INTERNATIONAL JOURNAL OF CIVIL ENGINEERING AND
  International Journal of Civil Engineering and Technology (IJCIET), ISSN 0976 – 6308
  (Print), ISSN 0976 – 6316(Online) Volume 4, Issue 2, March - April (2013), © IAEME
                                 TECHNOLOGY (IJCIET)
ISSN 0976 – 6308 (Print)
ISSN 0976 – 6316(Online)
Volume 4, Issue 2, March - April (2013), pp. 01-14
                                                                             IJCIET
© IAEME: www.iaeme.com/ijciet.asp
Journal Impact Factor (2013): 5.3277 (Calculated by GISI)                  © IAEME
www.jifactor.com



     MATHEMATICAL MODEL OF RCC DAM BREAK BASTORA RCC
                   DAM AS A CASE STUDY

                     NajmObaidSalim Alghazali1 and Dilshad A.H. Alhadrawi2
       (1)
             Corresponding author, Asst. Prof. Doctor, Civil Engineering Department, Babylon
                                             University, Iraq.
               (2)
                   M.Sc. Student, Civil Engineering Department, Babylon University, Iraq.


  ABSTRACT

         This is the first study on the failure of roller compacted concrete (RCC) dams. A
  mathematical model for over-stressing type of RCC dam failure is presented and a scenario
  for breach formation is presented. The hypothetical failure of Bastora dam, a RCC dam
  located north east of Iraq, due to overstress is selected as a case study. The reservoir outflow
  hydrograph is computed using the proposed mathematical model and then the outflow is
  routed downstream Bastora dam. The maximum water levels, maximum discharges and
  rescue level at the available (11) sections of Bastora River downstream Bastora dam are
  determined.

  Keywords: HEC- RAS, level pool routing method, mathematical model for RCC dam break,
  over-stressing failure, roller compacted concrete (RCC) dams

  1. INTRODUCTION

          ACI 207.5R [1] defines Roller-Compacted Concrete (RCC) as "a concrete of no-
  slump consistency in its unhardened state that is transported, placed, and compacted using
  earth and rock-fill construction equipment."ICODS [2] defines RCC damas" a concrete
  gravity dam constructed by the use of a dry mix concrete transported by conventional
  construction equipment and compacted by rolling, usually with vibratory rollers."
          RCC is an economical method and accepted material for constructing dams and
  rehabilitating and modifying existing concrete and embankment dams [1], [3], [4].The
  worldwide acceptance of RCC dams is due to their low cost, reduction period of construction,
  and successful performance [5].RCC dams were constructed in all types of climates and in all
  types of countries from the most developed to the still developing [6].There are more than
  250 RCC dams constructed throughout the world [7].

                                                   1
International Journal of Civil Engineering and Technology (IJCIET), ISSN 0976 – 6308
(Print), ISSN 0976 – 6316(Online) Volume 4, Issue 2, March - April (2013), © IAEME

         RCC gravity dams are designed to the same criteria as conventional concrete (CVC)
gravity dams with respect to stability and allowable stresses in the concrete [5], [8], [9].
However, there are differences in the uplift within the body of the dam and the minimum
sliding factors of safety [9].
         One significant difference between a RCC dam and a CVC dam is the continuous
placing of a horizontal lift of concrete from one abutment to the other, rather than
constructing the dam in a series of separate monoliths [3].Lift thicknesses depend on the
placement size, production capacity of the concrete batch plant, mixture proportions, and
compaction equipment [9], [10].There is no limited lift thickness used in all RCC dams. The
lift thicknesses used in RCC dams are 0.30 m (1 layer) [11], 0.60 m (composed of four 0.15
m layers) [9], 2 m (composed of eight layers of 0.25 m) [5], and 0.75 to 1 m (0.3 m layers)
[7], [12]. By the use of sloped layer method (SLM), the lift thickness is 3 to 4 m [13].
         A dam is a sword of two limits [14]. It is mainly used to supply the necessary quantity
of water downstream it, generates power, and protect from flood. On the other hand flood
resulting from dam failure is considered as a national disaster and classified as first degree
accidents for the damage it causes to human life, properties and economic systems.In many
countries the determination of the wave parameters that would follow the collapse of every
large dam is demanded by law to organize the defense of inhabitants and structures in the
valley downstream [15].
         For the knowledge of the researchers there is no study in literature on the failure of
RCC dams. This is the first study on the failure of RCC dams and it opens the door for further
researches.A mathematical model for over-stressing type of RCC dam failure is presented
and a scenario for breach formation is presented.
         Bastora dam, located north east of Iraq, is designed as a RCC gravity dam.Fig. (1)
shows the typical section of Bastora dam. The failure of Bastora RCC dam due to over-
stressing is selected as a case study. The wave parameters that would follow the hypothetical
collapse of Bastora dam are determined.


Dam crest      13m
EL. 897.5m asl             Detail B

                                 No. of steps = 97
                                 All steps with
                                 s:l = 0.9m:0.63m
                                 except the first step with
                                 s:l = 1.1:0.77
                                                              Detail B     0.77   0.63 0.63


                 Drainag gallery
                                              1
                                                                         1.10




                                                  0.7
                                                                                  0.90




  EL. 810m asl
                                                                                         0.90




                        73.62m
                                                                                                0.90




Figure (1): Schematic view of the typical Bastora dam section (All dimensions are in meters)
                                            [16]



                                                        2
International Journal of Civil Engineering and Technology (IJCIET), ISSN 0976 – 6308
(Print), ISSN 0976 – 6316(Online) Volume 4, Issue 2, March - April (2013), © IAEME

2. OBJECTIVES OF THE PRESENT STUDY

   I. Presenting a mathematical model for RCC dam break due to overstress.
   II. Determining the wave parameters that would follow the hypothetical collapse of
       Bastora damdue to overstress.

3. MATHEMATICAL MODEL OF CVC DAM BREAK

        A study of the different conventional concrete (CVC) gravity dam failures indicates
that concrete gravity dams breach by sudden collapse, overturning, sliding away of the dam
due to inadequate design, earthquakes, enemy attack and over-stressing [17]. Failure of
concrete gravity dams are often more catastrophic, because they have less obvious symptoms
prior to failure, collapse may be very rapid, with little or no advance warning [18].
        For the lack of data on the change of breach geometry with time or in order to
simplify the analysis, CVC dams’ break studies were based on the assumption of complete
(or partial) instantaneous removal of the dam [19], [20], [21]. Complete instantaneous failure
of a dam is conservative in the sense of simulating the worst possible downstream flooding
conditions but, in most cases, is unrealistic.

4. MATHEMATICAL MODEL OF RCC DAM BREAK

        RCC gravity dams like CVC gravity dams, they may fail due to sudden collapse,
overturning, sliding away of the dam due to inadequate design, earthquakes, enemy attack
and over-stressing. In this study, the failure of RCC gravity dams due to over-stressing is
investigated.
        According to the characteristics of RCC gravity dams, mentioned in the introduction,
it cannot be assumed that their failure due to overstressing is instantaneous but it can be
assumed gradual with a short time. The hydraulics of instantaneous and gradual collapse of a
dam is in fact quite different. Instantaneous failure of a dam causes a positive wave in the
downstream direction and a negative wave in the upstream direction. In gradual failure, the
breach dimensions grow with time and the reservoir level drops uniformly. Complete gradual
failure of a RCC dam due to overstressing can be assumed in the sense of simulating the
worst case.
        To build a mathematical model for the failure of RCC gravity dams due to
overstressing, the data on the change of breach geometry with time and the breach outflow
equation are required.
        In 2010, two studies for the failure of CVC gravity dams were presented. In the first
study, presented by Asrate [22], the breach width should be taken 0.2-0.5 times the crest
length of the dam and the breach development time should be about 0.2 hour. This means that
the failure of CVC gravity dams is gradual with a short time. This can be used for the gradual
failure of RCC gravity dams since for overstress failure type the breach shape and
development for these two types of dams are equal. For other types of failure such as sliding
failure type the breach shape and development for these two types of dams are not equal
because there are differences in the uplift within the body of the dam and the minimum
sliding factors of safety [9]. In the second study, presented by Welch [23], the breach
outflowof CVC gravity dams is computed by using Eq. (1):


                                              3
International Journal of Civil Engineering and Technology (IJCIET), ISSN 0976 – 6308
(Print), ISSN 0976 – 6316(Online) Volume 4, Issue 2, March - April (2013), © IAEME


                      ܳௗ ൌ 0.9 ‫݄ כ ܾ כ‬ଵ.ହ
                                      ௗ                             ሺ1ሻ

Where Qd = the discharge at the dam site (m3/s), hd = breach head (m) - defined as a depth of
water, and b = breach width (m).
This study is also for the gradual failure of CVC gravity dams. Based on the assumption that
failure of RCC gravity dams due to over stress is gradual, Eq. (1) can be used to compute the
breach outflowof RCC gravity dams.
         In summary, the failure of RCC gravity dams due to overstress is gradual with a short
time. The breach outflow can be computed by using Eq. (1) and the breach width should be
taken 0.2-0.5 times the crest length of the dam and the breach development time should be
about 0.2 hour.

5. THE HYPOTHETICAL FAILURE OF BASTORA DAM DUE TO OVERSTRESS

5.1 Methodology

   I. Computing the reservoir outflow hydrograph using the proposed mathematical model
       with actual field data.
   II. Routing the reservoir outflow hydrograph downstream Bastora dam using the
       computer program HEC-RAS 3.1.3 (2005) (The Hydrologic Engineering Center -
       River Analysis System) to determine the maximum discharges, maximum stages and
       rescue level at selected sections of Bastora River downstream Bastora dam.

5.2 Assumptions

The following assumptions are adopted in this study:

   I. The hypothetical failure of Bastora dam is due to overstressing.
   II. The breach dimensions grow linearly with time.
   III. The beauty of one-dimensional analysis using cross-sectional averaged flow quantities
        is that the details of two-or-three-dimensional variations of these variables in the
        channel can be avoided in the computation while a reasonable solution of the flow can
        be obtained [24]. Therefore, the flow in Bastora River is assumed to be one
        dimensional.
   IV. The cross sections of Bastora River remain constant during the flood routing.
   V. The Manning’s roughness coefficient (n = 0.0255) is assumed to remain constant with
        time and distance along the study reach.

