Understanding Software Estimation, Negotiation,
and Enterprise Demand Management
An Executive Primer
Douglas T. Putnam and C. Taylor Putnam-Majarian
with foreward by Lawrence Putnam, Sr.
Understanding Software
Estimation, Negotiation, and
Demand Management
An Executive Primer
Published by Quantitative Software Management, Inc.
2000 Corporate Ridge, Ste 700
McLean, VA 22102
800.424.6755
info@qsm.com
www.qsm.com
Copyright © 2015 by Quantitative Software Management.
All rights reserved. This publication is protected by copyright, and permission must be obtained from the publisher
prior to any prohibited reproduction, storage in a retrieval system, or transmission in any form or by any means,
electronic, mechanical, photocopying, microfilm, recording, or likewise. For information regarding permissions,
write to the publisher at the above address.
Portions of this publication were previously published in journals and forums, and are reprinted here special
arrangement with the original publishers, and are acknowledged in the preface of the respective chapters.
Trademark Notice: Product or corporate names may be trademarks or registered trademarks, and are used only for
identification and explanation, without intent to infringe. Every attempt has been made to annotate them as such.
First Edition
TABLE OF CONTENTS
FOREWORD: by Larry Putnam Sr. i
CHAPTER 1: The Journey Forward 1
CHAPTER 2: The IT Innovation Cycle 5
CHAPTER 3: Most Common Reasons Why Software Projects Fail
and What You Can Do About It 9
CHAPTER 4: Fact Based Decisions – It Starts with Data and Establishing a Baseline 13
CHAPTER 5: The Software Production Equation and Rayleigh Staffing Model 21
CHAPTER 6: Single Release Estimation Using the Software Production Equation
and the Rayleigh Staffing Model 27
CHAPTER 7: Multiple Release and Complex Program Estimation 35
CHAPTER 8: Capacity Planning and Demand Management 39
CHAPTER 9: Tracking, Forecasting, Execution, and Post Mortem 51
CHAPTER 10: Understanding Quality and Reliability 55
CHAPTER 11: What does it take to Successfully Implement Estimation? 63
CHAPTER 12: Summing It Up 67
CONTRIBUTING AUTHORS 69
i
FOREWORD
Larry Putnam Sr., President Emeritus of QSM, Inc.
______________________________________________
Thirty five years ago, people who were involved with software development were frustrated
because they did not have a good method to determine the cost and schedule for their
projects. The typical approach was to use a number for software productivity, such as source
lines of code per person-month (SLOC/PM), obtained from a previous project, from a friend, or
from a magazine article, and then divide this number, say 200 SLOC/PM, into the best guess for
the size of the project, say 50,000 SLOC (COBOL), to obtain 250 person months of effort. This did
not address the schedule or how long it was going to take, and it gave uniformly poor results
time after time. Bosses were not happy. They couldn’t plan this way.
I was on active duty in the Army at the time, and in charge of the Army’s Data Processing
budget. I had some historical data available to me to analyze. There was a pattern to how
software systems behaved in their demand for people at different points in time during the
project. A project had a typical staffing buildup, peak, and tail off as the project progressed.
Errors were made that had to be found and fixed and the project’s environment changed,
making changes to the software system necessary. It was a dynamic, time varying process that
needed to be treated as such.
Fortunately, over the next year or so, by looking at approximately 50 Army systems we found a
time varying model, a Rayleigh curve, that had the buildup, peak and tail off that we saw in the
budget data. The parameters of this curve could be expressed in terms the bosses wanted to
deal with – effort and schedule. We also found that these parameters could be related to the
product size of the system (the functionality). This led to what we called the software equation.
We have used this software equation effectively now since 1978 and it has been built into a
comprehensive system to deal with most of the management issues related to software
development in nearly every domain (business, engineering, real-time embedded) and industry
sector (finance, telecom, medical, aerospace, defense, government, etc.). It works well, gets
good results, and has stood the test of time for three generations. In fact, the fundamental
software equation that I used to estimate COBOL programs running on a mainframe in the
1970s, is the same one my son, Doug (now Co-CEO of QSM, Inc.), used to estimate object-
oriented C++ programs that ran on a PC client-server platform in the 1990s. It is also the same
equation that my granddaughter, Taylor (now a consulting analyst at QSM, Inc.), uses to
estimate modern software projects that are written in Java using Agile methods, and run on a
cloud computing platform.
ii
So the book that follows entitled, Software Estimation, Negotiation and Enterprise Demand
Management – An Executive Primer, tells that story and shows the many ways these methods
can be used by management to plan and control software development with the opportunity
to save lots of money in the process.
Lawrence H. Putnam, Sr.
Jan 1, 2015
1
CHAPTER 1. THE JOURNEY FORWARD
_______________________________________________
The news of another failed software project causes many to roll their eyes. As an industry that has
been around since the 1940’s, and with all the technological advancements made over the years,
one would think that by now we would have figured out how long it takes to build software
applications. What many do not understand is that software development is very complicated
and not nearly as intuitive as society would like to think. Although this notion is not fully understood,
many organizations are feeling pressure to do better.
By picking up this book, you have begun your journey towards better decision making in
controlling individual software projects, as well as in long-term process improvements at the
portfolio level. There are many reasons why process improvement may interest you. Perhaps you
want to learn how to best utilize the resources available to you. Or perhaps, you feel as though
you do not have the right resources necessary to ensure the success of your software
development projects. Maybe you want to be in a better position to negotiate schedules and
budgets with business stakeholders or vendors. Whatever your reason, I want to commend you
for educating yourself on a better way to achieve successful project outcomes.
You may or may not have a background in software development, yet you find yourself currently
responsible for that function in your organization. While learning the ins and outs of software
development may be useful, it’s likely that you don’t have enough time to do that in addition to
all your other responsibilities. Your main concerns probably include the following:
1. What is the status of the current project?
2. What can be done to make long-term improvements to our organization?
3. What options are available right now in the current development process?
In this book, we will help you answer those questions by providing a basic explanation of the
methods involved in the overall software management process including demand management,
software estimation and risk mitigation, as well as overall process improvement strategies.
SOFTWARE DEVELOPMENT IS NOT MANUFACTURING
One common mistake made when initiating a development project is that most businesses
assume software development mirrors manufacturing. In reality, the two behave very differently.
Manufacturing strives to gain predictability in production by eliminating any variance. Resources
are often carefully distributed so as to ensure that production is not only controllable, but also
controlled. In manufacturing, the relationship between time and cost is linear. If one wants to
double the output, you invest in a second manufacturing line and produce twice the volume of
product in half the time (see Figure 1.1).
2
Figure 1.1. The cost of a manufacturing project over time.
However, software development is much more abstract. You cannot physically touch a software
project like you would a manufactured item, which makes it especially hard to judge its status
towards completion. In manufacturing, the tasks are mostly dependent, meaning one task must
be completed before another task may be started. In software development, it is possible for
there to be both independent as well as dependent tasks, making it unique from traditional
manufacturing. Additionally, the relationship between time and cost is non-linear in software
development (see Figure 1.2).
Figure 1.2. The cost of a software development project over time.
If you attempt to shorten the schedule by adding people, you will find rapid diminishing returns on
the schedule with corresponding large increases in cost and decreases in quality. Why, you might
ask? The reason is quite simple, and relates to the basic laws of acceleration. Acceleration
requires energy. Energy efficiency decreases as acceleration increases. A simple analogy that
3
most people can relate to is a gasoline powered automobile. Suppose you are at a stop light
and the light turns green. If you stomp on the gas to get to the next stop light as quickly as possible,
the miles per gallon meter will immediately drop to a lower efficiency rating. In the same situation,
you can be more conservative by accelerating at a slower rate. It takes slightly longer to get to
the next light but you do it in a much more fuel efficient manner. Software development staffing
behaves in a similar manner. The “fuel” is the human effort “hours”. If you add more people, the
human communication complexity increases which manifests itself in more defects, all of which
need to be found and fixed. This creates more rework cycles and is one of the reasons why using
larger teams only achieves marginal schedule compression. From a management standpoint,
this means that leaders have a direct influence on cost and quality by simply controlling the
project’s staffing levels. As a leader, this can be very empowering.
SUMMARY
Understanding the non-linear relationship between schedule and cost can be extremely useful in
project planning. Additionally, knowledge of the software development lifecycle will facilitate
the logistics of how to staff projects. The following section describes the high-level phases of
software development and how they can be applied to project staffing.
4
5
CHAPTER 2. THE IT INNOVATION CYCLE
_______________________________________
When faced with a problem, regardless of what it is, humans will attempt to solve it using a
common process. First, we will determine if their desired course of action is even feasible. Next
they will formulate a design of action. The third step is to actually carry out the planned activities,
and finally, the fourth step is to clean up and fine tune the finished product.
This problem-solving process is applicable to software development as well. Regardless of the
development methodology that you use, all software projects have four high level phases: Phase
1 - Feasibility, Phase 2 - Requirements & High-Level Design, Phase 3 - Build and Test, and Phase 4 -
Post Delivery Stabilize and Deploy (see Figure 2.1). While various methodologies may further
subdivide the development activities and increase or decrease the amount of overlap and
concurrency, these are the overarching phases used in estimation and project management.
Figure 2.1. High-level software development phases
6
PHASE 1: THE ‘WHAT?’ PHASE
This is the earliest phase in the software development lifecycle, in which individuals determine
what it is that they hope to achieve by developing this software. This phase is extremely high-level
and the main focus is to brainstorm whether or not building an application is even feasible.
Typically these activities include: a statement of need or list of the capabilities that the user
expects from the system, a feasibility analysis assessing whether or not the project can and should
be done, and a set of high-level plans documenting the management approach. This phase
typically results in a go or no-go decision.
PHASE 2: THE ‘HOW?’ PHASE
The second high-level phase focuses primarily on how the work is going to get done. Many equate
this with planning because many decisions about the requirements and design are made. Typical
activities for this phase include: defining the interfaces between the system-level components,
specifying software architecture and requirements by describing inputs and outputs, and finalizing
the project plans. A design review may be held at the end of this phase or it may be iterative in
an agile-like development process. Phase 2 typically overlaps with the end of Phase 1, as well as
the beginning of Phase 3.
PHASE 3: THE ‘BUILD IT’ PHASE
The third phase of the software development lifecycle is the longest because it involves actually
carrying out the plans made in Phase 2. The phase begins with detailed design and coding. The
final portion of the phase includes system testing and hardening of the product prior to general
availability. Phase 3 ends at the first customer release, which is typically when the system is 95%
defect free and can run for about one day without encountering a critical defect.
PHASE 4: THE POST DELIVERY STABILIZATION PHASE
The last phase of the software development lifecycle begins after the software has been released
to customers. Typical activities include correcting latent defects found after general availability.
The purpose of this phase is to provide product support to the customer base, and stabilize the
existing product. This phase may be considered complete once the project reaches a particular
reliability milestone or certification level. The duration of this phase varies depending on the needs
of the users. Prior to the conclusion of this phase, the base product often transitions to long-term
operations and maintenance. The next innovation cycle begins as new capabilities are added
