SlideShare ist ein Scribd-Unternehmen logo
1 von 18
PROGRAM EVALUATION REVIEW TECHNIQUE




             VINCI VIVEKA
VINCI VIVEKA

•A statistical tool, used in project management

• It is designed to analyze and represent the tasks
involved in completing a given project.

•A decision making tool designed to save time in
achieving end objectives.

•It is one of the techniques of scientific management.

•It was developed for the U.S. Navy Special Projects
Office in 1957 to support the U.S. Navy's Polaris
nuclear submarine project
PERT
PERT chart is a tool that facilitates decision making.

PERT is a method to analyze the involved tasks in completing
a given project, especially the time needed to complete each
task and to identify the minimum time needed to complete the
total project.

PERT is valuable to manage where multiple tasks are
occurring simultaneously to reduce idleness.

For this it takes into consideration three factors:
  1. Time
   2. Resources
    3. Technical Performance Specifications.
                  VINCI VIVEKA
TERMINOLOGY
PERT Event: a point that marks the start or completion of one or
more activities. It consumes no time and uses no resources. When it
marks the completion of one or more tasks, it is not “reached” (does
not occur) until all of the activities leading to that event have been
completed.eg- start and finish*

Predecessor Event: an event that immediately precedes some other
event without any other events intervening. An event can have
multiple predecessor events and can be the predecessor of multiple
events. Eg: A and b are predecessor of C*

Successor Event: an event that immediately follows some other
event without any other intervening events. An event can have
multiple successor events and can be the successor of multiple
events.eg: D is the successor of C*.

*(refer Gantt Diagram)



                          VINCI VIVEKA
Optimistic Time (O): the minimum possible time required to
accomplish a task, assuming everything proceeds better than
is normally expected

Pessimistic Time (P): the maximum possible time
required to accomplish a task, assuming everything goes
wrong (but excluding major catastrophes).

Most Likely Time (M): the best estimate of the time
required to accomplish a task, assuming everything proceeds
as normal.

Expected Time (TE): the best estimate of the time
required to accomplish a task, accounting for the fact that
things don't always proceed as normal (the implication being
that the expected time is the average time the task would
require if the task were repeated on a number of occasions
over an extended period of time).

               TE = (O + 4M + P) ÷ 6
                       VINCI VIVEKA
PERT Activity: the actual performance of a task which
consumes time and requires resources (such as
labor, materials, space, machinery). It can be understood as
representing the time, effort, and resources required to move
from one event to another. A PERT activity cannot be
performed until the predecessor event has occurred. Eg:
A,B,C,D*

Float or Slack is a measure of the excess time and
resources available to complete a task. It is the amount of time
that a project task can be delayed without causing a delay in
any subsequent tasks (free float) or the whole project (total
float). Positive slack would indicate ahead of schedule; negative
slack would indicate behind schedule; and zero slack would
indicate on schedule.

Critical Path: the longest possible continuous pathway taken
from the initial event to the terminal event. It determines the
total calendar time required for the project; and, therefore, any
time delays along the critical path will delay the reaching of the
terminal event by at least the same amount.
                          VINCI VIVEKA
Activity   Predecessor                Time Estimates            Te


                              O                 M        P


   A       -             2                  8       6        4.00


   B       -             3                  5       9        5.33


   C       A,B           4                  5       7        5.17


   D       C             4                  6       10       6.13




                 TE = (O + 4M + P) ÷ 6

                             VINCI VIVEKA
Gantt Chart
( According to the table in previous chart)




     Activity On Node (AON) Diagram
              VINCI VIVEKA
EARLY     DURATION   EARLY
       START                FINISH




                   A
          LATE    SLACK      LATE
         START              FINISH




VINCI VIVEKA
In order to determine these following are the steps-
EARLY FINISH [ EF ]
Formula for EF= ES + Duration.

Duration can be taken from the table it is represented by Te
For the first activity i.e. START Early Start [ ES] =0,




                                                                          VINCI VIVEKA
As start is a pert event its duration is zero.
Therefore, for START
ES=0 Duration =0 ; EF= ES + Duration => EF=0

EF of the predecessor event becomes ES of its successor.

