The	
  Integrated	
  Master	
  Plan	
  And	
  
Integrated	
  Master	
  Schedule	
  
The	
  Integrated	
  Master	
  Plan	
  and	
  Integrated	
  Master	
  Schedule	
  are	
  one	
  of	
  the	
  
six	
  elements	
  of	
  a	
  Credible	
  Performance	
  Measurement	
  Baseline	
  (PMB).	
  
The	
  PMB	
  is	
  the	
  source	
  of	
  data	
  for	
  the	
  Program	
  Manager.	
  Some	
  of	
  this	
  data	
  is	
  
used	
  in	
  the	
  Integrated	
  Program	
  Measurement	
  Report	
  (IPMR).	
  Some	
  is	
  used	
  
in	
  the	
  assessment	
  of	
  the	
  Program’s	
  risk.	
  Some	
  define	
  the	
  deliverables	
  and	
  
their	
  Technical	
  Performance	
  Measures.	
  	
  
5
V8.7	
  
The	
  IMP	
  tells	
  us	
  where	
  is	
  the	
  program	
  going?	
  
The	
  Plan	
  describes	
  where	
  we	
  are	
  going,	
  the	
  various	
  paths	
  we	
  can	
  take	
  to	
  reach	
  our	
  
desLnaLon,	
  and	
  the	
  progress	
  or	
  performance	
  assessment	
  points	
  along	
  the	
  way	
  to	
  
assure	
  we	
  are	
  on	
  the	
  right	
  path.	
  
These	
  assessment	
  points	
  measures	
  the	
  “maturity”	
  of	
  the	
  product	
  or	
  service	
  against	
  
the	
  planned	
  maturity.	
  This	
  is	
  the	
  only	
  real	
  measure	
  of	
  progress	
  –	
  not	
  the	
  passage	
  
of	
  Lme	
  or	
  consumpLon	
  of	
  money.	
  
The	
  Integrated	
  Master	
  Plan	
  (IMP)	
  Is	
  A	
  Strategy	
  For	
  
The	
  Successful	
  Comple=on	
  Of	
  The	
  Project	
  
2	
  
5.0	
  Start	
  with	
  the	
  IMP	
  
3	
  
5.0	
  Start	
  with	
  the	
  IMP	
  
Quick	
  View	
  to	
  IMP/IMS	
  
!  VerLcal	
  traceability	
  defines	
  the	
  increasing	
  maturity	
  of	
  
key	
  deliverables	
  
!  Horizontal	
  traceability	
  defines	
  the	
  work	
  acLviLes	
  
needed	
  to	
  produce	
  this	
  increasing	
  maturity	
  
!  Both	
  are	
  needed,	
  but	
  the	
  verLcal	
  traceability	
  is	
  the	
  
starLng	
  point	
  
!  Program	
  Events,	
  Significant	
  Accomplishments,	
  and	
  
Accomplishment	
  Criteria	
  must	
  be	
  defined	
  before	
  the	
  
horizontal	
  work	
  acLviLes	
  can	
  be	
  idenLfied	
  
!  For	
  all	
  IMP	
  elements,	
  Key	
  Risks	
  must	
  be	
  idenLfied	
  and	
  
assigned	
  from	
  Day	
  One,	
  even	
  without	
  miLgaLons	
  
4	
  
5.0	
  Start	
  with	
  the	
  IMP	
  
The	
  IMP/IMS	
  is	
  Needed	
  on	
  	
  
Both	
  Sides	
  of	
  the	
  Contract	
  
!  Ver%cal	
  traceability	
  defines	
  the	
  increasing	
  maturity	
  of	
  
the	
  program’s	
  deliverables	
  measures	
  in	
  EffecLveness	
  
(MoE)	
  and	
  Performance	
  (MoP)	
  for	
  the	
  Government.	
  
!  Horizontal	
  traceability	
  defines	
  the	
  progress	
  to	
  plan	
  for	
  
MoE’s	
  and	
  MoP’s	
  with	
  tangible	
  evidence	
  for	
  both	
  the	
  
Government	
  and	
  the	
  Contractor.	
  
!  Ver%cal	
  traceability	
  provides	
  the	
  Government	
  with	
  
insight	
  into	
  the	
  progress	
  of	
  the	
  MoE’s	
  and	
  MoP’s	
  and	
  
Technical	
  Performance	
  Measures.	
  
!  Horizontal	
  traceability	
  provides	
  insight	
  into	
  Cost	
  and	
  
Schedule	
  performance	
  for	
  the	
  Contractor,	
  reportable	
  
through	
  the	
  IPMR	
  to	
  the	
  Government.	
  
5	
  
5.0	
  Start	
  with	
  the	
  IMP	
  
MisconcepLons	
  of	
  	
  
the	
  IMP	
  /	
  IMS	
  
Why	
  we	
  don’t	
  need/want	
  an	
  IMP/IMS	
  	
  
!  Only	
  required	
  for	
  ACAT	
  I	
  programs	
  
!  Too	
  big	
  and	
  burdensome	
  for	
  our	
  small	
  dollar	
  value	
  program	
  
!  Contractor	
  spends	
  B&P	
  and	
  program	
  budget	
  generaLng	
  and	
  
maintaining	
  the	
  IMP,	
  without	
  measurable	
  benefit	
  
!  Doesn’t	
  apply	
  on	
  a	
  services	
  contractors	
  
!  Management	
  tool,	
  not	
  a	
  technical	
  tool	
  
!  Doesn’t	
  apply	
  to	
  technology	
  programs	
  
!  Doesn’t	
  apply	
  to	
  R&D	
  efforts	
  
!  Doesn’t	
  apply	
  to	
  the	
  government	
  
!  Help	
  me	
  get	
  a	
  waiver	
  so	
  I	
  don’t	
  have	
  to	
  use	
  an	
  IMP/IMS	
  
6	
  
5.0	
  Start	
  with	
  the	
  IMP	
  
Aeributes	
  of	
  the	
  IMP	
  
!  Traceability	
  
–  Expands	
  and	
  complies	
  with	
  the	
  SOO,	
  Performance	
  
Requirements,	
  CWBS,	
  and	
  CSOW	
  
–  Based	
  on	
  the	
  customers	
  WBS	
  
–  Is	
  the	
  basis	
  of	
  the	
  IMS,	
  cost	
  reports,	
  and	
  award	
  fees	
  
!  Implements	
  a	
  measurable	
  and	
  trackable	
  program	
  
–  Accomplishes	
  integrated	
  product	
  development	
  
–  Integrates	
  the	
  funcLonal	
  acLviLes	
  of	
  the	
  program	
  
–  Incorporates	
  funcLonal,	
  lower	
  level	
  and	
  S/C	
  IMPs	
  
!  Provides	
  for	
  evaluaLon	
  of	
  Program	
  Maturity	
  
–  Provides	
  insight	
  into	
  the	
  overall	
  effort	
  
–  Level	
  of	
  detail	
  is	
  consistent	
  with	
  risk	
  and	
  complexity	
  per	
  §L	
  
–  Decomposes	
  events	
  into	
  a	
  logical	
  series	
  of	
  accomplishments	
  
–  Measurable	
  criteria	
  demonstrate	
  compleLon	
  /	
  quality	
  of	
  
accomplishments	
  
7	
  
5.0	
  Start	
  with	
  the	
  IMP	
  
Aeributes	
  of	
  the	
  IMS	
  
!  Integrated,	
  networked,	
  mulL-­‐layered	
  schedule	
  of	
  
efforts	
  required	
  to	
  achieve	
  each	
  IMP	
  
accomplishment	
  
–  Detailed	
  tasks	
  and	
  work	
  to	
  be	
  completed	
  
–  Calendar	
  schedule	
  shows	
  work	
  compleLon	
  dates	
  
–  Network	
  schedule	
  shows	
  interrelaLonships	
  and	
  
criLcal	
  path	
  
–  Expanded	
  granularity,	
  frequency,	
  and	
  depth	
  of	
  risk	
  
areas	
  
!  Resource	
  loading	
  
!  Correlates	
  IMS	
  work	
  with	
  IMP	
  events	
  
8	
  
5.0	
  Start	
  with	
  the	
  IMP	
  
The	
  Importance	
  of	
  the	
  IMP	
  
!  The	
  IMP/IMS	
  is	
  the	
  single	
  most	
  important	
  document	
  to	
  
a	
  program’s	
  success	
  
–  It	
  clearly	
  demonstrates	
  the	
  providers	
  understanding	
  of	
  the	
  
program	
  requirements	
  and	
  the	
  soundness	
  of	
  the	
  approach	
  
a	
  represented	
  by	
  the	
  plan	
  
!  The	
  program	
  uses	
  the	
  IMP/IMS	
  to	
  provide:	
  
–  Up	
  Front	
  Planning	
  and	
  commitment	
  from	
  all	
  parLcipants	
  
–  A	
  balanced	
  design	
  discipline	
  with	
  risk	
  miLgaLon	
  acLviLes	
  
–  Integrated	
  requirements	
  including	
  producLon	
  and	
  support	
  
–  Management	
  with	
  an	
  incremental	
  verificaLon	
  for	
  
informed	
  program	
  decisions	
  
9	
  
5.0	
  Start	
  with	
  the	
  IMP	
  
Just	
  A	
  Reminder,	
  before	
  moving	
  on	
  
10	
  
Page	
  47,	
  Defense	
  AcquisiLon	
  Guide,	
  January	
  10,	
  2012	
  
Page	
  317,	
  Defense	
  AcquisiLon	
  Guide,	
  January	
  10,	
  2012	
  
5.0	
  Start	
  with	
  the	
  IMP	
  
Our	
  Goal	
  is	
  simple	
  …	
  	
  
How	
  can	
  we	
  recognize	
  the	
  Reality	
  of	
  the	
  Program’s	
  
current	
  status	
  and	
  its	
  future	
  performance?	
  
The	
  top	
  spins	
  conLnuous	
  while	
  in	
  a	
  dream	
  –	
  stops	
  
spinning	
  in	
  the	
  real	
  world	
  –	
  Cobb’s	
  totem,	
  Incep=on	
  
5.0	
  Start	
  with	
  the	
  IMP	
  
11	
  
12	
  
5.0	
  Start	
  with	
  the	
  IMP	
  
Principles	
  of	
  Building	
  a	
  Credible	
  
Integrated	
  Master	
  Plan	
  
Building	
  the	
  IMP	
  is	
  a	
  Systems	
  Engineering	
  acLvity.	
  The	
  Integrated	
  Master	
  Plan	
  is	
  
the	
  Program	
  Architecture	
  in	
  the	
  same	
  way	
  the	
  hardware	
  and	
  sooware	
  are	
  the	
  
Product	
  Architecture.	
  
Poor,	
  weak,	
  or	
  unstructured	
  ProgrammaLc	
  Architecture	
  reduces	
  visibility	
  to	
  the	
  
Product	
  Architecture’s	
  performance	
  measures	
  of	
  cost	
  and	
  schedule	
  connected	
  
with	
  Technical	
  Performance	
  Measures.	
  
	
  
6
V8.7	
  
Quick	
  View	
  of	
  Building	
  the	
  IMP	
  
!  Start	
  with	
  each	
  Program	
  Event	
  and	
  define	
  the	
  
Significant	
  Accomplishments	
  their	
  entry	
  and	
  
exit	
  criteria	
  to	
  assess	
  the	
  needed	
  maturity	
  of	
  
the	
  key	
  deliverables	
  
!  Arrange	
  the	
  Significant	
  Accomplishments	
  in	
  
the	
  proper	
  dependency	
  order	
  	
  
!  Segregate	
  these	
  Significant	
  Accomplishments	
  
into	
  swim	
  lanes	
  for	
  IPTs	
  
!  Define	
  the	
  dependencies	
  between	
  each	
  SA	
  
14	
  
6.0	
  Build	
  IMP	
  
A	
  CriLcal	
  Understanding	
  of	
  the	
  IMP	
  
The	
  IMP	
  defines	
  the	
  connecLons	
  between	
  the	
  Product	
  maturity	
  –	
  VerLcal	
  –	
  and	
  the	
  
implementaLon	
  of	
  this	
  Product	
  maturity	
  through	
  the	
  FuncLonal	
  acLviLes	
  –	
  the	
  Horizontal	
  	
  
6.0	
  Build	
  IMP	
  
15	
  
Benefits	
  of	
  this	
  Formality	
  
16	
  
Objec%ve	
   Implementa%on	
  
Event	
  Driven	
  Plan	
  versus	
  Schedule	
  
Driven	
  Plan	
  is	
  based	
  on	
  compleLon	
  of	
  
tasks	
  not	
  passage	
  of	
  Lme	
  
Separate	
  the	
  plan	
  (IMP)	
  from	
  the	
  
schedule	
  (IMS)	
  but	
  link	
  elements	
  with	
  
numbering	
  system	
  
Condensed,	
  easy	
  to	
  read	
  “Plan”	
  showing	
  
the	
  “Events”	
  rather	
  than	
  the	
  work	
  effort	
  
Indentured,	
  outline	
  format	
  –	
  not	
  text	
  
Pre-­‐defined	
  entry	
  and	
  exit	
  criteria	
  for	
  
major	
  Program	
  Events	
  
Significant	
  Accomplishments	
  for	
  each	
  
key	
  Program	
  Event	
  
ObjecLve	
  measures	
  of	
  progress	
  and	
  
compleLon	
  for	
  each	
  Accomplishment	
  
Pre-­‐defined	
  Accomplishment	
  Criteria	
  
(AC)	
  for	
  each	
  Significant	
  
Accomplishment	
  (SA)	
  
Stable,	
  contracture	
  plan,	
  flexible	
  enough	
  
to	
  portray	
  program	
  status	
  
IMP	
  part	
  of	
  the	
  contract,	
  IMS	
  is	
  a	
  data	
  
item	
  
Capture	
  essence	
  of	
  the	
  funcLonal	
  
progress	
  without	
  mandaLng	
  a	
  parLcular	
  
process	
  for	
  performing	
  the	
  work	
  
Split	
  IMP	
  into	
  Product	
  and	
  Process	
  
6.0	
  Build	
  IMP	
  
Risk	
  Management	
  
Building	
  the	
  IMP	
  Starts	
  at	
  the	
  RFP	
  with	
  
Systems	
  Engineering	
  Measures	
  
17	
  
6.0	
  Build	
  IMP	
  
SOO	
  
ConOps	
  
SOW	
  
Techncial	
  and	
  OperaLonal	
  
Requirements	
  
CWBS	
  &	
  
CWBS	
  DicLonary	
  
Integrated	
  Master	
  Plan	
  
(IMP)	
  
Integrated	
  Master	
  Schedule	
  
(IMS)	
  	
  
Earned	
  Value	
  Management	
  
System	
  
ObjecLve	
  Status	
  and	
  EssenLal	
  Views	
  to	
  support	
  the	
  proacLve	
  management	
  
processes	
  needed	
  to	
  keep	
  the	
  program	
  GREEN	
  
Performance	
  Measurement	
  Baseline	
  
Measures	
  of	
  
EffecLveness	
  
Measures	
  of	
  
Performance	
  
TPMs	
  and	
  QBDs	
  
JROC	
  	
  
Key	
  Performance	
  Parameters	
  
Program	
  	
  Specific	
  
Key	
  Performance	
  Parameters	
  
Technical	
  Performance	
  
Measures	
  
WBS	
  
CWBS	
  
IMP	
  captures	
  end	
  user	
  requirements	
  in	
  
terms	
  MOEs,	
  MOPs,	
  KPPs,	
  and	
  TPMs	
  
18	
  
SOW	
  
ConOps	
  
WBS	
  
CWBS	
  
Technical	
  Performance	
  
Measures	
  	
  
(TPM)	
  
Messages	
  of	
  Performance	
  
(MOP)	
  
Measures	
  of	
  EffecLveness	
  
(MOE)	
  
Key	
  Performance	
  
Parameters	
  
(KPP)	
  
Integrated	
  Master	
  Plan	
  
(IMP)	
  
Integrated	
  Master	
  
Schedule	
  
(IMS)	
  
Performance	
  
Measurement	
  Baseline	
  
(PMB)	
  
Technical	
  Requirements	
  
The	
  IMP	
  /	
  IMS	
  Structure	
  
19	
  
IMS
IMP
Describes how program
capabilities will be
delivered and
how these
capabilities will
be recognized
as ready for
delivery
Supplemental Schedules (CAM Notebook)
Work Packages and Tasks
Criteria
Accomplishment
Events
or
Milestones
6.0	
  Build	
  IMP	
  
The	
  IMP/IMS	
  provides	
  Horizontal	
  and	
  
VerLcal	
  Traceability	
  of	
  	
  
progress	
  to	
  plan	
  
!  VerLcal	
  traceability	
  AC	
  "	
  SA	
  "	
  PE	
  
!  Horizontal	
  traceability	
  WP	
  "	
  WP	
  "	
  AC	
  
20	
  
Program Events
Define the maturity
of a Capability at a point in
time.
Significant Accomplishments
Represent requirements
that enable Capabilities.
Accomplishment Criteria
Exit Criteria for the Work
Packages that fulfill Requirements.
Work	
  
Package	
  
Work	
  
Package	
  
Work	
  
Package	
  
Work	
  
Package	
  
Work	
  
Package	
  
Work	
  
Package	
  
Work	
  
package	
  
6.0	
  Build	
  IMP	
  
The	
  IMP’s	
  role	
  during	
  ExecuLon	
  
21	
  
Program ExecutionPMB for IBRProposal SubmittalDRFP & RFP
Performance Measurement Baseline
Tasks (T)
BOE
% Complete
Statement of Work
Program Deliverables
IMP
Accomplishments (A)
Criteria (C)
EVMS
Events (E)
Budget Spreads by CA & WPCAIV
Capabilities Based Requirements
X BCWS =
Probabilistic Risk Analysis
=
Time keeping and ODC =
Technical Performance Measure
BCWP
ACWP
Cost & Schedule Risk Model
BCWS
Decreasing technical and programmatic risk using Risk Management Methods
IMS
Physical % Complete
Continuity and consistency from DRFP through Program Execution
WBS
6.0	
  Build	
  IMP	
  
!  IMP	
  phrases	
  in	
  past	
  tense	
  –	
  do	
  describe	
  what	
  
DONE	
  looks	
  like	
  
!  IMS	
  phrase	
  in	
  present	
  tense	
  –	
  do	
  describe	
  
work	
  needed	
  to	
  arrive	
  at	
  DONE	
  
22	
  
The	
  Grammar	
  of	
  the	
  Integrated	
  
Master	
  Plan	
  (IMP)	
  
Maturity	
   Product	
  AcLon	
   Product	
  State	
  
AdjecLve	
   Noun	
   Verb	
   Verb	
  
Demonstrates	
  
Maturity	
  
Step	
  in	
  the	
  
Process	
  
End	
  Item	
   Final	
  Status	
  
Preliminary	
   Model/Sim	
   Design	
   Complete	
  
Preliminary	
  Modeling	
  and	
  Simula%on	
  Design	
  Complete	
  
1st,	
  Principle	
  –	
  	
  
IMP	
  Building	
  is	
  a	
  Full	
  Contact	
  Sport	
  
23	
  
6.0	
  Build	
  IMP	
  
Our	
  First	
  Approach	
  to	
  the	
  IMP	
  /	
  
IMS	
  Paradigm	
  
!  The	
  1st	
  approach	
  defines	
  Program	
  Events	
  (PE),	
  
Significant	
  Accomplishments	
  (SA),	
  and	
  
Accomplishment	
  Criteria	
  (AC),	
  derived	
  from	
  the	
  
Work	
  Breakdown	
  Structure	
  or	
  the	
  SOW	
  
!  This	
  1st	
  approach	
  can	
  be	
  done	
  in	
  6	
  easy	
  steps	
  
24	
  
6.0	
  Build	
  IMP	
  
1.  IdenLfy	
  the	
  Program	
  Events	
  (PE)	
  
(as	
  the	
  ACQ	
  Guide	
  tells	
  us)	
  
2.  IdenLfy	
  the	
  Significant	
  
Accomplishments	
  (SA)	
  from	
  the	
  
WBS	
  deliverables	
  	
  
3.  IdenLfy	
  the	
  Accomplishment	
  
Criteria	
  (AC)	
  needed	
  to	
  produce	
  
these	
  deliverables	
  
4.  IdenLfy	
  the	
  Work	
  Packages	
  for	
  
each	
  Accomplishment	
  Criteria	
  
5.  Sequence	
  the	
  Work	
  Packages	
  
6.  Assemble	
  the	
  IMP/IMS	
  
This	
  approach	
  doesn’t	
  give	
  us	
  
visibility	
  into	
  what	
  “done”	
  looks	
  like	
  
!  We	
  must	
  measure	
  increasing	
  product	
  maturity	
  in	
  
units	
  meaningful	
  to	
  the	
  decision	
  makers	
  
!  We	
  must	
  see	
  the	
  risks	
  before	
  they	
  arrive	
  so	
  we	
  
can	
  take	
  correcLve	
  acLon	
  
6.0	
  Build	
  IMP	
  
25	
  
First	
  Look	
  at	
  a	
  Significant	
  
Accomplishment	
  (SA)	
  
!  SAs	
  are	
  interim	
  and	
  final	
  steps	
  to	
  define,	
  design,	
  develop,	
  
verify,	
  produce,	
  and	
  deploy	
  the	
  product	
  or	
  system.	
  	
  
!  SAs	
  must	
  occur	
  in	
  a	
  manner	
  that	
  ensures	
  a	
  logical	
  path	
  is	
  
maintained	
  throughout	
  the	
  development	
  effort.	
  	
  
!  SAs	
  are	
  event	
  related	
  and	
  not	
  just	
  Lme	
  coincidental.	
  	
  
!  SAs	
  should	
  have	
  one	
  or	
  more	
  of	
  the	
  following	
  characterisLcs:	
  	
  
–  Consists	
  of	
  a	
  discrete	
  step	
  in	
  the	
  process	
  of	
  planned	
  development	
  that	
  
must	
  be	
  complete	
  prior	
  to	
  an	
  event	
  
–  Produces	
  a	
  desired	
  result	
  at	
  a	
  specified	
  event	
  that	
  indicates	
  a	
  level	
  of	
  
design	
  maturity	
  (or	
  progress)	
  directly	
  related	
  to	
  each	
  product	
  and	
  
process	
  
–  Defines	
  interrelaLonships,	
  interdependencies,	
  or	
  “hand-­‐off”	
  points	
  of	
  
different	
  funcLonal	
  disciplines	
  applied	
  to	
  the	
  program	
  
26	
  
6.0	
  Build	
  IMP	
  
SAs	
  must	
  assess	
  compliance	
  with	
  Measures	
  of	
  EffecLveness	
  	
  
First	
  look	
  at	
  an	
  Accomplishment	
  
Criteria	
  (AC)	
  
!  ACs	
  are	
  definiLve	
  measures	
  directly	
  supporLng	
  successful	
  
compleLon	
  of	
  a	
  significant	
  accomplishment.	
  	
  
!  ACs	
  show	
  objecLve	
  evidence	
  of	
  work	
  progress	
  (maturity	
  of	
  a	
  
product);	
  i.e.,	
  be	
  seen,	
  read,	
  demonstrated,	
  or	
  quanLfied.	
  These	
  
results	
  are	
  usually	
  incorporated	
  into	
  a	
  report	
  or	
  document	
  as	
  
evidence	
  of	
  accomplishment.	
  	
  
!  ACs	
  are	
  prerequisites	
  for	
  compleLon	
  of	
  an	
  SA	
  (i.e.,	
  exit	
  criteria).	
  	
  
!  The	
  quesLons	
  that	
  need	
  to	
  be	
  repeatedly	
  asked	
  when	
  developing	
  
ACs	
  are:	
  
–  How	
  do	
  I	
  know	
  when	
  an	
  accomplishment	
  has	
  been	
  completed?	
  
–  Is	
  the	
  criteria	
  directly	
  related	
  to	
  the	
  accomplishment?	
  	
  
–  Is	
  it	
  proof?	
  	
  
–  What	
  is	
  the	
  work	
  product?”	
  
27	
  
6.0	
  Build	
  IMP	
  
ACs	
  must	
  assess	
  compliance	
  with	
  Measures	
  of	
  Performance	
  
The	
  IMP	
  speaks	
  to	
  Measures	
  of	
  EffecLveness	
  
(MoE)	
  and	
  Measures	
  of	
  Performance	
  (MoP)	
  
28	
  
6.0	
  Build	
  IMP	
  
!  This	
  is	
  where	
  TPMs	
  	
  
are	
  connected	
  with	
  
the	
  MoE’s	
  and	
  
MoP’s	
  
!  For	
  each	
  
deliverable	
  from	
  
the	
  program,	
  all	
  
the	
  “measures”	
  
must	
  be	
  defined	
  in	
  
units	
  meaningful	
  
to	
  the	
  decision	
  
makers.	
  
!  Here’s	
  some	
  “real”	
  
examples.	
  