to the base product.
An advantage of using a four-phase macro model of the innovation cycle is that it can be easily
adapted to any software development methodology. Given the introduction and change rate
of new methodologies, the ability to maintain some continuity with estimation techniques provides
great benefits as the industry adapts to the most effective development approaches. The
following table maps the four phases to some of the more popular methodologies used today.
7
Methodology Phase 1: What? Phase 2: How? Phase 3: Build
& Test
Phase 4: Deploy &
Stabilize
Waterfall Concept Requirements &
Design
Construct &
Test
Deploy
RUP Initiation Elaboration Construction Transition
Agile Initiation Iteration
Planning
Iteration
Development
Production
SAP ASAP Project
Preparation
Business Blueprint Realization &
Final Prep
Go Live
SUMMARY
In summary, humans follow a distinctive process that they apply to innovation projects. Initially
they identify problems and potential solutions. The following step is to determine the most feasible
solution to the problem. Next they conceptualize the solution and implement it. Finally, they put
the solution to use and fine tune it. This flexible macro model with four high-level phases is
adaptable and can be applied to any development methodology.
8
9
CHAPTER 3. THE MOST COMMON REASONS
WHY SOFTWARE PROJECTS FAIL
AND WHAT YOU CAN DO ABOUT IT
_______________________________________
An article based on this chapter is scheduled to appear in an
upcoming edition of the online journal InfoQ.
Knowing the basics of software development can greatly improve the project outcome.
However, that alone is not enough from preventing project failures. Projects can be categorized
as failures for a number of reasons. Cost overruns, late deliveries, poor quality, and developing
the wrong product are a few of the reasons why projects can be viewed unfavorably. When
faced with a failure, project managers often find themselves wondering where it went wrong.
More often than not, software developers bear the brunt of the responsibility for such situations;
after all, they’re the ones who built the application. However, closer examinations of the projects
do not always show evidence of incompetence. When asked to assess these projects, QSM
compares the completed projects with our industry trends, and often finds that they performed
“reasonably”. So then why are these projects considered failures? Our experience shows that the
overwhelming majority of the problems can be tied to flawed estimation or poor business decision
making. It is important to make sure that everyone understands a common set of terms because
we often find that individuals and organizations use them interchangeably when they each have
a unique meaning. Targets, constraints, estimates, commitments, and plans have distinct
definitions and can be reviewed below.
 Target – A goal, what we would like to do or achieve.
 Constraint – Some internal or external limitation on what we are able to do.
 Estimate – A technical calculation of what we might be able to do at some level of scope,
cost, schedule, staff, and probability.
 Commitment – A business decision made to select one estimate scenario and assign
appropriate resources to meet a target within some constraints.
 Plan – A set of project tasks and activities that (we calculate) will give us some probability
of meeting a commitment at a defined level of scope, budget, schedule, and staff.
In other words, decisions made based off of unrealistic targets or constraints can send a project
on a death march from the start. Here is our list of the top five reasons why IT projects fail:
1. Accepting a forced schedule or mandated completion/ milestone dates without
substantial data and analysis.
How many times have you found yourself in a situation in which you’ve been given an
unreasonably short deadline? Someone in your organization publicly speculates that the
project will be done by a particular date, thus unintentionally committing the team to that
deadline. Perhaps your budget cycle dictates that the money allocated to this project
10
must be spent by the end of the year or the next release will not get funded. Maybe the
stakeholder wants the project finished by Christmas so that he/she can enjoy the holiday
in peace, knowing that the project is complete. Or maybe the stakeholder just really likes
round numbers and wants the project to release the 1st of the month. There are numerous
reasons why a development team would be given an arbitrary project completion
deadline. The unfortunate reality of an overzealous schedule often results in overstaffing
the project, the next reason why software projects fail.
2. Adding excessive personnel to achieve unrealistic schedule compression.
How do project managers deal with an overly optimistic schedule? One common
response is to staff up the project, often adding way more people than necessary to
complete the project. Not only does this drastically increase the cost of a project, but it
also decreases the quality. Having more people involved in the project increases
opportunities for miscommunications and also makes it more challenging to integrate the
different sections of code together. Additionally, Frederick Brooks (1975) would argue that
“adding people to a late project only makes it later,” which makes sense. The people
have to come from somewhere, often from other projects. This puts the other projects
further behind schedule and requires that the new staff get caught up by veteran staff,
thus decreasing productivity across the board.
3. Failing to account and adjust for requirements growth or change into schedule and budget
forecasts.
“Wouldn’t it be great if…?” Those five words can be some of the most dreaded, especially
when heard halfway through the construction portion of a project. While there is certainly
a time and a place for brainstorming, those activities should take place in Phases 1 and 2.
In fact, the purpose of these two phases is to determine whether or not a project is feasible,
and what features the application should have. If you think of it this way, Phase 2 helps
you figure out what you are building, while in Phase 3, you build whatever you decided
upon in Phase 2. While some overlap may exist between the two high-level phases, by the
time you’re in the Phase 3, the scope of required functionality for a given product release
should be clear.
 Requirements growth is a problem if you’re adding functionality without allotting
more time and budget for development. In essence, you’re asking for more work
in a shorter amount of time, a technique that we’ve already found does not work.
 Changes to existing requirements can also be a problem depending on the nature
and timing of the change. Projects using Agile methods can manage changes to
requirements details, as long as they occur before construction of a given iteration.
However, any changes to requirements of software architecture that cause rework
of code already written will almost certainly have an impact to the schedule and
budget.
4. Emotional or “intuition-based” stakeholder negotiation that ignores facts and statistics.
At some point or another we’ve all become attached to a particular project that we’ve
worked on. It may not have been related to software development, but at some point
we’ve all become emotionally invested in a project’s outcome. For many, this may be the
11
project where your reputation is on the line; the one that is too-big-to-fail, and often we let
our emotions get the best of us.
When the pending success or failure of a software project puts an individual’s career on
the line, it’s likely that any related business decisions will be impacted. Stress can cloud
one’s thinking, especially when the stakes are high. A stakeholder may call for a 12 month
schedule in order to impress a customer despite the fact that reports from previous projects
of similar sizes all show a 15 month lifecycle. The stakeholder may dismiss advice from team
members, stating that he has “a feeling” that the team will be able to pull through. In such
situations, following your gut could be extremely detrimental and potentially lead to
project failures.
5. False, but common belief that the proverbial IT silver bullet alone can solve project
throughput or process issues.
When all else fails, a common next approach is a change of strategy. “We must be doing
it all wrong” and “What are our competitors doing?” are common thoughts at this point.
This is when musings of an “IT silver bullet” may start circulating around the office. For
instance, someone may suggest that the organization needs to adopt the latest
bandwagon development approach. While that might be a great direction in which to
take the organization, a decision like this should not be taken lightly. Whichever
development methodology your organization decides to use, it’s only as good as your
implementation. Merely switching development methodologies is not enough to
transform your development operation. Regardless of what you decide, in order to make
the implementation successful, there needs to be buy-in from all sides, individuals need to
be trained, and everyone needs to be held accountable to the same standards.
Otherwise, your development strategy will be roughly equivalent to waiting for the stars to
align perfectly and hoping for a miracle each time you begin a project. If implemented
without thought, this strategy is not only incredibly risky, but also reduces opportunities for
team members to give feedback mid-project.
SUMMARY
In short, software projects fail for a number of reasons. Take a moment to reflect on whether any
of the above reasons may have been the cause of a project failure in your organization. Now
what can you do about it? As an executive leader you can do a lot, but it will require courage
and a backbone to support your development operation. They need to function within a
reasonable set of expectations. Obviously, they will still have to be held accountable, so you will
also need historic performance data as evidence of their capability. Doing this will put you in a
much more powerful position to negotiate with customers and business stakeholders. A successful
outcome is one in which every entity can be successful. In all likelihood this will require some
compromise, but through this process you will be sowing the seeds of success. We will discuss this
further in the coming chapters.
12
References
Brooks, F. P. (1975). The Mythical Man-Month. Addison-Wesley.
13
CHAPTER 4. FACT-BASED DECISIONS
IT STARTS WITH DATA AND ESTABLISHING A BASELINE
_______________________________________
This article originally appeared in the May 20, 2015 online edition of
Project Management Times and is reprinted here with permission.
One of the best ways to assure realistic expectations for a project is to observe the past. Before
getting started with any process improvement endeavors, it is important to understand the big
picture and establish an initial baseline with your projects. To do this, you will want to collect data
on your completed projects.
While it may sound overwhelming to collect data on completed projects, there are actually only
a few pieces of information that your need to collect:
1. Size:
A measure of the amount of functionality or value delivered in a system. It can be
measured in Source Lines of Code (SLOC), Function Points, User Stories, Business or
Technical Requirements, or any other quantifiable artifact of product size.
2. Time:
The duration required to complete the system (i.e. schedule). This is typically measured in
months, weeks or days.
3. Effort:
A measure of the resources expended. This is typically measured in Person Hours or Person
Months of work and is related to staffing as well as cost. The total effort multiplied by the
labor rate is typically used to determine the project cost.
4. Quality:
The reliability of the system is typically measured in the number of errors injected into a
system, or the Mean Time to Defect (MTTD), which measures the amount of elapsed time
that the system can run between the discoveries of new errors.
Once the size, schedule, effort, and quality data have been collected a 5th metric, the
Productivity Index (PI), can be calculated. The PI is a measure that determines the capability and
complexity of a system. It is measured in Index Points ranging from 0.1 to 40 and takes into account
a variety of factors including personnel, skills and methods, process factors and reuse. See
Chapter 6 for more information on PI.
Together, these 5 metrics give a complete view of the project which can be used to assess its
performance. In order to establish a true baseline; a broad reaching sample of historic
performances is preferred (see Figure 4.1). However, it is better to start with something rather than
nothing at all, so begin by creating your baseline with whatever is practical, and then build on
that as you realize success from newly completed projects.
14
Figure 4.1. Build datasets to include a sample of historical data at a variety of project sizes.
THE INTERNAL BASELINE
Once a repository of an organization’s completed projects has been established, custom trend
lines for schedule, effort, and productivity can be calculated to use for creating the baseline.
These trend lines serve as a reference point which can be used for comparing projects within your
organization. Where your projects fall relative to the trend line will indicate better or worse
performance than the average. This will give insight into your organization’s current capabilities.
Figure 4.2. Project baseline and outliers.
15
We can learn a lot about what we do well and what we can improve upon from looking at our
projects relative to the baseline. Examining how far a project deviates from the various trends can
help isolate best- or worst-in-class performances. Project outliers can also provide great insight
into this. Figure 4.2 displays the company project portfolio against their baseline average
productivity. Two of the projects stand out since they fall outside two standard deviations, one