Therefore, for A
ES=0 Duration=4, EF=4

For B,( as A&B both have same Predecessor i.e. START hence B----
ES=0 Duration= 5.33 EF=5.33

For C ( as A&B both are C predecessor hence we take the one with higher
value)
ES=5.33 Duration=5.17 EF=10.5
For D,
ES= 10.5 Duration=6.13 EF=16.63

For FINISH [as FINISH is a pert event its duration is zero]
ES=16.63 Duration=0 EF=16.63

LATE START [ LS ]
Formula LS=LF – DURATION

In this we start with FINISH, as it is the last activity. LATE FINISH [LF ] of
FINISH = its EF.
Therefore, LF=EF=16.63 Duration= 0 LS=LF- Duration , Hence LS=16.63

For D, [ LS of successor event becomes LF for its predecessor event ]
LF=16.63 Duration=6.13 LS=10.5

For C,
LF=10.5 Duration=5.17 LS=5.33

For B,
LF=5.33 Duration=5.33 LS= 0

VINCI VIVEKA
For A, [ as C is also its successor ]
LF=5.33 Duration=4 LS=1.33

For START [as A&B both are successor but we take here one with the lower
value ]
LF=1.33 Duration =0 LS=1.33




                                                                                   VINCI VIVEKA
SLACK
To determine the critical path we have to find whether any activity has a slack.
Activity on the critical path has slack zero.
Formula SLACK=LF-EF or SLACK= LS-ES

For START                                     For C
LS=1.33 ES=0 SLACK=1.33                       LS=5.33     ES=5.33 SLACK=0

For A                                         For D
LS=1.33 ES=0 SLACK=1.33                       LS= 10.5 ES=10.5        SLACK=0

For B                                         For FINISH
LS=5.33 ES=0 SLACK=5.33                        LS=1.33 ES=0         SLACK=1.33
ES=0        DUR=0         EF=0          ES=0        DUR=4      EF=4
              START                                     A
LS=1.33    SLACK=1.33     LF=1.33       LS=0      SLACK=1.33   LF=5.33




ES=0         DUR=5.33      EF=5.33     ES=5.33     DUR=5.17    EF=10.5

                 B                                     C

LS=0       SLACK=5.33      LF=5.33     LS=5.33     SLACK=0     LF=10.5



 ES=10.5     DUR=6.13       EF=16.33   ES=16.63    DUR=0       EF=16.63
                  D                                  FINISH
 LS=10.5     SLACK=0        LF=16.63   LS=16.63   SLACK=1.33   LF=16.63


                      VINCI VIVEKA
CRITICAL PATH
It is the longest continous -path way. There can be
more than one critical path or the path can change.
In the drawn Gantt diagram there are two
alternatives to reach FINISH and adding there
SLACK timing-
START+A+C+D+FINISH=3.99
START+B+C+D+FINISH=7.99

Hence , the path START+B+C+D+FINISH is the
longest it is the critical path, shown in the diagram
in the next slide.

                        VINCI VIVEKA
VINCI VIVEKA




CRITICAL PATH
    [ in red ink ]
•PERT chart explicitly defines and makes visible
dependencies (precedence relationships) between the
work breakdown structure (commonly WBS) elements

•PERT facilitates identification of the critical path and
makes this visible

•PERT facilitates identification of early start, late start,
and slack for each activity

•PERT provides for potentially reduced project duration
due to better understanding of dependencies leading to
improved overlapping of activities and tasks where
feasible.
•The large amount of project data can be organized &
presented in diagram for use in decision making.
                        VINCI VIVEKA
DISADVANTAGES:
•There can be potentially hundreds or thousands of activities and
individual dependency relationships

•PERT is not easily scalable for smaller projects

•The network charts tend to be large and unwieldy requiring
several pages to print and requiring special size paper

•The lack of a timeframe on most PERT/CPM charts makes it
harder to show status although colours can help (e.g., specific
colour for completed nodes)

•When the PERT/CPM charts become unwieldy, they are no
longer used to manage the project.

                   VINCI VIVEKA
VINCI VIVEKA
Prepared by:
VINCI VIVEKA
M.ED SCHOLAR [2012-2013]
ST. XAVIER’S COLLEGE OF EDUCATION, PATNA.
vivekavinci@gmail.com
REFERENCE:
http://en.wikipedia.org/wiki/Program_Evaluation_and_Review_Technique

Weitere ähnliche Inhalte

Was ist angesagt?

Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisAsif Sultan Razu
 
PERT & Gantt Chart
PERT & Gantt Chart PERT & Gantt Chart
PERT & Gantt Chart Anju George
 
Program evaluation review technique (pert)
Program evaluation review technique (pert)Program evaluation review technique (pert)
Program evaluation review technique (pert)tomeh
 
PERT and CPM
PERT and CPMPERT and CPM
PERT and CPMstudent
 
PLANNING IN MANAGEMENT,DEFINITION CHARACTERISTICS, IMPORTANCE AND LIMITATIONS
PLANNING IN MANAGEMENT,DEFINITION CHARACTERISTICS, IMPORTANCE AND LIMITATIONSPLANNING IN MANAGEMENT,DEFINITION CHARACTERISTICS, IMPORTANCE AND LIMITATIONS
PLANNING IN MANAGEMENT,DEFINITION CHARACTERISTICS, IMPORTANCE AND LIMITATIONSAMALDASKH
 
Plannning and Types of planning
Plannning and Types of planningPlannning and Types of planning
Plannning and Types of planningEr Garima Patil
 
The Gantt Chart
The Gantt ChartThe Gantt Chart
The Gantt ChartNicola2903
 
Cost-Benefit Analysis
Cost-Benefit AnalysisCost-Benefit Analysis
Cost-Benefit AnalysisSakshi Sharma
 
ORGANIZATION
ORGANIZATIONORGANIZATION
ORGANIZATIONdsakhil7
 
Cost benefit analysis
Cost benefit analysisCost benefit analysis
Cost benefit analysisHarsh Rastogi
 

Was ist angesagt? (20)

Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network Analysis
 
Planning
PlanningPlanning
Planning
 
Ppt of planning
Ppt of planningPpt of planning
Ppt of planning
 
PERT & Gantt Chart
PERT & Gantt Chart PERT & Gantt Chart
PERT & Gantt Chart
 
Program evaluation review technique (pert)
Program evaluation review technique (pert)Program evaluation review technique (pert)
Program evaluation review technique (pert)
 
Pert
PertPert
Pert
 
Planning..
Planning..Planning..
Planning..
 
Gantt chart
Gantt chartGantt chart
Gantt chart
 
PERT and CPM
PERT and CPMPERT and CPM
PERT and CPM
 
PLANNING IN MANAGEMENT,DEFINITION CHARACTERISTICS, IMPORTANCE AND LIMITATIONS
PLANNING IN MANAGEMENT,DEFINITION CHARACTERISTICS, IMPORTANCE AND LIMITATIONSPLANNING IN MANAGEMENT,DEFINITION CHARACTERISTICS, IMPORTANCE AND LIMITATIONS
PLANNING IN MANAGEMENT,DEFINITION CHARACTERISTICS, IMPORTANCE AND LIMITATIONS
 
Plannning and Types of planning
Plannning and Types of planningPlannning and Types of planning
Plannning and Types of planning
 
crashing of project
crashing of project crashing of project
crashing of project
 
The Gantt Chart
The Gantt ChartThe Gantt Chart
The Gantt Chart
 
Gantt chart
Gantt chartGantt chart
Gantt chart
 
Planning process, types of planning
Planning process, types of planningPlanning process, types of planning
Planning process, types of planning
 
project management concepts
project management conceptsproject management concepts
project management concepts
 
Cost-Benefit Analysis
Cost-Benefit AnalysisCost-Benefit Analysis
Cost-Benefit Analysis
 
ORGANIZATION
ORGANIZATIONORGANIZATION
ORGANIZATION
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
 
Cost benefit analysis
Cost benefit analysisCost benefit analysis
Cost benefit analysis
 

Andere mochten auch

Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERTPulchowk Campus
 
Pert and its applications
Pert and its applicationsPert and its applications
Pert and its applicationsAmrit Mty
 
PERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursingPERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursingHariasha
 