6. RESERVOIR OUTFLOW HYDROGRAPH

Determination of the reservoir outflow hydrograph is divided into two tasks:
   I. Simulating the dam breach.
   II. Routing the reservoir outflow hydrograph through the breached and outlet structures.




                                              4
International Journal of Civil Engineering and Technology (IJCIET), ISSN 0976 – 6308
(Print), ISSN 0976 – 6316(Online) Volume 4, Issue 2, March - April (2013), © IAEME

6.1 Simulating the dam breach

       The breach width is taken 0.2-0.5 times the crest length of Bastora dam and the
breach development time is 0.2 hour. The breach side slopes is taken equal to zero.The
breach shape develops in time from initiation to its ultimate configuration.

6.2 Routing the Reservoir Outflow Hydrograph

       The reservoir outflow hydrograph is computed using the level pool routing method
[25]. The reservoir flood routing process requires determination of the following:

6.2.1 Bastora reservoir elevation-storage relationship
Eq. (2) represents the Bastora Reservoir Storage-Elevation Relationship [16]:

               ܸ‫ ݁݉ݑ݈݋‬ൌ 9.669 ‫ି01 כ‬ହ ሾ‫ .݈ܧ‬െ801.5ሿଷ.ଶସଷ                    ሺ2ሻ

where: El. = reservoir water surface elevation (m asl)
Volume = volume of the reservoir (MCM) at elevation (El.)

6.2.2 The inflow and outflow from the reservoir for the initial condition
The maximum mean monthly outflow from Bastora reservoir was (21.6 m3/s) which occurred
on December 1976 [26]. This flow is assumed to be the initial inflow and outflow from
Bastora reservoir.

6.2.3 The initial elevation of the reservoir water surface before the failure
Bastora reservoir is assumed to be full to its maximum live storage capacity. This
corresponds to spillway sill level of (892.5 m asl).

6.2.4 The inflow to Bastora reservoir at failure time
The flood hydrograph of 1000 years return period computed by [16], shown in Table (1),is
selected as the inflow to Bastora reservoir at failure time.This flood hydrograph represents
the maximum instantaneous inflow hydrograph.

       Table (1): Flood hydrograph for 1000 years Return Period at Bastora Dam [16]

                  Time           Inflow           Time           Inflow
                  (hr)           (CMS)            (hr)           (CMS)
                    0              0.0              7             97.4
                    1             120.9             8             43.8
                    2             510.0             9             18.5
                    3             680.6            10              7.4
                    4             567.0            11              2.9
                    5             364.9            12              0.0
                    6             199.4


                                              5
International Journal of Civil Engineering and Technology (IJCIET), ISSN 0976 – 6308
(Print), ISSN 0976 – 6316(Online) Volume 4, Issue 2, March - April (2013), © IAEME

6.2.5 Modeling outlet works, spillway and breach flows models
It is assumed that at the onset of failure the outlets are locked for any reason. Therefore, their
flows are not modeled.The reservoir water surface elevation was assumed to be at elevation
(892.5m asl) at the onset of failure which is at the spillway sill level. Therefore, the spillway
flows are not modeled.The breach is defined by its sill elevation and width, both given as a
function of time. Eq. (1) is used to calculate breach outflow.

6.3 Bastora Dam Break Simulation

        Five different cases of breach width are investigatedfor the analysis of Bastora dam
break simulations (0.2, 0.3, 0.35, 0.4, and 0.5 times Bastora dam crest length) to determine
the peak outflow. In all these five cases, the initial breach elevation is taken corresponding to
the top of Bastora dam (EL. 897.5 m asl). The final bottom elevation of the breach is taken as
(EL. 810.0 m asl) corresponding to the average foundation level of Bastora dam at the
location of the breach.
        The growth of the breach is proceeded vertically down at a rate of 7.3 m/ minute until
the breach reaches its final elevation and horizontally towards the dam sides at the same rate
until the dam destroyed completely except the dam parts that lie above the reservoir water
surface elevation.
        The breach parameters for the five cases of failure and discharges through the breach
are shown in Table (2). The outflow hydrographs for various breach widths are shown in Fig.
(2). Based on the results shown in Table (2), the breach parameters corresponding to case 5
are selected because the outflow is maximum which represents the worst case. For case 5,
shown in Fig. (2), after about 16 minutes from the dam failure, the peak breach outflow is
(138023.92 m3/s) and after about 99 minutes from the dam failure, the whole volume of the
reservoir is going out to the river reach, and this indicates that the reservoir was depleted at
the end of the simulation time. The breach formation is assumed to consist of two phases. The
sketch of case (5) is presented in Fig. (3).

                      Table (2): The Breach Parameters and Discharges


                                                                Max. dischargethrough the
              Breach width(w)        Breach elevation(m)
 Caseno.                                                        breach (m3/s)
                    (m)
                                       Initial       Final
     1             115.46              897.50        810.00                116218.90

     2             173.19              897.50        810.00                120890.47

     3             202.06              897.50        810.00                124243.07

     4             230.92              897.50        810.00                128171.92

     5             288.65              897.50        810.00                138023.92




                                                 6
International Journal of Civil Engineering and Technology (IJCIET), ISSN 0976 – 6308
(Print), ISSN 0976 – 6316(Online) Volume 4, Issue 2, March - April (2013), © IAEME




                                         7
International Journal of Civil Engineering and Technology (IJCIET), ISSN 0976 – 6308
(Print), ISSN 0976 – 6316(Online) Volume 4, Issue 2, March - April (2013), © IAEME

7. ROUTING THE RESERVOIR OUTFLOW HYDROGRAPH DOWNSTREAM
BASTORA DAM

        The (HEC-RAS) computer program is used to route the reservoir outflow hydrograph
downstream Bastora dam. This software is based on the four-point implicit finite difference
solution of the one dimensional unsteady flow equations of Saint-Venant. The derivation of
Saint-Venant equations, the continuity equation (conservation of mass) and momentum
equation (conservation of momentum) are available in most text books of open channel
hydraulics, e.g., [27], [28], [29].
        The one dimensional Saint-Venant equations,after neglecting the eddy losses, wind
shear effect and lateral flow, are written as:

                   ߲ܳ ߲‫ܣ‬
                     ൅   ൌ0                                         ሺ3ሻ
                   ߲‫ݐ߲ ݔ‬

                   ߲ܳ ߲ሺܳ ଶ ⁄‫ܣ‬ሻ       ߲‫ݖ‬
                      ൅         ൅ ݃‫ ܣ‬൬ ൅ ܵ௙ ൰ ൌ 0                    ሺ4ሻ
                   ߲‫ݐ‬   ߲‫ݔ‬            ߲‫ݔ‬

where Q = discharge (L3T-1), A = cross - sectional area of flow (L2), z = water surface
elevation (L), x = distance along the channel (L), t = time (T), g = gravity - acceleration
constant (LT-2), Sf = friction slope, defined as

                            ݊ଶ ܳ ଶ
                    ܵ௙ ൌ                                            ሺ5ሻ
                           ‫ܣ‬ଶ ܴ ସ⁄ଷ

in whichn = Manning’s roughness coefficient and R = hydraulic radius (L)
       The basic data requirements for performing the one dimensional flow calculations
using HEC-RAS are classified as geometric data and hydraulic data [30].

7.1 Geometric Data
        According to the available data, a reach distance along Bastora River of (14 Km)
downstream Bastora dam is considered. The site of (11) cross sections in this reach is shown
in Fig. (4).




                                             8
International Journal of Civil Engineering and Technology (IJCIET), ISSN 0976 – 6308
(Print), ISSN 0976 – 6316(Online) Volume 4, Issue 2, March - April (2013), © IAEME

7.2 Hydraulic Data

7.2.1 Manning’s Coefficient
         Manning’s roughness coefficient (n = 0.0255) determined by [26] is used in this study
and it is assumed to remain constant with time and distance.

7.2.2 Unsteady Flow Data

7.2.2.1 Initial Condition
        As mentioned in paragraph 6.2.2, the inflow to and outflow from Bastora reservoir for
the initial condition is assumed (21.6m3/s) which is the maximum mean monthly. Therefore,
this outflow from Bastora reservoir is the initial flow for the (14 Km) reach along Bastora
River.Table (3) shows the initial water surface elevation along the study reach for the steady
flow of (21.6 m3/s).
        .
                     Table (3): Bed Channel and Water Surface Elevation

Section      Distance Downstream        Channel Bed Elevation            Water Surface
  No.         Bastora Dam (km)                (m asl)                   Elevation (m asl)
   1                  0.00                        586.20                     586.72
   2                  1.00                        575.70                     576.33
   3                  2.50                        565.40                     565.64
   4                  4.25                        554.90                     555.66
   5                  6.00                        544.70                     545.27
   6                  7.00                        534.30                     534.45
   7                  8.50                        523.90                     524.71
   8                 10.25                        513.50                     514.20
   9                 11.50                        503.10                     503.83
   10                12.75                        492.80                     493.48
   11                14.00                        482.40                     483.47

7.2.2.2 Boundary Conditions

7.2.2.2.1 Upstream Boundary Condition

       The reservoir outflow hydrograph for case (5), shown in Fig.(2), is used as the
upstream boundary condition.

7.2.2.2.2 Downstream Boundary Condition
The downstream boundary condition is a rating curve at the last section of the routed reach.
The best fit equation for the discharge - stage data at the last sectionis:
               ‫ ݖ‬ൌ 483.81 ൅ 0.07471 ܳ ଴.ହ െ 1.407 expሺെܳ ሻ                  ሺ6ሻ
wherez = water surface elevation (m asl) and Q = discharge (m3/s). The coefficient of
determination (R2) for Eq. (6) is 0.997.



                                              9
International Journal of Civil Engineering and Technology (IJCIET), ISSN 0976 – 6308
(Print), ISSN 0976 – 6316(Online) Volume 4, Issue 2, March - April (2013), © IAEME

8. RESULTS OF FLOOD ROUTING

        The computed discharge hydrographs at the (11) sections in Bastora River are shown
in Fig. (5).The computed peak discharges, maximum water levels and their time of
occurrence at the (11) sections in Bastora River are listed in Table (4). The computed peak
discharges and the computed peak elevations at the (11) sections in Bastora River are shown
in Fig. (6) and Fig. (7)respectively.




