19
Electric Vehicles - Tax Benefits & Incentives_20.09.19Electric Vehicles - Tax Benefits & Incentives_20.09.19
Electric Vehicles - Tax Benefits & Incentives_20.09.19
 
Phases of Construction & Erection for Wind Power Project_03 09 2019
Phases of Construction & Erection for Wind Power Project_03 09 2019Phases of Construction & Erection for Wind Power Project_03 09 2019
Phases of Construction & Erection for Wind Power Project_03 09 2019
 
Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019
Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019
Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019
 
Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)
Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)
Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)
 
List of Solar PV Tenders Floated in India - 11.03.2019
List of Solar PV Tenders Floated in India - 11.03.2019List of Solar PV Tenders Floated in India - 11.03.2019
List of Solar PV Tenders Floated in India - 11.03.2019
 
List of successful bidders 11.03.2019
List of successful bidders 11.03.2019List of successful bidders 11.03.2019
List of successful bidders 11.03.2019
 
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
 
Module Price Trend Analysis
Module Price Trend AnalysisModule Price Trend Analysis
Module Price Trend Analysis
 
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
 
Comparison of Solar-Wind Hybrid Policies-07.02.2019
Comparison of Solar-Wind Hybrid Policies-07.02.2019Comparison of Solar-Wind Hybrid Policies-07.02.2019
Comparison of Solar-Wind Hybrid Policies-07.02.2019
 
Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid TenderTender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
 
Emerging Opportunities - Wind Solar Hybrid System
Emerging Opportunities - Wind Solar Hybrid System Emerging Opportunities - Wind Solar Hybrid System
Emerging Opportunities - Wind Solar Hybrid System
 
Wind Turbine Generator (WTG) Audit Checklist by Gensol - 16.06.18
Wind Turbine Generator (WTG) Audit Checklist by Gensol - 16.06.18Wind Turbine Generator (WTG) Audit Checklist by Gensol - 16.06.18
Wind Turbine Generator (WTG) Audit Checklist by Gensol - 16.06.18
 
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018
 
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...
 
Technical Risks in Solar PV Projects 18.03.18
Technical Risks in Solar PV Projects 18.03.18Technical Risks in Solar PV Projects 18.03.18
Technical Risks in Solar PV Projects 18.03.18
 
Gensol's Lender Engineer Credentials - 20.03.18
Gensol's Lender Engineer Credentials - 20.03.18Gensol's Lender Engineer Credentials - 20.03.18
Gensol's Lender Engineer Credentials - 20.03.18
 

KĂźrzlich hochgeladen

👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...rajveerescorts2022
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxWorkforce Group
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangaloreamitlee9823
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756dollysharma2066
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Centuryrwgiffor
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...amitlee9823
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsMichael W. Hawkins
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Trucks in Minnesota
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityEric T. Tung
 

KĂźrzlich hochgeladen (20)

👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael Hawkins
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 

