SlideShare ist ein Scribd-Unternehmen logo
1 von 30
Analysis of FHWA Example 5 Bridge at Tacoma
by
Lemuria Pathfinders
Supratik Bose
Sathvika Meenakshisundaram
Sharath Chandra Ranganath
Sandhya Ravindran
Amy Ruby
May 2014
Outline
Introduction
Motivation and Objectives
Response Spectra and Scaling of GM
Modeling Assumptions
Analysis Procedure and Results
Conclusions and Recommendations
CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 2
Introduction
Introduction
CSEE DEPARTMENT, UNIVERSITY AT BUFFALO
Plan View of the Eight Span Steel Girder Continuous Bridge
4
Details of Bridge
Objectives
Objectives
CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 6
 Primary objective was to evaluate the bridge response using various
analysis procedures given MCEER/ATC 49 report
 Comparison of the results obtained from various analysis
 Critical assessment of performance of the bridge based on those results
 Recommendations for improvement of performance during future
seismic event
Modeling
Assumptions
Modeling Assumptions
CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 8
SAP 2000 Model
 2D Bridge model was developed in SAP 2000 v. 16.0.1 program
 Uniformly distributed load (DL) on superstructure = 9.3 kips/feet
 Superstructure : Equivalent concrete cross-section with same area
and inertia of composite structure
 Centroid of the superstructure taken 8 feet above the top of the pier to
account for bearing height
Modeling Assumptions…
CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 9
Modeling of Substructure: Piers
 Modelled as three 2D frame
elements
 Foundation spring stiffness
attached to the bottommost
nodes of the piers
 Pinned piers: node 6XX transfers
shears but longitudinal moment
(M3) released
 Sliding piers: Only transverse
shear transferred and M3, V2
released
Relationship between actual pier and stick model
Details of sliding bearings
Modeling Assumptions…
CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 10
Foundation springs and abutment
 Foundation stiffness calculated in
FHWA- example was used as the soil
conditions are similar
 Abutments modelled as simple nodes
with vertical translation and torsional
rotation restraint and transverse
equivalent spring
Spring Foundation Model
Abutment Support Model
k11 2.66 × 104 Kip/ft
k22 7.847 × 105 Kip/ft
k33 1.70× 104 Kip/ft
k44 7.96 × 107 Kip-ft/rad
k55 4.785 × 106 Kip-ft/rad
K66 9.628 × 107 Kip-ft/rad
Response Spectra
and Scaling
Response Spectra
CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 12
Response Spectra of the Site
 MCEER/ATC 49 report suggests 2 level of earthquakes for analysis
Maximum Credible Earthquake Expected Earthquake
Scaling of GMs
CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 13
Selected GMs
 Selected ground motions are scaled such that
 Geometric mean spectra never lies below 15% of design spectra
 Average ratio of mean and target spectra not less than unity over
the period range of significance.
Selected Ground Motions
No Ground Motion NGA# Scale M Year Station
MCE
1
Cape
Mendocino
828 1.0 7.01 1992 Petrolia
2 North Ridge 960 1.0 6.69 1994 Canyon Country-W Lost Cany
3 Loma-Prieto 753 1.0 6.93 1989 Corralitos
EE
1 North Ridge 1048 0.38 6.69 1994 North Ridge 17645 Saticoy St
2 Imperial Valley 181 0.47 6.53 1979 El-Centro #6
3 Kobe Japan 1116 0.72 6.90 1995 Shin-Osake
Analysis Procedure
and Results
Analysis
CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 15
Uniform Load Method
 Maximum displacement (vs-max) obtained by assigning Po of 1 kip/ft,
Pe, K and Tm calculated based on these equations
max
o
s
P L
K
v 


sup
16011.2
18271.2
long super piers long
trans er piers trans
W W W kips
W W W kips


  
  
