WORK BREAKDOWN STRUCTURE
SOFTWARE PROJECT MANAGEMENT (SPM)




Work Breakdown Structure of Insurance Survey Portal (ISP)



                    Submitted To:


                    Madam Aasma Abid



                     Submitted By:


                    Abdul-Rehman Aslam
                           (9998)

                      Yasir Mehmood
                           (9994)
Introduction
The Work Breakdown Structure presented here represents all the work required to complete
this project. It helps to easily communicate the work and processes involved to execute the
project. The Project Manager and project team use the WBS to develop the project schedule,
resource requirements and costs




Outline View


1. Insurance Survey Portal

  1.1 Initiation
    1.1.1 Evaluation & Recommendations

    1.1.2 Develop Project Charter

    1.1.3 Deliverable: Submit Project Charter

    1.1.4 Project Sponsor Reviews Project Charter

    1.1.5 Project Charter Signed/Approved

  1.2 Planning
    1.2.1 Create Preliminary Scope Statement

    1.2.2 Determine Project Team

    1.2.3 Project Team Kickoff Meeting

    1.2.4 Develop Project Plan

    1.2.5 Submit Project Plan

    1.2.6 Milestone: Project Plan Approval
1.3 Execution
   1.3.1 Project Kickoff Meeting

   1.3.2 Verify & Validate User Requirements

   1.3.3 Design System

   1.3.4 Procure Hardware/Software

   1.3.5 Install Development System

   1.3.6 Testing Phase

   1.3.7 Install Live System

   1.3.8 User Training

   1.3.9 Go Live

  1.4 Control
   1.4.1 Project Management

   1.4.2 Project Status Meetings

   1.4.3 Risk Management

   1.4.4 Update Project Management Plan

  1.5 Closeout
   1.5.1 Audit Procurement

   1.5.2 Document Lessons Learned

   1.5.3 Update Files/Records

   1.5.4 Gain Formal Acceptance

   1.5.5 Archive Files/Documents
Tabular View


Level 1              Level 2          Level 3
1 Insurance Survey   1.1 Initiation   1.1.1 Evaluation & Recommendations
  Portal                              1.1.2 Develop Project Charter
                                      1.1.3 Deliverable: Submit Project Charter
                                      1.1.4 Project Sponsor Reviews Project Charter
                                      1.1.5 Project Charter Signed/Approved
                     1.2 Planning     1.2.1 Create Preliminary Scope Statement
                                      1.2.2 Determine Project Team
                                      1.2.3 Project Team Kickoff Meeting
                                      1.2.4 Develop Project Plan
                                      1.2.5 Submit Project Plan
                                      1.2.6 Milestone: Project Plan Approval
                     1.3 Execution    1.3.1 Project Kickoff Meeting
                                      1.3.2 Verify & Validate User Requirements
                                      1.3.3 Design System
                                      1.3.4 Procure Hardware/Software
                                      1.3.5 Install Development System
                                      1.3.6 Testing Phase
                                      1.3.7 Install Live System
                                      1.3.8 User Training
                                      1.3.9 Go Live
                     1.4 Control      1.4.1 Project Management
                                      1.4.2 Project Status Meetings
                                      1.4.3 Risk Management
                                      1.4.4 Update Project Management Plan
                     1.5 Closeout     1.5.1 Audit Procurement
                                      1.5.2 Document Lessons Learned
                                      1.5.3 Update Files/Records
                                      1.5.4 Gain Formal Acceptance
                                      1.5.5 Archive Files/Documents
Tree Structure View

Weitere ähnliche Inhalte

Was ist angesagt?