above the average and one below respectively. Further examining the factors that influenced
these projects (i.e. new technology, tools and methods, personnel, or project complexity) will help
shed some light on why these projects performed so well or so poorly. Mimicking what went well
for best-in-class projects and avoiding what didn’t for the worst-in-class projects can help improve
the performance of future projects.
Understanding the baseline for your current development operation can help set reasonable
expectations for future projects by showing what has been accomplished in the past. If the
desired project parameters push the estimate into uncharted territory, you can use the historical
baseline to negotiate for something more reasonable. This baseline can also be used for contract
negotiation, evaluating bids and vendor performance, and navigating customer constraints, thus
allowing you to achieve your cost reduction and process improvement goals. Chapters 5 and 6
discuss this in more detail.
INDUSTRY COMPARISON
While the internal baseline gives good insight into the practices of an individual organization, we
have the market to think about as well. The internal project standings within an organization may
not matter if they’re not competitive with the industry. Therefore, it is important to have an external
comparison for your project data.
QSM regularly collects and maintains project data that is used to create 17 different industry trend
groups, ranging from Business IT systems of various industry sectors and development methods to
engineering and real time systems. Since these industry trends are kept current, they can be a
good reference point if you are new to estimation and do not have enough data from your own
projects.
When using these trend lines to determine performance, it is important to examine the project
holistically. Judging a project’s performance based upon one metric can be very misleading
because of the tradeoffs that occur in software development. For instance, a project may have
been viewed favorably because it was delivered quickly. However, looking beyond the schedule,
a project may not have performed well overall.
16
Figure 4.3. Project delivered 4.7 months earlier than average.
Figure 4.3 shows a project that was delivered 4.7 months ahead of the industry average, an
accomplishment that is often viewed favorably by management because it provides an
advantage over market competition. While speed of delivery may be desirable in some
circumstances, compressing the schedule unnecessarily can cause tradeoffs, which often result
in higher costs and lower quality.
Figure 4.4 shows how the project performed in other areas including productivity, staffing, effort
expended, and the number of defects present during testing. These graphs tell a very different
story.
17
Figure 4.4. Holistic view of project shows that the effort, staffing, and defects are higher than
industry average.
While the productivity of this project was comparable with the industry average, the peak staffing
and effort expended were drastically higher than what is typical for other projects of similar
scopes. This directly translates into higher project costs to pay for the additional labor hours.
Additionally, the number of defects present in the system was also considerably higher than what
is typical for the industry (see Figure 4.4). This is likely a result of the higher staffing. When more
people work on a project, there is a greater chance that miscommunications between team
members could lead to errors being injected into the system. Utilizing more people further divides
the code base, which can result in more defects during integration. The following scenario helps
illustrate the challenges of working with large teams.
Suppose you and another team member were asked to write a book together. The two of you
would have to brainstorm a plot and characters, figure out who would write each chapter, and
make sure that all the chapters flow together. Now suppose that 20 more people were added to
your book-writing team, and each of them was assigned to write one chapter. Each of the
chapters might be really good on its own, but putting them together becomes increasingly
challenging as the number of team members grows. When put together, the chapters may seem
18
fragmented, especially if the authors of the earlier chapters do not communicate well with the
authors of the later chapters.
The editing process introduces challenges of its own. Suppose an author makes a change in
Chapter 2. This change has the potential to affect every chapter thereafter, thus creating a lot
of rework. If the ultimate goal of the project was to have a completed book by the end of the
allotted time, it may have actually been easier and faster for the two-person team to write the
book than the 22-person team.
The challenges of this scenario are similar to what it is like to develop software using large teams.
Often, many large teams struggle with communication between team members, which is why we
tend to see a higher degree of defects than those that use smaller teams. Overall, this example
reinforces the need to examine a project holistically. While excelling in one area may make the
project appear as though it was a top performer, further examination may indicate otherwise. By
viewing the performance using multiple dimensions, one can determine or assess the strategy
employed on a project and determine whether the strategy delivered what had been
anticipated.
Figure 4.5. The Five Star Report.
Five Star Report views, like the one shown in Figure 4.5, can be used to rate the overall
performance of a project or group of projects. For each metric, the project is given a rating of 1-
5 stars with one star being the worst performance and five stars being the best. The Composite
Project Star Rating column on the right gives an overall grade to the project by factoring in the
performance of all the individual metric scores. This value helps determine what effects adjusting
the staffing or schedule will have on the overall project rating. Here it is easy to see when a project
staffs up in order to decrease their schedule. In such a situation, the project would have a Duration
rating of 4 or 5 stars but a staffing and effort rating around 1 or 2 stars. The opposite can also
occur, thus indicating a project that used fewer than the average number of staff and lengthened
the schedule duration. Ideally, project managers should shoot for an average of 3 or more stars
for their projects.
19
SUMMARY
Establishing a baseline will eliminate much of the up-front ambiguity and will provide detailed
recommendations based on quantifiable data that define the range of the organization’s current
capabilities. As various organizations strive for improvement, knowing where they stand relative
to competition is important. A company with a lower than average productivity will have different
goals and implement different process improvement measures than one that is average, or better
than average. Knowing where you stand as an organization can help you determine the most
appropriate measures to take, and decide the best method for moving forward. With this data
you will empower the organization to move toward fact based decision making, thereby
maximizing the possibility of having successful project outcomes.
20
21
CHAPTER 5. THE SOFTWARE PRODUCTION
EQUATION AND THE RAYLEIGH
STAFFING MODEL
_______________________________________
SLIM® is the acronym for Software Lifecycle Management. It is a methodology as well as an
estimation and measurement product suite. SLIM® is based on two fundamental equations that
trace their origins to the seminal research of our founder Larry Putnam Sr. from the 1970’s. We
believe that these equations capture the fundamental time and effort behaviors related to how
people solve complex design problems. These equations are:
1. The Software Production Equation
2. The Rayleigh Equation
The software production equation is composed of four terms, namely: Size, Schedule, Effort and
Productivity. The equation is described below.
Size = Productivity × Time4/3 × Effort1/3
Notice the exponents attached to the time and effort variables. The schedule variable, or time,
has been raised to the 4/3rd power, while the effort variable has been raised to the 1/3rd power.
Without getting too technical, it means that there is a diminishing return of schedule compression
as people are added to a software project. In the most extreme conditions, it means that
spending a lot of money in labor costs can get little to no schedule compression (see Figure 5.1).
Figure 5.1. Utilizing more people requires exponentially more effort.
22
However, what’s nice is that this phenomenon also works in reverse. If a project can afford to
lengthen the schedule, it can be accomplished significantly cheaper by using fewer people (see
Figure 5.2). In today’s economic environment this is a very attractive option.
Figure 5.2. Lengthening the schedule drastically reduces the cost.
The software production equation is simply a quantification of “Brooks’ Law,” which states that
throwing people at a late project only makes it later. Fundamentally the software production
equation models the complexity of human communication and how that manifests itself in
defect creation and rework cycles. As more people are added to a project, human
communication complexity grows exponentially. The communication complexity results in larger
volumes of defects being created, and more rework cycles to fix the problems (see Figure 5.3).
Figure 5.3. Communication complexities increase as people are added to a project.
23
Figure 5.4. The Rayleigh curve occurs because of both dependent and independent tasks.
The Rayleigh equation uses the schedule and effort variables from the software production
equation to produce time-based predictions of effort, staffing, and cost. Software projects
typically begin with fewer resources during Phases 1 and 2. The necessary resources quickly
increase during Phase 3 when more people are needed to build the application due to the arrival
of independent work tasks, and then declines in the second half during testing when more of the
tasks become dependent. After delivery, a few staff remain to assist with fixing latent defects and
maintaining the application (see Figure 5.4).
The Rayleigh equation also produces cumulative curves to provide estimates of total effort and
cost, and rate curves to provide monthly or weekly estimates of staffing, effort or cash flow. These
are all important variables in the estimation, planning and negotiation process.
It is important to note that resource allocation in software development differs from traditional
manufacturing. In software development, the ideal work arrival rate follows the Rayleigh curve,
meaning the amount of available work is not always constant. Manufacturing, on the other
hand, tends to have a more stable amount of work, utilizing the same number of people working
from start to finish (see Figure 5.5).
24
Figure 5.5. Level loaded staffing shape is used in manufacturing.
Traditional project management has attempted to level load projects. However, this strategy is
often unsuccessful because it does not effectively utilize the available resources. It tends to
overstaff projects in the beginning and at the end of the lifecycle, thus wasting resources that
could be available to other projects. By using a Rayleigh curve to model the staffing buildup,
software projects can use their available resources more efficiently, and prevent some staff from
sitting idly at points in the project when there is not enough work to be done.
THE IMPOSSIBLE ZONE
QSM also uses historical data to determine the productivity of an organization and to identify
“The Impossible Zone”. “The Impossible Zone” is a schedule that no project has ever been able
to achieve (see Figure 5.6). It turns out that IT consumers and stakeholders love to demand
project schedules in the impossible zone.
Figure 5.6. ‘The Impossible Zone’ vs. ‘The Impractical Zone.’
25
QSM has over 10,000 historic projects in our repository which can be used to support clients that
have no history but we encourage our clients to collect their own data because it is more
powerful, especially when one needs to negotiate out of the impossible zone.
SUMMARY
The SLIM equations are field proven with over 35 years of practical application on real world
systems. The Software Equation allows one to predict both time and effort alternatives, while the
Rayleigh curve uses these outputs to create a staffing plan. One especially nice characteristic
of these algorithms is that they are applicable, even in the earliest phases of the software
development lifecycle, when little data is available but critical business decisions are often
made.
26
27
CHAPTER 6. SINGLE-RELEASE ESTIMATION
USING THE SOFTWARE PRODUCTION EQUATION AND
THE RAYLEIGH STAFFING MODEL
_______________________________________
So how would one actually do an estimate on a single release using our two equations? We like
to start with the software production equation, where the required inputs are size and
productivity. We rearrange our equations algebraically such that our inputs are on one side of
the equation and we can solve for effort (measured in labor hours) and time (schedule).
𝑆𝑖𝑧𝑒
𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑣𝑖𝑡𝑦
= (𝐸𝑓𝑓𝑜𝑟𝑡)1/3
(𝑇𝑖𝑚𝑒)4/3
PRODUCTIVITY ASSUMPTIONS
The first major input is Productivity, which is measured using the Productivity Index (PI). PI is a
calculated macro measure of the total development environment, and embraces many factors
in software development, including: management influence, development methods, tools,
techniques, skill and experience of the development team, and application type complexity.
It is measured on a normalized scale that ranges from 0.1 – 40. In general, low values are
associated with poor environments and tools, and complex systems. High values, on the other
hand, are typically associated with good environments, tools and management, and well-
understood, straightforward projects. Business IT systems tend to have the highest PI’s because
