Introduction and welcome
Keith Snook
Information Systems Development
Manager
BRE
Building Information Modelling (BIM)
Task Group Update
Richard Lane
Departmental Support & Training Development
25 September 2013
Background
• Lack of Clear Communication of Client Needs
• Incorrect Assumptions or Miscommunication within
the Supply Chain
• Rework / Recreation of Data
• Inability for Project Participants to ‘Speak the Same
Language’
• Poor or No Information Management
• Limited Reuse or Standardisation
35%
Background
Government Construction Strategy
Mandatory requirement for Level 2
BIM
“15-20% cost and carbon reduction
on all centrally procured government
construction projects within the
current parliament”
What is BIM?
• “A collection of value-creating best
practices, underpinned by a culture of
collaboration and the exchange of
structured asset data”
Building Information Modelling
What is BIM?
Building a consistent, collaborative industry, with
clear and open communication
Information of high-quality is procured to
support business outcomes
Modelling the design increases efficiency,
enabling simulation & analysis
What is BIM?
“A whole-estate, whole-life approach”
Thanks
For more information
www.bimtaskgroup.org
@BIMgcs
richard@creonova.co.uk
@richardlane
24 September 2013
BIM in the MoJ
Bill Davis
Ministry of Justice
Who are we?
• One of the largest government departments
• Employ around 76,000 people
• Annual budget of approximately £8 billion
• Around 500 courts and tribunals, and 133 prisons in England and Wales
– overall, nearly 2,000 properties of widely varying size and complexity
Why us?
Government target is for level 2 BIM
implementation on all Government
projects by 2016.
New MOJ Strategic Alliance Framework
was tendered in early 2012. It is for a
period of up to 6 years. So we needed to
include BIM in the tender exercise.
Our target is to have all projects at level 2
by summer 2013.
Benefits
Based on:
• Palace Exchange, Enfield
• Festival Place, Basingstoke
• Endeavour House, Stansted
• Terminal 5, Heathrow
• Portcullis House, London
• St. Bart’s Hospital, London
From: Government Construction Client Group
Building Information Modelling (BIM) Working Party Strategy Paper
March 2011
CookhamWood
Initial
Design
Tender Design &
Construct
Operate
Full
None
Knowledge
1st FM
Provider
Time
BIM
Traditional
2nd FM
Provider
3rd FM
Provider
Life Cycle Phase
BIM
Traditional
Keeping the information alive
What have we done?
What data do we need?
Key decision points Data drop points
• Drop 1 – Initial project data to inform Outline Business Case (OBC) submission.
• Drop 2a – lnitial project proposals based on preferred option from OBC to form
tender brief
• Drop 2b – Tenderer’s initial project proposals.
• Drop 3 – Selected constructor’s developed project proposals to agree the
contract maximum price (AMP) and to inform Full Business Case (FBC) when
required.
• Drop 4 – Practical completion (Certificate A) information.
• Drop 5 – Post occupancy validation.
Lessons
learned &
POE feed
back into
Standards
Committee
BIM – MOJ Value Model
Current standards are
modelled / depicted as
standard components
Cell Office Classroom Roof
Elements arranged to produce required product. QA is inbuilt as required standards are embedded and
automatically report non compliance. Virtual construction results in fewer mistakes and less waste
Appointed Constructor works up
Developed Project Proposals in open
book environment and submits Agreed
Maximum Price
Standard components
build up required
output for drop 2A
tender package
Delivery Benchmarking
(more product for our money)
MoJ Standard Component Library
Tenderers
prepare drop 2B
tender
More timely
handover
information
Escort costs
Client fees, design only
Client fees
Client risk
Profit, supply chain
Overhead, supply chain
Profit, main
Overhead, main
Prelims, C
Prelims, B
Prelims, A
Design development contingency
Constructor fees
Constructor risk
Non-productive
Product
Cookham Wood
• Provision of 179 room accommodation unit for the Youth Justice Board
together with an associated education facility at Cookham Wood
Young Offender Institution in Rochester, Kent.
• Approximate out-turn value of £20million
• Designers model and COBie 2a drop issued with tender package.
• Tenderers had to return a developed model, 2D cuts and COBie drop
2b.
• Constructor appointed: Interserve
• Commencement Agreement signed 19/10/12, Start on site November
2012
Cookham Wood
Cookham Wood
Drop 4 Pilot
HMP Oakwood (New Energy Centre only)
Some modelling done during construction, but full model now developed
and back populated with drop 4 data. From this we will extract a COBie
file. This will be used to develop how we get the information into our
CAFM and Asset Management systems.
Together with work that is being done on the Cookham Wood project
and on our handover procedures in general, this will inform what
information we need (and in what format) for the drop 4 for all future
projects.
Moving toward business as usual
HMP Winchester - New build kitchen
HMP Leeds - Improved reception facilities
HMP The Mount - New houseblock & kitchen and some refurbishment
works
HMP Durham – New healthcare
Other BIM projects now coming on line:
Refurbishments
What’s in it for us?
BIM
Component
Standardisation
Reduced
Cost
Build
off-site
Better &
timely handover
information
Better
stakeholder
involvement
through early 3D
visualisation
Stakeholder
feedback
Less
re-work
Virtual
constructionBetter design co-
ordination
Better
programming Better
cost
data
Carbon reduction
Clash
detection
Performance
modelling
Better
productivity
Compliance
checking
Improved
H&S
Lessons learned so far
A lessons learned (so far) document is available at www.bimtaskgroup.org
The following are some of the major findings:
• You have to fully understand your own processes and what information you need at each stage.
• There is great benefit to be had from using the model for early stakeholder engagement.
• IT security may be an issue. It certainly was, and continues to be, for MOJ.
• If you issue a model for tender purposes you need to decide what you expect your tenderers to do with it – and
make sure they know!
• The Contractors need to manage the tender process differently, and use different resources. They need more
forward planning and adherence to dates. A six week tender period was seen to be too short.
• Contractors are keen to engage
• BIM will change the way you operate your projects and you have to put appropriate systems and training in place.
• Although there seems to be a lot of experience of BIM amongst
Contractors, there is very little experience of COBie.
What do we need?
In the short term:
• Better interoperability between software packages including ‘no data loss’ IFC files from
native model(s) and seamless transfer of models from one software package to another.
• Better COBie data extraction tools.
• COBie data interrogation/analysis tools.
In the longer term:
• Seamless transfer from model to CAFM software or perhaps the model becoming the
CAFM tool - a ‘through life’ BIM package!
• More cost effective ways of getting models of our existing estate.
Thank you.
Alan Windley BSc
Nomitech
(on behalf of ForgeTrack Ltd)
07812 771860
alan@nomitech.eu
“Achieving BIM Level 2 - Estimating, 4D, 5D
& Value Engineering”
A LITTLE REMINDER
Level 2 BIM          
A managed 3D environment held in separate
discipline 'BIM' tools with data attached. Commercial
data will be managed by enterprise resource
planning software and integrated by proprietary
interfaces or bespoke middleware. This level of BIM
may utilise 4D construction sequencing and 5D cost
information. The Government’s BIM Strategy Paper
calls for the industry to achieve Level 2 BIM by 2016.
Sounds scary!!
DISPELLING MYTHS
• It is another fad
• It does not affect me
• Its just for Architects
• Its just CAD on steroids
• Its CAD with 3D
• Just to look pretty
• It is only for buildings
• The Architect doesn’t put all the information in
• It is no use to owners/clients
• It is no use to contractors
• It is no use for FM
• It is none of the above!
FROM BIM TO BILL TO BID TO BUILD
Early Phase / Feasibility
Utilise outline or incomplete
models
Standard Method Bills With
Associated Prices
Associate Costs & Descriptions
– Multiple Formats
Combining Parametric
Assemblies With Models
Value Engineering,
optimisation
Multiple Models
Different BIM Authoring Tools - IFC
Project Planning & Risk
Synchronised Integration with
Project Planning & Risk Analysis
Not just for buildingsInfrastructure Projects
Design Cost Schedule
From an early stage Model to
CostOS (5D) To Primavera Project
Planning To Synchro (4D)
Highlighting Transparency,
Synchronisation & Collaboration
Not just for buildings
The model, provided by the Architect, is loaded into the
estimating solution.
Cost data, (local, historical,
commercial) is associated with
each model element. In this
case, BCIS cost data.
If, as you would expect in the early stages of a project, if not much detail
regarding specification is available, then value options can be explored by
associating parametric cost assemblies.
A fully measured and costed estimate/cost plan is produced directly
from the model, and in this example, classified (WBS) in a simple
BCIS, industry standard elemental structure.
The relationship is maintained between the model entity and cost
and clearly visualised.
The estimate or cost plan in more detail, including productivities.
The information can be grouped by any of the traditional industry
standard formats eg, BCIS Elements, SMM7, NRM (New Rules Of
Measurement)
The estimate is then synchronised with the project planning solution
to create the initial project plan, fully cost loaded
The initial project plan now created directly from the estimate.
The project plan is then then synchronised with the construction
sequencing solution. Once here the schedule was linked to the model
and hence by ‘sliding’ the red vertical dotted timeline, you will next
see the model being built in line with the schedule and also the
‘Earned Value’ at each construction stage.
We have now started to collaborate 4 important aspects ie, the
design, the cost, the schedule and the construction sequence which
all started from an early stage (feasibility) design.
We can now visualise the potential sequence of construction and
make any required adjustments. In other words, ‘virtually’ constructing
the project now rather than making costly and wasteful mistakes
onsite.
In other words ‘will the project work?’
Any required adjustments are made and then simply synchronised back
to the project plan.
And in turn, synchronised back to the estimate so that any effect on
cost can be clearly highlighted and hence ultimately delivering the
most cost effective project.
Reduce waste – Reduce Cost – Create Transparency - Collaborate
Finally… the estimate, produced from a model, synchronised
with the plan and the construction sequence can be
synchronised with Risk Management solutions such as Crystal Ball
to run Monte Carlo simulation techniques.
Reducing and mitigating risk! In the example shown, a very high
value Oil & Gas project.
Case Study – The Ionion Highway
• The Ionion Highway and E65 were 2 major build and operate initiatives,
operating under a Public Private Partnership (around 2,700 miles long)
• Total budget 3 Billion Euros
• Winning consortium ‘Nea Odos’ to build, operate and receive tolls for
30 years
• The consortium invested 1.15 Billion euros into the programme.
• The principles, practices and knowledge used on the Ionion Highway
then used to support the E65 programme bid.
The Project
• Nomitech CostOS was chosen to undertake the cost estimating of all
the bridges and culverts for both highways
• Smart assemblies/cost models developed to model the different types
of bridges to be used.
The Concept
• Engineering optimized by modifying bridge cost assemblies
• Options quickly assessed
• Budgets producing in in double quick time
• Accurate budgets produced from typical first principles
The budgets were synchronised with the Project
plan!
What Happened?
•Large European banks funding
•Accurate & realistic schedule and cashflow demanded
•CostOS integrated with planning solution
Problem!
•2 major bridges on the critical path were causing delays
•Concerns raised
•Purchase another bridge?
Why The Importance?
• Design options were evaluated early – from a cost and a scheduling
viewpoint
• Informed decisions made
• On closer analysis, by collaborating design, cost and schedule, the
total cost was far less than the original 60 days delay would have
caused!
• All knowledge retained for the subsequent E65 project.
Let the Tolls begin! ££££
The Result!
BIM – Bringing the whole professional team
together – collaborating from the earliest
concept stage to final completion and
complete life cycle.
Reduce waste – Reduce Cost – Create
Transparency - Collaborate
It’s not that scary - really
In conclusion….
Thanks & Acknowledgements
Information and tools used during this webinar
CostOS Bim-enabled Estimating – Nomitech Ltd
Cost Data - BCIS
Synchro 4D Sequencing – Synchro
Oracle Primavera P6 – ForgeTrack Ltd
Oracle Crystal Ball Risk Management – Oracle
Model designed and provided by – Metz Architects
Integrated Process Facilitated by - Fulcro Ltd
Project courtesy of – Dudley College