2m
W
T
Kg
 e d
W
P C
L
 
Direction of applied load
Transverse Longitudinal
Max displacement (ft) 0.037 0.144
Lateral Stiffness (kip/ft) 36808.5 9631.17
Time Period (s) 0.78 1.43
Hazard level EE MCE EE MCE
Cd 0.2486 0.8825 0.133 0.47
Pe (kip/ft) 3.281 11.65 1.5386 5.437
Base Shear (kips) 4542.22 16124.33 2129.49 7525.26
Maximum Moment (kips-feet) 5698.64 20234.42 2704.91 9558.44
Max Displacement after Pe (ft) 0.124 0.442 0.228 0.775
Analysis…
CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 16
Multimode Method
 Modal analysis was carried out in SAP 2000 program
Mode
Period
(s)
Cumulative Modal Mass Participation
Mode of
VibrationTranslational Rotational
UX UY UZ RX RY RZ
1.00 1.54 0.57 0.00 0.00 0.00 0.00 0.06 Longitudinal
2.00 0.88 0.00 0.59 0.00 0.02 0.00 0.00 Transverse
3.00 0.75 0.05 0.00 0.00 0.00 0.00 0.54 Torsion
Direction Analytical Calculation (kip/feet) Modal Analysis (kip/feet)
Longitudinal (Local X) 8484 8277
Transverse (Local Y) 28793 28927
Comparison of bridge stiffness obtained analytically and from modal analysis
Analysis…
CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 17
Multimode Method…
 Modes were combined using CQC method and the directional effects
were considered by 100%-40% combination rule
 Ambient damping of 5% was considered
Results obtained from multimode response spectrum analysis at MCE
MCE Pier No.
Longitudinal Transverse
Axial
ForceShear Moment Shear Moment
1L+0.4T
Pier 1 993.8 37327.5 221. 9 114662.1 55.6
Pier 2 1322.1 68960.6 2330.0 125658.3 32.4
Pier 3 699.8 35743.1 2301.7 159105.4 64.9
Pier 4 437.2 20518.7 2693.0 186280.0 26.3
1T+0.4L
Pier 1 1413.3 53082.6 1587.5 79300.8 90.6
Pier 2 2325.7 124775.3 1573.5 84425.7 48.9
Pier 3 1310.0 71479.4 1372.0 91656.7 101.2
Pier 4 1092.5 51280.3 1078.0 74358.5 10.5
Analysis…
CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 18
Pushover Analysis
 Fiber PMM hinges were used to define non linearity
 Simplified bilinear behaviour assumed for concrete and steel
 Triangular loading pattern was used
 Individual piers: Hinges only at the bottom of the members
 Entire structure: Hinges considered at the base and the neck of the
trapezoidal part of the piers
Stiffness (kips/feet)
Longitudinal Transverse
Pushover Analytical Pushover Analytical
70 feet pier 5872 5022 1728 1259
50 feet pier 8100 7841 3375 2983
Stiffness (kips/feet) Chord Radial
Bridge 10500 10331 28889 29521
Comparison of stiffness obtained analytically and calculated from pushover analysis
Analysis…
CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 19
Pushover Curves…
70 feet - Transverse
0
500
1000
1500
2000
2500
0 5 10 15 20 25
LateralForce(kips)
Displacement (inches)
0
5 10
5
1 106
1.5 10
6
0 0.005 0.01 0.015 0.02 0.025
Moment(kips-inches)
Rotation (radians)
0
200
400
600
800
1000
0 5 10 15 20 25
LatrealForce(kips)
Displacement (inches)
0
1 105
2 10
5
3 10
5
4 10
5
5 10
5
0 0.005 0.01 0.015 0.02 0.025
Moment(kips-inches)
Rotation (radians)
70 feet - Longitudinal
0
5000
10000
15000
20000
25000
30000
0 2 4 6 8
LateralForce(kips)
Displacement (feet)
Entire bridge - Transverse
0
1000
2000
3000
4000
5000
0 2 4 6 8
LateralForce(kips)
Displacement (feet)
Entire bridge - Longitudinal
Analysis…
CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 20
Linear Elastic Time History Analysis (THA)
 Linear elastic THA carried out both in NONLIN and SAP 2000
Hazard
Level
Base Shear (kips) Displacement (feet)
Long Trans Long Trans
NON SAP NON SAP NON SAP NON SAP
MCE 8426.75 12130 20743.9 32080 0.81 1.16 0.70 1.33
EE 4051.63 5731 6803.53 10250 0.39 0.34 0.23 0.35
Comparison of maximum results from SAP 2000 and NONLIN
 EE has lesser demand on the structure and hence impose smaller
displacement on the piers as compared to MCE
 20% difference in results obtained from SAP2000 and NONLIN.
Analysis…
CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 21
Non Linear SDoF Time History Analysis (THA)
 Nonlinear SDoF THA was carried out in NONLIN
 Simplified bilinear behaviour was assumed with K2 = 0
 Yield strength obtained from pushover analysis
Hazard
Level
GM
Global X Linear Global X
Nonlinear
Global Y
Linear
Global Y
Nonlinear
Shear
(kips)
Disp.
(feet)
Shear
(kips)
Disp.
(feet)
Shear
(kips)
Disp.
(feet)
Shear
(kips)
Disp.
(feet)
MCE
NGA 753-FN 2757 0.27 2757 0.27 7356 0.25 7356 0.25
NGA 753-FP 6905 0.67 4250 0.72 20409 0.69 20409 0.69
NGA 828-FN 4165 0.40 4165 0.40 18876 0.64 18876 0.64
EE
NGA 1048-FP 3105 0.30 3105 0.30 5007 0.17 5007 0.17
NGA 1116-FP 2297 0.22 2297 0.22 5644 0.19 5644 0.19
NGA 1116-FP 4052 0.39 4052 0.39 6282 0.21 6282 0.21
Comparison of results from linear and nonlinear analysis in NONLIN
Analysis…
CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 22
Non Linear MDoF Time History Analysis
 Same nonlinear model as used in pushover analysis
 Newmark Beta direct integration procedure was used
Maximum displacement response during NR-GM Hysteretic begaviour during NR-GM
Analysis…
CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 23
Non Linear MDoF Time History Analysis
 Lesser demands observed at EE for linear and nonlinear analysis.
 Structure remain within the elastic range at EE hazard level
 In MCE for some of the GMs, the structure reached the inelastic zone
 Maximum displacement recorded from MDoF analysis in SAP 2000
program was higher compared to SDoF analysis in NONLIN.
Max
Moment
(kips-ft)
Shear (kips) Disp. (ft)
Trans Long Long Trans Long Trans
P1 86000 27670 754 1858 0.175 0.234
P2 101300 47930 1150 1959 0.460 0.280
P3 104700 36240 666 1584 0.439 0.363
P4 104900 28210 617 1634 0.331 0.369
Max
Moment
(kips-ft)
Shear (kips) Disp. (ft)
Trans Long Long Trans Long Trans
P1 141500 53740 1728 3403 0.699 0.647
P2 145800 56600 1413 3275 0.853 0.801
P3 140700 51320 2064 2325 0.915 1.106
P4 147300 43820 1824 2462 1.305 1.124
Expected Earthquake Maximum Credible Earthquake
Analysis…
CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 24
Capacity Spectrum Analysis
2
1
2 1
2
v n
C c
L y
gF S V
C C
B W
 
  
 