TID Chapter 6 Introduction To Microsoft Project
TID Chapter 6 Introduction To Microsoft ProjectTID Chapter 6 Introduction To Microsoft Project
TID Chapter 6 Introduction To Microsoft ProjectWanBK Leo
 
Project Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert ChartProject Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert ChartVinay Prajapati
 
The gantt Chart
The gantt Chart The gantt Chart
The gantt Chart Nicola2903
 
Lecture5---Gantt Chart
Lecture5---Gantt ChartLecture5---Gantt Chart
Lecture5---Gantt Chartdanishrafiq
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project managementRahul Dubey
 
Paper_26338_handout_2010_0
Paper_26338_handout_2010_0Paper_26338_handout_2010_0
Paper_26338_handout_2010_0Cee Cee Feng
 
Controlling
ControllingControlling
ControllingKumar
 
Chapter 10 controlling
Chapter 10   controllingChapter 10   controlling
Chapter 10 controllingArgon David
 
Advertisements
AdvertisementsAdvertisements
AdvertisementsSagar
 
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...yang lu
 
PM scheduling techniques
PM scheduling techniquesPM scheduling techniques
PM scheduling techniquesNazish khalid
 
Programme evaluation and review technique (pert)
Programme evaluation and review technique (pert)Programme evaluation and review technique (pert)
Programme evaluation and review technique (pert)Anupam Kumar
 

Andere mochten auch (20)

Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERT
 
Pert and its applications
Pert and its applicationsPert and its applications
Pert and its applications
 
PERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursingPERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursing
 
Gantt
GanttGantt
Gantt
 
TID Chapter 6 Introduction To Microsoft Project
TID Chapter 6 Introduction To Microsoft ProjectTID Chapter 6 Introduction To Microsoft Project
TID Chapter 6 Introduction To Microsoft Project
 
Project Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert ChartProject Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert Chart
 
The gantt Chart
The gantt Chart The gantt Chart
The gantt Chart
 
Lecture5---Gantt Chart
Lecture5---Gantt ChartLecture5---Gantt Chart
Lecture5---Gantt Chart
 
Project Management PERT and CPM
Project Management PERT and CPMProject Management PERT and CPM
Project Management PERT and CPM
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
Paper_26338_handout_2010_0
Paper_26338_handout_2010_0Paper_26338_handout_2010_0
Paper_26338_handout_2010_0
 
Controlling
ControllingControlling
Controlling
 
Chapter 10 controlling
Chapter 10   controllingChapter 10   controlling
Chapter 10 controlling
 
Advertisements
AdvertisementsAdvertisements
Advertisements
 
Ali Pert
Ali PertAli Pert
Ali Pert
 
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
 
Project management
Project managementProject management
Project management
 
PM scheduling techniques
PM scheduling techniquesPM scheduling techniques
PM scheduling techniques
 
Gantt pert
Gantt pertGantt pert
Gantt pert
 
Programme evaluation and review technique (pert)
Programme evaluation and review technique (pert)Programme evaluation and review technique (pert)
Programme evaluation and review technique (pert)
 

Ähnlich wie Pert- program evaluation and review technique

Critical path method (CPM).pptx
Critical path method (CPM).pptxCritical path method (CPM).pptx
Critical path method (CPM).pptxHimanshuKaklotar1
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)chandkec
 
Day 2 Revision
Day 2 RevisionDay 2 Revision
Day 2 RevisionJoyce Wong
 
Section 6 :Project Scheduling: PERT/CPM (1)
Section 6 :Project Scheduling: PERT/CPM (1)Section 6 :Project Scheduling: PERT/CPM (1)
Section 6 :Project Scheduling: PERT/CPM (1)Zakaria Hasaneen
 
PERT CPM.pptggfyufydtyfydyfyydyhffhhhydydyfu
PERT CPM.pptggfyufydtyfydyfyydyhffhhhydydyfuPERT CPM.pptggfyufydtyfydyfyydyhffhhhydydyfu
PERT CPM.pptggfyufydtyfydyfyydyhffhhhydydyfuinfinitepestcontrol
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1adeelmunir158
 
Cm ch4 scheduling
Cm ch4 schedulingCm ch4 scheduling
Cm ch4 schedulingAhmed Gamal
 
Critical path and fw bw pass
Critical path and fw bw passCritical path and fw bw pass
Critical path and fw bw passMartin Bailey
 
