SlideShare ist ein Scribd-Unternehmen logo
1 von 37
Ope a onsManagemen
Scheduling
Chapter 17
•
•
•
Objectives in Scheduling
Loading
Sequencing
•
•
•
•
Monitoring
Advanced Planning and
Theory of Constraints
Employee Scheduling
Scheduling Systems
17-879
Lecture Outline
•Last stage of planning before production
occurs
•Specifies when labor, equipment, and
facilities are needed
product or provide a
to produce
service
a
17-880
What is Scheduling?
Scheduled Operations
• Process Industry
• Linear programming
• EOQ with non-instantaneous
replenishment
• Batch Production
Aggregate planning
Master scheduling
•
•
• Mass Production
• Assembly line balancing
Project
• Project -scheduling
techniques (PERT, CPM)
Material requirements
planning (MRP)
Capacity requirements
planning (CRP)
•
• •
17-881
Scheduled Operation
Objectives in Scheduling
• Meet customer due
dates
•
•
Minimize overtime
Maximize machine
labor utilization
or
• Minimize job lateness
•
•
Minimize
Minimize
time
Minimize
system
response time
completion
•
•
Minimize idle time
Minimize work-in-
process inventory
• time in the
17-882
Objectives in Schedu
Shop Floor Control (SFC)
• scheduling and monitoring of day-to-day production
in a job shop
also called production control and production
activity control (PAC)
•
• usually performed by production control department
Loading
•
Check availability of material, machines, and labor
Sequencing
Release work orders to shop and issue dispatch lists for
individual machines
Monitoring
Maintain progress reports on each job until it is complete
•
•
•
•
•
17-883
Shop Floor Control (
•Process of assigning work to limited
resources
•Perform work with most efficient
resources
•Use assignment method of linear
programming to determine allocation
17-884
Loading
1. Perform row reductions
• subtract minimum value in each
row from all other row values
2. Perform column reductions
4. If number of lines equals number
of rows in matrix, then optimum
solution has been found. Make
assignments where zeros appear
Else modify matrix
•
• subtract minimum value in each
column from all other column
values
3. Cross out all zeros in matrix
• use minimum number of
horizontal and vertical lines
subtract minimum uncrossed value
from all uncrossed values
add it to all cells where two lines
intersect
other values in matrix remain
unchanged
•
•
•
5. Repeat steps 3 and 4 until
optimum solution is reached
17-885
Assignment Method
Assignment Method: Example
17-886
Initial PROJECT
Matrix 1 2 3 4
Bryan 10 5 6 10
Kari 6 2 4 6
Noah 7 6 5 6
Chris 9 5 4 10
Row reduction Column reduction Cover all zeros
5 0 1 5 3 0 1 4 3 0 1 4
4 0 2 4 2 0 2 3 2 0 2 3
2 1 0 1 0 1 0 0 0 1 0 0
5 1 0 6 3 1 0 5 3 1 0 5
Number lines number of rows so modify matrix
Assignment Method: E
Project Cost = (5 + 6 + 4 + 6) X $100 = $2,100
17-887
Assignment Method: Example (cont.)
Modify matrix Cover all zeros
1 0 1 2 1 0 1 2
0 0 2 1 0 0 2 1
0 3 2 0 0 3 2 0
1 1 0 3 1 1 0 3
Number of lines = number of rows so at optimal solution
PROJECT PROJECT
1 2 3 4 1 2 3 4
Bryan 1 0 1 2 Bryan 10 5 6 10
Kari 0 0 2 1 Kari 6 2 4 6
Noah 0 3 2 0 Noah 7 6 5 6
Chris 1 1 0 3 Chris 9 5 4 10
Prioritize jobs assigned to a resource
If no order specified use first-come first-served (FCFS)
Other Sequencing Rules
FCFS - first-come, first-served
LCFS - last come, first served
DDATE - earliest due date CUSTPR
- highest customer priority SETUP -
similar required setups SLACK -
smallest slack
CR - smallest critical ratio
SPT - shortest processing time
LPT - longest processing time
17-888
Sequencing
Simple Sequencing Rules
17-891
PROCESSING DUE
JOB TIME DA
TE
A 5 10
B 10 15
C 2 5
D 8 12
E 6 8
Simple Sequencing Ru
A 0 5 5 10 0
17-892
FCFS START PROCESSING COMPLETION DUE
SEQUENCE TIME TIME TIME DATE TARDINESS
B 5 10 15 15 0
C 15 2 17 5 12
D 17 8 25 12 13
E 25 6 31 8 23
Total 93 48
Average 93/5 = 18.60 48/5 = 9.6
Simple Sequencing
Rules: FCFS
17-893
DDATE START PROCESSING COMPLETION DUE
SEQUENCE TIME TIME TIME DATE TARDINESS
C 0 2 2 5 0
E 2 6 8 8 0
A 8 5 13 10 3
D 13 8 21 12 9
B 21 10 31 15 16
Total 75 28
Average 75/5 = 15.00 28/5 = 5.6
Simple Sequencing
Rules: DDATE
17-895
SPT START PROCESSING COMPLETION DUE
SEQUENCE TIME TIME TIME DATE TARDINESS
C 0 2 2 5 0
A 2 5 7 10 0
E 7 6 13 8 5
D 13 8 21 12 9
B 21 10 31 15 16
Total 74 30
Average 74/5 = 14.80 30/5 = 6
Simple Sequencing
Rules: SPT
5.6 3 16
17-896
AVERAGE AVERAGE NO. OF MAXIMUM
RULE COMPLETION TIME TARDINESS JOBS TARDY TARDINESS
FCFS 18.60 9.6 3 23
DDATE 15.00 5.6 3
SLACK 16.40 6.8 4 16
SPT 14.80 6.0 3 16
