SlideShare ist ein Scribd-Unternehmen logo
1 von 53
Unit Commitment
Daniel Kirschen
© 2011 Daniel Kirschen and the University of Washington
1
Economic Dispatch: Problem Definition
• Given load
• Given set of units on-line
• How much should each unit generate to meet this
load at minimum cost?
© 2011 Daniel Kirschen and the University of Washington 2
A B C
L
Typical summer and winter loads
© 2011 Daniel Kirschen and the University of Washington 3
Unit Commitment
• Given load profile
(e.g. values of the load for each hour of a day)
• Given set of units available
• When should each unit be started, stopped and
how much should it generate to meet the load at
minimum cost?
© 2011 Daniel Kirschen and the University of Washington 4
G G G
Load Profile
? ? ?
A Simple Example
• Unit 1:
• PMin = 250 MW, PMax = 600 MW
• C1 = 510.0 + 7.9 P1 + 0.00172 P1
2 $/h
• Unit 2:
• PMin = 200 MW, PMax = 400 MW
• C2 = 310.0 + 7.85 P2 + 0.00194 P2
2 $/h
• Unit 3:
• PMin = 150 MW, PMax = 500 MW
• C3 = 78.0 + 9.56 P3 + 0.00694 P3
2 $/h
• What combination of units 1, 2 and 3 will produce 550 MW at
minimum cost?
• How much should each unit in that combination generate?
© 2011 Daniel Kirschen and the University of Washington 5
Cost of the various combinations
© 2011 Daniel Kirschen and the University of Washington 6
Observations on the example:
• Far too few units committed:
Can’t meet the demand
• Not enough units committed:
Some units operate above optimum
• Too many units committed:
Some units below optimum
• Far too many units committed:
Minimum generation exceeds demand
• No-load cost affects choice of optimal
combination
© 2011 Daniel Kirschen and the University of Washington 7
A more ambitious example
• Optimal generation schedule for
a load profile
• Decompose the profile into a
set of period
• Assume load is constant over
each period
• For each time period, which
units should be committed to
generate at minimum cost
during that period?
© 2011 Daniel Kirschen and the University of Washington 8
Load
Time
1260 18 24
500
1000
Optimal combination for each hour
© 2011 Daniel Kirschen and the University of Washington 9
Matching the combinations to the load
© 2011 Daniel Kirschen and the University of Washington 10
Load
Time
1260 18 24
Unit 1
Unit 2
Unit 3
Issues
• Must consider constraints
– Unit constraints
– System constraints
• Some constraints create a link between periods
• Start-up costs
– Cost incurred when we start a generating unit
– Different units have different start-up costs
• Curse of dimensionality
© 2011 Daniel Kirschen and the University of Washington 11
Unit Constraints
• Constraints that affect each unit individually:
–Maximum generating capacity
–Minimum stable generation
–Minimum “up time”
–Minimum “down time”
–Ramp rate
© 2011 Daniel Kirschen and the University of Washington 12
Notations
© 2011 Daniel Kirschen and the University of Washington 13
u(i,t): Status of unit i at period t
x(i,t): Power produced by unit i during period t
Unit i is on during period tu(i,t) =1:
Unit i is off during period tu(i,t) = 0 :
Minimum up- and down-time
• Minimum up time
– Once a unit is running it may not be shut down
immediately:
• Minimum down time
– Once a unit is shut down, it may not be started
immediately
© 2011 Daniel Kirschen and the University of Washington 14
If u(i,t) =1 and ti
up
< ti
up,min
then u(i,t +1) =1
If u(i,t) = 0 and ti
down
< ti
down,min
then u(i,t +1) = 0
Ramp rates
• Maximum ramp rates
– To avoid damaging the turbine, the electrical output of a unit
cannot change by more than a certain amount over a period of
time:
© 2011 Daniel Kirschen and the University of Washington 15
x i,t +1( )- x i,t( )£ DPi
up,max
x(i,t)- x(i,t +1) £ DPi
down,max
Maximum ramp up rate constraint:
Maximum ramp down rate constraint:
System Constraints
• Constraints that affect more than one unit
– Load/generation balance
– Reserve generation capacity
– Emission constraints
– Network constraints
© 2011 Daniel Kirschen and the University of Washington 16
Load/Generation Balance Constraint
© 2011 Daniel Kirschen and the University of Washington 17
u(i,t)x(i,t)
i=1
N
å = L(t)
N : Set of available units
Reserve Capacity Constraint
• Unanticipated loss of a generating unit or an interconnection
causes unacceptable frequency drop if not corrected rapidly
• Need to increase production from other units to keep frequency
drop within acceptable limits
• Rapid increase in production only possible if committed units are
not all operating at their maximum capacity
© 2011 Daniel Kirschen and the University of Washington 18
u(i,t)
i=1
N
å Pi
max
³ L(t)+ R(t)
R(t): Reserve requirement at time t
How much reserve?
• Protect the system against “credible outages”
• Deterministic criteria:
– Capacity of largest unit or interconnection
– Percentage of peak load