Weitere ähnliche Inhalte

Was ist angesagt?

Bim level-2 information-management
Bim level-2 information-managementBim level-2 information-management
Bim level-2 information-managementIbrahem Naeem
 
Build Source-Company_Profile
Build Source-Company_ProfileBuild Source-Company_Profile
Build Source-Company_Profilebuildsource
 
Bim and project management
Bim and project managementBim and project management
Bim and project managementOmar Selim
 
Delivering Projects Better with BIM
Delivering Projects Better with BIMDelivering Projects Better with BIM
Delivering Projects Better with BIMAlex Ferguson
 
BASIC TERMS IN BIM-REVIT
BASIC TERMS IN BIM-REVITBASIC TERMS IN BIM-REVIT
BASIC TERMS IN BIM-REVITnilesh masne
 
Vico Software: 4D and 5D perspectives on BIM
Vico Software: 4D and 5D perspectives on BIMVico Software: 4D and 5D perspectives on BIM
Vico Software: 4D and 5D perspectives on BIMBe2camp Admin
 
Virtual design and construction
Virtual design and constructionVirtual design and construction
Virtual design and constructionAnkit Singhai
 
Software application (QS)
Software application (QS)Software application (QS)
Software application (QS)Hasif Alias
 
Software Presentation Slides
Software Presentation SlidesSoftware Presentation Slides
Software Presentation SlidesShze Hwa Lee
 
Building information modeling
Building information modelingBuilding information modeling
Building information modelingPradeepa M
 
Barriers to bim implementation in gcc
Barriers to bim implementation in gccBarriers to bim implementation in gcc
Barriers to bim implementation in gccHamzeh Nawar, MCIOB
 
The use of BIM to analyse the energy performance of a retrofitted educational...
The use of BIM to analyse the energy performance of a retrofitted educational...The use of BIM to analyse the energy performance of a retrofitted educational...
The use of BIM to analyse the energy performance of a retrofitted educational...Mark Thornton
 
COBIE2 Challenge - Perspectives
COBIE2 Challenge - PerspectivesCOBIE2 Challenge - Perspectives
COBIE2 Challenge - PerspectivesMike Bordenaro
 
ACE Team 2 - WK6 - IPD Presentation
ACE Team 2 - WK6 - IPD PresentationACE Team 2 - WK6 - IPD Presentation
ACE Team 2 - WK6 - IPD PresentationAusrine Rakauskaite
 
How BIM Can Accelerate Project-Wide Review Cycles - Webinar, November 11, 2015
How BIM Can Accelerate Project-Wide Review Cycles - Webinar, November 11, 2015How BIM Can Accelerate Project-Wide Review Cycles - Webinar, November 11, 2015
How BIM Can Accelerate Project-Wide Review Cycles - Webinar, November 11, 2015Aconex
 

Was ist angesagt? (20)

Bim level-2 information-management
Bim level-2 information-managementBim level-2 information-management
Bim level-2 information-management
 
Bim its applications
Bim   its applicationsBim   its applications
Bim its applications
 
Build Source-Company_Profile
Build Source-Company_ProfileBuild Source-Company_Profile
Build Source-Company_Profile
 
Bim and project management
Bim and project managementBim and project management
Bim and project management
 
BIM Analysis
BIM AnalysisBIM Analysis
BIM Analysis
 
Delivering Projects Better with BIM
Delivering Projects Better with BIMDelivering Projects Better with BIM
Delivering Projects Better with BIM
 
BIM – Just another buzzword or a real change in the Industry? - Professor Art...
BIM – Just another buzzword or a real change in the Industry? - Professor Art...BIM – Just another buzzword or a real change in the Industry? - Professor Art...
BIM – Just another buzzword or a real change in the Industry? - Professor Art...
 
