SUMMER INTERNSHIP PROGRAM ELECTRICAL ENGINEERING-2018
SITE Visit Report
2nd
JULY,2018
At
132/33 KV SUB –STATION,TELIARGANJ
ALLAHABAD
SUBMITTED TO- SUBMITTED BY-
MOTILAL NEHRU NATIONAL INSTITUTE ADARSH KUMAR
OF TECHNOLOGY ,ALLAHABAD (Reg. No.-16737209)
RAJKIYA ENGINEERING COLLEGE
AMBEDKARNAGAR-224122
CONTENT
1. Acknowledgement 2
2. Information 3
3. Purpose of Visit 3
4. What we learn? 4
5. Conclusion 7
ACKNOWLEDGEMENT
We are gladly & thankful to Dr. Navneet Kumar Singh sir and Dr. Niraj
Kumar Choudhayr Sir and SIPEE -2018 Team who decided to take visit in
132/33KV Substation, Teliarganj-Allahabad
We are especially thankful to respected assistant engineers of Teliarganj-
Substation who gave the proper guidance to us and gave practical based approach
learning to us.
GENERAL INFORMATION
An electrical substation is a subsidiary station of an electricity generation,
transmission and distribution system where voltage is transformed from high to
low or the reverse using transformers. Electric power may flow through several
substations between generating plant and consumer, and may be changed in
voltage in several steps.
Teliarganj substation that has a step-down transformer decreases the
voltage(133/33KV) while increasing the current for domestic and commercial
distribution.
PURPOSE OF VISIT
Our main purpose for this visit is to be get practical knowledge of electrical power
transmission and distribution
We are Electrical Engineering student so we will get the idea of electrical power
transmission and distribution. we will also get familiar with Transformer
maintenance, circuit breaker, Transformer isolator, bus bar, Protective relays,
Lightening arresters, Load break switches
WHAT WE LEARN?
On 2nd
july. ,2018 (Monday) at 03:00 pm we reached at
Teliarganj- Sub Station
Introduction About Single Line Diagram, Different Protection Equipment,
SCADA system
At the beginning, one of the assistant engineer explained all the essential
component of the 133KV substation and explained one line diagram of Teliarganj
.Sigle line diagram,132KV substation Teliargnaj

Key Points:-
1. Different Protection Equipment:
break switches,
2. SF6-Circuit Breakers: Due to the unique properties of SF6, it is used for 132KV
lines protection. . Some of the outstanding properties of SF6 making it desirable
to using power applications are:
1. High dielectric strength
2. Unique arc-quenching ability
3. Excellent thermal stability
4. Good thermal conductivity
3. Lightening arresters: Lightening arresters are provided in order to discharge
the high voltages. It acts as main protective device for feeder.
4. Capacitance Voltage Transformer: After the Lightening arresters “Capacitance
Voltage Transformer – CVT” which together with the Wave trapper acts as LC
circuit follows it. In this substation, we used CVT’s in the place of PT’s because it
easily passes high frequency signals"www.powergridindia.c. om
5.Step down Transformer” is used to step-down the voltage level from 133KV to
33KV by using “
6. Battery Room: There are three panel of battery source one is for PLCC, it is
48v, two panels are 220v, and it is for relay operation and many more application.
These batteries are charged when AC supply is ON.
CONCLUSION
From this visit, we got the information and practical knowledge about Power
Distribution and Transmission. Student got the knowledge about different
protection devices used in substation. They got the idea how to read the one line
diagram of power substation using different symbols used in diagram. Student
cleared out practical knowledge of transformer as how it step down voltage 133
KV to 33 KV.They also got knowledge about new SCADA based system as you
can operate substation by manually or by command from computer using SCADA
system and PLC programming. About 46 students were benefited from this visit as
they got chance to discussion with assistant engineers working at Substation.

Weitere ähnliche Inhalte

Was ist angesagt?

PPt on 220 kV substation
PPt on 220 kV substationPPt on 220 kV substation
PPt on 220 kV substation
Ishank Ranjan
 

Was ist angesagt? (20)

Substations
SubstationsSubstations
Substations
 
PPt on 220 kV substation
PPt on 220 kV substationPPt on 220 kV substation
PPt on 220 kV substation
 
Industrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation pptIndustrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation ppt
 
Electric substation
Electric substation Electric substation
Electric substation
 
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATIONPPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
 
Presentation on substations
Presentation on substationsPresentation on substations
Presentation on substations
 