their projects generally have well understood algorithms. Engineering systems have the next
highest PI’s followed by Real Time systems, because their increased algorithm complexity and
higher quality standards tend to lengthen the project durations.
Selecting the right Productivity Index is critical to producing a good estimate. As system size
increases, productivity typically also increases. Therefore, the PI selected will be size-dependent.
The best way to select your PI is from history. By rearranging the software production equation we
can calculate the actual productivity from past projects. This requires that we input actual
performance data on size produced, schedule months required and hours of effort expended.
𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑣𝑖𝑡𝑦 =
𝑆𝑖𝑧𝑒
(𝐸𝑓𝑓𝑜𝑟𝑡)1/3(𝑇𝑖𝑚𝑒)4/3
Using a database of your historical projects, a productivity trend will be created from the average
PI at each project size. To use this method, simply select the PI that corresponds with your desired
project size. If the project being estimated has 3-5 similar projects, we will have a good idea of
the developer’s average capability. We can then modify this productivity assumption based on
whether the project is expected to be more or less complicated than the historical baseline.
28
If no historical data is available there is another option. Simply use the PI from the QSM Industry
Trend that most closely corresponds with the type of project being built. The Industry Trends are
created from historical project data in the QSM Database. Project data and their corresponding
trends are regularly collected and updated to reflect what is currently typical in the industry.
SIZING ASSUMPTIONS
The other major assumption in estimation is sizing. Estimating the size of a software application
can be challenging. One must translate abstract requirements into a technical size quantity. It’s
like trying to determine the square footage for a new construction project. An architect might
use the number of floors to calculate the square footage of a house. In software development
we use sizing units such as Business Requirements, Agile Epics, Agile Stories, Function Points, or Use
Cases to calculate the number of programming constructs. As the design matures, component
based units like screens, reports, interfaces, scripts, and modules become more common and
can be used to help refine the estimate (see Figure 6.1).
Figure 6.1. Top-down estimation and the cone of uncertainty.
Top-down estimation is especially effective when used in the earlier phases of the software
development lifecycle. At the beginning of the lifecycle, the actual size can be as much as ±4
times the estimated size because there is much more uncertainty. The sizing units available at
this point in the lifecycle often measure the project’s functions (i.e. Business Requirements,
Function Points, Use Cases, etc.) and can vary somewhat. As the project progresses, the
uncertainty decreases until the project is complete. At this point it is easier to count the number
of programming constructs (i.e. Source Lines of Code, Configurations, etc.).
Often, when an initial estimate is needed, there is little sizing information available. Additionally,
the sizing information available may not be in the unit that is familiar to the developers who are
building the application. In such cases, we use a gearing factor to map the functional
29
requirements to the desired programming constructs. The gearing factor is simply the average
number of lines of code or configuration actions required to produce an average component.
It behaves similarly to the Rosetta Stone which translated the same text into three different scripts
(see Figure 6.2). In essence, gearing factors translate the high-level, abstract units, known at the
time of the estimate, into units more familiar to the developers. The gearing factors have been
calculated and validated from our clients’ historical project data.
Figure 6.2. Similar to the Rosetta Stone which translated the same meaning into three different
scripts, gearing factors translate the same functionality into different sizing methodologies.
For further information on sizing please refer to the included infographic.
THE INITIAL ESTIMATE & ALTERNATIVES
Now that you understand the inputs, size and productivity, you are able to begin your estimate.
SLIM takes the assumed inputs and uses them to estimate a range of potential schedule and
effort solutions. There are a finite but large number of schedule and effort combinations for any
set of inputs, so it is important to understand the available options (see Figure 6.3). For example,
30
one could use fewer people and lengthen the schedule, or they could shorten the schedule and
use more people. If you move the solution far enough in either direction you will eventually hit a
roadblock. Shortening the schedule too much could put the project into the impossible zone,
overstretch the budget constraint, or require more people than are available. Moving too far in
the other direction could also cause roadblocks. Lengthening the schedule too much could
cause the project to miss its deadline or go below the minimum staffing constraint.
Figure 6.3. The SLIM estimation process.
Once the project and organizational constraints are imposed they create a practical alternatives
region. Any combination of schedule and staffing within this region would be a reasonable
solution to select. The next step would then be to identify the solution with the highest probability
of success. This optimum solution would then be used as the inputs to the Rayleigh equation to
generate the staffing, effort, cash flow, and cumulative cost plans (see Figure 6.4).
Figure 6.4. Standard estimation solution graphs.
31
DEALING WITH UNCERTAINTY AND RISK
Of course, our knowledge of size and productivity are imperfect since they are assumptions. They
are our best guess given the information available. How can we realistically manage
uncertainty? A Monte Carlo Simulation is a technique that solves the equation thousands of times
using variations of size and productivity to produce a range of potential outcomes based on the
current understanding of the system.
More importantly it allows us to build a probability curve. We have an expected value – our
estimate and the uncertainty distribution. Now the business decision makers need to decide
how much risk they are willing to take while executing this project. If the outcome has the
potential to tarnish the reputation of the corporation, it is probably worthwhile to commit to a
99% probability of reaching the expected value. If the outcome is less critical, perhaps 80% would
be more appropriate (see Figure 6.5).
Figure 6.5. Risk probability charts for schedule and effort.
It is important to deal with uncertainty in a realistic and scientific manner. One particularly
effective method for managing risk is planning the project to the 50% risk solution, but make
commitments to stakeholders at the 99% solution to be very sure of not exceeding your
commitment. This builds in a buffer should the project deviate slightly from the original plan.
32
LEVERAGING ESTIMATES IN BUSINESS DECISIONS – LET THE FUN BEGIN!
The initial estimate rarely satisfies all of the targets and constraints that are imposed on the project.
When this happens, some negotiations need to take place. In such situations, the developers,
business stakeholders and executive management are faced with a few practical options.
1. Relax the schedule. Working with stakeholders to extend the schedule to include the
additional time necessary is typically a good first step. In many cases, the stakeholders
find that it’s perfectly acceptable to live without the system for a short period of time. In
general, this option is the most ideal as it tends to be the least expensive and requires fewer
resources than other options.
2. Reduce capability. If the amount of time needed greatly exceeds the desired deadline,
another strategy is to reduce the capability of the system. An initial release can be
delivered to the stakeholder, giving them the basic functionality at the desired deadline.
A second release can then be integrated later which includes the additional functionality
that the stakeholders initially wanted. While this strategy is more labor intensive and
ultimately requires more resources than building the system in one release (the integration
requires much testing), it also satisfies stakeholders by delivering some working software
while also keeping development costs fairly consistent.
3. Add additional personnel. This strategy involves adding as many people as possible in
order to meet the desired deadline. While commonly utilized in businesses, this strategy is
the least effective of the three, and is almost never a good alternative when the
stakeholder expectations are off by more than three months. Due to the non-linear
relationship between effort and duration, the amount of schedule compression achieved
is minimal compared with all the negative consequences, such as higher costs and
decreased quality.
4. A combination of options 1 – 3.
In such situations, estimates should be used as a negotiation and communication tool. Presenting
the flawed estimate to a stakeholder will help them realize that their expectations are
unreasonable. Sharing alternative solutions and their predicted outcomes will provide options
that facilitate the decision-making process. This strategy can help improve the chances of a
successful project outcome while also making the stakeholders feel more involved in the selection
process.
SUMMARY
Flawed estimation can drive ill-informed business decisions resulting in unrealistic expectations and
disappointing outcomes before the project even begins. It is well known that early in a project
lifecycle, information can be incomplete and undefined with a reduced ability to forecast results.
However, the core value of a good estimate is identifying and contending with that uncertainty
in a legitimate, objective and useful way – rather than speculating and hoping for a positive
outcome. It is not a good reason to forego data and measurement altogether.
33
The prevailing, critical flaw for countless software initiatives is that they are inherently destined to
disappoint because of ill-advised or overly optimistic expectations. Exposing such liabilities before
they cause an adverse, or disastrous, outcome will shed some light on current processes and
prevent future failures. Parametric estimation helps reveal probable scenarios and ongoing
considerations to guide and course-correct once the projects are underway. Those two core
principles are at the heart of the SLIM philosophy: to allow projects not only to begin on solid
ground, but to move, in control, more predictably through the full system development lifecycle.
Inherently non-deterministic estimates, after all, are still guesses. You can reduce uncertainty, but
can never completely eliminate it. How well you contend with that reality can be proportionate
to how well your projects meet their objectives.
34
35
CHAPTER 7. MULTIPLE RELEASE AND
COMPLEX PROGRAM ESTIMATION
_______________________________________
The previous two chapters outlined the basics for creating a single-release estimate. However,
sometimes due to budget or schedule constraints a project may need to be completed in two or
more releases. Additionally, some projects may have some non-development related
components such as training programs, hardware purchases or infrastructure cost, etc. This
chapter will discuss the various strategies for creating multiple-release and complex program
estimates.
There are several reasons why a project may be delivered in multiple releases. Perhaps the project
is larger than the allocated schedule and must be broken into smaller releases so that the
stakeholder is able to use a portion of the software by a certain date. It is also possible that the
project has a series of maintenance updates built into the overall schedule.
Whatever the reason, multiple release estimation can be much more difficult than basic single-
release estimation because of dependencies. Many organizations struggle with estimating one
release, so estimating beyond that can be particularly challenging, especially if very little
information is known.
The strategy here is not terribly different from that of the single-release estimate. If unsure about
the size or productivity inputs for your multi-release projects, examine the historical data and use
the averages. If none are available, use your best judgment. It is always possible to update the
estimates as more information becomes available.
COMPLEX SYSTEM INTEGRATION PROJECT
Once you have the basic estimates for each release, they can be aggregated into one view
using SLIM-MasterPlan. In this format (see Figure 7.1), it is easy to see how each contractor’s
portion and each release fits together with the project’s overall schedule. Additionally, it’s now
possible to assess the number of staff needed on a project at a particular point in time.
36
Figure 7.1. Multi-Release Complex Project View.
SLIM-MasterPlan allows users to view the complex estimate at both the high-level and detailed
levels. In Figure 7.1 the upper left chart shows the high-level total monthly average staff utilized
over the lifecycle of the project. Meanwhile, the lower left chart shows the monthly average staff
of each component in a greater level of detail.
The chart in the upper right shows some blue lines connecting all of the development and
integration components between the first and second release. These lines represent the
dependencies present in this multi-release project, meaning the status of one release depends on
the outcome of a prior release. The dependencies can be set up so that Release 2 begins 20%
before the end of Release 1. If Release 1 has a delayed start, these dependencies update the
start date for Release 2, thus preventing it from starting before there is a solid enough code
foundation from Release 1.
ITERATIVE RELEASE EXAMPLE