Program Evaluation And Review Technique
Program Evaluation And Review TechniqueProgram Evaluation And Review Technique
Program Evaluation And Review TechniqueSimonRobertson
 
Lu3 – the planning phase lectures
Lu3 – the planning phase lecturesLu3 – the planning phase lectures
Lu3 – the planning phase lecturesjillmitchell8778
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysistutor2u
 
The Network Diagram and Critical Path
The Network Diagram and Critical PathThe Network Diagram and Critical Path
The Network Diagram and Critical Pathdmdk12
 
Chapter seven lecture slides
Chapter seven lecture slidesChapter seven lecture slides
Chapter seven lecture slidesWilliam Perkins
 

Ähnlich wie Pert- program evaluation and review technique (20)

Critical path method (CPM).pptx
Critical path method (CPM).pptxCritical path method (CPM).pptx
Critical path method (CPM).pptx
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)
 
Day 2 Revision
Day 2 RevisionDay 2 Revision
Day 2 Revision
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 
Section 6 :Project Scheduling: PERT/CPM (1)
Section 6 :Project Scheduling: PERT/CPM (1)Section 6 :Project Scheduling: PERT/CPM (1)
Section 6 :Project Scheduling: PERT/CPM (1)
 
PERT CPM.pptggfyufydtyfydyfyydyhffhhhydydyfu
PERT CPM.pptggfyufydtyfydyfyydyhffhhhydydyfuPERT CPM.pptggfyufydtyfydyfyydyhffhhhydydyfu
PERT CPM.pptggfyufydtyfydyfyydyhffhhhydydyfu
 
Cpm and pert
Cpm and pertCpm and pert
Cpm and pert
 
Cpm pert
Cpm pertCpm pert
Cpm pert
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
 
Cm ch4 scheduling
Cm ch4 schedulingCm ch4 scheduling
Cm ch4 scheduling
 
Critical path and fw bw pass
Critical path and fw bw passCritical path and fw bw pass
Critical path and fw bw pass
 
Program Evaluation And Review Technique
Program Evaluation And Review TechniqueProgram Evaluation And Review Technique
Program Evaluation And Review Technique
 
Lu3 – the planning phase lectures
Lu3 – the planning phase lecturesLu3 – the planning phase lectures
Lu3 – the planning phase lectures
 
Project Management Techniques
Project Management TechniquesProject Management Techniques
Project Management Techniques
 
Gantt PERT and CPM
Gantt PERT and CPMGantt PERT and CPM
Gantt PERT and CPM
 
cpmpertmy (1)
cpmpertmy (1)cpmpertmy (1)
cpmpertmy (1)
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysis
 
The Network Diagram and Critical Path
The Network Diagram and Critical PathThe Network Diagram and Critical Path
The Network Diagram and Critical Path
 
Chapter seven lecture slides
Chapter seven lecture slidesChapter seven lecture slides
Chapter seven lecture slides
 

Mehr von Vinci Viveka

Cognitive development bruner
Cognitive development brunerCognitive development bruner
Cognitive development brunerVinci Viveka
 
chief minister’s girls cycle scheme-front pages
chief minister’s girls cycle scheme-front pageschief minister’s girls cycle scheme-front pages
chief minister’s girls cycle scheme-front pagesVinci Viveka
 
chief minister girls cycle scheme-suggestion, reccommendation Chief minister ...
chief minister girls cycle scheme-suggestion, reccommendation Chief minister ...chief minister girls cycle scheme-suggestion, reccommendation Chief minister ...
chief minister girls cycle scheme-suggestion, reccommendation Chief minister ...Vinci Viveka
 
chief ministers girls cycle scheme-analysis of data ch 04
chief ministers girls cycle scheme-analysis of data ch 04chief ministers girls cycle scheme-analysis of data ch 04
chief ministers girls cycle scheme-analysis of data ch 04Vinci Viveka
 
chief minister girls cycle scheme-review of related literature
chief minister girls cycle scheme-review of related literaturechief minister girls cycle scheme-review of related literature
chief minister girls cycle scheme-review of related literatureVinci Viveka
 
chief minister girls cycle scheme-introduction and conceptual framework
chief minister girls cycle scheme-introduction and conceptual frameworkchief minister girls cycle scheme-introduction and conceptual framework
chief minister girls cycle scheme-introduction and conceptual frameworkVinci Viveka
 
research methodology- Chief MInister Girls Cycle Scheme
research methodology- Chief MInister Girls Cycle Schemeresearch methodology- Chief MInister Girls Cycle Scheme
research methodology- Chief MInister Girls Cycle SchemeVinci Viveka
 