Simple Sequencing
Rules: Summary
Guidelines for Selecting a
1.
2.
3.
SPT most useful when shop is highly congested
Use SLACK for periods of normal activity
Use DDATE when only small tardiness values can
be tolerated
Use LPT if subcontracting is anticipated
Use FCFS when operating at low-capacity levels
Do not use SPT to sequence jobs that have to be
assembled with other jobs at a later date
4.
5.
6.
17-900
Guidelines for Selectin
Sequencing Rule
•Work package
• Shop paperwork that travels with a job
•Gantt Chart
• Shows both planned and completed
activities against a time scale
•Input/Output Control
• Monitors the input and output
work center
from each
17-901
Monitoring
17-902
Facility
Gantt Chart
Job 32B
3 Behind schedule
Job 23C
2 Ahead of schedule
Job 11C Job 12A
1 On schedule
1 2 3 4 5 6 8 9 10 11 12 Days
Today’s Date
Key: Planned activity
Completed activity
20 10 5 0
17-903
Input/Output Control
Input/Output Report
PERIOD 1 2 3 4 TOTAL
Planned input 65 65 70 70 270
Actual input 0
Deviation 0
Planned output 75 75 75 75 300
Actual output 0
Deviation 0
Backlog 30
17-904
Input/Output Control (cont.)
Input/Output Report
PERIOD 1 2 3 4 TOTAL
Planned input 65 65 70 70 270
Actual input 60 60 65 65 250
Deviation -5 -5 -5 -5 -20
Planned output 75 75 75 75 300
Actual output 75 75 65 65 280
Deviation -0 -0 -10 -10 -20
Backlog 30 15 0 0 0
•Infinite - assumes infinite capacity
• Loads without regard to capacity
• Then levels the load and sequences jobs
•Finite - assumes finite (limited) capacity
• Sequences jobs as part of the loading
decision
• Resources are never loaded beyond
capacity
17-905
Advanced Planning and
Scheduling Systems
Scheduling Systems (cont.)
• Advanced planning and scheduling (APS)
• Add-ins to ERP systems
• Constraint-based programming (CBP) identifies a
solution space and evaluates alternatives
• Genetic algorithms based on natural selection
properties of genetics
• Manufacturing execution system (MES) monitors
status, usage, availability, quality
17-906
Advanced Planning and
Scheduling Systems (c
• Not all resources are used evenly
• Concentrate on the” bottleneck” resource
• Synchronize flow through the bottleneck
• Use process and transfer batch sizes to
move product through facility
17-907
Theory of Constraints
• Drum
• Bottleneck, beating to set the pace of production for
the rest of the system
• Buffer
• Inventory placed in front of the bottleneck to ensure
it is always kept busy
• Determines output or throughput of the system
• Rope
• Communication signal; tells processes upstream
when they should begin production
17-908
Drum-Buffer-Rope
TOC Scheduling Procedure
• Identify bottleneck
• Schedule job first whose lead time to
bottleneck is less than or equal to
bottleneck processing time
• Forward schedule bottleneck machine
• Backward schedule other machines to
sustain bottleneck schedule
• Transfer in batch sizes smaller than
process batch size
17-909
TOC Scheduling Pro
D3 3 5
C3 2 15
B3 1 7
B2 2 3 C2 1 10 D2 2 8
B1 1 5 C1 3 2 D1 3 10
Synchronous ij k l Operation j of item i performed at
Manufacturing nutes
17-910
B C D
B3 1 7 C3
B2 2 3 C2
B1 1 5 C1
Key: i Item i
ij k l Operation j of item i perfor
machine center k takes l mi
to process
A
Demand = 100 A’s
Machine setup time = 60 minutes
* Bottleneck
17-911
MACHINE 1 MACHINE 2 MACHINE 3
B1 5 B2 3 C1 2
B3 7 C3 15 D3 5
C2 10 D2 8 D1 10
Sum 22 26* 17
Synchronous
Manufacturing (cont.)
Completion 2737
17-912
Synchronous Manufacturing (cont.)
Machine 1 Setup Setup
C2 B1 B3
2 1002 1562 2322
Idle
Machine 2 Setup Setup
C3 B2 D2
12 1512 1872 2732
Machine 3
Setup Setup
C1 D1 Idle D3
0 200 1260 1940
time
Employee Scheduling
• Labor is very flexible
resource
Scheduling workforce is
•
complicated, repetitive
task
Assignment method can
be used
Heuristics are commonly
used
•
•
17-913
Employee Schedulin
Employee Scheduling Heuristic
1. Let N = no. of workers available
Di = demand for workers on day i
X = day working
O = day off
Assign the first N - D1 workers day 1 off. Assign the next N - D2
2.
workers day 2 off. Continue in a similar manner until all days are
have been scheduled
3. If number of workdays for full time employee < 5, assign
remaining workdays so consecutive days off are possible
4. Assign any remaining work to part-time employees
5. If consecutive days off are desired, consider switching schedules
among days with the same demand requirements
17-914
Employee Scheduling
Automated Scheduling Systems
• Staff Scheduling
• Schedule Bidding
• Schedule
Optimization
17-918
Automated Scheduli

