A Presentation
on
North-West Corner Method
Prepared by
Akash S Jadhav
(Assistant Professor, SRES Sanjivani College of Engineering, Kopargaon)
and
Umesh T kulkarni
(Assistant Professor, SRES Sanjivani College of Engineering, Kopargaon)
1
North-West (N-W) Corner Method
• N-W corner method is one of the technique used to
solve transportation models.
• In N-W corner method, we have to give the allocation
to N-W corner cell of the matrix (Transportation
Model).
2
N-W Corner Method
 Let us solve a Transportation Model by this method.
 Let us consider the following Transportation Model.
I II III IV Supply↓
A 1 3 5 6 90
B 11 1 3 8 70
C 10 16 12 10 40
Demand → 50 50 25 75
Store →
Factory ↓
3
Step I
 In order to proceed further The ∑ demand Should be equal to ∑ Supply.
∑Demand = ∑ Supply
50+50+25+75 = 90+70+40
200 = 200 …………………..(satisfies)
I II III IV Supply ↓
A 1 3 5 6 90
B 11 1 3 8 70
C 10 16 12 10 40
Demand → 50 50 25 75 200
200
Store →
Factory ↓
4
Step II
• Select the N-W corner cell of the matrix(marked in
yellow color).
1
3 5 6
90
11 1 3 8
70
10 16 12 10
40
50 50 25 75
N
E
S
W
5
Step II
• Give the allocation sign to this N-W Corner cell as
shown.
1
3 5 6
90
11 1 3 8
70
10 16 12 10
40
50 50 25 75
N
E
S
W
Demand →
Supply↓
6
Step II
• For this selected cell, the corresponding demand and supply values are 50
& 90 respectively.
• Select the least value among the above two values i.e 50.
• Allocate this 50 value to the N-W corner cell.
1
3 5 6
90
11 1 3 8
70
10 16 12 10
40
50 50 25 75
Demand →
Supply↓
50
7
Step II
• Subtract the allocated value (50) from corresponding demand and supply values.
• Now the new corresponding demand & supply values are 0 & 40 as shown below.
1
3 5 6
90
11 1 3 8
70
10 16 12 10
40
50 50 25 75
Demand →
Supply↓
50
(50-50)
0
8
(90-50)
40
Step II
• As the demand value of first column is brought to zero, delete/scratch that column (First
column). After deleting the column, the new matrix will be of 3 factories & 3 Stores.
1
3 5 6
90
11 1 3 8
70
10 16 12 10
40
50 50 25 75
Demand →
Supply↓
50
(90-50)
40
9
(50-50)
0
Step II
• The new matrix is as below.
• Now select the N-W corner cell from this new matrix (marked in yellow color).
• Select the least value from the corresponding demand & supply value of this N-W corner cell
viz 40. (among 50 & 40).
• Allocate this least value (40) into the allocation sign as shown and subtract it from both ends
(i.e. from corresponding demand & Supply values).
• As the supply value for the first row is brought to zero, delete/scratch that row.
• The new matrix will be having 2 factories & 3 stores.
3
5 6
40
1 3 8
70
16 12 10
40
50 25 75Demand →
Supply↓
40
0
10 10
Step II
• The new matrix is as below.
• Now select the N-W corner cell from this new matrix (marked in yellow color).
• Select the least value from the corresponding demand & supply value of this N-W corner cell
viz 10. (among 10 & 70).
• Allocate this least value (10) into the allocation sign as shown and subtract it from both ends
(i.e. from corresponding demand & Supply values).
• As the demand value for the first column is brought to zero, delete/scratch that column.
• The new matrix will be having 2 factories & 2 stores.
1
3 8
70
16 12 10
40
10 25 75
Demand →
Supply↓
10
0
60
11
Step II
• The new matrix is as below.
• Now select the N-W corner cell from this new matrix (marked in yellow color).
• Select the least value from the corresponding demand & supply value of this N-W corner cell
viz 25. (among 25& 60).
• Allocate this least value (25) into the allocation sign as shown and subtract it from both ends
(i.e. from corresponding demand & Supply values).
• As the demand value for the first column is brought to zero, delete/scratch that column.
• The new matrix will be having 2 factories & 1 store.
3
8
60
12 10
40
25 75
Demand →
Supply↓
25
0
35
12
Step II
• The new matrix is as below.
• Now select the N-W corner cell from this new matrix (marked in yellow color).
• Select the least value from the corresponding demand & supply value of this N-W corner cell
viz 35. (among 75 & 35).
• Allocate this least value (35) into the allocation sign as shown and subtract it from both ends
(i.e. from corresponding demand & Supply values).
• As the demand value for the first row is brought to zero, delete/scratch that row.
• The new matrix will be having 1 factory & 1 store. i.e. only one value.
8 35
10 40
75Demand →
Supply↓
35
40
0
13
Step II
• The new matrix is as below. The matrix is having only one cell value.
• Now select this only remaining cell (marked in yellow color).
• Select the least value from the corresponding demand & supply value of this N-W corner cell
viz 40. (among 40 & 40). Both supply and demand values are same.
• Allocate this least value (40) into the allocation sign as shown and subtract it from both ends
(i.e. from corresponding demand & Supply values).
• Hence the demand value as well as the supply value for this only remaining cell is brought to
zero. This verifies that our calculations were right. At the end no demand and supply value
should remain.
10 40
40Demand →
Supply↓
40
0
0
14
Step III
• The solution matrix is as follows
• Finally to find the transportation cost, do the summation of product of allocation value
and corresponding transportation cost
• Hence we have,
Transportation cost = 1 x 50 + 3 X 40 + 1 X 10 + 3 X 25 + 8 X 35 + 10 X 40
= 935 units
1 3
5 6
11
1 3 8
10 16 12
10
50 40
10 25 35
40
Corresponding
Transportation cost
Allocation Value
15
THANK YOU
16