BL obtained from Table 5.4.1.1-1 of MCEER/ATC 49
MCE
y θpH 0.25CCH Modified CC Modified Vn
Long Trans Long Trans Long Trans Long Trans Long Trans
Operational 13.7 2.3 1.75 1.75 4.2 25.3 1.1 2.6 33722 33722
Life Safety 5.4 0.9 1.75 1.75 4.2 25.3 2.6 - 13174 -
Hazard Level
Operational Life Safety
Long Trans Long Trans
EE SAFE
MCE UNSAFE UNSAFE UNSAFE SAFE
Analysis Results…
CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 25
Comparison of results of various analysis
 Shear forces and displacements obtained are in close agreement
 Bending moment in some of the cases are different and the possible
reason is the irregular curved geometry of the bridge
Max
Expected earthquake Maximum Credible earthquake
Shear
(kips)
Moment
(kips-feet)
Displacement
(feet)
Shear
(kips)
Moment
(kips-feet)
Displacement
(feet)
Long Trans Trans Long Long Trans Long Trans Trans Long Long Trans
ULM 793 624 45482 45988 0.24 0.12 2217 2802 161485 162499 0.85 0.44
MM 761 657 52668 35293 0.18 0.15 2326 2693 186280 124783 0.64 0.51
Elastic
THA
672 2058 127500 42417 0.34 0.35 2850 7810 495833 152500 1.33 1.16
Inelastic
THA
1150 1959 104900 47930 0.46 0.37 2064 3403 147300 116600 1.31 1.12
Comparison of results from various analysis procedure
Analysis Results…
CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 26
Performance of the bridge
 Demands obtained from linear analysis were divided by R-factor
1 ( 1)
1.25
B B
S
T
R R R
T
    RB obtained from Table 4.7.1 of MCEER/ATC 49
Analysis
Expected Earthquake Maximum Credible Earthquake
Longitudinal Transverse Longitudinal Transverse
LS OP LS OP LS OP LS OP
ULM Safe Safe Safe Safe Unsafe Unsafe Safe Unsafe
MM Safe Safe Safe Safe Unsafe Unsafe Unsafe Unsafe
Elastic THA Safe Unsafe Safe Safe Safe Unsafe Safe Unsafe
Inelastic THA Unsafe Unsafe Unsafe Unsafe Unsafe Unsafe Unsafe Unsafe
Therefore it can be concluded that performance of bridge remains
operational in case of EE but leads to possible failure in MCE.
Recommendations
Recommendations
CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 28
Recommendation for improvement of bridge performance at MCE:
 Seismic isolation bearings can be used to accommodate the excess
displacement demands during high seismic event.
 Sliding friction pendulum bearings can be a good alternative to those
used in the present model to ensure better performance at MCE.
 Use of dampers along with the isolators can also improve the
performance of the bridge at large earthquakes.
 All the piers can be converted to sliding piers to accommodate the
high displacement demands expected at MCE
Thank You
References
CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 30
CSI., 2009. Integrated Software for Structural Analysis and Design, SAP 2000. CSI.
FHWA-SA-97-010. Seismic Design of Bridges, Design Example No. 5, Nine Span Viaduct Steel
Girder Bridge.
BERGER/ABAM Engineers. Federal Highway Administration. 1996.
MCEER/ATC 49. Recommended LFRD Guidelines for the Seismic Design of Highway Bridges, Part
I: Specifications. ATC MCEER Joint Venture. 2003
MCEER/ATC 49. Recommended LFRD Guidelines for the Seismic Design of Highway Bridges, Part
II: Commentary and Appendices. ATC MCEER Joint Venture. 2003
Bruneau, M., Uang, C. M. and Sabelli, R. 2010. Ductile Design of Steel Structures. Second Edition
Lawson, R.S., Vance, V. and Krawinkler, H. 1994. Nonlinear static pushover analysis: Why, When
and How?.
Proceedings of 5th US National Conference on Earthquake Engineering, July 10-14, 1994, Chicago.
Chopra, A. K. (2012). Earthquake Response of Linear Systems. Dynamics of Structures: Theory and
Applications to Earthquake Engineering (). Upper Saddle River, NJ: Pearson Education Inc.
Villaverde, R., 2009. Fundamental Concepts of Earthquake Engineering.

Weitere ähnliche Inhalte

Was ist angesagt?

Static load testing and prediction bengt h. fellenius
Static load testing  and prediction   bengt h. felleniusStatic load testing  and prediction   bengt h. fellenius
Static load testing and prediction bengt h. felleniuscfpbolivia
 
Unmanned Airplane Autopilot Tuning
Unmanned Airplane Autopilot TuningUnmanned Airplane Autopilot Tuning
Unmanned Airplane Autopilot TuningIJERA Editor
 
PR3 MODIS_VIIRS_Geo_Error_Trend_with_Kalman_Filter.pptx
PR3 MODIS_VIIRS_Geo_Error_Trend_with_Kalman_Filter.pptxPR3 MODIS_VIIRS_Geo_Error_Trend_with_Kalman_Filter.pptx
PR3 MODIS_VIIRS_Geo_Error_Trend_with_Kalman_Filter.pptxgrssieee
 
2009 Dransfield - conforming falcon gravity and the global gravity anomaly
2009 Dransfield - conforming falcon gravity and the global gravity anomaly2009 Dransfield - conforming falcon gravity and the global gravity anomaly
2009 Dransfield - conforming falcon gravity and the global gravity anomalyBrett Johnson
 
Velocity Models Difference
Velocity Models DifferenceVelocity Models Difference
Velocity Models DifferenceShah Naseer
 
“The strong attraction of gravity at Geoscience Australia” (Richard Lane, Geo...
“The strong attraction of gravity at Geoscience Australia” (Richard Lane, Geo...“The strong attraction of gravity at Geoscience Australia” (Richard Lane, Geo...
“The strong attraction of gravity at Geoscience Australia” (Richard Lane, Geo...Richard Lane
 
Aircraft Design for Boeing Phantom Works
Aircraft Design for Boeing Phantom WorksAircraft Design for Boeing Phantom Works
Aircraft Design for Boeing Phantom Workssimoalb88
 
The static loading test bengt h. fellenius
The  static loading test   bengt h. felleniusThe  static loading test   bengt h. fellenius
The static loading test bengt h. felleniuscfpbolivia
 
Spacecraft Formation Flying Navigation via a Novel Wireless Final
Spacecraft Formation Flying Navigation via a Novel Wireless FinalSpacecraft Formation Flying Navigation via a Novel Wireless Final
Spacecraft Formation Flying Navigation via a Novel Wireless FinalShu Ting Goh
 
2011 rowbiomnews04
2011 rowbiomnews042011 rowbiomnews04
2011 rowbiomnews04izar23sv
 