REPORT ON 33/11KV SUBSTATION
REPORT ON 33/11KV SUBSTATION REPORT ON 33/11KV SUBSTATION
REPORT ON 33/11KV SUBSTATION
 
132 kv gss summer training report from CPWD vidhyadar nagar jaipur
132 kv gss summer training report from CPWD vidhyadar nagar jaipur132 kv gss summer training report from CPWD vidhyadar nagar jaipur
132 kv gss summer training report from CPWD vidhyadar nagar jaipur
 
Electrical 132kv substation project .. shakir
Electrical 132kv substation project .. shakirElectrical 132kv substation project .. shakir
Electrical 132kv substation project .. shakir
 
220 kv Sub-station Summer Training ppt
220 kv Sub-station Summer Training ppt220 kv Sub-station Summer Training ppt
220 kv Sub-station Summer Training ppt
 
Substation Training presentation
Substation Training presentationSubstation Training presentation
Substation Training presentation
 
Ppt of 132kv gss sitapura jaipur
Ppt of 132kv gss sitapura jaipurPpt of 132kv gss sitapura jaipur
Ppt of 132kv gss sitapura jaipur
 
substation internship report
substation internship report substation internship report
substation internship report
 
Electrical SUBSTATION ppt
Electrical SUBSTATION pptElectrical SUBSTATION ppt
Electrical SUBSTATION ppt
 
industrial training on 132 kv substation
industrial training on 132 kv substationindustrial training on 132 kv substation
industrial training on 132 kv substation
 
132 kv
132 kv132 kv
132 kv
 
Distribution System
Distribution SystemDistribution System
Distribution System
 
VSC based HVDC system
VSC based HVDC systemVSC based HVDC system
VSC based HVDC system
 
ABCB(air blast circuit breaker)
ABCB(air blast circuit breaker)ABCB(air blast circuit breaker)
ABCB(air blast circuit breaker)
 
Directional over current relay
Directional over current relayDirectional over current relay
Directional over current relay
 

Ähnlich wie Report on visiting 132/33 kv substation teliarganj allahabad

220 kv g.s.s, report
 220 kv g.s.s, report 220 kv g.s.s, report
220 kv g.s.s, report
panna rayal
 

Ähnlich wie Report on visiting 132/33 kv substation teliarganj allahabad (20)

220 kv g.s.s, report
 220 kv g.s.s, report 220 kv g.s.s, report
220 kv g.s.s, report
 
finalseminar.docx
finalseminar.docxfinalseminar.docx
finalseminar.docx
 
DPL Training .doc file
DPL Training .doc file DPL Training .doc file
DPL Training .doc file
 
ppt on gss
ppt on gssppt on gss
ppt on gss
 
ppt on gss
ppt on gssppt on gss
ppt on gss
 
PPT ON SUMMER VOCATIONAL TRAINING ON 132/33 KV AT MOHADDIPUR, SUB-STATION, GO...
PPT ON SUMMER VOCATIONAL TRAINING ON 132/33 KV AT MOHADDIPUR, SUB-STATION, GO...PPT ON SUMMER VOCATIONAL TRAINING ON 132/33 KV AT MOHADDIPUR, SUB-STATION, GO...
PPT ON SUMMER VOCATIONAL TRAINING ON 132/33 KV AT MOHADDIPUR, SUB-STATION, GO...
 
INPLANT TRAINING.pptx
INPLANT TRAINING.pptxINPLANT TRAINING.pptx
INPLANT TRAINING.pptx
 
summer internship report on erection, commissioning and pre-comissioning of50...
summer internship report on erection, commissioning and pre-comissioning of50...summer internship report on erection, commissioning and pre-comissioning of50...
summer internship report on erection, commissioning and pre-comissioning of50...
 
Bharat singh 1
Bharat singh 1Bharat singh 1
Bharat singh 1
 
Uttar Pradesh Power Corparation Ltd. Training Report
Uttar Pradesh Power Corparation Ltd. Training ReportUttar Pradesh Power Corparation Ltd. Training Report
Uttar Pradesh Power Corparation Ltd. Training Report
 
My training
My trainingMy training
My training
 
Shashikdoc
ShashikdocShashikdoc
Shashikdoc
 
220kv gss pindwara(sirohi)
220kv gss pindwara(sirohi)220kv gss pindwara(sirohi)
220kv gss pindwara(sirohi)
 
Internship doc 33 11 kv substation
Internship doc 33 11 kv substation  Internship doc 33 11 kv substation
Internship doc 33 11 kv substation
 
REPORT ON INDUSTRIAL VISIT HARYANA VIDYUT PRASARAN NIGAM LTD
REPORT ON INDUSTRIAL VISIT HARYANA VIDYUT PRASARAN NIGAM LTDREPORT ON INDUSTRIAL VISIT HARYANA VIDYUT PRASARAN NIGAM LTD
REPORT ON INDUSTRIAL VISIT HARYANA VIDYUT PRASARAN NIGAM LTD
 