Weitere ähnliche Inhalte

Ă„hnlich wie Scheduling Operations Management Chapter 17 Lecture Outline

scheduling_1.ppt
scheduling_1.pptscheduling_1.ppt
scheduling_1.pptVELMURUGANM19
 
Tn6 facility layout
Tn6 facility layoutTn6 facility layout
Tn6 facility layoutvideoaakash15
 
Tn6 facility+layout
Tn6 facility+layoutTn6 facility+layout
Tn6 facility+layoutvideoaakash15
 
SBS - SMED Training (Set Up Reduction)
SBS - SMED Training (Set Up Reduction)SBS - SMED Training (Set Up Reduction)
SBS - SMED Training (Set Up Reduction)Chris Cummins
 
Operations scheduling
Operations schedulingOperations scheduling
Operations schedulingRajThakuri
 
A line in apparel
A line in apparelA line in apparel
A line in apparelsuniltalekar1
 
Round-ribon algorithm presntation
Round-ribon algorithm presntationRound-ribon algorithm presntation
Round-ribon algorithm presntationJamsheed Ali
 
Job Shop Scheduling with Setup Times Release times and Deadlines
Job Shop Scheduling with Setup Times  Release times and DeadlinesJob Shop Scheduling with Setup Times  Release times and Deadlines
Job Shop Scheduling with Setup Times Release times and DeadlinesAlkis Vazacopoulos
 
SCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaa
SCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaaSCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaa
SCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaainfinitepestcontrol
 
scheduling.ppt course not for industrial engineering students
scheduling.ppt course not for industrial engineering studentsscheduling.ppt course not for industrial engineering students
scheduling.ppt course not for industrial engineering studentsRezeneKahsayHagos
 
scheduling.ppt course not for industrial engineering students
scheduling.ppt course not for industrial engineering studentsscheduling.ppt course not for industrial engineering students
scheduling.ppt course not for industrial engineering studentsRezeneKahsayHagos
 
Production planning and control 2019
Production planning and control 2019Production planning and control 2019
Production planning and control 2019sserwaniko
 
Line balancing
Line balancingLine balancing
Line balancinggeetha_64
 
SCHEDULING
SCHEDULING  SCHEDULING
SCHEDULING SupanShah2
 
Macy's: Changing Engines in Mid-Flight
Macy's: Changing Engines in Mid-FlightMacy's: Changing Engines in Mid-Flight
Macy's: Changing Engines in Mid-FlightDataStax Academy
 
Unit 2 process Management
Unit 2 process ManagementUnit 2 process Management
Unit 2 process Managementzahid7578
 
LVOUG meetup #4 - Case Study 10g to 11g
LVOUG meetup #4 - Case Study 10g to 11gLVOUG meetup #4 - Case Study 10g to 11g
LVOUG meetup #4 - Case Study 10g to 11gMaris Elsins
 

Ă„hnlich wie Scheduling Operations Management Chapter 17 Lecture Outline (20)

scheduling_1.ppt
scheduling_1.pptscheduling_1.ppt
scheduling_1.ppt
 
Tn6 facility layout
Tn6 facility layoutTn6 facility layout
Tn6 facility layout
 
Tn6 facility+layout
Tn6 facility+layoutTn6 facility+layout
Tn6 facility+layout
 
Line Balancing In Garments Industry
Line Balancing In Garments IndustryLine Balancing In Garments Industry
Line Balancing In Garments Industry
 
SBS - SMED Training (Set Up Reduction)
SBS - SMED Training (Set Up Reduction)SBS - SMED Training (Set Up Reduction)
SBS - SMED Training (Set Up Reduction)
 
Operations scheduling
Operations schedulingOperations scheduling
Operations scheduling
 
A line in apparel
A line in apparelA line in apparel
A line in apparel
 
Round-ribon algorithm presntation
Round-ribon algorithm presntationRound-ribon algorithm presntation
Round-ribon algorithm presntation
 
Scheduling
SchedulingScheduling
Scheduling
 
Job Shop Scheduling with Setup Times Release times and Deadlines
Job Shop Scheduling with Setup Times  Release times and DeadlinesJob Shop Scheduling with Setup Times  Release times and Deadlines
Job Shop Scheduling with Setup Times Release times and Deadlines
 
SCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaa
SCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaaSCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaa
SCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaa
 
scheduling.ppt course not for industrial engineering students
scheduling.ppt course not for industrial engineering studentsscheduling.ppt course not for industrial engineering students
scheduling.ppt course not for industrial engineering students
 
scheduling.ppt course not for industrial engineering students
scheduling.ppt course not for industrial engineering studentsscheduling.ppt course not for industrial engineering students
scheduling.ppt course not for industrial engineering students
 
Log11 uitwerking opdrachten
Log11 uitwerking opdrachtenLog11 uitwerking opdrachten
Log11 uitwerking opdrachten
 
Production planning and control 2019
Production planning and control 2019Production planning and control 2019
Production planning and control 2019
 
Line balancing
Line balancingLine balancing
Line balancing
 
SCHEDULING
SCHEDULING  SCHEDULING
SCHEDULING
 
Macy's: Changing Engines in Mid-Flight
Macy's: Changing Engines in Mid-FlightMacy's: Changing Engines in Mid-Flight
Macy's: Changing Engines in Mid-Flight
 
Unit 2 process Management
Unit 2 process ManagementUnit 2 process Management
Unit 2 process Management
 