BASIC TERMS IN BIM-REVIT
BASIC TERMS IN BIM-REVITBASIC TERMS IN BIM-REVIT
BASIC TERMS IN BIM-REVIT
 
BIM Assessment
BIM AssessmentBIM Assessment
BIM Assessment
 
Vico Software: 4D and 5D perspectives on BIM
Vico Software: 4D and 5D perspectives on BIMVico Software: 4D and 5D perspectives on BIM
Vico Software: 4D and 5D perspectives on BIM
 
Virtual design and construction
Virtual design and constructionVirtual design and construction
Virtual design and construction
 
Software application (QS)
Software application (QS)Software application (QS)
Software application (QS)
 
Software Presentation Slides
Software Presentation SlidesSoftware Presentation Slides
Software Presentation Slides
 
Building information modeling
Building information modelingBuilding information modeling
Building information modeling
 
Barriers to bim implementation in gcc
Barriers to bim implementation in gccBarriers to bim implementation in gcc
Barriers to bim implementation in gcc
 
Ho.01 bim.arabic
Ho.01 bim.arabicHo.01 bim.arabic
Ho.01 bim.arabic
 
The use of BIM to analyse the energy performance of a retrofitted educational...
The use of BIM to analyse the energy performance of a retrofitted educational...The use of BIM to analyse the energy performance of a retrofitted educational...
The use of BIM to analyse the energy performance of a retrofitted educational...
 
COBIE2 Challenge - Perspectives
COBIE2 Challenge - PerspectivesCOBIE2 Challenge - Perspectives
COBIE2 Challenge - Perspectives
 
ACE Team 2 - WK6 - IPD Presentation
ACE Team 2 - WK6 - IPD PresentationACE Team 2 - WK6 - IPD Presentation
ACE Team 2 - WK6 - IPD Presentation
 
How BIM Can Accelerate Project-Wide Review Cycles - Webinar, November 11, 2015
How BIM Can Accelerate Project-Wide Review Cycles - Webinar, November 11, 2015How BIM Can Accelerate Project-Wide Review Cycles - Webinar, November 11, 2015
How BIM Can Accelerate Project-Wide Review Cycles - Webinar, November 11, 2015
 

Ähnlich wie Sustainability In Government - Bim Webinar

How to Create a Rock Star BIM Execution Plan (BEP) and MPDT* (Responsibility ...
How to Create a Rock Star BIM Execution Plan (BEP) and MPDT* (Responsibility ...How to Create a Rock Star BIM Execution Plan (BEP) and MPDT* (Responsibility ...
How to Create a Rock Star BIM Execution Plan (BEP) and MPDT* (Responsibility ...Fabio Roberti
 
Contractor Lead BIM: Baxall Construction: CE Lancashire 20th Jan
Contractor Lead BIM: Baxall Construction: CE Lancashire  20th JanContractor Lead BIM: Baxall Construction: CE Lancashire  20th Jan
Contractor Lead BIM: Baxall Construction: CE Lancashire 20th JanMartin Brown
 
BIFM North Region Key Learning Event - BIM & Soft Landings
BIFM North Region Key Learning Event - BIM & Soft LandingsBIFM North Region Key Learning Event - BIM & Soft Landings
BIFM North Region Key Learning Event - BIM & Soft LandingsWhitbags
 
BuildingSmart COBie presentation March 2014
BuildingSmart COBie presentation March 2014BuildingSmart COBie presentation March 2014
BuildingSmart COBie presentation March 2014Graham H Stewart
 
The NBS BIM Toolkit and Digital Plan of Work
The NBS BIM Toolkit and Digital Plan of WorkThe NBS BIM Toolkit and Digital Plan of Work
The NBS BIM Toolkit and Digital Plan of WorkThe NBS
 
Alistair Gardner ty BIM Overview 090212
Alistair Gardner ty BIM Overview 090212Alistair Gardner ty BIM Overview 090212
Alistair Gardner ty BIM Overview 090212AlistairGardner
 
Building information modelling - redefining the role of the project manager: ...
Building information modelling - redefining the role of the project manager: ...Building information modelling - redefining the role of the project manager: ...
Building information modelling - redefining the role of the project manager: ...Association for Project Management
 
Change Management For Building Information Modelling (BIM)
Change Management For Building Information Modelling (BIM)Change Management For Building Information Modelling (BIM)
Change Management For Building Information Modelling (BIM)Ir. Abdul Aziz Abas
 
How BIM Can Improve Decisions and Reduce Errors - Webinar, December 2, 2015
How BIM Can Improve Decisions and Reduce Errors - Webinar, December 2, 2015How BIM Can Improve Decisions and Reduce Errors - Webinar, December 2, 2015
How BIM Can Improve Decisions and Reduce Errors - Webinar, December 2, 2015Aconex
 
ETDP 2015 D2 Next Generation Bim - InEight
ETDP 2015 D2 Next Generation Bim - InEightETDP 2015 D2 Next Generation Bim - InEight
ETDP 2015 D2 Next Generation Bim - InEightComit Projects Ltd
 
Building information modeling BIM
Building information modeling BIMBuilding information modeling BIM
Building information modeling BIMfitsum yonas
 
BIM for Facility Managers - Hani Afendi - Facilities Show, 19 June 2014
BIM for Facility Managers - Hani Afendi - Facilities Show, 19 June 2014BIM for Facility Managers - Hani Afendi - Facilities Show, 19 June 2014
BIM for Facility Managers - Hani Afendi - Facilities Show, 19 June 2014Protectionandmanagement
 
10 points and the benefits of bim
10 points and the benefits of bim10 points and the benefits of bim
10 points and the benefits of bimEr. Jigar Rana
 
July 2015 Construct15_Richard Morwood_V4 (2)
July 2015 Construct15_Richard Morwood_V4 (2)July 2015 Construct15_Richard Morwood_V4 (2)
July 2015 Construct15_Richard Morwood_V4 (2)Richard Morwood
 
BIM for Local Government - Presentation by John Lorimer, Local Government BIM...
BIM for Local Government - Presentation by John Lorimer, Local Government BIM...BIM for Local Government - Presentation by John Lorimer, Local Government BIM...
BIM for Local Government - Presentation by John Lorimer, Local Government BIM...Clarkson Alliance
 
Digital Transformation 2018
Digital Transformation 2018Digital Transformation 2018
Digital Transformation 2018Aconex
 
Brochure BIM
Brochure BIM Brochure BIM
Brochure BIM UTHM
 
Foundation works norwich - 15th october 2012
Foundation works   norwich - 15th october 2012Foundation works   norwich - 15th october 2012
Foundation works norwich - 15th october 2012carolmcnulty
 

Ähnlich wie Sustainability In Government - Bim Webinar (20)

Innovation in practice presentation 10 06-15
Innovation in practice presentation 10 06-15Innovation in practice presentation 10 06-15
Innovation in practice presentation 10 06-15
 
How to Create a Rock Star BIM Execution Plan (BEP) and MPDT* (Responsibility ...
How to Create a Rock Star BIM Execution Plan (BEP) and MPDT* (Responsibility ...How to Create a Rock Star BIM Execution Plan (BEP) and MPDT* (Responsibility ...
How to Create a Rock Star BIM Execution Plan (BEP) and MPDT* (Responsibility ...
 