          Table (4): Peak Discharges, Water Levels and their Time of Occurrence

Section    Peak Discharge         Time of            Peak Elevation         Time of
  No.          (m3/s)         Occurrence (min)          (m asl)         Occurrence (min)

   1          138023.9                16                 593.92                 18
   2          135916.1                18                 591.86                 22
   3          126939.6                22                 576.62                 26
   4          123507.0                26                 576.01                 26
   5          122401.5                26                 561.48                 28
   6          121650.9                28                 548.70                 28
   7          120092.7                28                 538.71                 30
   8          117398.7                30                 528.54                 34
   9          113848.9                32                 516.92                 36
  10          110360.9                32                 508.99                 38
  11          103945.0                36                 508.96                 38



                                            10
International Journal of Civil Engineering and Technology (IJCIET), ISSN 0976 – 6308
(Print), ISSN 0976 – 6316(Online) Volume 4, Issue 2, March - April (2013), © IAEME




                                        11
International Journal of Civil Engineering and Technology (IJCIET), ISSN 0976 – 6308
(Print), ISSN 0976 – 6316(Online) Volume 4, Issue 2, March - April (2013), © IAEME

        Rescue level is an elevation, which is considered safe from flooding. It is usually
taken 1 to 4 meters above the maximum calculated water levels, rounded to the next full
meter [31]. The rescue level is taken 2 meters above the maximum calculated water levels,
rounded to the next full meter. Fig. (8)shows the computed rescue levels along Bastora River
for the selected sections.




9. CONCLUSIONS

I. For the hypothetical failure of Bastora Dam due to overstress, case (5) represents the
    worst case because it gives maximum outflow.
II. The values of computed peak discharges and maximum water levels at the (11) sections
    in Bastora River may be considered high values. The 14 Km reach downstream Bastora
    Dam is flooded in a short time. These are because:
A. The inflow and outflow from the reservoir for the initial condition is taken equal to (21.6
    m3/s) which is the maximum mean monthly outflow from Bastora reservoir.
B. Bastora reservoir is assumed to be full to its maximum live storage capacity before the
    failure of Bastora Dam.
C. The inflow to Bastora reservoir at failure time is taken as the flood hydrograph of 1000
    years return period which is the maximum instantaneous inflow hydrograph.
D. The breach development time is taken equal to 0.2 hour.
According to this, the computed peak discharges and maximum water levels at the (11)
sections in Bastora River correspond to the worst case.



                                             12
International Journal of Civil Engineering and Technology (IJCIET), ISSN 0976 – 6308
(Print), ISSN 0976 – 6316(Online) Volume 4, Issue 2, March - April (2013), © IAEME

10. RECOMMENDATIONS

   I.    A physical model based on Bastora dam data is required to show the validity of the
         proposed mathematical model.
   II. In addition to the overstress failure of RCC gravity dams, they, like CVC gravity
         dams, may fail due to overturning, sliding, earthquakes, or enemy attack.
         Constructing physical models to investigate these types of failures will led to novel
         researches into RCC dams’ failures and new insights into RCC dam breach
         mechanisms.
   III. The last section (section 11) floods after (36 min); therefore, peoples must evacuate
         from this area before this time when the dam breaks.
   IV. The rescue level ranged from (596 m asl) at section (1) to (511 m asl) at section
         (11). This can be used as a rescue boundary to evacuate peoples from the areas
         which are threatened by the flood wave.
   V. The rescue level determined in this study should be taken into consideration when it
         is planned to construct any building downstream Bastora dam.
   VI. When the cross sections within Bastora reservoir are available, the hypothetical
         failure of Bastora dam can be studied by using the dynamic model and the results
         can be compared with the hydrologic model used in this study.
   VII. Cross sections data downstream section (11) are required in order to determine the
         peak discharges and maximum water levels at these sections.
   VIII. Downstreamwater levels can cause backwater effects into the breach, thus reducing
         the outflow considerably. Hence it is required to take into consideration the
         backwater effects.
   IX. It is assumed that the streambed is fixed without erosion or sedimentation. Erosion
         and sedimentation simulation are needed to be investigated.

REFERENCES

[1] ACI 207.5R, “Roller-Compacted Mass Concrete",1999.
[2] ICODS, “Federal Guidelines for Dam Safety: Glossary of Terms", FEMA Publication,
     1-28, 2004.
[3] ACI 309.5R, "Compaction of Roller-Compacted Concrete", 2000.
[4] Hansen, K.D., and Reinhardt, W.G., “Roller- Compacted Concrete Dams”, McGraw-
     Hill, USA, 1991.
[5] ICOLD, “Roller- Compacted Concrete Dams”, Bulletin 126, ICOLD, 2003.
[6] Dunstan, M.R.H., "The State-of-the-Art of RCC Dams in 2002", Proc. of RCC Dams
     Workshop in Iran: 11-22, 2003.
[7] Kimitaka, U., "Roller Compacted Concrete Dam and Utilization of Fly Ash in Japan",
     k.uji @ ecomp.metro-u-ac.jp, 2005.
[8] USACE, "Seismic Design Provisions for Roller Compacted Concrete Dams", EP 1110-
     2-12, 1995.
[9] USACE, “Roller- Compacted Concrete”, EM 1110- 2- 2006, 2000.
[10] USACE, "Structural Design Using the Roller-Compacted Concrete (RCC) Construction
     Process", ETL 1110-2-343, 1993.




                                             13
International Journal of Civil Engineering and Technology (IJCIET), ISSN 0976 – 6308
(Print), ISSN 0976 – 6316(Online) Volume 4, Issue 2, March - April (2013), © IAEME

[11] Batista, E.L., Graca, N.G., Bitten court, R.M. and Andrade, W.P., "First Brazilian
     Experience Using the Horizontally Advancing Sloped layer Construction of RCC at
     Lajeado Dam", Middle East RCC Conference, Jordan, 102-112, 2002.
[12] Nagayama, I., and Jikan, S., "30 Years' History of Roller-Compacted Concrete Dams in
     Japan", 4th International Symposium on RCC Dams, Madrid, 1-14, 2003.
[13] Qiu, T., and Forbes, B.A., "Use of the Sloped Layer Method for Bonded Joints on
     Tannur RCC Dam, Jordan", ANCOLD 2003 Conference on Dams, 1-10, 2003.
[14] Alghazali, N.O., “Mathematical Model of Al-Adhaim Dam Break”, M.Sc. Thesis,
     College of Engineering, Babylon University, 1999.
[15] Rajar, R., "Mathematical simulation of dam-break flow", J. Hydr. Div., ASCE, 104(7),
     1011-1025, 1978.
[16] Alghazali, N.O., “Evaluation of Some Design Parameters of Roller Compacted Concrete
     Dams”, Ph.D. Thesis, Building and Construction Engineering Department, University of
     Technology, Iraq, 2007.
[17] Centre for Inter disciplinary Study of Mountain and Hill Environmental (CISMHE),
     “Dam Break Analysis & Disaster Management Plan Report”, University of Delhi, 2010.
[18] Ministry of Environment, Lands and Parks Water Management Branch (LPWMB),
     “Inspection & Maintenance of Dams. Dam Safety Guidelines”, British, Columbia, 1998.
[19] Macdonald, T.C. and Monopolis, J.L., "Breaching characteristics of dam failures", J.
     Hydr. Div., ASCE, 110(5), 567-586, 1984.
[20] Wurbs, R. A., “Dam Breach Flood Wave Models”, Journal of Hydraulic Engineering,
     Vol. 113, No. 1, pp. 29-46, 1987.
[21] Featherston, R.E. and Nalluri, C., “Civil Engineering Hydraulics”, 3rd ed., Blackwell
     Since, UK, 1995.
[22] Asrate, A.K., “Sensitivity Analysis of Dam Breach Parameters”, M.Sc. Thesis,
     Engineering College, California State University, 2010.
[23] Welch, D., “Breach Parameter Estimator and Dam Break Rules of Thumb
     Documentation”, V. 2. 30, 2010.
[24] Xia, R. and Yen, B.C., "Significance of averaging coefficients in open channel flow
     equations", J. Hydr. Div., ASCE, 120(2), 169-189, 1994.
[25] Chow, V.T., Maidment, D.R. and Mays, L.W., “Applied Hydrology”, McGraw-Hill,
     New York, 1988.
[26] El Concorde Consultant Engineers, “Bastora Dam and Irrigation Project”, Planning
     Report, Volume-1, Dam Planning Report, Republic of Iraq, Ministry of Water
     Resources, General Directorate for Engineering Designs, 2006.
[27] Henderson, F.M., “Open Channel Flow”, Macmillan, New York, 1966.
[28] Attari, J. and Yazdandoost, F., “Hydraulics of Dams & River Structures”, A. A.
     Balkema, London, 2004.
[29] Chaudhry, M.H., “Open Channel Flow”, 2nd ed., Columbia, 2008.
[30] HEC-RAS, “User's Manual”, Version 3.1.3, USACE, Hydrologic Engineering Center,
     Davis, California, 2005.
[31] Swiss Consultants, “Mosul Flood Wave”, 1984.
[32] Karim M Pathan, “Finite Element Analysis Of 99.60 M High Roller Compacted
     Concrete (RCC) Gravity Dam - Special Emphasis on Dynamic Analysis” International
     Journal of Civil Engineering & Technology (IJCIET), Volume 3, Issue 2, 2012,
     pp. 387 - 391, ISSN Print: 0976 – 6308, ISSN Online: 0976 – 6316, Published by
     IAEME.

                                           14

Weitere ähnliche Inhalte

Was ist angesagt?