• Probabilistic criteria:
– Takes into account the number and size of the
committed units as well as their outage rate
© 2011 Daniel Kirschen and the University of Washington 19
Types of Reserve
• Spinning reserve
– Primary
• Quick response for a short time
– Secondary
• Slower response for a longer time
• Tertiary reserve
– Replace primary and secondary reserve to protect
against another outage
– Provided by units that can start quickly (e.g. open cycle
gas turbines)
– Also called scheduled or off-line reserve
© 2011 Daniel Kirschen and the University of Washington 20
Types of Reserve
• Positive reserve
– Increase output when generation < load
• Negative reserve
– Decrease output when generation > load
• Other sources of reserve:
– Pumped hydro plants
– Demand reduction (e.g. voluntary load shedding)
• Reserve must be spread around the network
– Must be able to deploy reserve even if the network is
congested
© 2011 Daniel Kirschen and the University of Washington 21
Cost of Reserve
• Reserve has a cost even when it is not called
• More units scheduled than required
– Units not operated at their maximum efficiency
– Extra start up costs
• Must build units capable of rapid response
• Cost of reserve proportionally larger in small
systems
• Important driver for the creation of interconnections
between systems
© 2011 Daniel Kirschen and the University of Washington 22
Environmental constraints
• Scheduling of generating units may be affected by
environmental constraints
• Constraints on pollutants such SO2, NOx
– Various forms:
• Limit on each plant at each hour
• Limit on plant over a year
• Limit on a group of plants over a year
• Constraints on hydro generation
– Protection of wildlife
– Navigation, recreation
© 2011 Daniel Kirschen and the University of Washington 23
Network Constraints
• Transmission network may have an effect on the
commitment of units
– Some units must run to provide voltage support
– The output of some units may be limited because their
output would exceed the transmission capacity of the
network
© 2011 Daniel Kirschen and the University of Washington 24
Cheap generators
May be “constrained off”
More expensive generator
May be “constrained on”
A B
Start-up Costs
• Thermal units must be “warmed up” before they
can be brought on-line
• Warming up a unit costs money
• Start-up cost depends on time unit has been off
© 2011 Daniel Kirschen and the University of Washington 25
SCi (ti
OFF
) = ai + bi (1 - e
-
ti
OFF
t i
)
ti
OFF
αi
αi + βi
Start-up Costs
• Need to “balance” start-up costs and running costs
• Example:
– Diesel generator: low start-up cost, high running cost
– Coal plant: high start-up cost, low running cost
• Issues:
– How long should a unit run to “recover” its start-up cost?
– Start-up one more large unit or a diesel generator to cover
the peak?
– Shutdown one more unit at night or run several units part-
loaded?
© 2011 Daniel Kirschen and the University of Washington 26
Summary
• Some constraints link periods together
• Minimizing the total cost (start-up + running) must
be done over the whole period of study
• Generation scheduling or unit commitment is a
more general problem than economic dispatch
• Economic dispatch is a sub-problem of generation
scheduling
© 2011 Daniel Kirschen and the University of Washington 27
Flexible Plants
• Power output can be adjusted (within limits)
• Examples:
– Coal-fired
– Oil-fired
– Open cycle gas turbines
– Combined cycle gas turbines
– Hydro plants with storage
• Status and power output can be optimized
© 2011 Daniel Kirschen and the University of Washington 28
Thermal units
Inflexible Plants
• Power output cannot be adjusted for technical or
commercial reasons
• Examples:
– Nuclear
– Run-of-the-river hydro
– Renewables (wind, solar,…)
– Combined heat and power (CHP, cogeneration)
• Output treated as given when optimizing
© 2011 Daniel Kirschen and the University of Washington 29
Solving the Unit Commitment Problem
• Decision variables:
– Status of each unit at each period:
– Output of each unit at each period:
• Combination of integer and continuous variables
© 2011 Daniel Kirschen and the University of Washington 30
u(i,t) Î 0,1{ }   " i,t
x(i,t) Î 0, Pi
min
;Pi
max
éë ùû{ }  " i,t
Optimization with integer variables
• Continuous variables
– Can follow the gradients or use LP
– Any value within the feasible set is OK
• Discrete variables
– There is no gradient
– Can only take a finite number of values
– Problem is not convex
– Must try combinations of discrete values
© 2011 Daniel Kirschen and the University of Washington 31
How many combinations are there?
© 2011 Daniel Kirschen and the University of Washington 32
• Examples
– 3 units: 8 possible states
– N units: 2N possible states
111
110
101
100
011
010
001
000
How many solutions are there anyway?