1.  Provide	
  Precision	
  
Approach	
  for	
  a	
  200	
  
FT/0.5	
  NM	
  DH	
  
2.  Provide	
  bearing	
  and	
  
range	
  to	
  AC	
  plasorm	
  
3.  Provide	
  AC	
  
surveillance	
  to	
  GRND	
  
plasorm	
  	
  
Measures	
  of	
  
EffecLveness	
  (MoE)	
  
1.  Net	
  Ready	
  
2.  Guidance	
  Quality	
  
3.  Land	
  Interoperability	
  
4.  Manpower	
  
5.  Availability	
  
JROC	
  Key	
  Performance	
  
Parameters	
  (KPP)	
  
1.  Net	
  Ready	
  
! IPv4/6	
  compliance	
  
! 1Gb	
  Ethernet	
  
2.  Guidance	
  quality	
  
! Accuracy	
  threshold	
  p70	
  
@	
  6M	
  
! 	
  Integrity	
  threshold	
  4M	
  
@	
  10-­‐6	
  /approach	
  
3.  Land	
  interoperability	
  
! Processing	
  capability	
  
meets	
  LB	
  growth	
  matrix	
  
4.  Manpower	
  
! MTBC	
  >1000	
  hrs	
  
! MCM	
  <	
  2	
  hrs	
  
5.  Availability	
  
! Clear	
  threshold	
  >99%	
  
! Jam	
  threshold	
  >90%	
  
Measures	
  of	
  Performance	
  
(MoP)	
  
1.  Net	
  Ready	
  
! Standard	
  message	
  packets	
  
2.  Guidance	
  Quality	
  
! MulLpath	
  allocaLon	
  budget	
  
! MulLpath	
  bias	
  protecLon	
  
3.  Land	
  Interoperability	
  
! MOSA	
  compliant	
  
! Civil	
  compliant	
  
4.  Manpower	
  
! OperaLng	
  elapsed	
  Lme	
  
meters	
  
! Standby	
  elapsed	
  Lme	
  
indicators	
  
5.  Availability	
  
! Phase	
  center	
  variaLons	
  	
  
Technical	
  Performance	
  
Measures	
  (TPM)	
  
Mission	
  CapabiliLes	
  and	
  OperaLonal	
  Need	
  
Technical	
  Insight	
  –	
  Risk	
  adjusted	
  performance	
  to	
  plan	
  	
  
The	
  1st	
  Problem	
  with	
  the	
  IniLal	
  
IMP/IMS	
  Paradigm	
  
!  There	
  is	
  no	
  single	
  source	
  of	
  guidance	
  for	
  
construcLng	
  a	
  credible	
  IMP	
  and	
  IMS	
  
– A	
  DOD	
  Guidebook,	
  but	
  sLll	
  in	
  Version	
  0.9	
  
– A	
  few	
  DOD	
  service	
  pamphlets	
  
– A	
  commercial	
  guidebook	
  
– Many	
  contractor	
  guidelines	
  
!  No	
  definiLve	
  guidance	
  from	
  DoD	
  on	
  what	
  
makes	
  a	
  good	
  IMP	
  
!  No	
  definiLve	
  DID	
  requiring	
  an	
  IMP	
  on	
  specific	
  
programs	
  
29	
  
6.0	
  Build	
  IMP	
  
The	
  IMP	
  is	
  a	
  good	
  start,	
  but	
  we’re	
  
really	
  aoer	
  the	
  IMP	
  NarraLves	
  
!  The	
  IMP	
  NarraLves	
  start	
  with	
  the	
  Statement	
  
of	
  ObjecLves	
  (SOO)	
  or	
  Concept	
  of	
  OperaLons	
  
(ConOps)	
  
– These	
  idenLfy	
  the	
  top	
  level	
  program	
  objecLves	
  
– They	
  define	
  the	
  big	
  picture	
  and	
  provide	
  pre-­‐award	
  
trade	
  space	
  
– They	
  provide	
  the	
  framework	
  for	
  the	
  Contractor	
  to	
  
develop	
  the	
  proposal	
  through	
  the	
  IMP	
  
!  With	
  the	
  Government’s	
  ExecuLve	
  summary,	
  
provides	
  the	
  contractor	
  an	
  understanding	
  of	
  
what	
  is	
  needed	
  and	
  what	
  is	
  important	
  
30	
  
6.0	
  Build	
  IMP	
  
The	
  IMP	
  Process	
  NarraLve	
  
The	
  IMP	
  Process	
  NarraLve	
  describes	
  how	
  the	
  
technical	
  and	
  business	
  elements	
  of	
  the	
  program	
  
will	
  be	
  conducted,	
  monitored,	
  and	
  controlled.	
  	
  
NarraLves	
  provide	
  the	
  customer	
  visibility	
  into	
  
the	
  contractor’s	
  key	
  funcLonal	
  processes	
  and	
  
procedures,	
  the	
  relaLonship	
  of	
  these	
  processes	
  
and	
  procedures,	
  and	
  an	
  overview	
  of	
  the	
  effort	
  
required	
  to	
  implement	
  them.	
  
31	
  
6.0	
  Build	
  IMP	
  
IMP	
  NarraLve	
  for	
  PDR	
  
Program	
  
Event	
  
Event	
  Descrip%on	
  
PE	
  Maturity	
  Assessment	
  
shown	
  in	
  SAs	
  
PDR	
   PDR	
  establishes	
  the	
  “design-­‐	
  to”	
  allocated	
  
baseline	
  to	
  the	
  subsystem	
  level,	
  assures	
  this	
  
design	
  meets	
  the	
  funcLonal	
  baseline,	
  assures	
  
system	
  requirements	
  have	
  been	
  properly	
  
allocated	
  to	
  the	
  proper	
  subsystem.	
  
PDR	
  establishes	
  the	
  feasibility	
  of	
  the	
  design	
  
approach	
  to	
  meet	
  the	
  technical	
  requirements	
  and	
  
provide	
  acceptable	
  interface	
  relaLonships	
  
between	
  the	
  hardware	
  and	
  other	
  interfacing	
  
items.	
  	
  
Any	
  changes	
  to	
  the	
  requirements	
  that	
  have	
  
occurred	
  since	
  the	
  System	
  Requirements	
  Review	
  
(SRR2)	
  will	
  be	
  verified	
  at	
  the	
  PDR.	
  	
  
PDR	
  assures	
  the	
  design	
  is	
  verifiable,	
  does	
  not	
  pose	
  
major	
  IMS	
  or	
  Cost	
  risk,	
  and	
  is	
  mature	
  enough	
  to	
  
advance	
  to	
  the	
  detailed	
  design	
  phase	
  –	
  CDR	
  
!  Subsystem	
  level	
  
operaLonal	
  concepts	
  
defined	
  
!  System	
  level	
  interfaces	
  
baselined	
  
!  Supportability	
  plans	
  
established	
  
!  Sooware	
  requirements	
  
finalized	
  
!  Subsystem	
  requirements	
  
finalized	
  &	
  allocated	
  
!  System	
  verificaLon,	
  
validaLon	
  &	
  cerLficaLon	
  
plans	
  updated	
  
!  PDR	
  subsystem	
  design	
  
completed	
  
32	
  
6.0	
  Build	
  IMP	
  
What	
  the	
  IMP	
  NarraLve	
  Tells	
  Us?	
  
!  States	
  the	
  objecLve	
  of	
  the	
  processes	
  used	
  to	
  build	
  the	
  
products	
  describe	
  in	
  the	
  SOW	
  
!  Provides	
  the	
  governing	
  documents,	
  compliance,	
  and	
  
reference	
  for	
  the	
  process	
  acLviLes	
  
!  Explains	
  the	
  process	
  approach	
  
–  Portrays	
  the	
  key	
  acLviLes	
  of	
  the	
  approach	
  
–  Illustrates	
  the	
  processes	
  tailored	
  for	
  the	
  specific	
  program	
  
33	
  
Inputs	
  
AcLvity	
  
3	
  
AcLvity	
  
5	
  
AcLvity	
  
4	
  
Tools	
  
AcLvity	
  
1	
  
AcLvity	
  
2	
  
Outputs	
  
Metrics	
  
6.0	
  Build	
  IMP	
  
Some	
  IMP	
  Guidance	
  	
  
34	
  
6.0	
  Build	
  IMP	
  
The	
  Defense	
  AcquisiLon	
  Guide	
  
(DAG)	
  Tells	
  Us	
  About	
  the	
  IMP	
  
35	
  
6.0	
  Build	
  IMP	
  
The	
  DAG	
  Also	
  Tells	
  Us	
  
36	
  
6.0	
  Build	
  IMP	
  
5000.01	
  Part	
  2.B.3	
  AcquisiLon	
  Strategies,	
  
Exit	
  Criteria,	
  and	
  Risk	
  Management	
  
“Event	
  driven	
  acquisiLon	
  strategies	
  and	
  program	
  plans	
  
must	
  be	
  based	
  on	
  rigorous,	
  objecLve	
  assessments	
  of	
  a	
  
program’s	
  status	
  and	
  the	
  plans	
  for	
  managing	
  risk	
  during	
  
the	
  next	
  phase	
  and	
  the	
  remainder	
  of	
  the	
  program.	
  	
  
The	
  acquisiLon	
  strategy	
  and	
  associated	
  contracLng	
  
acLviLes	
  must	
  explicitly	
  link	
  milestone	
  decision	
  reviews	
  
to	
  events	
  and	
  demonstrated	
  accomplishments	
  in	
  
development,	
  tesLng,	
  and	
  iniLal	
  producLon.	
  	
  
The	
  acquisiLon	
  strategy	
  must	
  reflect	
  the	
  
interrelaLonships	
  and	
  schedule	
  of	
  acquisiLon	
  phases	
  and	
  
events	
  based	
  on	
  logical	
  sequence	
  of	
  demonstrated	
  
accomplishments	
  not	
  on	
  fiscal	
  or	
  calendar	
  expediency.”	
  
37	
  
6.0	
  Build	
  IMP	
  
What	
  makes	
  a	
  good	
  	
  
Program	
  Event	
  (PE)?	
  
!  Events	
  are	
  the	
  conclusion	
  of	
  an	
  interval	
  of	
  major	
  
program	
  accomplishments	
  (SA)	
  with	
  their	
  criteria	
  (AC)	
  	
  
!  IMP	
  events	
  represent	
  key	
  decision	
  transiLon	
  points	
  
between	
  major	
  acLviLes	
  distributed	
  over	
  the	
  contract	
  
period	
  
–  The	
  IMP	
  is	
  a	
  Mini	
  Authoriza=on’s	
  to	
  Proceed	
  (ATP)	
  to	
  the	
  
next	
  Program	
  Event	
  (PE)	
  
!  Some	
  guidance	
  for	
  establishing	
  program/product	
  
events:	
  
–  Customer	
  Given	
  Events.	
  	
  
–  Key	
  Decisions	
  Needed	
  
–  Risk	
  MiLgaLon	
  Event	
  
–  DOD	
  Systems	
  Engineering	
  Technology	
  Review	
  (SETR)	
  
Guidance	
  
38	
  
6.0	
  Build	
  IMP	
  
What	
  makes	
  a	
  good	
  
Significant	
  Accomplishment	
  (SA)?	
  
!  IPT	
  can	
  manage	
  it	
  at	
  a	
  working	
  level	
  
!  Shows	
  compleLon	
  and	
  result	
  s	
  of	
  discrete	
  steps	
  in	
  the	
  
development	
  process	
  
!  Indicates	
  maturity	
  of	
  the	
  product	
  through	
  MoEs	
  and	
  MoPs	
  
!  Its	
  “significance”	
  measures	
  program	
  event	
  status	
  
!  Relevant	
  and	
  logically	
  linked	
  to	
  the	
  proper	
  PE	
  
–  Just	
  because	
  the	
  work	
  occurs	
  during	
  the	
  Lme-­‐frame	
  for	
  PE	
  A	
  
doesn’t	
  mean	
  it’s	
  logically	
  linked	
  to	
  PE	
  A	
  
!  Uses	
  consistent	
  language,	
  style,	
  format	
  through	
  verb	
  
dicLonary,	
  for	
  example:	
  
–  Segment	
  build	
  4	
  detailed	
  design	
  completed	
  
–  Analysis	
  of	
  structural	
  integrity	
  completed	
  
–  Structural	
  integrity	
  verified	
  
39	
  
6.0	
  Build	
  IMP	
  
IMP	
  Significant	
  Accomplishments	
  
!  SAs	
  are	
  NOT	
  just	
  a	
  list	
  of	
  “things”	
  to	
  do	
  before	
  the	
  
Program	
  Event	
  (PE)	
  
!  They	
  are	
  sequenced	
  accomplishments,	
  each	
  of	
  which	
  
leads	
  to	
  the	
  PE,	
  e.g.	
  CriLcal	
  Design	
  Review	
  (CDR),	
  each	
  
increasing	
  the	
  maturity	
  of	
  the	
  deliverables	
  	
  
–  SA	
  #	
  1	
  =	
  CDR	
  meeLng	
  conducted	
  
–  SA	
  #	
  2	
  =	
  CDR	
  acLon	
  item	
  work-­‐off	
  plan	
  established	
  
–  SA	
  #	
  3	
  =	
  85%	
  drawings	
  completed	
  
–  SA	
  #	
  4	
  =	
  CDR	
  CDRLs	
  delivered	
  
–  SA	
  #	
  5	
  =	
  Development	
  environment	
  operaLonal	
  
–  SA	
  #	
  6	
  =	
  CriLcal	
  methods	
  analyses	
  completed	
  
–  SA	
  #	
  7	
  =	
  RVTM	
  approved	
  
40	
  
6.0	
  Build	
  IMP	
  
What	
  makes	
  a	
  good	
  
Accomplishment	
  Criteria	
  (AC)?	
  
!  Provides	
  objecLve,	
  measureable,	
  and	
  explicit	
  
evidence	
  of	
  compleLon	
  and	
  closure	
  of	
  the	
  
work	
  acLviLes	
  in	
  Work	
  Packages	
  that	
  saLsfies	
  
the	
  Measure	
  of	
  Performance.	
  
!  Defines	
  condiLons	
  for	
  closing	
  the	
  Significant	
  
Accomplishment	
  (SA).	
  
!  Answers	
  the	
  quesLon	
  how	
  do	
  we	
  know	
  when	
  
a	
  Significant	
  Accomplishment	
  has	
  been	
  
completed?	
  
41	
  
6.0	
  Build	
  IMP	
  
!  Not	
  Significant	
  
–  Too	
  small	
  to	
  significantly	
  contribute	
  to	
  successful	
  event	
  compleLon	
  
–  Would	
  lead	
  to	
  trivial	
  tasks	
  (e.g.,	
  1	
  day	
  duraLon)	
  
!  Ambiguous	
  
–  Read	
  can’t	
  tell	
  what	
  Done	
  looks	
  like	
  
!  Wrong	
  verb	
  
–  Uses	
  a	
  verb	
  that’s	
  not	
  on	
  the	
  list	
  (DicLonary)	
  
–  Uses	
  a	
  listed	
  verb	
  incorrectly	
  
–  Doesn’t	
  have	
  a	
  verb	
  at	
  all	
  
!  Not	
  measurable	
  
–  Can’t	
  tell	
  when	
  we’re	
  done	
  
!  Too	
  Many	
  SAs	
  or	
  ACs	
  
–  Confuses	
  the	
  reader	
  and	
  confuses	
  the	
  execuLon	
  process	
  of	
  the	
  
program	
  
–  Dilutes	
  the	
  MoE	
  and	
  MoP	
  
–  Reduces	
  visibility	
  into	
  increasing	
  maturity	
  
42	
  
What	
  makes	
  a	
  Not	
  So	
  Good	
  	
  
SA	
  or	
  AC?	
  
6.0	
  Build	
  IMP	
  
!  Program	
  Event	
  (PE)	
  
–  A	
  PE	
  assess	
  the	
  readiness	
  or	
  compleLon	
  as	
  a	
  measure	
  
of	
  progress	
  
–  First	
  Flight	
  Complete	
  
!  Significant	
  Accomplishment	
  (SA)	
  
–  The	
  desired	
  result(s)	
  prior	
  to	
  or	
  at	
  compleLon	
  of	
  an	
  
event	
  demonstrate	
  the	
  level	
  of	
  the	
  program’s	
  
progress	
  
–  Flight	
  Test	
  Readiness	
  Review	
  Complete	
  
!  Accomplishment	
  Criteria	
  (AC)	
  
–  DefiniLve	
  evidence	
  (measures	
  or	
  indicators)	
  that	
  
verify	
  a	
  specific	
  accomplishment	
  has	
  been	
  completed	
  
–  SEEK	
  EAGLE	
  Flight	
  Clearance	
  Obtained	
  
43	
  
F-­‐22	
  Example	
  
6.0	
  Build	
  IMP	
  
!  PE’s	
  are	
  easy,	
  they	
  are	
  in	
  the	
  SETR	
  and	
  Integrated	
  
LogisLcs	
  Lifecycle	
  Management	
  System	
  
!  The	
  SA’s	
  can	
  be	
  defined	
  from	
  the	
  program’s	
  
deliverables	
  –	
  these	
  may	
  not	
  be	
  obvious	
  but	
  can	
  
be	
  discovered	
  with	
  a	
  Product	
  Development	
  
Kaizen	
  process	
  (more	
  later)	
  
!  It’s	
  the	
  AC’s	
  that	
  are	
  hard	
  part	
  –	
  the	
  ACs	
  must	
  
represent	
  the	
  exit	
  criteria	
  for	
  the	
  series	
  of	
  Work	
  
Packages	
  that	
  do	
  the	
  work	
  to	
  produce	
  the	
  
product	
  
44	
  
Now	
  comes	
  the	
  Hard	
  Part	
  
6.0	
  Build	
  IMP	
  
6	
  Steps	
  to	
  IMP	
  Development	
  
Let’s	
  start	
  to	
  build	
  the	
  IMP.	
  	
  
This	
  step-­‐by-­‐step	
  process	
  needs	
  to	
  be	
  followed	
  carefully.	
  
The	
  IMP	
  is	
  constructed	
  one	
  Program	
  Event	
  at	
  a	
  Lme	
  –	
  Leo	
  to	
  Right	
  in	
  Lme.	
  	
  
To	
  do	
  otherwise	
  allows	
  confusion	
  and	
  disconnecLon	
  between	
  Program	
  Events	
  to	
  
occur	
  and	
  dilutes	
  our	
  focus	
  on	
  defining	
  what	
  Done	
  looks	
  like	
  for	
  each	
  Program	
  
Event.	
  
	
  	
  
7
V8.7	
  
46	
  
7.0	
  6	
  Steps	
  
Quick	
  View	
  of	
  Step-­‐By-­‐Step	
  IMP	
  
IdenLfy	
  Program	
  Events	
  
IdenLfy	
  Significant	
  Accomplishments	
  
IdenLfy	
  Accomplishment	
  Criteria	
  
IdenLfy	
  Work	
  Packages	
  needed	
  to	
  complete	
  
the	
  Accomplishment	
  Criteria	
  
Sequence	
  the	
  Work	
  Packages	
  (WP),	
  Planning	
  
Packages	
  (PP),	
  Summary	
  Level	
  Planning	
  
Packages	
  (SLPP)	
  	
  in	
  a	
  logical	
  network.	
  
Adjust	
  the	
  sequence	
  of	
  WPs,	
  PPs,	
  &	
  SLPPs	
  to	
  
miLgate	
  major	
  risks.	
  
47	
  
7.0	
  6	
  Steps	
  
1
2
3
4
5
6
IdenLfy	
  the	
  Program	
  Events	
  
Actors	
   Processes	
   Outcomes	
  
Systems	
  Engineer	
  
Define	
  the	
  process	
  flow	
  for	
  
product	
  producLon	
  from	
  
contract	
  award	
  to	
  end	
  of	
  
contract	
  
!  Confirm	
  Program	
  Events	
  represent	
  the	
  
logical	
  process	
  flow	
  for	
  program	
  
maturity	
  
Program	
  Manager	
  
Confirm	
  customer	
  is	
  willing	
  to	
  
accept	
  the	
  process	
  flows	
  
developed	
  by	
  the	
  IMP	
  
!  Engage	
  with	
  contracts	
  and	
  customer	
  
for	
  PE	
  definiLon	
  
Project	
  Engineer	
  
IdenLfy	
  interdependencies	
  
between	
  program	
  event	
  work	
  
streams	
  
!  IdenLfy	
  Value	
  Stream	
  components	
  at	
  
the	
  PE	
  level	
  before	
  flowing	
  them	
  down	
  
to	
  the	
  SA	
  level	
  
IMP/IMS	
  Architect	
  
Capture	
  Program	
  Event	
  
contents	
  for	
  each	
  IPT	
  or	
  work	
  
stream	
  
!  Establish	
  foundaLon	
  for	
  a	
  structure	
  to	
  
support	
  the	
  descripLon	
  of	
  the	
  
increasing	
  mature	
  as	
  well	
  as	
  the	
  flow	
  
to	
  needed	
  work.	
  
Copyright	
  ©	
  2012,	
  Glen	
  B.	
  Alleman,	
  Niwot	
  Ridge,	
  LLC	
   48	
  
1
7.0	
  6	
  Steps	
  
Outcomes	
  of	
  Step	
  
!  Confirm	
  the	
  end	
  to	
  end	
  descripLon	
  of	
  the	
  
increasing	
  maturity	
  of	
  the	
  program’s	
  
deliverables	
  
!  Establish	
  of	
  RFP	
  or	
  Contract	
  target	
  dates	
  for	
  
each	
  Event.	
  	
  
!  Socialize	
  the	
  language	
  of	
  speaking	
  in	
  “Events”	
  
rather	
  than	
  Lme	
  and	
  efforts	
  
49	
  
1
7.0	
  6	
  Steps	
  
Events	
  Define	
  the	
  Assessment	
  	
  
of	
  the	
  Program’s	
  Maturity	
  
50	
  
! Program	
  Events	
  are	
  maturity	
  
assessment	
  points	
  in	
  the	
  program	
  
! They	
  define	
  what	
  levels	
  of	
  maturity	
  
for	
  the	
  products	
  and	
  services	
  are	
  
needed	
  before	
  proceeding	
  to	
  the	
  next	
  
maturity	
  assessment	
  point	
  
! The	
  entry	
  criteria	
  for	
  each	
  Event	
  
defines	
  the	
  units	
  of	
  measure	
  for	
  the	
  
successful	
  compleLon	
  of	
  the	
  Event	
  
! The	
  example	
  below	
  is	
  typical	
  of	
  the	
  
purpose	
  of	
  a	
  Program	
  Event	
  
The	
  Cri=cal	
  Design	
  Review	
  (CDR)	
  is	
  a	
  mul=-­‐disciplined	
  product	
  and	
  process	
  assessment	
  to	
  ensure	
  
that	
  the	
  system	
  under	
  review	
  can	
  proceed	
  into	
  system	
  fabrica=on,	
  demonstra=on,	
  and	
  test,	
  and	
  
can	
  meet	
  the	
  stated	
  performance	
  requirements	
  within	
  cost	
  (program	
  budget),	
  schedule	
  (program	
  
schedule),	
  risk,	
  and	
  other	
  system	
  constraints.	
  	
  
1
7.0	
  6	
  Steps	
  
IdenLfy	
  the	
  Significant	
  Accomplishments	
  
(SA)	
  for	
  Each	
  Program	
  Event	
  (PE)	
  
51	
  
Actors	
   Processes	
   Outcomes	
  
System	
  Engineer	
  
IdenLfy	
  Integrated	
  Product	
  Teams	
  
(IPT)	
  responsible	
  for	
  the	
  SA’s	
  	
  
!  Define	
  the	
  boundaries	
  of	
  these	
  
programmaLc	
  interfaces	
  
!  Define	
  technical	
  and	
  process	
  risk	
  
categories	
  and	
  their	
  bounds	
  
Technical	
  Lead	
  
Confirm	
  the	
  sequence	
  of	
  SA’s	
  has	
  
the	
  proper	
  dependency	
  
relaLonships	
  
!  Define	
  the	
  product	
  development	
  
flow	
  process	
  improves	
  maturity	
  
!  Define	
  technical	
  risk	
  drivers	
  
Project	
  Engineer	
  
Confirm	
  logic	
  of	
  SA’s	
  for	
  project	
  
sequence	
  integrity	
  
!  Define	
  the	
  program	
  flows	
  
improves	
  maturity	
  	
  
Control	
  Account	
  
Manager	
  
Validate	
  SA	
  outcomes	
  in	
  support	
  of	
  
PE	
  entry	
  condiLons	
  
!  Confirm	
  budget	
  and	
  resources	
  
adequate	
  for	
  defined	
  work	
  effort	
  
IMP/IMS	
  Architect	
  
Assure	
  the	
  assessment	
  points	
  
provide	
  a	
  logical	
  flow	
  of	
  maturity	
  at	
  
the	
  proper	
  intervals	
  for	
  the	
  
program	
  
!  Maintain	
  the	
  integrity	
  of	
  the	
  IMP,	
  
WBS,	
  and	
  IMS	
  
2
7.0	
  6	
  Steps	
  
Outcomes	
  of	
  Step	
  
!  The	
  Significant	
  Accomplishments	
  are	
  the	
  
“road	
  map”	
  to	
  the	
  increasing	
  maturity	
  of	
  the	
  
program	
  
!  The	
  “Value	
  Stream	
  Map”	
  resulLng	
  from	
  the	
  
flow	
  of	
  SA’s	
  describes	
  how	
  the	
  products	
  or	
  
services	
  move	
  through	
  the	
  maturaLon	
  process	
  
while	
  reducing	
  risk	
  
!  The	
  SA	
  map	
  is	
  the	
  path	
  to	
  “done”	
  	
  
52	
  
2
7.0	
  6	
  Steps	
  
SAs	
  define	
  the	
  entry	
  criteria	
  for	
  
each	
  Program	
  Event	
  
53	
  
Preliminary	
  Design	
  Review	
  Complete	
  
3
7.0	
  6	
  Steps	
  
IdenLfy	
  Accomplishment	
  Criteria	
  (AC)	
  for	
  each	
  
Significant	
  Accomplishment	
  (SA)	
  
Actors	
   Processes	
   Outcomes	
  
CAM	
  
Define	
  and	
  sequence	
  the	
  contents	
  
of	
  each	
  Work	
  Package	
  and	
  select	
  
the	
  EV	
  criteria	
  for	
  each	
  Task	
  
needed	
  to	
  roll	
  up	
  the	
  BCWP	
  
measurement	
  
!  Establish	
  ownership	
  for	
  the	
  
content	
  of	
  each	
  Work	
  Package	
  
and	
  the	
  Exit	
  Criteria	
  –	
  the	
  
Accomplishment	
  Criteria	
  (AC)	
  
Project	
  Engineer	
  
IdenLfy	
  the	
  logical	
  process	
  flow	
  of	
  
the	
  Work	
  Package	
  to	
  assure	
  the	
  
least	
  effort,	
  maximum	
  value	
  and	
  
lowest	
  risk	
  path	
  to	
  the	
  Program	
  
Event	
  
!  Establish	
  ownership	
  for	
  the	
  
process	
  flow	
  of	
  the	
  product	
  or	
  
service	
  
Technical	
  Lead	
  
Assure	
  all	
  technical	
  processes	
  are	
  
covered	
  in	
  each	
  Work	
  Package	
  
!  Establish	
  ownership	
  for	
  the	
  
technical	
  outcome	
  of	
  each	
  Work	
  
Package	
  
IMP/IMS	
  Architect	
  
Confirm	
  the	
  process	
  flow	
  of	
  the	
  ACs	
  
can	
  follow	
  the	
  DID	
  81650	
  
structuring	
  and	
  Risk	
  Assessment	
  
processes	
  
!  Guide	
  the	
  development	
  of	
  
outcomes	
  for	
  each	
  Work	
  Package	
  
to	
  assure	
  increasing	
  maturity	
  of	
  
the	
  program	
   54	
  
3
7.0	
  6	
  Steps	
  
Outcomes	
  of	
  Step	
  
!  The	
  definiLon	
  of	
  “done”	
  emerges	
  in	
  the	
  form	
  
of	
  deliverables	
  rather	
  than	
  measures	
  of	
  cost	
  
and	
  passage	
  of	
  Lme.	
  