Seismic behavior of rc elevated water tankunder different types of staging pa...
Seismic behavior of rc elevated water tankunder different types of staging pa...Seismic behavior of rc elevated water tankunder different types of staging pa...
Seismic behavior of rc elevated water tankunder different types of staging pa...CADmantra Technologies
 
Time History Analysis of Circular and Rectangular Elevated Water Storage Tank...
Time History Analysis of Circular and Rectangular Elevated Water Storage Tank...Time History Analysis of Circular and Rectangular Elevated Water Storage Tank...
Time History Analysis of Circular and Rectangular Elevated Water Storage Tank...Dr. Amarjeet Singh
 
synopsis on design and estimation of intze tank
synopsis on design and estimation of intze tanksynopsis on design and estimation of intze tank
synopsis on design and estimation of intze tankganesh sharma
 
Introduction & under ground water tank problem
Introduction & under ground water tank problemIntroduction & under ground water tank problem
Introduction & under ground water tank problemdhineshkumar002
 
Seismic Analysis of Elevated Water Tank
Seismic Analysis of Elevated Water TankSeismic Analysis of Elevated Water Tank
Seismic Analysis of Elevated Water TankKalaivanan Murthy
 
Chapter 2 Of Rock Engineering
Chapter 2 Of  Rock  EngineeringChapter 2 Of  Rock  Engineering
Chapter 2 Of Rock EngineeringNgo Hung Long
 
Physical model for coastal inlet
Physical model for coastal inletPhysical model for coastal inlet
Physical model for coastal inletNguyen Thanh Luan
 
Elevated water tank
Elevated water tankElevated water tank
Elevated water tankAamir Patni
 
introduction of intze tank
introduction of intze tankintroduction of intze tank
introduction of intze tankjenish patel
 
200%20 questions%20and%20answers%20on%20ce%20works
200%20 questions%20and%20answers%20on%20ce%20works200%20 questions%20and%20answers%20on%20ce%20works
200%20 questions%20and%20answers%20on%20ce%20worksajaipurushothaman
 
IRJET- Design of Overhead RCC Rectangular Water Tank by using Working Stre...
IRJET- 	  Design of Overhead RCC Rectangular Water Tank by using Working Stre...IRJET- 	  Design of Overhead RCC Rectangular Water Tank by using Working Stre...
IRJET- Design of Overhead RCC Rectangular Water Tank by using Working Stre...IRJET Journal
 
Complete design of r.c.c over head tank & boq estimate
Complete design of r.c.c over head tank & boq estimateComplete design of r.c.c over head tank & boq estimate
Complete design of r.c.c over head tank & boq estimateHarish Mahavar
 
Review on seismic analysis of elevated water tank 2
Review on seismic analysis of elevated water tank 2Review on seismic analysis of elevated water tank 2
Review on seismic analysis of elevated water tank 2IAEME Publication
 
Seminar at University of Western Sydney
Seminar at University of Western SydneySeminar at University of Western Sydney
Seminar at University of Western SydneyQuang Huy Nguyen
 
Rectangular tank example_latest
Rectangular tank example_latestRectangular tank example_latest
Rectangular tank example_latestVedachalam Mani
 
Embankment dam engineering,
Embankment dam engineering,Embankment dam engineering,
Embankment dam engineering,shaymaa17
 

Was ist angesagt? (20)

Intze tank design
Intze tank designIntze tank design
Intze tank design
 
Seismic behavior of rc elevated water tankunder different types of staging pa...
Seismic behavior of rc elevated water tankunder different types of staging pa...Seismic behavior of rc elevated water tankunder different types of staging pa...
Seismic behavior of rc elevated water tankunder different types of staging pa...
 
Time History Analysis of Circular and Rectangular Elevated Water Storage Tank...
Time History Analysis of Circular and Rectangular Elevated Water Storage Tank...Time History Analysis of Circular and Rectangular Elevated Water Storage Tank...
Time History Analysis of Circular and Rectangular Elevated Water Storage Tank...
 
synopsis on design and estimation of intze tank
synopsis on design and estimation of intze tanksynopsis on design and estimation of intze tank
synopsis on design and estimation of intze tank
 
Introduction & under ground water tank problem
Introduction & under ground water tank problemIntroduction & under ground water tank problem
Introduction & under ground water tank problem
 
Water tank
Water tankWater tank
Water tank
 
Seismic Analysis of Elevated Water Tank
Seismic Analysis of Elevated Water TankSeismic Analysis of Elevated Water Tank
Seismic Analysis of Elevated Water Tank
 
Chapter 2 Of Rock Engineering
Chapter 2 Of  Rock  EngineeringChapter 2 Of  Rock  Engineering
Chapter 2 Of Rock Engineering
 
Physical model for coastal inlet
Physical model for coastal inletPhysical model for coastal inlet
Physical model for coastal inlet
 
Intze tank design
Intze tank designIntze tank design
Intze tank design
 
Elevated water tank
Elevated water tankElevated water tank
Elevated water tank
 
introduction of intze tank
introduction of intze tankintroduction of intze tank
introduction of intze tank
 
200%20 questions%20and%20answers%20on%20ce%20works
200%20 questions%20and%20answers%20on%20ce%20works200%20 questions%20and%20answers%20on%20ce%20works
200%20 questions%20and%20answers%20on%20ce%20works
 
IRJET- Design of Overhead RCC Rectangular Water Tank by using Working Stre...
IRJET- 	  Design of Overhead RCC Rectangular Water Tank by using Working Stre...IRJET- 	  Design of Overhead RCC Rectangular Water Tank by using Working Stre...
IRJET- Design of Overhead RCC Rectangular Water Tank by using Working Stre...
 
Complete design of r.c.c over head tank & boq estimate
Complete design of r.c.c over head tank & boq estimateComplete design of r.c.c over head tank & boq estimate
Complete design of r.c.c over head tank & boq estimate
 
Review on seismic analysis of elevated water tank 2
Review on seismic analysis of elevated water tank 2Review on seismic analysis of elevated water tank 2
Review on seismic analysis of elevated water tank 2
 
Seminar at University of Western Sydney
Seminar at University of Western SydneySeminar at University of Western Sydney
Seminar at University of Western Sydney
 
Intze ppt
Intze pptIntze ppt
Intze ppt
 
Rectangular tank example_latest
Rectangular tank example_latestRectangular tank example_latest
Rectangular tank example_latest
 
Embankment dam engineering,
Embankment dam engineering,Embankment dam engineering,
Embankment dam engineering,
 

Andere mochten auch

ISPS: Security Awareness Training / Designated Security Duty
ISPS: Security Awareness Training / Designated Security DutyISPS: Security Awareness Training / Designated Security Duty
ISPS: Security Awareness Training / Designated Security DutyCapt Moin Uddin
 
Especialidades y niveles_por_actividad_desempenada_a_bordo
Especialidades y niveles_por_actividad_desempenada_a_bordoEspecialidades y niveles_por_actividad_desempenada_a_bordo
Especialidades y niveles_por_actividad_desempenada_a_bordoMiguel Diaz Medina
 
Port operations & management slideshow
Port operations & management slideshowPort operations & management slideshow
Port operations & management slideshowVijay Hiranandani
 
Common symptoms of food borne illness
Common symptoms of food borne illnessCommon symptoms of food borne illness
Common symptoms of food borne illnessMiguel Diaz Medina
 
Uscg general deck questions master's license (question)`
Uscg general deck questions  master's license (question)`Uscg general deck questions  master's license (question)`
Uscg general deck questions master's license (question)`Miguel Diaz Medina
 
Training isps codeon board mv. ctp fortune
Training isps codeon board mv. ctp fortuneTraining isps codeon board mv. ctp fortune
Training isps codeon board mv. ctp fortuneCapt. Persobi Waldemar
 
Maritime (isps code) regulations 2014
Maritime (isps code) regulations 2014Maritime (isps code) regulations 2014
Maritime (isps code) regulations 2014captlouis
 
A. security threats and patterns
A. security threats and patternsA. security threats and patterns
A. security threats and patternsNoel Tan
 
Anti ship piracy training
Anti ship piracy trainingAnti ship piracy training
Anti ship piracy trainingNoel Tan
 
pfso cert english.PDF
pfso cert  english.PDFpfso cert  english.PDF
pfso cert english.PDFJock ANDRE
 
Ship Security Training Manual (Sample)
Ship Security Training Manual (Sample)Ship Security Training Manual (Sample)
Ship Security Training Manual (Sample)Pawanexh Kohli
 

Andere mochten auch (20)

ISPS: Security Awareness Training / Designated Security Duty
ISPS: Security Awareness Training / Designated Security DutyISPS: Security Awareness Training / Designated Security Duty
ISPS: Security Awareness Training / Designated Security Duty
 
Especialidades y niveles_por_actividad_desempenada_a_bordo
Especialidades y niveles_por_actividad_desempenada_a_bordoEspecialidades y niveles_por_actividad_desempenada_a_bordo
Especialidades y niveles_por_actividad_desempenada_a_bordo
 
Port operations & management slideshow
Port operations & management slideshowPort operations & management slideshow
Port operations & management slideshow
 
Omamarine
OmamarineOmamarine
Omamarine
 
Isps code
Isps codeIsps code
Isps code
 
Common symptoms of food borne illness
Common symptoms of food borne illnessCommon symptoms of food borne illness
Common symptoms of food borne illness
 
Uscg general deck questions master's license (question)`
Uscg general deck questions  master's license (question)`Uscg general deck questions  master's license (question)`
Uscg general deck questions master's license (question)`
 
Ballast Water Management Convention
Ballast Water Management ConventionBallast Water Management Convention
Ballast Water Management Convention
 
Ism code reminder lesson
Ism code reminder lessonIsm code reminder lesson
Ism code reminder lesson
 
Training isps codeon board mv. ctp fortune
Training isps codeon board mv. ctp fortuneTraining isps codeon board mv. ctp fortune
Training isps codeon board mv. ctp fortune
 
OPA vs MARPOL
OPA vs MARPOLOPA vs MARPOL
OPA vs MARPOL
 
Maritime (isps code) regulations 2014
Maritime (isps code) regulations 2014Maritime (isps code) regulations 2014
Maritime (isps code) regulations 2014
 
Risk assessment presentasi
Risk assessment presentasiRisk assessment presentasi
Risk assessment presentasi
 
Man Over Board Drill
Man Over Board DrillMan Over Board Drill
Man Over Board Drill
 
Kepil (mooring buoy)
Kepil (mooring buoy)Kepil (mooring buoy)
Kepil (mooring buoy)
 
(External) initial audit
(External) initial audit(External) initial audit
(External) initial audit
 
A. security threats and patterns
A. security threats and patternsA. security threats and patterns
A. security threats and patterns
 
Anti ship piracy training
Anti ship piracy trainingAnti ship piracy training
Anti ship piracy training
 
pfso cert english.PDF
pfso cert  english.PDFpfso cert  english.PDF
pfso cert english.PDF
 
Ship Security Training Manual (Sample)
Ship Security Training Manual (Sample)Ship Security Training Manual (Sample)
Ship Security Training Manual (Sample)
 