© 2011 Daniel Kirschen and the University of Washington 33
1 2 3 4 5 6T=
• Optimization over a time
horizon divided into
intervals
• A solution is a path linking
one combination at each
interval
• How many such paths are
there?
How many solutions are there anyway?
© 2011 Daniel Kirschen and the University of Washington 34
1 2 3 4 5 6T=
Optimization over a time
horizon divided into intervals
A solution is a path linking
one combination at each
interval
How many such path are
there?
Answer: 2N
( ) 2N
( )… 2N
( ) = 2N
( )T
The Curse of Dimensionality
• Example: 5 units, 24 hours
• Processing 109 combinations/second, this would
take 1.9 1019 years to solve
• There are 100’s of units in large power systems...
• Many of these combinations do not satisfy the
constraints
© 2011 Daniel Kirschen and the University of Washington 35
2N
( )
T
= 25
( )
24
= 6.21035
combinations
How do you Beat the Curse?
Brute force approach won’t work!
• Need to be smart
• Try only a small subset of all combinations
• Can’t guarantee optimality of the solution
• Try to get as close as possible within a reasonable
amount of time
© 2011 Daniel Kirschen and the University of Washington 36
Main Solution Techniques
• Characteristics of a good technique
– Solution close to the optimum
– Reasonable computing time
– Ability to model constraints
• Priority list / heuristic approach
• Dynamic programming
• Lagrangian relaxation
• Mixed Integer Programming
© 2011 Daniel Kirschen and the University of Washington 37
State of the art
A Simple Unit Commitment Example
© 2011 Daniel Kirschen and the University of Washington
38
Unit Data
© 2011 Daniel Kirschen and the University of Washington 39
Unit
Pmin
(MW)
Pmax
(MW)
Min
up
(h)
Min
down
(h)
No-load
cost
($)
Marginal
cost
($/MWh)
Start-up
cost
($)
Initial
status
A 150 250 3 3 0 10 1,000 ON
B 50 100 2 1 0 12 600 OFF
C 10 50 1 1 0 20 100 OFF
Demand Data
© 2011 Daniel Kirschen and the University of Washington 40
Hourly Demand
0
50
100
150
200
250
300
350
1 2 3
Hours
Load
Reserve requirements are not considered
Feasible Unit Combinations (states)
© 2011 Daniel Kirschen and the University of Washington 41
Combinations
Pmin Pmax
A B C
1 1 1 210 400
1 1 0 200 350
1 0 1 160 300
1 0 0 150 250
0 1 1 60 150
0 1 0 50 100
0 0 1 10 50
0 0 0 0 0
1 2 3
150 300 200
Transitions between feasible combinations
© 2011 Daniel Kirschen and the University of Washington 42
A B C
1 1 1
1 1 0
1 0 1
1 0 0
0 1 1
1 2 3
Initial State
Infeasible transitions: Minimum down time of unit A
© 2011 Daniel Kirschen and the University of Washington 43
A B C
1 1 1
1 1 0
1 0 1
1 0 0
0 1 1
1 2 3
Initial State
TD TU
A 3 3
B 1 2
C 1 1
Infeasible transitions: Minimum up time of unit B
© 2011 Daniel Kirschen and the University of Washington 44
A B C
1 1 1
1 1 0
1 0 1
1 0 0
0 1 1
1 2 3
Initial State
TD TU
A 3 3
B 1 2
C 1 1
Feasible transitions
© 2011 Daniel Kirschen and the University of Washington 45
A B C
1 1 1
1 1 0
1 0 1
1 0 0
0 1 1
1 2 3
Initial State
Operating costs
© 2011 Daniel Kirschen and the University of Washington 46
1 1 1
1 1 0
1 0 1
1 0 0 1
4
3
2
5
6
7
Economic dispatch
© 2011 Daniel Kirschen and the University of Washington 47
State Load PA PB PC Cost
1 150 150 0 0 1500
2 300 250 0 50 3500
3 300 250 50 0 3100
4 300 240 50 10 3200
5 200 200 0 0 2000
6 200 190 0 10 2100
7 200 150 50 0 2100
Unit Pmin Pmax No-load cost Marginal cost
A 150 250 0 10
B 50 100 0 12
C 10 50 0 20
Operating costs
© 2011 Daniel Kirschen and the University of Washington 48
1 1 1
1 1 0
1 0 1
1 0 0 1
4
3
2
5
6
7
$1500
$3500
$3100
$3200
$2000
$2100
$2100
Start-up costs
© 2011 Daniel Kirschen and the University of Washington 49
1 1 1
1 1 0
1 0 1
1 0 0 1
4
3
2
5
6
7
$1500
$3500
$3100
$3200
$2000
$2100
$2100
Unit Start-up cost
A 1000
B 600
C 100
$0
$0
$0
$0
$0
$600
$100
$600
$700
Accumulated costs
© 2011 Daniel Kirschen and the University of Washington 50
1 1 1
1 1 0
1 0 1
1 0 0 1
4
3
2
5
6
7
$1500
$3500
$3100
$3200
$2000
$2100
$2100
$1500
$5100
$5200
$5400
$7300
$7200
$7100
$0
$0
$0
$0
$0
$600
$100
$600
$700
Total costs
© 2011 Daniel Kirschen and the University of Washington 51
1 1 1
1 1 0
1 0 1
1 0 0 1
4
3
2
5
6
7
$7300
$7200
$7100
Lowest total cost
Optimal solution
© 2011 Daniel Kirschen and the University of Washington 52
1 1 1
1 1 0
1 0 1
1 0 0 1
2
5
$7100
Notes
• This example is intended to illustrate the principles of
unit commitment
• Some constraints have been ignored and others
artificially tightened to simplify the problem and make
it solvable by hand
• Therefore it does not illustrate the true complexity of
the problem
• The solution method used in this example is based on
dynamic programming. This technique is no longer
used in industry because it only works for small
systems (< 20 units)
© 2011 Daniel Kirschen and the University of Washington 53

