  Network analysis is the general name given to
  certain specific techniques which can be used
  for the planning, management and control of
  projects.
 Use of nodes and arrows:-

Arrows  An arrow leads from tail to head
  directionally
       Indicate ACTIVITY, a time consuming effort that is
        required to perform a part of the work.
•   NODE:-
    A  node is represented by a circle
    - Indicate EVENT, a point in time where one or
      more activities start and/or finish.
•   Activity:-
    –   A task or a certain amount of work required in the
        project
    –   Requires time to complete
    –   Represented by an arrow
•   Dummy Activity:-
    – Indicates only precedence relationships
    – Does not require any time of effort.
   Event:-
       Signals the beginning or ending of an activity
       Designates a point in time
       Represented by a circle (node)
   Network:-
       Shows the sequential relationships among
        activities using nodes and arrows
   Activity-on-node (AON):-
    nodes represent activities, and arrows show precedence
      relationships
   Activity-on-arrow (AOA):-
    arrows represent activities and nodes are events for points
      in time
SITUATIONS IN NETWORK DIAGRAM:-
             B
                         A must finish before either B or C
             C           can start.
    A
                 C       Both A and B must finish before C
    B                    can start.
    A        C            Both A and B must finish before
                         either of C or D can start.
    B        D


                         A must finish before B can start
         B
A                        both A and C must finish before
        Dummy            D can start.

    C                D
 illustration of network analysis of a minor
  redesign of a product and its associated
  packaging.
The key question is: How long will it take to
complete this project ?
   Path
       A connected sequence of activities leading from the
        starting event to the ending event
   Critical Path
       The longest path (time); determines the project
        duration
   Critical Activities
       All of the activities that make up the critical path.
Forward Pass:-
   Earliest Start Time (ES)
     earliest time an activity can start
     ES = maximum EF of immediate predecessors


   Earliest finish time (EF)
     earliest time an activity can finish
     earliest start time plus activity time
                            EF= ES+t
Backward Pass:-
   Latest Start Time (LS)
    Latest time an activity can start without delaying critical
      path time
      LS= LF - t
   Latest finish time (LF)
    latest time an activity can be completed without
       delaying critical path time
    LS = minimum LS of immediate predecessors
   Draw the CPM network
   Analyze the paths through the network
   Determine the float for each activity
     Compute the activity’s float
                float = LS - ES = LF - EF
     Float is the maximum amount of time that this
      activity can be delay in its completion before it
      becomes a critical activity, i.e., delays completion of
      the project
   Find the critical path is that the sequence of activities
    and events where there is no “slack” i.e.. Zero slack
     Longest path through a network
   Find the project duration is minimum project
   CPM Network:-
                            f, 15


                              g, 17              h, 9
       a, 6
                                      i, 6


              b, 8

                             d, 13       j, 12


                     c, 5
                            e, 9
   ES and EF Times:-
                            f, 15

                              g, 17              h, 9
      a, 6
      0 6                             i, 6

             b, 8
           0 8                           j, 12
                            d, 13


       0     5      c, 5
                           e, 9
   ES and EF Times:-
                                         6     21
                                             f, 15


                                                  g, 17                   h, 9
            a, 6
                                     6       23
        0        6                                             i, 6


                     b, 8
                 0        8                   d, 13               j, 12

                                         8        21
                              c, 5
             0        5
                                             e, 9

                                                    5     14
   ES and EF Times:-
                                          6   21
                                    f, 15
                                                                         21 30
       0     6
                                      g, 17                               h, 9
      a, 6
                               6     23
                                                          i, 6
                    0      8                            23 29
             b, 8

                                     d, 13 8       21            j, 12

                                                                         21 33
                    c, 5
       0     5
                                   e, 9
                                                         Project’s EF = 33
                                          5   14
   LS and LF Times:-
                                              6    21
                                              0     0
                                  f, 15                                21 30
          0     6                                                      24 33
          0     0
                                    g, 17                              h, 9
         a, 6
                              6     23
                                                             i, 6 23 29
                              0      0                            27 33
                 0     8
                 0     0
                b, 8                               8    21     j, 12
                                  d, 13
                                                   0     0
                                                                       21 33
                       c, 5                                            21 33
     0     5
     0     0                  e, 9

                                          5       14
                                          0        0
   LS and LF Times:-
                                            6 21
                                           18 24
                                                                    21 30
                                   f, 15
         0      6                                                   24 33
         4     10
                              6 23 g, 17                           h, 9
        a, 6                                          23 29
                             10 27
                                                      27 33 i, 6