Optimisation of Balance of System (BOS) for Solar Projects

  • 1. Balance of Systems- Solar PV Project Gensol Engineering Pvt Ltd
  • 2. Balance of Systems (BOS) • Inverters • Mounting & Racking Systems • Electrical Equipment and Installation • Cabling-AC & DC • Transformers & Breakers • Combiner Boxes • Earthing • Transmission Line, etc • Civil Work & Development • Inverter Rooms, CMCS • Roads, Boundary, Drainage, Cleaning Systems, etc • Land • Miscellaneous All components of a photovoltaic system other the photovoltaic panels “ ”
  • 3. BOS Trends -10.00 10.00 30.00 50.00 70.00 90.00 110.00 2010-11 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17 Normalized Value N ormalized CERC P V Cost Cu rves Project Cost Module Cost BOS Cost 0.00% 20.00% 40.00% 60.00% 80.00% 100.00% 2010-11 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17 Module-BOS Cost Breakup Module BOS • Module cost curve has outrun BOS cost curve • BOS optimization from 2013-14 • Module:BOS at 65:35 • Module CARR~ 9% • BOS CARR ~8%
  • 4. Cost Breakup Head Components Trend Inverters Mounting Structures MMS, Fasteners, Installation Civil Works & Development Rooms, Roads, Boundary, Drainage, Cleaning, etc Electrical BOS Cabling, Transformers, Breakers, Combiner Boxes, Earthing, etc Land Miscellaneous CCTV, Monitoring, etc Module 65% Inverters 4% Mounting Structures 7% Civil Works & Development 7% Electrical BOS 10% Land 6% Miscellaneous 1% Solar Project Cost Breakup
  • 5. BOS Reduction due to Module Efficiency • Efficiency of average commercial wafer based silicon module has grown from 10% to 17% in last 10 years • Best efficiency multi-crystalline module: 19.2% Source: Fraunhofer ISE, 2016
  • 6. BOS Reduction due to Module Efficiency Impact of increase in module efficiency Item Components Saving Trend Scalable DC Cabling, Structures, SCBs, Connectors, Land Semi-Scalable Roads, Periphery, Drains, Lighting Neutral AC BOS, Evacuation, etc 0.0% 2.0% 4.0% 6.0% 8.0% 10.0% 12.0% 14.0% 16.0% 18.0% Efficiency DC Works Structure Ass. Civil Work Land 0.0% 0.0% 0.0% 0.0% 0.0% 8.3% 8.0% 7.7% 6.0% 7.7% 16.7% 14.1% 16.7% 11.1% 14.2% % Cost Savings Cost Savings- Efficiency Increase 300W 325W 350W For every 5W increase in module wattage • project costs decrease by 0.27% • BOS costs reduce by 0.8%
  • 7. BOS Reduction due to Overloading (DC:AC) Impact of increase in overloading (DC:AC) Item Components Saving Trend Neutral DC Cabling, Structures, SCBs, Connectors, Land Semi-Scalable Roads, Periphery, Drains, Lighting Scalable AC BOS, Evacuation, etc
  • 8. BOS Reduction due to Overloading (DC:AC) 1.00 0.96 0.94 0.92 0.91 0.90 1.000 0.984 0.979 0.972 0.968 0.962 0.84 0.86 0.88 0.90 0.92 0.94 0.96 0.98 1.00 1.02 0 10% 15% 20% 25% 30% Normalization Factor Overloading(%) Effect of Overloading on Plant Costs Normalized BOS Cost/Wp Normalized Cost/Wp 1.000 1.083 1.125 1.167 1.209 1.251 1.00 1.10 1.15 1.20 1.25 1.30 1.000 1.050 1.100 1.150 1.200 1.250 1.300 0 10% 15% 20% 25% 30% NORMALIZED GAIN OVERLOADING(5) Cost Benefit Analysis Of Overloading Normalized Normaized Enegy Gain For every 10% increase in overloading • project costs decrease by 1.25% • BOS costs reduce by 3.5% Cost Benefit Analysis • Till Generation gain surpasses increase in cost
  • 9. DC Cabling & Combiner Boxes DC side cabling costs have decreased by about 40% due to efficient design in the last few years Smart DC Block Sizing 55:45 65:35 75:25 55:35 65:35 75:25 Cost(%) 100% 115% 124% Loss(%) 100% 113% 120% Overall Cost(INR/Wp) 0.23 0.37 • Big Plant sizes allow DC block sizing optimization
  • 10. DC Cabling & Combiner Boxes String Fusing by Y-connectors-> Solar Cable & SCB Cost reduction by around 30% String Monitoring removed, relying on inverter zone monitoring Item Saving Solar Cable 32% SCB 26% Overall 28% Leap Frogging saves 25% cable cost in the case of tracker With effective design optimization on the DC side, a reduction of 1.1% and 3.6% on project cost and BOS can be achieved“