Contractor Lead BIM: Baxall Construction: CE Lancashire 20th Jan
Contractor Lead BIM: Baxall Construction: CE Lancashire  20th JanContractor Lead BIM: Baxall Construction: CE Lancashire  20th Jan
Contractor Lead BIM: Baxall Construction: CE Lancashire 20th Jan
 
BIFM North Region Key Learning Event - BIM & Soft Landings
BIFM North Region Key Learning Event - BIM & Soft LandingsBIFM North Region Key Learning Event - BIM & Soft Landings
BIFM North Region Key Learning Event - BIM & Soft Landings
 
1 andrew thomas, room 4
1   andrew thomas, room 41   andrew thomas, room 4
1 andrew thomas, room 4
 
BuildingSmart COBie presentation March 2014
BuildingSmart COBie presentation March 2014BuildingSmart COBie presentation March 2014
BuildingSmart COBie presentation March 2014
 
The NBS BIM Toolkit and Digital Plan of Work
The NBS BIM Toolkit and Digital Plan of WorkThe NBS BIM Toolkit and Digital Plan of Work
The NBS BIM Toolkit and Digital Plan of Work
 
Alistair Gardner ty BIM Overview 090212
Alistair Gardner ty BIM Overview 090212Alistair Gardner ty BIM Overview 090212
Alistair Gardner ty BIM Overview 090212
 
Building information modelling - redefining the role of the project manager: ...
Building information modelling - redefining the role of the project manager: ...Building information modelling - redefining the role of the project manager: ...
Building information modelling - redefining the role of the project manager: ...
 
Change Management For Building Information Modelling (BIM)
Change Management For Building Information Modelling (BIM)Change Management For Building Information Modelling (BIM)
Change Management For Building Information Modelling (BIM)
 
How BIM Can Improve Decisions and Reduce Errors - Webinar, December 2, 2015
How BIM Can Improve Decisions and Reduce Errors - Webinar, December 2, 2015How BIM Can Improve Decisions and Reduce Errors - Webinar, December 2, 2015
How BIM Can Improve Decisions and Reduce Errors - Webinar, December 2, 2015
 
ETDP 2015 D2 Next Generation Bim - InEight
ETDP 2015 D2 Next Generation Bim - InEightETDP 2015 D2 Next Generation Bim - InEight
ETDP 2015 D2 Next Generation Bim - InEight
 
Building information modeling BIM
Building information modeling BIMBuilding information modeling BIM
Building information modeling BIM
 
BIM for Facility Managers - Hani Afendi - Facilities Show, 19 June 2014
BIM for Facility Managers - Hani Afendi - Facilities Show, 19 June 2014BIM for Facility Managers - Hani Afendi - Facilities Show, 19 June 2014
BIM for Facility Managers - Hani Afendi - Facilities Show, 19 June 2014
 
10 points and the benefits of bim
10 points and the benefits of bim10 points and the benefits of bim
10 points and the benefits of bim
 
July 2015 Construct15_Richard Morwood_V4 (2)
July 2015 Construct15_Richard Morwood_V4 (2)July 2015 Construct15_Richard Morwood_V4 (2)
July 2015 Construct15_Richard Morwood_V4 (2)
 
BIM for Local Government - Presentation by John Lorimer, Local Government BIM...
BIM for Local Government - Presentation by John Lorimer, Local Government BIM...BIM for Local Government - Presentation by John Lorimer, Local Government BIM...
BIM for Local Government - Presentation by John Lorimer, Local Government BIM...
 
Digital Transformation 2018
Digital Transformation 2018Digital Transformation 2018
Digital Transformation 2018
 
Brochure BIM
Brochure BIM Brochure BIM
Brochure BIM
 
Foundation works norwich - 15th october 2012
Foundation works   norwich - 15th october 2012Foundation works   norwich - 15th october 2012
Foundation works norwich - 15th october 2012
 

Mehr von 4 All of Us

UK Cities and the Impact of Covid 19
UK Cities and the Impact of Covid 19UK Cities and the Impact of Covid 19
UK Cities and the Impact of Covid 194 All of Us
 
Sustainability in the NHS Virtual Conference
Sustainability in the NHS Virtual ConferenceSustainability in the NHS Virtual Conference
Sustainability in the NHS Virtual Conference4 All of Us
 
NHS Sustainability and the Impact of Covid19 Virtual Conference
NHS Sustainability and the Impact of Covid19 Virtual ConferenceNHS Sustainability and the Impact of Covid19 Virtual Conference
NHS Sustainability and the Impact of Covid19 Virtual Conference4 All of Us
 
POCT equipment in response to covid 19 to prevent hospital admissions
POCT equipment in response to covid 19 to prevent hospital admissionsPOCT equipment in response to covid 19 to prevent hospital admissions
POCT equipment in response to covid 19 to prevent hospital admissions4 All of Us
 
Diagnostic Testing Conference 2020
Diagnostic Testing Conference 2020Diagnostic Testing Conference 2020
Diagnostic Testing Conference 20204 All of Us
 
Sustainability in the Operating Theatre
Sustainability in the Operating TheatreSustainability in the Operating Theatre
Sustainability in the Operating Theatre4 All of Us
 
Developing a Digital Strategy
Developing a Digital StrategyDeveloping a Digital Strategy
Developing a Digital Strategy4 All of Us
 
Reducing Single Use Plastic in the NHS
Reducing Single Use Plastic in the NHSReducing Single Use Plastic in the NHS
Reducing Single Use Plastic in the NHS4 All of Us
 
Role of diagnostics for disease & infection prevention webinar
Role of diagnostics for disease & infection prevention webinarRole of diagnostics for disease & infection prevention webinar
Role of diagnostics for disease & infection prevention webinar4 All of Us
 
NHS Sustainability Day Cardiff Roadshow
NHS Sustainability Day Cardiff RoadshowNHS Sustainability Day Cardiff Roadshow
NHS Sustainability Day Cardiff Roadshow4 All of Us
 
Sustainability Day Campaign Manchester Roadshow
Sustainability Day Campaign Manchester RoadshowSustainability Day Campaign Manchester Roadshow
Sustainability Day Campaign Manchester Roadshow4 All of Us
 
Creating an SDMP for your NHS Trust
Creating an SDMP for your NHS Trust Creating an SDMP for your NHS Trust
Creating an SDMP for your NHS Trust 4 All of Us
 
UK Diagnostics Summit 2019
UK Diagnostics Summit 2019UK Diagnostics Summit 2019
UK Diagnostics Summit 20194 All of Us
 
Sustainable Health Scotland 2017
Sustainable Health Scotland 2017Sustainable Health Scotland 2017
Sustainable Health Scotland 20174 All of Us
 
Sustainability Day Leeds 2017
Sustainability Day Leeds 2017Sustainability Day Leeds 2017
Sustainability Day Leeds 20174 All of Us
 