Weitere ähnliche Inhalte

Was ist angesagt?

Was ist angesagt? (20)

EE6603 - Power System Operation & Control
EE6603 - Power System Operation & ControlEE6603 - Power System Operation & Control
EE6603 - Power System Operation & Control
 
Hydrothermal scheduling
Hydrothermal schedulingHydrothermal scheduling
Hydrothermal scheduling
 
Introduction to power system analysis
Introduction to power system analysisIntroduction to power system analysis
Introduction to power system analysis
 
Small signal stability analysis
Small signal stability analysisSmall signal stability analysis
Small signal stability analysis
 
Two area system
Two area systemTwo area system
Two area system
 
Generation of High D.C. Voltage (HVDC generation)
Generation of High D.C. Voltage (HVDC generation)Generation of High D.C. Voltage (HVDC generation)
Generation of High D.C. Voltage (HVDC generation)
 
Economic load dispatch(with and without losses)
Economic load dispatch(with and without losses)Economic load dispatch(with and without losses)
Economic load dispatch(with and without losses)
 
Load Frequency Control of two area Power system
Load Frequency Control  of two area Power systemLoad Frequency Control  of two area Power system
Load Frequency Control of two area Power system
 
Multi terminal dc systems (mtdc)
Multi terminal dc systems (mtdc)Multi terminal dc systems (mtdc)
Multi terminal dc systems (mtdc)
 
Input output , heat rate characteristics and Incremental cost
Input output , heat rate characteristics and Incremental costInput output , heat rate characteristics and Incremental cost
Input output , heat rate characteristics and Incremental cost
 
Economic load dispatch
Economic load dispatchEconomic load dispatch
Economic load dispatch
 
Lecture 10
Lecture 10Lecture 10
Lecture 10
 
Power system planing and operation (pce5312) chapter five
Power system planing and operation (pce5312) chapter fivePower system planing and operation (pce5312) chapter five
Power system planing and operation (pce5312) chapter five
 
Power system protection topic 1
Power system protection topic 1Power system protection topic 1
Power system protection topic 1
 
Symmetrical Fault Analysis
Symmetrical Fault AnalysisSymmetrical Fault Analysis
Symmetrical Fault Analysis
 
power flow and optimal power flow
power flow and optimal power flowpower flow and optimal power flow
power flow and optimal power flow
 
Thyristor switched capacitor
Thyristor switched capacitorThyristor switched capacitor
Thyristor switched capacitor
 
Power Factor
Power FactorPower Factor
Power Factor
 
VSC based HVDC system
VSC based HVDC systemVSC based HVDC system
VSC based HVDC system
 
Microgrid
MicrogridMicrogrid
Microgrid
 

Andere mochten auch

Measurement of high_voltage_and_high_currentunit_iv_full_version
Measurement of high_voltage_and_high_currentunit_iv_full_versionMeasurement of high_voltage_and_high_currentunit_iv_full_version
Measurement of high_voltage_and_high_currentunit_iv_full_version
Aman Ansari
 
Design, planning and layout of high voltage lab
Design, planning and layout of high voltage labDesign, planning and layout of high voltage lab
Design, planning and layout of high voltage lab
Nidhi Maru
 
Installing, Programming & Commissioning of Power System Protection Relays and...
Installing, Programming & Commissioning of Power System Protection Relays and...Installing, Programming & Commissioning of Power System Protection Relays and...
Installing, Programming & Commissioning of Power System Protection Relays and...
Living Online
 
Project on economic load dispatch
Project on economic load dispatchProject on economic load dispatch
Project on economic load dispatch
ayantudu
 
EE2353 / High Voltage Engineering - Testing of Cables
EE2353 / High Voltage Engineering - Testing of CablesEE2353 / High Voltage Engineering - Testing of Cables
EE2353 / High Voltage Engineering - Testing of Cables
Rajesh Ramesh
 
POWER DISTRIBUTION 2.docx
POWER DISTRIBUTION 2.docxPOWER DISTRIBUTION 2.docx
POWER DISTRIBUTION 2.docx
Jeffrey Dorsey
 
POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION
moiz89
 
Load forecasting
Load forecastingLoad forecasting
Load forecasting
sushrut p
 

Andere mochten auch (15)

HIGH VOLTAGE ENGINEERING
HIGH VOLTAGE ENGINEERINGHIGH VOLTAGE ENGINEERING
HIGH VOLTAGE ENGINEERING
 
Measurement of high_voltage_and_high_currentunit_iv_full_version
Measurement of high_voltage_and_high_currentunit_iv_full_versionMeasurement of high_voltage_and_high_currentunit_iv_full_version
Measurement of high_voltage_and_high_currentunit_iv_full_version
 
Design, planning and layout of high voltage lab
Design, planning and layout of high voltage labDesign, planning and layout of high voltage lab
Design, planning and layout of high voltage lab
 
Unit Commitment
Unit CommitmentUnit Commitment
Unit Commitment
 
High voltage engineering
High voltage engineeringHigh voltage engineering
High voltage engineering
 
Installing, Programming & Commissioning of Power System Protection Relays and...
Installing, Programming & Commissioning of Power System Protection Relays and...Installing, Programming & Commissioning of Power System Protection Relays and...
Installing, Programming & Commissioning of Power System Protection Relays and...
 