  • 11. Inverters & Transformers Inverters • Inverter costs have reduced by more than 70% from 2010-11 • Driven by o Scale of Production (Inverter learning rates vary from 18-20%)1 o Technological advancements: Ăź Material (SiC, GaN) Ăź Block Size Ăź Voltage Increase (1500V) o Localization • Inverters are predicted to see price reductions of 8-9% per annum upto 20202 Tranformers • Have shown reduction in costs in recent years due to: • Higher transformer capacities due to bigger block size • Metal Prices • Multi- winding transformer (5-winding, 7 winding) resulting in BOS optimization Source: 1. Fraunhofer ISE, 2015 2 Greentech Media, 2015.
  • 12. Case Study: Impact of Block Size on BOS Case: 65MW Plant with 5 nos. Of 10MW and 1 no. of 15MW Block Feeder Comparison for use of various Transformer winding options (5 Nos. of 10MW Feeders & 1 No. of 15MW Feeder) S.No Parameter Case 1 Case 3 Inverter Room with 2 Inverters & 3 Winding Transformer (1No.) Inverter Room with 4 Inverters & 5 Winding Transformer (1No.) 1 Design Type 2.5MVA Block with 3-winding Xmer 5MVA Block with 5-winding Xmer 3 No. of Inverter Transformers 26 Nos. (2.5 MVA Capacity) 13 Nos. (5MVA Capacity) 4 No. of Aux. Transformers 26 Nos. (One Aux Trasf for each Inverter room) 13 Nos. (One Aux Trasf for each Inverter room) 5 No. of UPS 26 Nos. (One UPS for each Inverter room) 13 Nos. (One UPS for each Inverter room, but size of UPS will be almost twice compared to Case 1) 6 No. of VCBs 58 Nos. VCB (630A) & 3Nos. VCB (1600A) 32 Nos. VCB (630A) & 3Nos. VCB (1600A) 7 DC Power cable (SMB to Inverter Cable) 45000 Mtrs (150 Sqmm) & 70000 Mtrs (185 Sqmm) 60000 Mtrs (150 Sqmm) & 90000 Mtrs (185Sqmm) 8 HT Cable 13650 Mtrs (3Cx120 Sqmm), 3560 Mtrs (3Cx240 Sqmm), 600 Mtrs (3Cx300 sqmm) 3950 Mtrs (3Cx240Sqmm), 4320 Mtrs (3Cx300 sqmm) 9 Aux Power Cable (3Cx1.5 sqmm Cu.) 22815 Mtrs 31900 Mtrs 10 Communication Cable (RS 485) 18590 Mtrs 26050 Mtrs 11 Communication Cable (OFC) 31330 Mtrs 12560 Mtrs 12 HDPE Pipes 49950 Mtrs 38610 Mtrs 13 No. of PEB Inverter Rooms (Pre Engineered Building) 26 13 14 Size of each Inverter Room (Approx) 8.5m x 6m 14.5m x 6m 15 Transformer foundation 26 Nos. 13 Nos. 16 CCTV 32 Nos. of HD PTZ type & 7 Nos. of HD Fixed type 19 Nos. of HD PTZ type & 7 Nos. of HD Fixed type Item Savings (INR/W) 1. Tranformers +Aux.+ UPS 0.06 2. Switchgear 0.25 3. Cables (Power + Aux. + Communication) 0.08 4. Civil Work 0.06 Saving of INR 0.45/W due to Block Size Increase and use of 5-winding Transformer “ ”
  • 13. 1500V Inverter Advantages • Higher DC and AC voltage i.e. lesser current and lesser cabling • Lesser current allows the increase in inverter block power, lesser BOS • 50% longer strings, implying lesser strings, and 33% lesser junction boxes • Lesser monitoring, and economical installation • IEC certifications are in place • Higher yield Disadvantages • Component availability limited at present, thus driving BOS costs higher • Higher inverter costs due to 1500V components
  • 14. 1500V v/s 1000V Comparison of 1500V v/s 1000V Item Remarks Savings (%) Savings (INR/Wp) Saving Trend PV Modules 0.5 USD cents higher for 1500V -1.15% -0.34 DC Cables Quantity Saving ~30% Unit Cost considered 10% extra for 1500V 22.22% 0.16 SCB Quantity Saving ~32% Unit Cost considered 25% extra for 1500V 15.70% 0.05 AC Subsystem Inverter Trafo, LT Cable, Aux. Trafo 11.44% 0.08 Inverter 25% higher cost -25.00% -0.44 Civil & Labour Inverter Pad for 1500V, Room for 1000V. Installation Labour work reduction by 10% assumed 31.08% 0.22 Overall -0.83% -0.28
  • 15. 1500V v/s 1000V Comparison of 1500V v/s 1000V (Alternate Optimization) • For same DC ohmic losses, a 7.5MW block can be formed in 1500V when compared to 5MW block • Bigger block size would mean optimization can be carried on AC side 1500V 7.5MW 1000V 5 MW