Weitere ähnliche Inhalte

Was ist angesagt?

MODI Method (Operations Research)
MODI Method (Operations Research) MODI Method (Operations Research)
MODI Method (Operations Research) Nilraj Vasandia
 
Transportation problem
Transportation problemTransportation problem
Transportation problemShubhagata Roy
 
VAM and MODI Method in Solving Transportation Problems
VAM and MODI Method in Solving Transportation ProblemsVAM and MODI Method in Solving Transportation Problems
VAM and MODI Method in Solving Transportation ProblemsKarlo Maniego
 
Deepika(14 mba5012) transportation ppt
Deepika(14 mba5012)  transportation pptDeepika(14 mba5012)  transportation ppt
Deepika(14 mba5012) transportation pptDeepika Bansal
 
Transportation problem
Transportation problemTransportation problem
Transportation problemKamel Attar
 
Transportation problem_Operation research
Transportation problem_Operation researchTransportation problem_Operation research
Transportation problem_Operation researchAtaur Rahman
 
Assignment problem
Assignment problemAssignment problem
Assignment problemAbu Bashar
 
Vogel’s Approximation Method (VAM)
Vogel’s Approximation Method (VAM)Vogel’s Approximation Method (VAM)
Vogel’s Approximation Method (VAM)dkpawar
 
Transportation model
Transportation modelTransportation model
Transportation modelLokesh Payasi
 
Transportation model
Transportation modelTransportation model
Transportation modelSATISH
 
Transportation problem ppt
Transportation problem pptTransportation problem ppt
Transportation problem pptDr T.Sivakami
 
Unit.5. transportation and assignment problems
Unit.5. transportation and assignment problemsUnit.5. transportation and assignment problems
Unit.5. transportation and assignment problemsDagnaygebawGoshme
 
Modified distribution method (modi method)
Modified distribution method (modi method)Modified distribution method (modi method)
Modified distribution method (modi method)Dinesh Suthar
 
Transportatopn problm
Transportatopn problmTransportatopn problm
Transportatopn problmAnshul Singh
 

Was ist angesagt? (20)

Transportation problems
Transportation problemsTransportation problems
Transportation problems
 
MODI Method (Operations Research)
MODI Method (Operations Research) MODI Method (Operations Research)
MODI Method (Operations Research)
 
Transportation problem
Transportation problemTransportation problem
Transportation problem
 
VAM and MODI Method in Solving Transportation Problems
VAM and MODI Method in Solving Transportation ProblemsVAM and MODI Method in Solving Transportation Problems
VAM and MODI Method in Solving Transportation Problems
 