                 0     8
                 0     8      8   21
               b, 8           8   21                       j, 12
                                           d, 13
                                                                   21 33
    0    5
                      c, 5                                         21 33
    7   12
                                  e, 9
                                               5 14
                                              12 21
FLOAT:-
                                                 6     21
                                        03
                                                 9     24
                                              f, 15                              21 30
                                                                             3
                                                                                 24 33
                 0 6
        3
                 4 10                       g, 17                                h, 9
                a, 6                     6 23
                                     04
                                        10 27
                                                                    23 29 i, 6
                                                                4
                          0      8                                  27 33
                  0                      8      21
                          0      8   0
                      b, 8               8      21
                                                      d, 13              j, 12

                                                                                     21 33
                                                                                 0
            0     5           c, 5                                                   21 33
    7
            7    12                      e, 9            5 14
                                                 7
                                                        12 21
   Critical Path:-
                              f, 15


                                  g, 17                h, 9
      a, 6
                                                i, 6



             b, 8
                                      d, 13   j, 12


                    c, 5
                           e, 9
   PERT is based on the assumption that an activity’s
    duration follows a probability distribution instead
    of being a single value
   Three time estimates are required to compute the
    parameters of an activity’s duration distribution:
     pessimistic time (tp ) - the time the activity
      would take if things did not go well
     most likely time (tm ) - the consensus best
      estimate of the activity’s duration
     optimistic time (to ) - the time the activity would
      take if things did go well
       te = a+4m+b
                6
   Draw the network.
   Analyze the paths through the network and find
    the critical path.
   The length of the critical path is the mean of the
    project duration probability distribution which is
    assumed to be normal
   The standard deviation of the project duration
    probability distribution is computed by adding
    the variances of the critical activities (all of the
    activities that make up the critical path) and
    taking the square root of that sum
   Probability computations can now be made using
    the normal distribution table.
Determine probability that project is completed
 within specified time
Z=   x-



   where   = tp = project mean time
      = project standard mean time
    x = (proposed ) specified time
Probability




       Z




= tp       x             Time
   Useful at many stages of project management
   Mathematically simple
   Give critical path and slack time
   Provide project documentation
   Useful in monitoring costs
•   How long will the entire project take to be
    completed? What are the risks involved?
•   Which are the critical activities or tasks in the
    project which could delay the entire project if they
    were not completed on time?
•   Is the project on schedule, behind schedule or
    ahead of schedule?
•   If the project has to be finished earlier than
    planned, what is the best way to do this at the least
    cost?
   Parallel paths-identifying a single path is difficult
    when there are parallel paths with similar duration.
   Time consuming-critics note that it takes too much
    time to identify all activities and inter-relate them to
    get multiple projects paths.
   First time projects-CPM is not suitable if projects
    cannot be broken down into discrete activities with
    known completion times.
PRESENTED BY:-
BHUPENDRA SINGH SHEKHAWAT
ANKIT VINOD AGARWAL

Weitere ähnliche Inhalte

Was ist angesagt?

Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-control
Jatindra Malik
 

Was ist angesagt? (20)

Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
 
Pert and cpm
Pert and cpmPert and cpm
Pert and cpm
 
Project management-planning and scheduling
Project management-planning and schedulingProject management-planning and scheduling
Project management-planning and scheduling
 
Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/Slacks
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )
 
Project Management Techniques
Project Management TechniquesProject Management Techniques
Project Management Techniques
 
Per tand project crashing
Per tand project crashingPer tand project crashing
Per tand project crashing
 
Critical Path Method(CPM)
Critical Path Method(CPM)Critical Path Method(CPM)
Critical Path Method(CPM)
 
Project appraisal for financial markets
Project appraisal for financial marketsProject appraisal for financial markets
Project appraisal for financial markets
 
Pert Cpm Nis
Pert   Cpm NisPert   Cpm Nis
Pert Cpm Nis
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 
The role and responsibilities of the project manager
The role and responsibilities of the project manager The role and responsibilities of the project manager
The role and responsibilities of the project manager
 
Project management tools and techniques
Project management tools and techniquesProject management tools and techniques
Project management tools and techniques
 
Module :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levellingModule :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levelling
 
Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-control
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)
 
Project planning and scheduling
Project planning and schedulingProject planning and scheduling
Project planning and scheduling
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost Management
 