!  At	
  each	
  Program	
  Event,	
  the	
  increasing	
  
maturity	
  of	
  the	
  deliverables	
  is	
  defined	
  through	
  
the	
  Measures	
  of	
  EffecLveness	
  (MoE)	
  and	
  
Measures	
  of	
  Performance	
  (MoP)	
  
55	
  
3
7.0	
  6	
  Steps	
  
ACs	
  are	
  higher	
  fidelity	
  
descripLons	
  of	
  “Done”	
  than	
  SAs	
  
56	
  Cri%cal	
  Design	
  Review	
  Complete	
  
4
7.0	
  6	
  Steps	
  
IdenLfy	
  the	
  Work	
  for	
  Each	
  Accomplishment	
  
Criteria	
  in	
  Work	
  Packages	
  
Actors	
   Processes	
   Outcomes	
  
Control	
  Account	
  
Manager	
  
IdenLfy	
  or	
  confirm	
  the	
  work	
  
acLviLes	
  in	
  the	
  Work	
  Package	
  
represent	
  the	
  allocated	
  work	
  
!  Define	
  bounded	
  work	
  effort	
  
defined	
  “inside”	
  each	
  Work	
  
Package	
  
Technical	
  Lead	
  
Confirm	
  this	
  work	
  covers	
  the	
  SOW	
  
and	
  CDRLs	
  
!  Define	
  all	
  work	
  effort	
  for	
  100%	
  
compleLon	
  of	
  deliverable	
  visible	
  in	
  
a	
  single	
  locaLon	
  –	
  the	
  Work	
  
Package	
  
!  Confirm	
  risk	
  drivers	
  and	
  duraLon	
  
variances	
  
IMP/IMS	
  Architect	
  
Assist	
  in	
  the	
  sequencing	
  the	
  work	
  
efforts	
  in	
  a	
  logical	
  manner	
  
!  Develop	
  foundaLon	
  of	
  the	
  
maturity	
  flow	
  starLng	
  to	
  emerge	
  
from	
  the	
  contents	
  of	
  the	
  Work	
  
Packages	
  
Earned	
  Value	
  
Analyst	
  
Assign	
  iniLal	
  BCWS	
  from	
  BOE	
  to	
  
Work	
  Package	
  
!  ConfirmaLon	
  of	
  work	
  effort	
  
against	
  BOEs	
  
!  Define	
  EVT	
  for	
  measures	
  progress	
  
to	
  plan	
   57	
  
4
7.0	
  6	
  Steps	
  
Outcomes	
  of	
  Step	
  
!  The	
  work	
  idenLfied	
  that	
  produces	
  a	
  
measurable	
  outcome.	
  
!  This	
  work	
  defined	
  in	
  each	
  Work	
  Package	
  
!  The	
  Accomplishment	
  Criteria	
  (AC)	
  state	
  
explicitly	
  what	
  “done”	
  looks	
  like	
  for	
  this	
  effort	
  
!  With	
  “done”	
  stated,	
  measures	
  of	
  Performance	
  
and	
  measures	
  of	
  EffecLveness	
  can	
  be	
  defined	
  
58	
  
4
7.0	
  6	
  Steps	
  
Work	
  is	
  done	
  in	
  “packages”	
  that	
  
produce	
  measureable	
  outcomes	
  
59	
  
Launch	
  Readiness	
  Review	
  Complete	
  
5
7.0	
  6	
  Steps	
  
Sequence	
  Work	
  Packages	
  (ACs)	
  for	
  each	
  
Significant	
  Accomplishment	
  (SA)	
  
60	
  
Actors	
   Processes	
   Outcomes	
  
Control	
  Account	
  
Manager	
  
Define	
  the	
  order	
  of	
  the	
  Work	
  
Packages	
  needed	
  to	
  meet	
  the	
  
Significant	
  Accomplishments	
  for	
  
each	
  Program	
  Event	
  
!  Define	
  the	
  process	
  flow	
  of	
  work	
  
and	
  the	
  resulLng	
  
accomplishments.	
  
!  Assure	
  value	
  is	
  being	
  produced	
  at	
  
each	
  SA	
  and	
  the	
  AC’s	
  that	
  drive	
  
them	
  
IMP/IMS	
  Architect	
  
Assure	
  that	
  the	
  sequence	
  of	
  Work	
  
Packages	
  adheres	
  to	
  the	
  guidance	
  
provided	
  by	
  DCMA	
  and	
  the	
  EVMS	
  
System	
  descripLon	
  
!  Begin	
  the	
  structuring	
  of	
  the	
  IMS	
  
for	
  compliance	
  and	
  loading	
  into	
  
the	
  cost	
  system	
  
Program	
  Controls	
  
Staff	
  
Baseline	
  the	
  sequence	
  of	
  Work	
  
Packages	
  using	
  Earned	
  Value	
  
Techniques	
  (EVT)	
  with	
  measures	
  of	
  
Physical	
  Percent	
  Complete	
  
!  Develop	
  insight	
  to	
  progress	
  to	
  
plan	
  with	
  measures	
  of	
  physical	
  
progress	
  for	
  each	
  Work	
  Packages	
  
(EVT)	
  
5
7.0	
  6	
  Steps	
  
Outcomes	
  of	
  Step	
  
!  Work	
  Packages	
  parLLon	
  work	
  efforts	
  into	
  
“bounded”	
  scope	
  
!  Interdependencies	
  constrained	
  to	
  Work	
  
Package	
  boundaries	
  prevents	
  “spaghe{	
  code”	
  
style	
  schedule	
  flow	
  
!  Visibility	
  of	
  the	
  Increasing	
  Flow	
  of	
  Maturity	
  
starLng	
  to	
  emerge	
  from	
  the	
  flow	
  of	
  
Accomplishment	
  Criteria	
  (AC)	
  
61	
  
5
7.0	
  6	
  Steps	
  
Sequence	
  Work	
  Packages	
  (AC’s)	
  into	
  
an	
  IMS	
  for	
  each	
  Program	
  Event	
  
62	
  
6
7.0	
  6	
  Steps	
  
Assemble	
  Final	
  IMP/IMS	
  
Actors	
   Processes	
   Outcomes	
  
IMP/IMS	
  Architect	
  
StarLng	
  with	
  the	
  AC’s	
  under	
  each	
  
SA’s	
  connect	
  Work	
  Packages	
  in	
  the	
  
proper	
  order	
  for	
  each	
  Program	
  
Event	
  
!  Establish	
  the	
  Performance	
  
Measurement	
  Baseline	
  
framework.	
  
!  IdenLfy	
  MoE	
  and	
  MoP	
  points	
  in	
  
the	
  IMP	
  
Program	
  Manager	
  
Confirm	
  the	
  work	
  efforts	
  represent	
  
the	
  commieed	
  acLviLes	
  for	
  the	
  
contract	
  
!  Review	
  and	
  approval	
  of	
  the	
  IMS	
  –	
  
ready	
  for	
  baseline.	
  
!  Review	
  and	
  approve	
  risk	
  drivers	
  
and	
  duraLon	
  variance	
  models	
  
Project	
  Engineer	
  
Assess	
  the	
  product	
  development	
  
flow	
  for	
  opLmizaLons	
  
!  Review	
  and	
  approval	
  of	
  the	
  IMS	
  –	
  
ready	
  for	
  baseline.	
  
!  IdenLfy	
  risk	
  drivers	
  and	
  their	
  
miLgaLons	
  
Systems	
  Engineer	
  
Confirm	
  the	
  work	
  process	
  flows	
  
result	
  in	
  the	
  proper	
  products	
  being	
  
built	
  in	
  the	
  right	
  order	
  
!  Confirm	
  risk	
  drivers	
  and	
  duraLon	
  
variances.	
  
!  Review	
  and	
  approval	
  of	
  the	
  IMS	
  –	
  
ready	
  for	
  baseline	
   63	
  
6
7.0	
  6	
  Steps	
  
Outcomes	
  of	
  Step	
  
!  Both	
  the	
  maturity	
  assessment	
  criteria	
  and	
  the	
  
work	
  needed	
  to	
  reach	
  that	
  level	
  of	
  maturity	
  are	
  
described	
  in	
  a	
  single	
  locaLon	
  
!  Risks	
  are	
  integrated	
  with	
  the	
  IMP	
  and	
  IMS	
  at	
  
their	
  appropriate	
  levels	
  
–  Risks	
  to	
  EffecLveness	
  –	
  risk	
  to	
  JROC	
  KPPs	
  
–  Risks	
  to	
  Performance	
  –	
  risk	
  to	
  program	
  KPPs	
  and	
  
TPMs	
  
!  Leading	
  and	
  Lagging	
  indicator	
  data	
  provide	
  
through	
  each	
  measure	
  to	
  forecast	
  future	
  
performance	
  
	
   64	
  
6
7.0	
  6	
  Steps	
  
The	
  Previous	
  6	
  Steps	
  Result	
  In	
  A	
  
Credible	
  IMP/IMS	
  
65	
  
!  The	
  IMP	
  is	
  the	
  “Outer	
  Mold	
  
Line”,	
  the	
  Framework,	
  the	
  
“Going	
  Forward”	
  Strategy	
  for	
  
the	
  Program.	
  
!  The	
  IMP	
  describes	
  the	
  path	
  
to	
  increasing	
  maturity	
  and	
  
the	
  Events	
  measuring	
  that	
  
maturity.	
  
!  The	
  IMP	
  tells	
  us	
  “How”	
  the	
  
program	
  will	
  flow	
  with	
  the	
  
least	
  risk,	
  the	
  maximum	
  
value,	
  and	
  the	
  clearest	
  
visibility	
  to	
  progress.	
  
!  The	
  IMS	
  tells	
  us	
  what	
  work	
  is	
  
needed	
  to	
  produce	
  the	
  
product	
  or	
  service	
  at	
  the	
  
Work	
  Package	
  level.	
  
Our	
  Plan	
  Tells	
  Us	
  “How”	
  We	
  
are	
  Going	
  to	
  Proceed	
  
The	
  Schedule	
  Tells	
  Us	
  
“What”	
  Work	
  is	
  Needed	
  to	
  
Proceed	
  
7.0	
  6	
  Steps	
  
Significant	
  Accomplishments	
  for	
  an	
  actual	
  
Program	
  Event	
  
Flight	
  Test	
  Ascent	
  Aerodynamics	
  Confirmed	
  
66	
  
7.0	
  6	
  Steps	
  
Horizontal	
  and	
  VerLcal	
  Traceability	
  
of	
  the	
  IMP/IMS	
  
Integrated	
  Master	
  Schedule	
  
Work	
  sequenced	
  to	
  
produce	
  outcomes	
  
for	
  each	
  WP.	
  
!  VerLcal	
  traceability	
  AC	
  "	
  SA	
  "	
  PE	
  
!  Horizontal	
  traceability	
  WP	
  "	
  WP	
  "AC	
  
Program Events
Define the maturity
of a Capability at a point in
time.
Significant Accomplishments
Represent requirements
that enable Capabilities.
Accomplishment Criteria
Exit Criteria for the Work
Packages that fulfill Requirements.
Work	
  
Package	
  
Work	
  
Package	
  
Work	
  
Package	
  
Work	
  
Package	
  
Work	
  
Package	
  
Work	
  
package	
  
Work	
  
Package	
  
Work	
  
Package	
  
67	
  
7.0	
  6	
  Steps	
  
The	
  IMP’s	
  connecLon	
  to	
  the	
  WBS	
  
!  Start	
  with	
  the	
  Significant	
  Accomplishments	
  and	
  sequence	
  
them	
  to	
  the	
  maturity	
  flow	
  for	
  each	
  Program	
  Event	
  
!  The	
  WBS	
  connecLons	
  then	
  become	
  orthogonal	
  to	
  this	
  flow	
  
68	
  
7.0	
  6	
  Steps	
  
Program	
  Event	
  
SRR	
   SDR	
   PDR	
   CDR	
   TRR	
   ATLO	
  
Work	
  Breakdown	
  
Structure	
  
4.920-­‐SDAI	
   A01,	
  A02	
   B01	
   C01,	
  C02	
   D01	
   E01	
   F01	
  
4.200-­‐Sys	
  Test	
   A05	
   B03,	
  B04	
   D02,	
  D03	
   E02	
   F02	
  
4.300-­‐Radar	
   A03	
   B02	
   C03	
   E03	
  
4.330-­‐O&C	
  Sys	
   A06,	
  A07	
   B05	
   C04	
   D04	
   E04	
   F03,	
  F04	
  
4.400-­‐	
  I&T	
   A08	
   C05	
   E05,	
  E06	
   F05	
  
4.500-­‐Support	
   A09	
   D05	
   E07	
   F06,	
  F07	
  
69	
  
7.0	
  6	
  Steps	
  
70	
  
7.0	
  6	
  Steps	
  
71	
  
7.0	
  6	
  Steps	
  
72	
  
7.0	
  6	
  Steps	
  
73	
  
7.0	
  6	
  Steps	
  
74	
  
7.0	
  6	
  Steps	
  
Nuances	
  Of	
  These	
  6	
  Steps	
  
Building	
  the	
  Program	
  Event,	
  to	
  Significant	
  Accomplishment,	
  to	
  Accomplishment	
  
decomposiLon	
  is	
  straight	
  forward.	
  
For	
  each	
  Program	
  Event,	
  simply	
  idenLfy	
  what	
  are	
  the	
  needed	
  Significant	
  
Accomplishment	
  for	
  the	
  entry	
  and	
  exit	
  criteria,	
  and	
  the	
  Accomplishment	
  Criteria	
  
for	
  the	
  Work	
  Packages	
  that	
  produce	
  the	
  AC.	
  
Yea	
  Right,	
  no	
  problem	
  
8
V8.7	
  
76	
  
8.0	
  Nuances	
  
Quick	
  View	
  of	
  the	
  Nuances	
  
!  Unfortunately	
  building	
  a	
  credible	
  IMP/IMS	
  is	
  a	
  
nuanced	
  process,	
  subject	
  to	
  many	
  opportuniLes	
  
for	
  diversions,	
  blind	
  alleys,	
  and	
  false	
  starts	
  	
  
!  It	
  is	
  slightly	
  counter	
  intuiLve	
  from	
  the	
  tradiLonal	
  
scheduling	
  approach	
  to	
  start	
  with	
  the	
  verLcal	
  
integraLon	
  –	
  but	
  it	
  is	
  criLcal	
  to	
  start	
  verLcally	
  
!  Success	
  requires	
  the	
  full	
  parLcipaLon	
  of	
  Systems	
  
Engineering,	
  CAMs,	
  and	
  the	
  Program	
  Manager	
  
!  Success	
  requires	
  everyone	
  to	
  understand	
  the	
  
nuances	
  of	
  the	
  IMP	
  building	
  efforts	
  
77	
  
8.0	
  Nuances	
  
The	
  1st	
  Nuance	
  
We	
  need	
  to	
  change	
  the	
  Planning	
  Paradigm	
  
Beginner	
  	
   Intermediate	
   Advanced	
  
! Take	
  the	
  program	
  events	
  
and	
  use	
  the	
  WBS	
  to	
  define	
  
the	
  SAs	
  and	
  ACs.	
  
! IdenLfy	
  the	
  tasks	
  to	
  produce	
  
the	
  ACs	
  and	
  SAs	
  
! Collect	
  them	
  into	
  Program	
  
Events	
  
! Organize	
  the	
  tasks	
  by	
  Work	
  
Package	
  
! Sequence	
  the	
  work	
  packages	
  
(AC’s)	
  	
  
! Examine	
  the	
  exit	
  criteria	
  for	
  
the	
  Program	
  Events	
  –	
  what	
  
does	
  Done	
  look	
  like?	
  
! Ask	
  what	
  the	
  entry	
  criteria	
  
are	
  for	
  each	
  Program	
  Event	
  
! Build	
  the	
  AC’s	
  to	
  support	
  
these	
  entry	
  criteria	
  
! Pull	
  these	
  together	
  under	
  
each	
  SA	
  
! Determine	
  the	
  Technical	
  and	
  
ProgrammaLc	
  maturity	
  for	
  
each	
  Program	
  Event	
  from	
  
the	
  Concept	
  of	
  OperaLons	
  
! Assess	
  the	
  SA’s	
  for	
  each	
  
Integrated	
  Product	
  Team	
  in	
  
terms	
  of	
  their	
  streams	
  
maturity	
  at	
  that	
  point	
  in	
  the	
  
program	
  
! Sequence	
  the	
  SA’s	
  for	
  each	
  
PE	
  and	
  assess	
  the	
  units	
  of	
  
measure	
  of	
  “maturity”	
  
! Build	
  the	
  AC’s	
  to	
  support	
  
each	
  SA’s	
  level	
  of	
  maturity	
  
Copyright	
  ©	
  2012,	
  Glen	
  B.	
  Alleman,	
  Niwot	
  Ridge,	
  LLC	
   78	
  
8.0	
  Nuances	
  
The	
  2nd	
  Nuance	
  
We	
  need	
  to	
  speak	
  about	
  Increasing	
  Maturity	
  
Beginner	
   Intermediate	
   Advanced	
  
! The	
  sequence	
  of	
  work	
  
closely	
  matches	
  the	
  
horizontal	
  schedules	
  of	
  the	
  
past	
  
! Align	
  this	
  work	
  with	
  the	
  WBS	
  
elements	
  
! Focus	
  on	
  the	
  WBS	
  DicLonary	
  
of	
  the	
  delivered	
  products	
  or	
  
services	
  
! No	
  explicit	
  TPM,	
  MOE,	
  and	
  
MOP	
  elements	
  
	
  
! The	
  sequence	
  of	
  work	
  is	
  
related	
  to	
  the	
  Program	
  
Events,	
  but	
  essenLally	
  
“hangs”	
  from	
  the	
  PE	
  to	
  the	
  
SA’s	
  and	
  then	
  the	
  AC’s	
  
! All	
  deliverables	
  are	
  visible	
  
but	
  their	
  TPMs	
  and	
  other	
  
system	
  measures	
  are	
  not	
  
stated	
  in	
  the	
  IMP	
  or	
  its	
  
narraLve.	
  
! There	
  is	
  a	
  narraLve	
  in	
  the	
  
form	
  of	
  SA’s	
  and	
  AC’s	
  that	
  
describes	
  how	
  the	
  program	
  
moves	
  from	
  leo	
  to	
  right	
  
alone	
  its	
  maturity	
  path	
  
! Risk	
  buy	
  down	
  and	
  
reLrement	
  are	
  visible	
  
! Intermediate	
  Technical	
  
Performance	
  Measures,	
  
Measures	
  of	
  EffecLveness,	
  
and	
  Measures	
  of	
  
Performance	
  are	
  visible	
  in	
  
the	
  IMP	
  
Copyright	
  ©	
  2012,	
  Glen	
  B.	
  Alleman,	
  Niwot	
  Ridge,	
  LLC	
   79	
  
8.0	
  Nuances	
  
The	
  3rd	
  Nuance	
  
Everything	
  Foot	
  and	
  Ties	
  to	
  the	
  IMP	
  &	
  IMS	
  
Beginner	
   Intermediate	
   Advanced	
  
! The	
  IMS	
  contains	
  all	
  the	
  
proper	
  fields	
  in	
  columns	
  and	
  
is	
  horizontally	
  linked	
  
! The	
  WBS	
  elements	
  can	
  be	
  
found	
  for	
  all	
  work	
  elements	
  
! CDRL’s	
  are	
  visible	
  and	
  their	
  
mulLple	
  delivery	
  dates	
  
connected	
  to	
  each	
  Program	
  
Event	
  
! WBS	
  is	
  structured	
  in	
  a	
  
product	
  manner	
  or	
  possibly	
  
a	
  funcLonal	
  manner	
  with	
  
some	
  deliverables	
  defined	
  in	
  
the	
  terminal	
  nodes	
  
! The	
  WBS	
  is	
  properly	
  formed	
  
inside	
  each	
  AC	
  with	
  
incremental	
  deliverables	
  
! WBS	
  numbers	
  form	
  a	
  “well	
  
structured”	
  tree,	
  but	
  sLll	
  is	
  
not	
  “pure”	
  in	
  the	
  sense	
  of	
  
deliverables	
  only,	
  no	
  
funcLonal	
  
! Each	
  column	
  and	
  each	
  field	
  
can	
  be	
  “pivoted”	
  to	
  form	
  a	
  
proper	
  “tree”	
  of	
  value	
  flow.	
  
! The	
  WBS	
  is	
  a	
  “pure”	
  Product	
  
Breakdown	
  Structure	
  (PBS)	
  
and	
  the	
  services	
  needed	
  to	
  
produce	
  those	
  products	
  
! The	
  WBS	
  defines	
  the	
  
structure	
  of	
  the	
  delivered	
  
product	
  or	
  service	
  
! The	
  VerLcal	
  trace	
  of	
  the	
  IPM	
  
describes	
  the	
  flow	
  of	
  
increasing	
  maturity	
  of	
  these	
  
products	
  or	
  services	
  
! The	
  Horizontal	
  trace	
  of	
  the	
  
IMP	
  describes	
  to	
  work	
  to	
  be	
  
done	
  to	
  produce	
  this	
  
maturity	
   80	
  
8.0	
  Nuances	
  
The	
  4th	
  Nuance	
  
IMP/IMS	
  is	
  ProgrammaLc	
  Architecture	
  
Beginner	
   Intermediate	
   Advanced	
  
! The	
  IMP	
  is	
  built	
  from	
  the	
  
WBS	
  for	
  each	
  Program	
  
Event.	
  
! The	
  IMP	
  is	
  seen	
  as	
  a	
  
compliance	
  document	
  that	
  
lists	
  the	
  Program	
  Events	
  and	
  
a	
  “bunch	
  of	
  stuff”	
  
underneath.	
  	
  
! The	
  IMP	
  is	
  structured	
  
around	
  separate	
  Program	
  
Events,	
  but	
  below	
  the	
  SA’s	
  
looks	
  like	
  a	
  “shop	
  floor”	
  
schedule	
  with	
  liele	
  verLcal	
  
connecLvity.	
  
! The	
  IMP	
  is	
  built	
  as	
  a	
  “value	
  
stream”	
  flow	
  for	
  the	
  
program	
  but	
  the	
  Systems	
  
Engineers	
  
! This	
  programmaLc	
  
architecture	
  is	
  built	
  in	
  the	
  
same	
  way	
  the	
  technical	
  
system	
  architecture	
  is	
  built	
  
! It	
  is	
  derived	
  from	
  the	
  
ConOps	
  and	
  Tier	
  1	
  System	
  
Requirements	
  
! The	
  IMP	
  shows	
  explicitly	
  
how	
  these	
  are	
  supported	
  in	
  
the	
  flow	
  of	
  the	
  SA’s	
  
81	
  
8.0	
  Nuances	
  
The	
  5th	
  Nuance	
  
The	
  IMP/IMS	
  connects	
  all	
  the	
  dots	
  
82	
  
8.0	
  Nuances	
  
Measure	
  of	
  
EffecLveness	
  
Measure	
  of	
  
Performance	
  
Technical	
  
Performance	
  
Measure	
  
Risk	
  
Aleatory	
  
Uncertainty	
  
Epistemic	
  
Uncertainty	
  
Reference	
  
Classes	
  
Past	
  
Performance	
  
SME	
  
Past	
  
Performance	
  
System	
  
Architecture	
  
AHP	
  
ConnecLng	
  The	
  IMP	
  To	
  Program	
  
Performance	
  Measures	
  
Assembling	
  the	
  IMS	
  from	
  the	
  IMP	
  appears	
  to	
  be	
  a	
  straight	
  forward	
  process	
  –	
  
details	
  the	
  tasks	
  that	
  support	
  the	
  Accomplishment	
  Criteria.	
  But	
  there	
  are	
  some	
  
criLcal	
  steps	
  that	
  must	
  be	
  done	
  in	
  the	
  right	
  order	
  to	
  end	
  up	
  with	
  a	
  risk	
  tolerant	
  
IMS.	
  
Let’s	
  do	
  this	
  for	
  Our	
  Program	
  
9
V8.7	
  
The	
  Primary	
  Role	
  for	
  the	
  IMP	
  is	
  to	
  describe	
  
what	
  done	
  looks	
  like	
  in	
  MoE’s	
  and	
  MoP’s	
  
84	
  19	
  October	
  1899	
  Robert	
  Goddard	
  decided	
  that	
  he	
  wanted	
  to	
  "fly	
  without	
  wings"	
  to	
  Moon.	
  