Another benefit to using SLIM-MasterPlan is that it has the ability to help manage your product line
release schedule. With this tool, it is easy to determine the resources necessary for executing
complex, multi-release projects.
37
Figure 7.2. Incremental Build Project Estimate.
Figure 7.2 shows a project with several releasable builds. While the staffing initially starts out slowly,
it quickly ramps up as the number of concurrent builds increases. The project reaches its peak
staff of 22 FTE’s in July of 2010. Start dates and their respective dependencies for each release
can be updated in this view to create alternative options if the necessary resources are not
available. Slipping the schedule creates less overlap between the releases, thus reducing the
overall staffing for the multi-release project.
Multiple product lines within an organization can also be modeled in SLIM, resulting in improved
abilities to manage product demand and organizational resources. Suppose that an organization
is planning the development activities of 5 product lines during the next fiscal year that will be
released at staggered intervals. Similar to the multi-release estimate scenario, these individual
estimates can be combined into one view to allow for resource totals to be appropriately
distributed among all the 5 applications. If running too many projects simultaneously requires more
staff than are currently available, this view facilitates deciding which projects need to be
prioritized or delayed. Additionally, this view can also accommodate other tasks, such as
management, training, etc., which may not impact the development schedule, but may have
an effect on the overall budget costs or personnel estimates. By examining the staffing and
schedule for all of the applications simultaneously, one can easily determine the company’s busy
periods, and when there are opportunities to take on more work. The following chapter examines
this concept in more detail.
38
An added benefit to examining an entire portfolio rather than individual projects is that if you want
to make adjustments to the estimates and try out some “what if?” scenarios, you can see how
they’ll impact not just an individual project but the overall schedule, staffing, and cost of the entire
portfolio (see Figure 7.3).
Figure 7.3. The Master What If Feature.
For many projects, scope creep is not only probable, it’s typical. With some projects increasing
their size as much as 15%, creating estimates with multiple sizing scenarios provides beneficial
insight into plausible ranges for staffing, cost, and effort. The sizes of each project can be adjusted
either by the total size or by a percentage increase and will illustrate how these adjustments could
affect the entire product line. Similar “what-if” scenarios can be run by adjusting the productivity
and staffing as well. This type of insight can be particularly useful when it comes to complex
decision-making. By understanding the impact that changes to an individual application can
have on an entire product line, more informed decisions and effective project planning can result.
SUMMARY
To summarize, multi-release estimation builds on the skills acquired from single-release estimation
and adds a degree of complexity. This method provides a more holistic view of your project
portfolio and allows estimators to gain greater insight into how their individual projects impact the
overall software development practices. The next chapter will focus on how users can utilize this
information to make informed decisions regarding their development capacity and demand.
39
CHAPTER 8. CAPACITY PLANNING AND
DEMAND MANAGEMENT
_______________________________________
This article originally appeared in the March 20, 2015 online edition of
Software Magazine and is reprinted here with permission.
If you think about it, enterprise application capacity planning can be a difficult juggling act. On
one side of the equation you have business demand. The business exists in a fluid, competitive
environment. With stakeholders hoping to gain an edge over their competitors, they are
constantly looking to innovation and technology to help them improve business performance and
increase their profitability. The IT organization stands on the other side of the equation, and is
responsible for satisfying the demands of the stakeholders. Their capacity is limited by their
facilities, the volume of developers and their specific skills, and the infrastructure that is in place to
enhance their productivity. This leaves the business and technology executives in the unenviable
position of trying to balance the demand for IT development with their current capacity levels.
Figure 8.1. Conflicting demands on executive management.
Moreover, in a large enterprise there are thousands of projects moving through the development
pipeline, making the balancing process that much more difficult. In order to address these
complexities many organizations have implemented enterprise Project and Portfolio
40
Management (PPM) systems. These PPM systems are great for allocating known resources against
approved projects, and aggregating the data into a portfolio to give a current picture of how the
IT capacity satisfies business demands.
In order for the capacity planning process to work, it is important to have a robust demand
estimation capability. This is a discipline that has proven to be difficult for many organizations.
Why is it so difficult? There are many reasons, but two stand out.
The first is that most organizations only estimate an aggregate number of hours by skill category
and have no estimate of the schedule or how the skills are applied over time on the project. The
most common practice today is based on using a detailed task-based estimation method.
Imagine a spreadsheet with a generic list of hundreds of tasks that typically are performed on any
given project. It is the estimator’s job to review the requirements and estimate the number of
labor hours required for each task. The task estimates are rolled up into a total labor estimate
which is then allocated out to labor categories. The problem is that this method does not provide
details for how the skilled labor categories are required to ramp on or taper off the project. This is
an important component of capacity planning process. So using today’s most common
estimation practices, one ends up with a project estimate that looks something like Figure 8.2:
Unfortunately, this method also does not
include a schedule. The schedule is usually
decided arbitrarily by the stakeholders and
often does not align with the estimated
effort. QSM research shows that unrealistic
schedule expectations are the number one
reason why projects fail. This is clearly a big
deficiency. The second issue is that task-
based estimation is not well matched for the
information that is available during the early
stages of a project when the estimates and business decisions are typically made. The initial
estimates are typically performed when there are only a few pages of business requirements. This
clearly is not sufficient information to do a detailed task-level estimate. Moreover, doing a task-
based estimate requires a lot of time and energy, so it would not be appropriate if numerous
alternative scenarios are requested.
TOP-DOWN ESTIMATION IS VERY EFFECTIVE IN THE EARLY STAGES OF THE PROJECT LIFECYCLE
Top-down parametric estimation is particularly effective in the early stages of the lifecycle. It
utilizes gross sizing and productivity assumptions to produce schedule and effort estimates. If the
estimates do not match expectations, top-down estimation tools can quickly evaluate what can
be accomplished with the available resources or determine how much additional time and effort
will be required to achieve the business objectives (see Figure 8.3).
Figure 8.2. Typical bottoms-up estimate without project
schedule.
41
Figure 8.3. Desired schedule and cost compared against historical data and benchmark trends.
The beauty of the top-down method is that it uses crude size measures like Business Requirements,
Agile Epics, Use Cases or Function Points as a direct input. Coincidentally, these are the design
artifacts that are most likely to be available during the early stages of estimation.
With this basic information, top-down methods can quickly identify both high risk and conservative
expectations, and if appropriate, suggest more reasonable alternatives. Let’s take a look at a
typical estimation situation early in the lifecycle. Suppose, for example, that a business has
identified some new capabilities that they would like to have implemented. They have a 5 page
document that describes 19 business requirements or capabilities. They would like to have the
capabilities available within 3 months and have a budget of $250,000. Figure 8.4 shows their
desired outcome.
42
Figure 8.4. Risky desired outcome compared with the recommended, more realistic estimate.
When compared to historical data, the desired outcome is determined to be “Risky” and an
alternative estimate of 5.7 months and $571,000 is recommended. Now a negotiation between
the stakeholders and the IT department can take place to explore more viable options. For
example, 11 business requirements could be completed in 3 months using the previously outlined
resources, or all 19 requirements could be completed in 4 months using a team of 12 people and
a budget of $1.8 million. The main purpose for estimating at this stage of the demand
management process is to smoke out grossly unrealistic expectations and negotiate realistic
options in order for all parties to be winners in this development.
TURNING HOURS INTO SKILLS AND STAFFING REQUIREMENTS
The most “common practice” labor estimates just aren’t good enough to support capacity
planning. What is really needed is an estimate of how the various skills will ramp up and taper off
over the course of the project (see Figure 8.5).
43
Figure 8.5. Staffing skill categories by month.
With this information, PPM systems can match individuals with their respective skills to the project’s
needs at the time they are required and free them up when their work is done. It is important to
recognize that one size does not fit all projects. For a large enterprise there might be several skill
profiles or templates to support the different project types and methodologies. Typical
methodology and project examples today include Agile, Traditional Waterfall, Package
Implementation, Infrastructure, etc. The key point is to have just enough flexibility to provide
adequate coverage but not so much that the organization becomes a slave to template creation
and maintenance.
Configuration within the SLIM tool is flexible enough to add, change, and delete labor categories
and rates. It is also intuitive enough to allocate the buildup and ramp down of skill categories
over time (see Figure 8.6).
44
Figure 8.6. Configuring skill categories.
With a method to produce estimated skill allocation over time, it is possible to incorporate realistic
demand into the planning process and match demand with the available capacity. The SLIM
estimation tool has a PPM integration framework which allows SLIM to integrate with any PPM
program (see Figure 8.7).
45
Figure 8.7. SLIM integration with PPM tools.
The PPM integration allows SLIM to assess and adjust the planned resources and/ or start dates to
projects already present in the PPM system or to those prior to entry. This feature can be
particularly useful for projects that require further evaluation and validation.
MATCH DEMAND TO CAPACITY
Now we have a way to realistically estimate schedule, effort, cost and skill requirements over the
duration of a project, and can feed that information into a PPM system. By implementing this
discipline throughout the enterprise, it is possible to evaluate how demand matches capacity and
determine whether they are out of sync. If we discover that they are out of alignment, we can
evaluate practical options for matching demand and capacity.
Let’s use an example to illustrate the process:
Our example enterprise has 3 different data centers: one is located in the U.S., while the other
two are in India and Ireland. The total capacity for these three centers is limited to 250 IT
developers, and there are currently 35 projects that have been approved for production (see
Figure 8.8).
46
Figure 8.8. Peak staffing over time for individual projects and aggregated by development center.
Each of these projects is in a different stage of production, with some in the early planning stages,
others beginning coding, and some that are approaching delivery. At any point in time, it is fairly
typical to have a portfolio with projects at all of these production stages. Additionally, it is
common for a portfolio to have a wide range of project scopes, and team sizes. Each project
can be estimated individually, and they can be rolled up to show the aggregate data at either
the data center level or the enterprise level to help determine the capacity and demand levels.
For simplicity sake, we’ll examine at the enterprise level in this example. When the data is
aggregated at this level, we notice that for a 9 month period, between August 2014 and May
2015, the demand for developers exceeds capacity by 65 Full Time Equivalents (FTEs), see Figure
8.9.
47
Figure 8.9. Demand exceeded capacity by 65 people for 9 months.
When the demand for developers exceeds its capacity there are usually 3 options:
1. Eliminate projects (usually not a practical option since there is a definitive business need),
2. Push back the start dates on projects that have not yet begun, or
3. Make a select staffing reduction on projects in-progress or those yet to begin and relax
their respective delivery dates.
48
Figure 8.10. Project start date delayed.
In this example case, we chose option 2 and pushed back the start dates. In a relatively short
period of time we were able to optimize the staffing to meet the capacity limit of 250 people. The
resulting impact this had on the eight projects was a delay that lasted anywhere from 2 to 8
months (see Figure 8.10).
If we want to assess the skill requirements and match those to our pool of available resources, we