Project on economic load dispatch
Project on economic load dispatchProject on economic load dispatch
Project on economic load dispatch
 
Summer Internship Report -By Rahul Mehra
Summer Internship Report -By Rahul MehraSummer Internship Report -By Rahul Mehra
Summer Internship Report -By Rahul Mehra
 
EE2353 / High Voltage Engineering - Testing of Cables
EE2353 / High Voltage Engineering - Testing of CablesEE2353 / High Voltage Engineering - Testing of Cables
EE2353 / High Voltage Engineering - Testing of Cables
 
SWITCH GEAR & PROTECTIVE DEVICE (EEN-437)
SWITCH GEAR & PROTECTIVE DEVICE (EEN-437)SWITCH GEAR & PROTECTIVE DEVICE (EEN-437)
SWITCH GEAR & PROTECTIVE DEVICE (EEN-437)
 
Load Forecasting Techniques.pdf
Load Forecasting Techniques.pdfLoad Forecasting Techniques.pdf
Load Forecasting Techniques.pdf
 
POWER DISTRIBUTION 2.docx
POWER DISTRIBUTION 2.docxPOWER DISTRIBUTION 2.docx
POWER DISTRIBUTION 2.docx
 
Measurement & Instrumentation (BE)
Measurement & Instrumentation (BE)Measurement & Instrumentation (BE)
Measurement & Instrumentation (BE)
 
POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION
 
Load forecasting
Load forecastingLoad forecasting
Load forecasting
 

Ähnlich wie Unit commitment in power system

Wind and Solar Power - Renewable Energy Technologies
Wind and Solar Power - Renewable Energy TechnologiesWind and Solar Power - Renewable Energy Technologies
Wind and Solar Power - Renewable Energy Technologies
Living Online
 

Ähnlich wie Unit commitment in power system (20)

[2020.2] PSOC - Unit_Commitment.pptx
[2020.2] PSOC - Unit_Commitment.pptx[2020.2] PSOC - Unit_Commitment.pptx
[2020.2] PSOC - Unit_Commitment.pptx
 
Power station
Power stationPower station
Power station
 
Economics of Power Generation
Economics of Power GenerationEconomics of Power Generation
Economics of Power Generation
 
Economic load dispatch
Economic load dispatch Economic load dispatch
Economic load dispatch
 
Bunaken Island | Nov-15 | Renewable Energy in Small Island Grids
Bunaken Island | Nov-15 | Renewable Energy in Small Island GridsBunaken Island | Nov-15 | Renewable Energy in Small Island Grids
Bunaken Island | Nov-15 | Renewable Energy in Small Island Grids
 
Shreelakshmi(power).pptx
Shreelakshmi(power).pptxShreelakshmi(power).pptx
Shreelakshmi(power).pptx
 
Electrical Plan Electrical System Electrical Design
Electrical Plan Electrical System Electrical Design Electrical Plan Electrical System Electrical Design
Electrical Plan Electrical System Electrical Design
 
Copy of PSOC-unit1.pdf
Copy of PSOC-unit1.pdfCopy of PSOC-unit1.pdf
Copy of PSOC-unit1.pdf
 
Module1-Power-System-operation and-control
Module1-Power-System-operation and-controlModule1-Power-System-operation and-control
Module1-Power-System-operation and-control
 
Lecture 8 load duration curves
Lecture 8 load duration curvesLecture 8 load duration curves
Lecture 8 load duration curves
 
Lecture 7 load duration curves
Lecture 7 load duration curvesLecture 7 load duration curves
Lecture 7 load duration curves
 
Design and construction of wind turbine towers for maximum power generation
Design and construction of wind turbine towers for maximum power generationDesign and construction of wind turbine towers for maximum power generation
Design and construction of wind turbine towers for maximum power generation
 
Securing Australia's Energy Future: The Challenge - Simon Gamble, Hydro Tasmania
Securing Australia's Energy Future: The Challenge - Simon Gamble, Hydro TasmaniaSecuring Australia's Energy Future: The Challenge - Simon Gamble, Hydro Tasmania
Securing Australia's Energy Future: The Challenge - Simon Gamble, Hydro Tasmania
 
Power_plant_ecomices.pptx
Power_plant_ecomices.pptxPower_plant_ecomices.pptx
Power_plant_ecomices.pptx
 
CH-2_PPEE.ppt
CH-2_PPEE.pptCH-2_PPEE.ppt
CH-2_PPEE.ppt
 
Wind and Solar Power - Renewable Energy Technologies
Wind and Solar Power - Renewable Energy TechnologiesWind and Solar Power - Renewable Energy Technologies
Wind and Solar Power - Renewable Energy Technologies
 
Ctws ocean energy lovely
Ctws ocean energy lovelyCtws ocean energy lovely
Ctws ocean energy lovely
 
Energy Storage: New Capabilities for the Electric Grid – The Tehachapi Energy...
Energy Storage: New Capabilities for the Electric Grid – The Tehachapi Energy...Energy Storage: New Capabilities for the Electric Grid – The Tehachapi Energy...
Energy Storage: New Capabilities for the Electric Grid – The Tehachapi Energy...
 