Transport and Travel Challenges for the NHS - Webinar
Transport and Travel Challenges for the NHS - WebinarTransport and Travel Challenges for the NHS - Webinar
Transport and Travel Challenges for the NHS - Webinar4 All of Us
 
Sustainability Day Manchester 2017
Sustainability Day Manchester 2017Sustainability Day Manchester 2017
Sustainability Day Manchester 20174 All of Us
 
Antibiotic Guardian Bristol Workshop
Antibiotic Guardian Bristol WorkshopAntibiotic Guardian Bristol Workshop
Antibiotic Guardian Bristol Workshop4 All of Us
 
Smart Cities Day 2 Urban Innovation
Smart Cities Day 2 Urban InnovationSmart Cities Day 2 Urban Innovation
Smart Cities Day 2 Urban Innovation4 All of Us
 
Smart Cities Day 1 Secure Cities
Smart Cities Day 1 Secure CitiesSmart Cities Day 1 Secure Cities
Smart Cities Day 1 Secure Cities4 All of Us
 

Mehr von 4 All of Us (20)

UK Cities and the Impact of Covid 19
UK Cities and the Impact of Covid 19UK Cities and the Impact of Covid 19
UK Cities and the Impact of Covid 19
 
Sustainability in the NHS Virtual Conference
Sustainability in the NHS Virtual ConferenceSustainability in the NHS Virtual Conference
Sustainability in the NHS Virtual Conference
 
NHS Sustainability and the Impact of Covid19 Virtual Conference
NHS Sustainability and the Impact of Covid19 Virtual ConferenceNHS Sustainability and the Impact of Covid19 Virtual Conference
NHS Sustainability and the Impact of Covid19 Virtual Conference
 
POCT equipment in response to covid 19 to prevent hospital admissions
POCT equipment in response to covid 19 to prevent hospital admissionsPOCT equipment in response to covid 19 to prevent hospital admissions
POCT equipment in response to covid 19 to prevent hospital admissions
 
Diagnostic Testing Conference 2020
Diagnostic Testing Conference 2020Diagnostic Testing Conference 2020
Diagnostic Testing Conference 2020
 
Sustainability in the Operating Theatre
Sustainability in the Operating TheatreSustainability in the Operating Theatre
Sustainability in the Operating Theatre
 
Developing a Digital Strategy
Developing a Digital StrategyDeveloping a Digital Strategy
Developing a Digital Strategy
 
Reducing Single Use Plastic in the NHS
Reducing Single Use Plastic in the NHSReducing Single Use Plastic in the NHS
Reducing Single Use Plastic in the NHS
 
Role of diagnostics for disease & infection prevention webinar
Role of diagnostics for disease & infection prevention webinarRole of diagnostics for disease & infection prevention webinar
Role of diagnostics for disease & infection prevention webinar
 
NHS Sustainability Day Cardiff Roadshow
NHS Sustainability Day Cardiff RoadshowNHS Sustainability Day Cardiff Roadshow
NHS Sustainability Day Cardiff Roadshow
 
Sustainability Day Campaign Manchester Roadshow
Sustainability Day Campaign Manchester RoadshowSustainability Day Campaign Manchester Roadshow
Sustainability Day Campaign Manchester Roadshow
 
Creating an SDMP for your NHS Trust
Creating an SDMP for your NHS Trust Creating an SDMP for your NHS Trust
Creating an SDMP for your NHS Trust
 
UK Diagnostics Summit 2019
UK Diagnostics Summit 2019UK Diagnostics Summit 2019
UK Diagnostics Summit 2019
 
Sustainable Health Scotland 2017
Sustainable Health Scotland 2017Sustainable Health Scotland 2017
Sustainable Health Scotland 2017
 
Sustainability Day Leeds 2017
Sustainability Day Leeds 2017Sustainability Day Leeds 2017
Sustainability Day Leeds 2017
 
Transport and Travel Challenges for the NHS - Webinar
Transport and Travel Challenges for the NHS - WebinarTransport and Travel Challenges for the NHS - Webinar
Transport and Travel Challenges for the NHS - Webinar
 
Sustainability Day Manchester 2017
Sustainability Day Manchester 2017Sustainability Day Manchester 2017
Sustainability Day Manchester 2017
 
Antibiotic Guardian Bristol Workshop
Antibiotic Guardian Bristol WorkshopAntibiotic Guardian Bristol Workshop
Antibiotic Guardian Bristol Workshop
 
Smart Cities Day 2 Urban Innovation
Smart Cities Day 2 Urban InnovationSmart Cities Day 2 Urban Innovation
Smart Cities Day 2 Urban Innovation
 
Smart Cities Day 1 Secure Cities
Smart Cities Day 1 Secure CitiesSmart Cities Day 1 Secure Cities
Smart Cities Day 1 Secure Cities
 

Kürzlich hochgeladen

VIP Call Girl Amravati Aashi 8250192130 Independent Escort Service Amravati
VIP Call Girl Amravati Aashi 8250192130 Independent Escort Service AmravatiVIP Call Girl Amravati Aashi 8250192130 Independent Escort Service Amravati
VIP Call Girl Amravati Aashi 8250192130 Independent Escort Service AmravatiSuhani Kapoor
 
The_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdf
The_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdfThe_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdf
The_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdfAmirYakdi
 
Verified Trusted Call Girls Adugodi💘 9352852248 Good Looking standard Profil...
Verified Trusted Call Girls Adugodi💘 9352852248  Good Looking standard Profil...Verified Trusted Call Girls Adugodi💘 9352852248  Good Looking standard Profil...
Verified Trusted Call Girls Adugodi💘 9352852248 Good Looking standard Profil...kumaririma588
 
Captivating Charm: Exploring Marseille's Hillside Villas with Our 3D Architec...
Captivating Charm: Exploring Marseille's Hillside Villas with Our 3D Architec...Captivating Charm: Exploring Marseille's Hillside Villas with Our 3D Architec...
Captivating Charm: Exploring Marseille's Hillside Villas with Our 3D Architec...Yantram Animation Studio Corporation
 
The history of music videos a level presentation
The history of music videos a level presentationThe history of music videos a level presentation
The history of music videos a level presentationamedia6
 
CBD Belapur Individual Call Girls In 08976425520 Panvel Only Genuine Call Girls
CBD Belapur Individual Call Girls In 08976425520 Panvel Only Genuine Call GirlsCBD Belapur Individual Call Girls In 08976425520 Panvel Only Genuine Call Girls
CBD Belapur Individual Call Girls In 08976425520 Panvel Only Genuine Call Girlsmodelanjalisharma4
 
(AISHA) Ambegaon Khurd Call Girls Just Call 7001035870 [ Cash on Delivery ] P...
(AISHA) Ambegaon Khurd Call Girls Just Call 7001035870 [ Cash on Delivery ] P...(AISHA) Ambegaon Khurd Call Girls Just Call 7001035870 [ Cash on Delivery ] P...
(AISHA) Ambegaon Khurd Call Girls Just Call 7001035870 [ Cash on Delivery ] P...ranjana rawat
 
Editorial design Magazine design project.pdf
Editorial design Magazine design project.pdfEditorial design Magazine design project.pdf
Editorial design Magazine design project.pdftbatkhuu1
 
Best VIP Call Girls Noida Sector 47 Call Me: 8448380779
Best VIP Call Girls Noida Sector 47 Call Me: 8448380779Best VIP Call Girls Noida Sector 47 Call Me: 8448380779
Best VIP Call Girls Noida Sector 47 Call Me: 8448380779Delhi Call girls
 
Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...
Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...
Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...home
 