9.0	
  Framework	
  
Quick	
  View	
  to	
  IMP/IMS	
  Framework	
  
!  Measures	
  of	
  increasing	
  maturity	
  for	
  the	
  key	
  
deliverables	
  is	
  the	
  foundaLon	
  for	
  increasing	
  
the	
  Probability	
  of	
  Program	
  Success	
  
!  Measures	
  of	
  EffecLveness	
  (MoE)	
  and	
  
Measures	
  of	
  Performance	
  (MoP)	
  are	
  defined	
  
in	
  the	
  Integrated	
  Master	
  Plan	
  (IMP)	
  NarraLve	
  
!  Key	
  Performance	
  Parameters	
  (KPP)	
  –	
  both	
  
JROC	
  and	
  program	
  specific	
  are	
  needed	
  
!  Technical	
  Performance	
  Measures	
  (TPM)	
  are	
  
needed	
  for	
  all	
  key	
  deliverables	
  
85	
  
9.0	
  Framework	
  
Components	
  we’ll	
  meet	
  along	
  the	
  way	
  
to	
  our	
  desLnaLon	
  to	
  the	
  credible	
  PMB	
  
86	
  
86	
  
ObjecLve	
  Status	
  and	
  EssenLal	
  Views	
  to	
  support	
  the	
  proacLve	
  management	
  processes	
  needed	
  
to	
  keep	
  the	
  program	
  GREEN	
  
Risk	
  Management	
  
SOW	
  
SOO	
  
ConOps	
  
WBS	
  
Techncial	
  and	
  OperaLonal	
  
Requirements	
  
CWBS	
  &	
  
CWBS	
  DicLonary	
  
Integrated	
  Master	
  Plan	
  
(IMP)	
  
Integrated	
  Master	
  Schedule	
  
(IMS)	
  	
  
Measures	
  of	
  
EffecLveness	
  
Measures	
  of	
  
Performance	
  
Measures	
  of	
  
Progress	
  
JROC	
  	
  
Key	
  Performance	
  Parameters	
  
Program	
  	
  Specific	
  
Key	
  Performance	
  Parameters	
  
Technical	
  Performance	
  
Measures	
  
Earned	
  Value	
  Management	
  
System	
  
TPMs	
  Live	
  
Here	
  
Performance	
  Measurement	
  Baseline	
  
86
9.0	
  Framework	
  
Components	
  of	
  our	
  Final	
  
DesLnaLon	
  
87	
  
Sow	
  
SOO	
  
ConOps	
  
WBS	
  
Techncial	
  and	
  OperaLonal	
  
Requirements	
  
Performance	
  Measurement	
  Baseline	
  
CWBS	
  &	
  
CWBS	
  DicLonary	
  
Integrated	
  Master	
  Plan	
  
(IMP)	
  
Integrated	
  Master	
  Schedule	
  
(IMS)	
  	
  
Earned	
  Value	
  Management	
  
System	
  
Technical Performance Measurement (TPM) involves the predicting the future
values of a key technical performance parameter of the higher-level end product
under development, based on current assessments of products lower in the
system structure. Continuous verification of actual versus anticipated achievement
for selected technical parameters confirms progress and identifies variances that
might jeopardize meeting a higher-level end product requirement. Assessed
values falling outside established tolerances indicate the need for management
attention and corrective action.
A well thought out TPM program provides early warning of technical problems,
supports assessments of the extent to which operational requirements will be met,
and assesses the impacts of proposed changes made to lower-level elements in
the system hierarchy on system performance.
Techncial	
  Performance	
  
Measurement	
  
heps://dap.dau.mil/acquipedia/Pages/Default.aspx	
   87
9.0	
  Framework	
  
IdenLfying	
  the	
  TPMs	
  starts	
  with	
  
good	
  Systems	
  Engineering	
  
88	
  
9.0	
  Framework	
  
!  EIA-­‐632	
  –	
  involves	
  a	
  technique	
  of	
  predicLng	
  
the	
  future	
  value	
  of	
  a	
  key	
  technical	
  
performance	
  parameter	
  of	
  the	
  higher-­‐level	
  
end	
  product	
  under	
  development,	
  based	
  on	
  
current	
  assessments	
  of	
  products	
  lower	
  in	
  the	
  
system	
  structure.	
  	
  
!  INCOSE	
  Systems	
  Engineering	
  Handbook.	
  
InternaLonal	
  Council	
  on	
  Systems	
  Engineering	
  
!  INCOSE	
  Metrics	
  Guidebook	
  for	
  Integrated	
  
System	
  and	
  Product	
  Development	
  
89	
  
Policy	
  Guidance	
  for	
  TPMs	
  
9.0	
  Framework	
  
The	
  NDIA	
  EVM	
  Intent	
  Guide	
  Says	
  
90	
  
Notice the inclusion of Technical along with
Cost and Schedule
That’s the next step is generating Value from Earned Value
EV MUST include the Technical Performance Measures
9.0	
  Framework	
  
Some	
  More	
  Guidance	
  
91	
  
Systems	
  engineering	
  uses	
  technical	
  performance	
  
measurements	
  to	
  balance	
  cost,	
  schedule,	
  and	
  performance	
  
throughout	
  the	
  life	
  cycle.	
  Technical	
  performance	
  
measurements	
  compare	
  actual	
  versus	
  planned	
  technical	
  
development	
  and	
  design.	
  They	
  also	
  report	
  the	
  degree	
  to	
  
which	
  system	
  requirements	
  are	
  met	
  in	
  terms	
  of	
  performance,	
  
cost,	
  schedule,	
  and	
  progress	
  in	
  implemenLng	
  risk	
  handling.	
  
Performance	
  metrics	
  are	
  traceable	
  to	
  user–defined	
  
capabiliLes.	
  
―	
  Defense	
  Acquisi=on	
  Guide	
  (heps://dag.dau.mil/Pages/
Default.aspx)	
  
In The End ― It’s All About Systems Engineering
9.0	
  Framework	
  
More	
  Guidance	
  Can	
  Be	
  Found	
  in	
  …	
  
92	
  
9.0	
  Framework	
  
This	
  Has	
  All	
  Been	
  Said	
  Before.	
  	
  
We	
  Just	
  Weren’t	
  Listening…	
  
93	
  
… the basic tenets of the process are the need for
seamless management tools, that support an integrated
approach … and “proactive identification and
management of risk” for critical cost, schedule, and
technical performance parameters.
― Secretary of Defense, Perry memo, May 1995
Why Is This Hard To Understand?
! We seem to be focused on EV reporting, not the use of
EV to manage the program.
! Getting the CPR out the door is the end of Program
Planning and Control’s efforts, not the beginning.
TPM Handbook 1984
9.0	
  Framework	
  
A	
  Final	
  Reminder	
  …	
  
94	
  
TPMs are one source of Risk Management processes
Risk	
  Management	
  Guide	
  to	
  DOD	
  Acquisi=on,	
  Sixth	
  EdiLon	
  (Version	
  1,0),	
  Aug	
  2006	
  
9.0	
  Framework	
  
StarLng	
  out	
  on	
  the	
  Right	
  Foot	
  …	
  
!  Most	
  IMP/IMS	
  literature	
  states	
  how	
  to	
  build	
  an	
  IMP	
  from	
  the	
  RFP	
  and	
  
contractual	
  elements,	
  in	
  simple	
  and	
  maybe	
  simple	
  minded	
  terms	
  
–  Decompose	
  the	
  events	
  into	
  SAs,	
  ACs,	
  and	
  their	
  Tasks	
  –	
  sounds	
  easy	
  
!  This	
  approach	
  fails	
  to	
  provide	
  advice	
  for	
  several	
  things:	
  
–  How	
  to	
  minimize	
  the	
  topological	
  connecLons	
  between	
  Events	
  
–  How	
  to	
  increase	
  the	
  concurrency	
  between	
  IPTs	
  
–  How	
  to	
  increase	
  the	
  tolerance	
  of	
  the	
  IMS	
  to	
  disrupLve	
  events	
  
•  Known	
  and	
  knowable	
  risk	
  
•  Unknown	
  and	
  possibly	
  unknowable	
  risk	
  
!  The	
  construcLon	
  of	
  the	
  IMS	
  needs	
  to	
  take	
  place	
  in	
  what	
  seems	
  to	
  be	
  a	
  
reverse	
  order	
  
–  Build	
  the	
  IMP	
  as	
  a	
  Value	
  Stream	
  Map	
  describing	
  the	
  increasing	
  maturity	
  –	
  and	
  
therefore	
  the	
  increasing	
  VALUE	
  of	
  the	
  deliverables	
  to	
  the	
  customer.	
  
–  It’s	
  the	
  delivery	
  of	
  Customer	
  Value	
  that	
  inverts	
  the	
  management	
  process,	
  and	
  
focuses	
  on	
  Keeping	
  the	
  Program	
  GREEN	
  as	
  planned	
  that	
  maximizes	
  value	
  to	
  
the	
  customer	
  (the	
  Government)	
  	
   95	
  
9.0	
  Framework	
  
SETR	
  Program	
  Events	
  
96	
  heps://acc.dau.mil/docs/technicalreviews/dod_tech_reviews.htm	
  
9.0	
  Framework	
  
Build	
  PEs	
  Leo	
  to	
  Right	
  
Start	
  with	
  SRR	
  (or	
  something	
  on	
  the	
  leW)	
  and	
  completely	
  
define	
  its	
  comple=on,	
  before	
  moving	
  to	
  the	
  next	
  PE	
  
!  Define	
  the	
  SAs	
  for	
  an	
  Event	
  and	
  construct	
  a	
  work	
  flow	
  
of	
  the	
  acLviLes	
  needed	
  to	
  saLsfy	
  the	
  SA	
  
–  These	
  acLviLes	
  are	
  yet	
  tasks,	
  so	
  don’t	
  commit	
  too	
  soon	
  to	
  
defining	
  the	
  detailed	
  work	
  
–  Isolate	
  the	
  SAs	
  by	
  event	
  first	
  –	
  only	
  work	
  on	
  one	
  event	
  at	
  a	
  
Lme	
  
!  IdenLfy	
  the	
  parLcipants	
  in	
  the	
  work	
  
–  What	
  IPTs	
  parLcipate	
  in	
  this	
  work?	
  
–  What	
  swim	
  lanes	
  are	
  needed	
  to	
  isolate	
  the	
  IPTs?	
  
!  Define	
  the	
  elements	
  	
  
–  AcLviLes	
  performed	
  to	
  saLsfy	
  the	
  SA	
  
–  Deliverables	
  that	
  result	
  from	
  these	
  acLviLes	
  
!  There	
  are	
  sLll	
  not	
  Accomplishment	
  Criteria	
  (AC),	
  but	
  
that	
  comes	
  next	
   97	
  
9.0	
  Framework	
  
The	
  Accomplishment	
  Criteria	
  (AC)	
  
!  A	
  definiLve	
  measure	
  or	
  indicator	
  that	
  verifies	
  
compleLon	
  of	
  work	
  for	
  the	
  accomplishment	
  
– Completed	
  work	
  effort	
  	
  
•  Manufacturing	
  Plan	
  Completed	
  
– ConfirmaLon	
  of	
  performance	
  compliance	
  	
  
•  Flight	
  Test	
  Report	
  Approved	
  
– Incremental	
  verificaLon	
  	
  
•  Maintenance	
  DemonstraLon	
  Completed	
  
– Completed	
  criLcal	
  process	
  acLviLes	
  
•  Risk	
  Management	
  Plan	
  Approved	
  
98	
  
9.0	
  Framework	
  
The	
  Accomplishment	
  Criteria	
  (AC)	
  
!  Defines	
  the	
  measure	
  by	
  which	
  an	
  Accomplishment	
  (SA)	
  is	
  
considered	
  “done”	
  
!  Terms	
  like	
  complete,	
  delivered,	
  closed	
  have	
  no	
  “units	
  of	
  
measure”	
  in	
  the	
  context	
  of	
  a	
  Significant	
  Accomplishment	
  
(SA)	
  and	
  are	
  open	
  to	
  interpretaLon	
  
!  Terms	
  like	
  …	
  
–  Measures	
  of	
  compleLon	
  –	
  80%	
  of	
  drawings	
  approved	
  for	
  release	
  
–  Counts	
  of	
  available	
  items	
  –	
  75%	
  of	
  pin-­‐outs	
  assigned	
  voltage	
  
–  Fidelity	
  of	
  a	
  design	
  –	
  outer	
  mold	
  line	
  defined	
  within	
  90%	
  of	
  
target	
  
–  Error	
  bounds	
  –	
  spacecraW	
  mass	
  known	
  to	
  ±20%	
  
–  Performance	
  parameters	
  –	
  disconnect	
  force	
  within	
  allowed	
  
limits	
  
–  Maturity	
  parameters	
  –	
  flight	
  ar=cle	
  successful	
  in	
  last	
  3	
  tests	
  
…	
  are	
  used	
  to	
  define	
  the	
  “exit	
  criteria”	
  
99	
  
9.0	
  Framework	
  
2	
  Types	
  of	
  Accomplishment	
  	
  
Criteria:	
  Entry	
  and	
  Exit	
  
!  Entry	
  Criteria	
  –	
  SubstanLates	
  readiness	
  for	
  the	
  
review	
  
!  Exit	
  Criteria	
  –	
  SubstanLates	
  successful	
  
compleLon	
  of	
  the	
  review	
  
!  CriLcal	
  Design	
  Review	
  (CDR)	
  example	
  
– Are	
  we	
  ready	
  for	
  the	
  Flight	
  Test	
  Readiness	
  
Review?	
  
– How	
  do	
  we	
  know	
  the	
  FTRR	
  a	
  success?	
  
– What	
  did	
  we	
  learn	
  from	
  the	
  FTRR	
  that	
  increases	
  
the	
  maturity	
  of	
  the	
  program’s	
  deliverables.	
  
100	
  
9.0	
  Framework	
  
The	
  IMP	
  Focuses	
  us	
  on	
  Measures	
  
of	
  EffecLveness	
  and	
  Performance	
  
101	
  
MoE	
  
KPP	
  
MoP	
   TPM	
  
Mission	
  
Need	
  
Acquirer	
  Defines	
  the	
  Needs	
  and	
  CapabiliLes	
  
in	
  terms	
  of	
  OperaLonal	
  Scenarios	
  
Supplier	
  Defines	
  Physical	
  SoluLons	
  that	
  
meet	
  the	
  needs	
  of	
  the	
  Stakeholders	
  
Opera%onal	
  
measures	
  of	
  success	
  
related	
  to	
  the	
  
achievement	
  of	
  the	
  
mission	
  or	
  
opera%onal	
  
objec%ve	
  being	
  
evaluated.	
  
Measures	
  that	
  
characterize	
  
physical	
  or	
  
func%onal	
  aKributes	
  
rela%ng	
  to	
  the	
  
system	
  opera%on.	
  
Measures	
  used	
  to	
  
assess	
  design	
  
progress,	
  
compliance	
  to	
  
performance	
  
requirements,	
  and	
  
technical	
  risks.	
  
9.0	
  Framework	
  
Measure	
  of	
  EffecLveness	
  (MoE)	
  
!  Measures	
  of	
  EffecLveness	
  …	
  
!  Are	
  stated	
  in	
  units	
  meaningful	
  to	
  the	
  buyer,	
  
!  Focus	
  on	
  capabiliLes	
  independent	
  of	
  any	
  
technical	
  implementaLon,	
  
!  Are	
  connected	
  to	
  the	
  mission	
  success.	
  
The	
  operaLonal	
  measures	
  of	
  success	
  that	
  are	
  closely	
  related	
  to	
  the	
  
achievements	
  of	
  the	
  mission	
  or	
  operaLonal	
  objecLves	
  evaluated	
  in	
  
the	
  operaLonal	
  environment,	
  under	
  a	
  specific	
  set	
  of	
  condiLons.	
  
“Technical	
  Measurement,”	
  INCOSE–TP–2003–020–01	
  
MoE’s	
  Belong	
  to	
  the	
  End	
  User	
  
102	
  
9.0	
  Framework	
  
Measure	
  of	
  Performance	
  (MoP)	
  
!  Measures	
  of	
  Performance	
  are	
  …	
  
!  Aeributes	
  that	
  assure	
  the	
  system	
  has	
  the	
  
capability	
  to	
  perform,	
  
!  Assessment	
  of	
  the	
  system	
  to	
  assure	
  it	
  meets	
  
design	
  requirements	
  to	
  saLsfy	
  the	
  MoE.	
  
Measures	
  that	
  characterize	
  physical	
  or	
  funcLonal	
  aeributes	
  
relaLng	
  to	
  the	
  system	
  operaLon,	
  measured	
  or	
  esLmated	
  
under	
  specific	
  condiLons.	
  
“Technical	
  Measurement,”	
  INCOSE–TP–2003–020–01	
  
MoP’s	
  belong	
  to	
  the	
  Program	
  –	
  Developed	
  by	
  the	
  Systems	
  
Engineer,	
  Measured	
  By	
  CAMs,	
  and	
  Analyzed	
  by	
  PP&C	
  	
  
103	
  
9.0	
  Framework	
  
Key	
  Performance	
  Parameters	
  (KPP)	
  
Both	
  JROC	
  and	
  Program	
  Specific	
  
!  Key	
  Performance	
  Parameters	
  …	
  
!  Have	
  a	
  threshold	
  or	
  objecLve	
  value,	
  
!  Characterize	
  the	
  major	
  drivers	
  of	
  
performance,	
  
!  Are	
  considered	
  CriLcal	
  to	
  Customer	
  (CTC).	
  
Represent	
  the	
  capabiliLes	
  and	
  characterisLcs	
  so	
  
significant	
  that	
  failure	
  to	
  meet	
  them	
  can	
  be	
  cause	
  for	
  
reevaluaLon,	
  reassessing,	
  or	
  terminaLon	
  of	
  the	
  program	
  
“Technical	
  Measurement,”	
  INCOSE–TP–2003–020–01	
  
The	
  acquirer	
  defines	
  the	
  KPPs	
  during	
  the	
  operaLonal	
  
concept	
  development	
  –	
  KPPs	
  say	
  what	
  DONE	
  looks	
  like	
  
104	
  
9.0	
  Framework	
  
 
Technical	
  Performance	
  Measures	
  
(TPM)	
  for	
  key	
  deliverables	
  	
  
!  Technical	
  Performance	
  Measures	
  …	
  
!  Assess	
  design	
  progress,	
  
!  Define	
  compliance	
  to	
  performance	
  
requirements,	
  
!  IdenLfy	
  technical	
  risk,	
  
!  Are	
  limited	
  to	
  criLcal	
  thresholds,	
  
!  Include	
  projected	
  performance.	
  “Technical	
  Measurement,”	
  INCOSE–TP–2003–020–01	
  
Aeributes	
  that	
  determine	
  how	
  well	
  a	
  system	
  or	
  system	
  
element	
  is	
  saLsfying	
  or	
  expected	
  to	
  saLsfy	
  a	
  technical	
  
requirement	
  or	
  goal	
  
105	
  
9.0	
  Framework	
  
What	
  are	
  Technical	
  Performance	
  
Measures	
  Really?	
  
!  TPMs	
  are	
  measures	
  of	
  the	
  system	
  
technical	
  performance	
  that	
  have	
  
been	
  chosen	
  because	
  they	
  are	
  
indicators	
  of	
  system	
  success.	
  They	
  
are	
  based	
  on	
  the	
  driving	
  
requirements	
  or	
  technical	
  
parameters	
  of	
  high	
  risk	
  or	
  
significance	
  -­‐	
  e.g.,	
  mass,	
  power	
  or	
  
data	
  rate.	
  
!  TPMs	
  are	
  analogous	
  to	
  the	
  
programmaLc	
  measures	
  of	
  
expected	
  total	
  cost	
  or	
  esLmated	
  
Lme-­‐to-­‐compleLon.	
  There	
  is	
  a	
  
required	
  performance,	
  a	
  current	
  
best	
  esLmate,	
  and	
  a	
  trend	
  line.	
  
!  Actual	
  versus	
  planned	
  progress	
  of	
  
TPMs	
  are	
  tracked	
  so	
  the	
  systems	
  
engineer	
  or	
  project	
  manager	
  can	
  
assess	
  progress	
  and	
  the	
  risk	
  
associated	
  with	
  each	
  TPM.	
  	
  
!  The	
  final,	
  delivered	
  system	
  value	
  
can	
  be	
  esLmated	
  by	
  extending	
  the	
  
TPM	
  trend	
  line	
  and	
  using	
  the	
  
recommended	
  conLngency	
  values	
  
for	
  each	
  project	
  phase.	
  
!  The	
  project	
  life	
  trend-­‐to-­‐date,	
  
current	
  value,	
  and	
  forecast	
  of	
  all	
  
TPMs	
  are	
  reviewed	
  periodically	
  
(typically	
  monthly)	
  and	
  at	
  all	
  major	
  
milestone	
  reviews.	
  
106	
  
9.0	
  Framework	
  
!  Tracking	
  TPMs	
  and	
  comparing	
  them	
  to	
  the	
  resource	
  growth	
  
provides	
  an	
  early	
  warning	
  system	
  to	
  detect	
  deficiencies	
  or	
  
excesses	
  
!  Reserve	
  allocaLons	
  narrow	
  as	
  design	
  proceeds	
  
!  TPMs	
  that	
  violate	
  reserve	
  allocaLons	
  or	
  have	
  trends	
  that	
  
do	
  not	
  meet	
  the	
  final	
  performance	
  trigger	
  correcLve	
  
acLons	
  
107	
  
Tracking	
  the	
  Technical	
  	
  
Performance	
  Measures	
  
9.0	
  Framework	
  
NoLonal	
  TPM	
  Design	
  Margin	
  
Guidelines	
  
108	
  
9.0	
  Framework	
  
Sample	
  IMP:	
  
A	
  Flight	
  Avionics	
  System	
  (ConLnued)	
  
Hardware	
  PDR	
  –	
  Purpose	
  
	
  
!  Ensure	
  system	
  hardware	
  iniLal	
  design	
  has	
  been	
  updated,	
  and	
  meets	
  
funcLonal	
  and	
  allocated	
  performance	
  requirements	
  within	
  program	
  
constraints.	
  	
  
!  OperaLonal	
  security	
  concept	
  assessed.	
  	
  
!  Ensure	
  training	
  requirements	
  have	
  been	
  analyzed	
  and	
  their	
  objecLves	
  
have	
  been	
  defined	
  for	
  training	
  missions.	
  	
  
!  ConfirmaLon	
  training	
  objecLves	
  and	
  MTC	
  design	
  and	
  integraLon	
  conform	
  
to	
  the	
  Air	
  Force	
  syllabus	
  and	
  Ready	
  Aircrew	
  Program	
  (RAP).	
  	
  
!  Training	
  plan	
  will	
  be	
  updated.	
  
!  Hardware	
  PDR	
  –	
  ExpectaLons	
  
!  Team	
  agrees	
  system	
  hardware	
  iniLal	
  design	
  has	
  been	
  updated	
  and	
  can	
  
proceed	
  to	
  the	
  detailed	
  design	
  phase.	
  	
  
!  Team	
  agrees	
  training	
  plans	
  and	
  objecLves	
  correlate	
  with	
  the	
  Air	
  Force	
  
syllabus,	
  RAP	
  and	
  training	
  planning,	
  development	
  can	
  conLnue.	
  	
  
!  System	
  SpecificaLon	
  and	
  TTL	
  requirements	
  are	
  traceable	
  to	
  the	
  allocated	
  
hardware	
  design.	
  	
  
109	
  
9.0	
  Framework	
  
Sample	
  IMP:	
  
A	
  Flight	
  Avionics	
  System	
  (ConLnued)	
  
!  Hardware	
  PDR	
  –	
  Entry	
  Criteria	
  
!  FuncLonal	
  Baseline	
  AuthenLcated	
  (FBA)	
  
!  IniLate	
  system	
  hardware	
  iniLal	
  design	
  and	
  
allocate	
  funcLons	
  to	
  the	
  appropriate	
  
ConfiguraLon	
  Items	
  
!  All	
  specificaLons	
  updated	
  and	
  required	
  
documentaLon	
  is	
  made	
  available	
  including	
  
anLcipated	
  lower	
  level	
  design	
  documentaLon	
  
!  All	
  SRR/SFR	
  acLon	
  items	
  closed	
  or	
  
disposiLoned	
  	
  
110	
  
9.0	
  Framework	
  
Sample	
  IMP:	
  
A	
  Flight	
  Avionics	
  System	
  (ConLnued)	
  
Hardware	
  PDR	
  –	
  Accomplishments	
  
!  System	
  hardware	
  iniLal	
  design	
  complete.	
  	
  
–  FuncLons	
  allocated	
  to	
  one	
  or	
  more	
  hardware	
  configuraLon	
  items	
  and	
  
are	
  traceable	
  to	
  the	
  MTC	
  SSS	
  and	
  TSSC	
  SSS.	
  	
  
–  Human,	
  safety,	
  R&M,	
  EMI,	
  operaLonal	
  security,	
  instructor	
  and	
  
operator	
  interfaces,	
  etc,	
  design	
  factors	
  have	
  been	
  reviewed.	
  	
  
!  Drao	
  instructor	
  and	
  operator	
  manuals	
  reviewed	
  	
  
!  Program	
  risks	
  updated,	
  assessed,	
  and	
  reviewed.	
  	
  
–  MiLgaLon	
  plans	
  in	
  place.	
  
!  Program	
  schedule	
  and	
  constraints	
  updated	
  and	
  reviewed.	
  	
  
–  CriLcal	
  schedule	
  path	
  drivers	
  reviewed.	
  	
  
!  Design	
  criteria	
  for	
  the	
  simulaLon	
  and	
  database	
  development	
  
reviewed	
  and	
  updated.	
  
!  Program	
  processes	
  and	
  metrics	
  reviewed.	
  
!  Test	
  Planning	
  acLviLes	
  and	
  relevant	
  documentaLon	
  reviewed	
  by	
  
test	
  team.	
  
111	
  
9.0	
  Framework	
  
Sample	
  IMP:	
  
A	
  Flight	
  Avionics	
  System	
  (Concluded)	
  
Hardware	
  PDR	
  –	
  Exit	
  Criteria	
  
	
  
!  Hardware	
  (ownership,	
  visual,	
  IOS,	
  brief/debrief)	
  design	
  reviewed,	
  allocated	
  to	
  a	
  
hardware	
  configuraLon	
  item	
  and	
  updated	
  to	
  include	
  instructor	
  and	
  operators	
  
interfaces,	
  malfuncLon	
  and	
  control	
  requirements,	
  etc.	
  	
  
!  RTM	
  updated,	
  MTC	
  SSS,	
  TSSC	
  SSS	
  and	
  TTL	
  traceable	
  to	
  allocated	
  hardware	
  design	
  
to	
  include	
  ESOH	
  requirements.	
  	
  
!  Human,	
  safety,	
  R&M,	
  EMI,	
  operaLonal	
  security,	
  instructor	
  and	
  operator	
  interfaces,	
  
etc,	
  design	
  factors	
  reviewed.	
  	
  
!  MTC	
  and	
  TSSC	
  allocated	
  baselines	
  established	
  and	
  controlled	
  by	
  appropriate	
  level	
  
documentaLon	
  for	
  PDR.	
  
!  Drao	
  instructor	
  and	
  operator	
  manuals	
  reviewed	
  with	
  user	
  concurrence	
  and	
  
incorporate	
  saLsfactory	
  human	
  factor	
  design	
  factors	
  into	
  the	
  operator	
  interfaces.	
  	
  
!  Risk	
  management	
  and	
  miLgaLon	
  plans	
  updated,	
  in	
  place,	
  addresses	
  ESOH	
  plans	
  
and	
  risks,	
  and	
  within	
  program	
  constraints.	
  	
  
!  Risks	
  assesses,	
  understood,	
  documented,	
  accepted	
  and	
  understood	
  by	
  team.	
  