Bibliography- research thesis
Bibliography- research thesisBibliography- research thesis
Bibliography- research thesisVinci Viveka
 
Computer assisted instruction
Computer assisted instructionComputer assisted instruction
Computer assisted instructionVinci Viveka
 
Concept attainment strategy
Concept attainment strategyConcept attainment strategy
Concept attainment strategyVinci Viveka
 
Marxism philosophy
Marxism philosophyMarxism philosophy
Marxism philosophyVinci Viveka
 
Research practicum
Research practicumResearch practicum
Research practicumVinci Viveka
 

Mehr von Vinci Viveka (15)

Cognitive development bruner
Cognitive development brunerCognitive development bruner
Cognitive development bruner
 
chief minister’s girls cycle scheme-front pages
chief minister’s girls cycle scheme-front pageschief minister’s girls cycle scheme-front pages
chief minister’s girls cycle scheme-front pages
 
chief minister girls cycle scheme-suggestion, reccommendation Chief minister ...
chief minister girls cycle scheme-suggestion, reccommendation Chief minister ...chief minister girls cycle scheme-suggestion, reccommendation Chief minister ...
chief minister girls cycle scheme-suggestion, reccommendation Chief minister ...
 
chief ministers girls cycle scheme-analysis of data ch 04
chief ministers girls cycle scheme-analysis of data ch 04chief ministers girls cycle scheme-analysis of data ch 04
chief ministers girls cycle scheme-analysis of data ch 04
 
chief minister girls cycle scheme-review of related literature
chief minister girls cycle scheme-review of related literaturechief minister girls cycle scheme-review of related literature
chief minister girls cycle scheme-review of related literature
 
chief minister girls cycle scheme-introduction and conceptual framework
chief minister girls cycle scheme-introduction and conceptual frameworkchief minister girls cycle scheme-introduction and conceptual framework
chief minister girls cycle scheme-introduction and conceptual framework
 
Finance
FinanceFinance
Finance
 
research methodology- Chief MInister Girls Cycle Scheme
research methodology- Chief MInister Girls Cycle Schemeresearch methodology- Chief MInister Girls Cycle Scheme
research methodology- Chief MInister Girls Cycle Scheme
 
Bibliography- research thesis
Bibliography- research thesisBibliography- research thesis
Bibliography- research thesis
 
Appendix
AppendixAppendix
Appendix
 
Computer assisted instruction
Computer assisted instructionComputer assisted instruction
Computer assisted instruction
 
Concept attainment strategy
Concept attainment strategyConcept attainment strategy
Concept attainment strategy
 
Marxism philosophy
Marxism philosophyMarxism philosophy
Marxism philosophy
 
Research practicum
Research practicumResearch practicum
Research practicum
 
Marxism
MarxismMarxism
Marxism
 

Kürzlich hochgeladen

Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfAdmir Softic
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwaitdaisycvs
 
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 MonthsIndeedSEO
 
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableCall Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableSeo
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityEric T. Tung
 
Falcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon investment
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...daisycvs
 
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...amitlee9823
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...amitlee9823
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...amitlee9823
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Centuryrwgiffor
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...rajveerescorts2022
 
Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000
Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000
Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000dlhescort
 
Business Model Canvas (BMC)- A new venture concept
Business Model Canvas (BMC)-  A new venture conceptBusiness Model Canvas (BMC)-  A new venture concept
Business Model Canvas (BMC)- A new venture conceptP&CO
 
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...allensay1
 
PHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPanhandleOilandGas
 
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort ServiceMalegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort ServiceDamini Dixit
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...Aggregage
 

Kürzlich hochgeladen (20)

Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
 
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
 
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableCall Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
Falcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business Growth
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investors
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
 
Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000
Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000
Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000
 
Business Model Canvas (BMC)- A new venture concept
Business Model Canvas (BMC)-  A new venture conceptBusiness Model Canvas (BMC)-  A new venture concept
Business Model Canvas (BMC)- A new venture concept
 
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
 
PHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation Final
 
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort ServiceMalegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 

Pert- program evaluation and review technique

  • 1. PROGRAM EVALUATION REVIEW TECHNIQUE VINCI VIVEKA
  • 2. VINCI VIVEKA •A statistical tool, used in project management • It is designed to analyze and represent the tasks involved in completing a given project. •A decision making tool designed to save time in achieving end objectives. •It is one of the techniques of scientific management. •It was developed for the U.S. Navy Special Projects Office in 1957 to support the U.S. Navy's Polaris nuclear submarine project
  • 3. PERT PERT chart is a tool that facilitates decision making. PERT is a method to analyze the involved tasks in completing a given project, especially the time needed to complete each task and to identify the minimum time needed to complete the total project. PERT is valuable to manage where multiple tasks are occurring simultaneously to reduce idleness. For this it takes into consideration three factors: 1. Time 2. Resources 3. Technical Performance Specifications. VINCI VIVEKA
  • 4. TERMINOLOGY PERT Event: a point that marks the start or completion of one or more activities. It consumes no time and uses no resources. When it marks the completion of one or more tasks, it is not “reached” (does not occur) until all of the activities leading to that event have been completed.eg- start and finish* Predecessor Event: an event that immediately precedes some other event without any other events intervening. An event can have multiple predecessor events and can be the predecessor of multiple events. Eg: A and b are predecessor of C* Successor Event: an event that immediately follows some other event without any other intervening events. An event can have multiple successor events and can be the successor of multiple events.eg: D is the successor of C*. *(refer Gantt Diagram) VINCI VIVEKA
  • 5. Optimistic Time (O): the minimum possible time required to accomplish a task, assuming everything proceeds better than is normally expected Pessimistic Time (P): the maximum possible time required to accomplish a task, assuming everything goes wrong (but excluding major catastrophes). Most Likely Time (M): the best estimate of the time required to accomplish a task, assuming everything proceeds as normal. Expected Time (TE): the best estimate of the time required to accomplish a task, accounting for the fact that things don't always proceed as normal (the implication being that the expected time is the average time the task would require if the task were repeated on a number of occasions over an extended period of time). TE = (O + 4M + P) ÷ 6 VINCI VIVEKA
  • 6. PERT Activity: the actual performance of a task which consumes time and requires resources (such as labor, materials, space, machinery). It can be understood as representing the time, effort, and resources required to move from one event to another. A PERT activity cannot be performed until the predecessor event has occurred. Eg: A,B,C,D* Float or Slack is a measure of the excess time and resources available to complete a task. It is the amount of time that a project task can be delayed without causing a delay in any subsequent tasks (free float) or the whole project (total float). Positive slack would indicate ahead of schedule; negative slack would indicate behind schedule; and zero slack would indicate on schedule. Critical Path: the longest possible continuous pathway taken from the initial event to the terminal event. It determines the total calendar time required for the project; and, therefore, any time delays along the critical path will delay the reaching of the terminal event by at least the same amount. VINCI VIVEKA