Project management
Project managementProject management
Project management
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 

Ähnlich wie Project Management PERT and CPM (8)

Day 6 graphing review
Day 6 graphing reviewDay 6 graphing review
Day 6 graphing review
 
Algo 23 MSTP
Algo 23 MSTPAlgo 23 MSTP
Algo 23 MSTP
 
Critical Path Examples
Critical Path ExamplesCritical Path Examples
Critical Path Examples
 
Img 0002
Img 0002Img 0002
Img 0002
 
Double patterning (4/20 update)
Double patterning (4/20 update)Double patterning (4/20 update)
Double patterning (4/20 update)
 
Greedy embedding problem
Greedy embedding problemGreedy embedding problem
Greedy embedding problem
 
Minimum spanning Tree
Minimum spanning TreeMinimum spanning Tree
Minimum spanning Tree
 
Cpm & network diagrams
Cpm & network diagramsCpm & network diagrams
Cpm & network diagrams
 

Mehr von Institute of Rural Management

Mehr von Institute of Rural Management (11)

Opec Organization of Petroleum Exporting Countries
Opec Organization of Petroleum Exporting CountriesOpec Organization of Petroleum Exporting Countries
Opec Organization of Petroleum Exporting Countries
 
Talent management
Talent managementTalent management
Talent management
 
Economic System
Economic SystemEconomic System
Economic System
 
Business cycle
Business cycleBusiness cycle
Business cycle
 
3 c's 4 p's of Management
3 c's 4 p's of Management3 c's 4 p's of Management
3 c's 4 p's of Management
 
MBO and MBE
MBO and MBEMBO and MBE
MBO and MBE
 
Personality and emotions ppt marks.
Personality and emotions ppt marks.Personality and emotions ppt marks.
Personality and emotions ppt marks.
 
Research process and sampling
Research process and samplingResearch process and sampling
Research process and sampling
 
Supply
SupplySupply
Supply
 
Planning
PlanningPlanning
Planning
 
Project management and project life cycle
Project management and project life cycleProject management and project life cycle
Project management and project life cycle
 

Kürzlich hochgeladen

Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
dlhescort
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
lizamodels9
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
daisycvs
 
Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000
Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000
Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000
dlhescort
 
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
lizamodels9
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 

Kürzlich hochgeladen (20)

Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
 
Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000
Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000
Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000
 
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
 
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableCall Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
 
Falcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in indiaFalcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in india
 
PHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation Final
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors Data
 
Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024
 
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
 
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort ServiceEluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investors
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 

