SlideShare ist ein Scribd-Unternehmen logo
1 von 2
IMPEDANCE MEASUREMENT ON FIELD WINDINGS
General:
Measuring the impedance of field windings is done in order to detect turn-to turn failures in these
field windings.
Introduction
During long-time service of rotating machines it cannot be excluded that the turn-to-turn insulation of
the field windings becomes poor which can cause this insulation to fail. Reasons for these defects
often are long-time thermal ageing effects in addition with the high mechanical stresses due to
centrifugal forces, but can also be influenced by humidity or improper cleaning agents.
Single turn-to-turn failures in field winding usually are of no danger, but single turn-to-turn short can
cause local over-temperature which will consequently lead to further turn-to-turn failures. Such
shorted turns reduce the actually effective ampere-turns of a pole and thus unbalanced magnetic
forces are caused.
During machine service a single turn-to-turn failure can hardly be detected: The reduction of the
ohmic resistance of the field windings is small and thus the deviations in the exciter current are
small, too, and these deviations usually are covered by other effects (e.g. by the variation of the
ohmic resistance due to temperature). In a few cases only deviation in the dynamic behavior
(deviations in the vibration pattern) can be recognized due to the un-balanced magnetic forces.
Page 1
Test Technique
The test techniques most commonly used (and visualized by means of figure 1) are:
• Measuring the voltage drops ∆U across each pole
• Measuring the actual impedance Z’ of each pole
In the first-mentioned case the series connection of all field windings is energized by an appropriate
AC source and the voltage drop ∆U across each pole is measured. Poles with turn-to-turn shorts in
their field windings will show a remarkably reduced voltage ∆U in comparison with the average value
of ∆U. The impedance Z’ of a pole can be calculated by ∆U/I~.
In the second-mentioned case each pole is energized separately by an AC source and the
impedance Z’ = ∆U/I’ is recorded; field windings with turn-to-turn failures will show remarkably
reduced values of Z’.
It must be kept in mind that Z’ is influenced to a remarkable extent whether the magnet wheel is in
its stator or not!
In cases where the pole connectors are not accessible, only the total impedance Z’ can be
determined by measuring U~ and I~. The higher the number of poles, the more difficulty to detect a
single turn-to-turn short!
Special test techniques are necessary in order to detect turn-to-turn short which depend on
centrifugal forces. i.e. the rotor must have a certain speed above which turn-to-turn failures occur. In
the simplest way in such cases the rotor is energized by an AC source via the slip-rings and both I~
and U~ are recorded in relation to the rotor speed (limitations see above!) and Z(n) is calculated.
Another special test technique is using surge voltages in order to detect voltage-depending turn-to-
turn failures.
General Requirements
Under normal circumstances some disassembly work is necessary to ensure accessibility of the pole
connectors.
In cases where the pole connectors are not accessible and in cases where the expected turn-to-turn
failures depend on rotor speed there is the request of a well experienced technician in order to
detect such failures.
© This QM-Instruction is properly of PNG Power and must neither be copied nor used in any other
way without the written consent of PNG Power. Neither is it to be handed over nor in other way
communicated to a third party. Infringement will lead to prosecution.
Page 2

Weitere ähnliche Inhalte

Was ist angesagt?

CT design aspects - Nageswar-6
CT design aspects - Nageswar-6CT design aspects - Nageswar-6
CT design aspects - Nageswar-6Nageswar Rao
 
Overload capacity of power transformers
Overload capacity of power transformersOverload capacity of power transformers
Overload capacity of power transformersLeonardo ENERGY
 
Transformer Differential Protection Setting Calculations
Transformer Differential Protection Setting CalculationsTransformer Differential Protection Setting Calculations
Transformer Differential Protection Setting CalculationsPower System Operation
 
Generator capability curve
Generator capability curveGenerator capability curve
Generator capability curveAmit Pathak
 
System neutral-earthing
System neutral-earthingSystem neutral-earthing
System neutral-earthingazzaabo
 
Introduction to power transformers
Introduction to power transformersIntroduction to power transformers
Introduction to power transformersLeonardo ENERGY
 
Synchronous machines
Synchronous machinesSynchronous machines
Synchronous machinesmichaeljmack
 
Sample calculation-for-differential-relays
Sample calculation-for-differential-relaysSample calculation-for-differential-relays
Sample calculation-for-differential-relaysRoberto Costa
 
Symmetrical Components Fault Calculations
Symmetrical Components Fault CalculationsSymmetrical Components Fault Calculations
Symmetrical Components Fault Calculationsmichaeljmack
 