Baby Smart Grid 11/09
Baby Smart Grid 11/09Baby Smart Grid 11/09
Baby Smart Grid 11/09
 
Ch#1_Power Generation, Transmission and Distribution System_MS.Rashid.pptx
Ch#1_Power Generation, Transmission and Distribution System_MS.Rashid.pptxCh#1_Power Generation, Transmission and Distribution System_MS.Rashid.pptx
Ch#1_Power Generation, Transmission and Distribution System_MS.Rashid.pptx
 

Kürzlich hochgeladen

Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Christo Ananth
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Christo Ananth
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
amitlee9823
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 

Kürzlich hochgeladen (20)

Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 

Unit commitment in power system

  • 1. Unit Commitment Daniel Kirschen © 2011 Daniel Kirschen and the University of Washington 1
  • 2. Economic Dispatch: Problem Definition • Given load • Given set of units on-line • How much should each unit generate to meet this load at minimum cost? © 2011 Daniel Kirschen and the University of Washington 2 A B C L
  • 3. Typical summer and winter loads © 2011 Daniel Kirschen and the University of Washington 3
  • 4. Unit Commitment • Given load profile (e.g. values of the load for each hour of a day) • Given set of units available • When should each unit be started, stopped and how much should it generate to meet the load at minimum cost? © 2011 Daniel Kirschen and the University of Washington 4 G G G Load Profile ? ? ?
  • 5. A Simple Example • Unit 1: • PMin = 250 MW, PMax = 600 MW • C1 = 510.0 + 7.9 P1 + 0.00172 P1 2 $/h • Unit 2: • PMin = 200 MW, PMax = 400 MW • C2 = 310.0 + 7.85 P2 + 0.00194 P2 2 $/h • Unit 3: • PMin = 150 MW, PMax = 500 MW • C3 = 78.0 + 9.56 P3 + 0.00694 P3 2 $/h • What combination of units 1, 2 and 3 will produce 550 MW at minimum cost? • How much should each unit in that combination generate? © 2011 Daniel Kirschen and the University of Washington 5
  • 6. Cost of the various combinations © 2011 Daniel Kirschen and the University of Washington 6
  • 7. Observations on the example: • Far too few units committed: Can’t meet the demand • Not enough units committed: Some units operate above optimum • Too many units committed: Some units below optimum • Far too many units committed: Minimum generation exceeds demand • No-load cost affects choice of optimal combination © 2011 Daniel Kirschen and the University of Washington 7
  • 8. A more ambitious example • Optimal generation schedule for a load profile • Decompose the profile into a set of period • Assume load is constant over each period • For each time period, which units should be committed to generate at minimum cost during that period? © 2011 Daniel Kirschen and the University of Washington 8 Load Time 1260 18 24 500 1000
  • 9. Optimal combination for each hour © 2011 Daniel Kirschen and the University of Washington 9
  • 10. Matching the combinations to the load © 2011 Daniel Kirschen and the University of Washington 10 Load Time 1260 18 24 Unit 1 Unit 2 Unit 3
  • 11. Issues • Must consider constraints – Unit constraints – System constraints • Some constraints create a link between periods • Start-up costs – Cost incurred when we start a generating unit – Different units have different start-up costs • Curse of dimensionality © 2011 Daniel Kirschen and the University of Washington 11
  • 12. Unit Constraints • Constraints that affect each unit individually: –Maximum generating capacity –Minimum stable generation –Minimum “up time” –Minimum “down time” –Ramp rate © 2011 Daniel Kirschen and the University of Washington 12
  • 13. Notations © 2011 Daniel Kirschen and the University of Washington 13 u(i,t): Status of unit i at period t x(i,t): Power produced by unit i during period t Unit i is on during period tu(i,t) =1: Unit i is off during period tu(i,t) = 0 :
  • 14. Minimum up- and down-time • Minimum up time – Once a unit is running it may not be shut down immediately: • Minimum down time – Once a unit is shut down, it may not be started immediately © 2011 Daniel Kirschen and the University of Washington 14 If u(i,t) =1 and ti up < ti up,min then u(i,t +1) =1 If u(i,t) = 0 and ti down < ti down,min then u(i,t +1) = 0
  • 15. Ramp rates • Maximum ramp rates – To avoid damaging the turbine, the electrical output of a unit cannot change by more than a certain amount over a period of time: © 2011 Daniel Kirschen and the University of Washington 15 x i,t +1( )- x i,t( )£ DPi up,max x(i,t)- x(i,t +1) £ DPi down,max Maximum ramp up rate constraint: Maximum ramp down rate constraint:
  • 16. System Constraints • Constraints that affect more than one unit – Load/generation balance – Reserve generation capacity – Emission constraints – Network constraints © 2011 Daniel Kirschen and the University of Washington 16
  • 17. Load/Generation Balance Constraint © 2011 Daniel Kirschen and the University of Washington 17 u(i,t)x(i,t) i=1 N å = L(t) N : Set of available units