Project Management PERT and CPM

  • 1.
  • 2.  Network analysis is the general name given to certain specific techniques which can be used for the planning, management and control of projects.  Use of nodes and arrows:- Arrows  An arrow leads from tail to head directionally  Indicate ACTIVITY, a time consuming effort that is required to perform a part of the work.
  • 3. NODE:- A node is represented by a circle - Indicate EVENT, a point in time where one or more activities start and/or finish. • Activity:- – A task or a certain amount of work required in the project – Requires time to complete – Represented by an arrow • Dummy Activity:- – Indicates only precedence relationships – Does not require any time of effort.
  • 4. Event:-  Signals the beginning or ending of an activity  Designates a point in time  Represented by a circle (node)  Network:-  Shows the sequential relationships among activities using nodes and arrows  Activity-on-node (AON):- nodes represent activities, and arrows show precedence relationships  Activity-on-arrow (AOA):- arrows represent activities and nodes are events for points in time
  • 5. SITUATIONS IN NETWORK DIAGRAM:- B A must finish before either B or C C can start. A C Both A and B must finish before C B can start. A C Both A and B must finish before either of C or D can start. B D A must finish before B can start B A both A and C must finish before Dummy D can start. C D
  • 6.  illustration of network analysis of a minor redesign of a product and its associated packaging. The key question is: How long will it take to complete this project ?
  • 7.
  • 8.
  • 9. Path  A connected sequence of activities leading from the starting event to the ending event  Critical Path  The longest path (time); determines the project duration  Critical Activities  All of the activities that make up the critical path.
  • 10. Forward Pass:-  Earliest Start Time (ES)  earliest time an activity can start  ES = maximum EF of immediate predecessors  Earliest finish time (EF)  earliest time an activity can finish  earliest start time plus activity time EF= ES+t
  • 11. Backward Pass:-  Latest Start Time (LS) Latest time an activity can start without delaying critical path time LS= LF - t  Latest finish time (LF) latest time an activity can be completed without delaying critical path time LS = minimum LS of immediate predecessors
  • 12. Draw the CPM network  Analyze the paths through the network  Determine the float for each activity  Compute the activity’s float float = LS - ES = LF - EF  Float is the maximum amount of time that this activity can be delay in its completion before it becomes a critical activity, i.e., delays completion of the project  Find the critical path is that the sequence of activities and events where there is no “slack” i.e.. Zero slack  Longest path through a network  Find the project duration is minimum project
  • 13. CPM Network:- f, 15 g, 17 h, 9 a, 6 i, 6 b, 8 d, 13 j, 12 c, 5 e, 9
  • 14. ES and EF Times:- f, 15 g, 17 h, 9 a, 6 0 6 i, 6 b, 8 0 8 j, 12 d, 13 0 5 c, 5 e, 9
  • 15. ES and EF Times:- 6 21 f, 15 g, 17 h, 9 a, 6 6 23 0 6 i, 6 b, 8 0 8 d, 13 j, 12 8 21 c, 5 0 5 e, 9 5 14
  • 16. ES and EF Times:- 6 21 f, 15 21 30 0 6 g, 17 h, 9 a, 6 6 23 i, 6 0 8 23 29 b, 8 d, 13 8 21 j, 12 21 33 c, 5 0 5 e, 9 Project’s EF = 33 5 14
  • 17. LS and LF Times:- 6 21 0 0 f, 15 21 30 0 6 24 33 0 0 g, 17 h, 9 a, 6 6 23 i, 6 23 29 0 0 27 33 0 8 0 0 b, 8 8 21 j, 12 d, 13 0 0 21 33 c, 5 21 33 0 5 0 0 e, 9 5 14 0 0
  • 18. LS and LF Times:- 6 21 18 24 21 30 f, 15 0 6 24 33 4 10 6 23 g, 17 h, 9 a, 6 23 29 10 27 27 33 i, 6 0 8 0 8 8 21 b, 8 8 21 j, 12 d, 13 21 33 0 5 c, 5 21 33 7 12 e, 9 5 14 12 21
  • 19. FLOAT:- 6 21  03 9 24 f, 15 21 30 3 24 33 0 6 3 4 10 g, 17 h, 9 a, 6 6 23 04 10 27 23 29 i, 6 4 0 8 27 33 0 8 21 0 8 0 b, 8 8 21 d, 13 j, 12 21 33 0 0 5 c, 5 21 33 7 7 12 e, 9 5 14 7 12 21
  • 20. Critical Path:- f, 15 g, 17 h, 9 a, 6 i, 6 b, 8 d, 13 j, 12 c, 5 e, 9
  • 21. PERT is based on the assumption that an activity’s duration follows a probability distribution instead of being a single value  Three time estimates are required to compute the parameters of an activity’s duration distribution:  pessimistic time (tp ) - the time the activity would take if things did not go well  most likely time (tm ) - the consensus best estimate of the activity’s duration  optimistic time (to ) - the time the activity would take if things did go well te = a+4m+b 6
  • 22. Draw the network.  Analyze the paths through the network and find the critical path.  The length of the critical path is the mean of the project duration probability distribution which is assumed to be normal  The standard deviation of the project duration probability distribution is computed by adding the variances of the critical activities (all of the activities that make up the critical path) and taking the square root of that sum  Probability computations can now be made using the normal distribution table.
  • 23. Determine probability that project is completed within specified time Z= x-  where = tp = project mean time  = project standard mean time  x = (proposed ) specified time
  • 24. Probability Z = tp x Time
  • 25. Useful at many stages of project management  Mathematically simple  Give critical path and slack time  Provide project documentation  Useful in monitoring costs
  • 26. How long will the entire project take to be completed? What are the risks involved? • Which are the critical activities or tasks in the project which could delay the entire project if they were not completed on time? • Is the project on schedule, behind schedule or ahead of schedule? • If the project has to be finished earlier than planned, what is the best way to do this at the least cost?
  • 27. Parallel paths-identifying a single path is difficult when there are parallel paths with similar duration.  Time consuming-critics note that it takes too much time to identify all activities and inter-relate them to get multiple projects paths.  First time projects-CPM is not suitable if projects cannot be broken down into discrete activities with known completion times.
  • 28. PRESENTED BY:- BHUPENDRA SINGH SHEKHAWAT ANKIT VINOD AGARWAL