need to aggregate the skill categories to match that to our skill capacity.
49
Figure 8.11. Staffing resource profile.
Figure 8.11 gives a graphic depiction of the necessary resources at the enterprise level. It shows
the aggregated demand for each of the skill sets at various times within a 28 month period. This
information is useful to have because it lays out what you will need to successfully complete the
approved projects and compare them with the resources currently available. If there are
imbalances between supply and demand, you now know what areas need to be supported and
can take actions such as hiring or training additional employees to help fill the void. By having this
kind of information available and understanding its significance, great progress in capacity
planning can be realized by the IT organization.
SUMMARY
Capacity planning and demand management go hand in hand. To manage them effectively,
one needs to be able to:
1. Realistically forecast demand early in the lifecycle,
2. Negotiate functionality, schedule and effort with business stakeholders when their
expectations are unrealistic,
3. Have the ability to forecast effort by skill category, by month, or by week, and feed this
information to PPM systems, and
4. Be in a position to perform quick what-if analyses on the portfolio when demand exceeds
capacity.
If you take action to address these issues, then you can have a best-in-class IT capacity planning
solution for the enterprise.
50
51
CHAPTER 9. TRACKING, FORECASTING,
EXECUTION, AND POST MORTEM
_______________________________________
The previous chapters discussed the best practices involved in creating estimates. While creating
estimates is an important and necessary skill in improving productivity; that is only half the battle.
The second half is tracking actual performance against the estimate and reforecasting when
significant changes occur.
TRACKING
Suppose that after much consideration, an organization puts forth an estimate with the intention
of carrying it out as a project plan. At this point, many estimators would believe that they are
done. However, in order to maximize the benefits of the estimate, it will be necessary to track the
project’s progress through completion. While this may seem like a tedious process, project
tracking allows for organizations to gain the greatest insight into their software development
lifecycles.
To do this, estimators will want to collect data on the current actuals for the following metrics at
regular intervals:
 Cumulative Size Produced – this metric is customizable and can include but is not limited
to Source Lines of Code, Agile Stories, Screens, etc.
 Monthly Effort – the Person Months or Person Hours expended thus far
 Staff – the number of Full Time Equivalents currently billing time to the project
 Defects – how many errors were discovered
Depending on the length of the project’s schedule, it’s recommended to collect data on the
actuals at the end of each month, or for shorter projects at the end of each week. This data can
then be compared against the original estimate to track the project’s in-flight progress, as well as
any deviations from the estimate. Utilizing these practices can increase accountability within the
organization because current statuses are regularly maintained.
Additionally, tracking these various metrics over time can help identify areas for improvement
within an organization. For example, if the project’s actual data match the projected values from
the original estimate in staffing and cumulative effort but not cumulative size, this observation
could indicate a couple of potential scenarios (see Figure 9.1). One possible explanation might
be that the organization has staffed the project with the correct number of people at a given
point in time, but has not appropriately accounted for the skills necessary to complete the project.
An excessive number of management personnel may have been staffed for the project, resulting
in a decreased staffing allotment for the developers. With fewer developers staffed or those
lacking the skills needed for the project, producing code at the estimated rate would be
impossible and deviations from the original estimate would be expected.
52
Another possible explanation for the decreased code production is that the actual productivity
of the organizations is in fact lower than originally estimated. There are a number of explanations
for why this occurs. Introducing new tools, development methodologies, or team members
impacts the development environment and can require additional time for developers to perform
at the previous productivity level. The next section describes some potential solutions if this
happens to your project.
Figure 9.1. Tracking actuals against the planned values: Consumption vs. construction.
FORECASTING AND EXECUTION
Life is rarely predictable, and that holds true in software estimation as well. Even the best estimates
cannot anticipate some of the curveballs that life throws at them. For instance, if several team
members are pulled off the project and temporarily reassigned to another, it is unlikely that the
project will progress as originally planned. In such situations, the best suggestion would be to
reforecast the estimate.
Similar to a GPS, SLIM is able to recalculate a new trajectory, or roadmap, if the project gets off
track. It factors in what has already been done and re-estimates a new productivity based on
the actual values entered. If a project drifts so far off course that the original plan is no longer
feasible, a new plan can be implemented and briefed to stakeholders so that everyone has similar
expectations (see Figure 9.2).
In this chart we see the project’s plan in blue compared with the actual data collected in monthly
intervals in red. In January, the amount of code produced was slightly below the quota outlined
in the plan, yet the cumulative effort expended was above the allotted amount. Additionally,
53
they were finding more defects in the system than initially predicted. Since the project has begun
to get off track from the original estimate, the wise choice would be to reforecast the project plan.
The new forecast is displayed in white and shows that based on the current trajectory, the project
should end about 2.5 months later and require 6,600 more person hours of effort than the original
plan. Knowing this information early can allow time for orderly changes while still underway.
Figure 9.2. Forecasting chart.
One of the greatest benefits of this technique is that it provides transparency into the
development process by showing the project’s progress at regular intervals. Development teams
know how much functionality will have to be delivered at each interval, and can plan
accordingly. If a project begins to drift off course, it’s much easier to determine this from the start
and take measures to mitigate risk early. Additionally, as new data is added, SLIM reforecasts the
plan like a GPS would recalculate the roadmap. If the new data shows improvements, it will be
reflected in the forecast going forward, thus creating a refined learning system. By having this
kind of insight and level of detail up front can dramatically improve accountability across the
organization.
POST MORTEM
Once a project has reached completion, it’s very easy to move onto the next without a second
thought. Regardless of whether the project went really well and the momentum is continuing or
if the project was so utterly painful that the wounds are still fresh, a post mortem assessment is
SEI Core Metrics
Schedule
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31
Oct
'02
Dec Feb
'03
Apr Jun Aug Oct Dec Feb
'04
Apr Jun Aug Oct Dec Feb
'05
Apr Jun
Requiremts & D...
Construct and T...
Test & Evaluate
Phases
87654321
321 87654
Milestones
1 - PDR
2 - INC_1
3 - INC_2
4 - INC_3
5 - ST
6 - TRR
7 - FAT
8 - 99R
Milestones
1 - PDR
2 - INC_1
3 - INC_2
4 - INC_3
5 - ST
6 - TRR
7 - FAT
8 - 99R
Cum Effort C&T
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31
Oct
'02
Dec Feb
'03
Apr Jun Aug Oct Dec Feb
'04
Apr Jun Aug Oct Dec Feb
'05
Apr Jun
0
10
20
30
40
PHR(thousands)
87654321
321
Defects Found Moderate
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31
Oct
'02
Dec Feb
'03
Apr Jun Aug Oct Dec Feb
'04
Apr Jun Aug Oct Dec Feb
'05
Apr Jun
0
5
10
15
20
25
30
35
Defects
87654321
321
Cum Eff SLOC
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31
Oct
'02
Dec Feb
'03
Apr Jun Aug Oct Dec Feb
'04
Apr Jun Aug Oct Dec Feb
'05
Apr Jun
0
10
20
30
40
50
60
SLOC(thousands)
87654321
321
Current Plan Actuals Current Forecast Project: TechPro 5.0
54
always a valuable exercise. Post mortems provide opportunities for teams to discuss what went
well and what areas could be improved. Additionally, post mortems allow teams to reconvene
at the end of the project to collect the final data for the project repository. This newly completed
project can be entered into SLIM along with the rest of the completed project data. A new set of
custom trends can then be created using the most recently added historical data, which can be
used for more accurate estimates in the future. You will find that over time, this process of
collecting historical data, updating trends, and using those trends to estimate future projects
allows the estimation process to come full circle, refining itself each time.
SUMMARY
While creating estimates is a great way to start a project off on the right foot, using parametric
methods to track and monitor your project’s progress provides even greater insight into the
development of your project. Knowing the status of a project inflight and having the ability to
share that with developers and stakeholders, when most can merely guess, is extremely beneficial
and puts project managers in a much more powerful position. The project can be tracked all the
way through completion, at which point, a post mortem assessment can be done to collect data
and further refine the estimation process. Using this model creates a refinement cycle whereby
collecting accurate data leads to creating more accurate estimates.
55
CHAPTER 10. UNDERSTANDING QUALITY
AND RELIABILITY
_______________________________________
One of the most overlooked but important areas of software estimation, measurement, and
assessment is quality. It often is not considered or even discussed during the early planning stages
of a development project, but it’s almost always the ultimate criteria for when a product is ready
to ship or deploy. Therefore, it needs to be part of the expectation-setting conversation from the
outset of the project.
So how can we talk about quality? It can be measured a number of ways but two in particular
give excellent insights into the stability of the product. They are:
1. The number of errors discovered in the system during testing, and
2. The Mean Time to Defect (MTTD), or the amount of time between errors discovered prior
to and after delivery.
The reason we like these two measures is that they both relate to product stability, a critical issue
as the release date approaches. They are objective, measurable, and can usually be derived
from most organizations’ current quality monitoring systems without too much trouble.
Generally, having fewer errors and a higher MTTD is associated with better overall quality. While
having the highest quality possible may not always be a primary concern for stakeholders, the
reliability of the project must meet some minimum standards before it can be shipped to the
customer. This means that at delivery, the project is about 95% defect free, or the application can
run for about 1 day without crashing. Another good rule of thumb is that the software typically
will be of minimum acceptable reliability when testers are finding fewer than 20 errors per month.
In other words, the product will run about an 8 hour work day. Of course this rule of thumb is mostly
applicable for commercial IT applications. Industrial and military embedded applications require
a higher degree of reliability.
THE RAYLEIGH DEFECT MODEL
The QSM defect estimation approach uses the Rayleigh function to forecast the discovery rate of
defects as a function of time throughout the software development process. The Rayleigh
function was discovered by the English physicist Lord Rayleigh in his work related to scattering of
acoustic and electro‐magnetic waves. We have found in our research that a Rayleigh reliability
model closely approximates the actual profile of defect data collected from software
development efforts.
In the QSM reliability modeling approach, the Rayleigh equation is used to predict the number of
defects discovered over time. The QSM application of the Rayleigh model has been formulated
to cover the duration of time from the High Level Design Review (HLDR ‐ High Level Design is
56
Complete) until 99.9% of all the defects have been discovered. A sample Rayleigh defect
estimate is shown in Figure 10.1.
Figure 10.1. Sample Rayleigh defect estimate.
Note that the peak of the curve occurs early in the build and test phase. This means that a large
number of the total defects are created and discovered early in the project. These defects are
mostly requirements, design and unit coding defects. If they are not found they will surface later
in the project resulting in extensive rework.
Milestone 10 is declared to be the point in time when 99.9% of the defects have been discovered.
Less than 5% of the organizations that QSM has worked with record defect data during the
detailed design phase. Industry researchers claim that it can cost 3‐10 times more to fix a defect
found during system test rather than during design or coding, so one could make a compelling
case to start measuring and taking action earlier in the process.
Simple extensions of the model provide other useful information. For example, defect priority
classes can be specified as percentages of the total curve. This allows the model to predict
defects by severity categories over time. This is illustrated in Figure 10.2.
57
Figure 10.2. Rayleigh defect model broken out by defect severity class.