Dubai Call Girls Pro Domain O525547819 Call Girls Dubai Doux
Dubai Call Girls Pro Domain O525547819 Call Girls Dubai DouxDubai Call Girls Pro Domain O525547819 Call Girls Dubai Doux
Dubai Call Girls Pro Domain O525547819 Call Girls Dubai Douxkojalkojal131
 
Booking open Available Pune Call Girls Nanded City 6297143586 Call Hot India...
Booking open Available Pune Call Girls Nanded City  6297143586 Call Hot India...Booking open Available Pune Call Girls Nanded City  6297143586 Call Hot India...
Booking open Available Pune Call Girls Nanded City 6297143586 Call Hot India...Call Girls in Nagpur High Profile
 
SCRIP Lua HTTP PROGRACMACION PLC WECON CA
SCRIP Lua HTTP PROGRACMACION PLC  WECON CASCRIP Lua HTTP PROGRACMACION PLC  WECON CA
SCRIP Lua HTTP PROGRACMACION PLC WECON CANestorGamez6
 
Cheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk Gurgaon
Cheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk GurgaonCheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk Gurgaon
Cheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk GurgaonDelhi Call girls
 
Presentation.pptx about blender what is blender
Presentation.pptx about blender what is blenderPresentation.pptx about blender what is blender
Presentation.pptx about blender what is blenderUbaidurrehman997675
 
Cosumer Willingness to Pay for Sustainable Bricks
Cosumer Willingness to Pay for Sustainable BricksCosumer Willingness to Pay for Sustainable Bricks
Cosumer Willingness to Pay for Sustainable Bricksabhishekparmar618
 
Chapter 19_DDA_TOD Policy_First Draft 2012.pdf
Chapter 19_DDA_TOD Policy_First Draft 2012.pdfChapter 19_DDA_TOD Policy_First Draft 2012.pdf
Chapter 19_DDA_TOD Policy_First Draft 2012.pdfParomita Roy
 

Kürzlich hochgeladen (20)

VIP Call Girl Amravati Aashi 8250192130 Independent Escort Service Amravati
VIP Call Girl Amravati Aashi 8250192130 Independent Escort Service AmravatiVIP Call Girl Amravati Aashi 8250192130 Independent Escort Service Amravati
VIP Call Girl Amravati Aashi 8250192130 Independent Escort Service Amravati
 
The_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdf
The_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdfThe_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdf
The_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdf
 
escort service sasti (*~Call Girls in Prasad Nagar Metro❤️9953056974
escort service sasti (*~Call Girls in Prasad Nagar Metro❤️9953056974escort service sasti (*~Call Girls in Prasad Nagar Metro❤️9953056974
escort service sasti (*~Call Girls in Prasad Nagar Metro❤️9953056974
 
Verified Trusted Call Girls Adugodi💘 9352852248 Good Looking standard Profil...
Verified Trusted Call Girls Adugodi💘 9352852248  Good Looking standard Profil...Verified Trusted Call Girls Adugodi💘 9352852248  Good Looking standard Profil...
Verified Trusted Call Girls Adugodi💘 9352852248 Good Looking standard Profil...
 
Captivating Charm: Exploring Marseille's Hillside Villas with Our 3D Architec...
Captivating Charm: Exploring Marseille's Hillside Villas with Our 3D Architec...Captivating Charm: Exploring Marseille's Hillside Villas with Our 3D Architec...
Captivating Charm: Exploring Marseille's Hillside Villas with Our 3D Architec...
 
B. Smith. (Architectural Portfolio.).pdf
B. Smith. (Architectural Portfolio.).pdfB. Smith. (Architectural Portfolio.).pdf
B. Smith. (Architectural Portfolio.).pdf
 
The history of music videos a level presentation
The history of music videos a level presentationThe history of music videos a level presentation
The history of music videos a level presentation
 
CBD Belapur Individual Call Girls In 08976425520 Panvel Only Genuine Call Girls
CBD Belapur Individual Call Girls In 08976425520 Panvel Only Genuine Call GirlsCBD Belapur Individual Call Girls In 08976425520 Panvel Only Genuine Call Girls
CBD Belapur Individual Call Girls In 08976425520 Panvel Only Genuine Call Girls
 
(AISHA) Ambegaon Khurd Call Girls Just Call 7001035870 [ Cash on Delivery ] P...
(AISHA) Ambegaon Khurd Call Girls Just Call 7001035870 [ Cash on Delivery ] P...(AISHA) Ambegaon Khurd Call Girls Just Call 7001035870 [ Cash on Delivery ] P...
(AISHA) Ambegaon Khurd Call Girls Just Call 7001035870 [ Cash on Delivery ] P...
 
Editorial design Magazine design project.pdf
Editorial design Magazine design project.pdfEditorial design Magazine design project.pdf
Editorial design Magazine design project.pdf
 
Best VIP Call Girls Noida Sector 47 Call Me: 8448380779
Best VIP Call Girls Noida Sector 47 Call Me: 8448380779Best VIP Call Girls Noida Sector 47 Call Me: 8448380779
Best VIP Call Girls Noida Sector 47 Call Me: 8448380779
 
Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...
Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...
Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...
 
Dubai Call Girls Pro Domain O525547819 Call Girls Dubai Doux
Dubai Call Girls Pro Domain O525547819 Call Girls Dubai DouxDubai Call Girls Pro Domain O525547819 Call Girls Dubai Doux
Dubai Call Girls Pro Domain O525547819 Call Girls Dubai Doux
 
Booking open Available Pune Call Girls Nanded City 6297143586 Call Hot India...
Booking open Available Pune Call Girls Nanded City  6297143586 Call Hot India...Booking open Available Pune Call Girls Nanded City  6297143586 Call Hot India...
Booking open Available Pune Call Girls Nanded City 6297143586 Call Hot India...
 
SCRIP Lua HTTP PROGRACMACION PLC WECON CA
SCRIP Lua HTTP PROGRACMACION PLC  WECON CASCRIP Lua HTTP PROGRACMACION PLC  WECON CA
SCRIP Lua HTTP PROGRACMACION PLC WECON CA
 
Cheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk Gurgaon
Cheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk GurgaonCheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk Gurgaon
Cheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk Gurgaon
 
Presentation.pptx about blender what is blender
Presentation.pptx about blender what is blenderPresentation.pptx about blender what is blender
Presentation.pptx about blender what is blender
 
young call girls in Pandav nagar 🔝 9953056974 🔝 Delhi escort Service
young call girls in Pandav nagar 🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Pandav nagar 🔝 9953056974 🔝 Delhi escort Service
young call girls in Pandav nagar 🔝 9953056974 🔝 Delhi escort Service
 
Cosumer Willingness to Pay for Sustainable Bricks
Cosumer Willingness to Pay for Sustainable BricksCosumer Willingness to Pay for Sustainable Bricks
Cosumer Willingness to Pay for Sustainable Bricks
 
Chapter 19_DDA_TOD Policy_First Draft 2012.pdf
Chapter 19_DDA_TOD Policy_First Draft 2012.pdfChapter 19_DDA_TOD Policy_First Draft 2012.pdf
Chapter 19_DDA_TOD Policy_First Draft 2012.pdf
 