  • 18. Reserve Capacity Constraint • Unanticipated loss of a generating unit or an interconnection causes unacceptable frequency drop if not corrected rapidly • Need to increase production from other units to keep frequency drop within acceptable limits • Rapid increase in production only possible if committed units are not all operating at their maximum capacity © 2011 Daniel Kirschen and the University of Washington 18 u(i,t) i=1 N å Pi max ³ L(t)+ R(t) R(t): Reserve requirement at time t
  • 19. How much reserve? • Protect the system against “credible outages” • Deterministic criteria: – Capacity of largest unit or interconnection – Percentage of peak load • Probabilistic criteria: – Takes into account the number and size of the committed units as well as their outage rate © 2011 Daniel Kirschen and the University of Washington 19
  • 20. Types of Reserve • Spinning reserve – Primary • Quick response for a short time – Secondary • Slower response for a longer time • Tertiary reserve – Replace primary and secondary reserve to protect against another outage – Provided by units that can start quickly (e.g. open cycle gas turbines) – Also called scheduled or off-line reserve © 2011 Daniel Kirschen and the University of Washington 20
  • 21. Types of Reserve • Positive reserve – Increase output when generation < load • Negative reserve – Decrease output when generation > load • Other sources of reserve: – Pumped hydro plants – Demand reduction (e.g. voluntary load shedding) • Reserve must be spread around the network – Must be able to deploy reserve even if the network is congested © 2011 Daniel Kirschen and the University of Washington 21
  • 22. Cost of Reserve • Reserve has a cost even when it is not called • More units scheduled than required – Units not operated at their maximum efficiency – Extra start up costs • Must build units capable of rapid response • Cost of reserve proportionally larger in small systems • Important driver for the creation of interconnections between systems © 2011 Daniel Kirschen and the University of Washington 22
  • 23. Environmental constraints • Scheduling of generating units may be affected by environmental constraints • Constraints on pollutants such SO2, NOx – Various forms: • Limit on each plant at each hour • Limit on plant over a year • Limit on a group of plants over a year • Constraints on hydro generation – Protection of wildlife – Navigation, recreation © 2011 Daniel Kirschen and the University of Washington 23
  • 24. Network Constraints • Transmission network may have an effect on the commitment of units – Some units must run to provide voltage support – The output of some units may be limited because their output would exceed the transmission capacity of the network © 2011 Daniel Kirschen and the University of Washington 24 Cheap generators May be “constrained off” More expensive generator May be “constrained on” A B
  • 25. Start-up Costs • Thermal units must be “warmed up” before they can be brought on-line • Warming up a unit costs money • Start-up cost depends on time unit has been off © 2011 Daniel Kirschen and the University of Washington 25 SCi (ti OFF ) = ai + bi (1 - e - ti OFF t i ) ti OFF αi αi + βi
  • 26. Start-up Costs • Need to “balance” start-up costs and running costs • Example: – Diesel generator: low start-up cost, high running cost – Coal plant: high start-up cost, low running cost • Issues: – How long should a unit run to “recover” its start-up cost? – Start-up one more large unit or a diesel generator to cover the peak? – Shutdown one more unit at night or run several units part- loaded? © 2011 Daniel Kirschen and the University of Washington 26
  • 27. Summary • Some constraints link periods together • Minimizing the total cost (start-up + running) must be done over the whole period of study • Generation scheduling or unit commitment is a more general problem than economic dispatch • Economic dispatch is a sub-problem of generation scheduling © 2011 Daniel Kirschen and the University of Washington 27
  • 28. Flexible Plants • Power output can be adjusted (within limits) • Examples: – Coal-fired – Oil-fired – Open cycle gas turbines – Combined cycle gas turbines – Hydro plants with storage • Status and power output can be optimized © 2011 Daniel Kirschen and the University of Washington 28 Thermal units
  • 29. Inflexible Plants • Power output cannot be adjusted for technical or commercial reasons • Examples: – Nuclear – Run-of-the-river hydro – Renewables (wind, solar,…) – Combined heat and power (CHP, cogeneration) • Output treated as given when optimizing © 2011 Daniel Kirschen and the University of Washington 29
  • 30. Solving the Unit Commitment Problem • Decision variables: – Status of each unit at each period: – Output of each unit at each period: • Combination of integer and continuous variables © 2011 Daniel Kirschen and the University of Washington 30 u(i,t) Î 0,1{ }   " i,t x(i,t) Î 0, Pi min ;Pi max éë ùû{ }  " i,t
  • 31. Optimization with integer variables • Continuous variables – Can follow the gradients or use LP – Any value within the feasible set is OK • Discrete variables – There is no gradient – Can only take a finite number of values – Problem is not convex – Must try combinations of discrete values © 2011 Daniel Kirschen and the University of Washington 31