!  Program	
  schedule	
  reviewed	
  	
  
–  CriLcal	
  path	
  drivers	
  idenLfied	
  	
  
–  IMS	
  Updated	
  and	
  reflects	
  criLcal	
  paths	
  
112	
  
9.0	
  Framework	
  
One	
  More	
  IMP	
  Sample	
  
!  (SA)	
  System	
  &	
  Segment	
  
Requirements	
  Updated	
  &	
  Allocated	
  
–  (AC)	
  SRR	
  /	
  SDR	
  Update	
  Review	
  
Conducted	
  
–  (AC)	
  Preliminary	
  System	
  
SpecificaLon	
  Documents	
  (A011)	
  
Baselined	
  
–  (AC)	
  Preliminary	
  Spacecrao	
  
Segment	
  SpecificaLon	
  Baselined	
  
–  (AC)	
  Preliminary	
  Ground	
  Segment	
  
SpecificaLon	
  Baselined	
  
–  (AC)	
  Preliminary	
  SpecificaLon	
  Tree	
  
Baselined	
  
!  (SA)	
  Preliminary	
  ICDs	
  Baselined	
  For	
  
Customer	
  Review	
  
–  (AC)	
  Preliminary	
  Space-­‐Ground	
  
ICD	
  Baselined	
  	
  
!  (SA)	
  PDR	
  System	
  Design	
  Completed	
  
–  (AC)	
  Top	
  Level	
  System	
  
Architecture	
  Updated	
  
–  (AC)	
  PDR	
  Level	
  System	
  Analyses	
  
Completed	
  
–  (AC)	
  PDR	
  Level	
  Reliability	
  /	
  
Availability	
  Analysis	
  Completed	
  
–  (AC)	
  Preliminary	
  System	
  Level	
  Risk	
  
Assessment	
  Completed	
  
–  (AC)	
  System	
  Level	
  Plans	
  Updated	
  
For	
  PDR	
  
–  (AC)	
  Flight	
  Long	
  Lead	
  Review	
  
Conducted	
  
113	
  
Preliminary	
  Design	
  Review	
  
9.0	
  Framework	
  
The	
  “But”	
  for	
  this	
  Guidance	
  
!  With	
  these	
  samples	
  and	
  the	
  SETR	
  guidance	
  
we’ve	
  just	
  started	
  
!  The	
  program	
  needs	
  to	
  define	
  program	
  specific	
  
events	
  to	
  assure	
  the	
  actual	
  maturity	
  measures	
  
are	
  captured	
  
– The	
  IMP	
  provides	
  sufficient	
  defini=on	
  to	
  track	
  the	
  
step-­‐by-­‐step	
  comple=on	
  of	
  the	
  required	
  
accomplishments	
  for	
  each	
  event	
  and	
  to	
  
demonstrate	
  sa=sfac=on	
  of	
  the	
  comple=on	
  
criteria	
  for	
  each	
  accomplishment.	
  [AFMC	
  
PAMPHLET	
  63-­‐5]	
  
114	
  
9.0	
  Framework	
  
IMP	
  Verbs	
  for	
  Significant	
  
Accomplishments	
  
115	
  
Integrated	
  Master	
  Plan	
  Allowable	
  Verbs	
  
Allocated:	
  Segment	
  requirement	
  is	
  flowed	
  down	
  
from	
  the	
  System	
  SpecificaLon	
  
Released:	
  Approved	
  item	
  for	
  delivery	
  for	
  
intended	
  customer	
  or	
  supplier;	
  all	
  internal	
  
distribuLon	
  and	
  sign	
  offs	
  complete.	
  An	
  
electronic	
  version	
  is	
  made	
  accessible	
  on	
  the	
  IDE	
  
Completed:	
  The	
  subject	
  item,	
  data,	
  document,	
  
or	
  process	
  is	
  prepared	
  or	
  concluded,	
  and	
  
reviewed	
  and	
  accepted	
  by	
  the	
  responsible	
  IPT.	
  
SupporLng	
  documentaLon	
  is	
  available	
  through	
  
IDE	
  
Reviewed:	
  The	
  subject	
  item,	
  data,	
  document,	
  or	
  
process	
  is	
  prepared	
  or	
  concluded,	
  and	
  
documented	
  for	
  compleLon.	
  SupporLng	
  
documentaLon	
  is	
  available	
  through	
  IDE	
  
Conducted:	
  The	
  subject	
  meeLng	
  or	
  review	
  has	
  
been	
  held	
  with	
  all	
  required	
  parLcipants.	
  The	
  
charts	
  or	
  minutes	
  are	
  available	
  through	
  the	
  IDE	
  
Updated:	
  The	
  subject	
  process,	
  data,	
  or	
  
document	
  has	
  been	
  reevaluated	
  using	
  later	
  
informaLon,	
  and	
  adjustments	
  incorporated.	
  
Defined:	
  The	
  subject	
  configuraLon	
  items,	
  data,	
  
or	
  document	
  was	
  submieed	
  to	
  the	
  customer	
  
Validated:	
  Requirements	
  are	
  validated,	
  received	
  
contractor	
  approvals,	
  were	
  distributed,	
  and	
  are	
  
available	
  through	
  the	
  IDE	
  
Established:	
  The	
  subject	
  items	
  is	
  created	
  and	
  set	
  
in	
  place	
  in	
  a	
  manner	
  consistent	
  with	
  its	
  intended	
  
use	
  aoer	
  review	
  and	
  accepted	
  by	
  the	
  IPT	
  
Verified:	
  Requirements	
  are	
  verified	
  or	
  processed	
  
in	
  accordance	
  with	
  established	
  pracLce.	
  
9.0	
  Framework	
  
The	
  IMP	
  Process	
  NarraLve	
  
!  ObjecMve:	
  a	
  brief	
  statement	
  explaining	
  why	
  this	
  
process	
  set	
  is	
  applied	
  for	
  this	
  program	
  
!  Governing	
  DocumentaMon:	
  lists	
  of	
  the	
  guidance	
  
or	
  compliance	
  documents;	
  e.g.,	
  specificaLons,	
  
manuals,	
  and	
  procedures	
  including	
  company,	
  
government,	
  and	
  industry	
  references	
  
!  Approach:	
  concise	
  descripLon	
  as	
  to	
  who	
  owns	
  
each	
  process;	
  what	
  are	
  the	
  roles	
  and	
  
responsibiliLes;	
  and	
  the	
  overall	
  process	
  including	
  
a	
  process	
  flow	
  diagram.	
  
116	
  
9.0	
  Framework	
  
Generic	
  IMP	
  EvaluaLon	
  Criteria	
  
!  Do	
  the	
  Program	
  Events	
  and	
  Accomplishments	
  
reflect	
  the	
  logical	
  evoluLon	
  and	
  progress	
  of	
  the	
  
overall	
  Program?	
  
–  Do	
  program	
  events	
  and	
  their	
  definiLons	
  clearly	
  
demonstrate	
  the	
  maturity	
  of	
  the	
  program	
  over	
  
its	
  life?	
  
–  Do	
  the	
  selected	
  Accomplishments	
  and	
  
associated	
  Criteria	
  idenLfy	
  meaningful	
  and	
  
measurable	
  progress	
  toward	
  the	
  key	
  goals	
  of	
  
the	
  Program?	
  
!  Do	
  the	
  Accomplishments	
  for	
  each	
  event	
  
demonstrate	
  a	
  meaningful	
  understanding	
  of	
  the	
  
program	
  requirements	
  or	
  are	
  they	
  tasks	
  that	
  
anyone	
  could	
  do	
  for	
  any	
  contract?	
  
–  Do	
  they	
  reflect	
  your	
  SOW	
  requirements?	
  	
  
!  Does	
  the	
  IMP	
  structure	
  readily	
  map	
  to	
  the	
  IPT	
  
structure	
  such	
  that	
  each	
  IPT	
  can	
  easily	
  visualize	
  
the	
  scope	
  of	
  their	
  responsibility?	
  	
  
!  When	
  awarded,	
  could	
  the	
  contractor	
  use	
  the	
  
Accomplishments	
  as	
  discrete	
  acLvity	
  cost	
  accounts	
  
in	
  their	
  earned	
  value	
  system?	
  Or	
  are	
  they	
  level	
  of	
  
effort	
  in	
  nature?	
  	
  
!  Is	
  sufficient	
  visibility	
  provided	
  to	
  idenLfy	
  and	
  track	
  
the	
  Program	
  Risk	
  Plan	
  and	
  associated	
  risk	
  
miLgaLon	
  accomplishments	
  and/or	
  
conLngencies?	
  
–  Does	
  criteria	
  supporLng	
  the	
  accomplishments	
  
include	
  key	
  performance	
  requirements?	
  
!  Are	
  IPT	
  cross-­‐dependencies	
  and	
  dependencies	
  
external	
  to	
  the	
  Program	
  appropriately	
  reflected	
  if	
  
they	
  reflect	
  potenLal	
  schedule	
  or	
  performance	
  
risks	
  to	
  the	
  success	
  of	
  the	
  Program?	
  
!  Is	
  the	
  submieed	
  "Contract	
  IMP"	
  (the	
  Product	
  IMP	
  
that	
  is	
  to	
  be	
  included	
  as	
  part	
  of	
  the	
  Program	
  
Contract)	
  defined	
  to	
  the	
  appropriate	
  level:	
  
–  Do	
  the	
  Accomplishments	
  and	
  associated	
  
Criteria	
  go	
  down	
  to	
  a	
  level	
  sufficient	
  to	
  provide	
  
visibility	
  into	
  key	
  subcontractor	
  acLviLes	
  upon	
  
which	
  the	
  success	
  of	
  the	
  Program	
  may	
  be	
  
dependent?	
  
–  Are	
  the	
  Events	
  and	
  Accomplishments	
  included	
  
in	
  the	
  IMP	
  at	
  such	
  a	
  level	
  as	
  to	
  make	
  the	
  
maintenance	
  of	
  the	
  'Contractual	
  IMP'	
  pracLcal	
  
or	
  does	
  it	
  include	
  an	
  unnecessary	
  level	
  of	
  
detail?	
  
117	
  
9.0	
  Framework	
  
Program	
  Management	
  Levels	
  
Program Levels" IMP/IMS Elements" CWBS"
Tier 1!
Program Manager!
Technical Leads!
IPT Manager!
Technical performance goals!
Major Program Events
(PE)!
!
!
!
Significant
Accomplishments (SA)!
Level 1 & 2!
Links to CLINs!
Level 3 & 4!
Control Packages!
Link to PBS!
Integrated EVMS!
Tier 2!
Control Account Managers !
Product Work Plan!
Responsible organization
elements!
!
Accomplishment
Criteria (AC)!
!
!
!
!
Tasks (NA)!
Level 5!
Cost Account
Package!
Cost Collection Level!
Links to WBS by OBS!
Resource summaries!
Early warning EVMS
analysis!
Tier 3!
Work Package Manager!
Detailed plans! Work package!
Earned value
calculations!
118	
  
9.0	
  Framework	
  
ConnecLng	
  the	
  Components	
  	
  
of	
  the	
  IMP/IMS	
  
!  The	
  assembled	
  IMP/IMS	
  links	
  all	
  work	
  
acLviLes	
  verLcally	
  to	
  the	
  ACs,	
  SAs,	
  and	
  PEs	
  
119	
  
IMS	
  
Customer	
  
Requirements	
   IMP	
  
ORG	
  
IPTs	
  
ORG	
  
IPTs	
  
Performance	
  
Analysis/	
  
Management 	
  
Review	
  
Events (E)	
  Events (E)	
  
Accomplishments	
  
Process	
  
Narratives	
  
Criteria	
  
Integrated Master	
  
Schedule (IMS)	
  
Integrated Master	
  
Schedule (IMS)	
  
Control Account	
  Control Account	
  
Work Package	
  Work Package	
  
Work Package Tasks	
  Work Package Tasks	
  
WBS	
  
Program 	
  
Performance	
  
Management 	
  
System	
  
Supplemental Schedules	
  
Risk and 	
  
opportunity	
  
Risk and 	
  
opportunity	
  
9.0	
  Framework	
  
120	
  
9.0	
  Framework	
  
First	
  Pass	
  At	
  Building	
  The	
  
Integrated	
  Master	
  Plan	
  	
  
Many	
  contractors	
  all	
  ready	
  have	
  work	
  processes	
  to	
  do	
  this.	
  These	
  steps	
  are	
  
guidance	
  for	
  contractors	
  new	
  to	
  this	
  process.	
  	
  
With	
  the	
  RFP,	
  the	
  contract	
  should	
  be	
  capable	
  of	
  the	
  following	
  steps	
  to	
  create	
  the	
  
Integrated	
  Master	
  Plan	
  and	
  Integrated	
  Master	
  Schedule.	
  	
  
We’ll	
  build	
  the	
  IMP/IMS	
  from	
  the	
  point	
  of	
  view	
  of	
  the	
  Government	
  to	
  compare	
  
the	
  contractors	
  IMP	
  in	
  the	
  proposal	
  
10	
  
V8.7	
  
Focused	
  with	
  the	
  Air	
  Vehicle	
  
122	
  
10.	
  1st	
  Pass	
  
Quick	
  View	
  of	
  1st	
  Pass	
  for	
  IMP	
  
!  Start	
  with	
  WBS	
  
!  Use	
  Preliminary	
  Design	
  Review	
  Program	
  Event	
  
!  IdenLfy	
  subsystems	
  for	
  flight	
  vehicle	
  
!  IdenLfy	
  Significant	
  Accomplishments	
  for	
  PDR	
  
compleLon	
  
!  IdenLfy	
  Accomplishment	
  Criteria	
  for	
  each	
  
sequence	
  of	
  Work	
  Packages	
  to	
  produce	
  the	
  
deliverables	
  for	
  PDR	
  
123	
  
10.	
  1st	
  Pass	
  
Integrated Master Plan Development
Integrated Master Plan Development
Integrated Master Plan Development
Integrated Master Plan Development
Integrated Master Plan Development
Integrated Master Plan Development
Integrated Master Plan Development
Integrated Master Plan Development
Integrated Master Plan Development
Integrated Master Plan Development
Integrated Master Plan Development
Integrated Master Plan Development
Integrated Master Plan Development
Integrated Master Plan Development
Integrated Master Plan Development
Integrated Master Plan Development
Integrated Master Plan Development

Weitere ähnliche Inhalte

Was ist angesagt?

Project Management Framework
Project Management FrameworkProject Management Framework
Project Management FrameworkRahul Sudame
 
ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...
ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...
ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...Project Controls Expo
 
Project Closure Activities In Project Management Powerpoint Presentation Slides
Project Closure Activities In Project Management Powerpoint Presentation SlidesProject Closure Activities In Project Management Powerpoint Presentation Slides
Project Closure Activities In Project Management Powerpoint Presentation SlidesSlideTeam
 
La strutturazione di un progetto in pacchetti di lavoro, output, outcome e de...
La strutturazione di un progetto in pacchetti di lavoro, output, outcome e de...La strutturazione di un progetto in pacchetti di lavoro, output, outcome e de...
La strutturazione di un progetto in pacchetti di lavoro, output, outcome e de...Sardegna Ricerche
 
Journey to Maturity Building a PMO
Journey to Maturity Building a PMOJourney to Maturity Building a PMO
Journey to Maturity Building a PMOJames Brown
 
Project risk management
Project risk managementProject risk management
Project risk managementDewang Agrawal
 
My BIM Profesional Portafolio English version
My BIM Profesional Portafolio English versionMy BIM Profesional Portafolio English version
My BIM Profesional Portafolio English versionDaniel Almenares
 
Project execution and implementation
Project execution and implementationProject execution and implementation
Project execution and implementationDr. Saima Baig
 
PMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkPMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkejlp12
 
10 Project Management Knowledge Areas
10 Project Management Knowledge Areas10 Project Management Knowledge Areas
10 Project Management Knowledge AreasElizabeth Harrin FAPM
 
Recovery Scheduling
Recovery SchedulingRecovery Scheduling
Recovery SchedulingChris Carson
 
How to perform time impact analysis (TIA)
How to perform time impact analysis (TIA)How to perform time impact analysis (TIA)
How to perform time impact analysis (TIA)Amr Morsy
 
How to set up a project management office (PMO)
How to set up a project management office (PMO)How to set up a project management office (PMO)
How to set up a project management office (PMO)PM Majik
 
Project Status Report Presentation Visuals
Project Status Report Presentation VisualsProject Status Report Presentation Visuals
Project Status Report Presentation VisualsSlideTeam
 
Project management assignment 1
Project management assignment 1 Project management assignment 1
Project management assignment 1 Weng Chuan
 

Was ist angesagt? (20)

Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
Advanced Work Packaging: Applying Project Controls
Advanced Work Packaging: Applying Project ControlsAdvanced Work Packaging: Applying Project Controls
Advanced Work Packaging: Applying Project Controls
 
PMO Challenges and Opportunities; DIPMF Presentation
PMO Challenges and Opportunities; DIPMF PresentationPMO Challenges and Opportunities; DIPMF Presentation
PMO Challenges and Opportunities; DIPMF Presentation
 
ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...
ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...
ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...
 
Project Closure Activities In Project Management Powerpoint Presentation Slides
Project Closure Activities In Project Management Powerpoint Presentation SlidesProject Closure Activities In Project Management Powerpoint Presentation Slides
Project Closure Activities In Project Management Powerpoint Presentation Slides
 
La strutturazione di un progetto in pacchetti di lavoro, output, outcome e de...
La strutturazione di un progetto in pacchetti di lavoro, output, outcome e de...La strutturazione di un progetto in pacchetti di lavoro, output, outcome e de...
La strutturazione di un progetto in pacchetti di lavoro, output, outcome e de...
 
Journey to Maturity Building a PMO
Journey to Maturity Building a PMOJourney to Maturity Building a PMO
Journey to Maturity Building a PMO
 
Project risk management
Project risk managementProject risk management
Project risk management
 
My BIM Profesional Portafolio English version
My BIM Profesional Portafolio English versionMy BIM Profesional Portafolio English version
My BIM Profesional Portafolio English version
 
080613 Mega-Project Schedule Integration & Management RCF Method-1
080613 Mega-Project Schedule Integration & Management RCF Method-1 080613 Mega-Project Schedule Integration & Management RCF Method-1
080613 Mega-Project Schedule Integration & Management RCF Method-1
 
Project execution and implementation
Project execution and implementationProject execution and implementation
Project execution and implementation
 
PMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkPMP Training - 01 introduction to framework
PMP Training - 01 introduction to framework
 
10 Project Management Knowledge Areas
10 Project Management Knowledge Areas10 Project Management Knowledge Areas
10 Project Management Knowledge Areas
 
Recovery Scheduling
Recovery SchedulingRecovery Scheduling
Recovery Scheduling
 
How to perform time impact analysis (TIA)
How to perform time impact analysis (TIA)How to perform time impact analysis (TIA)
How to perform time impact analysis (TIA)
 
How to set up a project management office (PMO)
How to set up a project management office (PMO)How to set up a project management office (PMO)
How to set up a project management office (PMO)
 
Project Status Report Presentation Visuals
Project Status Report Presentation VisualsProject Status Report Presentation Visuals
Project Status Report Presentation Visuals
 
041006-Program Management PMI NB - PMI Logo
041006-Program Management PMI NB - PMI Logo041006-Program Management PMI NB - PMI Logo
041006-Program Management PMI NB - PMI Logo
 
Project management assignment 1
Project management assignment 1 Project management assignment 1
Project management assignment 1
 
PMP PMBOK 6th
PMP PMBOK 6thPMP PMBOK 6th
PMP PMBOK 6th
 

Andere mochten auch

Build an integrated master plan and integrated master
Build an integrated master plan and integrated masterBuild an integrated master plan and integrated master
Build an integrated master plan and integrated masterGlen Alleman
 
Sibale, Romblon Master Development Plan
Sibale, Romblon Master Development PlanSibale, Romblon Master Development Plan
Sibale, Romblon Master Development Planjoecely
 
Economic Development Master Plan Phase I
Economic Development Master Plan Phase IEconomic Development Master Plan Phase I
Economic Development Master Plan Phase ICity of College Station
 
1 c. functions, roles and skills of a manager2
1 c. functions, roles and skills of a manager21 c. functions, roles and skills of a manager2
1 c. functions, roles and skills of a manager2Perla Pelicano Corpez
 
Big data meets evm (submitted).pptx
Big data meets evm (submitted).pptxBig data meets evm (submitted).pptx
Big data meets evm (submitted).pptxGlen Alleman
 
Customer Intelligence & Social Media
Customer Intelligence & Social MediaCustomer Intelligence & Social Media
Customer Intelligence & Social MediaAmplified Analytics
 
PMI chapter meeting (v4)
PMI chapter meeting (v4)PMI chapter meeting (v4)
PMI chapter meeting (v4)Glen Alleman
 
Inversion of Control
Inversion of ControlInversion of Control
Inversion of ControlGlen Alleman
 
Systems Engineering in One Picture
Systems Engineering in One PictureSystems Engineering in One Picture
Systems Engineering in One PictureGlen Alleman
 
Fix you some bad estimation habits
Fix you some bad estimation habitsFix you some bad estimation habits
Fix you some bad estimation habitsTed M. Young
 
Cure for cost and schedule growth
Cure for cost and schedule growthCure for cost and schedule growth
Cure for cost and schedule growthGlen Alleman
 
The Social Shift Fund - Presentation
The Social Shift Fund - Presentation The Social Shift Fund - Presentation
The Social Shift Fund - Presentation Marine Aubin
 
Pedir lo mismo de diferentes maneras
Pedir lo mismo de diferentes manerasPedir lo mismo de diferentes maneras
Pedir lo mismo de diferentes manerasAntonio Salvadores
 
Risk management processes
Risk management processesRisk management processes
Risk management processesGlen Alleman
 

Andere mochten auch (20)

Build an integrated master plan and integrated master
Build an integrated master plan and integrated masterBuild an integrated master plan and integrated master
Build an integrated master plan and integrated master
 
Sibale, Romblon Master Development Plan
Sibale, Romblon Master Development PlanSibale, Romblon Master Development Plan
Sibale, Romblon Master Development Plan
 
Manifesto 2010
Manifesto 2010Manifesto 2010
Manifesto 2010
 
Economic Development Master Plan Update
Economic Development Master Plan UpdateEconomic Development Master Plan Update
Economic Development Master Plan Update
 
Economic Development Master Plan Phase I
Economic Development Master Plan Phase IEconomic Development Master Plan Phase I
Economic Development Master Plan Phase I
 
1 c. functions, roles and skills of a manager2
1 c. functions, roles and skills of a manager21 c. functions, roles and skills of a manager2
1 c. functions, roles and skills of a manager2
 
PUSD Facilities Master Plan Development
PUSD Facilities Master Plan DevelopmentPUSD Facilities Master Plan Development
PUSD Facilities Master Plan Development
 
210512 gas development master plan steering committe meeting
210512 gas development master plan steering committe meeting210512 gas development master plan steering committe meeting
210512 gas development master plan steering committe meeting
 
Unit 3 integrated hse
Unit 3 integrated hseUnit 3 integrated hse
Unit 3 integrated hse
 
Big data meets evm (submitted).pptx
Big data meets evm (submitted).pptxBig data meets evm (submitted).pptx
Big data meets evm (submitted).pptx
 
Customer Intelligence & Social Media
Customer Intelligence & Social MediaCustomer Intelligence & Social Media
Customer Intelligence & Social Media
 
PMI chapter meeting (v4)
PMI chapter meeting (v4)PMI chapter meeting (v4)
PMI chapter meeting (v4)
 
Universidades
Universidades Universidades
Universidades
 
Inversion of Control
Inversion of ControlInversion of Control
Inversion of Control
 
Systems Engineering in One Picture
Systems Engineering in One PictureSystems Engineering in One Picture
Systems Engineering in One Picture
 
Fix you some bad estimation habits
Fix you some bad estimation habitsFix you some bad estimation habits
Fix you some bad estimation habits
 
Cure for cost and schedule growth
Cure for cost and schedule growthCure for cost and schedule growth
Cure for cost and schedule growth
 
The Social Shift Fund - Presentation
The Social Shift Fund - Presentation The Social Shift Fund - Presentation
The Social Shift Fund - Presentation
 
Pedir lo mismo de diferentes maneras
Pedir lo mismo de diferentes manerasPedir lo mismo de diferentes maneras
Pedir lo mismo de diferentes maneras
 
Risk management processes
Risk management processesRisk management processes
Risk management processes
 

Ähnlich wie Integrated Master Plan Development

Integrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleIntegrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleGlen Alleman
 
Beyond CPI and SPI
Beyond CPI and SPIBeyond CPI and SPI
Beyond CPI and SPIGlen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Glen Alleman
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value ManagementGlen Alleman
 
Focus on the nine I's (v9)
Focus on the nine I's (v9)Focus on the nine I's (v9)
Focus on the nine I's (v9)Glen Alleman
 
Building A Credible Measurement Baseline
Building A Credible Measurement BaselineBuilding A Credible Measurement Baseline
Building A Credible Measurement BaselineGlen Alleman
 
Building a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two DaysBuilding a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two DaysGlen Alleman
 
Building a Credible Performance Measurement Baseline (v3)
Building a Credible Performance Measurement Baseline (v3)Building a Credible Performance Measurement Baseline (v3)
Building a Credible Performance Measurement Baseline (v3)Glen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Assessing Project Performance Beyond CPI/SPI
Assessing Project Performance Beyond CPI/SPIAssessing Project Performance Beyond CPI/SPI
Assessing Project Performance Beyond CPI/SPIGlen Alleman
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by StepGlen Alleman
 
Project cost management a simplified approach white paper - Oracle Primaver...
Project cost management   a simplified approach white paper - Oracle Primaver...Project cost management   a simplified approach white paper - Oracle Primaver...
Project cost management a simplified approach white paper - Oracle Primaver...p6academy
 
Agile in an ANSI-748-C environment
Agile in an ANSI-748-C environmentAgile in an ANSI-748-C environment
Agile in an ANSI-748-C environmentGlen Alleman
 
Integrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value ManagementIntegrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value ManagementGlen Alleman
 
How should we estimates agile projects (CAST)
How should we estimates agile projects (CAST)How should we estimates agile projects (CAST)
How should we estimates agile projects (CAST)Glen Alleman
 
Deliverables based planning handbook
Deliverables based planning handbookDeliverables based planning handbook
Deliverables based planning handbookGlen Alleman
 

Ähnlich wie Integrated Master Plan Development (20)

Integrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleIntegrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master Schedule
 
Beyond CPI and SPI
Beyond CPI and SPIBeyond CPI and SPI
Beyond CPI and SPI
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
T24 Temenos Earned Value Management &amp; Project Planning Presentation
T24 Temenos Earned Value Management &amp; Project Planning PresentationT24 Temenos Earned Value Management &amp; Project Planning Presentation
T24 Temenos Earned Value Management &amp; Project Planning Presentation
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value Management
 
Focus on the nine I's (v9)
Focus on the nine I's (v9)Focus on the nine I's (v9)
Focus on the nine I's (v9)
 
Building A Credible Measurement Baseline
Building A Credible Measurement BaselineBuilding A Credible Measurement Baseline
Building A Credible Measurement Baseline
 
Building a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two DaysBuilding a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two Days
 
Building a Credible Performance Measurement Baseline (v3)
Building a Credible Performance Measurement Baseline (v3)Building a Credible Performance Measurement Baseline (v3)
Building a Credible Performance Measurement Baseline (v3)
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Ev+agile=success
Ev+agile=successEv+agile=success
Ev+agile=success
 
Assessing Project Performance Beyond CPI/SPI
Assessing Project Performance Beyond CPI/SPIAssessing Project Performance Beyond CPI/SPI
Assessing Project Performance Beyond CPI/SPI
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
Project cost management a simplified approach white paper - Oracle Primaver...
Project cost management   a simplified approach white paper - Oracle Primaver...Project cost management   a simplified approach white paper - Oracle Primaver...
Project cost management a simplified approach white paper - Oracle Primaver...
 