MCR: USLI 2009-2010, UAHuntsville
MCR: USLI 2009-2010, UAHuntsvilleMCR: USLI 2009-2010, UAHuntsville
MCR: USLI 2009-2010, UAHuntsvilleSeiya Shimizu
 
Modeling of Flexible and Rigid Pavements under Aircraft Loading
Modeling of Flexible and Rigid Pavements under Aircraft LoadingModeling of Flexible and Rigid Pavements under Aircraft Loading
Modeling of Flexible and Rigid Pavements under Aircraft LoadingElise M. Mansour
 
Synthesis of Research Project-FlappingWing
Synthesis of Research Project-FlappingWingSynthesis of Research Project-FlappingWing
Synthesis of Research Project-FlappingWingKarthik Ch
 
Experimental and numerical stress analysis of a rectangular wing structure
Experimental and numerical stress analysis of a rectangular wing structureExperimental and numerical stress analysis of a rectangular wing structure
Experimental and numerical stress analysis of a rectangular wing structureLahiru Dilshan
 
Airbus Civil Aircraft Design
Airbus Civil Aircraft DesignAirbus Civil Aircraft Design
Airbus Civil Aircraft DesignBaba Kakkar
 
C3 Corvette chassis upgrade 2021
C3 Corvette chassis upgrade 2021C3 Corvette chassis upgrade 2021
C3 Corvette chassis upgrade 2021William Harbin
 
Gyroscope JAA QUESTIONS
Gyroscope JAA QUESTIONSGyroscope JAA QUESTIONS
Gyroscope JAA QUESTIONSquimrubau
 
Action Trajectory Reconstruction for Controlling of Vehicle Using Sensors
Action Trajectory Reconstruction for Controlling of Vehicle Using SensorsAction Trajectory Reconstruction for Controlling of Vehicle Using Sensors
Action Trajectory Reconstruction for Controlling of Vehicle Using SensorsIOSR Journals
 

Was ist angesagt? (20)

Static load testing and prediction bengt h. fellenius
Static load testing  and prediction   bengt h. felleniusStatic load testing  and prediction   bengt h. fellenius
Static load testing and prediction bengt h. fellenius
 
Unmanned Airplane Autopilot Tuning
Unmanned Airplane Autopilot TuningUnmanned Airplane Autopilot Tuning
Unmanned Airplane Autopilot Tuning
 
PR3 MODIS_VIIRS_Geo_Error_Trend_with_Kalman_Filter.pptx
PR3 MODIS_VIIRS_Geo_Error_Trend_with_Kalman_Filter.pptxPR3 MODIS_VIIRS_Geo_Error_Trend_with_Kalman_Filter.pptx
PR3 MODIS_VIIRS_Geo_Error_Trend_with_Kalman_Filter.pptx
 
2009 Dransfield - conforming falcon gravity and the global gravity anomaly
2009 Dransfield - conforming falcon gravity and the global gravity anomaly2009 Dransfield - conforming falcon gravity and the global gravity anomaly
2009 Dransfield - conforming falcon gravity and the global gravity anomaly
 
Velocity Models Difference
Velocity Models DifferenceVelocity Models Difference
Velocity Models Difference
 
“The strong attraction of gravity at Geoscience Australia” (Richard Lane, Geo...
“The strong attraction of gravity at Geoscience Australia” (Richard Lane, Geo...“The strong attraction of gravity at Geoscience Australia” (Richard Lane, Geo...
“The strong attraction of gravity at Geoscience Australia” (Richard Lane, Geo...
 
Aircraft Design for Boeing Phantom Works
Aircraft Design for Boeing Phantom WorksAircraft Design for Boeing Phantom Works
Aircraft Design for Boeing Phantom Works
 
The static loading test bengt h. fellenius
The  static loading test   bengt h. felleniusThe  static loading test   bengt h. fellenius
The static loading test bengt h. fellenius
 
FINAL PAPER
FINAL PAPERFINAL PAPER
FINAL PAPER
 
Spacecraft Formation Flying Navigation via a Novel Wireless Final
Spacecraft Formation Flying Navigation via a Novel Wireless FinalSpacecraft Formation Flying Navigation via a Novel Wireless Final
Spacecraft Formation Flying Navigation via a Novel Wireless Final
 
2011 rowbiomnews04
2011 rowbiomnews042011 rowbiomnews04
2011 rowbiomnews04
 
MCR: USLI 2009-2010, UAHuntsville
MCR: USLI 2009-2010, UAHuntsvilleMCR: USLI 2009-2010, UAHuntsville
MCR: USLI 2009-2010, UAHuntsville
 
Modeling of Flexible and Rigid Pavements under Aircraft Loading
Modeling of Flexible and Rigid Pavements under Aircraft LoadingModeling of Flexible and Rigid Pavements under Aircraft Loading
Modeling of Flexible and Rigid Pavements under Aircraft Loading
 
Synthesis of Research Project-FlappingWing
Synthesis of Research Project-FlappingWingSynthesis of Research Project-FlappingWing
Synthesis of Research Project-FlappingWing
 
Experimental and numerical stress analysis of a rectangular wing structure
Experimental and numerical stress analysis of a rectangular wing structureExperimental and numerical stress analysis of a rectangular wing structure
Experimental and numerical stress analysis of a rectangular wing structure
 
Mpc final report
Mpc final reportMpc final report
Mpc final report
 
Airbus Civil Aircraft Design
Airbus Civil Aircraft DesignAirbus Civil Aircraft Design
Airbus Civil Aircraft Design
 
C3 Corvette chassis upgrade 2021
C3 Corvette chassis upgrade 2021C3 Corvette chassis upgrade 2021
C3 Corvette chassis upgrade 2021
 
Gyroscope JAA QUESTIONS
Gyroscope JAA QUESTIONSGyroscope JAA QUESTIONS
Gyroscope JAA QUESTIONS
 