A defect estimate could be thought of as a plan. For a particular set of conditions (size,
complexity, efficiency, staffing, etc.) a planned curve could be generated. A manager could
use this as a rough gauge of performance to see if his project is performing consistently with the
plan and by association with comparable historic projects. If there are significant deviations, this
would probably cause the manager to investigate and, if justified, take remedial action.
Figure 10.3 shows how one can use the defect discovery estimate to track and compare actuals.
Obviously, the actual measurements are a little noisier than the estimate but they track the
general pattern nicely and give confidence that the error discovery rate will be below 20 per
month, our minimum acceptable delivery criteria, at the schedule end of the project.
Defect Rate
Quick Estimate Wizard Solution
6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Jul
'15
Aug Sep Oct Nov Dec Jan
'16
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
0
25
50
75
100
125
150
DefectRate
1098765432
Cosmetic
Tolerable
Moderate
Serious
Critical
Project: Single Release Estimate
58
Figure 10.3. Defect discovery rate plan with actuals plotted.
DEFECT MODEL DRIVERS
There are specific inputs that determine the duration and magnitude of the Rayleigh defect
model. The inputs enable the model to provide an accurate forecast for a given situation. There
are three macro parameters that the QSM model uses:
 Size (new and modified)
 Productivity Index
 Peak Staffing
These driving factors impact the defect behavior patterns that we see with regards to software
projects.
Size
Historically, we have seen that as project size increases, so do the number of defects present in
the system (see Figure 10.4). Stated simply, building a larger project provides more opportunities
for developers to inject defects into the system, and also requires more testing to be completed.
This rate of defect increase is close to linear. Similarly, as size increases the MTTD decreases. This
is due to the increased number of errors in the system. Larger projects tend to have lower
reliabilities because there is less time between defects. These trends are typical for the industry.
Total Defects Found
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Oct
'02
Nov Dec Jan
'03
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
'04
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
'05
Feb Mar Apr May Jun
0
20
40
60
80
100
120
140
Defects
87654321
321
Current Plan Actuals Project: TechPro 5.0
59
Figure 10.4. As size increases so do the number of defects.
Productivity Index
Productivity also tends to have a great impact in the overall quality of a system. Historic data has
shown that the number of defects discovered exponentially decreases as the Productivity Index
increases. Figure 10.5 shows the cumulative number of defects discovered for the same sized
software application using two different PI’s (17 and 21 respectively). The project with the higher
PI not only delivers the application 9 months faster, but also discovers about 360 fewer errors in
total. It makes sense that when development teams improve, they tend to make fewer errors to
begin with, thus decreasing the number of errors found during testing. Operating at a higher
productivity level can drastically increase software quality.
60
Figure 10.5. Comparison of defects produced for the same size system using different PI’s.
Staffing
The size of the development team also can impact the quality of a system. As discussed previously
in Chapters 3 and 4, using larger teams produces more errors than using smaller teams. As shown
in Figure 10.6, when comparing a large team (red) with a small team (grey) at the same project
sizes, the small teams produce between 50-65 fewer errors than large teams at all project sizes.
Additionally, they paid little, if any, schedule penalty and used significantly less effort. This finding
can be especially useful when looking to identify areas of waste within an organization, because
it shows that adding resources to a project does not always improve its quality.
61
Figure 10.6. Small teams produce fewer errors than large teams at all project sizes.
SUMMARY
To conclude this section, software reliability and quality are two areas that should be addressed
in the expectation setting and project negotiation stages of a project. As a leader there are
several strategies that you can use to improve reliability. Keep the developed size as small as
possible, use smaller teams of people, and make regular investments in your environment to
improve the efficiency of your development shop. All of these actions will pay reliability and
quality dividends.
62
63
CHAPTER 11. WHAT DOES IT TAKE TO
SUCCESSFULLY IMPLEMENT
ESTIMATION?
_______________________________________
It doesn’t take long for an individual or small team to achieve quick wins implementing the
estimation best practices outlined in the previous chapters. However, that initial success is always
at risk of becoming derailed when a key individual leaves the organization, unless those best
practices are institutionalized (i.e. fully embraced by the organizational culture, supported by a
majority of stakeholders, and incorporated into the organizational process). So what needs to
happen if you want to actually implement an effective estimation and measurement function?
Well it is going to take some determination and hard work but the rewards are well worth it!
An “Estimation Center of Excellence” (ECoE) is an excellent way to operationalize the concepts
that we have been discussing to a structure that can support the needs of an enterprise. The
ECoE encompasses aspects of People, Process, and Tools such that all three of these areas are
incorporated into the planning and execution process.
The most common organizational structures for an ECoE include centralized, distributed, and a
hybrid “spoke and hub,” but the method selected really depends on the organization. It’s
important to find a structure that will satisfy your culture and business decision making needs.
Sometimes the function is housed in an existing part of the operation, like a project management
office PMO, while others prefer that it be its own entity.
Here are some implementation issues that need to be considered:
1. How will this fit into our organization?
2. What is the best structure to support our needs and decision making?
3. What people will be needed and what skills do they need to possess?
4. What tooling will be required?
5. How long will it take to stand up the operation?
6. What ROI can be expected from this endeavor?
7. How do you overcome the resistance to change?
We have found that best implementations usually follow a 4 stage process. These four stages are:
1. Stage I – Requirement Definition
2. Stage II – Design and Implement
3. Stage III – Launch and Pilot Operation
4. Stage IV – Transition to Full Scale Operation
During each stage, people, process, and tooling activities are addressed. Here is a brief
description of what takes place during each of the implementation stages.
64
STAGE I – REQUIREMENTS DEFINITION
During this stage, one identifies the major pain points and goals of the organization and builds a
business case for addressing issues. A charter is developed to identify the major stakeholders in
the ECoE implementation and the ground rules that they will follow. The current estimation process
maturity is assessed to establish a baseline and starting point of departure. From there, the tooling
as well as the various skill sets of the ECoE staff are identified and advertised. Finally, a change
management strategy is designed.
STAGE II – EcoE DESIGN AND DEVELOPMENT
During this stage, the ECoE staff are hired and trained. Detailed business processes are defined
and service level agreements are established. Next, the estimation tooling is customized and
templates are created to support the estimation process. Additionally, a historical data repository
is set up to support estimation and business case ROI analysis. Several pilot estimates will be
performed to gain experience and fine tune the estimation methods. This stage will include
regular information briefings to individuals throughout the organization to garner support and
demonstrate the value of this solution.
STAGE III – EcoE LAUNCH AND PILOT OPERATION
During this phase the ECoE becomes operational. ECoE staff are mentored as they gain
experience, working towards a formal estimation expert certification. The tooling templates and
processes are adjusted as necessary based on feedback from operation use. Training sessions
are conducted for new users, as required, if a distributed or hub and spoke model are
implemented. Sharing circles are also implemented to share knowledge and practical
experience throughout the estimation community. Case studies and other findings will continue
to be briefed, thus showing the value of the ECoE.
STAGE IV – FULL OPERATION
The ECoE is fully operational. The tools and processes will continue to be improved based on
newly completed projects and operational experience. Additional staff training and certification
are conducted on an as-needed basis.
In our experience it can take as little as 6 months or up to 15 months to complete the first three
stages depending on size and complexity of the organization. Figure 11.1 is a good example of
an ECoE implementation in a large organization.
65
Figure 11.1. Example Estimation Center of Excellence Implementation
ECoE FOCUS AREAS
The ECoE can have different areas of focus based on the needs of the organization. They are:
1. The Internal Development ECoE
2. The Acquisition and Vendor Management ECoE
3. The Oversight ECoE
The Internal ECoE’s primary focus is on estimation, stakeholder negotiation, risk assessment,
resource management, capacity planning, and business decision support. The Acquisition and
Vendor Management ECoE focuses on ensuring successful procurements of outsourced projects.
It does this by providing a framework for establishing a realistic “should cost” analysis and method
for quantifying vendor bids. This can then be used to select vendors that put forth realistic
proposals, and quantitatively monitor their execution so that there are no surprises along the way.
The Oversight ECoE typically operates at the portfolio level and provides executive level oversight.
It provides independent reviews at key points during the development lifecycle process, to ensure
that the project has a realistic estimate and is proceeding under control. Often special emphasis
is placed on high-risk and/ or high-visibility projects.
66
RETURN ON INVESTMENT
Your return will depend on the size of your organization, and the size and volume of projects that
are subject to ECoE analysis. Below is a chart that shows what others have achieved.
Figure 11.2. Return on Investment for using SLIM.
SUMMARY
Adopting an Estimation Center of Excellence is a strategic, long-term investment rather than a
quick fix. Leveraging defensible metrics and greater quantitative analysis will help your
organization gain more insight into its own productivity, both internal and external, as well as its
estimation maturity while better positioning it to plan, prioritize, track and empirically assess the
interrelated variables of project size, cost, quality, and duration related to these projects. Before
making drastic changes such as those needed to properly implement a similar change in
development practices, invest time at all levels of the organization to fully understand the task at
hand and assess how long it will take to reap the benefits and achieve the expected return on
investment. Making deliberate, fully-informed decisions will ultimately lead to better outcomes.
67
CHAPTER 12. SUMMING IT UP
_______________________________________
If you’ve stayed with us this far, you’ll know that there is a lot to be gained from incorporating top-
down estimation into your current software development practices. Before leaving you, we
wanted to recap some of our main points.
In any type of project, software development or otherwise, accountability is essential for success.
By establishing some expectations up front, the developers will know what they are responsible for
and the stakeholders will know when the final product should be ready. However, without
quantitative methods to measure productivity this task is much easier said than done. A good
estimate will provide the framework necessary for establishing expectations and keeping
everyone accountable.
To get to that point, it’s critical to measure not
just the consumption of the project (i.e. how
much money has been spent), but also the
construction (i.e. how much functionality has
been built). Monitoring and tracking both of
these together will provide a holistic view of the
project’s progress and can allow teams to
adapt to changes in-flight, should they be
necessary.
Understanding how the two SLIM algorithms
function is key to making business decisions
about your projects. The law of tradeoffs states
that there are numerous ways that a project
can be accomplished by adjusting the
schedule and the effort. Estimators can create
several what-if scenarios which can be
presented as options to stakeholders and
decision-makers. In essence, they become a
vital negotiation tool because they back your
proposals with quantitative data. Additionally,
presenting multiple options to stakeholders
inadvertently solicits their participation in the decision-making process, thus shaping better project
outcomes overall.
One of the greatest benefits of top-down estimation is that you can start creating more accurate
estimates right away and the results are immediate. As you continue to estimate over time, the
benefits compound even more (see Figure 12.1). Improving resource and demand management
can free up staffing resources for other projects, thus increasing productivity and creating a higher
utilization of staff.
Figure 12.1. The benefits of top-down software
estimation.
QSM Executive Primer Estimation and demand Management
QSM Executive Primer Estimation and demand Management