LVOUG meetup #4 - Case Study 10g to 11g
LVOUG meetup #4 - Case Study 10g to 11gLVOUG meetup #4 - Case Study 10g to 11g
LVOUG meetup #4 - Case Study 10g to 11g
 

Mehr von Aminullah Assagaf

Aminullah Assagaf_Regresi Lengkap 22_11 April 2024.pdf
Aminullah Assagaf_Regresi Lengkap 22_11 April 2024.pdfAminullah Assagaf_Regresi Lengkap 22_11 April 2024.pdf
Aminullah Assagaf_Regresi Lengkap 22_11 April 2024.pdfAminullah Assagaf
 
Aminullah Assagaf_Regresi Lengkap 22_11 April 2024.pptx
Aminullah Assagaf_Regresi Lengkap 22_11 April 2024.pptxAminullah Assagaf_Regresi Lengkap 22_11 April 2024.pptx
Aminullah Assagaf_Regresi Lengkap 22_11 April 2024.pptxAminullah Assagaf
 
Aminullah Assagaf_Regresi Lengkap 22_11 April 2024.pdf
Aminullah Assagaf_Regresi Lengkap 22_11 April 2024.pdfAminullah Assagaf_Regresi Lengkap 22_11 April 2024.pdf
Aminullah Assagaf_Regresi Lengkap 22_11 April 2024.pdfAminullah Assagaf
 
Aminullah Assagaf_Regresi Lengkap 21_11 April 2024.pdf
Aminullah Assagaf_Regresi Lengkap 21_11 April 2024.pdfAminullah Assagaf_Regresi Lengkap 21_11 April 2024.pdf
Aminullah Assagaf_Regresi Lengkap 21_11 April 2024.pdfAminullah Assagaf
 
Aminullah Assagaf_Regresi Lengkap 21_11 April 2024.pptx
Aminullah Assagaf_Regresi Lengkap 21_11 April 2024.pptxAminullah Assagaf_Regresi Lengkap 21_11 April 2024.pptx
Aminullah Assagaf_Regresi Lengkap 21_11 April 2024.pptxAminullah Assagaf
 
Aminullah Assagaf_Regresi Lengkap 20_10 April 2024_Inc. Data panel & Perbandi...
Aminullah Assagaf_Regresi Lengkap 20_10 April 2024_Inc. Data panel & Perbandi...Aminullah Assagaf_Regresi Lengkap 20_10 April 2024_Inc. Data panel & Perbandi...
Aminullah Assagaf_Regresi Lengkap 20_10 April 2024_Inc. Data panel & Perbandi...Aminullah Assagaf
 
Aminullah Assagaf_Regresi Lengkap 19_8 Nov 2023_Inc. Data panel & Perbandinga...
Aminullah Assagaf_Regresi Lengkap 19_8 Nov 2023_Inc. Data panel & Perbandinga...Aminullah Assagaf_Regresi Lengkap 19_8 Nov 2023_Inc. Data panel & Perbandinga...
Aminullah Assagaf_Regresi Lengkap 19_8 Nov 2023_Inc. Data panel & Perbandinga...Aminullah Assagaf
 
Aminullah Assagaf_Regresi Lengkap 19_8 Nov 2023_Inc. Data panel & Perbandinga...
Aminullah Assagaf_Regresi Lengkap 19_8 Nov 2023_Inc. Data panel & Perbandinga...Aminullah Assagaf_Regresi Lengkap 19_8 Nov 2023_Inc. Data panel & Perbandinga...
Aminullah Assagaf_Regresi Lengkap 19_8 Nov 2023_Inc. Data panel & Perbandinga...Aminullah Assagaf
 
Aminullah Assagaf_K12-14_Manj Oprs dan Prod_2024.ppt
Aminullah Assagaf_K12-14_Manj Oprs dan Prod_2024.pptAminullah Assagaf_K12-14_Manj Oprs dan Prod_2024.ppt
Aminullah Assagaf_K12-14_Manj Oprs dan Prod_2024.pptAminullah Assagaf
 
Aminullah Assagaf_K10-11_Manj Oprs dan Prod_2024.ppt
Aminullah Assagaf_K10-11_Manj Oprs dan Prod_2024.pptAminullah Assagaf_K10-11_Manj Oprs dan Prod_2024.ppt
Aminullah Assagaf_K10-11_Manj Oprs dan Prod_2024.pptAminullah Assagaf
 
Aminullah Assagaf_K6-7_29 Oktober 2024.ppt
Aminullah Assagaf_K6-7_29 Oktober 2024.pptAminullah Assagaf_K6-7_29 Oktober 2024.ppt
Aminullah Assagaf_K6-7_29 Oktober 2024.pptAminullah Assagaf
 
Aminullah Assagaf_K8-9_Manj Oprs dan Prod_2024.ppt
Aminullah Assagaf_K8-9_Manj Oprs dan Prod_2024.pptAminullah Assagaf_K8-9_Manj Oprs dan Prod_2024.ppt
Aminullah Assagaf_K8-9_Manj Oprs dan Prod_2024.pptAminullah Assagaf
 
Aminullah Assagaf_K4-5_Manj Oprs dan Prod_2021 [Autosaved].ppt
Aminullah Assagaf_K4-5_Manj Oprs dan Prod_2021 [Autosaved].pptAminullah Assagaf_K4-5_Manj Oprs dan Prod_2021 [Autosaved].ppt
Aminullah Assagaf_K4-5_Manj Oprs dan Prod_2021 [Autosaved].pptAminullah Assagaf
 