Ähnlich wie Mathematical model ofrcc dam breakbastorarcc dam as a case study

Seismic Analysis for Safety of Dams
Seismic Analysis for Safety of DamsSeismic Analysis for Safety of Dams
Seismic Analysis for Safety of DamsIOSR Journals
 
IRJET - Behaviour of Over Head Tank with Hydrodynamic Forces
IRJET - Behaviour of Over Head Tank with Hydrodynamic ForcesIRJET - Behaviour of Over Head Tank with Hydrodynamic Forces
IRJET - Behaviour of Over Head Tank with Hydrodynamic ForcesIRJET Journal
 
SUGGESTING DEFLECTION EXPRESSIONS FOR RC BEAMS
SUGGESTING DEFLECTION EXPRESSIONS FOR RC BEAMSSUGGESTING DEFLECTION EXPRESSIONS FOR RC BEAMS
SUGGESTING DEFLECTION EXPRESSIONS FOR RC BEAMSIAEME Publication
 
SUGGESTING DEFLECTION EXPRESSIONS FOR RC BEAMS
SUGGESTING DEFLECTION EXPRESSIONS FOR RC BEAMSSUGGESTING DEFLECTION EXPRESSIONS FOR RC BEAMS
SUGGESTING DEFLECTION EXPRESSIONS FOR RC BEAMSIAEME Publication
 
SUGGESTING DEFLECTION EXPRESSIONS FOR RC BEAMS
SUGGESTING DEFLECTION EXPRESSIONS FOR RC BEAMSSUGGESTING DEFLECTION EXPRESSIONS FOR RC BEAMS
SUGGESTING DEFLECTION EXPRESSIONS FOR RC BEAMSIAEME Publication
 
Tank Design Comparisons.pdf
Tank Design Comparisons.pdfTank Design Comparisons.pdf
Tank Design Comparisons.pdfssuserf75a23
 
GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16Leo Youngman
 
Reservoir hydrostatic pressure effect on roller compacted concrete (rcc) dams
Reservoir hydrostatic pressure effect on roller compacted concrete (rcc) damsReservoir hydrostatic pressure effect on roller compacted concrete (rcc) dams
Reservoir hydrostatic pressure effect on roller compacted concrete (rcc) damsRamin Vaghei
 
IRJET- Study on Comparison Analysis of Circular and Intze Water Tank on Slopi...
IRJET- Study on Comparison Analysis of Circular and Intze Water Tank on Slopi...IRJET- Study on Comparison Analysis of Circular and Intze Water Tank on Slopi...
IRJET- Study on Comparison Analysis of Circular and Intze Water Tank on Slopi...IRJET Journal
 
A Study of Dynamic Response of Circular Water Tank with Baffle Walls
A Study of Dynamic Response of Circular Water Tank with Baffle WallsA Study of Dynamic Response of Circular Water Tank with Baffle Walls
A Study of Dynamic Response of Circular Water Tank with Baffle WallsIRJET Journal
 
WS-D1-CEWRE_PPT.pdf
WS-D1-CEWRE_PPT.pdfWS-D1-CEWRE_PPT.pdf
WS-D1-CEWRE_PPT.pdfssuserca460e
 
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...Egyptian Engineers Association
 
A STUDY ON THE SEISMIC RESPONSE OF ELEVATED WATER TANK
A STUDY ON THE SEISMIC RESPONSE OF ELEVATED WATER TANKA STUDY ON THE SEISMIC RESPONSE OF ELEVATED WATER TANK
A STUDY ON THE SEISMIC RESPONSE OF ELEVATED WATER TANKIRJET Journal
 
IMPROVING THE STRUCTURAL EFFICIENCY OF STEEL TRUSSES BY COMPARATIVE STUDY
IMPROVING THE STRUCTURAL EFFICIENCY OF STEEL TRUSSES BY COMPARATIVE STUDYIMPROVING THE STRUCTURAL EFFICIENCY OF STEEL TRUSSES BY COMPARATIVE STUDY
IMPROVING THE STRUCTURAL EFFICIENCY OF STEEL TRUSSES BY COMPARATIVE STUDYIRJET Journal
 
FORECASTING THE TECHNICAL RESOURCE OF THE MECHANICAL AND CIVIL BUILDING STRUC...
FORECASTING THE TECHNICAL RESOURCE OF THE MECHANICAL AND CIVIL BUILDING STRUC...FORECASTING THE TECHNICAL RESOURCE OF THE MECHANICAL AND CIVIL BUILDING STRUC...
FORECASTING THE TECHNICAL RESOURCE OF THE MECHANICAL AND CIVIL BUILDING STRUC...IAEME Publication
 
IRJET - Dynamic Analysis of Steel Truss Bridge under Various Combinational Mo...
IRJET - Dynamic Analysis of Steel Truss Bridge under Various Combinational Mo...IRJET - Dynamic Analysis of Steel Truss Bridge under Various Combinational Mo...
IRJET - Dynamic Analysis of Steel Truss Bridge under Various Combinational Mo...IRJET Journal
 
Design of Skew Culvert Analysis: A review
Design of Skew Culvert Analysis: A reviewDesign of Skew Culvert Analysis: A review
Design of Skew Culvert Analysis: A reviewIRJET Journal
 

Ähnlich wie Mathematical model ofrcc dam breakbastorarcc dam as a case study (20)

Seismic Analysis for Safety of Dams
Seismic Analysis for Safety of DamsSeismic Analysis for Safety of Dams
Seismic Analysis for Safety of Dams
 
IRJET - Behaviour of Over Head Tank with Hydrodynamic Forces
IRJET - Behaviour of Over Head Tank with Hydrodynamic ForcesIRJET - Behaviour of Over Head Tank with Hydrodynamic Forces
IRJET - Behaviour of Over Head Tank with Hydrodynamic Forces
 
SUGGESTING DEFLECTION EXPRESSIONS FOR RC BEAMS
SUGGESTING DEFLECTION EXPRESSIONS FOR RC BEAMSSUGGESTING DEFLECTION EXPRESSIONS FOR RC BEAMS
SUGGESTING DEFLECTION EXPRESSIONS FOR RC BEAMS
 
SUGGESTING DEFLECTION EXPRESSIONS FOR RC BEAMS
SUGGESTING DEFLECTION EXPRESSIONS FOR RC BEAMSSUGGESTING DEFLECTION EXPRESSIONS FOR RC BEAMS
SUGGESTING DEFLECTION EXPRESSIONS FOR RC BEAMS
 
SUGGESTING DEFLECTION EXPRESSIONS FOR RC BEAMS
SUGGESTING DEFLECTION EXPRESSIONS FOR RC BEAMSSUGGESTING DEFLECTION EXPRESSIONS FOR RC BEAMS
SUGGESTING DEFLECTION EXPRESSIONS FOR RC BEAMS
 
Tank Design Comparisons.pdf
Tank Design Comparisons.pdfTank Design Comparisons.pdf
Tank Design Comparisons.pdf
 
GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16
 
Reservoir hydrostatic pressure effect on roller compacted concrete (rcc) dams
Reservoir hydrostatic pressure effect on roller compacted concrete (rcc) damsReservoir hydrostatic pressure effect on roller compacted concrete (rcc) dams
Reservoir hydrostatic pressure effect on roller compacted concrete (rcc) dams
 
IRJET- Study on Comparison Analysis of Circular and Intze Water Tank on Slopi...
IRJET- Study on Comparison Analysis of Circular and Intze Water Tank on Slopi...IRJET- Study on Comparison Analysis of Circular and Intze Water Tank on Slopi...
IRJET- Study on Comparison Analysis of Circular and Intze Water Tank on Slopi...
 
A Study of Dynamic Response of Circular Water Tank with Baffle Walls
A Study of Dynamic Response of Circular Water Tank with Baffle WallsA Study of Dynamic Response of Circular Water Tank with Baffle Walls
A Study of Dynamic Response of Circular Water Tank with Baffle Walls
 
MODELLING AND VIBRATION ANALYSIS OF REINFORCED CONCRETE BRIDGE
MODELLING AND VIBRATION ANALYSIS OF REINFORCED CONCRETE BRIDGEMODELLING AND VIBRATION ANALYSIS OF REINFORCED CONCRETE BRIDGE
MODELLING AND VIBRATION ANALYSIS OF REINFORCED CONCRETE BRIDGE
 
WS-D1-CEWRE_PPT.pdf
WS-D1-CEWRE_PPT.pdfWS-D1-CEWRE_PPT.pdf
WS-D1-CEWRE_PPT.pdf
 
Hospital building project
Hospital building projectHospital building project
Hospital building project
 
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
 
A STUDY ON THE SEISMIC RESPONSE OF ELEVATED WATER TANK
A STUDY ON THE SEISMIC RESPONSE OF ELEVATED WATER TANKA STUDY ON THE SEISMIC RESPONSE OF ELEVATED WATER TANK
A STUDY ON THE SEISMIC RESPONSE OF ELEVATED WATER TANK
 
IMPROVING THE STRUCTURAL EFFICIENCY OF STEEL TRUSSES BY COMPARATIVE STUDY
IMPROVING THE STRUCTURAL EFFICIENCY OF STEEL TRUSSES BY COMPARATIVE STUDYIMPROVING THE STRUCTURAL EFFICIENCY OF STEEL TRUSSES BY COMPARATIVE STUDY
IMPROVING THE STRUCTURAL EFFICIENCY OF STEEL TRUSSES BY COMPARATIVE STUDY
 
FORECASTING THE TECHNICAL RESOURCE OF THE MECHANICAL AND CIVIL BUILDING STRUC...
FORECASTING THE TECHNICAL RESOURCE OF THE MECHANICAL AND CIVIL BUILDING STRUC...FORECASTING THE TECHNICAL RESOURCE OF THE MECHANICAL AND CIVIL BUILDING STRUC...
FORECASTING THE TECHNICAL RESOURCE OF THE MECHANICAL AND CIVIL BUILDING STRUC...
 
IRJET - Dynamic Analysis of Steel Truss Bridge under Various Combinational Mo...
IRJET - Dynamic Analysis of Steel Truss Bridge under Various Combinational Mo...IRJET - Dynamic Analysis of Steel Truss Bridge under Various Combinational Mo...
IRJET - Dynamic Analysis of Steel Truss Bridge under Various Combinational Mo...
 