Auto synch considerations methods
Auto synch considerations methodsAuto synch considerations methods
Auto synch considerations methodsmichaeljmack
 
Principles of Power Systems V.K Mehta Complete Book - Chapter 3
Principles of Power Systems V.K Mehta Complete Book - Chapter 3Principles of Power Systems V.K Mehta Complete Book - Chapter 3
Principles of Power Systems V.K Mehta Complete Book - Chapter 3Power System Operation
 
Transmission line insulators
Transmission line insulatorsTransmission line insulators
Transmission line insulatorsPrashant Sharma
 
Power Factor Correction.ppt
Power Factor Correction.pptPower Factor Correction.ppt
Power Factor Correction.pptSalmanHameed26
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformervikasgupta1965
 
Transformer differential protection
Transformer differential protection Transformer differential protection
Transformer differential protection michaeljmack
 
Hv module 3 Impulse voltage generation
Hv module 3 Impulse voltage generationHv module 3 Impulse voltage generation
Hv module 3 Impulse voltage generationAsha Anu Kurian
 

Was ist angesagt? (20)

CT design aspects - Nageswar-6
CT design aspects - Nageswar-6CT design aspects - Nageswar-6
CT design aspects - Nageswar-6
 
Overload capacity of power transformers
Overload capacity of power transformersOverload capacity of power transformers
Overload capacity of power transformers
 
Transformer Differential Protection Setting Calculations
Transformer Differential Protection Setting CalculationsTransformer Differential Protection Setting Calculations
Transformer Differential Protection Setting Calculations
 
Generator capability curve
Generator capability curveGenerator capability curve
Generator capability curve
 
System neutral-earthing
System neutral-earthingSystem neutral-earthing
System neutral-earthing
 
Introduction to power transformers
Introduction to power transformersIntroduction to power transformers
Introduction to power transformers
 
Synchronous machines
Synchronous machinesSynchronous machines
Synchronous machines
 
Chapter 02- Breakdown in Gases (part-2)
Chapter 02- Breakdown in Gases (part-2)Chapter 02- Breakdown in Gases (part-2)
Chapter 02- Breakdown in Gases (part-2)
 
Protection of alternator
Protection of alternatorProtection of alternator
Protection of alternator
 
Sample calculation-for-differential-relays
Sample calculation-for-differential-relaysSample calculation-for-differential-relays
Sample calculation-for-differential-relays
 
Symmetrical Components Fault Calculations
Symmetrical Components Fault CalculationsSymmetrical Components Fault Calculations
Symmetrical Components Fault Calculations
 
Auto synch considerations methods
Auto synch considerations methodsAuto synch considerations methods
Auto synch considerations methods
 
Power System Stablity
Power System StablityPower System Stablity
Power System Stablity
 
Principles of Power Systems V.K Mehta Complete Book - Chapter 3
Principles of Power Systems V.K Mehta Complete Book - Chapter 3Principles of Power Systems V.K Mehta Complete Book - Chapter 3
Principles of Power Systems V.K Mehta Complete Book - Chapter 3
 
Transmission line insulators
Transmission line insulatorsTransmission line insulators
Transmission line insulators
 
Power Factor Correction.ppt
Power Factor Correction.pptPower Factor Correction.ppt
Power Factor Correction.ppt
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
 
Transformer differential protection
Transformer differential protection Transformer differential protection
Transformer differential protection
 
Hv module 3 Impulse voltage generation
Hv module 3 Impulse voltage generationHv module 3 Impulse voltage generation
Hv module 3 Impulse voltage generation
 
Transformer
TransformerTransformer
Transformer
 

Ähnlich wie FIELD WINDING IMPEDANCE

Power System Faults and Protection System
Power System Faults and Protection SystemPower System Faults and Protection System
Power System Faults and Protection SystemHarshalJain48
 
Stator core induction test
Stator core induction testStator core induction test
Stator core induction testDonald Stephen
 
Switch Gear & Protection (2170908) (Generator Protection)
Switch Gear & Protection (2170908) (Generator Protection)Switch Gear & Protection (2170908) (Generator Protection)
Switch Gear & Protection (2170908) (Generator Protection)Abhishek Choksi
 
4 PROTECTION OF ALTERNATOR.pptx
4 PROTECTION OF ALTERNATOR.pptx4 PROTECTION OF ALTERNATOR.pptx
4 PROTECTION OF ALTERNATOR.pptxNoname812799
 
Rotor earth fault protection of electric generator
Rotor earth fault protection of electric generatorRotor earth fault protection of electric generator
Rotor earth fault protection of electric generatorCS V
 