Deepika(14 mba5012) transportation ppt
Deepika(14 mba5012)  transportation pptDeepika(14 mba5012)  transportation ppt
Deepika(14 mba5012) transportation ppt
 
Transportation problem
Transportation problemTransportation problem
Transportation problem
 
Transportation problem_Operation research
Transportation problem_Operation researchTransportation problem_Operation research
Transportation problem_Operation research
 
Assignment model
Assignment modelAssignment model
Assignment model
 
Assignment problem
Assignment problemAssignment problem
Assignment problem
 
Vogel’s Approximation Method (VAM)
Vogel’s Approximation Method (VAM)Vogel’s Approximation Method (VAM)
Vogel’s Approximation Method (VAM)
 
North West Corner Method
North West Corner MethodNorth West Corner Method
North West Corner Method
 
Transportation model
Transportation modelTransportation model
Transportation model
 
North West Corner Method
North West Corner MethodNorth West Corner Method
North West Corner Method
 
Transportation model
Transportation modelTransportation model
Transportation model
 
Transportation problem ppt
Transportation problem pptTransportation problem ppt
Transportation problem ppt
 
Modi method
Modi methodModi method
Modi method
 
Assignment problems
Assignment problemsAssignment problems
Assignment problems
 
Unit.5. transportation and assignment problems
Unit.5. transportation and assignment problemsUnit.5. transportation and assignment problems
Unit.5. transportation and assignment problems
 
Modified distribution method (modi method)
Modified distribution method (modi method)Modified distribution method (modi method)
Modified distribution method (modi method)
 
Transportatopn problm
Transportatopn problmTransportatopn problm
Transportatopn problm
 

Ähnlich wie North west corner method

Transporataion method north waste corner
Transporataion method north waste cornerTransporataion method north waste corner
Transporataion method north waste cornerSmitaSonawane7
 
Vogel's Approximation Method
Vogel's Approximation MethodVogel's Approximation Method
Vogel's Approximation MethodUsharaniRavikumar
 
Lecture 7 transportation problem finding initial basic feasible solution
Lecture 7 transportation problem finding initial basic feasible solutionLecture 7 transportation problem finding initial basic feasible solution
Lecture 7 transportation problem finding initial basic feasible solutionAathi Suku
 
VOGEL'S APPROXIMATION METHOD
VOGEL'S APPROXIMATION METHODVOGEL'S APPROXIMATION METHOD
VOGEL'S APPROXIMATION METHODSwethaShree13
 
north west corner and matrix minima
north west corner and matrix minimanorth west corner and matrix minima
north west corner and matrix minimaMallaJayachandra
 
Karnaugh map
Karnaugh mapKarnaugh map
Karnaugh mapchandkec
 
Assignment method
Assignment methodAssignment method
Assignment methodR A Shah
 
Classbfs121001503719748
Classbfs121001503719748Classbfs121001503719748
Classbfs121001503719748Raju Panthadi
 
Lecture (3) _transportation problem31-10-2020.pdf
Lecture (3) _transportation problem31-10-2020.pdfLecture (3) _transportation problem31-10-2020.pdf
Lecture (3) _transportation problem31-10-2020.pdfamrhebafamily
 
Row Pattern Matching 12c MATCH_RECOGNIZE OOW14
Row Pattern Matching 12c MATCH_RECOGNIZE OOW14Row Pattern Matching 12c MATCH_RECOGNIZE OOW14
Row Pattern Matching 12c MATCH_RECOGNIZE OOW14stewashton
 
BEEE-UNIT 1.pptx
BEEE-UNIT 1.pptxBEEE-UNIT 1.pptx
BEEE-UNIT 1.pptxGigi203211
 
Top schools in ghaziabad
Top schools in ghaziabadTop schools in ghaziabad
Top schools in ghaziabadEdhole.com
 

Ähnlich wie North west corner method (16)

Transporataion method north waste corner
Transporataion method north waste cornerTransporataion method north waste corner
Transporataion method north waste corner
 
Vogel's Approximation Method
Vogel's Approximation MethodVogel's Approximation Method
Vogel's Approximation Method
 