  • 7. Activity Predecessor Time Estimates Te O M P A - 2 8 6 4.00 B - 3 5 9 5.33 C A,B 4 5 7 5.17 D C 4 6 10 6.13 TE = (O + 4M + P) ÷ 6 VINCI VIVEKA
  • 8. Gantt Chart ( According to the table in previous chart) Activity On Node (AON) Diagram VINCI VIVEKA
  • 9. EARLY DURATION EARLY START FINISH A LATE SLACK LATE START FINISH VINCI VIVEKA
  • 10. In order to determine these following are the steps- EARLY FINISH [ EF ] Formula for EF= ES + Duration. Duration can be taken from the table it is represented by Te For the first activity i.e. START Early Start [ ES] =0, VINCI VIVEKA As start is a pert event its duration is zero. Therefore, for START ES=0 Duration =0 ; EF= ES + Duration => EF=0 EF of the predecessor event becomes ES of its successor. Therefore, for A ES=0 Duration=4, EF=4 For B,( as A&B both have same Predecessor i.e. START hence B---- ES=0 Duration= 5.33 EF=5.33 For C ( as A&B both are C predecessor hence we take the one with higher value) ES=5.33 Duration=5.17 EF=10.5
  • 11. For D, ES= 10.5 Duration=6.13 EF=16.63 For FINISH [as FINISH is a pert event its duration is zero] ES=16.63 Duration=0 EF=16.63 LATE START [ LS ] Formula LS=LF – DURATION In this we start with FINISH, as it is the last activity. LATE FINISH [LF ] of FINISH = its EF. Therefore, LF=EF=16.63 Duration= 0 LS=LF- Duration , Hence LS=16.63 For D, [ LS of successor event becomes LF for its predecessor event ] LF=16.63 Duration=6.13 LS=10.5 For C, LF=10.5 Duration=5.17 LS=5.33 For B, LF=5.33 Duration=5.33 LS= 0 VINCI VIVEKA
  • 12. For A, [ as C is also its successor ] LF=5.33 Duration=4 LS=1.33 For START [as A&B both are successor but we take here one with the lower value ] LF=1.33 Duration =0 LS=1.33 VINCI VIVEKA SLACK To determine the critical path we have to find whether any activity has a slack. Activity on the critical path has slack zero. Formula SLACK=LF-EF or SLACK= LS-ES For START For C LS=1.33 ES=0 SLACK=1.33 LS=5.33 ES=5.33 SLACK=0 For A For D LS=1.33 ES=0 SLACK=1.33 LS= 10.5 ES=10.5 SLACK=0 For B For FINISH LS=5.33 ES=0 SLACK=5.33 LS=1.33 ES=0 SLACK=1.33
  • 13. ES=0 DUR=0 EF=0 ES=0 DUR=4 EF=4 START A LS=1.33 SLACK=1.33 LF=1.33 LS=0 SLACK=1.33 LF=5.33 ES=0 DUR=5.33 EF=5.33 ES=5.33 DUR=5.17 EF=10.5 B C LS=0 SLACK=5.33 LF=5.33 LS=5.33 SLACK=0 LF=10.5 ES=10.5 DUR=6.13 EF=16.33 ES=16.63 DUR=0 EF=16.63 D FINISH LS=10.5 SLACK=0 LF=16.63 LS=16.63 SLACK=1.33 LF=16.63 VINCI VIVEKA
  • 14. CRITICAL PATH It is the longest continous -path way. There can be more than one critical path or the path can change. In the drawn Gantt diagram there are two alternatives to reach FINISH and adding there SLACK timing- START+A+C+D+FINISH=3.99 START+B+C+D+FINISH=7.99 Hence , the path START+B+C+D+FINISH is the longest it is the critical path, shown in the diagram in the next slide. VINCI VIVEKA
  • 15. VINCI VIVEKA CRITICAL PATH [ in red ink ]
  • 16. •PERT chart explicitly defines and makes visible dependencies (precedence relationships) between the work breakdown structure (commonly WBS) elements •PERT facilitates identification of the critical path and makes this visible •PERT facilitates identification of early start, late start, and slack for each activity •PERT provides for potentially reduced project duration due to better understanding of dependencies leading to improved overlapping of activities and tasks where feasible. •The large amount of project data can be organized & presented in diagram for use in decision making. VINCI VIVEKA
  • 17. DISADVANTAGES: •There can be potentially hundreds or thousands of activities and individual dependency relationships •PERT is not easily scalable for smaller projects •The network charts tend to be large and unwieldy requiring several pages to print and requiring special size paper •The lack of a timeframe on most PERT/CPM charts makes it harder to show status although colours can help (e.g., specific colour for completed nodes) •When the PERT/CPM charts become unwieldy, they are no longer used to manage the project. VINCI VIVEKA
  • 18. VINCI VIVEKA Prepared by: VINCI VIVEKA M.ED SCHOLAR [2012-2013] ST. XAVIER’S COLLEGE OF EDUCATION, PATNA. vivekavinci@gmail.com REFERENCE: http://en.wikipedia.org/wiki/Program_Evaluation_and_Review_Technique