TOPIC 6.2- Power System Faults and Protection System.pptx
TOPIC 6.2- Power System Faults and Protection System.pptxTOPIC 6.2- Power System Faults and Protection System.pptx
TOPIC 6.2- Power System Faults and Protection System.pptxMartMantilla1
 
Generator Protection
Generator ProtectionGenerator Protection
Generator ProtectionPriten Vasa
 
Equipment protection
Equipment protectionEquipment protection
Equipment protectionSlides Hub
 
Major faults in an alternator and their protection.
Major faults in an alternator and their protection.Major faults in an alternator and their protection.
Major faults in an alternator and their protection.javid iqbal sodagar
 
Generator Protection By - Er Rahul Sharma
Generator Protection By - Er Rahul Sharma Generator Protection By - Er Rahul Sharma
Generator Protection By - Er Rahul Sharma Rahul Ruddra
 
Transcat and Megger: Power Quality 101 Webinar
Transcat and Megger: Power Quality 101 WebinarTranscat and Megger: Power Quality 101 Webinar
Transcat and Megger: Power Quality 101 WebinarTranscat
 
Generator protection by bhushan kumbhalkar
Generator protection by bhushan kumbhalkarGenerator protection by bhushan kumbhalkar
Generator protection by bhushan kumbhalkarBhushan Kumbhalkar
 
Presentation OutDoorSwithGear(AIS) .pptx
Presentation OutDoorSwithGear(AIS) .pptxPresentation OutDoorSwithGear(AIS) .pptx
Presentation OutDoorSwithGear(AIS) .pptxRAJKIRANR3
 
Alternator protection
Alternator protectionAlternator protection
Alternator protectionjawaharramaya
 
Protection & switchgear
Protection & switchgear  Protection & switchgear
Protection & switchgear johny renoald
 
Advanced Generator Ground Fault Protections
Advanced Generator Ground Fault ProtectionsAdvanced Generator Ground Fault Protections
Advanced Generator Ground Fault ProtectionsArjay Automation
 
New Microsoft Word Document
New Microsoft Word DocumentNew Microsoft Word Document
New Microsoft Word DocumentBarunava Sikdar
 

Ähnlich wie FIELD WINDING IMPEDANCE (20)

Power System Faults and Protection System
Power System Faults and Protection SystemPower System Faults and Protection System
Power System Faults and Protection System
 
Stator core induction test
Stator core induction testStator core induction test
Stator core induction test
 
Switch Gear & Protection (2170908) (Generator Protection)
Switch Gear & Protection (2170908) (Generator Protection)Switch Gear & Protection (2170908) (Generator Protection)
Switch Gear & Protection (2170908) (Generator Protection)
 
4 PROTECTION OF ALTERNATOR.pptx
4 PROTECTION OF ALTERNATOR.pptx4 PROTECTION OF ALTERNATOR.pptx
4 PROTECTION OF ALTERNATOR.pptx
 
Rotor earth fault protection of electric generator
Rotor earth fault protection of electric generatorRotor earth fault protection of electric generator
Rotor earth fault protection of electric generator
 
TOPIC 6.2- Power System Faults and Protection System.pptx
TOPIC 6.2- Power System Faults and Protection System.pptxTOPIC 6.2- Power System Faults and Protection System.pptx
TOPIC 6.2- Power System Faults and Protection System.pptx
 
Generator Protection
Generator ProtectionGenerator Protection
Generator Protection
 
Equipment protection
Equipment protectionEquipment protection
Equipment protection
 
Major faults in an alternator and their protection.
Major faults in an alternator and their protection.Major faults in an alternator and their protection.
Major faults in an alternator and their protection.
 
Generator Protection By - Er Rahul Sharma
Generator Protection By - Er Rahul Sharma Generator Protection By - Er Rahul Sharma
Generator Protection By - Er Rahul Sharma
 
Transcat and Megger: Power Quality 101 Webinar
Transcat and Megger: Power Quality 101 WebinarTranscat and Megger: Power Quality 101 Webinar
Transcat and Megger: Power Quality 101 Webinar
 
Generator protection by bhushan kumbhalkar
Generator protection by bhushan kumbhalkarGenerator protection by bhushan kumbhalkar
Generator protection by bhushan kumbhalkar
 
Presentation OutDoorSwithGear(AIS) .pptx
Presentation OutDoorSwithGear(AIS) .pptxPresentation OutDoorSwithGear(AIS) .pptx
Presentation OutDoorSwithGear(AIS) .pptx
 