Sustainability In Government - Bim Webinar

  • 1. Introduction and welcome Keith Snook Information Systems Development Manager BRE
  • 2. Building Information Modelling (BIM) Task Group Update Richard Lane Departmental Support & Training Development 25 September 2013
  • 3. Background • Lack of Clear Communication of Client Needs • Incorrect Assumptions or Miscommunication within the Supply Chain • Rework / Recreation of Data • Inability for Project Participants to ‘Speak the Same Language’ • Poor or No Information Management • Limited Reuse or Standardisation 35%
  • 4. Background Government Construction Strategy Mandatory requirement for Level 2 BIM “15-20% cost and carbon reduction on all centrally procured government construction projects within the current parliament”
  • 5. What is BIM? • “A collection of value-creating best practices, underpinned by a culture of collaboration and the exchange of structured asset data” Building Information Modelling
  • 6. What is BIM? Building a consistent, collaborative industry, with clear and open communication Information of high-quality is procured to support business outcomes Modelling the design increases efficiency, enabling simulation & analysis
  • 7. What is BIM? “A whole-estate, whole-life approach”
  • 9. 24 September 2013 BIM in the MoJ Bill Davis Ministry of Justice
  • 10. Who are we? • One of the largest government departments • Employ around 76,000 people • Annual budget of approximately £8 billion • Around 500 courts and tribunals, and 133 prisons in England and Wales – overall, nearly 2,000 properties of widely varying size and complexity
  • 11. Why us? Government target is for level 2 BIM implementation on all Government projects by 2016. New MOJ Strategic Alliance Framework was tendered in early 2012. It is for a period of up to 6 years. So we needed to include BIM in the tender exercise. Our target is to have all projects at level 2 by summer 2013.
  • 12. Benefits Based on: • Palace Exchange, Enfield • Festival Place, Basingstoke • Endeavour House, Stansted • Terminal 5, Heathrow • Portcullis House, London • St. Bart’s Hospital, London From: Government Construction Client Group Building Information Modelling (BIM) Working Party Strategy Paper March 2011 CookhamWood
  • 13. Initial Design Tender Design & Construct Operate Full None Knowledge 1st FM Provider Time BIM Traditional 2nd FM Provider 3rd FM Provider Life Cycle Phase BIM Traditional Keeping the information alive
  • 14. What have we done?
  • 15. What data do we need? Key decision points Data drop points • Drop 1 – Initial project data to inform Outline Business Case (OBC) submission. • Drop 2a – lnitial project proposals based on preferred option from OBC to form tender brief • Drop 2b – Tenderer’s initial project proposals. • Drop 3 – Selected constructor’s developed project proposals to agree the contract maximum price (AMP) and to inform Full Business Case (FBC) when required. • Drop 4 – Practical completion (Certificate A) information. • Drop 5 – Post occupancy validation.
  • 16. Lessons learned & POE feed back into Standards Committee BIM – MOJ Value Model Current standards are modelled / depicted as standard components Cell Office Classroom Roof Elements arranged to produce required product. QA is inbuilt as required standards are embedded and automatically report non compliance. Virtual construction results in fewer mistakes and less waste Appointed Constructor works up Developed Project Proposals in open book environment and submits Agreed Maximum Price Standard components build up required output for drop 2A tender package Delivery Benchmarking (more product for our money) MoJ Standard Component Library Tenderers prepare drop 2B tender More timely handover information Escort costs Client fees, design only Client fees Client risk Profit, supply chain Overhead, supply chain Profit, main Overhead, main Prelims, C Prelims, B Prelims, A Design development contingency Constructor fees Constructor risk Non-productive Product
  • 17. Cookham Wood • Provision of 179 room accommodation unit for the Youth Justice Board together with an associated education facility at Cookham Wood Young Offender Institution in Rochester, Kent. • Approximate out-turn value of £20million • Designers model and COBie 2a drop issued with tender package. • Tenderers had to return a developed model, 2D cuts and COBie drop 2b. • Constructor appointed: Interserve • Commencement Agreement signed 19/10/12, Start on site November 2012
  • 20. Drop 4 Pilot HMP Oakwood (New Energy Centre only) Some modelling done during construction, but full model now developed and back populated with drop 4 data. From this we will extract a COBie file. This will be used to develop how we get the information into our CAFM and Asset Management systems. Together with work that is being done on the Cookham Wood project and on our handover procedures in general, this will inform what information we need (and in what format) for the drop 4 for all future projects.
  • 21. Moving toward business as usual HMP Winchester - New build kitchen HMP Leeds - Improved reception facilities HMP The Mount - New houseblock & kitchen and some refurbishment works HMP Durham – New healthcare Other BIM projects now coming on line:
  • 23. What’s in it for us? BIM Component Standardisation Reduced Cost Build off-site Better & timely handover information Better stakeholder involvement through early 3D visualisation Stakeholder feedback Less re-work Virtual constructionBetter design co- ordination Better programming Better cost data Carbon reduction Clash detection Performance modelling Better productivity Compliance checking Improved H&S
  • 24. Lessons learned so far A lessons learned (so far) document is available at www.bimtaskgroup.org The following are some of the major findings: • You have to fully understand your own processes and what information you need at each stage. • There is great benefit to be had from using the model for early stakeholder engagement. • IT security may be an issue. It certainly was, and continues to be, for MOJ. • If you issue a model for tender purposes you need to decide what you expect your tenderers to do with it – and make sure they know! • The Contractors need to manage the tender process differently, and use different resources. They need more forward planning and adherence to dates. A six week tender period was seen to be too short. • Contractors are keen to engage • BIM will change the way you operate your projects and you have to put appropriate systems and training in place. • Although there seems to be a lot of experience of BIM amongst Contractors, there is very little experience of COBie.
  • 25. What do we need? In the short term: • Better interoperability between software packages including ‘no data loss’ IFC files from native model(s) and seamless transfer of models from one software package to another. • Better COBie data extraction tools. • COBie data interrogation/analysis tools. In the longer term: • Seamless transfer from model to CAFM software or perhaps the model becoming the CAFM tool - a ‘through life’ BIM package! • More cost effective ways of getting models of our existing estate.
  • 27. Alan Windley BSc Nomitech (on behalf of ForgeTrack Ltd) 07812 771860 alan@nomitech.eu “Achieving BIM Level 2 - Estimating, 4D, 5D & Value Engineering”
  • 28. A LITTLE REMINDER Level 2 BIM           A managed 3D environment held in separate discipline 'BIM' tools with data attached. Commercial data will be managed by enterprise resource planning software and integrated by proprietary interfaces or bespoke middleware. This level of BIM may utilise 4D construction sequencing and 5D cost information. The Government’s BIM Strategy Paper calls for the industry to achieve Level 2 BIM by 2016. Sounds scary!!
  • 29. DISPELLING MYTHS • It is another fad • It does not affect me • Its just for Architects • Its just CAD on steroids • Its CAD with 3D • Just to look pretty • It is only for buildings • The Architect doesn’t put all the information in • It is no use to owners/clients • It is no use to contractors • It is no use for FM • It is none of the above!
  • 30. FROM BIM TO BILL TO BID TO BUILD Early Phase / Feasibility Utilise outline or incomplete models Standard Method Bills With Associated Prices Associate Costs & Descriptions – Multiple Formats Combining Parametric Assemblies With Models Value Engineering, optimisation Multiple Models Different BIM Authoring Tools - IFC Project Planning & Risk Synchronised Integration with Project Planning & Risk Analysis Not just for buildingsInfrastructure Projects Design Cost Schedule
  • 31. From an early stage Model to CostOS (5D) To Primavera Project Planning To Synchro (4D) Highlighting Transparency, Synchronisation & Collaboration
  • 32. Not just for buildings
  • 33. The model, provided by the Architect, is loaded into the estimating solution. Cost data, (local, historical, commercial) is associated with each model element. In this case, BCIS cost data.
  • 34. If, as you would expect in the early stages of a project, if not much detail regarding specification is available, then value options can be explored by associating parametric cost assemblies.
  • 35. A fully measured and costed estimate/cost plan is produced directly from the model, and in this example, classified (WBS) in a simple BCIS, industry standard elemental structure. The relationship is maintained between the model entity and cost and clearly visualised.
  • 36. The estimate or cost plan in more detail, including productivities. The information can be grouped by any of the traditional industry standard formats eg, BCIS Elements, SMM7, NRM (New Rules Of Measurement)
  • 37. The estimate is then synchronised with the project planning solution to create the initial project plan, fully cost loaded
  • 38. The initial project plan now created directly from the estimate.
  • 39. The project plan is then then synchronised with the construction sequencing solution. Once here the schedule was linked to the model and hence by ‘sliding’ the red vertical dotted timeline, you will next see the model being built in line with the schedule and also the ‘Earned Value’ at each construction stage.
  • 40. We have now started to collaborate 4 important aspects ie, the design, the cost, the schedule and the construction sequence which all started from an early stage (feasibility) design.
  • 41. We can now visualise the potential sequence of construction and make any required adjustments. In other words, ‘virtually’ constructing the project now rather than making costly and wasteful mistakes onsite. In other words ‘will the project work?’
  • 42. Any required adjustments are made and then simply synchronised back to the project plan.
  • 43. And in turn, synchronised back to the estimate so that any effect on cost can be clearly highlighted and hence ultimately delivering the most cost effective project. Reduce waste – Reduce Cost – Create Transparency - Collaborate
  • 44. Finally… the estimate, produced from a model, synchronised with the plan and the construction sequence can be synchronised with Risk Management solutions such as Crystal Ball to run Monte Carlo simulation techniques. Reducing and mitigating risk! In the example shown, a very high value Oil & Gas project.
  • 45. Case Study – The Ionion Highway
  • 46. • The Ionion Highway and E65 were 2 major build and operate initiatives, operating under a Public Private Partnership (around 2,700 miles long) • Total budget 3 Billion Euros • Winning consortium ‘Nea Odos’ to build, operate and receive tolls for 30 years • The consortium invested 1.15 Billion euros into the programme. • The principles, practices and knowledge used on the Ionion Highway then used to support the E65 programme bid. The Project
  • 47. • Nomitech CostOS was chosen to undertake the cost estimating of all the bridges and culverts for both highways • Smart assemblies/cost models developed to model the different types of bridges to be used. The Concept
  • 48. • Engineering optimized by modifying bridge cost assemblies • Options quickly assessed • Budgets producing in in double quick time • Accurate budgets produced from typical first principles The budgets were synchronised with the Project plan! What Happened?
  • 49. •Large European banks funding •Accurate & realistic schedule and cashflow demanded •CostOS integrated with planning solution Problem! •2 major bridges on the critical path were causing delays •Concerns raised •Purchase another bridge? Why The Importance?
  • 50. • Design options were evaluated early – from a cost and a scheduling viewpoint • Informed decisions made • On closer analysis, by collaborating design, cost and schedule, the total cost was far less than the original 60 days delay would have caused! • All knowledge retained for the subsequent E65 project. Let the Tolls begin! ££££ The Result!
  • 51. BIM – Bringing the whole professional team together – collaborating from the earliest concept stage to final completion and complete life cycle. Reduce waste – Reduce Cost – Create Transparency - Collaborate It’s not that scary - really In conclusion….
  • 52. Thanks & Acknowledgements Information and tools used during this webinar CostOS Bim-enabled Estimating – Nomitech Ltd Cost Data - BCIS Synchro 4D Sequencing – Synchro Oracle Primavera P6 – ForgeTrack Ltd Oracle Crystal Ball Risk Management – Oracle Model designed and provided by – Metz Architects Integrated Process Facilitated by - Fulcro Ltd Project courtesy of – Dudley College