IMP IMS overview
IMP IMS overviewIMP IMS overview
IMP IMS overview
 
Agile in an ANSI-748-C environment
Agile in an ANSI-748-C environmentAgile in an ANSI-748-C environment
Agile in an ANSI-748-C environment
 
Integrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value ManagementIntegrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value Management
 
How should we estimates agile projects (CAST)
How should we estimates agile projects (CAST)How should we estimates agile projects (CAST)
How should we estimates agile projects (CAST)
 
Deliverables based planning handbook
Deliverables based planning handbookDeliverables based planning handbook
Deliverables based planning handbook
 

Mehr von Glen Alleman

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planningGlen Alleman
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSGlen Alleman
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project SuccessGlen Alleman
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMGlen Alleman
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk managementGlen Alleman
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk ManagementGlen Alleman
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Glen Alleman
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringGlen Alleman
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideGlen Alleman
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)Glen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possibleGlen Alleman
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic AbundanceGlen Alleman
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planningGlen Alleman
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for AgileGlen Alleman
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement BaselineGlen Alleman
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaGlen Alleman
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure RolloutGlen Alleman
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management TheoryGlen Alleman
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesGlen Alleman
 
Seven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project managerSeven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project managerGlen Alleman
 

Mehr von Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management Theory
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and Practices
 
Seven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project managerSeven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project manager
 

Kürzlich hochgeladen

Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxLoriGlavin3
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsPixlogix Infotech
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsMark Billinghurst
 
Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Manik S Magar
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii SoldatenkoFwdays
 
SAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxSAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxNavinnSomaal
 
H2O.ai CEO/Founder: Sri Ambati Keynote at Wells Fargo Day
H2O.ai CEO/Founder: Sri Ambati Keynote at Wells Fargo DayH2O.ai CEO/Founder: Sri Ambati Keynote at Wells Fargo Day
H2O.ai CEO/Founder: Sri Ambati Keynote at Wells Fargo DaySri Ambati
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfAlex Barbosa Coqueiro
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubKalema Edgar
 
Search Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdfSearch Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdfRankYa
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Scott Keck-Warren
 
Powerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time ClashPowerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time Clashcharlottematthew16
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Commit University
 
Story boards and shot lists for my a level piece
Story boards and shot lists for my a level pieceStory boards and shot lists for my a level piece
Story boards and shot lists for my a level piececharlottematthew16
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.Curtis Poe
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brandgvaughan
 
DSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine TuningDSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine TuningLars Bell
 
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupFlorian Wilhelm
 

Kürzlich hochgeladen (20)

Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and Cons
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR Systems
 
Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko
 
SAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxSAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptx
 
H2O.ai CEO/Founder: Sri Ambati Keynote at Wells Fargo Day
H2O.ai CEO/Founder: Sri Ambati Keynote at Wells Fargo DayH2O.ai CEO/Founder: Sri Ambati Keynote at Wells Fargo Day
H2O.ai CEO/Founder: Sri Ambati Keynote at Wells Fargo Day
 
DMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special EditionDMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special Edition
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdf
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding Club
 
Search Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdfSearch Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdf
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024
 
Powerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time ClashPowerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time Clash
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!
 
Story boards and shot lists for my a level piece
Story boards and shot lists for my a level pieceStory boards and shot lists for my a level piece
Story boards and shot lists for my a level piece
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brand
 
DSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine TuningDSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine Tuning
 