High potential test
High potential testHigh potential test
High potential test
 
Alternator protection
Alternator protectionAlternator protection
Alternator protection
 
Protection & switchgear
Protection & switchgear  Protection & switchgear
Protection & switchgear
 
Chap16 254-279
Chap16 254-279Chap16 254-279
Chap16 254-279
 
Transformers Protection
Transformers ProtectionTransformers Protection
Transformers Protection
 
Advanced Generator Ground Fault Protections
Advanced Generator Ground Fault ProtectionsAdvanced Generator Ground Fault Protections
Advanced Generator Ground Fault Protections
 
New Microsoft Word Document
New Microsoft Word DocumentNew Microsoft Word Document
New Microsoft Word Document
 

Mehr von Donald Stephen

Tangent delta test report form
Tangent delta test report formTangent delta test report form
Tangent delta test report formDonald Stephen
 
Sustained three phase short-circuit test and overcurrent test
Sustained three phase short-circuit test and overcurrent testSustained three phase short-circuit test and overcurrent test
Sustained three phase short-circuit test and overcurrent testDonald Stephen
 
Sudden three phase short-circuit test
Sudden three phase short-circuit testSudden three phase short-circuit test
Sudden three phase short-circuit testDonald Stephen
 
Stator insulation test setup
Stator insulation test setupStator insulation test setup
Stator insulation test setupDonald Stephen
 
Stator core compr test
Stator core compr testStator core compr test
Stator core compr testDonald Stephen
 
Open circuit saturation test
Open circuit saturation testOpen circuit saturation test
Open circuit saturation testDonald Stephen
 
Rotor insul test setup
Rotor insul test setupRotor insul test setup
Rotor insul test setupDonald Stephen
 
Measurement of winding resistances
Measurement of winding resistancesMeasurement of winding resistances
Measurement of winding resistancesDonald Stephen
 
Measurement of shaft voltage and shaft current on machines with sleeve bearings
Measurement of shaft voltage and shaft current on machines with sleeve bearingsMeasurement of shaft voltage and shaft current on machines with sleeve bearings
Measurement of shaft voltage and shaft current on machines with sleeve bearingsDonald Stephen
 
Measurement of partial discharges
Measurement of partial dischargesMeasurement of partial discharges
Measurement of partial dischargesDonald Stephen
 
Loss tangent delta test
Loss tangent delta testLoss tangent delta test
Loss tangent delta testDonald Stephen
 
Line to-line sustained short-circuit test
Line to-line sustained short-circuit testLine to-line sustained short-circuit test
Line to-line sustained short-circuit testDonald Stephen
 
Insulation resistance testing
Insulation resistance testingInsulation resistance testing
Insulation resistance testingDonald Stephen
 
Insulation resistance test
Insulation resistance testInsulation resistance test
Insulation resistance testDonald Stephen
 
Efficiency determination on hydrogenerators by calorimetric method
Efficiency determination on hydrogenerators by calorimetric methodEfficiency determination on hydrogenerators by calorimetric method
Efficiency determination on hydrogenerators by calorimetric methodDonald Stephen
 
Determination of the transient open circuit time constant
Determination of the transient open circuit time constantDetermination of the transient open circuit time constant
Determination of the transient open circuit time constantDonald Stephen
 
Determination of inertia by load rejection
Determination of inertia by load rejectionDetermination of inertia by load rejection
Determination of inertia by load rejectionDonald Stephen
 

Mehr von Donald Stephen (20)

Tangent delta test report form
Tangent delta test report formTangent delta test report form
Tangent delta test report form
 
Sustained three phase short-circuit test and overcurrent test
Sustained three phase short-circuit test and overcurrent testSustained three phase short-circuit test and overcurrent test
Sustained three phase short-circuit test and overcurrent test
 
Sudden three phase short-circuit test
Sudden three phase short-circuit testSudden three phase short-circuit test
Sudden three phase short-circuit test
 
Stator insulation test setup
Stator insulation test setupStator insulation test setup
Stator insulation test setup
 
Stator core compr test
Stator core compr testStator core compr test
Stator core compr test
 
Open circuit saturation test
Open circuit saturation testOpen circuit saturation test
Open circuit saturation test
 
Rotor insul test setup
Rotor insul test setupRotor insul test setup
Rotor insul test setup
 
Noise measurement
Noise measurementNoise measurement
Noise measurement
 
Measurement of winding resistances
Measurement of winding resistancesMeasurement of winding resistances
Measurement of winding resistances
 
