4.
Problem Statement
Design a power plant who provides 10KW of
output power
Assumptions
Effective Head = 10m
Delivery Pipe Dia = 0.5 m
Gen RPM = 1800
Delivery Pipe Material = Steel
ŋt = ŋgen = ŋrotor – gen = 80 %
Problem and Assumptions
7.
Q = 0.2 m3/s
Av = Q = 0.2 m3/s
D = 13.5 cm = 5.3 in
This is the diameter of the nozzle
Note: Water Velocity will be different in delivery pipe
because it is 0.5 m wide.
Nozzle Diameter Required
12.
Consideration of losses is very important in design
Suitable assumptions should be made to avoid
complexity in design
Hydro power generation doesn’t make any pollution
Serious thoughts and actions can help PAKISTAN in
present load shedding problem
Conclusions