PB 602 OPERATION MANAGEMENT 
PROJECT MANAGEMENT TECHNIQUES 
PN SITI MARIAM BINTI SAMAT 
Mohamad Ihsan Hakim Bin Rozali 16BPM12F2004 
Muhamad Shaiful Nizam Bin Abd Rahman 16BPM12F2003 
Raja Izzat Muqri Bin Raja Zahari 16DPM11F2033
PERT AND CPM 
Program evaluation and review technique and the Critical 
path method is develop in 1950s to help managers 
schedule, monitor and control large and complex projects.
Définition PERT 
• PERT stands for program évaluation and review 
technique 
• A Project management technique That employs three 
times estimates for each activity
Definition CPM 
• CPM stands for critical path method 
• A Project management technique That uses only one 
time factor per activity
Six basic step for PERT and CPM 
1. Define the project and prepare the work breakdown structure 
2. Develop the relationship among the activities. Decide which 
activities must precede and which must follow others. 
3. Draw the network connecting all the activities 
4. Assign time and/or cost estimates to each activity 
5. Compute the longest time path through the network. This is called 
critical path. 
6. Use the network to help plan, schedule, monitor and control the 
project
Important of PERT and CPM 
Answer the question of: 
• When will the entire project be completed? 
• Which are the noncritical activities? 
• What is the probability that the project will be completed by a 
specific date? 
• At any particular date, is the project on schedule,behind 
schedule or ahead of schedule? 
• On any given time is the money spend equal to,less than,or 
greater than budgeted amount?
Important of PERT and CPM 
• Are there enough resources available to finish the project on 
time? 
• If the project is to be finished in a shorter amount of time, what 
is the best way to accomplish this goal at the least cost?
Program Evaluation and 
Review Technique (PERT)
Steps to Develop and Analyze a PERT 
Network 
STEP 1 
Decompose project into individual job or tasks and 
identify each of them. 
STEP 2 
Find out activities or tasks sequence and develop 
network. 
STEP 3 
Estimate each activities duration time
STEP 4 
Obtain expected duration time of each activity 
STEP 5 
Determine each activity time variance 
STEP 6 
Find out the critical path of the network under study. 
Step 7 
Calculate project completion probability on the 
specified time (date).
Earliest start (ES) = earliest time at which an activity can start, assuming all 
Activity Description Time (weeks) 
predecessors have been completed 
A Build internal components 2 
B Modify roof and floor 3 
C Construct collection stack 2 
D Pour concrete and install frame 4 
E Build high-temperature burner 4 
F Install pollution control system 3 
G Install air pollution device 5 
H Inspect and test 2 
Earliest finish (EF) = earliest time at which an activity can be finished 
Latest start (LS) = latest time at which an activity can start so as to not delay 
the completion time of the entire project 
Latest finish (LF) = latest time by which an activity has to be finished so as to 
not delay the completion time of the entire project 
Total Time (weeks) 25
A 
Activity Name or 
Symbol 
Earliest 
Start ES 
Earliest 
EF Finish 
Latest 
Start 
LS Latest 
Finish 
LF 
Activity Duration 
2
Forward Pass 
Begin at starting event and work forward 
Earliest Start Time Rule: 
 If an activity has only a single immediate 
predecessor, its ES equals the EF of the 
predecessor 
 If an activity has multiple immediate 
predecessors, its ES is the maximum of all 
the EF values of its predecessors 
ES = Max {EF of all immediate predecessors}
Forward Pass 
Begin at starting event and work forward 
Earliest Finish Time Rule: 
 The earliest finish time (EF) of an activity is 
the sum of its earliest start time (ES) and its 
activity time 
EF = ES + Activity time
Backward Pass 
Begin with the last event and work backwards 
Latest Finish Time Rule: 
 If an activity is an immediate predecessor for 
just a single activity, its LF equals the LS of the 
activity that immediately follows it 
 If an activity is an immediate predecessor to 
more than one activity, its LF is the minimum 
of all LS values of all activities that 
immediately follow it 
LF = Min {LS of all immediate following activities}
Backward Pass 
Begin with the last event and work backwards 
Latest Start Time Rule: 
 The latest start time (LS) of an activity is the 
difference of its latest finish time (LF) and its 
activity time 
LS = LF – Activity time
AON Example 
Milwaukee Paper Manufacturing's 
Activities and Predecessors 
Activity Description 
Immediate 
Predecessors 
A Build internal components — 
B Modify roof and floor — 
C Construct collection stack A 
D Pour concrete and install frame A, B 
E Build high-temperature burner C 
F Install pollution control system C 
G Install air pollution device D, E 
H Inspect and test F, G
AON Network for Milwaukee 
Paper 
G 
E 
F 
H 
A C 
Start 
B D 
Arrows Show Precedence 
Relationships
Activity Description Times(week) 
A Build internal components 2 
B Modify roof and floor 3 
C Construct collection stack 2 
D Pour concrete and install 
frame 
4 
E Build high-temperature 
burner 
4 
F Install pollution control 
system 
3 
G Install air pollution device 5 
H Inspect and test 2
Perth diagram for 
Milwaukee Paper 
E 
7 
4 8 13 15 
4 
F 
3 
G 
5 
H 
2 
4 
8 13 
13 15 
10 13 
8 13 
4 8 
C 
2 4 
2 
D 
3 7 
4 
0 2 
B 
0 3 
3 
Start 
0 
0 
0 
A 
2 
2 4 
4 8 
0 2 
1 4 
0 0
Example 2 : 
lisa Sdn Bhd owns a data needed to complete a work on a project in Kulim Kedah Farm. Ask 
your company Assistant Project Manager to prepare a working paper based on information 
table 
Activities Immediate 
precedence 
Activities 
Optimistic 
Time 
(month) 
Most Likely Time Pessimistic time 
A - 4 5 12 
B A 3 4.5 15 
C A 2 3 4 
D C 6 8 22 
E B 4 6 8 
F C 3 4 5 
G D,E 1.5 3 4.5 
H B 5 7 15 
I H 3 4 5 
J G,I 2 4 6
(I) The time required to complete each activity 
(II) Construct the PERT network for each activity 
(III) Count ES,EF,LS, and LF 
(IV) The longest time to complete the project 
i. The optimistic time (a) 
ii. The pessimistic time(m) 
iii. The most likely time(b) 
t =a+4m+b 
6
Activities Immediate 
precedence 
Activities 
Optimistic 
Time 
(month) 
Most Likely 
Time 
Pessimistic 
time 
Expected 
time 
A - 4 5 12 6 
B A 3 4.5 15 6 
C A 2 3 4 3 
D C 6 8 22 10 
E B 4 6 8 6 
F C 3 4 5 4 
G D,E 1.5 3 4.5 3 
H B 5 7 15 8 
I H 3 4 5 4 
J G,I 2 4 6 4
Answer:Pert diagram and cpm 
will be show at the whiteboard
Advantages of PERT/CPM 
1. Especially useful when scheduling and 
controlling large projects 
2. Straightforward concept and not mathematically 
complex 
3. Graphical networks help highlight relationships 
among project activities 
4. Critical path and slack time analyses help 
pinpoint activities that need to be closely 
watched
Advantages of PERT/CPM 
5. Project documentation and graphics point out 
who is responsible for various activities 
6. Applicable to a wide variety of projects 
7. Useful in monitoring not only schedules but 
costs as well
Limitations of PERT/CPM 
1. Project activities have to be clearly defined, 
independent, and stable in their relationships 
2. Precedence relationships must be specified and 
networked together 
3. Time estimates tend to be subjective and are 
subject to fudging by managers 
4. There is an inherent danger of too much 
emphasis being placed on the longest, or critical, 
path