Aminullah Assagaf_K1-3_Manj Oprs dan Prod_2024.ppt
Aminullah Assagaf_K1-3_Manj Oprs dan Prod_2024.pptAminullah Assagaf_K1-3_Manj Oprs dan Prod_2024.ppt
Aminullah Assagaf_K1-3_Manj Oprs dan Prod_2024.pptAminullah Assagaf
 
Aminullah Assagaf_P7-Ch.9_Project management-32.pptx
Aminullah Assagaf_P7-Ch.9_Project management-32.pptxAminullah Assagaf_P7-Ch.9_Project management-32.pptx
Aminullah Assagaf_P7-Ch.9_Project management-32.pptxAminullah Assagaf
 
Aminullah Assagaf_P6-Ch.8_Human resources-32.pptx
Aminullah Assagaf_P6-Ch.8_Human resources-32.pptxAminullah Assagaf_P6-Ch.8_Human resources-32.pptx
Aminullah Assagaf_P6-Ch.8_Human resources-32.pptxAminullah Assagaf
 
Aminullah Assagaf_P5-Ch.7_Capacity and Facility_32.pptx
Aminullah Assagaf_P5-Ch.7_Capacity and Facility_32.pptxAminullah Assagaf_P5-Ch.7_Capacity and Facility_32.pptx
Aminullah Assagaf_P5-Ch.7_Capacity and Facility_32.pptxAminullah Assagaf
 
Aminullah Assagaf_P4-Ch.6_Processes and technology-32.pptx
Aminullah Assagaf_P4-Ch.6_Processes and technology-32.pptxAminullah Assagaf_P4-Ch.6_Processes and technology-32.pptx
Aminullah Assagaf_P4-Ch.6_Processes and technology-32.pptxAminullah Assagaf
 
Aminullah Assagaf_P3-Ch.4-5_Product Design & Srvice Design.pptx
Aminullah Assagaf_P3-Ch.4-5_Product Design & Srvice Design.pptxAminullah Assagaf_P3-Ch.4-5_Product Design & Srvice Design.pptx
Aminullah Assagaf_P3-Ch.4-5_Product Design & Srvice Design.pptxAminullah Assagaf
 
Aminullah Assagaf_P2-Ch.2-3_Operations Strategy & Qualittty Mangt.pptx
Aminullah Assagaf_P2-Ch.2-3_Operations Strategy & Qualittty Mangt.pptxAminullah Assagaf_P2-Ch.2-3_Operations Strategy & Qualittty Mangt.pptx
Aminullah Assagaf_P2-Ch.2-3_Operations Strategy & Qualittty Mangt.pptxAminullah Assagaf
 

Mehr von Aminullah Assagaf (20)

Aminullah Assagaf_Regresi Lengkap 22_11 April 2024.pdf
Aminullah Assagaf_Regresi Lengkap 22_11 April 2024.pdfAminullah Assagaf_Regresi Lengkap 22_11 April 2024.pdf
Aminullah Assagaf_Regresi Lengkap 22_11 April 2024.pdf
 
Aminullah Assagaf_Regresi Lengkap 22_11 April 2024.pptx
Aminullah Assagaf_Regresi Lengkap 22_11 April 2024.pptxAminullah Assagaf_Regresi Lengkap 22_11 April 2024.pptx
Aminullah Assagaf_Regresi Lengkap 22_11 April 2024.pptx
 
Aminullah Assagaf_Regresi Lengkap 22_11 April 2024.pdf
Aminullah Assagaf_Regresi Lengkap 22_11 April 2024.pdfAminullah Assagaf_Regresi Lengkap 22_11 April 2024.pdf
Aminullah Assagaf_Regresi Lengkap 22_11 April 2024.pdf
 
Aminullah Assagaf_Regresi Lengkap 21_11 April 2024.pdf
Aminullah Assagaf_Regresi Lengkap 21_11 April 2024.pdfAminullah Assagaf_Regresi Lengkap 21_11 April 2024.pdf
Aminullah Assagaf_Regresi Lengkap 21_11 April 2024.pdf
 
Aminullah Assagaf_Regresi Lengkap 21_11 April 2024.pptx
Aminullah Assagaf_Regresi Lengkap 21_11 April 2024.pptxAminullah Assagaf_Regresi Lengkap 21_11 April 2024.pptx
Aminullah Assagaf_Regresi Lengkap 21_11 April 2024.pptx
 
Aminullah Assagaf_Regresi Lengkap 20_10 April 2024_Inc. Data panel & Perbandi...
Aminullah Assagaf_Regresi Lengkap 20_10 April 2024_Inc. Data panel & Perbandi...Aminullah Assagaf_Regresi Lengkap 20_10 April 2024_Inc. Data panel & Perbandi...
Aminullah Assagaf_Regresi Lengkap 20_10 April 2024_Inc. Data panel & Perbandi...
 
Aminullah Assagaf_Regresi Lengkap 19_8 Nov 2023_Inc. Data panel & Perbandinga...
Aminullah Assagaf_Regresi Lengkap 19_8 Nov 2023_Inc. Data panel & Perbandinga...Aminullah Assagaf_Regresi Lengkap 19_8 Nov 2023_Inc. Data panel & Perbandinga...
Aminullah Assagaf_Regresi Lengkap 19_8 Nov 2023_Inc. Data panel & Perbandinga...
 