Action Trajectory Reconstruction for Controlling of Vehicle Using Sensors
Action Trajectory Reconstruction for Controlling of Vehicle Using SensorsAction Trajectory Reconstruction for Controlling of Vehicle Using Sensors
Action Trajectory Reconstruction for Controlling of Vehicle Using Sensors
 

Ähnlich wie Presentation CIE619

Final Presentation_25 May
Final Presentation_25 MayFinal Presentation_25 May
Final Presentation_25 MayKallol Barua
 
Modellistica Lagrangiana in ISAC Torino - risultati e nuovi sviluppi
Modellistica Lagrangiana in ISAC Torino - risultati e nuovi sviluppiModellistica Lagrangiana in ISAC Torino - risultati e nuovi sviluppi
Modellistica Lagrangiana in ISAC Torino - risultati e nuovi sviluppiARIANET
 
An Enhanced Control Technique for the Elimination of Residual
An Enhanced Control Technique for the Elimination of ResidualAn Enhanced Control Technique for the Elimination of Residual
An Enhanced Control Technique for the Elimination of ResidualDoç.Dr. Selçuk MISTIKOĞLU
 
ÖNCEL AKADEMİ: İSTANBUL DEPREMİ
ÖNCEL AKADEMİ: İSTANBUL DEPREMİÖNCEL AKADEMİ: İSTANBUL DEPREMİ
ÖNCEL AKADEMİ: İSTANBUL DEPREMİAli Osman Öncel
 
Multiphase Flow Modeling and Simulation: HPC-Enabled Capabilities Today and T...
Multiphase Flow Modeling and Simulation: HPC-Enabled Capabilities Today and T...Multiphase Flow Modeling and Simulation: HPC-Enabled Capabilities Today and T...
Multiphase Flow Modeling and Simulation: HPC-Enabled Capabilities Today and T...inside-BigData.com
 
Presentation (Pagkratios Chitas)
Presentation (Pagkratios Chitas)Presentation (Pagkratios Chitas)
Presentation (Pagkratios Chitas)Pagkratios Chitas
 
Seismic Assessment of Existing Bridge Using OPENSEES
Seismic Assessment of Existing Bridge Using OPENSEESSeismic Assessment of Existing Bridge Using OPENSEES
Seismic Assessment of Existing Bridge Using OPENSEESIJMER
 
Dynamic Analysis And Optimization Of Fatigue Crack Propagation Using Full Fac...
Dynamic Analysis And Optimization Of Fatigue Crack Propagation Using Full Fac...Dynamic Analysis And Optimization Of Fatigue Crack Propagation Using Full Fac...
Dynamic Analysis And Optimization Of Fatigue Crack Propagation Using Full Fac...IJERA Editor
 
Attitude Control of Satellite Test Setup Using Reaction Wheels
Attitude Control of Satellite Test Setup Using Reaction WheelsAttitude Control of Satellite Test Setup Using Reaction Wheels
Attitude Control of Satellite Test Setup Using Reaction WheelsA. Bilal Özcan
 
Proposal Wide Blower No.1 & 2 with inverter
Proposal Wide Blower No.1 & 2  with inverterProposal Wide Blower No.1 & 2  with inverter
Proposal Wide Blower No.1 & 2 with inverterRidhoIrawan12
 
TENSILE TEST REPORT
TENSILE TEST REPORTTENSILE TEST REPORT
TENSILE TEST REPORTmusadoto
 
DESIGN AND OPTIMIZATION OF “KLANN MECHANISM” USING OCTO-POD ROBOT
DESIGN AND OPTIMIZATION OF “KLANN MECHANISM”  USING OCTO-POD ROBOTDESIGN AND OPTIMIZATION OF “KLANN MECHANISM”  USING OCTO-POD ROBOT
DESIGN AND OPTIMIZATION OF “KLANN MECHANISM” USING OCTO-POD ROBOTNikhil Koli
 
Nir_pres_Hagana_v1
Nir_pres_Hagana_v1Nir_pres_Hagana_v1
Nir_pres_Hagana_v1Nir Morgulis
 
Design And Analysis of Test Rig for Rudder Pedal
Design And Analysis of Test Rig for Rudder PedalDesign And Analysis of Test Rig for Rudder Pedal
Design And Analysis of Test Rig for Rudder PedalIRJET Journal
 
A New geotechnical method for natural slope exploration and analysis
A New geotechnical method for natural slope exploration and analysisA New geotechnical method for natural slope exploration and analysis
A New geotechnical method for natural slope exploration and analysisRasika Athapaththu
 
Final course project report
Final course project reportFinal course project report
Final course project reportKaggwa Abdul
 

Ähnlich wie Presentation CIE619 (20)

Final Presentation_25 May
Final Presentation_25 MayFinal Presentation_25 May
Final Presentation_25 May
 
FYP Structure.pdf
FYP Structure.pdfFYP Structure.pdf
FYP Structure.pdf
 
Modellistica Lagrangiana in ISAC Torino - risultati e nuovi sviluppi
Modellistica Lagrangiana in ISAC Torino - risultati e nuovi sviluppiModellistica Lagrangiana in ISAC Torino - risultati e nuovi sviluppi
Modellistica Lagrangiana in ISAC Torino - risultati e nuovi sviluppi
 
An Enhanced Control Technique for the Elimination of Residual
An Enhanced Control Technique for the Elimination of ResidualAn Enhanced Control Technique for the Elimination of Residual
An Enhanced Control Technique for the Elimination of Residual
 
ÖNCEL AKADEMİ: İSTANBUL DEPREMİ
ÖNCEL AKADEMİ: İSTANBUL DEPREMİÖNCEL AKADEMİ: İSTANBUL DEPREMİ
ÖNCEL AKADEMİ: İSTANBUL DEPREMİ
 
Multiphase Flow Modeling and Simulation: HPC-Enabled Capabilities Today and T...
Multiphase Flow Modeling and Simulation: HPC-Enabled Capabilities Today and T...Multiphase Flow Modeling and Simulation: HPC-Enabled Capabilities Today and T...
Multiphase Flow Modeling and Simulation: HPC-Enabled Capabilities Today and T...
 