  • 16. Land • The cost of land for solar projects has risen about 6-10 times as compared to 2010-11 • Not only expensive, but difficulties in acquisition • As the cost of PV modules decrease, land use optimization by decreasing the tilt, and increasing the power density (kW/sqm) East-West Mounting • For places closer to equator, i.e. latitude <10°, solar modules can be mounted in east west fashion at low tilt angles (around 3°) • High land utilization, with GCR>80% can be achieved • Wider peak • Lesser structure and foundation cost • Lesser BOS cost • Marginal drop in generation
  • 17. East-West Mounting -11.98% -14.47% -11.55% -12.15% -11.08% -10.98% -11.12% -7.68% -4.22% -3.90% -4.31% -4.26% -3.70% -3.81% -4.81% -3.72% -2.62% -1.73% 30.16 28.59 26.84 24.97 23.76 23.07 22.31 22.36 21.32 18.52 17.38 14.66 14.29 13.14 11.87 9.9 9.36 8.36 GENERATION REDUCTION% LATITUDE East West Mounting v/s South Facing
  • 18. Shift from Fixed to Seasonal – How numbers work • 20 X 315Wp modules in series = 6.3kWp = 1 Table • 1MWp = 160 Tables (approx.) • A team of 3 persons will take 15 minutes to change tilt of 1 table (on an average), hence, 32 tables per day. • Five such teams i.e 15 persons per day shall be able to change tilt of 1MWp installation. • At a labour rate of Rs. 350/- per day, it takes less than Rs. 6000 to change tilt of 1MWp installation. • Assuming an increment of 3T / MWp between fixed and seasonal tilt, additional capex comes out to be Rs. 2.4Lacs approx.
  • 19. Structure Trend - Seasonal Tilt - Y 2014 – 60T S.No Description Section Size Length (m) Tot. Quantity Unit Weight (kg/m) Tot. Wt. (kg) 1) Column Post 130CU60x5 2.80 656 9.42 17302.66 2) Rafter 120CS50x18x3 3.375 656 5.74 12708.36 3) Purlin 130CS50x14x1. 5 4.97 1312 2.96 19301.09 4) Side Bracing-1 L-55x55x5 1.28 984 4.12 5189.222 5) Side Bracing-2 L-55x55x5 1.49 656 4.12 4027.053 6) Connection plate 0.265 656 1.04 682.24 6) Connection Cleat 0.167 2624 0.157 411.968 7) SQ. Washer 0.05 3936 0.0589 231.8304 Total Structural Steel Qty. (kg) 59854.42 Say 60 Ton
  • 20. Structure Trend - Seasonal Tilt - Y 2015 – 40T Module Mounting Structural Steel Qty. Description Sectional Details Quantity /Table Grade of Steel Finish Length (m) Unit. Wt (Kg/m) Component wt. (kg) Quantity/ MW Total Wt (Kg) Column 120CU50x3.15 5 350 Mpa GAL 2.390 5.10 12.189 835 10177.82 Washer Plate PLT 50x50x5 10 250 Mpa GAL 0.050 1.96 0.098 1670 163.87 Rafter 100CU50x2 5 350 Mpa GAL 2.910 3.00 8.730 835 7289.55 Purlin (A) 70CS40x15x1.2 4 350 Mpa GAL 3.460 1.61 5.576 668 3724.63 Purlin (B) 70CS40x15x1.2 4 350 Mpa GAL 5.195 1.61 8.372 668 5592.32 Purlin (C) 70CS40x15x1.2 4 350 Mpa GAL 3.460 1.61 5.576 668 3724.63 Side Bracing-1 40CU40x2 5 350 Mpa GAL 1.270 1.75 2.223 835 1855.79 Side Bracing-2 40CU40x2 5 350 Mpa GAL 1.470 1.75 2.573 835 2148.04 Connection Plate-1 330x100x4 5 250 Mpa GAL 0.330 3.140 1.036 835 865.23 Connection Plate-2 265x100x4 5 250 Mpa GAL 0.265 3.140 0.832 835 694.80 Connection angleL PLT 70x70x3 20 250 Mpa GAL 0.110 3.23 0.355 3340 1185.23 Tie Rod 12mm dia 8 250 Mpa GAL 0.965 0.889 0.858 1336 1145.99 Total Weight Per MW 38567.89 Spare 3 % 1157.04 Say 40 Ton
  • 21. Pre Fab rooms and Decking Sheets • Pre fab rooms offer significant time advantages in execution timelines hence bring generation gains and more efficient supplies • Instances where Pre fab buildings are not considered, decking sheets with concrete layer on top can offer same benefits. It provides both required strength, insulation and quicker installation benefits
  • 22. Wind Shielding of Outer most structures • Recent designs leverage on the density of array yard and consider lower values of k2 factor in design calculations of structures. • Outer rows are designed with higher sections as they have more impact of wind speeds, however inner rows are designed 10-15% lighter to leverage the shielding that outer structure provides