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project Setup
 

Integrated Master Plan Development

  • 1. The  Integrated  Master  Plan  And   Integrated  Master  Schedule   The  Integrated  Master  Plan  and  Integrated  Master  Schedule  are  one  of  the   six  elements  of  a  Credible  Performance  Measurement  Baseline  (PMB).   The  PMB  is  the  source  of  data  for  the  Program  Manager.  Some  of  this  data  is   used  in  the  Integrated  Program  Measurement  Report  (IPMR).  Some  is  used   in  the  assessment  of  the  Program’s  risk.  Some  define  the  deliverables  and   their  Technical  Performance  Measures.     5 V8.7  
  • 2. The  IMP  tells  us  where  is  the  program  going?   The  Plan  describes  where  we  are  going,  the  various  paths  we  can  take  to  reach  our   desLnaLon,  and  the  progress  or  performance  assessment  points  along  the  way  to   assure  we  are  on  the  right  path.   These  assessment  points  measures  the  “maturity”  of  the  product  or  service  against   the  planned  maturity.  This  is  the  only  real  measure  of  progress  –  not  the  passage   of  Lme  or  consumpLon  of  money.   The  Integrated  Master  Plan  (IMP)  Is  A  Strategy  For   The  Successful  Comple=on  Of  The  Project   2   5.0  Start  with  the  IMP  
  • 3. 3   5.0  Start  with  the  IMP  
  • 4. Quick  View  to  IMP/IMS   !  VerLcal  traceability  defines  the  increasing  maturity  of   key  deliverables   !  Horizontal  traceability  defines  the  work  acLviLes   needed  to  produce  this  increasing  maturity   !  Both  are  needed,  but  the  verLcal  traceability  is  the   starLng  point   !  Program  Events,  Significant  Accomplishments,  and   Accomplishment  Criteria  must  be  defined  before  the   horizontal  work  acLviLes  can  be  idenLfied   !  For  all  IMP  elements,  Key  Risks  must  be  idenLfied  and   assigned  from  Day  One,  even  without  miLgaLons   4   5.0  Start  with  the  IMP  
  • 5. The  IMP/IMS  is  Needed  on     Both  Sides  of  the  Contract   !  Ver%cal  traceability  defines  the  increasing  maturity  of   the  program’s  deliverables  measures  in  EffecLveness   (MoE)  and  Performance  (MoP)  for  the  Government.   !  Horizontal  traceability  defines  the  progress  to  plan  for   MoE’s  and  MoP’s  with  tangible  evidence  for  both  the   Government  and  the  Contractor.   !  Ver%cal  traceability  provides  the  Government  with   insight  into  the  progress  of  the  MoE’s  and  MoP’s  and   Technical  Performance  Measures.   !  Horizontal  traceability  provides  insight  into  Cost  and   Schedule  performance  for  the  Contractor,  reportable   through  the  IPMR  to  the  Government.   5   5.0  Start  with  the  IMP  
  • 6. MisconcepLons  of     the  IMP  /  IMS   Why  we  don’t  need/want  an  IMP/IMS     !  Only  required  for  ACAT  I  programs   !  Too  big  and  burdensome  for  our  small  dollar  value  program   !  Contractor  spends  B&P  and  program  budget  generaLng  and   maintaining  the  IMP,  without  measurable  benefit   !  Doesn’t  apply  on  a  services  contractors   !  Management  tool,  not  a  technical  tool   !  Doesn’t  apply  to  technology  programs   !  Doesn’t  apply  to  R&D  efforts   !  Doesn’t  apply  to  the  government   !  Help  me  get  a  waiver  so  I  don’t  have  to  use  an  IMP/IMS   6   5.0  Start  with  the  IMP  
  • 7. Aeributes  of  the  IMP   !  Traceability   –  Expands  and  complies  with  the  SOO,  Performance   Requirements,  CWBS,  and  CSOW   –  Based  on  the  customers  WBS   –  Is  the  basis  of  the  IMS,  cost  reports,  and  award  fees   !  Implements  a  measurable  and  trackable  program   –  Accomplishes  integrated  product  development   –  Integrates  the  funcLonal  acLviLes  of  the  program   –  Incorporates  funcLonal,  lower  level  and  S/C  IMPs   !  Provides  for  evaluaLon  of  Program  Maturity   –  Provides  insight  into  the  overall  effort   –  Level  of  detail  is  consistent  with  risk  and  complexity  per  §L   –  Decomposes  events  into  a  logical  series  of  accomplishments   –  Measurable  criteria  demonstrate  compleLon  /  quality  of   accomplishments   7   5.0  Start  with  the  IMP  
  • 8. Aeributes  of  the  IMS   !  Integrated,  networked,  mulL-­‐layered  schedule  of   efforts  required  to  achieve  each  IMP   accomplishment   –  Detailed  tasks  and  work  to  be  completed   –  Calendar  schedule  shows  work  compleLon  dates   –  Network  schedule  shows  interrelaLonships  and   criLcal  path   –  Expanded  granularity,  frequency,  and  depth  of  risk   areas   !  Resource  loading   !  Correlates  IMS  work  with  IMP  events   8   5.0  Start  with  the  IMP  
  • 9. The  Importance  of  the  IMP   !  The  IMP/IMS  is  the  single  most  important  document  to   a  program’s  success   –  It  clearly  demonstrates  the  providers  understanding  of  the   program  requirements  and  the  soundness  of  the  approach   a  represented  by  the  plan   !  The  program  uses  the  IMP/IMS  to  provide:   –  Up  Front  Planning  and  commitment  from  all  parLcipants   –  A  balanced  design  discipline  with  risk  miLgaLon  acLviLes   –  Integrated  requirements  including  producLon  and  support   –  Management  with  an  incremental  verificaLon  for   informed  program  decisions   9   5.0  Start  with  the  IMP  
  • 10. Just  A  Reminder,  before  moving  on   10   Page  47,  Defense  AcquisiLon  Guide,  January  10,  2012   Page  317,  Defense  AcquisiLon  Guide,  January  10,  2012   5.0  Start  with  the  IMP  
  • 11. Our  Goal  is  simple  …     How  can  we  recognize  the  Reality  of  the  Program’s   current  status  and  its  future  performance?   The  top  spins  conLnuous  while  in  a  dream  –  stops   spinning  in  the  real  world  –  Cobb’s  totem,  Incep=on   5.0  Start  with  the  IMP   11  
  • 12. 12   5.0  Start  with  the  IMP  
  • 13. Principles  of  Building  a  Credible   Integrated  Master  Plan   Building  the  IMP  is  a  Systems  Engineering  acLvity.  The  Integrated  Master  Plan  is   the  Program  Architecture  in  the  same  way  the  hardware  and  sooware  are  the   Product  Architecture.   Poor,  weak,  or  unstructured  ProgrammaLc  Architecture  reduces  visibility  to  the   Product  Architecture’s  performance  measures  of  cost  and  schedule  connected   with  Technical  Performance  Measures.     6 V8.7  
  • 14. Quick  View  of  Building  the  IMP   !  Start  with  each  Program  Event  and  define  the   Significant  Accomplishments  their  entry  and   exit  criteria  to  assess  the  needed  maturity  of   the  key  deliverables   !  Arrange  the  Significant  Accomplishments  in   the  proper  dependency  order     !  Segregate  these  Significant  Accomplishments   into  swim  lanes  for  IPTs   !  Define  the  dependencies  between  each  SA   14   6.0  Build  IMP  
  • 15. A  CriLcal  Understanding  of  the  IMP   The  IMP  defines  the  connecLons  between  the  Product  maturity  –  VerLcal  –  and  the   implementaLon  of  this  Product  maturity  through  the  FuncLonal  acLviLes  –  the  Horizontal     6.0  Build  IMP   15  
  • 16. Benefits  of  this  Formality   16   Objec%ve   Implementa%on   Event  Driven  Plan  versus  Schedule   Driven  Plan  is  based  on  compleLon  of   tasks  not  passage  of  Lme   Separate  the  plan  (IMP)  from  the   schedule  (IMS)  but  link  elements  with   numbering  system   Condensed,  easy  to  read  “Plan”  showing   the  “Events”  rather  than  the  work  effort   Indentured,  outline  format  –  not  text   Pre-­‐defined  entry  and  exit  criteria  for   major  Program  Events   Significant  Accomplishments  for  each   key  Program  Event   ObjecLve  measures  of  progress  and   compleLon  for  each  Accomplishment   Pre-­‐defined  Accomplishment  Criteria   (AC)  for  each  Significant   Accomplishment  (SA)   Stable,  contracture  plan,  flexible  enough   to  portray  program  status   IMP  part  of  the  contract,  IMS  is  a  data   item   Capture  essence  of  the  funcLonal   progress  without  mandaLng  a  parLcular   process  for  performing  the  work   Split  IMP  into  Product  and  Process   6.0  Build  IMP  
  • 17. Risk  Management   Building  the  IMP  Starts  at  the  RFP  with   Systems  Engineering  Measures   17   6.0  Build  IMP   SOO   ConOps   SOW   Techncial  and  OperaLonal   Requirements   CWBS  &   CWBS  DicLonary   Integrated  Master  Plan   (IMP)   Integrated  Master  Schedule   (IMS)     Earned  Value  Management   System   ObjecLve  Status  and  EssenLal  Views  to  support  the  proacLve  management   processes  needed  to  keep  the  program  GREEN   Performance  Measurement  Baseline   Measures  of   EffecLveness   Measures  of   Performance   TPMs  and  QBDs   JROC     Key  Performance  Parameters   Program    Specific   Key  Performance  Parameters   Technical  Performance   Measures   WBS   CWBS  
  • 18. IMP  captures  end  user  requirements  in   terms  MOEs,  MOPs,  KPPs,  and  TPMs   18   SOW   ConOps   WBS   CWBS   Technical  Performance   Measures     (TPM)   Messages  of  Performance   (MOP)   Measures  of  EffecLveness   (MOE)   Key  Performance   Parameters   (KPP)   Integrated  Master  Plan   (IMP)   Integrated  Master   Schedule   (IMS)   Performance   Measurement  Baseline   (PMB)   Technical  Requirements  
  • 19. The  IMP  /  IMS  Structure   19   IMS IMP Describes how program capabilities will be delivered and how these capabilities will be recognized as ready for delivery Supplemental Schedules (CAM Notebook) Work Packages and Tasks Criteria Accomplishment Events or Milestones 6.0  Build  IMP  
  • 20. The  IMP/IMS  provides  Horizontal  and   VerLcal  Traceability  of     progress  to  plan   !  VerLcal  traceability  AC  "  SA  "  PE   !  Horizontal  traceability  WP  "  WP  "  AC   20   Program Events Define the maturity of a Capability at a point in time. Significant Accomplishments Represent requirements that enable Capabilities. Accomplishment Criteria Exit Criteria for the Work Packages that fulfill Requirements. Work   Package   Work   Package   Work   Package   Work   Package   Work   Package   Work   Package   Work   package   6.0  Build  IMP  
  • 21. The  IMP’s  role  during  ExecuLon   21   Program ExecutionPMB for IBRProposal SubmittalDRFP & RFP Performance Measurement Baseline Tasks (T) BOE % Complete Statement of Work Program Deliverables IMP Accomplishments (A) Criteria (C) EVMS Events (E) Budget Spreads by CA & WPCAIV Capabilities Based Requirements X BCWS = Probabilistic Risk Analysis = Time keeping and ODC = Technical Performance Measure BCWP ACWP Cost & Schedule Risk Model BCWS Decreasing technical and programmatic risk using Risk Management Methods IMS Physical % Complete Continuity and consistency from DRFP through Program Execution WBS 6.0  Build  IMP  
  • 22. !  IMP  phrases  in  past  tense  –  do  describe  what   DONE  looks  like   !  IMS  phrase  in  present  tense  –  do  describe   work  needed  to  arrive  at  DONE   22   The  Grammar  of  the  Integrated   Master  Plan  (IMP)   Maturity   Product  AcLon   Product  State   AdjecLve   Noun   Verb   Verb   Demonstrates   Maturity   Step  in  the   Process   End  Item   Final  Status   Preliminary   Model/Sim   Design   Complete   Preliminary  Modeling  and  Simula%on  Design  Complete  
  • 23. 1st,  Principle  –     IMP  Building  is  a  Full  Contact  Sport   23   6.0  Build  IMP  
  • 24. Our  First  Approach  to  the  IMP  /   IMS  Paradigm   !  The  1st  approach  defines  Program  Events  (PE),   Significant  Accomplishments  (SA),  and   Accomplishment  Criteria  (AC),  derived  from  the   Work  Breakdown  Structure  or  the  SOW   !  This  1st  approach  can  be  done  in  6  easy  steps   24   6.0  Build  IMP   1.  IdenLfy  the  Program  Events  (PE)   (as  the  ACQ  Guide  tells  us)   2.  IdenLfy  the  Significant   Accomplishments  (SA)  from  the   WBS  deliverables     3.  IdenLfy  the  Accomplishment   Criteria  (AC)  needed  to  produce   these  deliverables   4.  IdenLfy  the  Work  Packages  for   each  Accomplishment  Criteria   5.  Sequence  the  Work  Packages   6.  Assemble  the  IMP/IMS  
  • 25. This  approach  doesn’t  give  us   visibility  into  what  “done”  looks  like   !  We  must  measure  increasing  product  maturity  in   units  meaningful  to  the  decision  makers   !  We  must  see  the  risks  before  they  arrive  so  we   can  take  correcLve  acLon   6.0  Build  IMP   25  
  • 26. First  Look  at  a  Significant   Accomplishment  (SA)   !  SAs  are  interim  and  final  steps  to  define,  design,  develop,   verify,  produce,  and  deploy  the  product  or  system.     !  SAs  must  occur  in  a  manner  that  ensures  a  logical  path  is   maintained  throughout  the  development  effort.     !  SAs  are  event  related  and  not  just  Lme  coincidental.     !  SAs  should  have  one  or  more  of  the  following  characterisLcs:     –  Consists  of  a  discrete  step  in  the  process  of  planned  development  that   must  be  complete  prior  to  an  event   –  Produces  a  desired  result  at  a  specified  event  that  indicates  a  level  of   design  maturity  (or  progress)  directly  related  to  each  product  and   process   –  Defines  interrelaLonships,  interdependencies,  or  “hand-­‐off”  points  of   different  funcLonal  disciplines  applied  to  the  program   26   6.0  Build  IMP   SAs  must  assess  compliance  with  Measures  of  EffecLveness    
  • 27. First  look  at  an  Accomplishment   Criteria  (AC)   !  ACs  are  definiLve  measures  directly  supporLng  successful   compleLon  of  a  significant  accomplishment.     !  ACs  show  objecLve  evidence  of  work  progress  (maturity  of  a   product);  i.e.,  be  seen,  read,  demonstrated,  or  quanLfied.  These   results  are  usually  incorporated  into  a  report  or  document  as   evidence  of  accomplishment.     !  ACs  are  prerequisites  for  compleLon  of  an  SA  (i.e.,  exit  criteria).     !  The  quesLons  that  need  to  be  repeatedly  asked  when  developing   ACs  are:   –  How  do  I  know  when  an  accomplishment  has  been  completed?   –  Is  the  criteria  directly  related  to  the  accomplishment?     –  Is  it  proof?     –  What  is  the  work  product?”   27   6.0  Build  IMP   ACs  must  assess  compliance  with  Measures  of  Performance  
  • 28. The  IMP  speaks  to  Measures  of  EffecLveness   (MoE)  and  Measures  of  Performance  (MoP)   28   6.0  Build  IMP   !  This  is  where  TPMs     are  connected  with   the  MoE’s  and   MoP’s   !  For  each   deliverable  from   the  program,  all   the  “measures”   must  be  defined  in   units  meaningful   to  the  decision   makers.   !  Here’s  some  “real”   examples.   1.  Provide  Precision   Approach  for  a  200   FT/0.5  NM  DH   2.  Provide  bearing  and   range  to  AC  plasorm   3.  Provide  AC   surveillance  to  GRND   plasorm     Measures  of   EffecLveness  (MoE)   1.  Net  Ready   2.  Guidance  Quality   3.  Land  Interoperability   4.  Manpower   5.  Availability   JROC  Key  Performance   Parameters  (KPP)   1.  Net  Ready   ! IPv4/6  compliance   ! 1Gb  Ethernet   2.  Guidance  quality   ! Accuracy  threshold  p70   @  6M   !   Integrity  threshold  4M   @  10-­‐6  /approach   3.  Land  interoperability   ! Processing  capability   meets  LB  growth  matrix   4.  Manpower   ! MTBC  >1000  hrs   ! MCM  <  2  hrs   5.  Availability   ! Clear  threshold  >99%   ! Jam  threshold  >90%   Measures  of  Performance   (MoP)   1.  Net  Ready   ! Standard  message  packets   2.  Guidance  Quality   ! MulLpath  allocaLon  budget   ! MulLpath  bias  protecLon   3.  Land  Interoperability   ! MOSA  compliant   ! Civil  compliant   4.  Manpower   ! OperaLng  elapsed  Lme   meters   ! Standby  elapsed  Lme   indicators   5.  Availability   ! Phase  center  variaLons     Technical  Performance   Measures  (TPM)   Mission  CapabiliLes  and  OperaLonal  Need   Technical  Insight  –  Risk  adjusted  performance  to  plan    
  • 29. The  1st  Problem  with  the  IniLal   IMP/IMS  Paradigm   !  There  is  no  single  source  of  guidance  for   construcLng  a  credible  IMP  and  IMS   – A  DOD  Guidebook,  but  sLll  in  Version  0.9   – A  few  DOD  service  pamphlets   – A  commercial  guidebook   – Many  contractor  guidelines   !  No  definiLve  guidance  from  DoD  on  what   makes  a  good  IMP   !  No  definiLve  DID  requiring  an  IMP  on  specific   programs   29   6.0  Build  IMP  
  • 30. The  IMP  is  a  good  start,  but  we’re   really  aoer  the  IMP  NarraLves   !  The  IMP  NarraLves  start  with  the  Statement   of  ObjecLves  (SOO)  or  Concept  of  OperaLons   (ConOps)   – These  idenLfy  the  top  level  program  objecLves   – They  define  the  big  picture  and  provide  pre-­‐award   trade  space   – They  provide  the  framework  for  the  Contractor  to   develop  the  proposal  through  the  IMP   !  With  the  Government’s  ExecuLve  summary,   provides  the  contractor  an  understanding  of   what  is  needed  and  what  is  important   30   6.0  Build  IMP  
  • 31. The  IMP  Process  NarraLve   The  IMP  Process  NarraLve  describes  how  the   technical  and  business  elements  of  the  program   will  be  conducted,  monitored,  and  controlled.     NarraLves  provide  the  customer  visibility  into   the  contractor’s  key  funcLonal  processes  and   procedures,  the  relaLonship  of  these  processes   and  procedures,  and  an  overview  of  the  effort   required  to  implement  them.   31   6.0  Build  IMP  
  • 32. IMP  NarraLve  for  PDR   Program   Event   Event  Descrip%on   PE  Maturity  Assessment   shown  in  SAs   PDR   PDR  establishes  the  “design-­‐  to”  allocated   baseline  to  the  subsystem  level,  assures  this   design  meets  the  funcLonal  baseline,  assures   system  requirements  have  been  properly   allocated  to  the  proper  subsystem.   PDR  establishes  the  feasibility  of  the  design   approach  to  meet  the  technical  requirements  and   provide  acceptable  interface  relaLonships   between  the  hardware  and  other  interfacing   items.     Any  changes  to  the  requirements  that  have   occurred  since  the  System  Requirements  Review   (SRR2)  will  be  verified  at  the  PDR.     PDR  assures  the  design  is  verifiable,  does  not  pose   major  IMS  or  Cost  risk,  and  is  mature  enough  to   advance  to  the  detailed  design  phase  –  CDR   !  Subsystem  level   operaLonal  concepts   defined   !  System  level  interfaces   baselined   !  Supportability  plans   established   !  Sooware  requirements   finalized   !  Subsystem  requirements   finalized  &  allocated   !  System  verificaLon,   validaLon  &  cerLficaLon   plans  updated   !  PDR  subsystem  design   completed   32   6.0  Build  IMP  
  • 33. What  the  IMP  NarraLve  Tells  Us?   !  States  the  objecLve  of  the  processes  used  to  build  the   products  describe  in  the  SOW   !  Provides  the  governing  documents,  compliance,  and   reference  for  the  process  acLviLes   !  Explains  the  process  approach   –  Portrays  the  key  acLviLes  of  the  approach   –  Illustrates  the  processes  tailored  for  the  specific  program   33   Inputs   AcLvity   3   AcLvity   5   AcLvity   4   Tools   AcLvity   1   AcLvity   2   Outputs   Metrics   6.0  Build  IMP  
  • 34. Some  IMP  Guidance     34   6.0  Build  IMP  
  • 35. The  Defense  AcquisiLon  Guide   (DAG)  Tells  Us  About  the  IMP   35   6.0  Build  IMP  
  • 36. The  DAG  Also  Tells  Us   36   6.0  Build  IMP  
  • 37. 5000.01  Part  2.B.3  AcquisiLon  Strategies,   Exit  Criteria,  and  Risk  Management   “Event  driven  acquisiLon  strategies  and  program  plans   must  be  based  on  rigorous,  objecLve  assessments  of  a   program’s  status  and  the  plans  for  managing  risk  during   the  next  phase  and  the  remainder  of  the  program.     The  acquisiLon  strategy  and  associated  contracLng   acLviLes  must  explicitly  link  milestone  decision  reviews   to  events  and  demonstrated  accomplishments  in   development,  tesLng,  and  iniLal  producLon.     The  acquisiLon  strategy  must  reflect  the   interrelaLonships  and  schedule  of  acquisiLon  phases  and   events  based  on  logical  sequence  of  demonstrated   accomplishments  not  on  fiscal  or  calendar  expediency.”   37   6.0  Build  IMP  
  • 38. What  makes  a  good     Program  Event  (PE)?   !  Events  are  the  conclusion  of  an  interval  of  major   program  accomplishments  (SA)  with  their  criteria  (AC)     !  IMP  events  represent  key  decision  transiLon  points   between  major  acLviLes  distributed  over  the  contract   period   –  The  IMP  is  a  Mini  Authoriza=on’s  to  Proceed  (ATP)  to  the   next  Program  Event  (PE)   !  Some  guidance  for  establishing  program/product   events:   –  Customer  Given  Events.     –  Key  Decisions  Needed   –  Risk  MiLgaLon  Event   –  DOD  Systems  Engineering  Technology  Review  (SETR)   Guidance   38   6.0  Build  IMP  
  • 39. What  makes  a  good   Significant  Accomplishment  (SA)?   !  IPT  can  manage  it  at  a  working  level   !  Shows  compleLon  and  result  s  of  discrete  steps  in  the   development  process   !  Indicates  maturity  of  the  product  through  MoEs  and  MoPs   !  Its  “significance”  measures  program  event  status   !  Relevant  and  logically  linked  to  the  proper  PE   –  Just  because  the  work  occurs  during  the  Lme-­‐frame  for  PE  A   doesn’t  mean  it’s  logically  linked  to  PE  A   !  Uses  consistent  language,  style,  format  through  verb   dicLonary,  for  example:   –  Segment  build  4  detailed  design  completed   –  Analysis  of  structural  integrity  completed   –  Structural  integrity  verified   39   6.0  Build  IMP  
  • 40. IMP  Significant  Accomplishments   !  SAs  are  NOT  just  a  list  of  “things”  to  do  before  the   Program  Event  (PE)   !  They  are  sequenced  accomplishments,  each  of  which   leads  to  the  PE,  e.g.  CriLcal  Design  Review  (CDR),  each   increasing  the  maturity  of  the  deliverables     –  SA  #  1  =  CDR  meeLng  conducted   –  SA  #  2  =  CDR  acLon  item  work-­‐off  plan  established   –  SA  #  3  =  85%  drawings  completed   –  SA  #  4  =  CDR  CDRLs  delivered   –  SA  #  5  =  Development  environment  operaLonal   –  SA  #  6  =  CriLcal  methods  analyses  completed   –  SA  #  7  =  RVTM  approved   40   6.0  Build  IMP  
  • 41. What  makes  a  good   Accomplishment  Criteria  (AC)?   !  Provides  objecLve,  measureable,  and  explicit   evidence  of  compleLon  and  closure  of  the   work  acLviLes  in  Work  Packages  that  saLsfies   the  Measure  of  Performance.   !  Defines  condiLons  for  closing  the  Significant   Accomplishment  (SA).   !  Answers  the  quesLon  how  do  we  know  when   a  Significant  Accomplishment  has  been   completed?   41   6.0  Build  IMP  
  • 42. !  Not  Significant   –  Too  small  to  significantly  contribute  to  successful  event  compleLon   –  Would  lead  to  trivial  tasks  (e.g.,  1  day  duraLon)   !  Ambiguous   –  Read  can’t  tell  what  Done  looks  like   !  Wrong  verb   –  Uses  a  verb  that’s  not  on  the  list  (DicLonary)   –  Uses  a  listed  verb  incorrectly   –  Doesn’t  have  a  verb  at  all   !  Not  measurable   –  Can’t  tell  when  we’re  done   !  Too  Many  SAs  or  ACs   –  Confuses  the  reader  and  confuses  the  execuLon  process  of  the   program   –  Dilutes  the  MoE  and  MoP   –  Reduces  visibility  into  increasing  maturity   42   What  makes  a  Not  So  Good     SA  or  AC?   6.0  Build  IMP  
  • 43. !  Program  Event  (PE)   –  A  PE  assess  the  readiness  or  compleLon  as  a  measure   of  progress   –  First  Flight  Complete   !  Significant  Accomplishment  (SA)   –  The  desired  result(s)  prior  to  or  at  compleLon  of  an   event  demonstrate  the  level  of  the  program’s   progress   –  Flight  Test  Readiness  Review  Complete   !  Accomplishment  Criteria  (AC)   –  DefiniLve  evidence  (measures  or  indicators)  that   verify  a  specific  accomplishment  has  been  completed   –  SEEK  EAGLE  Flight  Clearance  Obtained   43   F-­‐22  Example   6.0  Build  IMP  
  • 44. !  PE’s  are  easy,  they  are  in  the  SETR  and  Integrated   LogisLcs  Lifecycle  Management  System   !  The  SA’s  can  be  defined  from  the  program’s   deliverables  –  these  may  not  be  obvious  but  can   be  discovered  with  a  Product  Development   Kaizen  process  (more  later)   !  It’s  the  AC’s  that  are  hard  part  –  the  ACs  must   represent  the  exit  criteria  for  the  series  of  Work   Packages  that  do  the  work  to  produce  the   product   44   Now  comes  the  Hard  Part   6.0  Build  IMP  
  • 45. 6  Steps  to  IMP  Development   Let’s  start  to  build  the  IMP.     This  step-­‐by-­‐step  process  needs  to  be  followed  carefully.   The  IMP  is  constructed  one  Program  Event  at  a  Lme  –  Leo  to  Right  in  Lme.     To  do  otherwise  allows  confusion  and  disconnecLon  between  Program  Events  to   occur  and  dilutes  our  focus  on  defining  what  Done  looks  like  for  each  Program   Event.       7 V8.7  
  • 46. 46   7.0  6  Steps  
  • 47. Quick  View  of  Step-­‐By-­‐Step  IMP   IdenLfy  Program  Events   IdenLfy  Significant  Accomplishments   IdenLfy  Accomplishment  Criteria   IdenLfy  Work  Packages  needed  to  complete   the  Accomplishment  Criteria   Sequence  the  Work  Packages  (WP),  Planning   Packages  (PP),  Summary  Level  Planning   Packages  (SLPP)    in  a  logical  network.   Adjust  the  sequence  of  WPs,  PPs,  &  SLPPs  to   miLgate  major  risks.   47   7.0  6  Steps   1 2 3 4 5 6
  • 48. IdenLfy  the  Program  Events   Actors   Processes   Outcomes   Systems  Engineer   Define  the  process  flow  for   product  producLon  from   contract  award  to  end  of   contract   !  Confirm  Program  Events  represent  the   logical  process  flow  for  program   maturity   Program  Manager   Confirm  customer  is  willing  to   accept  the  process  flows   developed  by  the  IMP   !  Engage  with  contracts  and  customer   for  PE  definiLon   Project  Engineer   IdenLfy  interdependencies   between  program  event  work   streams   !  IdenLfy  Value  Stream  components  at   the  PE  level  before  flowing  them  down   to  the  SA  level   IMP/IMS  Architect   Capture  Program  Event   contents  for  each  IPT  or  work   stream   !  Establish  foundaLon  for  a  structure  to   support  the  descripLon  of  the   increasing  mature  as  well  as  the  flow   to  needed  work.   Copyright  ©  2012,  Glen  B.  Alleman,  Niwot  Ridge,  LLC   48   1 7.0  6  Steps  
  • 49. Outcomes  of  Step   !  Confirm  the  end  to  end  descripLon  of  the   increasing  maturity  of  the  program’s   deliverables   !  Establish  of  RFP  or  Contract  target  dates  for   each  Event.     !  Socialize  the  language  of  speaking  in  “Events”   rather  than  Lme  and  efforts   49   1 7.0  6  Steps  
  • 50. Events  Define  the  Assessment     of  the  Program’s  Maturity   50   ! Program  Events  are  maturity   assessment  points  in  the  program   ! They  define  what  levels  of  maturity   for  the  products  and  services  are   needed  before  proceeding  to  the  next   maturity  assessment  point   ! The  entry  criteria  for  each  Event   defines  the  units  of  measure  for  the   successful  compleLon  of  the  Event   ! The  example  below  is  typical  of  the   purpose  of  a  Program  Event   The  Cri=cal  Design  Review  (CDR)  is  a  mul=-­‐disciplined  product  and  process  assessment  to  ensure   that  the  system  under  review  can  proceed  into  system  fabrica=on,  demonstra=on,  and  test,  and   can  meet  the  stated  performance  requirements  within  cost  (program  budget),  schedule  (program   schedule),  risk,  and  other  system  constraints.     1 7.0  6  Steps  
  • 51. IdenLfy  the  Significant  Accomplishments   (SA)  for  Each  Program  Event  (PE)   51   Actors   Processes   Outcomes   System  Engineer   IdenLfy  Integrated  Product  Teams   (IPT)  responsible  for  the  SA’s     !  Define  the  boundaries  of  these   programmaLc  interfaces   !  Define  technical  and  process  risk   categories  and  their  bounds   Technical  Lead   Confirm  the  sequence  of  SA’s  has   the  proper  dependency   relaLonships   !  Define  the  product  development   flow  process  improves  maturity   !  Define  technical  risk  drivers   Project  Engineer   Confirm  logic  of  SA’s  for  project   sequence  integrity   !  Define  the  program  flows   improves  maturity     Control  Account   Manager   Validate  SA  outcomes  in  support  of   PE  entry  condiLons   !  Confirm  budget  and  resources   adequate  for  defined  work  effort   IMP/IMS  Architect   Assure  the  assessment  points   provide  a  logical  flow  of  maturity  at   the  proper  intervals  for  the   program   !  Maintain  the  integrity  of  the  IMP,   WBS,  and  IMS   2 7.0  6  Steps  
  • 52. Outcomes  of  Step   !  The  Significant  Accomplishments  are  the   “road  map”  to  the  increasing  maturity  of  the   program   !  The  “Value  Stream  Map”  resulLng  from  the   flow  of  SA’s  describes  how  the  products  or   services  move  through  the  maturaLon  process   while  reducing  risk   !  The  SA  map  is  the  path  to  “done”     52   2 7.0  6  Steps  
  • 53. SAs  define  the  entry  criteria  for   each  Program  Event   53   Preliminary  Design  Review  Complete   3 7.0  6  Steps  
  • 54. IdenLfy  Accomplishment  Criteria  (AC)  for  each   Significant  Accomplishment  (SA)   Actors   Processes   Outcomes   CAM   Define  and  sequence  the  contents   of  each  Work  Package  and  select   the  EV  criteria  for  each  Task   needed  to  roll  up  the  BCWP   measurement   !  Establish  ownership  for  the   content  of  each  Work  Package   and  the  Exit  Criteria  –  the   Accomplishment  Criteria  (AC)   Project  Engineer   IdenLfy  the  logical  process  flow  of   the  Work  Package  to  assure  the   least  effort,  maximum  value  and   lowest  risk  path  to  the  Program   Event   !  Establish  ownership  for  the   process  flow  of  the  product  or   service   Technical  Lead   Assure  all  technical  processes  are   covered  in  each  Work  Package   !  Establish  ownership  for  the   technical  outcome  of  each  Work   Package   IMP/IMS  Architect   Confirm  the  process  flow  of  the  ACs   can  follow  the  DID  81650   structuring  and  Risk  Assessment   processes   !  Guide  the  development  of   outcomes  for  each  Work  Package   to  assure  increasing  maturity  of   the  program   54   3 7.0  6  Steps  
  • 55. Outcomes  of  Step   !  The  definiLon  of  “done”  emerges  in  the  form   of  deliverables  rather  than  measures  of  cost   and  passage  of  Lme.   !  At  each  Program  Event,  the  increasing   maturity  of  the  deliverables  is  defined  through   the  Measures  of  EffecLveness  (MoE)  and   Measures  of  Performance  (MoP)   55   3 7.0  6  Steps  
  • 56. ACs  are  higher  fidelity   descripLons  of  “Done”  than  SAs   56  Cri%cal  Design  Review  Complete   4 7.0  6  Steps  
  • 57. IdenLfy  the  Work  for  Each  Accomplishment   Criteria  in  Work  Packages   Actors   Processes   Outcomes   Control  Account   Manager   IdenLfy  or  confirm  the  work   acLviLes  in  the  Work  Package   represent  the  allocated  work   !  Define  bounded  work  effort   defined  “inside”  each  Work   Package   Technical  Lead   Confirm  this  work  covers  the  SOW   and  CDRLs   !  Define  all  work  effort  for  100%   compleLon  of  deliverable  visible  in   a  single  locaLon  –  the  Work   Package   !  Confirm  risk  drivers  and  duraLon   variances   IMP/IMS  Architect   Assist  in  the  sequencing  the  work   efforts  in  a  logical  manner   !  Develop  foundaLon  of  the   maturity  flow  starLng  to  emerge   from  the  contents  of  the  Work   Packages   Earned  Value   Analyst   Assign  iniLal  BCWS  from  BOE  to   Work  Package   !  ConfirmaLon  of  work  effort   against  BOEs   !  Define  EVT  for  measures  progress   to  plan   57   4 7.0  6  Steps  
  • 58. Outcomes  of  Step   !  The  work  idenLfied  that  produces  a   measurable  outcome.   !  This  work  defined  in  each  Work  Package   !  The  Accomplishment  Criteria  (AC)  state   explicitly  what  “done”  looks  like  for  this  effort   !  With  “done”  stated,  measures  of  Performance   and  measures  of  EffecLveness  can  be  defined   58   4 7.0  6  Steps  
  • 59. Work  is  done  in  “packages”  that   produce  measureable  outcomes   59   Launch  Readiness  Review  Complete   5 7.0  6  Steps  
  • 60. Sequence  Work  Packages  (ACs)  for  each   Significant  Accomplishment  (SA)   60   Actors   Processes   Outcomes   Control  Account   Manager   Define  the  order  of  the  Work   Packages  needed  to  meet  the   Significant  Accomplishments  for   each  Program  Event   !  Define  the  process  flow  of  work   and  the  resulLng   accomplishments.   !  Assure  value  is  being  produced  at   each  SA  and  the  AC’s  that  drive   them   IMP/IMS  Architect   Assure  that  the  sequence  of  Work   Packages  adheres  to  the  guidance   provided  by  DCMA  and  the  EVMS   System  descripLon   !  Begin  the  structuring  of  the  IMS   for  compliance  and  loading  into   the  cost  system   Program  Controls   Staff   Baseline  the  sequence  of  Work   Packages  using  Earned  Value   Techniques  (EVT)  with  measures  of   Physical  Percent  Complete   !  Develop  insight  to  progress  to   plan  with  measures  of  physical   progress  for  each  Work  Packages   (EVT)   5 7.0  6  Steps  
  • 61. Outcomes  of  Step   !  Work  Packages  parLLon  work  efforts  into   “bounded”  scope   !  Interdependencies  constrained  to  Work   Package  boundaries  prevents  “spaghe{  code”   style  schedule  flow   !  Visibility  of  the  Increasing  Flow  of  Maturity   starLng  to  emerge  from  the  flow  of   Accomplishment  Criteria  (AC)   61   5 7.0  6  Steps  
  • 62. Sequence  Work  Packages  (AC’s)  into   an  IMS  for  each  Program  Event   62   6 7.0  6  Steps  
  • 63. Assemble  Final  IMP/IMS   Actors   Processes   Outcomes   IMP/IMS  Architect   StarLng  with  the  AC’s  under  each   SA’s  connect  Work  Packages  in  the   proper  order  for  each  Program   Event   !  Establish  the  Performance   Measurement  Baseline   framework.   !  IdenLfy  MoE  and  MoP  points  in   the  IMP   Program  Manager   Confirm  the  work  efforts  represent   the  commieed  acLviLes  for  the   contract   !  Review  and  approval  of  the  IMS  –   ready  for  baseline.   !  Review  and  approve  risk  drivers   and  duraLon  variance  models   Project  Engineer   Assess  the  product  development   flow  for  opLmizaLons   !  Review  and  approval  of  the  IMS  –   ready  for  baseline.   !  IdenLfy  risk  drivers  and  their   miLgaLons   Systems  Engineer   Confirm  the  work  process  flows   result  in  the  proper  products  being   built  in  the  right  order   !  Confirm  risk  drivers  and  duraLon   variances.   !  Review  and  approval  of  the  IMS  –   ready  for  baseline   63   6 7.0  6  Steps  