Weitere ähnliche Inhalte

Was ist angesagt?

Critical path method
Critical path methodCritical path method
Critical path method
Nicola2903
 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path Method
Nicola2903
 
05 critical path analysis
05 critical path analysis05 critical path analysis
05 critical path analysis
Sam Catlin
 

Was ist angesagt? (19)

Critical path method
Critical path methodCritical path method
Critical path method
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Complex Project Crashing Algorithm
Complex Project Crashing AlgorithmComplex Project Crashing Algorithm
Complex Project Crashing Algorithm
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
 
Critical path method
Critical path methodCritical path method
Critical path method
 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path Method
 
(Aoa) and (aon) networks
(Aoa) and (aon) networks(Aoa) and (aon) networks
(Aoa) and (aon) networks
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 
Pert analysis
Pert analysisPert analysis
Pert analysis
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysis
 
Per tand project crashing
Per tand project crashingPer tand project crashing
Per tand project crashing
 
CPM-Updating
CPM-UpdatingCPM-Updating
CPM-Updating
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
05 critical path analysis
05 critical path analysis05 critical path analysis
05 critical path analysis
 
Project management@ ppt doms
Project management@ ppt doms Project management@ ppt doms
Project management@ ppt doms
 
Critical Path Method(CPM)
Critical Path Method(CPM)Critical Path Method(CPM)
Critical Path Method(CPM)
 
Cpmprt
CpmprtCpmprt
Cpmprt
 
CPM - Critical Path Method
CPM - Critical Path MethodCPM - Critical Path Method
CPM - Critical Path Method
 

Ähnlich wie Pb602 operation management chapter 7

C10 project management
C10 project managementC10 project management
C10 project management
hakimizaki
 
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
hannahpepino1
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
Debanjan15
 
Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02
kongara
 
Scheduling, PERT, Critical Path Analysis.pdf
Scheduling, PERT, Critical Path Analysis.pdfScheduling, PERT, Critical Path Analysis.pdf
Scheduling, PERT, Critical Path Analysis.pdf
ssuserc9c6261
 

Ähnlich wie Pb602 operation management chapter 7 (20)

C10 project management
C10 project managementC10 project management
C10 project management
 
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
 
Presentation7
Presentation7Presentation7
Presentation7
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering Economics
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
 
Cpm n pert
Cpm n pertCpm n pert
Cpm n pert
 
Project management
Project managementProject management
Project management
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
 
Ch 5.pptx
Ch 5.pptxCh 5.pptx
Ch 5.pptx
 
PM-Problems.pptx
PM-Problems.pptxPM-Problems.pptx
PM-Problems.pptx
 
Pertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLPertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOL
 
Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02
 
Cpm and pert
Cpm and pertCpm and pert
Cpm and pert
 
Project Networking Techniques
Project Networking TechniquesProject Networking Techniques
Project Networking Techniques
 
cpmpertmy (1)
cpmpertmy (1)cpmpertmy (1)
cpmpertmy (1)
 
DEFINITION OF TERMS IN A NETWORK.pdf
DEFINITION OF TERMS IN A NETWORK.pdfDEFINITION OF TERMS IN A NETWORK.pdf
DEFINITION OF TERMS IN A NETWORK.pdf
 
chapter 8 examples of networks.pdf
chapter 8 examples of networks.pdfchapter 8 examples of networks.pdf
chapter 8 examples of networks.pdf
 
EXAMPLES OF THE USE OF DUMMYACTIVITY.pdf
EXAMPLES OF THE USE OF DUMMYACTIVITY.pdfEXAMPLES OF THE USE OF DUMMYACTIVITY.pdf
EXAMPLES OF THE USE OF DUMMYACTIVITY.pdf
 
Scheduling, PERT, Critical Path Analysis.pdf
Scheduling, PERT, Critical Path Analysis.pdfScheduling, PERT, Critical Path Analysis.pdf
Scheduling, PERT, Critical Path Analysis.pdf
 

Kürzlich hochgeladen

Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please Practise
AnaAcapella
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
ciinovamais
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
negromaestrong
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
kauryashika82
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
heathfieldcps1
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
QucHHunhnh
 

Kürzlich hochgeladen (20)

Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please Practise
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptxSKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 