  • 23. The 0.8mm Galvalume! In Sub 30 T structures! One name that has echoed in procurement teams lately. It’s a fine play and tight walk on the line between Optimization and Under design Galvalume suits fixed tilt structures and can be very good for optimization Use of galvalume in seasonal tilt structures has seen many failures recently and resulted in loss of PV modules & of course generation Extra caution to be exercised while tilting galvalume based structures and must be done only using proper jacks. Manual tilting is a strict no, if not particularly addressed during Engineering
  • 24. Cost Saving by Internal Transmission Line Site specific: If land is not highly constrained, and HT cables are running along northern boundary Pros: • Cheaper compared to HT cable (30-40% lesser at full load evacuation) • Maintenance friendly, and lesser probability of fault • Higher current carrying capacity. New age AAAC panther conductors can carry 25MW on single circuit, whereas typical 33kV cables will take around15MW Cons: • Land wastage around poles due to shadow • Land wastage can be minimized by planning TL along boundary, and suitably oriented to north direction
  • 25. Future Trends Main Drives of BOS Cost Reduction in future • Best practices assimilation across the industry • Module efficiency • Technological developments • Incremental design improvements, such as higher overloading, mounting structure, block size, etc • Localization including streamlined logistics • Increase in market volume • Automation in production, development and installation Based on the above factors and historical trends, we foresee a BOS cost reduction of 30%-35% by 2020
  • 26. About Gensol Gensol, found in 2007 is India’s leading Advisory and System Integrator for Solar PV Power Projects. Gensol is a channel partner to MNRE and enjoys empanelmentwith most major Lending Institutions in India. 2,500+ MW 12,000+ kW Gensol has an advisory portfolio of more than 2.5 GW with every 5th MW in India developed with our expertise. Being an MNRE Channel partner, Gensol has executed more than 12 MW of Solar Rooftop Projects across India. Gensol is based out of Ahmedabad in Gujarat but has operational solar projects across 16 Indian States. With a 130+ Employee Strength – Gensol prides itself on having the best technical talent in industry. AWARDS BusinessWorld – India’s largest weekly business magazine awarded Gensol with “Hottest Young Entrepreneur” in 2009. Economic Times – India’s largest financial daily awarded Gensol in its “Power of Ideas” series in 2010. Gensol was the only non-UK based firm to be nominated for Global Consultancy of the Year at BusinessGreen Leader Awards, London in 2014.
  • 27. Gensol Engineering Pvt Ltd | Gensol Consultants Pvt Ltd Corporate Office 108, Pinnacle Business Park Opp Royal Arcade, Prahladnagar Ahmedabad, Gujarat India - 380015 Email: solar@gensol.in Website: www.gensol.in Phone: +91 79 40068235 Fax: +91 79 40068239 Twitter: gensol_tweets Gensol is one of the leading consultants and system integrators for Solar Power Plants. We boast of a portfolio of over 2500 MW of Solar Photovoltaic Plants. Gensol is also a channel partner to Ministry of New & Renewable Energy and installs kW scale Solar Rooftop systems on a turnkey basis with more than 15 MW of cumulative installations across the country. The information contained herein is of a general nature and is not intended to address the circumstances of any particular individual or entity.Although we endeavor to provide accurate and timely information,there can be no guarantee that such information is accurate as of the date it is received or that it will continue to be accurate in the future. No one should act on such information withoutappropriate professional advice after a thorough examination ofthe particular situation.