  • 64. Outcomes  of  Step   !  Both  the  maturity  assessment  criteria  and  the   work  needed  to  reach  that  level  of  maturity  are   described  in  a  single  locaLon   !  Risks  are  integrated  with  the  IMP  and  IMS  at   their  appropriate  levels   –  Risks  to  EffecLveness  –  risk  to  JROC  KPPs   –  Risks  to  Performance  –  risk  to  program  KPPs  and   TPMs   !  Leading  and  Lagging  indicator  data  provide   through  each  measure  to  forecast  future   performance     64   6 7.0  6  Steps  
  • 65. The  Previous  6  Steps  Result  In  A   Credible  IMP/IMS   65   !  The  IMP  is  the  “Outer  Mold   Line”,  the  Framework,  the   “Going  Forward”  Strategy  for   the  Program.   !  The  IMP  describes  the  path   to  increasing  maturity  and   the  Events  measuring  that   maturity.   !  The  IMP  tells  us  “How”  the   program  will  flow  with  the   least  risk,  the  maximum   value,  and  the  clearest   visibility  to  progress.   !  The  IMS  tells  us  what  work  is   needed  to  produce  the   product  or  service  at  the   Work  Package  level.   Our  Plan  Tells  Us  “How”  We   are  Going  to  Proceed   The  Schedule  Tells  Us   “What”  Work  is  Needed  to   Proceed   7.0  6  Steps  
  • 66. Significant  Accomplishments  for  an  actual   Program  Event   Flight  Test  Ascent  Aerodynamics  Confirmed   66   7.0  6  Steps  
  • 67. Horizontal  and  VerLcal  Traceability   of  the  IMP/IMS   Integrated  Master  Schedule   Work  sequenced  to   produce  outcomes   for  each  WP.   !  VerLcal  traceability  AC  "  SA  "  PE   !  Horizontal  traceability  WP  "  WP  "AC   Program Events Define the maturity of a Capability at a point in time. Significant Accomplishments Represent requirements that enable Capabilities. Accomplishment Criteria Exit Criteria for the Work Packages that fulfill Requirements. Work   Package   Work   Package   Work   Package   Work   Package   Work   Package   Work   package   Work   Package   Work   Package   67   7.0  6  Steps  
  • 68. The  IMP’s  connecLon  to  the  WBS   !  Start  with  the  Significant  Accomplishments  and  sequence   them  to  the  maturity  flow  for  each  Program  Event   !  The  WBS  connecLons  then  become  orthogonal  to  this  flow   68   7.0  6  Steps   Program  Event   SRR   SDR   PDR   CDR   TRR   ATLO   Work  Breakdown   Structure   4.920-­‐SDAI   A01,  A02   B01   C01,  C02   D01   E01   F01   4.200-­‐Sys  Test   A05   B03,  B04   D02,  D03   E02   F02   4.300-­‐Radar   A03   B02   C03   E03   4.330-­‐O&C  Sys   A06,  A07   B05   C04   D04   E04   F03,  F04   4.400-­‐  I&T   A08   C05   E05,  E06   F05   4.500-­‐Support   A09   D05   E07   F06,  F07  
  • 69. 69   7.0  6  Steps  
  • 70. 70   7.0  6  Steps  
  • 71. 71   7.0  6  Steps  
  • 72. 72   7.0  6  Steps  
  • 73. 73   7.0  6  Steps  
  • 74. 74   7.0  6  Steps  
  • 75. Nuances  Of  These  6  Steps   Building  the  Program  Event,  to  Significant  Accomplishment,  to  Accomplishment   decomposiLon  is  straight  forward.   For  each  Program  Event,  simply  idenLfy  what  are  the  needed  Significant   Accomplishment  for  the  entry  and  exit  criteria,  and  the  Accomplishment  Criteria   for  the  Work  Packages  that  produce  the  AC.   Yea  Right,  no  problem   8 V8.7  
  • 77. Quick  View  of  the  Nuances   !  Unfortunately  building  a  credible  IMP/IMS  is  a   nuanced  process,  subject  to  many  opportuniLes   for  diversions,  blind  alleys,  and  false  starts     !  It  is  slightly  counter  intuiLve  from  the  tradiLonal   scheduling  approach  to  start  with  the  verLcal   integraLon  –  but  it  is  criLcal  to  start  verLcally   !  Success  requires  the  full  parLcipaLon  of  Systems   Engineering,  CAMs,  and  the  Program  Manager   !  Success  requires  everyone  to  understand  the   nuances  of  the  IMP  building  efforts   77   8.0  Nuances  
  • 78. The  1st  Nuance   We  need  to  change  the  Planning  Paradigm   Beginner     Intermediate   Advanced   ! Take  the  program  events   and  use  the  WBS  to  define   the  SAs  and  ACs.   ! IdenLfy  the  tasks  to  produce   the  ACs  and  SAs   ! Collect  them  into  Program   Events   ! Organize  the  tasks  by  Work   Package   ! Sequence  the  work  packages   (AC’s)     ! Examine  the  exit  criteria  for   the  Program  Events  –  what   does  Done  look  like?   ! Ask  what  the  entry  criteria   are  for  each  Program  Event   ! Build  the  AC’s  to  support   these  entry  criteria   ! Pull  these  together  under   each  SA   ! Determine  the  Technical  and   ProgrammaLc  maturity  for   each  Program  Event  from   the  Concept  of  OperaLons   ! Assess  the  SA’s  for  each   Integrated  Product  Team  in   terms  of  their  streams   maturity  at  that  point  in  the   program   ! Sequence  the  SA’s  for  each   PE  and  assess  the  units  of   measure  of  “maturity”   ! Build  the  AC’s  to  support   each  SA’s  level  of  maturity   Copyright  ©  2012,  Glen  B.  Alleman,  Niwot  Ridge,  LLC   78   8.0  Nuances  
  • 79. The  2nd  Nuance   We  need  to  speak  about  Increasing  Maturity   Beginner   Intermediate   Advanced   ! The  sequence  of  work   closely  matches  the   horizontal  schedules  of  the   past   ! Align  this  work  with  the  WBS   elements   ! Focus  on  the  WBS  DicLonary   of  the  delivered  products  or   services   ! No  explicit  TPM,  MOE,  and   MOP  elements     ! The  sequence  of  work  is   related  to  the  Program   Events,  but  essenLally   “hangs”  from  the  PE  to  the   SA’s  and  then  the  AC’s   ! All  deliverables  are  visible   but  their  TPMs  and  other   system  measures  are  not   stated  in  the  IMP  or  its   narraLve.   ! There  is  a  narraLve  in  the   form  of  SA’s  and  AC’s  that   describes  how  the  program   moves  from  leo  to  right   alone  its  maturity  path   ! Risk  buy  down  and   reLrement  are  visible   ! Intermediate  Technical   Performance  Measures,   Measures  of  EffecLveness,   and  Measures  of   Performance  are  visible  in   the  IMP   Copyright  ©  2012,  Glen  B.  Alleman,  Niwot  Ridge,  LLC   79   8.0  Nuances  
  • 80. The  3rd  Nuance   Everything  Foot  and  Ties  to  the  IMP  &  IMS   Beginner   Intermediate   Advanced   ! The  IMS  contains  all  the   proper  fields  in  columns  and   is  horizontally  linked   ! The  WBS  elements  can  be   found  for  all  work  elements   ! CDRL’s  are  visible  and  their   mulLple  delivery  dates   connected  to  each  Program   Event   ! WBS  is  structured  in  a   product  manner  or  possibly   a  funcLonal  manner  with   some  deliverables  defined  in   the  terminal  nodes   ! The  WBS  is  properly  formed   inside  each  AC  with   incremental  deliverables   ! WBS  numbers  form  a  “well   structured”  tree,  but  sLll  is   not  “pure”  in  the  sense  of   deliverables  only,  no   funcLonal   ! Each  column  and  each  field   can  be  “pivoted”  to  form  a   proper  “tree”  of  value  flow.   ! The  WBS  is  a  “pure”  Product   Breakdown  Structure  (PBS)   and  the  services  needed  to   produce  those  products   ! The  WBS  defines  the   structure  of  the  delivered   product  or  service   ! The  VerLcal  trace  of  the  IPM   describes  the  flow  of   increasing  maturity  of  these   products  or  services   ! The  Horizontal  trace  of  the   IMP  describes  to  work  to  be   done  to  produce  this   maturity   80   8.0  Nuances  
  • 81. The  4th  Nuance   IMP/IMS  is  ProgrammaLc  Architecture   Beginner   Intermediate   Advanced   ! The  IMP  is  built  from  the   WBS  for  each  Program   Event.   ! The  IMP  is  seen  as  a   compliance  document  that   lists  the  Program  Events  and   a  “bunch  of  stuff”   underneath.     ! The  IMP  is  structured   around  separate  Program   Events,  but  below  the  SA’s   looks  like  a  “shop  floor”   schedule  with  liele  verLcal   connecLvity.   ! The  IMP  is  built  as  a  “value   stream”  flow  for  the   program  but  the  Systems   Engineers   ! This  programmaLc   architecture  is  built  in  the   same  way  the  technical   system  architecture  is  built   ! It  is  derived  from  the   ConOps  and  Tier  1  System   Requirements   ! The  IMP  shows  explicitly   how  these  are  supported  in   the  flow  of  the  SA’s   81   8.0  Nuances  
  • 82. The  5th  Nuance   The  IMP/IMS  connects  all  the  dots   82   8.0  Nuances   Measure  of   EffecLveness   Measure  of   Performance   Technical   Performance   Measure   Risk   Aleatory   Uncertainty   Epistemic   Uncertainty   Reference   Classes   Past   Performance   SME   Past   Performance   System   Architecture   AHP  
  • 83. ConnecLng  The  IMP  To  Program   Performance  Measures   Assembling  the  IMS  from  the  IMP  appears  to  be  a  straight  forward  process  –   details  the  tasks  that  support  the  Accomplishment  Criteria.  But  there  are  some   criLcal  steps  that  must  be  done  in  the  right  order  to  end  up  with  a  risk  tolerant   IMS.   Let’s  do  this  for  Our  Program   9 V8.7  
  • 84. The  Primary  Role  for  the  IMP  is  to  describe   what  done  looks  like  in  MoE’s  and  MoP’s   84  19  October  1899  Robert  Goddard  decided  that  he  wanted  to  "fly  without  wings"  to  Moon.   9.0  Framework  
  • 85. Quick  View  to  IMP/IMS  Framework   !  Measures  of  increasing  maturity  for  the  key   deliverables  is  the  foundaLon  for  increasing   the  Probability  of  Program  Success   !  Measures  of  EffecLveness  (MoE)  and   Measures  of  Performance  (MoP)  are  defined   in  the  Integrated  Master  Plan  (IMP)  NarraLve   !  Key  Performance  Parameters  (KPP)  –  both   JROC  and  program  specific  are  needed   !  Technical  Performance  Measures  (TPM)  are   needed  for  all  key  deliverables   85   9.0  Framework  
  • 86. Components  we’ll  meet  along  the  way   to  our  desLnaLon  to  the  credible  PMB   86   86   ObjecLve  Status  and  EssenLal  Views  to  support  the  proacLve  management  processes  needed   to  keep  the  program  GREEN   Risk  Management   SOW   SOO   ConOps   WBS   Techncial  and  OperaLonal   Requirements   CWBS  &   CWBS  DicLonary   Integrated  Master  Plan   (IMP)   Integrated  Master  Schedule   (IMS)     Measures  of   EffecLveness   Measures  of   Performance   Measures  of   Progress   JROC     Key  Performance  Parameters   Program    Specific   Key  Performance  Parameters   Technical  Performance   Measures   Earned  Value  Management   System   TPMs  Live   Here   Performance  Measurement  Baseline   86 9.0  Framework  
  • 87. Components  of  our  Final   DesLnaLon   87   Sow   SOO   ConOps   WBS   Techncial  and  OperaLonal   Requirements   Performance  Measurement  Baseline   CWBS  &   CWBS  DicLonary   Integrated  Master  Plan   (IMP)   Integrated  Master  Schedule   (IMS)     Earned  Value  Management   System   Technical Performance Measurement (TPM) involves the predicting the future values of a key technical performance parameter of the higher-level end product under development, based on current assessments of products lower in the system structure. Continuous verification of actual versus anticipated achievement for selected technical parameters confirms progress and identifies variances that might jeopardize meeting a higher-level end product requirement. Assessed values falling outside established tolerances indicate the need for management attention and corrective action. A well thought out TPM program provides early warning of technical problems, supports assessments of the extent to which operational requirements will be met, and assesses the impacts of proposed changes made to lower-level elements in the system hierarchy on system performance. Techncial  Performance   Measurement   heps://dap.dau.mil/acquipedia/Pages/Default.aspx   87 9.0  Framework  
  • 88. IdenLfying  the  TPMs  starts  with   good  Systems  Engineering   88   9.0  Framework  
  • 89. !  EIA-­‐632  –  involves  a  technique  of  predicLng   the  future  value  of  a  key  technical   performance  parameter  of  the  higher-­‐level   end  product  under  development,  based  on   current  assessments  of  products  lower  in  the   system  structure.     !  INCOSE  Systems  Engineering  Handbook.   InternaLonal  Council  on  Systems  Engineering   !  INCOSE  Metrics  Guidebook  for  Integrated   System  and  Product  Development   89   Policy  Guidance  for  TPMs   9.0  Framework  
  • 90. The  NDIA  EVM  Intent  Guide  Says   90   Notice the inclusion of Technical along with Cost and Schedule That’s the next step is generating Value from Earned Value EV MUST include the Technical Performance Measures 9.0  Framework  
  • 91. Some  More  Guidance   91   Systems  engineering  uses  technical  performance   measurements  to  balance  cost,  schedule,  and  performance   throughout  the  life  cycle.  Technical  performance   measurements  compare  actual  versus  planned  technical   development  and  design.  They  also  report  the  degree  to   which  system  requirements  are  met  in  terms  of  performance,   cost,  schedule,  and  progress  in  implemenLng  risk  handling.   Performance  metrics  are  traceable  to  user–defined   capabiliLes.   ―  Defense  Acquisi=on  Guide  (heps://dag.dau.mil/Pages/ Default.aspx)   In The End ― It’s All About Systems Engineering 9.0  Framework  
  • 92. More  Guidance  Can  Be  Found  in  …   92   9.0  Framework  
  • 93. This  Has  All  Been  Said  Before.     We  Just  Weren’t  Listening…   93   … the basic tenets of the process are the need for seamless management tools, that support an integrated approach … and “proactive identification and management of risk” for critical cost, schedule, and technical performance parameters. ― Secretary of Defense, Perry memo, May 1995 Why Is This Hard To Understand? ! We seem to be focused on EV reporting, not the use of EV to manage the program. ! Getting the CPR out the door is the end of Program Planning and Control’s efforts, not the beginning. TPM Handbook 1984 9.0  Framework  
  • 94. A  Final  Reminder  …   94   TPMs are one source of Risk Management processes Risk  Management  Guide  to  DOD  Acquisi=on,  Sixth  EdiLon  (Version  1,0),  Aug  2006   9.0  Framework  
  • 95. StarLng  out  on  the  Right  Foot  …   !  Most  IMP/IMS  literature  states  how  to  build  an  IMP  from  the  RFP  and   contractual  elements,  in  simple  and  maybe  simple  minded  terms   –  Decompose  the  events  into  SAs,  ACs,  and  their  Tasks  –  sounds  easy   !  This  approach  fails  to  provide  advice  for  several  things:   –  How  to  minimize  the  topological  connecLons  between  Events   –  How  to  increase  the  concurrency  between  IPTs   –  How  to  increase  the  tolerance  of  the  IMS  to  disrupLve  events   •  Known  and  knowable  risk   •  Unknown  and  possibly  unknowable  risk   !  The  construcLon  of  the  IMS  needs  to  take  place  in  what  seems  to  be  a   reverse  order   –  Build  the  IMP  as  a  Value  Stream  Map  describing  the  increasing  maturity  –  and   therefore  the  increasing  VALUE  of  the  deliverables  to  the  customer.   –  It’s  the  delivery  of  Customer  Value  that  inverts  the  management  process,  and   focuses  on  Keeping  the  Program  GREEN  as  planned  that  maximizes  value  to   the  customer  (the  Government)     95   9.0  Framework  
  • 96. SETR  Program  Events   96  heps://acc.dau.mil/docs/technicalreviews/dod_tech_reviews.htm   9.0  Framework  
  • 97. Build  PEs  Leo  to  Right   Start  with  SRR  (or  something  on  the  leW)  and  completely   define  its  comple=on,  before  moving  to  the  next  PE   !  Define  the  SAs  for  an  Event  and  construct  a  work  flow   of  the  acLviLes  needed  to  saLsfy  the  SA   –  These  acLviLes  are  yet  tasks,  so  don’t  commit  too  soon  to   defining  the  detailed  work   –  Isolate  the  SAs  by  event  first  –  only  work  on  one  event  at  a   Lme   !  IdenLfy  the  parLcipants  in  the  work   –  What  IPTs  parLcipate  in  this  work?   –  What  swim  lanes  are  needed  to  isolate  the  IPTs?   !  Define  the  elements     –  AcLviLes  performed  to  saLsfy  the  SA   –  Deliverables  that  result  from  these  acLviLes   !  There  are  sLll  not  Accomplishment  Criteria  (AC),  but   that  comes  next   97   9.0  Framework  
  • 98. The  Accomplishment  Criteria  (AC)   !  A  definiLve  measure  or  indicator  that  verifies   compleLon  of  work  for  the  accomplishment   – Completed  work  effort     •  Manufacturing  Plan  Completed   – ConfirmaLon  of  performance  compliance     •  Flight  Test  Report  Approved   – Incremental  verificaLon     •  Maintenance  DemonstraLon  Completed   – Completed  criLcal  process  acLviLes   •  Risk  Management  Plan  Approved   98   9.0  Framework  
  • 99. The  Accomplishment  Criteria  (AC)   !  Defines  the  measure  by  which  an  Accomplishment  (SA)  is   considered  “done”   !  Terms  like  complete,  delivered,  closed  have  no  “units  of   measure”  in  the  context  of  a  Significant  Accomplishment   (SA)  and  are  open  to  interpretaLon   !  Terms  like  …   –  Measures  of  compleLon  –  80%  of  drawings  approved  for  release   –  Counts  of  available  items  –  75%  of  pin-­‐outs  assigned  voltage   –  Fidelity  of  a  design  –  outer  mold  line  defined  within  90%  of   target   –  Error  bounds  –  spacecraW  mass  known  to  ±20%   –  Performance  parameters  –  disconnect  force  within  allowed   limits   –  Maturity  parameters  –  flight  ar=cle  successful  in  last  3  tests   …  are  used  to  define  the  “exit  criteria”   99   9.0  Framework  
  • 100. 2  Types  of  Accomplishment     Criteria:  Entry  and  Exit   !  Entry  Criteria  –  SubstanLates  readiness  for  the   review   !  Exit  Criteria  –  SubstanLates  successful   compleLon  of  the  review   !  CriLcal  Design  Review  (CDR)  example   – Are  we  ready  for  the  Flight  Test  Readiness   Review?   – How  do  we  know  the  FTRR  a  success?   – What  did  we  learn  from  the  FTRR  that  increases   the  maturity  of  the  program’s  deliverables.   100   9.0  Framework  
  • 101. The  IMP  Focuses  us  on  Measures   of  EffecLveness  and  Performance   101   MoE   KPP   MoP   TPM   Mission   Need   Acquirer  Defines  the  Needs  and  CapabiliLes   in  terms  of  OperaLonal  Scenarios   Supplier  Defines  Physical  SoluLons  that   meet  the  needs  of  the  Stakeholders   Opera%onal   measures  of  success   related  to  the   achievement  of  the   mission  or   opera%onal   objec%ve  being   evaluated.   Measures  that   characterize   physical  or   func%onal  aKributes   rela%ng  to  the   system  opera%on.   Measures  used  to   assess  design   progress,   compliance  to   performance   requirements,  and   technical  risks.   9.0  Framework  
  • 102. Measure  of  EffecLveness  (MoE)   !  Measures  of  EffecLveness  …   !  Are  stated  in  units  meaningful  to  the  buyer,   !  Focus  on  capabiliLes  independent  of  any   technical  implementaLon,   !  Are  connected  to  the  mission  success.   The  operaLonal  measures  of  success  that  are  closely  related  to  the   achievements  of  the  mission  or  operaLonal  objecLves  evaluated  in   the  operaLonal  environment,  under  a  specific  set  of  condiLons.   “Technical  Measurement,”  INCOSE–TP–2003–020–01   MoE’s  Belong  to  the  End  User   102   9.0  Framework  
  • 103. Measure  of  Performance  (MoP)   !  Measures  of  Performance  are  …   !  Aeributes  that  assure  the  system  has  the   capability  to  perform,   !  Assessment  of  the  system  to  assure  it  meets   design  requirements  to  saLsfy  the  MoE.   Measures  that  characterize  physical  or  funcLonal  aeributes   relaLng  to  the  system  operaLon,  measured  or  esLmated   under  specific  condiLons.   “Technical  Measurement,”  INCOSE–TP–2003–020–01   MoP’s  belong  to  the  Program  –  Developed  by  the  Systems   Engineer,  Measured  By  CAMs,  and  Analyzed  by  PP&C     103   9.0  Framework  
  • 104. Key  Performance  Parameters  (KPP)   Both  JROC  and  Program  Specific   !  Key  Performance  Parameters  …   !  Have  a  threshold  or  objecLve  value,   !  Characterize  the  major  drivers  of   performance,   !  Are  considered  CriLcal  to  Customer  (CTC).   Represent  the  capabiliLes  and  characterisLcs  so   significant  that  failure  to  meet  them  can  be  cause  for   reevaluaLon,  reassessing,  or  terminaLon  of  the  program   “Technical  Measurement,”  INCOSE–TP–2003–020–01   The  acquirer  defines  the  KPPs  during  the  operaLonal   concept  development  –  KPPs  say  what  DONE  looks  like   104   9.0  Framework  
  • 105.   Technical  Performance  Measures   (TPM)  for  key  deliverables     !  Technical  Performance  Measures  …   !  Assess  design  progress,   !  Define  compliance  to  performance   requirements,   !  IdenLfy  technical  risk,   !  Are  limited  to  criLcal  thresholds,   !  Include  projected  performance.  “Technical  Measurement,”  INCOSE–TP–2003–020–01   Aeributes  that  determine  how  well  a  system  or  system   element  is  saLsfying  or  expected  to  saLsfy  a  technical   requirement  or  goal   105   9.0  Framework  
  • 106. What  are  Technical  Performance   Measures  Really?   !  TPMs  are  measures  of  the  system   technical  performance  that  have   been  chosen  because  they  are   indicators  of  system  success.  They   are  based  on  the  driving   requirements  or  technical   parameters  of  high  risk  or   significance  -­‐  e.g.,  mass,  power  or   data  rate.   !  TPMs  are  analogous  to  the   programmaLc  measures  of   expected  total  cost  or  esLmated   Lme-­‐to-­‐compleLon.  There  is  a   required  performance,  a  current   best  esLmate,  and  a  trend  line.   !  Actual  versus  planned  progress  of   TPMs  are  tracked  so  the  systems   engineer  or  project  manager  can   assess  progress  and  the  risk   associated  with  each  TPM.     !  The  final,  delivered  system  value   can  be  esLmated  by  extending  the   TPM  trend  line  and  using  the   recommended  conLngency  values   for  each  project  phase.   !  The  project  life  trend-­‐to-­‐date,   current  value,  and  forecast  of  all   TPMs  are  reviewed  periodically   (typically  monthly)  and  at  all  major   milestone  reviews.   106   9.0  Framework  
  • 107. !  Tracking  TPMs  and  comparing  them  to  the  resource  growth   provides  an  early  warning  system  to  detect  deficiencies  or   excesses   !  Reserve  allocaLons  narrow  as  design  proceeds   !  TPMs  that  violate  reserve  allocaLons  or  have  trends  that   do  not  meet  the  final  performance  trigger  correcLve   acLons   107   Tracking  the  Technical     Performance  Measures   9.0  Framework  
  • 108. NoLonal  TPM  Design  Margin   Guidelines   108   9.0  Framework  
  • 109. Sample  IMP:   A  Flight  Avionics  System  (ConLnued)   Hardware  PDR  –  Purpose     !  Ensure  system  hardware  iniLal  design  has  been  updated,  and  meets   funcLonal  and  allocated  performance  requirements  within  program   constraints.     !  OperaLonal  security  concept  assessed.     !  Ensure  training  requirements  have  been  analyzed  and  their  objecLves   have  been  defined  for  training  missions.     !  ConfirmaLon  training  objecLves  and  MTC  design  and  integraLon  conform   to  the  Air  Force  syllabus  and  Ready  Aircrew  Program  (RAP).     !  Training  plan  will  be  updated.   !  Hardware  PDR  –  ExpectaLons   !  Team  agrees  system  hardware  iniLal  design  has  been  updated  and  can   proceed  to  the  detailed  design  phase.     !  Team  agrees  training  plans  and  objecLves  correlate  with  the  Air  Force   syllabus,  RAP  and  training  planning,  development  can  conLnue.     !  System  SpecificaLon  and  TTL  requirements  are  traceable  to  the  allocated   hardware  design.     109   9.0  Framework  
  • 110. Sample  IMP:   A  Flight  Avionics  System  (ConLnued)   !  Hardware  PDR  –  Entry  Criteria   !  FuncLonal  Baseline  AuthenLcated  (FBA)   !  IniLate  system  hardware  iniLal  design  and   allocate  funcLons  to  the  appropriate   ConfiguraLon  Items   !  All  specificaLons  updated  and  required   documentaLon  is  made  available  including   anLcipated  lower  level  design  documentaLon   !  All  SRR/SFR  acLon  items  closed  or   disposiLoned     110   9.0  Framework  
  • 111. Sample  IMP:   A  Flight  Avionics  System  (ConLnued)   Hardware  PDR  –  Accomplishments   !  System  hardware  iniLal  design  complete.     –  FuncLons  allocated  to  one  or  more  hardware  configuraLon  items  and   are  traceable  to  the  MTC  SSS  and  TSSC  SSS.     –  Human,  safety,  R&M,  EMI,  operaLonal  security,  instructor  and   operator  interfaces,  etc,  design  factors  have  been  reviewed.     !  Drao  instructor  and  operator  manuals  reviewed     !  Program  risks  updated,  assessed,  and  reviewed.     –  MiLgaLon  plans  in  place.   !  Program  schedule  and  constraints  updated  and  reviewed.     –  CriLcal  schedule  path  drivers  reviewed.     !  Design  criteria  for  the  simulaLon  and  database  development   reviewed  and  updated.   !  Program  processes  and  metrics  reviewed.   !  Test  Planning  acLviLes  and  relevant  documentaLon  reviewed  by   test  team.   111   9.0  Framework  
  • 112. Sample  IMP:   A  Flight  Avionics  System  (Concluded)   Hardware  PDR  –  Exit  Criteria     !  Hardware  (ownership,  visual,  IOS,  brief/debrief)  design  reviewed,  allocated  to  a   hardware  configuraLon  item  and  updated  to  include  instructor  and  operators   interfaces,  malfuncLon  and  control  requirements,  etc.     !  RTM  updated,  MTC  SSS,  TSSC  SSS  and  TTL  traceable  to  allocated  hardware  design   to  include  ESOH  requirements.     !  Human,  safety,  R&M,  EMI,  operaLonal  security,  instructor  and  operator  interfaces,   etc,  design  factors  reviewed.     !  MTC  and  TSSC  allocated  baselines  established  and  controlled  by  appropriate  level   documentaLon  for  PDR.   !  Drao  instructor  and  operator  manuals  reviewed  with  user  concurrence  and   incorporate  saLsfactory  human  factor  design  factors  into  the  operator  interfaces.     !  Risk  management  and  miLgaLon  plans  updated,  in  place,  addresses  ESOH  plans   and  risks,  and  within  program  constraints.     !  Risks  assesses,  understood,  documented,  accepted  and  understood  by  team.   !  Program  schedule  reviewed     –  CriLcal  path  drivers  idenLfied     –  IMS  Updated  and  reflects  criLcal  paths   112   9.0  Framework  
  • 113. One  More  IMP  Sample   !  (SA)  System  &  Segment   Requirements  Updated  &  Allocated   –  (AC)  SRR  /  SDR  Update  Review   Conducted   –  (AC)  Preliminary  System   SpecificaLon  Documents  (A011)   Baselined   –  (AC)  Preliminary  Spacecrao   Segment  SpecificaLon  Baselined   –  (AC)  Preliminary  Ground  Segment   SpecificaLon  Baselined   –  (AC)  Preliminary  SpecificaLon  Tree   Baselined   !  (SA)  Preliminary  ICDs  Baselined  For   Customer  Review   –  (AC)  Preliminary  Space-­‐Ground   ICD  Baselined     !  (SA)  PDR  System  Design  Completed   –  (AC)  Top  Level  System   Architecture  Updated   –  (AC)  PDR  Level  System  Analyses   Completed   –  (AC)  PDR  Level  Reliability  /   Availability  Analysis  Completed   –  (AC)  Preliminary  System  Level  Risk   Assessment  Completed   –  (AC)  System  Level  Plans  Updated   For  PDR   –  (AC)  Flight  Long  Lead  Review   Conducted   113   Preliminary  Design  Review   9.0  Framework  
  • 114. The  “But”  for  this  Guidance   !  With  these  samples  and  the  SETR  guidance   we’ve  just  started   !  The  program  needs  to  define  program  specific   events  to  assure  the  actual  maturity  measures   are  captured   – The  IMP  provides  sufficient  defini=on  to  track  the   step-­‐by-­‐step  comple=on  of  the  required   accomplishments  for  each  event  and  to   demonstrate  sa=sfac=on  of  the  comple=on   criteria  for  each  accomplishment.  [AFMC   PAMPHLET  63-­‐5]   114   9.0  Framework  
  • 115. IMP  Verbs  for  Significant   Accomplishments   115   Integrated  Master  Plan  Allowable  Verbs   Allocated:  Segment  requirement  is  flowed  down   from  the  System  SpecificaLon   Released:  Approved  item  for  delivery  for   intended  customer  or  supplier;  all  internal   distribuLon  and  sign  offs  complete.  An   electronic  version  is  made  accessible  on  the  IDE   Completed:  The  subject  item,  data,  document,   or  process  is  prepared  or  concluded,  and   reviewed  and  accepted  by  the  responsible  IPT.   SupporLng  documentaLon  is  available  through   IDE   Reviewed:  The  subject  item,  data,  document,  or   process  is  prepared  or  concluded,  and   documented  for  compleLon.  SupporLng   documentaLon  is  available  through  IDE   Conducted:  The  subject  meeLng  or  review  has   been  held  with  all  required  parLcipants.  The   charts  or  minutes  are  available  through  the  IDE   Updated:  The  subject  process,  data,  or   document  has  been  reevaluated  using  later   informaLon,  and  adjustments  incorporated.   Defined:  The  subject  configuraLon  items,  data,   or  document  was  submieed  to  the  customer   Validated:  Requirements  are  validated,  received   contractor  approvals,  were  distributed,  and  are   available  through  the  IDE   Established:  The  subject  items  is  created  and  set   in  place  in  a  manner  consistent  with  its  intended   use  aoer  review  and  accepted  by  the  IPT   Verified:  Requirements  are  verified  or  processed   in  accordance  with  established  pracLce.   9.0  Framework  
  • 116. The  IMP  Process  NarraLve   !  ObjecMve:  a  brief  statement  explaining  why  this   process  set  is  applied  for  this  program   !  Governing  DocumentaMon:  lists  of  the  guidance   or  compliance  documents;  e.g.,  specificaLons,   manuals,  and  procedures  including  company,   government,  and  industry  references   !  Approach:  concise  descripLon  as  to  who  owns   each  process;  what  are  the  roles  and   responsibiliLes;  and  the  overall  process  including   a  process  flow  diagram.   116   9.0  Framework  
  • 117. Generic  IMP  EvaluaLon  Criteria   !  Do  the  Program  Events  and  Accomplishments   reflect  the  logical  evoluLon  and  progress  of  the   overall  Program?   –  Do  program  events  and  their  definiLons  clearly   demonstrate  the  maturity  of  the  program  over   its  life?   –  Do  the  selected  Accomplishments  and   associated  Criteria  idenLfy  meaningful  and   measurable  progress  toward  the  key  goals  of   the  Program?   !  Do  the  Accomplishments  for  each  event   demonstrate  a  meaningful  understanding  of  the   program  requirements  or  are  they  tasks  that   anyone  could  do  for  any  contract?   –  Do  they  reflect  your  SOW  requirements?     !  Does  the  IMP  structure  readily  map  to  the  IPT   structure  such  that  each  IPT  can  easily  visualize   the  scope  of  their  responsibility?     !  When  awarded,  could  the  contractor  use  the   Accomplishments  as  discrete  acLvity  cost  accounts   in  their  earned  value  system?  Or  are  they  level  of   effort  in  nature?     !  Is  sufficient  visibility  provided  to  idenLfy  and  track   the  Program  Risk  Plan  and  associated  risk   miLgaLon  accomplishments  and/or   conLngencies?   –  Does  criteria  supporLng  the  accomplishments   include  key  performance  requirements?   !  Are  IPT  cross-­‐dependencies  and  dependencies   external  to  the  Program  appropriately  reflected  if   they  reflect  potenLal  schedule  or  performance   risks  to  the  success  of  the  Program?   !  Is  the  submieed  "Contract  IMP"  (the  Product  IMP   that  is  to  be  included  as  part  of  the  Program   Contract)  defined  to  the  appropriate  level:   –  Do  the  Accomplishments  and  associated   Criteria  go  down  to  a  level  sufficient  to  provide   visibility  into  key  subcontractor  acLviLes  upon   which  the  success  of  the  Program  may  be   dependent?   –  Are  the  Events  and  Accomplishments  included   in  the  IMP  at  such  a  level  as  to  make  the   maintenance  of  the  'Contractual  IMP'  pracLcal   or  does  it  include  an  unnecessary  level  of   detail?   117   9.0  Framework  
  • 118. Program  Management  Levels   Program Levels" IMP/IMS Elements" CWBS" Tier 1! Program Manager! Technical Leads! IPT Manager! Technical performance goals! Major Program Events (PE)! ! ! ! Significant Accomplishments (SA)! Level 1 & 2! Links to CLINs! Level 3 & 4! Control Packages! Link to PBS! Integrated EVMS! Tier 2! Control Account Managers ! Product Work Plan! Responsible organization elements! ! Accomplishment Criteria (AC)! ! ! ! ! Tasks (NA)! Level 5! Cost Account Package! Cost Collection Level! Links to WBS by OBS! Resource summaries! Early warning EVMS analysis! Tier 3! Work Package Manager! Detailed plans! Work package! Earned value calculations! 118   9.0  Framework  
  • 119. ConnecLng  the  Components     of  the  IMP/IMS   !  The  assembled  IMP/IMS  links  all  work   acLviLes  verLcally  to  the  ACs,  SAs,  and  PEs   119   IMS   Customer   Requirements   IMP   ORG   IPTs   ORG   IPTs   Performance   Analysis/   Management   Review   Events (E)  Events (E)   Accomplishments   Process   Narratives   Criteria   Integrated Master   Schedule (IMS)   Integrated Master   Schedule (IMS)   Control Account  Control Account   Work Package  Work Package   Work Package Tasks  Work Package Tasks   WBS   Program   Performance   Management   System   Supplemental Schedules   Risk and   opportunity   Risk and   opportunity   9.0  Framework  
  • 121. First  Pass  At  Building  The   Integrated  Master  Plan     Many  contractors  all  ready  have  work  processes  to  do  this.  These  steps  are   guidance  for  contractors  new  to  this  process.     With  the  RFP,  the  contract  should  be  capable  of  the  following  steps  to  create  the   Integrated  Master  Plan  and  Integrated  Master  Schedule.     We’ll  build  the  IMP/IMS  from  the  point  of  view  of  the  Government  to  compare   the  contractors  IMP  in  the  proposal   10   V8.7  
  • 122. Focused  with  the  Air  Vehicle   122   10.  1st  Pass  
  • 123. Quick  View  of  1st  Pass  for  IMP   !  Start  with  WBS   !  Use  Preliminary  Design  Review  Program  Event   !  IdenLfy  subsystems  for  flight  vehicle   !  IdenLfy  Significant  Accomplishments  for  PDR   compleLon   !  IdenLfy  Accomplishment  Criteria  for  each   sequence  of  Work  Packages  to  produce  the   deliverables  for  PDR   123   10.  1st  Pass