Pb602 operation management chapter 7

  • 1. PB 602 OPERATION MANAGEMENT PROJECT MANAGEMENT TECHNIQUES PN SITI MARIAM BINTI SAMAT Mohamad Ihsan Hakim Bin Rozali 16BPM12F2004 Muhamad Shaiful Nizam Bin Abd Rahman 16BPM12F2003 Raja Izzat Muqri Bin Raja Zahari 16DPM11F2033
  • 2. PERT AND CPM Program evaluation and review technique and the Critical path method is develop in 1950s to help managers schedule, monitor and control large and complex projects.
  • 3. Définition PERT • PERT stands for program évaluation and review technique • A Project management technique That employs three times estimates for each activity
  • 4. Definition CPM • CPM stands for critical path method • A Project management technique That uses only one time factor per activity
  • 5. Six basic step for PERT and CPM 1. Define the project and prepare the work breakdown structure 2. Develop the relationship among the activities. Decide which activities must precede and which must follow others. 3. Draw the network connecting all the activities 4. Assign time and/or cost estimates to each activity 5. Compute the longest time path through the network. This is called critical path. 6. Use the network to help plan, schedule, monitor and control the project
  • 6. Important of PERT and CPM Answer the question of: • When will the entire project be completed? • Which are the noncritical activities? • What is the probability that the project will be completed by a specific date? • At any particular date, is the project on schedule,behind schedule or ahead of schedule? • On any given time is the money spend equal to,less than,or greater than budgeted amount?
  • 7. Important of PERT and CPM • Are there enough resources available to finish the project on time? • If the project is to be finished in a shorter amount of time, what is the best way to accomplish this goal at the least cost?
  • 8. Program Evaluation and Review Technique (PERT)
  • 9. Steps to Develop and Analyze a PERT Network STEP 1 Decompose project into individual job or tasks and identify each of them. STEP 2 Find out activities or tasks sequence and develop network. STEP 3 Estimate each activities duration time
  • 10. STEP 4 Obtain expected duration time of each activity STEP 5 Determine each activity time variance STEP 6 Find out the critical path of the network under study. Step 7 Calculate project completion probability on the specified time (date).
  • 11. Earliest start (ES) = earliest time at which an activity can start, assuming all Activity Description Time (weeks) predecessors have been completed A Build internal components 2 B Modify roof and floor 3 C Construct collection stack 2 D Pour concrete and install frame 4 E Build high-temperature burner 4 F Install pollution control system 3 G Install air pollution device 5 H Inspect and test 2 Earliest finish (EF) = earliest time at which an activity can be finished Latest start (LS) = latest time at which an activity can start so as to not delay the completion time of the entire project Latest finish (LF) = latest time by which an activity has to be finished so as to not delay the completion time of the entire project Total Time (weeks) 25
  • 12. A Activity Name or Symbol Earliest Start ES Earliest EF Finish Latest Start LS Latest Finish LF Activity Duration 2
  • 13. Forward Pass Begin at starting event and work forward Earliest Start Time Rule:  If an activity has only a single immediate predecessor, its ES equals the EF of the predecessor  If an activity has multiple immediate predecessors, its ES is the maximum of all the EF values of its predecessors ES = Max {EF of all immediate predecessors}
  • 14. Forward Pass Begin at starting event and work forward Earliest Finish Time Rule:  The earliest finish time (EF) of an activity is the sum of its earliest start time (ES) and its activity time EF = ES + Activity time
  • 15. Backward Pass Begin with the last event and work backwards Latest Finish Time Rule:  If an activity is an immediate predecessor for just a single activity, its LF equals the LS of the activity that immediately follows it  If an activity is an immediate predecessor to more than one activity, its LF is the minimum of all LS values of all activities that immediately follow it LF = Min {LS of all immediate following activities}
  • 16. Backward Pass Begin with the last event and work backwards Latest Start Time Rule:  The latest start time (LS) of an activity is the difference of its latest finish time (LF) and its activity time LS = LF – Activity time
  • 17. AON Example Milwaukee Paper Manufacturing's Activities and Predecessors Activity Description Immediate Predecessors A Build internal components — B Modify roof and floor — C Construct collection stack A D Pour concrete and install frame A, B E Build high-temperature burner C F Install pollution control system C G Install air pollution device D, E H Inspect and test F, G
  • 18. AON Network for Milwaukee Paper G E F H A C Start B D Arrows Show Precedence Relationships
  • 19. Activity Description Times(week) A Build internal components 2 B Modify roof and floor 3 C Construct collection stack 2 D Pour concrete and install frame 4 E Build high-temperature burner 4 F Install pollution control system 3 G Install air pollution device 5 H Inspect and test 2
  • 20. Perth diagram for Milwaukee Paper E 7 4 8 13 15 4 F 3 G 5 H 2 4 8 13 13 15 10 13 8 13 4 8 C 2 4 2 D 3 7 4 0 2 B 0 3 3 Start 0 0 0 A 2 2 4 4 8 0 2 1 4 0 0
  • 21. Example 2 : lisa Sdn Bhd owns a data needed to complete a work on a project in Kulim Kedah Farm. Ask your company Assistant Project Manager to prepare a working paper based on information table Activities Immediate precedence Activities Optimistic Time (month) Most Likely Time Pessimistic time A - 4 5 12 B A 3 4.5 15 C A 2 3 4 D C 6 8 22 E B 4 6 8 F C 3 4 5 G D,E 1.5 3 4.5 H B 5 7 15 I H 3 4 5 J G,I 2 4 6
  • 22. (I) The time required to complete each activity (II) Construct the PERT network for each activity (III) Count ES,EF,LS, and LF (IV) The longest time to complete the project i. The optimistic time (a) ii. The pessimistic time(m) iii. The most likely time(b) t =a+4m+b 6
  • 23. Activities Immediate precedence Activities Optimistic Time (month) Most Likely Time Pessimistic time Expected time A - 4 5 12 6 B A 3 4.5 15 6 C A 2 3 4 3 D C 6 8 22 10 E B 4 6 8 6 F C 3 4 5 4 G D,E 1.5 3 4.5 3 H B 5 7 15 8 I H 3 4 5 4 J G,I 2 4 6 4
  • 24. Answer:Pert diagram and cpm will be show at the whiteboard
  • 25. Advantages of PERT/CPM 1. Especially useful when scheduling and controlling large projects 2. Straightforward concept and not mathematically complex 3. Graphical networks help highlight relationships among project activities 4. Critical path and slack time analyses help pinpoint activities that need to be closely watched
  • 26. Advantages of PERT/CPM 5. Project documentation and graphics point out who is responsible for various activities 6. Applicable to a wide variety of projects 7. Useful in monitoring not only schedules but costs as well
  • 27. Limitations of PERT/CPM 1. Project activities have to be clearly defined, independent, and stable in their relationships 2. Precedence relationships must be specified and networked together 3. Time estimates tend to be subjective and are subject to fudging by managers 4. There is an inherent danger of too much emphasis being placed on the longest, or critical, path