Presentation (Pagkratios Chitas)
Presentation (Pagkratios Chitas)Presentation (Pagkratios Chitas)
Presentation (Pagkratios Chitas)
 
Seismic Assessment of Existing Bridge Using OPENSEES
Seismic Assessment of Existing Bridge Using OPENSEESSeismic Assessment of Existing Bridge Using OPENSEES
Seismic Assessment of Existing Bridge Using OPENSEES
 
Dynamic Analysis And Optimization Of Fatigue Crack Propagation Using Full Fac...
Dynamic Analysis And Optimization Of Fatigue Crack Propagation Using Full Fac...Dynamic Analysis And Optimization Of Fatigue Crack Propagation Using Full Fac...
Dynamic Analysis And Optimization Of Fatigue Crack Propagation Using Full Fac...
 
5 ijsrms-02617 (1)
5 ijsrms-02617 (1)5 ijsrms-02617 (1)
5 ijsrms-02617 (1)
 
Attitude Control of Satellite Test Setup Using Reaction Wheels
Attitude Control of Satellite Test Setup Using Reaction WheelsAttitude Control of Satellite Test Setup Using Reaction Wheels
Attitude Control of Satellite Test Setup Using Reaction Wheels
 
Proposal Wide Blower No.1 & 2 with inverter
Proposal Wide Blower No.1 & 2  with inverterProposal Wide Blower No.1 & 2  with inverter
Proposal Wide Blower No.1 & 2 with inverter
 
TENSILE TEST REPORT
TENSILE TEST REPORTTENSILE TEST REPORT
TENSILE TEST REPORT
 
DESIGN AND OPTIMIZATION OF “KLANN MECHANISM” USING OCTO-POD ROBOT
DESIGN AND OPTIMIZATION OF “KLANN MECHANISM”  USING OCTO-POD ROBOTDESIGN AND OPTIMIZATION OF “KLANN MECHANISM”  USING OCTO-POD ROBOT
DESIGN AND OPTIMIZATION OF “KLANN MECHANISM” USING OCTO-POD ROBOT
 
ICDE2006, Singapore
ICDE2006, SingaporeICDE2006, Singapore
ICDE2006, Singapore
 
Nir_pres_Hagana_v1
Nir_pres_Hagana_v1Nir_pres_Hagana_v1
Nir_pres_Hagana_v1
 
Design And Analysis of Test Rig for Rudder Pedal
Design And Analysis of Test Rig for Rudder PedalDesign And Analysis of Test Rig for Rudder Pedal
Design And Analysis of Test Rig for Rudder Pedal
 
CONTINIOUS BRIDGE.pptx
CONTINIOUS BRIDGE.pptxCONTINIOUS BRIDGE.pptx
CONTINIOUS BRIDGE.pptx
 
A New geotechnical method for natural slope exploration and analysis
A New geotechnical method for natural slope exploration and analysisA New geotechnical method for natural slope exploration and analysis
A New geotechnical method for natural slope exploration and analysis
 
Final course project report
Final course project reportFinal course project report
Final course project report
 

Kürzlich hochgeladen

result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 

Kürzlich hochgeladen (20)