Analist Eğitimi - Tüm Bölümler - [535 Slides]
Analist Eğitimi - Tüm Bölümler -  [535 Slides]Analist Eğitimi - Tüm Bölümler -  [535 Slides]
Analist Eğitimi - Tüm Bölümler - [535 Slides]
Erol Bozkurt
 
ePMO Workshop - Ali Kaabi
ePMO Workshop - Ali KaabiePMO Workshop - Ali Kaabi
ePMO Workshop - Ali Kaabi
Ali Kaabi
 

Was ist angesagt? (20)

041006-Program Management PMI NB - PMI Logo
041006-Program Management PMI NB - PMI Logo041006-Program Management PMI NB - PMI Logo
041006-Program Management PMI NB - PMI Logo
 
Analist Eğitimi - Tüm Bölümler - [535 Slides]
Analist Eğitimi - Tüm Bölümler -  [535 Slides]Analist Eğitimi - Tüm Bölümler -  [535 Slides]
Analist Eğitimi - Tüm Bölümler - [535 Slides]
 
Risk Yönetim Planı Oluşturma
Risk Yönetim Planı OluşturmaRisk Yönetim Planı Oluşturma
Risk Yönetim Planı Oluşturma
 
Pmo
PmoPmo
Pmo
 
PMO Handbook - How to Plan, Build, and Run a PMO
PMO Handbook - How to Plan, Build, and Run a PMOPMO Handbook - How to Plan, Build, and Run a PMO
PMO Handbook - How to Plan, Build, and Run a PMO
 
PMBOK 6 Summary: Module 2 (Planning Processes)
PMBOK 6 Summary: Module 2 (Planning Processes)PMBOK 6 Summary: Module 2 (Planning Processes)
PMBOK 6 Summary: Module 2 (Planning Processes)
 
8 risk yonetimi
8   risk yonetimi8   risk yonetimi
8 risk yonetimi
 
Oim Pmo It Governance Structure Cox
Oim Pmo It Governance Structure CoxOim Pmo It Governance Structure Cox
Oim Pmo It Governance Structure Cox
 
Einführung in DMN mit Camunda
Einführung in DMN mit CamundaEinführung in DMN mit Camunda
Einführung in DMN mit Camunda
 
ePMO Workshop - Ali Kaabi
ePMO Workshop - Ali KaabiePMO Workshop - Ali Kaabi
ePMO Workshop - Ali Kaabi
 
Agile Testing: The Role Of The Agile Tester
Agile Testing: The Role Of The Agile TesterAgile Testing: The Role Of The Agile Tester
Agile Testing: The Role Of The Agile Tester
 
PMO - Added value instead of administration
PMO - Added value instead of administrationPMO - Added value instead of administration
PMO - Added value instead of administration
 
PMO Challenges and Opportunities; DIPMF Presentation
PMO Challenges and Opportunities; DIPMF PresentationPMO Challenges and Opportunities; DIPMF Presentation
PMO Challenges and Opportunities; DIPMF Presentation
 
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5
 
The PMO journey
The PMO journeyThe PMO journey
The PMO journey
 
Pmbok Processes Flow, ALL!
Pmbok Processes Flow, ALL!Pmbok Processes Flow, ALL!
Pmbok Processes Flow, ALL!
 
Agile Project and Portfolio Management Using Jira - AgileSolutions
Agile Project and Portfolio Management Using Jira - AgileSolutionsAgile Project and Portfolio Management Using Jira - AgileSolutions
Agile Project and Portfolio Management Using Jira - AgileSolutions
 
3 zaman yonetimi
3   zaman yonetimi3   zaman yonetimi
3 zaman yonetimi
 
BPMN 2.0 erfolgreich einsetzen mit Signavio
BPMN 2.0 erfolgreich einsetzen mit SignavioBPMN 2.0 erfolgreich einsetzen mit Signavio
BPMN 2.0 erfolgreich einsetzen mit Signavio
 
Pmo Gap Analysis Sample Itvamp 2008
Pmo Gap Analysis Sample Itvamp 2008Pmo Gap Analysis Sample Itvamp 2008
Pmo Gap Analysis Sample Itvamp 2008
 

Andere mochten auch

Plan 06 perencanaan manajemen proyek2
Plan 06 perencanaan manajemen proyek2Plan 06 perencanaan manajemen proyek2
Plan 06 perencanaan manajemen proyek2
Anggunara Thea
 
El aguila de wilmar ivan G L
El aguila de wilmar ivan G LEl aguila de wilmar ivan G L
El aguila de wilmar ivan G L
wilmar gonzalez
 