Hinweis der Redaktion

  1. https://www.gov.uk/government/publications/government-construction-strategy -Government construction strategy mandate (Level 2 BIM) = collection of best-practice based on current technology, contractual arrangements, work flows. The future promises even greater returns, once key questions have been addressed. Hypothesis “ Government as a client can derive significant improvements in cost, value and carbon performance through the use of open sharable asset information” Hypothesis Criteria Description Valuable The overall aim is to maximise client value by increasing benefits at little or no extra cost. Understandable The approach is to be presented in an understandable learning package suitable for different types of government asset procurers. Generally Applicable The approach is equally applicable to buildings and infrastructure, whether large and small new build and where possible existing structures. Non-proprietary All requirements are non-proprietary as to applications and as to the required formats of the deliverables. Competitive Wherever possible there are at least two solutions or methods available so as to minimise market influence in terms of anti competitive clauses. Open Wherever possible, low-cost methods are to be made available to allow all stakeholders to participate, irrespective of size and experience, so as to minimise barriers to involvement. Verifiable All contractual expectations are documented with transparent and testable measurement of pass / fail. Compliant Measurement of LC/Carbon/Sustainability/etc is published to GB, EU and ISO standards. Implementable The approach is self funding by the client and the industry Timescale The approach is phased in over 5 years. Pull (Government) Be good a buying data (as well as assets and services) Do it consistently Leave the “How” to the Supply Chain Push (Supply Chain) Early Warning to Mobilise Training Methods & Documentation
  2. ‘ Building’ suggests a focus only on Architecture projects, but BIM applies equally to Civil and Infrastructure assets ‘ Modelling’ has a narrow definition which infers 3D CAD, BIM is easier to understand if you consider M to stand for ‘Management’ BIM is not a ‘binary’ solution you switch on or off but a collection of best practices which, on their own, don’t constitute BIM. It is possible that you have already implemented some of these best practices to drive efficiency and to reduce risk / cost, this project is aimed at building-out that collection of best practices, based on standard approaches, shared experience across government and department-specific priorities, challenges & working practices. Implementation can be phased, bringing-in specific value-creating changes on a project by project basis. Enabling us to make better decisions. BIM can not be done in isolation, if your projects operate largely as before, but with the addition of a ‘BIM Guy’ or a ‘BIM Computer’, you are likely not doing BIM
  3. B uilding  a consistent, collaborative industry, with clear and open communication Adoption of common standard processes and documents Transitioning from an adversarial to collaborative culture Early involvement from all key stakeholders, including end users, operators, contractors using a 'language' they can understand Develop & reuse standard designs, share best practice across clients (within NHS and with other departments e.g. DIO) I nformation of high-quality is procured  to support business outcomes Define information needs based on the desired outcomes at each stage of the project Implement appropriate information and quality assurance roles and processes Establish the supporting contractual arrangements (using existing forms of contract and without impacting existing liabilities) Leverage standard data formats and technical collaboration tools Determining how will be received, stored, validated & used to support the business (during the capital project and asset lifecycle)  M odelling the design increases efficiency, enabling simulation & analysis Leverage efficient 3d modelling to develop designs  and automate complex tasks (e.g. clash detection) Federate designs from all disciplines e.g. Architectural, Structural, Building Services etc. 4D: Map model to program, include temporary works to optimise sequencing 5D: Associate cost/take information to the model Simulate the completed project before it is built (e.g. visual walkthroughs, thermal / energy analysis, people movements / evacuations etc.)
  4. The Ministry of Justice is one of the largest government departments, employing around 76,000 people, with a budget of approximately £9 billion. Each year millions of people use our services including 500 courts and tribunals, and 133 prisons in England and Wales – around 2,000 properties an all.