  • 32. How many combinations are there? © 2011 Daniel Kirschen and the University of Washington 32 • Examples – 3 units: 8 possible states – N units: 2N possible states 111 110 101 100 011 010 001 000
  • 33. How many solutions are there anyway? © 2011 Daniel Kirschen and the University of Washington 33 1 2 3 4 5 6T= • Optimization over a time horizon divided into intervals • A solution is a path linking one combination at each interval • How many such paths are there?
  • 34. How many solutions are there anyway? © 2011 Daniel Kirschen and the University of Washington 34 1 2 3 4 5 6T= Optimization over a time horizon divided into intervals A solution is a path linking one combination at each interval How many such path are there? Answer: 2N ( ) 2N ( )… 2N ( ) = 2N ( )T
  • 35. The Curse of Dimensionality • Example: 5 units, 24 hours • Processing 109 combinations/second, this would take 1.9 1019 years to solve • There are 100’s of units in large power systems... • Many of these combinations do not satisfy the constraints © 2011 Daniel Kirschen and the University of Washington 35 2N ( ) T = 25 ( ) 24 = 6.21035 combinations
  • 36. How do you Beat the Curse? Brute force approach won’t work! • Need to be smart • Try only a small subset of all combinations • Can’t guarantee optimality of the solution • Try to get as close as possible within a reasonable amount of time © 2011 Daniel Kirschen and the University of Washington 36
  • 37. Main Solution Techniques • Characteristics of a good technique – Solution close to the optimum – Reasonable computing time – Ability to model constraints • Priority list / heuristic approach • Dynamic programming • Lagrangian relaxation • Mixed Integer Programming © 2011 Daniel Kirschen and the University of Washington 37 State of the art
  • 38. A Simple Unit Commitment Example © 2011 Daniel Kirschen and the University of Washington 38
  • 39. Unit Data © 2011 Daniel Kirschen and the University of Washington 39 Unit Pmin (MW) Pmax (MW) Min up (h) Min down (h) No-load cost ($) Marginal cost ($/MWh) Start-up cost ($) Initial status A 150 250 3 3 0 10 1,000 ON B 50 100 2 1 0 12 600 OFF C 10 50 1 1 0 20 100 OFF
  • 40. Demand Data © 2011 Daniel Kirschen and the University of Washington 40 Hourly Demand 0 50 100 150 200 250 300 350 1 2 3 Hours Load Reserve requirements are not considered
  • 41. Feasible Unit Combinations (states) © 2011 Daniel Kirschen and the University of Washington 41 Combinations Pmin Pmax A B C 1 1 1 210 400 1 1 0 200 350 1 0 1 160 300 1 0 0 150 250 0 1 1 60 150 0 1 0 50 100 0 0 1 10 50 0 0 0 0 0 1 2 3 150 300 200
  • 42. Transitions between feasible combinations © 2011 Daniel Kirschen and the University of Washington 42 A B C 1 1 1 1 1 0 1 0 1 1 0 0 0 1 1 1 2 3 Initial State
  • 43. Infeasible transitions: Minimum down time of unit A © 2011 Daniel Kirschen and the University of Washington 43 A B C 1 1 1 1 1 0 1 0 1 1 0 0 0 1 1 1 2 3 Initial State TD TU A 3 3 B 1 2 C 1 1
  • 44. Infeasible transitions: Minimum up time of unit B © 2011 Daniel Kirschen and the University of Washington 44 A B C 1 1 1 1 1 0 1 0 1 1 0 0 0 1 1 1 2 3 Initial State TD TU A 3 3 B 1 2 C 1 1
  • 45. Feasible transitions © 2011 Daniel Kirschen and the University of Washington 45 A B C 1 1 1 1 1 0 1 0 1 1 0 0 0 1 1 1 2 3 Initial State
  • 46. Operating costs © 2011 Daniel Kirschen and the University of Washington 46 1 1 1 1 1 0 1 0 1 1 0 0 1 4 3 2 5 6 7
  • 47. Economic dispatch © 2011 Daniel Kirschen and the University of Washington 47 State Load PA PB PC Cost 1 150 150 0 0 1500 2 300 250 0 50 3500 3 300 250 50 0 3100 4 300 240 50 10 3200 5 200 200 0 0 2000 6 200 190 0 10 2100 7 200 150 50 0 2100 Unit Pmin Pmax No-load cost Marginal cost A 150 250 0 10 B 50 100 0 12 C 10 50 0 20
  • 48. Operating costs © 2011 Daniel Kirschen and the University of Washington 48 1 1 1 1 1 0 1 0 1 1 0 0 1 4 3 2 5 6 7 $1500 $3500 $3100 $3200 $2000 $2100 $2100
  • 49. Start-up costs © 2011 Daniel Kirschen and the University of Washington 49 1 1 1 1 1 0 1 0 1 1 0 0 1 4 3 2 5 6 7 $1500 $3500 $3100 $3200 $2000 $2100 $2100 Unit Start-up cost A 1000 B 600 C 100 $0 $0 $0 $0 $0 $600 $100 $600 $700
  • 50. Accumulated costs © 2011 Daniel Kirschen and the University of Washington 50 1 1 1 1 1 0 1 0 1 1 0 0 1 4 3 2 5 6 7 $1500 $3500 $3100 $3200 $2000 $2100 $2100 $1500 $5100 $5200 $5400 $7300 $7200 $7100 $0 $0 $0 $0 $0 $600 $100 $600 $700
  • 51. Total costs © 2011 Daniel Kirschen and the University of Washington 51 1 1 1 1 1 0 1 0 1 1 0 0 1 4 3 2 5 6 7 $7300 $7200 $7100 Lowest total cost
  • 52. Optimal solution © 2011 Daniel Kirschen and the University of Washington 52 1 1 1 1 1 0 1 0 1 1 0 0 1 2 5 $7100
  • 53. Notes • This example is intended to illustrate the principles of unit commitment • Some constraints have been ignored and others artificially tightened to simplify the problem and make it solvable by hand • Therefore it does not illustrate the true complexity of the problem • The solution method used in this example is based on dynamic programming. This technique is no longer used in industry because it only works for small systems (< 20 units) © 2011 Daniel Kirschen and the University of Washington 53