Tugas plkj
Tugas plkjTugas plkj
Tugas plkj
hanif003
 
ดนตรีสากล
ดนตรีสากลดนตรีสากล
ดนตรีสากล
Kan Directioner
 

Andere mochten auch (20)

Work Breakdown Structure ( WBS) : For a Project Management Process
Work Breakdown Structure ( WBS) : For a Project Management ProcessWork Breakdown Structure ( WBS) : For a Project Management Process
Work Breakdown Structure ( WBS) : For a Project Management Process
 
Pm Student Ho
Pm Student HoPm Student Ho
Pm Student Ho
 
Plan 06 perencanaan manajemen proyek2
Plan 06 perencanaan manajemen proyek2Plan 06 perencanaan manajemen proyek2
Plan 06 perencanaan manajemen proyek2
 
WBS PROJECT
WBS PROJECTWBS PROJECT
WBS PROJECT
 
Ravi tiwari
Ravi tiwariRavi tiwari
Ravi tiwari
 
Ihm2
Ihm2Ihm2
Ihm2
 
El aguila de wilmar ivan G L
El aguila de wilmar ivan G LEl aguila de wilmar ivan G L
El aguila de wilmar ivan G L
 
Sec Presentation
Sec  PresentationSec  Presentation
Sec Presentation
 
Реализация мероприятий развития государственных программ города Москвы в 2013...
Реализация мероприятий развития государственных программ города Москвы в 2013...Реализация мероприятий развития государственных программ города Москвы в 2013...
Реализация мероприятий развития государственных программ города Москвы в 2013...
 
E 12 bsp1779_pankajkumarvisualcv
E 12 bsp1779_pankajkumarvisualcvE 12 bsp1779_pankajkumarvisualcv
E 12 bsp1779_pankajkumarvisualcv
 
Стимулирование органов местного самоуправления в Москве по итогам первого пол...
Стимулирование органов местного самоуправления в Москве по итогам первого пол...Стимулирование органов местного самоуправления в Москве по итогам первого пол...
Стимулирование органов местного самоуправления в Москве по итогам первого пол...
 
Tugas plkj
Tugas plkjTugas plkj
Tugas plkj
 
T pack presentation
T pack presentationT pack presentation
T pack presentation
 
Presentazione Tweetaliano Erasmus/EILC
Presentazione Tweetaliano Erasmus/EILCPresentazione Tweetaliano Erasmus/EILC
Presentazione Tweetaliano Erasmus/EILC
 
Spm report
Spm reportSpm report
Spm report
 
Radhin 4+
Radhin 4+Radhin 4+
Radhin 4+
 
Hindi kavita laal tamatar
Hindi kavita  laal tamatarHindi kavita  laal tamatar
Hindi kavita laal tamatar
 
SMX Melbourne 2012 - Auditing PPC Campaigns - Leigh Hanney
SMX Melbourne 2012 - Auditing PPC Campaigns - Leigh HanneySMX Melbourne 2012 - Auditing PPC Campaigns - Leigh Hanney
SMX Melbourne 2012 - Auditing PPC Campaigns - Leigh Hanney
 
Kumpulan 1
Kumpulan 1Kumpulan 1
Kumpulan 1
 
ดนตรีสากล
ดนตรีสากลดนตรีสากล
ดนตรีสากล
 

Ähnlich wie Work BreakDown Structure

Implementation-Plan_X_Corp
Implementation-Plan_X_CorpImplementation-Plan_X_Corp
Implementation-Plan_X_Corp
Jared Bourne
 
Work Breakdown Structure (WBS) TemplateThis Project WB.docx
Work Breakdown Structure (WBS) TemplateThis Project WB.docxWork Breakdown Structure (WBS) TemplateThis Project WB.docx
Work Breakdown Structure (WBS) TemplateThis Project WB.docx
ambersalomon88660
 
Project mgmt life cycle origination
Project mgmt life cycle originationProject mgmt life cycle origination
Project mgmt life cycle origination
Mujtaba Masood
 
MSF Process model
MSF Process modelMSF Process model
MSF Process model
unruliness
 

Ähnlich wie Work BreakDown Structure (20)