Ijciet 06 09_018
Ijciet 06 09_018Ijciet 06 09_018
Ijciet 06 09_018
 
Design of Skew Culvert Analysis: A review
Design of Skew Culvert Analysis: A reviewDesign of Skew Culvert Analysis: A review
Design of Skew Culvert Analysis: A review
 

Mehr von IAEME Publication

IAEME_Publication_Call_for_Paper_September_2022.pdf
IAEME_Publication_Call_for_Paper_September_2022.pdfIAEME_Publication_Call_for_Paper_September_2022.pdf
IAEME_Publication_Call_for_Paper_September_2022.pdfIAEME Publication
 
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...IAEME Publication
 
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURSA STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURSIAEME Publication
 
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURSBROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURSIAEME Publication
 
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONS
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONSDETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONS
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONSIAEME Publication
 
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONS
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONSANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONS
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONSIAEME Publication
 
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINO
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINOVOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINO
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINOIAEME Publication
 
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...IAEME Publication
 
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMY
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMYVISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMY
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMYIAEME Publication
 
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...IAEME Publication
 
GANDHI ON NON-VIOLENT POLICE
GANDHI ON NON-VIOLENT POLICEGANDHI ON NON-VIOLENT POLICE
GANDHI ON NON-VIOLENT POLICEIAEME Publication
 
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...IAEME Publication
 
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...IAEME Publication
 
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...IAEME Publication
 
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...IAEME Publication
 
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...IAEME Publication
 
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...IAEME Publication
 
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...IAEME Publication
 
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...IAEME Publication
 
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENT
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENTA MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENT
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENTIAEME Publication
 

Mehr von IAEME Publication (20)

IAEME_Publication_Call_for_Paper_September_2022.pdf
IAEME_Publication_Call_for_Paper_September_2022.pdfIAEME_Publication_Call_for_Paper_September_2022.pdf
IAEME_Publication_Call_for_Paper_September_2022.pdf
 
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...
 
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURSA STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
 
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURSBROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
 
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONS
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONSDETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONS
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONS
 
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONS
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONSANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONS
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONS
 
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINO
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINOVOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINO
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINO
 
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...
 
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMY
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMYVISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMY
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMY
 
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...
 
GANDHI ON NON-VIOLENT POLICE
GANDHI ON NON-VIOLENT POLICEGANDHI ON NON-VIOLENT POLICE
GANDHI ON NON-VIOLENT POLICE
 
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
 
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
 
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
 
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
 
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...
 
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
 
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
 
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
 
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENT
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENTA MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENT
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENT
 