result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 

Presentation CIE619

  • 1. Analysis of FHWA Example 5 Bridge at Tacoma by Lemuria Pathfinders Supratik Bose Sathvika Meenakshisundaram Sharath Chandra Ranganath Sandhya Ravindran Amy Ruby May 2014
  • 2. Outline Introduction Motivation and Objectives Response Spectra and Scaling of GM Modeling Assumptions Analysis Procedure and Results Conclusions and Recommendations CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 2
  • 4. Introduction CSEE DEPARTMENT, UNIVERSITY AT BUFFALO Plan View of the Eight Span Steel Girder Continuous Bridge 4 Details of Bridge
  • 6. Objectives CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 6  Primary objective was to evaluate the bridge response using various analysis procedures given MCEER/ATC 49 report  Comparison of the results obtained from various analysis  Critical assessment of performance of the bridge based on those results  Recommendations for improvement of performance during future seismic event
  • 8. Modeling Assumptions CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 8 SAP 2000 Model  2D Bridge model was developed in SAP 2000 v. 16.0.1 program  Uniformly distributed load (DL) on superstructure = 9.3 kips/feet  Superstructure : Equivalent concrete cross-section with same area and inertia of composite structure  Centroid of the superstructure taken 8 feet above the top of the pier to account for bearing height
  • 9. Modeling Assumptions… CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 9 Modeling of Substructure: Piers  Modelled as three 2D frame elements  Foundation spring stiffness attached to the bottommost nodes of the piers  Pinned piers: node 6XX transfers shears but longitudinal moment (M3) released  Sliding piers: Only transverse shear transferred and M3, V2 released Relationship between actual pier and stick model Details of sliding bearings
  • 10. Modeling Assumptions… CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 10 Foundation springs and abutment  Foundation stiffness calculated in FHWA- example was used as the soil conditions are similar  Abutments modelled as simple nodes with vertical translation and torsional rotation restraint and transverse equivalent spring Spring Foundation Model Abutment Support Model k11 2.66 × 104 Kip/ft k22 7.847 × 105 Kip/ft k33 1.70× 104 Kip/ft k44 7.96 × 107 Kip-ft/rad k55 4.785 × 106 Kip-ft/rad K66 9.628 × 107 Kip-ft/rad
  • 12. Response Spectra CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 12 Response Spectra of the Site  MCEER/ATC 49 report suggests 2 level of earthquakes for analysis Maximum Credible Earthquake Expected Earthquake
  • 13. Scaling of GMs CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 13 Selected GMs  Selected ground motions are scaled such that  Geometric mean spectra never lies below 15% of design spectra  Average ratio of mean and target spectra not less than unity over the period range of significance. Selected Ground Motions No Ground Motion NGA# Scale M Year Station MCE 1 Cape Mendocino 828 1.0 7.01 1992 Petrolia 2 North Ridge 960 1.0 6.69 1994 Canyon Country-W Lost Cany 3 Loma-Prieto 753 1.0 6.93 1989 Corralitos EE 1 North Ridge 1048 0.38 6.69 1994 North Ridge 17645 Saticoy St 2 Imperial Valley 181 0.47 6.53 1979 El-Centro #6 3 Kobe Japan 1116 0.72 6.90 1995 Shin-Osake
  • 15. Analysis CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 15 Uniform Load Method  Maximum displacement (vs-max) obtained by assigning Po of 1 kip/ft, Pe, K and Tm calculated based on these equations max o s P L K v    sup 16011.2 18271.2 long super piers long trans er piers trans W W W kips W W W kips         2m W T Kg  e d W P C L   Direction of applied load Transverse Longitudinal Max displacement (ft) 0.037 0.144 Lateral Stiffness (kip/ft) 36808.5 9631.17 Time Period (s) 0.78 1.43 Hazard level EE MCE EE MCE Cd 0.2486 0.8825 0.133 0.47 Pe (kip/ft) 3.281 11.65 1.5386 5.437 Base Shear (kips) 4542.22 16124.33 2129.49 7525.26 Maximum Moment (kips-feet) 5698.64 20234.42 2704.91 9558.44 Max Displacement after Pe (ft) 0.124 0.442 0.228 0.775
  • 16. Analysis… CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 16 Multimode Method  Modal analysis was carried out in SAP 2000 program Mode Period (s) Cumulative Modal Mass Participation Mode of VibrationTranslational Rotational UX UY UZ RX RY RZ 1.00 1.54 0.57 0.00 0.00 0.00 0.00 0.06 Longitudinal 2.00 0.88 0.00 0.59 0.00 0.02 0.00 0.00 Transverse 3.00 0.75 0.05 0.00 0.00 0.00 0.00 0.54 Torsion Direction Analytical Calculation (kip/feet) Modal Analysis (kip/feet) Longitudinal (Local X) 8484 8277 Transverse (Local Y) 28793 28927 Comparison of bridge stiffness obtained analytically and from modal analysis
  • 17. Analysis… CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 17 Multimode Method…  Modes were combined using CQC method and the directional effects were considered by 100%-40% combination rule  Ambient damping of 5% was considered Results obtained from multimode response spectrum analysis at MCE MCE Pier No. Longitudinal Transverse Axial ForceShear Moment Shear Moment 1L+0.4T Pier 1 993.8 37327.5 221. 9 114662.1 55.6 Pier 2 1322.1 68960.6 2330.0 125658.3 32.4 Pier 3 699.8 35743.1 2301.7 159105.4 64.9 Pier 4 437.2 20518.7 2693.0 186280.0 26.3 1T+0.4L Pier 1 1413.3 53082.6 1587.5 79300.8 90.6 Pier 2 2325.7 124775.3 1573.5 84425.7 48.9 Pier 3 1310.0 71479.4 1372.0 91656.7 101.2 Pier 4 1092.5 51280.3 1078.0 74358.5 10.5
  • 18. Analysis… CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 18 Pushover Analysis  Fiber PMM hinges were used to define non linearity  Simplified bilinear behaviour assumed for concrete and steel  Triangular loading pattern was used  Individual piers: Hinges only at the bottom of the members  Entire structure: Hinges considered at the base and the neck of the trapezoidal part of the piers Stiffness (kips/feet) Longitudinal Transverse Pushover Analytical Pushover Analytical 70 feet pier 5872 5022 1728 1259 50 feet pier 8100 7841 3375 2983 Stiffness (kips/feet) Chord Radial Bridge 10500 10331 28889 29521 Comparison of stiffness obtained analytically and calculated from pushover analysis
  • 19. Analysis… CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 19 Pushover Curves… 70 feet - Transverse 0 500 1000 1500 2000 2500 0 5 10 15 20 25 LateralForce(kips) Displacement (inches) 0 5 10 5 1 106 1.5 10 6 0 0.005 0.01 0.015 0.02 0.025 Moment(kips-inches) Rotation (radians) 0 200 400 600 800 1000 0 5 10 15 20 25 LatrealForce(kips) Displacement (inches) 0 1 105 2 10 5 3 10 5 4 10 5 5 10 5 0 0.005 0.01 0.015 0.02 0.025 Moment(kips-inches) Rotation (radians) 70 feet - Longitudinal 0 5000 10000 15000 20000 25000 30000 0 2 4 6 8 LateralForce(kips) Displacement (feet) Entire bridge - Transverse 0 1000 2000 3000 4000 5000 0 2 4 6 8 LateralForce(kips) Displacement (feet) Entire bridge - Longitudinal