Work Breakdown Structure Template(1).docx
Work Breakdown Structure Template(1).docxWork Breakdown Structure Template(1).docx
Work Breakdown Structure Template(1).docx
 
Implementation-Plan_X_Corp
Implementation-Plan_X_CorpImplementation-Plan_X_Corp
Implementation-Plan_X_Corp
 
Iso12207:2008 standard
Iso12207:2008 standardIso12207:2008 standard
Iso12207:2008 standard
 
Work Breakdown Structure (WBS) TemplateThis Project WB.docx
Work Breakdown Structure (WBS) TemplateThis Project WB.docxWork Breakdown Structure (WBS) TemplateThis Project WB.docx
Work Breakdown Structure (WBS) TemplateThis Project WB.docx
 
2nd meeting
2nd meeting2nd meeting
2nd meeting
 
Project Work Breakdown Structure
Project Work Breakdown StructureProject Work Breakdown Structure
Project Work Breakdown Structure
 
PgM ITTOs
PgM ITTOsPgM ITTOs
PgM ITTOs
 
Pmt 01
Pmt 01Pmt 01
Pmt 01
 
Training Report
Training ReportTraining Report
Training Report
 
Iss 05
Iss 05Iss 05
Iss 05
 
Project mgmt life cycle origination
Project mgmt life cycle originationProject mgmt life cycle origination
Project mgmt life cycle origination
 
Software proposal sample_project_1-_web_site_development_by_zx_7_of_november_...
Software proposal sample_project_1-_web_site_development_by_zx_7_of_november_...Software proposal sample_project_1-_web_site_development_by_zx_7_of_november_...
Software proposal sample_project_1-_web_site_development_by_zx_7_of_november_...
 
MSF Process model
MSF Process modelMSF Process model
MSF Process model
 
Archive Documents
Archive DocumentsArchive Documents
Archive Documents
 
Maximo project approach using prince2
Maximo project approach using prince2Maximo project approach using prince2
Maximo project approach using prince2
 
Project Scope Management Chapter 05.pptx
Project Scope Management Chapter 05.pptxProject Scope Management Chapter 05.pptx
Project Scope Management Chapter 05.pptx
 
project managment - wang jing yuan (Eric Wang)
project managment - wang jing yuan (Eric Wang)project managment - wang jing yuan (Eric Wang)
project managment - wang jing yuan (Eric Wang)
 
Peer Review
Peer ReviewPeer Review
Peer Review
 
Trn 04
Trn 04Trn 04
Trn 04
 
Software proposal sample_project_2-_mobile_application_development_by_swpropo...
Software proposal sample_project_2-_mobile_application_development_by_swpropo...Software proposal sample_project_2-_mobile_application_development_by_swpropo...
Software proposal sample_project_2-_mobile_application_development_by_swpropo...
 

Mehr von Abdul Aslam (12)

Challenges of cloud final
Challenges of cloud finalChallenges of cloud final
Challenges of cloud final
 
Star ,Snow and Fact-Constullation Schemas??
Star ,Snow and  Fact-Constullation Schemas??Star ,Snow and  Fact-Constullation Schemas??
Star ,Snow and Fact-Constullation Schemas??
 
Job analysis of a reporter
Job analysis of a reporterJob analysis of a reporter
Job analysis of a reporter
 
Project Progress Report
Project Progress ReportProject Progress Report
Project Progress Report
 
Components of a Data-Warehouse
Components of a Data-WarehouseComponents of a Data-Warehouse
Components of a Data-Warehouse
 
Difference between ER-Modeling and Dimensional Modeling
Difference between ER-Modeling and Dimensional ModelingDifference between ER-Modeling and Dimensional Modeling
Difference between ER-Modeling and Dimensional Modeling
 
Transaction Processing System
Transaction Processing SystemTransaction Processing System
Transaction Processing System
 
Final Year Project (ISP),Project Demo
Final Year Project (ISP),Project DemoFinal Year Project (ISP),Project Demo
Final Year Project (ISP),Project Demo
 
Distributed Operating System,Network OS and Middle-ware.??
Distributed Operating System,Network OS and Middle-ware.??Distributed Operating System,Network OS and Middle-ware.??
Distributed Operating System,Network OS and Middle-ware.??
 