O.R UNIT 3.pdf
O.R UNIT 3.pdfO.R UNIT 3.pdf
O.R UNIT 3.pdf
 
Lecture 7 transportation problem finding initial basic feasible solution
Lecture 7 transportation problem finding initial basic feasible solutionLecture 7 transportation problem finding initial basic feasible solution
Lecture 7 transportation problem finding initial basic feasible solution
 
VOGEL'S APPROXIMATION METHOD
VOGEL'S APPROXIMATION METHODVOGEL'S APPROXIMATION METHOD
VOGEL'S APPROXIMATION METHOD
 
north west corner and matrix minima
north west corner and matrix minimanorth west corner and matrix minima
north west corner and matrix minima
 
Eco
EcoEco
Eco
 
Karnaugh map
Karnaugh mapKarnaugh map
Karnaugh map
 
Lec 25 26_27
Lec 25 26_27Lec 25 26_27
Lec 25 26_27
 
Assignment method
Assignment methodAssignment method
Assignment method
 
Classbfs121001503719748
Classbfs121001503719748Classbfs121001503719748
Classbfs121001503719748
 
Lecture (3) _transportation problem31-10-2020.pdf
Lecture (3) _transportation problem31-10-2020.pdfLecture (3) _transportation problem31-10-2020.pdf
Lecture (3) _transportation problem31-10-2020.pdf
 
Row Pattern Matching 12c MATCH_RECOGNIZE OOW14
Row Pattern Matching 12c MATCH_RECOGNIZE OOW14Row Pattern Matching 12c MATCH_RECOGNIZE OOW14
Row Pattern Matching 12c MATCH_RECOGNIZE OOW14
 
BEEE-UNIT 1.pptx
BEEE-UNIT 1.pptxBEEE-UNIT 1.pptx
BEEE-UNIT 1.pptx
 
Top schools in ghaziabad
Top schools in ghaziabadTop schools in ghaziabad
Top schools in ghaziabad
 
Assignment problem
Assignment problemAssignment problem
Assignment problem
 

Kürzlich hochgeladen

1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdfAldoGarca30
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxSCMS School of Architecture
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...drmkjayanthikannan
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Call Girls Mumbai
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"mphochane1998
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Servicemeghakumariji156
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesRAJNEESHKUMAR341697
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxchumtiyababu
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdfKamal Acharya
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network DevicesChandrakantDivate1
 
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEGEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEselvakumar948
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdfKamal Acharya
 

Kürzlich hochgeladen (20)

1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planes
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptx
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEGEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 