Aminullah Assagaf_Regresi Lengkap 19_8 Nov 2023_Inc. Data panel & Perbandinga...
Aminullah Assagaf_Regresi Lengkap 19_8 Nov 2023_Inc. Data panel & Perbandinga...Aminullah Assagaf_Regresi Lengkap 19_8 Nov 2023_Inc. Data panel & Perbandinga...
Aminullah Assagaf_Regresi Lengkap 19_8 Nov 2023_Inc. Data panel & Perbandinga...
 
Aminullah Assagaf_K12-14_Manj Oprs dan Prod_2024.ppt
Aminullah Assagaf_K12-14_Manj Oprs dan Prod_2024.pptAminullah Assagaf_K12-14_Manj Oprs dan Prod_2024.ppt
Aminullah Assagaf_K12-14_Manj Oprs dan Prod_2024.ppt
 
Aminullah Assagaf_K10-11_Manj Oprs dan Prod_2024.ppt
Aminullah Assagaf_K10-11_Manj Oprs dan Prod_2024.pptAminullah Assagaf_K10-11_Manj Oprs dan Prod_2024.ppt
Aminullah Assagaf_K10-11_Manj Oprs dan Prod_2024.ppt
 
Aminullah Assagaf_K6-7_29 Oktober 2024.ppt
Aminullah Assagaf_K6-7_29 Oktober 2024.pptAminullah Assagaf_K6-7_29 Oktober 2024.ppt
Aminullah Assagaf_K6-7_29 Oktober 2024.ppt
 
Aminullah Assagaf_K8-9_Manj Oprs dan Prod_2024.ppt
Aminullah Assagaf_K8-9_Manj Oprs dan Prod_2024.pptAminullah Assagaf_K8-9_Manj Oprs dan Prod_2024.ppt
Aminullah Assagaf_K8-9_Manj Oprs dan Prod_2024.ppt
 
Aminullah Assagaf_K4-5_Manj Oprs dan Prod_2021 [Autosaved].ppt
Aminullah Assagaf_K4-5_Manj Oprs dan Prod_2021 [Autosaved].pptAminullah Assagaf_K4-5_Manj Oprs dan Prod_2021 [Autosaved].ppt
Aminullah Assagaf_K4-5_Manj Oprs dan Prod_2021 [Autosaved].ppt
 
Aminullah Assagaf_K1-3_Manj Oprs dan Prod_2024.ppt
Aminullah Assagaf_K1-3_Manj Oprs dan Prod_2024.pptAminullah Assagaf_K1-3_Manj Oprs dan Prod_2024.ppt
Aminullah Assagaf_K1-3_Manj Oprs dan Prod_2024.ppt
 
Aminullah Assagaf_P7-Ch.9_Project management-32.pptx
Aminullah Assagaf_P7-Ch.9_Project management-32.pptxAminullah Assagaf_P7-Ch.9_Project management-32.pptx
Aminullah Assagaf_P7-Ch.9_Project management-32.pptx
 
Aminullah Assagaf_P6-Ch.8_Human resources-32.pptx
Aminullah Assagaf_P6-Ch.8_Human resources-32.pptxAminullah Assagaf_P6-Ch.8_Human resources-32.pptx
Aminullah Assagaf_P6-Ch.8_Human resources-32.pptx
 
Aminullah Assagaf_P5-Ch.7_Capacity and Facility_32.pptx
Aminullah Assagaf_P5-Ch.7_Capacity and Facility_32.pptxAminullah Assagaf_P5-Ch.7_Capacity and Facility_32.pptx
Aminullah Assagaf_P5-Ch.7_Capacity and Facility_32.pptx
 
Aminullah Assagaf_P4-Ch.6_Processes and technology-32.pptx
Aminullah Assagaf_P4-Ch.6_Processes and technology-32.pptxAminullah Assagaf_P4-Ch.6_Processes and technology-32.pptx
Aminullah Assagaf_P4-Ch.6_Processes and technology-32.pptx
 
Aminullah Assagaf_P3-Ch.4-5_Product Design & Srvice Design.pptx
Aminullah Assagaf_P3-Ch.4-5_Product Design & Srvice Design.pptxAminullah Assagaf_P3-Ch.4-5_Product Design & Srvice Design.pptx
Aminullah Assagaf_P3-Ch.4-5_Product Design & Srvice Design.pptx
 
Aminullah Assagaf_P2-Ch.2-3_Operations Strategy & Qualittty Mangt.pptx
Aminullah Assagaf_P2-Ch.2-3_Operations Strategy & Qualittty Mangt.pptxAminullah Assagaf_P2-Ch.2-3_Operations Strategy & Qualittty Mangt.pptx
Aminullah Assagaf_P2-Ch.2-3_Operations Strategy & Qualittty Mangt.pptx
 

KĂĽrzlich hochgeladen

Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfUmakantAnnand
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
Micromeritics - Fundamental and Derived Properties of Powders
Micromeritics - Fundamental and Derived Properties of PowdersMicromeritics - Fundamental and Derived Properties of Powders
Micromeritics - Fundamental and Derived Properties of PowdersChitralekhaTherkar
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 

KĂĽrzlich hochgeladen (20)

Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
CĂłdigo Creativo y Arte de Software | Unidad 1
CĂłdigo Creativo y Arte de Software | Unidad 1CĂłdigo Creativo y Arte de Software | Unidad 1
CĂłdigo Creativo y Arte de Software | Unidad 1
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.Compdf
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Micromeritics - Fundamental and Derived Properties of Powders
Micromeritics - Fundamental and Derived Properties of PowdersMicromeritics - Fundamental and Derived Properties of Powders
Micromeritics - Fundamental and Derived Properties of Powders
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 