  • 20. Analysis… CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 20 Linear Elastic Time History Analysis (THA)  Linear elastic THA carried out both in NONLIN and SAP 2000 Hazard Level Base Shear (kips) Displacement (feet) Long Trans Long Trans NON SAP NON SAP NON SAP NON SAP MCE 8426.75 12130 20743.9 32080 0.81 1.16 0.70 1.33 EE 4051.63 5731 6803.53 10250 0.39 0.34 0.23 0.35 Comparison of maximum results from SAP 2000 and NONLIN  EE has lesser demand on the structure and hence impose smaller displacement on the piers as compared to MCE  20% difference in results obtained from SAP2000 and NONLIN.
  • 21. Analysis… CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 21 Non Linear SDoF Time History Analysis (THA)  Nonlinear SDoF THA was carried out in NONLIN  Simplified bilinear behaviour was assumed with K2 = 0  Yield strength obtained from pushover analysis Hazard Level GM Global X Linear Global X Nonlinear Global Y Linear Global Y Nonlinear Shear (kips) Disp. (feet) Shear (kips) Disp. (feet) Shear (kips) Disp. (feet) Shear (kips) Disp. (feet) MCE NGA 753-FN 2757 0.27 2757 0.27 7356 0.25 7356 0.25 NGA 753-FP 6905 0.67 4250 0.72 20409 0.69 20409 0.69 NGA 828-FN 4165 0.40 4165 0.40 18876 0.64 18876 0.64 EE NGA 1048-FP 3105 0.30 3105 0.30 5007 0.17 5007 0.17 NGA 1116-FP 2297 0.22 2297 0.22 5644 0.19 5644 0.19 NGA 1116-FP 4052 0.39 4052 0.39 6282 0.21 6282 0.21 Comparison of results from linear and nonlinear analysis in NONLIN
  • 22. Analysis… CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 22 Non Linear MDoF Time History Analysis  Same nonlinear model as used in pushover analysis  Newmark Beta direct integration procedure was used Maximum displacement response during NR-GM Hysteretic begaviour during NR-GM
  • 23. Analysis… CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 23 Non Linear MDoF Time History Analysis  Lesser demands observed at EE for linear and nonlinear analysis.  Structure remain within the elastic range at EE hazard level  In MCE for some of the GMs, the structure reached the inelastic zone  Maximum displacement recorded from MDoF analysis in SAP 2000 program was higher compared to SDoF analysis in NONLIN. Max Moment (kips-ft) Shear (kips) Disp. (ft) Trans Long Long Trans Long Trans P1 86000 27670 754 1858 0.175 0.234 P2 101300 47930 1150 1959 0.460 0.280 P3 104700 36240 666 1584 0.439 0.363 P4 104900 28210 617 1634 0.331 0.369 Max Moment (kips-ft) Shear (kips) Disp. (ft) Trans Long Long Trans Long Trans P1 141500 53740 1728 3403 0.699 0.647 P2 145800 56600 1413 3275 0.853 0.801 P3 140700 51320 2064 2325 0.915 1.106 P4 147300 43820 1824 2462 1.305 1.124 Expected Earthquake Maximum Credible Earthquake
  • 24. Analysis… CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 24 Capacity Spectrum Analysis 2 1 2 1 2 v n C c L y gF S V C C B W        BL obtained from Table 5.4.1.1-1 of MCEER/ATC 49 MCE y θpH 0.25CCH Modified CC Modified Vn Long Trans Long Trans Long Trans Long Trans Long Trans Operational 13.7 2.3 1.75 1.75 4.2 25.3 1.1 2.6 33722 33722 Life Safety 5.4 0.9 1.75 1.75 4.2 25.3 2.6 - 13174 - Hazard Level Operational Life Safety Long Trans Long Trans EE SAFE MCE UNSAFE UNSAFE UNSAFE SAFE
  • 25. Analysis Results… CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 25 Comparison of results of various analysis  Shear forces and displacements obtained are in close agreement  Bending moment in some of the cases are different and the possible reason is the irregular curved geometry of the bridge Max Expected earthquake Maximum Credible earthquake Shear (kips) Moment (kips-feet) Displacement (feet) Shear (kips) Moment (kips-feet) Displacement (feet) Long Trans Trans Long Long Trans Long Trans Trans Long Long Trans ULM 793 624 45482 45988 0.24 0.12 2217 2802 161485 162499 0.85 0.44 MM 761 657 52668 35293 0.18 0.15 2326 2693 186280 124783 0.64 0.51 Elastic THA 672 2058 127500 42417 0.34 0.35 2850 7810 495833 152500 1.33 1.16 Inelastic THA 1150 1959 104900 47930 0.46 0.37 2064 3403 147300 116600 1.31 1.12 Comparison of results from various analysis procedure
  • 26. Analysis Results… CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 26 Performance of the bridge  Demands obtained from linear analysis were divided by R-factor 1 ( 1) 1.25 B B S T R R R T     RB obtained from Table 4.7.1 of MCEER/ATC 49 Analysis Expected Earthquake Maximum Credible Earthquake Longitudinal Transverse Longitudinal Transverse LS OP LS OP LS OP LS OP ULM Safe Safe Safe Safe Unsafe Unsafe Safe Unsafe MM Safe Safe Safe Safe Unsafe Unsafe Unsafe Unsafe Elastic THA Safe Unsafe Safe Safe Safe Unsafe Safe Unsafe Inelastic THA Unsafe Unsafe Unsafe Unsafe Unsafe Unsafe Unsafe Unsafe Therefore it can be concluded that performance of bridge remains operational in case of EE but leads to possible failure in MCE.
  • 28. Recommendations CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 28 Recommendation for improvement of bridge performance at MCE:  Seismic isolation bearings can be used to accommodate the excess displacement demands during high seismic event.  Sliding friction pendulum bearings can be a good alternative to those used in the present model to ensure better performance at MCE.  Use of dampers along with the isolators can also improve the performance of the bridge at large earthquakes.  All the piers can be converted to sliding piers to accommodate the high displacement demands expected at MCE
  • 30. References CSEE DEPARTMENT, UNIVERSITY AT BUFFALO 30 CSI., 2009. Integrated Software for Structural Analysis and Design, SAP 2000. CSI. FHWA-SA-97-010. Seismic Design of Bridges, Design Example No. 5, Nine Span Viaduct Steel Girder Bridge. BERGER/ABAM Engineers. Federal Highway Administration. 1996. MCEER/ATC 49. Recommended LFRD Guidelines for the Seismic Design of Highway Bridges, Part I: Specifications. ATC MCEER Joint Venture. 2003 MCEER/ATC 49. Recommended LFRD Guidelines for the Seismic Design of Highway Bridges, Part II: Commentary and Appendices. ATC MCEER Joint Venture. 2003 Bruneau, M., Uang, C. M. and Sabelli, R. 2010. Ductile Design of Steel Structures. Second Edition Lawson, R.S., Vance, V. and Krawinkler, H. 1994. Nonlinear static pushover analysis: Why, When and How?. Proceedings of 5th US National Conference on Earthquake Engineering, July 10-14, 1994, Chicago. Chopra, A. K. (2012). Earthquake Response of Linear Systems. Dynamics of Structures: Theory and Applications to Earthquake Engineering (). Upper Saddle River, NJ: Pearson Education Inc. Villaverde, R., 2009. Fundamental Concepts of Earthquake Engineering.