North west corner method

  • 1. A Presentation on North-West Corner Method Prepared by Akash S Jadhav (Assistant Professor, SRES Sanjivani College of Engineering, Kopargaon) and Umesh T kulkarni (Assistant Professor, SRES Sanjivani College of Engineering, Kopargaon) 1
  • 2. North-West (N-W) Corner Method • N-W corner method is one of the technique used to solve transportation models. • In N-W corner method, we have to give the allocation to N-W corner cell of the matrix (Transportation Model). 2
  • 3. N-W Corner Method  Let us solve a Transportation Model by this method.  Let us consider the following Transportation Model. I II III IV Supply↓ A 1 3 5 6 90 B 11 1 3 8 70 C 10 16 12 10 40 Demand → 50 50 25 75 Store → Factory ↓ 3
  • 4. Step I  In order to proceed further The ∑ demand Should be equal to ∑ Supply. ∑Demand = ∑ Supply 50+50+25+75 = 90+70+40 200 = 200 …………………..(satisfies) I II III IV Supply ↓ A 1 3 5 6 90 B 11 1 3 8 70 C 10 16 12 10 40 Demand → 50 50 25 75 200 200 Store → Factory ↓ 4
  • 5. Step II • Select the N-W corner cell of the matrix(marked in yellow color). 1 3 5 6 90 11 1 3 8 70 10 16 12 10 40 50 50 25 75 N E S W 5
  • 6. Step II • Give the allocation sign to this N-W Corner cell as shown. 1 3 5 6 90 11 1 3 8 70 10 16 12 10 40 50 50 25 75 N E S W Demand → Supply↓ 6
  • 7. Step II • For this selected cell, the corresponding demand and supply values are 50 & 90 respectively. • Select the least value among the above two values i.e 50. • Allocate this 50 value to the N-W corner cell. 1 3 5 6 90 11 1 3 8 70 10 16 12 10 40 50 50 25 75 Demand → Supply↓ 50 7
  • 8. Step II • Subtract the allocated value (50) from corresponding demand and supply values. • Now the new corresponding demand & supply values are 0 & 40 as shown below. 1 3 5 6 90 11 1 3 8 70 10 16 12 10 40 50 50 25 75 Demand → Supply↓ 50 (50-50) 0 8 (90-50) 40
  • 9. Step II • As the demand value of first column is brought to zero, delete/scratch that column (First column). After deleting the column, the new matrix will be of 3 factories & 3 Stores. 1 3 5 6 90 11 1 3 8 70 10 16 12 10 40 50 50 25 75 Demand → Supply↓ 50 (90-50) 40 9 (50-50) 0
  • 10. Step II • The new matrix is as below. • Now select the N-W corner cell from this new matrix (marked in yellow color). • Select the least value from the corresponding demand & supply value of this N-W corner cell viz 40. (among 50 & 40). • Allocate this least value (40) into the allocation sign as shown and subtract it from both ends (i.e. from corresponding demand & Supply values). • As the supply value for the first row is brought to zero, delete/scratch that row. • The new matrix will be having 2 factories & 3 stores. 3 5 6 40 1 3 8 70 16 12 10 40 50 25 75Demand → Supply↓ 40 0 10 10
  • 11. Step II • The new matrix is as below. • Now select the N-W corner cell from this new matrix (marked in yellow color). • Select the least value from the corresponding demand & supply value of this N-W corner cell viz 10. (among 10 & 70). • Allocate this least value (10) into the allocation sign as shown and subtract it from both ends (i.e. from corresponding demand & Supply values). • As the demand value for the first column is brought to zero, delete/scratch that column. • The new matrix will be having 2 factories & 2 stores. 1 3 8 70 16 12 10 40 10 25 75 Demand → Supply↓ 10 0 60 11
  • 12. Step II • The new matrix is as below. • Now select the N-W corner cell from this new matrix (marked in yellow color). • Select the least value from the corresponding demand & supply value of this N-W corner cell viz 25. (among 25& 60). • Allocate this least value (25) into the allocation sign as shown and subtract it from both ends (i.e. from corresponding demand & Supply values). • As the demand value for the first column is brought to zero, delete/scratch that column. • The new matrix will be having 2 factories & 1 store. 3 8 60 12 10 40 25 75 Demand → Supply↓ 25 0 35 12
  • 13. Step II • The new matrix is as below. • Now select the N-W corner cell from this new matrix (marked in yellow color). • Select the least value from the corresponding demand & supply value of this N-W corner cell viz 35. (among 75 & 35). • Allocate this least value (35) into the allocation sign as shown and subtract it from both ends (i.e. from corresponding demand & Supply values). • As the demand value for the first row is brought to zero, delete/scratch that row. • The new matrix will be having 1 factory & 1 store. i.e. only one value. 8 35 10 40 75Demand → Supply↓ 35 40 0 13
  • 14. Step II • The new matrix is as below. The matrix is having only one cell value. • Now select this only remaining cell (marked in yellow color). • Select the least value from the corresponding demand & supply value of this N-W corner cell viz 40. (among 40 & 40). Both supply and demand values are same. • Allocate this least value (40) into the allocation sign as shown and subtract it from both ends (i.e. from corresponding demand & Supply values). • Hence the demand value as well as the supply value for this only remaining cell is brought to zero. This verifies that our calculations were right. At the end no demand and supply value should remain. 10 40 40Demand → Supply↓ 40 0 0 14
  • 15. Step III • The solution matrix is as follows • Finally to find the transportation cost, do the summation of product of allocation value and corresponding transportation cost • Hence we have, Transportation cost = 1 x 50 + 3 X 40 + 1 X 10 + 3 X 25 + 8 X 35 + 10 X 40 = 935 units 1 3 5 6 11 1 3 8 10 16 12 10 50 40 10 25 35 40 Corresponding Transportation cost Allocation Value 15