Mathematical model ofrcc dam breakbastorarcc dam as a case study

  • 1. INTERNATIONAL JOURNAL OF CIVIL ENGINEERING AND International Journal of Civil Engineering and Technology (IJCIET), ISSN 0976 – 6308 (Print), ISSN 0976 – 6316(Online) Volume 4, Issue 2, March - April (2013), © IAEME TECHNOLOGY (IJCIET) ISSN 0976 – 6308 (Print) ISSN 0976 – 6316(Online) Volume 4, Issue 2, March - April (2013), pp. 01-14 IJCIET © IAEME: www.iaeme.com/ijciet.asp Journal Impact Factor (2013): 5.3277 (Calculated by GISI) © IAEME www.jifactor.com MATHEMATICAL MODEL OF RCC DAM BREAK BASTORA RCC DAM AS A CASE STUDY NajmObaidSalim Alghazali1 and Dilshad A.H. Alhadrawi2 (1) Corresponding author, Asst. Prof. Doctor, Civil Engineering Department, Babylon University, Iraq. (2) M.Sc. Student, Civil Engineering Department, Babylon University, Iraq. ABSTRACT This is the first study on the failure of roller compacted concrete (RCC) dams. A mathematical model for over-stressing type of RCC dam failure is presented and a scenario for breach formation is presented. The hypothetical failure of Bastora dam, a RCC dam located north east of Iraq, due to overstress is selected as a case study. The reservoir outflow hydrograph is computed using the proposed mathematical model and then the outflow is routed downstream Bastora dam. The maximum water levels, maximum discharges and rescue level at the available (11) sections of Bastora River downstream Bastora dam are determined. Keywords: HEC- RAS, level pool routing method, mathematical model for RCC dam break, over-stressing failure, roller compacted concrete (RCC) dams 1. INTRODUCTION ACI 207.5R [1] defines Roller-Compacted Concrete (RCC) as "a concrete of no- slump consistency in its unhardened state that is transported, placed, and compacted using earth and rock-fill construction equipment."ICODS [2] defines RCC damas" a concrete gravity dam constructed by the use of a dry mix concrete transported by conventional construction equipment and compacted by rolling, usually with vibratory rollers." RCC is an economical method and accepted material for constructing dams and rehabilitating and modifying existing concrete and embankment dams [1], [3], [4].The worldwide acceptance of RCC dams is due to their low cost, reduction period of construction, and successful performance [5].RCC dams were constructed in all types of climates and in all types of countries from the most developed to the still developing [6].There are more than 250 RCC dams constructed throughout the world [7]. 1
  • 2. International Journal of Civil Engineering and Technology (IJCIET), ISSN 0976 – 6308 (Print), ISSN 0976 – 6316(Online) Volume 4, Issue 2, March - April (2013), © IAEME RCC gravity dams are designed to the same criteria as conventional concrete (CVC) gravity dams with respect to stability and allowable stresses in the concrete [5], [8], [9]. However, there are differences in the uplift within the body of the dam and the minimum sliding factors of safety [9]. One significant difference between a RCC dam and a CVC dam is the continuous placing of a horizontal lift of concrete from one abutment to the other, rather than constructing the dam in a series of separate monoliths [3].Lift thicknesses depend on the placement size, production capacity of the concrete batch plant, mixture proportions, and compaction equipment [9], [10].There is no limited lift thickness used in all RCC dams. The lift thicknesses used in RCC dams are 0.30 m (1 layer) [11], 0.60 m (composed of four 0.15 m layers) [9], 2 m (composed of eight layers of 0.25 m) [5], and 0.75 to 1 m (0.3 m layers) [7], [12]. By the use of sloped layer method (SLM), the lift thickness is 3 to 4 m [13]. A dam is a sword of two limits [14]. It is mainly used to supply the necessary quantity of water downstream it, generates power, and protect from flood. On the other hand flood resulting from dam failure is considered as a national disaster and classified as first degree accidents for the damage it causes to human life, properties and economic systems.In many countries the determination of the wave parameters that would follow the collapse of every large dam is demanded by law to organize the defense of inhabitants and structures in the valley downstream [15]. For the knowledge of the researchers there is no study in literature on the failure of RCC dams. This is the first study on the failure of RCC dams and it opens the door for further researches.A mathematical model for over-stressing type of RCC dam failure is presented and a scenario for breach formation is presented. Bastora dam, located north east of Iraq, is designed as a RCC gravity dam.Fig. (1) shows the typical section of Bastora dam. The failure of Bastora RCC dam due to over- stressing is selected as a case study. The wave parameters that would follow the hypothetical collapse of Bastora dam are determined. Dam crest 13m EL. 897.5m asl Detail B No. of steps = 97 All steps with s:l = 0.9m:0.63m except the first step with s:l = 1.1:0.77 Detail B 0.77 0.63 0.63 Drainag gallery 1 1.10 0.7 0.90 EL. 810m asl 0.90 73.62m 0.90 Figure (1): Schematic view of the typical Bastora dam section (All dimensions are in meters) [16] 2
  • 3. International Journal of Civil Engineering and Technology (IJCIET), ISSN 0976 – 6308 (Print), ISSN 0976 – 6316(Online) Volume 4, Issue 2, March - April (2013), © IAEME 2. OBJECTIVES OF THE PRESENT STUDY I. Presenting a mathematical model for RCC dam break due to overstress. II. Determining the wave parameters that would follow the hypothetical collapse of Bastora damdue to overstress. 3. MATHEMATICAL MODEL OF CVC DAM BREAK A study of the different conventional concrete (CVC) gravity dam failures indicates that concrete gravity dams breach by sudden collapse, overturning, sliding away of the dam due to inadequate design, earthquakes, enemy attack and over-stressing [17]. Failure of concrete gravity dams are often more catastrophic, because they have less obvious symptoms prior to failure, collapse may be very rapid, with little or no advance warning [18]. For the lack of data on the change of breach geometry with time or in order to simplify the analysis, CVC dams’ break studies were based on the assumption of complete (or partial) instantaneous removal of the dam [19], [20], [21]. Complete instantaneous failure of a dam is conservative in the sense of simulating the worst possible downstream flooding conditions but, in most cases, is unrealistic. 4. MATHEMATICAL MODEL OF RCC DAM BREAK RCC gravity dams like CVC gravity dams, they may fail due to sudden collapse, overturning, sliding away of the dam due to inadequate design, earthquakes, enemy attack and over-stressing. In this study, the failure of RCC gravity dams due to over-stressing is investigated. According to the characteristics of RCC gravity dams, mentioned in the introduction, it cannot be assumed that their failure due to overstressing is instantaneous but it can be assumed gradual with a short time. The hydraulics of instantaneous and gradual collapse of a dam is in fact quite different. Instantaneous failure of a dam causes a positive wave in the downstream direction and a negative wave in the upstream direction. In gradual failure, the breach dimensions grow with time and the reservoir level drops uniformly. Complete gradual failure of a RCC dam due to overstressing can be assumed in the sense of simulating the worst case. To build a mathematical model for the failure of RCC gravity dams due to overstressing, the data on the change of breach geometry with time and the breach outflow equation are required. In 2010, two studies for the failure of CVC gravity dams were presented. In the first study, presented by Asrate [22], the breach width should be taken 0.2-0.5 times the crest length of the dam and the breach development time should be about 0.2 hour. This means that the failure of CVC gravity dams is gradual with a short time. This can be used for the gradual failure of RCC gravity dams since for overstress failure type the breach shape and development for these two types of dams are equal. For other types of failure such as sliding failure type the breach shape and development for these two types of dams are not equal because there are differences in the uplift within the body of the dam and the minimum sliding factors of safety [9]. In the second study, presented by Welch [23], the breach outflowof CVC gravity dams is computed by using Eq. (1): 3
  • 4. International Journal of Civil Engineering and Technology (IJCIET), ISSN 0976 – 6308 (Print), ISSN 0976 – 6316(Online) Volume 4, Issue 2, March - April (2013), © IAEME ܳௗ ൌ 0.9 ‫݄ כ ܾ כ‬ଵ.ହ ௗ ሺ1ሻ Where Qd = the discharge at the dam site (m3/s), hd = breach head (m) - defined as a depth of water, and b = breach width (m). This study is also for the gradual failure of CVC gravity dams. Based on the assumption that failure of RCC gravity dams due to over stress is gradual, Eq. (1) can be used to compute the breach outflowof RCC gravity dams. In summary, the failure of RCC gravity dams due to overstress is gradual with a short time. The breach outflow can be computed by using Eq. (1) and the breach width should be taken 0.2-0.5 times the crest length of the dam and the breach development time should be about 0.2 hour. 5. THE HYPOTHETICAL FAILURE OF BASTORA DAM DUE TO OVERSTRESS 5.1 Methodology I. Computing the reservoir outflow hydrograph using the proposed mathematical model with actual field data. II. Routing the reservoir outflow hydrograph downstream Bastora dam using the computer program HEC-RAS 3.1.3 (2005) (The Hydrologic Engineering Center - River Analysis System) to determine the maximum discharges, maximum stages and rescue level at selected sections of Bastora River downstream Bastora dam. 5.2 Assumptions The following assumptions are adopted in this study: I. The hypothetical failure of Bastora dam is due to overstressing. II. The breach dimensions grow linearly with time. III. The beauty of one-dimensional analysis using cross-sectional averaged flow quantities is that the details of two-or-three-dimensional variations of these variables in the channel can be avoided in the computation while a reasonable solution of the flow can be obtained [24]. Therefore, the flow in Bastora River is assumed to be one dimensional. IV. The cross sections of Bastora River remain constant during the flood routing. V. The Manning’s roughness coefficient (n = 0.0255) is assumed to remain constant with time and distance along the study reach. 6. RESERVOIR OUTFLOW HYDROGRAPH Determination of the reservoir outflow hydrograph is divided into two tasks: I. Simulating the dam breach. II. Routing the reservoir outflow hydrograph through the breached and outlet structures. 4
  • 5. International Journal of Civil Engineering and Technology (IJCIET), ISSN 0976 – 6308 (Print), ISSN 0976 – 6316(Online) Volume 4, Issue 2, March - April (2013), © IAEME 6.1 Simulating the dam breach The breach width is taken 0.2-0.5 times the crest length of Bastora dam and the breach development time is 0.2 hour. The breach side slopes is taken equal to zero.The breach shape develops in time from initiation to its ultimate configuration. 6.2 Routing the Reservoir Outflow Hydrograph The reservoir outflow hydrograph is computed using the level pool routing method [25]. The reservoir flood routing process requires determination of the following: 6.2.1 Bastora reservoir elevation-storage relationship Eq. (2) represents the Bastora Reservoir Storage-Elevation Relationship [16]: ܸ‫ ݁݉ݑ݈݋‬ൌ 9.669 ‫ି01 כ‬ହ ሾ‫ .݈ܧ‬െ801.5ሿଷ.ଶସଷ ሺ2ሻ where: El. = reservoir water surface elevation (m asl) Volume = volume of the reservoir (MCM) at elevation (El.) 6.2.2 The inflow and outflow from the reservoir for the initial condition The maximum mean monthly outflow from Bastora reservoir was (21.6 m3/s) which occurred on December 1976 [26]. This flow is assumed to be the initial inflow and outflow from Bastora reservoir. 6.2.3 The initial elevation of the reservoir water surface before the failure Bastora reservoir is assumed to be full to its maximum live storage capacity. This corresponds to spillway sill level of (892.5 m asl). 6.2.4 The inflow to Bastora reservoir at failure time The flood hydrograph of 1000 years return period computed by [16], shown in Table (1),is selected as the inflow to Bastora reservoir at failure time.This flood hydrograph represents the maximum instantaneous inflow hydrograph. Table (1): Flood hydrograph for 1000 years Return Period at Bastora Dam [16] Time Inflow Time Inflow (hr) (CMS) (hr) (CMS) 0 0.0 7 97.4 1 120.9 8 43.8 2 510.0 9 18.5 3 680.6 10 7.4 4 567.0 11 2.9 5 364.9 12 0.0 6 199.4 5