Scheduling Operations Management Chapter 17 Lecture Outline

  • 1.
  • 2.
  • 3.
  • 4.
  • 5.
  • 7. • • • Objectives in Scheduling Loading Sequencing • • • • Monitoring Advanced Planning and Theory of Constraints Employee Scheduling Scheduling Systems 17-879 Lecture Outline
  • 8. •Last stage of planning before production occurs •Specifies when labor, equipment, and facilities are needed product or provide a to produce service a 17-880 What is Scheduling?
  • 9. Scheduled Operations • Process Industry • Linear programming • EOQ with non-instantaneous replenishment • Batch Production Aggregate planning Master scheduling • • • Mass Production • Assembly line balancing Project • Project -scheduling techniques (PERT, CPM) Material requirements planning (MRP) Capacity requirements planning (CRP) • • • 17-881 Scheduled Operation
  • 10. Objectives in Scheduling • Meet customer due dates • • Minimize overtime Maximize machine labor utilization or • Minimize job lateness • • Minimize Minimize time Minimize system response time completion • • Minimize idle time Minimize work-in- process inventory • time in the 17-882 Objectives in Schedu
  • 11. Shop Floor Control (SFC) • scheduling and monitoring of day-to-day production in a job shop also called production control and production activity control (PAC) • • usually performed by production control department Loading • Check availability of material, machines, and labor Sequencing Release work orders to shop and issue dispatch lists for individual machines Monitoring Maintain progress reports on each job until it is complete • • • • • 17-883 Shop Floor Control (
  • 12. •Process of assigning work to limited resources •Perform work with most efficient resources •Use assignment method of linear programming to determine allocation 17-884 Loading
  • 13. 1. Perform row reductions • subtract minimum value in each row from all other row values 2. Perform column reductions 4. If number of lines equals number of rows in matrix, then optimum solution has been found. Make assignments where zeros appear Else modify matrix • • subtract minimum value in each column from all other column values 3. Cross out all zeros in matrix • use minimum number of horizontal and vertical lines subtract minimum uncrossed value from all uncrossed values add it to all cells where two lines intersect other values in matrix remain unchanged • • • 5. Repeat steps 3 and 4 until optimum solution is reached 17-885 Assignment Method
  • 14. Assignment Method: Example 17-886 Initial PROJECT Matrix 1 2 3 4 Bryan 10 5 6 10 Kari 6 2 4 6 Noah 7 6 5 6 Chris 9 5 4 10 Row reduction Column reduction Cover all zeros 5 0 1 5 3 0 1 4 3 0 1 4 4 0 2 4 2 0 2 3 2 0 2 3 2 1 0 1 0 1 0 0 0 1 0 0 5 1 0 6 3 1 0 5 3 1 0 5 Number lines number of rows so modify matrix Assignment Method: E
  • 15. Project Cost = (5 + 6 + 4 + 6) X $100 = $2,100 17-887 Assignment Method: Example (cont.) Modify matrix Cover all zeros 1 0 1 2 1 0 1 2 0 0 2 1 0 0 2 1 0 3 2 0 0 3 2 0 1 1 0 3 1 1 0 3 Number of lines = number of rows so at optimal solution PROJECT PROJECT 1 2 3 4 1 2 3 4 Bryan 1 0 1 2 Bryan 10 5 6 10 Kari 0 0 2 1 Kari 6 2 4 6 Noah 0 3 2 0 Noah 7 6 5 6 Chris 1 1 0 3 Chris 9 5 4 10
  • 16. Prioritize jobs assigned to a resource If no order specified use first-come first-served (FCFS) Other Sequencing Rules FCFS - first-come, first-served LCFS - last come, first served DDATE - earliest due date CUSTPR - highest customer priority SETUP - similar required setups SLACK - smallest slack CR - smallest critical ratio SPT - shortest processing time LPT - longest processing time 17-888 Sequencing
  • 17. Simple Sequencing Rules 17-891 PROCESSING DUE JOB TIME DA TE A 5 10 B 10 15 C 2 5 D 8 12 E 6 8 Simple Sequencing Ru
  • 18. A 0 5 5 10 0 17-892 FCFS START PROCESSING COMPLETION DUE SEQUENCE TIME TIME TIME DATE TARDINESS B 5 10 15 15 0 C 15 2 17 5 12 D 17 8 25 12 13 E 25 6 31 8 23 Total 93 48 Average 93/5 = 18.60 48/5 = 9.6 Simple Sequencing Rules: FCFS
  • 19. 17-893 DDATE START PROCESSING COMPLETION DUE SEQUENCE TIME TIME TIME DATE TARDINESS C 0 2 2 5 0 E 2 6 8 8 0 A 8 5 13 10 3 D 13 8 21 12 9 B 21 10 31 15 16 Total 75 28 Average 75/5 = 15.00 28/5 = 5.6 Simple Sequencing Rules: DDATE
  • 20. 17-895 SPT START PROCESSING COMPLETION DUE SEQUENCE TIME TIME TIME DATE TARDINESS C 0 2 2 5 0 A 2 5 7 10 0 E 7 6 13 8 5 D 13 8 21 12 9 B 21 10 31 15 16 Total 74 30 Average 74/5 = 14.80 30/5 = 6 Simple Sequencing Rules: SPT
  • 21. 5.6 3 16 17-896 AVERAGE AVERAGE NO. OF MAXIMUM RULE COMPLETION TIME TARDINESS JOBS TARDY TARDINESS FCFS 18.60 9.6 3 23 DDATE 15.00 5.6 3 SLACK 16.40 6.8 4 16 SPT 14.80 6.0 3 16 Simple Sequencing Rules: Summary