Software Testing Tool Report
Software Testing Tool ReportSoftware Testing Tool Report
Software Testing Tool Report
 
Cloud Computing
 Cloud Computing Cloud Computing
Cloud Computing
 
Erd For Gift Shop
Erd For Gift ShopErd For Gift Shop
Erd For Gift Shop
 

Kürzlich hochgeladen

Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please Practise
AnaAcapella
 
Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
KarakKing
 
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdfVishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdf
ssuserdda66b
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
heathfieldcps1
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
ciinovamais
 

Kürzlich hochgeladen (20)

Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptx
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701
 
Single or Multiple melodic lines structure
Single or Multiple melodic lines structureSingle or Multiple melodic lines structure
Single or Multiple melodic lines structure
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
Google Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptxGoogle Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptx
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - English
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please Practise
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...
 
Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdfVishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdf
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 

Work BreakDown Structure

  • 2. SOFTWARE PROJECT MANAGEMENT (SPM) Work Breakdown Structure of Insurance Survey Portal (ISP) Submitted To: Madam Aasma Abid Submitted By: Abdul-Rehman Aslam (9998) Yasir Mehmood (9994)
  • 3. Introduction The Work Breakdown Structure presented here represents all the work required to complete this project. It helps to easily communicate the work and processes involved to execute the project. The Project Manager and project team use the WBS to develop the project schedule, resource requirements and costs Outline View 1. Insurance Survey Portal 1.1 Initiation 1.1.1 Evaluation & Recommendations 1.1.2 Develop Project Charter 1.1.3 Deliverable: Submit Project Charter 1.1.4 Project Sponsor Reviews Project Charter 1.1.5 Project Charter Signed/Approved 1.2 Planning 1.2.1 Create Preliminary Scope Statement 1.2.2 Determine Project Team 1.2.3 Project Team Kickoff Meeting 1.2.4 Develop Project Plan 1.2.5 Submit Project Plan 1.2.6 Milestone: Project Plan Approval
  • 4. 1.3 Execution 1.3.1 Project Kickoff Meeting 1.3.2 Verify & Validate User Requirements 1.3.3 Design System 1.3.4 Procure Hardware/Software 1.3.5 Install Development System 1.3.6 Testing Phase 1.3.7 Install Live System 1.3.8 User Training 1.3.9 Go Live 1.4 Control 1.4.1 Project Management 1.4.2 Project Status Meetings 1.4.3 Risk Management 1.4.4 Update Project Management Plan 1.5 Closeout 1.5.1 Audit Procurement 1.5.2 Document Lessons Learned 1.5.3 Update Files/Records 1.5.4 Gain Formal Acceptance 1.5.5 Archive Files/Documents
  • 5. Tabular View Level 1 Level 2 Level 3 1 Insurance Survey 1.1 Initiation 1.1.1 Evaluation & Recommendations Portal 1.1.2 Develop Project Charter 1.1.3 Deliverable: Submit Project Charter 1.1.4 Project Sponsor Reviews Project Charter 1.1.5 Project Charter Signed/Approved 1.2 Planning 1.2.1 Create Preliminary Scope Statement 1.2.2 Determine Project Team 1.2.3 Project Team Kickoff Meeting 1.2.4 Develop Project Plan 1.2.5 Submit Project Plan 1.2.6 Milestone: Project Plan Approval 1.3 Execution 1.3.1 Project Kickoff Meeting 1.3.2 Verify & Validate User Requirements 1.3.3 Design System 1.3.4 Procure Hardware/Software 1.3.5 Install Development System 1.3.6 Testing Phase 1.3.7 Install Live System 1.3.8 User Training 1.3.9 Go Live 1.4 Control 1.4.1 Project Management 1.4.2 Project Status Meetings 1.4.3 Risk Management 1.4.4 Update Project Management Plan 1.5 Closeout 1.5.1 Audit Procurement 1.5.2 Document Lessons Learned 1.5.3 Update Files/Records 1.5.4 Gain Formal Acceptance 1.5.5 Archive Files/Documents