  • 6. International Journal of Civil Engineering and Technology (IJCIET), ISSN 0976 – 6308 (Print), ISSN 0976 – 6316(Online) Volume 4, Issue 2, March - April (2013), © IAEME 6.2.5 Modeling outlet works, spillway and breach flows models It is assumed that at the onset of failure the outlets are locked for any reason. Therefore, their flows are not modeled.The reservoir water surface elevation was assumed to be at elevation (892.5m asl) at the onset of failure which is at the spillway sill level. Therefore, the spillway flows are not modeled.The breach is defined by its sill elevation and width, both given as a function of time. Eq. (1) is used to calculate breach outflow. 6.3 Bastora Dam Break Simulation Five different cases of breach width are investigatedfor the analysis of Bastora dam break simulations (0.2, 0.3, 0.35, 0.4, and 0.5 times Bastora dam crest length) to determine the peak outflow. In all these five cases, the initial breach elevation is taken corresponding to the top of Bastora dam (EL. 897.5 m asl). The final bottom elevation of the breach is taken as (EL. 810.0 m asl) corresponding to the average foundation level of Bastora dam at the location of the breach. The growth of the breach is proceeded vertically down at a rate of 7.3 m/ minute until the breach reaches its final elevation and horizontally towards the dam sides at the same rate until the dam destroyed completely except the dam parts that lie above the reservoir water surface elevation. The breach parameters for the five cases of failure and discharges through the breach are shown in Table (2). The outflow hydrographs for various breach widths are shown in Fig. (2). Based on the results shown in Table (2), the breach parameters corresponding to case 5 are selected because the outflow is maximum which represents the worst case. For case 5, shown in Fig. (2), after about 16 minutes from the dam failure, the peak breach outflow is (138023.92 m3/s) and after about 99 minutes from the dam failure, the whole volume of the reservoir is going out to the river reach, and this indicates that the reservoir was depleted at the end of the simulation time. The breach formation is assumed to consist of two phases. The sketch of case (5) is presented in Fig. (3). Table (2): The Breach Parameters and Discharges Max. dischargethrough the Breach width(w) Breach elevation(m) Caseno. breach (m3/s) (m) Initial Final 1 115.46 897.50 810.00 116218.90 2 173.19 897.50 810.00 120890.47 3 202.06 897.50 810.00 124243.07 4 230.92 897.50 810.00 128171.92 5 288.65 897.50 810.00 138023.92 6
  • 7. International Journal of Civil Engineering and Technology (IJCIET), ISSN 0976 – 6308 (Print), ISSN 0976 – 6316(Online) Volume 4, Issue 2, March - April (2013), © IAEME 7
  • 8. International Journal of Civil Engineering and Technology (IJCIET), ISSN 0976 – 6308 (Print), ISSN 0976 – 6316(Online) Volume 4, Issue 2, March - April (2013), © IAEME 7. ROUTING THE RESERVOIR OUTFLOW HYDROGRAPH DOWNSTREAM BASTORA DAM The (HEC-RAS) computer program is used to route the reservoir outflow hydrograph downstream Bastora dam. This software is based on the four-point implicit finite difference solution of the one dimensional unsteady flow equations of Saint-Venant. The derivation of Saint-Venant equations, the continuity equation (conservation of mass) and momentum equation (conservation of momentum) are available in most text books of open channel hydraulics, e.g., [27], [28], [29]. The one dimensional Saint-Venant equations,after neglecting the eddy losses, wind shear effect and lateral flow, are written as: ߲ܳ ߲‫ܣ‬ ൅ ൌ0 ሺ3ሻ ߲‫ݐ߲ ݔ‬ ߲ܳ ߲ሺܳ ଶ ⁄‫ܣ‬ሻ ߲‫ݖ‬ ൅ ൅ ݃‫ ܣ‬൬ ൅ ܵ௙ ൰ ൌ 0 ሺ4ሻ ߲‫ݐ‬ ߲‫ݔ‬ ߲‫ݔ‬ where Q = discharge (L3T-1), A = cross - sectional area of flow (L2), z = water surface elevation (L), x = distance along the channel (L), t = time (T), g = gravity - acceleration constant (LT-2), Sf = friction slope, defined as ݊ଶ ܳ ଶ ܵ௙ ൌ ሺ5ሻ ‫ܣ‬ଶ ܴ ସ⁄ଷ in whichn = Manning’s roughness coefficient and R = hydraulic radius (L) The basic data requirements for performing the one dimensional flow calculations using HEC-RAS are classified as geometric data and hydraulic data [30]. 7.1 Geometric Data According to the available data, a reach distance along Bastora River of (14 Km) downstream Bastora dam is considered. The site of (11) cross sections in this reach is shown in Fig. (4). 8
  • 9. International Journal of Civil Engineering and Technology (IJCIET), ISSN 0976 – 6308 (Print), ISSN 0976 – 6316(Online) Volume 4, Issue 2, March - April (2013), © IAEME 7.2 Hydraulic Data 7.2.1 Manning’s Coefficient Manning’s roughness coefficient (n = 0.0255) determined by [26] is used in this study and it is assumed to remain constant with time and distance. 7.2.2 Unsteady Flow Data 7.2.2.1 Initial Condition As mentioned in paragraph 6.2.2, the inflow to and outflow from Bastora reservoir for the initial condition is assumed (21.6m3/s) which is the maximum mean monthly. Therefore, this outflow from Bastora reservoir is the initial flow for the (14 Km) reach along Bastora River.Table (3) shows the initial water surface elevation along the study reach for the steady flow of (21.6 m3/s). . Table (3): Bed Channel and Water Surface Elevation Section Distance Downstream Channel Bed Elevation Water Surface No. Bastora Dam (km) (m asl) Elevation (m asl) 1 0.00 586.20 586.72 2 1.00 575.70 576.33 3 2.50 565.40 565.64 4 4.25 554.90 555.66 5 6.00 544.70 545.27 6 7.00 534.30 534.45 7 8.50 523.90 524.71 8 10.25 513.50 514.20 9 11.50 503.10 503.83 10 12.75 492.80 493.48 11 14.00 482.40 483.47 7.2.2.2 Boundary Conditions 7.2.2.2.1 Upstream Boundary Condition The reservoir outflow hydrograph for case (5), shown in Fig.(2), is used as the upstream boundary condition. 7.2.2.2.2 Downstream Boundary Condition The downstream boundary condition is a rating curve at the last section of the routed reach. The best fit equation for the discharge - stage data at the last sectionis: ‫ ݖ‬ൌ 483.81 ൅ 0.07471 ܳ ଴.ହ െ 1.407 expሺെܳ ሻ ሺ6ሻ wherez = water surface elevation (m asl) and Q = discharge (m3/s). The coefficient of determination (R2) for Eq. (6) is 0.997. 9
  • 10. International Journal of Civil Engineering and Technology (IJCIET), ISSN 0976 – 6308 (Print), ISSN 0976 – 6316(Online) Volume 4, Issue 2, March - April (2013), © IAEME 8. RESULTS OF FLOOD ROUTING The computed discharge hydrographs at the (11) sections in Bastora River are shown in Fig. (5).The computed peak discharges, maximum water levels and their time of occurrence at the (11) sections in Bastora River are listed in Table (4). The computed peak discharges and the computed peak elevations at the (11) sections in Bastora River are shown in Fig. (6) and Fig. (7)respectively. Table (4): Peak Discharges, Water Levels and their Time of Occurrence Section Peak Discharge Time of Peak Elevation Time of No. (m3/s) Occurrence (min) (m asl) Occurrence (min) 1 138023.9 16 593.92 18 2 135916.1 18 591.86 22 3 126939.6 22 576.62 26 4 123507.0 26 576.01 26 5 122401.5 26 561.48 28 6 121650.9 28 548.70 28 7 120092.7 28 538.71 30 8 117398.7 30 528.54 34 9 113848.9 32 516.92 36 10 110360.9 32 508.99 38 11 103945.0 36 508.96 38 10
  • 11. International Journal of Civil Engineering and Technology (IJCIET), ISSN 0976 – 6308 (Print), ISSN 0976 – 6316(Online) Volume 4, Issue 2, March - April (2013), © IAEME 11
  • 12. International Journal of Civil Engineering and Technology (IJCIET), ISSN 0976 – 6308 (Print), ISSN 0976 – 6316(Online) Volume 4, Issue 2, March - April (2013), © IAEME Rescue level is an elevation, which is considered safe from flooding. It is usually taken 1 to 4 meters above the maximum calculated water levels, rounded to the next full meter [31]. The rescue level is taken 2 meters above the maximum calculated water levels, rounded to the next full meter. Fig. (8)shows the computed rescue levels along Bastora River for the selected sections. 9. CONCLUSIONS I. For the hypothetical failure of Bastora Dam due to overstress, case (5) represents the worst case because it gives maximum outflow. II. The values of computed peak discharges and maximum water levels at the (11) sections in Bastora River may be considered high values. The 14 Km reach downstream Bastora Dam is flooded in a short time. These are because: A. The inflow and outflow from the reservoir for the initial condition is taken equal to (21.6 m3/s) which is the maximum mean monthly outflow from Bastora reservoir. B. Bastora reservoir is assumed to be full to its maximum live storage capacity before the failure of Bastora Dam. C. The inflow to Bastora reservoir at failure time is taken as the flood hydrograph of 1000 years return period which is the maximum instantaneous inflow hydrograph. D. The breach development time is taken equal to 0.2 hour. According to this, the computed peak discharges and maximum water levels at the (11) sections in Bastora River correspond to the worst case. 12
  • 13. International Journal of Civil Engineering and Technology (IJCIET), ISSN 0976 – 6308 (Print), ISSN 0976 – 6316(Online) Volume 4, Issue 2, March - April (2013), © IAEME 10. RECOMMENDATIONS I. A physical model based on Bastora dam data is required to show the validity of the proposed mathematical model. II. In addition to the overstress failure of RCC gravity dams, they, like CVC gravity dams, may fail due to overturning, sliding, earthquakes, or enemy attack. Constructing physical models to investigate these types of failures will led to novel researches into RCC dams’ failures and new insights into RCC dam breach mechanisms. III. The last section (section 11) floods after (36 min); therefore, peoples must evacuate from this area before this time when the dam breaks. IV. The rescue level ranged from (596 m asl) at section (1) to (511 m asl) at section (11). This can be used as a rescue boundary to evacuate peoples from the areas which are threatened by the flood wave. V. The rescue level determined in this study should be taken into consideration when it is planned to construct any building downstream Bastora dam. VI. When the cross sections within Bastora reservoir are available, the hypothetical failure of Bastora dam can be studied by using the dynamic model and the results can be compared with the hydrologic model used in this study. VII. Cross sections data downstream section (11) are required in order to determine the peak discharges and maximum water levels at these sections. VIII. Downstreamwater levels can cause backwater effects into the breach, thus reducing the outflow considerably. Hence it is required to take into consideration the backwater effects. IX. It is assumed that the streambed is fixed without erosion or sedimentation. Erosion and sedimentation simulation are needed to be investigated. REFERENCES [1] ACI 207.5R, “Roller-Compacted Mass Concrete",1999. [2] ICODS, “Federal Guidelines for Dam Safety: Glossary of Terms", FEMA Publication, 1-28, 2004. [3] ACI 309.5R, "Compaction of Roller-Compacted Concrete", 2000. [4] Hansen, K.D., and Reinhardt, W.G., “Roller- Compacted Concrete Dams”, McGraw- Hill, USA, 1991. [5] ICOLD, “Roller- Compacted Concrete Dams”, Bulletin 126, ICOLD, 2003. [6] Dunstan, M.R.H., "The State-of-the-Art of RCC Dams in 2002", Proc. of RCC Dams Workshop in Iran: 11-22, 2003. [7] Kimitaka, U., "Roller Compacted Concrete Dam and Utilization of Fly Ash in Japan", k.uji @ ecomp.metro-u-ac.jp, 2005. [8] USACE, "Seismic Design Provisions for Roller Compacted Concrete Dams", EP 1110- 2-12, 1995. [9] USACE, “Roller- Compacted Concrete”, EM 1110- 2- 2006, 2000. [10] USACE, "Structural Design Using the Roller-Compacted Concrete (RCC) Construction Process", ETL 1110-2-343, 1993. 13
  • 14. International Journal of Civil Engineering and Technology (IJCIET), ISSN 0976 – 6308 (Print), ISSN 0976 – 6316(Online) Volume 4, Issue 2, March - April (2013), © IAEME [11] Batista, E.L., Graca, N.G., Bitten court, R.M. and Andrade, W.P., "First Brazilian Experience Using the Horizontally Advancing Sloped layer Construction of RCC at Lajeado Dam", Middle East RCC Conference, Jordan, 102-112, 2002. [12] Nagayama, I., and Jikan, S., "30 Years' History of Roller-Compacted Concrete Dams in Japan", 4th International Symposium on RCC Dams, Madrid, 1-14, 2003. [13] Qiu, T., and Forbes, B.A., "Use of the Sloped Layer Method for Bonded Joints on Tannur RCC Dam, Jordan", ANCOLD 2003 Conference on Dams, 1-10, 2003. [14] Alghazali, N.O., “Mathematical Model of Al-Adhaim Dam Break”, M.Sc. Thesis, College of Engineering, Babylon University, 1999. [15] Rajar, R., "Mathematical simulation of dam-break flow", J. Hydr. Div., ASCE, 104(7), 1011-1025, 1978. [16] Alghazali, N.O., “Evaluation of Some Design Parameters of Roller Compacted Concrete Dams”, Ph.D. Thesis, Building and Construction Engineering Department, University of Technology, Iraq, 2007. [17] Centre for Inter disciplinary Study of Mountain and Hill Environmental (CISMHE), “Dam Break Analysis & Disaster Management Plan Report”, University of Delhi, 2010. [18] Ministry of Environment, Lands and Parks Water Management Branch (LPWMB), “Inspection & Maintenance of Dams. Dam Safety Guidelines”, British, Columbia, 1998. [19] Macdonald, T.C. and Monopolis, J.L., "Breaching characteristics of dam failures", J. Hydr. Div., ASCE, 110(5), 567-586, 1984. [20] Wurbs, R. A., “Dam Breach Flood Wave Models”, Journal of Hydraulic Engineering, Vol. 113, No. 1, pp. 29-46, 1987. [21] Featherston, R.E. and Nalluri, C., “Civil Engineering Hydraulics”, 3rd ed., Blackwell Since, UK, 1995. [22] Asrate, A.K., “Sensitivity Analysis of Dam Breach Parameters”, M.Sc. Thesis, Engineering College, California State University, 2010. [23] Welch, D., “Breach Parameter Estimator and Dam Break Rules of Thumb Documentation”, V. 2. 30, 2010. [24] Xia, R. and Yen, B.C., "Significance of averaging coefficients in open channel flow equations", J. Hydr. Div., ASCE, 120(2), 169-189, 1994. [25] Chow, V.T., Maidment, D.R. and Mays, L.W., “Applied Hydrology”, McGraw-Hill, New York, 1988. [26] El Concorde Consultant Engineers, “Bastora Dam and Irrigation Project”, Planning Report, Volume-1, Dam Planning Report, Republic of Iraq, Ministry of Water Resources, General Directorate for Engineering Designs, 2006. [27] Henderson, F.M., “Open Channel Flow”, Macmillan, New York, 1966. [28] Attari, J. and Yazdandoost, F., “Hydraulics of Dams & River Structures”, A. A. Balkema, London, 2004. [29] Chaudhry, M.H., “Open Channel Flow”, 2nd ed., Columbia, 2008. [30] HEC-RAS, “User's Manual”, Version 3.1.3, USACE, Hydrologic Engineering Center, Davis, California, 2005. [31] Swiss Consultants, “Mosul Flood Wave”, 1984. [32] Karim M Pathan, “Finite Element Analysis Of 99.60 M High Roller Compacted Concrete (RCC) Gravity Dam - Special Emphasis on Dynamic Analysis” International Journal of Civil Engineering & Technology (IJCIET), Volume 3, Issue 2, 2012, pp. 387 - 391, ISSN Print: 0976 – 6308, ISSN Online: 0976 – 6316, Published by IAEME. 14