  • 22. Guidelines for Selecting a 1. 2. 3. SPT most useful when shop is highly congested Use SLACK for periods of normal activity Use DDATE when only small tardiness values can be tolerated Use LPT if subcontracting is anticipated Use FCFS when operating at low-capacity levels Do not use SPT to sequence jobs that have to be assembled with other jobs at a later date 4. 5. 6. 17-900 Guidelines for Selectin Sequencing Rule
  • 23. •Work package • Shop paperwork that travels with a job •Gantt Chart • Shows both planned and completed activities against a time scale •Input/Output Control • Monitors the input and output work center from each 17-901 Monitoring
  • 24. 17-902 Facility Gantt Chart Job 32B 3 Behind schedule Job 23C 2 Ahead of schedule Job 11C Job 12A 1 On schedule 1 2 3 4 5 6 8 9 10 11 12 Days Today’s Date Key: Planned activity Completed activity
  • 25. 20 10 5 0 17-903 Input/Output Control Input/Output Report PERIOD 1 2 3 4 TOTAL Planned input 65 65 70 70 270 Actual input 0 Deviation 0 Planned output 75 75 75 75 300 Actual output 0 Deviation 0 Backlog 30
  • 26. 17-904 Input/Output Control (cont.) Input/Output Report PERIOD 1 2 3 4 TOTAL Planned input 65 65 70 70 270 Actual input 60 60 65 65 250 Deviation -5 -5 -5 -5 -20 Planned output 75 75 75 75 300 Actual output 75 75 65 65 280 Deviation -0 -0 -10 -10 -20 Backlog 30 15 0 0 0
  • 27. •Infinite - assumes infinite capacity • Loads without regard to capacity • Then levels the load and sequences jobs •Finite - assumes finite (limited) capacity • Sequences jobs as part of the loading decision • Resources are never loaded beyond capacity 17-905 Advanced Planning and Scheduling Systems
  • 28. Scheduling Systems (cont.) • Advanced planning and scheduling (APS) • Add-ins to ERP systems • Constraint-based programming (CBP) identifies a solution space and evaluates alternatives • Genetic algorithms based on natural selection properties of genetics • Manufacturing execution system (MES) monitors status, usage, availability, quality 17-906 Advanced Planning and Scheduling Systems (c
  • 29. • Not all resources are used evenly • Concentrate on the” bottleneck” resource • Synchronize flow through the bottleneck • Use process and transfer batch sizes to move product through facility 17-907 Theory of Constraints
  • 30. • Drum • Bottleneck, beating to set the pace of production for the rest of the system • Buffer • Inventory placed in front of the bottleneck to ensure it is always kept busy • Determines output or throughput of the system • Rope • Communication signal; tells processes upstream when they should begin production 17-908 Drum-Buffer-Rope
  • 31. TOC Scheduling Procedure • Identify bottleneck • Schedule job first whose lead time to bottleneck is less than or equal to bottleneck processing time • Forward schedule bottleneck machine • Backward schedule other machines to sustain bottleneck schedule • Transfer in batch sizes smaller than process batch size 17-909 TOC Scheduling Pro
  • 32. D3 3 5 C3 2 15 B3 1 7 B2 2 3 C2 1 10 D2 2 8 B1 1 5 C1 3 2 D1 3 10 Synchronous ij k l Operation j of item i performed at Manufacturing nutes 17-910 B C D B3 1 7 C3 B2 2 3 C2 B1 1 5 C1 Key: i Item i ij k l Operation j of item i perfor machine center k takes l mi to process A
  • 33. Demand = 100 A’s Machine setup time = 60 minutes * Bottleneck 17-911 MACHINE 1 MACHINE 2 MACHINE 3 B1 5 B2 3 C1 2 B3 7 C3 15 D3 5 C2 10 D2 8 D1 10 Sum 22 26* 17 Synchronous Manufacturing (cont.)
  • 34. Completion 2737 17-912 Synchronous Manufacturing (cont.) Machine 1 Setup Setup C2 B1 B3 2 1002 1562 2322 Idle Machine 2 Setup Setup C3 B2 D2 12 1512 1872 2732 Machine 3 Setup Setup C1 D1 Idle D3 0 200 1260 1940 time
  • 35. Employee Scheduling • Labor is very flexible resource Scheduling workforce is • complicated, repetitive task Assignment method can be used Heuristics are commonly used • • 17-913 Employee Schedulin
  • 36. Employee Scheduling Heuristic 1. Let N = no. of workers available Di = demand for workers on day i X = day working O = day off Assign the first N - D1 workers day 1 off. Assign the next N - D2 2. workers day 2 off. Continue in a similar manner until all days are have been scheduled 3. If number of workdays for full time employee < 5, assign remaining workdays so consecutive days off are possible 4. Assign any remaining work to part-time employees 5. If consecutive days off are desired, consider switching schedules among days with the same demand requirements 17-914 Employee Scheduling
  • 37. Automated Scheduling Systems • Staff Scheduling • Schedule Bidding • Schedule Optimization 17-918 Automated Scheduli