Industrial summer training
Industrial summer trainingIndustrial summer training
Industrial summer training
 
NAVEEN inter.pdf
NAVEEN inter.pdfNAVEEN inter.pdf
NAVEEN inter.pdf
 
internship report of 220/132 kV substation
internship report of 220/132 kV substationinternship report of 220/132 kV substation
internship report of 220/132 kV substation
 
220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54
220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54
220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54
 
66 kv substation
66 kv substation66 kv substation
66 kv substation
 

Kürzlich hochgeladen

Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
MayuraD1
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
jaanualu31
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
MsecMca
 

Kürzlich hochgeladen (20)

DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
Air Compressor reciprocating single stage
Air Compressor reciprocating single stageAir Compressor reciprocating single stage
Air Compressor reciprocating single stage
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planes
 
Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 

Report on visiting 132/33 kv substation teliarganj allahabad

  • 1. SUMMER INTERNSHIP PROGRAM ELECTRICAL ENGINEERING-2018 SITE Visit Report 2nd JULY,2018 At 132/33 KV SUB –STATION,TELIARGANJ ALLAHABAD SUBMITTED TO- SUBMITTED BY- MOTILAL NEHRU NATIONAL INSTITUTE ADARSH KUMAR OF TECHNOLOGY ,ALLAHABAD (Reg. No.-16737209) RAJKIYA ENGINEERING COLLEGE AMBEDKARNAGAR-224122
  • 2. CONTENT 1. Acknowledgement 2 2. Information 3 3. Purpose of Visit 3 4. What we learn? 4 5. Conclusion 7 ACKNOWLEDGEMENT We are gladly & thankful to Dr. Navneet Kumar Singh sir and Dr. Niraj Kumar Choudhayr Sir and SIPEE -2018 Team who decided to take visit in 132/33KV Substation, Teliarganj-Allahabad We are especially thankful to respected assistant engineers of Teliarganj- Substation who gave the proper guidance to us and gave practical based approach learning to us.
  • 3. GENERAL INFORMATION An electrical substation is a subsidiary station of an electricity generation, transmission and distribution system where voltage is transformed from high to low or the reverse using transformers. Electric power may flow through several substations between generating plant and consumer, and may be changed in voltage in several steps. Teliarganj substation that has a step-down transformer decreases the voltage(133/33KV) while increasing the current for domestic and commercial distribution. PURPOSE OF VISIT Our main purpose for this visit is to be get practical knowledge of electrical power transmission and distribution We are Electrical Engineering student so we will get the idea of electrical power transmission and distribution. we will also get familiar with Transformer maintenance, circuit breaker, Transformer isolator, bus bar, Protective relays, Lightening arresters, Load break switches
  • 4. WHAT WE LEARN? On 2nd july. ,2018 (Monday) at 03:00 pm we reached at Teliarganj- Sub Station Introduction About Single Line Diagram, Different Protection Equipment, SCADA system At the beginning, one of the assistant engineer explained all the essential component of the 133KV substation and explained one line diagram of Teliarganj
  • 5. .Sigle line diagram,132KV substation Teliargnaj  Key Points:- 1. Different Protection Equipment: break switches, 2. SF6-Circuit Breakers: Due to the unique properties of SF6, it is used for 132KV lines protection. . Some of the outstanding properties of SF6 making it desirable to using power applications are: 1. High dielectric strength 2. Unique arc-quenching ability 3. Excellent thermal stability 4. Good thermal conductivity
  • 6. 3. Lightening arresters: Lightening arresters are provided in order to discharge the high voltages. It acts as main protective device for feeder. 4. Capacitance Voltage Transformer: After the Lightening arresters “Capacitance Voltage Transformer – CVT” which together with the Wave trapper acts as LC circuit follows it. In this substation, we used CVT’s in the place of PT’s because it easily passes high frequency signals"www.powergridindia.c. om 5.Step down Transformer” is used to step-down the voltage level from 133KV to 33KV by using “ 6. Battery Room: There are three panel of battery source one is for PLCC, it is 48v, two panels are 220v, and it is for relay operation and many more application. These batteries are charged when AC supply is ON.
  • 7. CONCLUSION From this visit, we got the information and practical knowledge about Power Distribution and Transmission. Student got the knowledge about different protection devices used in substation. They got the idea how to read the one line diagram of power substation using different symbols used in diagram. Student cleared out practical knowledge of transformer as how it step down voltage 133 KV to 33 KV.They also got knowledge about new SCADA based system as you can operate substation by manually or by command from computer using SCADA system and PLC programming. About 46 students were benefited from this visit as they got chance to discussion with assistant engineers working at Substation.