Measurement of shaft voltage and shaft current on machines with sleeve bearings
Measurement of shaft voltage and shaft current on machines with sleeve bearingsMeasurement of shaft voltage and shaft current on machines with sleeve bearings
Measurement of shaft voltage and shaft current on machines with sleeve bearings
 
Measurement of partial discharges
Measurement of partial dischargesMeasurement of partial discharges
Measurement of partial discharges
 
Loss tangent delta test
Loss tangent delta testLoss tangent delta test
Loss tangent delta test
 
Load test
Load testLoad test
Load test
 
Line to-line sustained short-circuit test
Line to-line sustained short-circuit testLine to-line sustained short-circuit test
Line to-line sustained short-circuit test
 
Insulation resistance testing
Insulation resistance testingInsulation resistance testing
Insulation resistance testing
 
Insulation resistance test
Insulation resistance testInsulation resistance test
Insulation resistance test
 
Efficiency determination on hydrogenerators by calorimetric method
Efficiency determination on hydrogenerators by calorimetric methodEfficiency determination on hydrogenerators by calorimetric method
Efficiency determination on hydrogenerators by calorimetric method
 
Determination of the transient open circuit time constant
Determination of the transient open circuit time constantDetermination of the transient open circuit time constant
Determination of the transient open circuit time constant
 
Determination of inertia by load rejection
Determination of inertia by load rejectionDetermination of inertia by load rejection
Determination of inertia by load rejection
 
Crack monitor
Crack monitorCrack monitor
Crack monitor
 

Kürzlich hochgeladen

KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGSIVASHANKAR N
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxfenichawla
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 

Kürzlich hochgeladen (20)

KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 

FIELD WINDING IMPEDANCE

  • 1. IMPEDANCE MEASUREMENT ON FIELD WINDINGS General: Measuring the impedance of field windings is done in order to detect turn-to turn failures in these field windings. Introduction During long-time service of rotating machines it cannot be excluded that the turn-to-turn insulation of the field windings becomes poor which can cause this insulation to fail. Reasons for these defects often are long-time thermal ageing effects in addition with the high mechanical stresses due to centrifugal forces, but can also be influenced by humidity or improper cleaning agents. Single turn-to-turn failures in field winding usually are of no danger, but single turn-to-turn short can cause local over-temperature which will consequently lead to further turn-to-turn failures. Such shorted turns reduce the actually effective ampere-turns of a pole and thus unbalanced magnetic forces are caused. During machine service a single turn-to-turn failure can hardly be detected: The reduction of the ohmic resistance of the field windings is small and thus the deviations in the exciter current are small, too, and these deviations usually are covered by other effects (e.g. by the variation of the ohmic resistance due to temperature). In a few cases only deviation in the dynamic behavior (deviations in the vibration pattern) can be recognized due to the un-balanced magnetic forces. Page 1
  • 2. Test Technique The test techniques most commonly used (and visualized by means of figure 1) are: • Measuring the voltage drops ∆U across each pole • Measuring the actual impedance Z’ of each pole In the first-mentioned case the series connection of all field windings is energized by an appropriate AC source and the voltage drop ∆U across each pole is measured. Poles with turn-to-turn shorts in their field windings will show a remarkably reduced voltage ∆U in comparison with the average value of ∆U. The impedance Z’ of a pole can be calculated by ∆U/I~. In the second-mentioned case each pole is energized separately by an AC source and the impedance Z’ = ∆U/I’ is recorded; field windings with turn-to-turn failures will show remarkably reduced values of Z’. It must be kept in mind that Z’ is influenced to a remarkable extent whether the magnet wheel is in its stator or not! In cases where the pole connectors are not accessible, only the total impedance Z’ can be determined by measuring U~ and I~. The higher the number of poles, the more difficulty to detect a single turn-to-turn short! Special test techniques are necessary in order to detect turn-to-turn short which depend on centrifugal forces. i.e. the rotor must have a certain speed above which turn-to-turn failures occur. In the simplest way in such cases the rotor is energized by an AC source via the slip-rings and both I~ and U~ are recorded in relation to the rotor speed (limitations see above!) and Z(n) is calculated. Another special test technique is using surge voltages in order to detect voltage-depending turn-to- turn failures. General Requirements Under normal circumstances some disassembly work is necessary to ensure accessibility of the pole connectors. In cases where the pole connectors are not accessible and in cases where the expected turn-to-turn failures depend on rotor speed there is the request of a well experienced technician in order to detect such failures. © This QM-Instruction is properly of PNG Power and must neither be copied nor used in any other way without the written consent of PNG Power. Neither is it to be handed over nor in other way communicated to a third party. Infringement will lead to prosecution. Page 2