4. 4
Pohick Creek PL-566 Dams
The Natural Resources Conservation Service (NRCS) designed and
built six dams in the Pohick Creek Watershed between 1970 and 1985,
under the authority of Public Law 83-566, the Watershed and Flood
Prevention Act
The Northern Virginia Soil and Water Conservation District
(NVSWCD) and Fairfax County were the project sponsors
Fairfax County owns and maintains the six facilities
The Pohick dams have helped mitigate downstream flood damages and
provide improved water quality, wildlife habitat, recreational
opportunities, and economic benefits to the residents of Fairfax
County, and are a significant asset to the residents who live near the
lakes
5. PL-566 Dams Auxiliary Spillway Erosion Study
• In 1995, partly as a result of the White Oak dam failure, Fairfax County initiated a
spillway erosion study on four of the PL-566 dams (Royal Lake, Woodglen Lake, Lake
Barton, and Huntsman Lake)
• The studies indicated remedial measures were required to preclude excessive
headcutting and possible dam failure during the design flow event (PMF)
White Oak Dam in Madison County after June 1995 rainfall event
(~18” in 24 hours)
6. NRCS Technical and Financial Assistance
• Fairfax County and NVSWCD as the original project sponsors requested NRCS
assistance to rehabilitate the four PL-566 facilities (starting with Royal Lake) in
2005
• NRCS developed a rehabilitation plan for Royal Lake in 2006, working
collaboratively with Fairfax County, NVSWCD, and a citizen’s task force set up
by the Braddock District Supervisor’s office
• After adoption of the rehabilitation plan, NRCS asked Fairfax County and
NVSWCD to consider taking the lead on the design and construction effort,
with NRCS continuing to provide technical and financial assistance
• NRCS also asked Fairfax County and NVSWCD to provide assistance with the
Hydrologic and Hydraulic (H&H) studies required to develop rehabilitation
plans for the other facilities (Woodglen Lake, Lake Barton and Huntsman Lake)
7. PL-566 Facility Rehabilitation – Royal Lake
• Challenges
– First project – significant learning curve for county
and consultant in understanding and utilizing
NRCS design standards and specifications
– Tropical Storm Hanna impacts
14. PL-566 Facility Rehabilitation – Woodglen Lake
NRCS received ARRA funding which accelerated the design schedule
somewhat
Unsuitable subgrade material encountered at the end of the new
auxiliary spillway exit channel resulted in a field design change for the
installation of a subsurface drainage system
17. PL-566 Facility Rehabilitation – Lake Barton
Preferred concept (ACB armoring) in original NRCS rehabilitation plan was
changed at the request of landowners from whom easements were required. A
new concept utilizing cutoff walls that resulted in a much smaller tree loss was
moved forward
The sediment pool did not meet the minimum 50-year life requirement at the
completion of rehabilitation, and the rehabilitation plan recommended raising
the permanent pool elevation by 0.8 feet to achieve the required sediment
storage
Because of resident concerns and land rights issues, Fairfax County decided to
dredge Lake Barton to meet the sediment pool capacity requirements
NRCS also received ARRA funding for this project which significantly accelerated
the design schedule
19. PL-566 Rehabilitation Projects: Cost-Share Funds Received
• 2007/2008: Royal Lake Dam, $1.8 million
• 2009/2010: Woodglen Lake Dam, $1.4 million
• 2010/2011: Lake Barton Dam, $2.8 million
• 2013: Huntsman Lake, $1.8 million (obligated)
Fairfax County and NVSWCD as project sponsors have received approximately
$6 million to date for rehabilitation of the PL-566 facilities:
20. Huntsman Lake Dam Rehabilitation Project
Background
• Huntsman Lake Dam is regulated by the Virginia Department of
Conservation and Recreation (DCR), Division of Dam Safety
• Huntsman Dam is operating under a conditional operation and
maintenance (O&M) certificate from DCR because it’s auxiliary spillway
can only convey about 50 percent of the flows from the design storm
21. Huntsman Lake Dam Rehabilitation Project
Summary of Rehabilitation Plan
25. Lake Dredging and Restoration
Lake
Sediment
(CY)
Sediment
Pool
Capacity
(CY)
% sediment
pool
expended
Annual Load
(CY)
Annual Load
(CY/AC)
Lake Barton 32,500 75,000 43.33% 1,100 2.04
Huntsman Lake 65,000 295,000 22.03% 2,968 2.00
Woodglen Lake 32,500 160,000 20.31% 1,244 1.69
Lake Royal 105,000 416,000 25.24% 4,411 1.88
Lake Mercer* 37,000 550,000 6.60% 1,650 0.41
Lake Barton Example
27. Lake Restoration and Dredging Projects
Project Goals
• Restore sediment pool capacity
– Downstream water quality benefits
– Aesthetics
• Improve lake water quality and habitat
• Provide long term maintenance improvements
30. Disposal Site – Sediment Reuse
• Topsoil for landfill cover
• Topsoil product for resale
31. Lake Restoration
• In-lake forebay
• Wetland planting
• Shoreline stabilization
• Fish habitat
• Fish stocking
Lake Barton: Fish stocking by Virginia Game and Inland Fisheries
Fish habitat created from salvaged trees
49. Lake Accotink Dredging Disposal Site
at Virginia Concrete
Disposal site during dredging – March 2008
(198,000 cubic yards of dredge material was disposed at this site)
Disposal site 3 months after final site reclamation – July 2009
(Dredging and disposal were completed in 2008. Site reclamation was performed in spring 2009)
50. Reclaimed Old Concrete Disposal Site
Lake Accotink Dredge Disposal Site
2013
concrete
plant