Weitere ähnliche Inhalte

Was ist angesagt?

Software development project management
Software development project managementSoftware development project management
Software development project managementRoni Banerjee
 
The communications plan with notes
The communications plan with notesThe communications plan with notes
The communications plan with noteskenmeuser
 
Top Ten Obstacles To Project Success
Top Ten Obstacles To Project SuccessTop Ten Obstacles To Project Success
Top Ten Obstacles To Project SuccessLou Gasco
 
We need to talk about tech debt
We need to talk about tech debtWe need to talk about tech debt
We need to talk about tech debtMatthew Whetton
 

Was ist angesagt? (6)

Software development project management
Software development project managementSoftware development project management
Software development project management
 
Untitled
UntitledUntitled
Untitled
 
The communications plan with notes
The communications plan with notesThe communications plan with notes
The communications plan with notes
 
Why it project fail
Why it project failWhy it project fail
Why it project fail
 
Top Ten Obstacles To Project Success
Top Ten Obstacles To Project SuccessTop Ten Obstacles To Project Success
Top Ten Obstacles To Project Success
 
We need to talk about tech debt
We need to talk about tech debtWe need to talk about tech debt
We need to talk about tech debt
 

Ähnlich wie QSM Executive Primer Estimation and demand Management

Breaking Through the Roadblocks of a New ELM Implementation eBook
Breaking Through the Roadblocks of a New ELM Implementation eBookBreaking Through the Roadblocks of a New ELM Implementation eBook
Breaking Through the Roadblocks of a New ELM Implementation eBookJason Emanis
 
Agile ERP_ Continuous Improvements Through Rapid, Incremental Implementations...
Agile ERP_ Continuous Improvements Through Rapid, Incremental Implementations...Agile ERP_ Continuous Improvements Through Rapid, Incremental Implementations...
Agile ERP_ Continuous Improvements Through Rapid, Incremental Implementations...Steven Parker
 
Immutable Principles Of Project Management (V7 Final Cmu)
Immutable Principles Of Project Management (V7 Final Cmu)Immutable Principles Of Project Management (V7 Final Cmu)
Immutable Principles Of Project Management (V7 Final Cmu)Glen Alleman
 
Scalable light weight processes
Scalable light weight processesScalable light weight processes
Scalable light weight processesGlen Alleman
 
A Pattern-Language-for-software-Development
A Pattern-Language-for-software-DevelopmentA Pattern-Language-for-software-Development
A Pattern-Language-for-software-DevelopmentShiraz316
 
The Business value of agile development
The Business value of agile developmentThe Business value of agile development
The Business value of agile developmentPhavadol Srisarnsakul
 
Software For Software Development Life Cycle
Software For Software Development Life CycleSoftware For Software Development Life Cycle
Software For Software Development Life CycleChristina Padilla
 
54 C o m m u n i C at i o n s o F t h e a C m j u.docx
54    C o m m u n i C at i o n s  o F  t h e  a C m       j u.docx54    C o m m u n i C at i o n s  o F  t h e  a C m       j u.docx
54 C o m m u n i C at i o n s o F t h e a C m j u.docxevonnehoggarth79783
 
SOFTWARE COST ESTIMATION USING FUZZY NUMBER AND PARTICLE SWARM OPTIMIZATION
SOFTWARE COST ESTIMATION USING FUZZY NUMBER AND PARTICLE SWARM OPTIMIZATIONSOFTWARE COST ESTIMATION USING FUZZY NUMBER AND PARTICLE SWARM OPTIMIZATION
SOFTWARE COST ESTIMATION USING FUZZY NUMBER AND PARTICLE SWARM OPTIMIZATIONIJCI JOURNAL
 
Defect effort prediction models in software
Defect effort prediction models in softwareDefect effort prediction models in software
Defect effort prediction models in softwareIAEME Publication
 
The Five Levels of Requirements Management Maturity
The Five Levels of Requirements Management MaturityThe Five Levels of Requirements Management Maturity
The Five Levels of Requirements Management MaturityIBM Rational software
 
Releasing Software Without Testing Team
Releasing Software Without Testing TeamReleasing Software Without Testing Team
Releasing Software Without Testing TeamAkshay Mathur
 
Quality Assurance, Testing, And Implementation
Quality Assurance, Testing, And ImplementationQuality Assurance, Testing, And Implementation
Quality Assurance, Testing, And ImplementationKristen Wilson
 
Putting-MANAGEMENT-into-Your-Requirements-Management_Dec2005
Putting-MANAGEMENT-into-Your-Requirements-Management_Dec2005Putting-MANAGEMENT-into-Your-Requirements-Management_Dec2005
Putting-MANAGEMENT-into-Your-Requirements-Management_Dec2005pbaxter
 
hroughout the fifty-odd years of software development, the ind.docx
hroughout the fifty-odd years of software development, the ind.docxhroughout the fifty-odd years of software development, the ind.docx
hroughout the fifty-odd years of software development, the ind.docxpooleavelina
 
COMPUTER APPLICATION PROJECT ON
COMPUTER APPLICATION PROJECT ON COMPUTER APPLICATION PROJECT ON
COMPUTER APPLICATION PROJECT ON Jitender Suryavansh
 
Discussion 1 post responses.Please respond to the following.docx
Discussion 1 post responses.Please respond to the following.docxDiscussion 1 post responses.Please respond to the following.docx
Discussion 1 post responses.Please respond to the following.docxcuddietheresa
 

Ähnlich wie QSM Executive Primer Estimation and demand Management (20)

How To Plan a Software Project
How To Plan a Software ProjectHow To Plan a Software Project
How To Plan a Software Project
 
Breaking Through the Roadblocks of a New ELM Implementation eBook
Breaking Through the Roadblocks of a New ELM Implementation eBookBreaking Through the Roadblocks of a New ELM Implementation eBook
Breaking Through the Roadblocks of a New ELM Implementation eBook
 
Agile ERP_ Continuous Improvements Through Rapid, Incremental Implementations...
Agile ERP_ Continuous Improvements Through Rapid, Incremental Implementations...Agile ERP_ Continuous Improvements Through Rapid, Incremental Implementations...
Agile ERP_ Continuous Improvements Through Rapid, Incremental Implementations...
 
Software for Optimal Operations
Software for Optimal OperationsSoftware for Optimal Operations
Software for Optimal Operations
 
Immutable Principles Of Project Management (V7 Final Cmu)
Immutable Principles Of Project Management (V7 Final Cmu)Immutable Principles Of Project Management (V7 Final Cmu)
Immutable Principles Of Project Management (V7 Final Cmu)
 
Scalable light weight processes
Scalable light weight processesScalable light weight processes
Scalable light weight processes
 
A Pattern-Language-for-software-Development
A Pattern-Language-for-software-DevelopmentA Pattern-Language-for-software-Development
A Pattern-Language-for-software-Development
 
The Business value of agile development
The Business value of agile developmentThe Business value of agile development
The Business value of agile development
 
Software For Software Development Life Cycle
Software For Software Development Life CycleSoftware For Software Development Life Cycle
Software For Software Development Life Cycle
 
54 C o m m u n i C at i o n s o F t h e a C m j u.docx
54    C o m m u n i C at i o n s  o F  t h e  a C m       j u.docx54    C o m m u n i C at i o n s  o F  t h e  a C m       j u.docx
54 C o m m u n i C at i o n s o F t h e a C m j u.docx
 
SOFTWARE COST ESTIMATION USING FUZZY NUMBER AND PARTICLE SWARM OPTIMIZATION
SOFTWARE COST ESTIMATION USING FUZZY NUMBER AND PARTICLE SWARM OPTIMIZATIONSOFTWARE COST ESTIMATION USING FUZZY NUMBER AND PARTICLE SWARM OPTIMIZATION
SOFTWARE COST ESTIMATION USING FUZZY NUMBER AND PARTICLE SWARM OPTIMIZATION
 
Defect effort prediction models in software
Defect effort prediction models in softwareDefect effort prediction models in software
Defect effort prediction models in software
 
The Five Levels of Requirements Management Maturity
The Five Levels of Requirements Management MaturityThe Five Levels of Requirements Management Maturity
The Five Levels of Requirements Management Maturity
 
Releasing Software Without Testing Team
Releasing Software Without Testing TeamReleasing Software Without Testing Team
Releasing Software Without Testing Team
 
Quality Assurance, Testing, And Implementation
Quality Assurance, Testing, And ImplementationQuality Assurance, Testing, And Implementation
Quality Assurance, Testing, And Implementation
 
Putting-MANAGEMENT-into-Your-Requirements-Management_Dec2005
Putting-MANAGEMENT-into-Your-Requirements-Management_Dec2005Putting-MANAGEMENT-into-Your-Requirements-Management_Dec2005
Putting-MANAGEMENT-into-Your-Requirements-Management_Dec2005
 
hroughout the fifty-odd years of software development, the ind.docx
hroughout the fifty-odd years of software development, the ind.docxhroughout the fifty-odd years of software development, the ind.docx
hroughout the fifty-odd years of software development, the ind.docx
 
COMPUTER APPLICATION PROJECT ON
COMPUTER APPLICATION PROJECT ON COMPUTER APPLICATION PROJECT ON
COMPUTER APPLICATION PROJECT ON
 
Software modernization
Software modernizationSoftware modernization
Software modernization
 
Discussion 1 post responses.Please respond to the following.docx
Discussion 1 post responses.Please respond to the following.docxDiscussion 1 post responses.Please respond to the following.docx
Discussion 1 post responses.Please respond to the following.docx
 

QSM Executive Primer Estimation and demand Management

  • 1. Understanding Software Estimation, Negotiation, and Enterprise Demand Management An Executive Primer Douglas T. Putnam and C. Taylor Putnam-Majarian with foreward by Lawrence Putnam, Sr.
  • 2.
  • 3. Understanding Software Estimation, Negotiation, and Demand Management An Executive Primer
  • 4. Published by Quantitative Software Management, Inc. 2000 Corporate Ridge, Ste 700 McLean, VA 22102 800.424.6755 info@qsm.com www.qsm.com Copyright © 2015 by Quantitative Software Management. All rights reserved. This publication is protected by copyright, and permission must be obtained from the publisher prior to any prohibited reproduction, storage in a retrieval system, or transmission in any form or by any means, electronic, mechanical, photocopying, microfilm, recording, or likewise. For information regarding permissions, write to the publisher at the above address. Portions of this publication were previously published in journals and forums, and are reprinted here special arrangement with the original publishers, and are acknowledged in the preface of the respective chapters. Trademark Notice: Product or corporate names may be trademarks or registered trademarks, and are used only for identification and explanation, without intent to infringe. Every attempt has been made to annotate them as such. First Edition
  • 5. TABLE OF CONTENTS FOREWORD: by Larry Putnam Sr. i CHAPTER 1: The Journey Forward 1 CHAPTER 2: The IT Innovation Cycle 5 CHAPTER 3: Most Common Reasons Why Software Projects Fail and What You Can Do About It 9 CHAPTER 4: Fact Based Decisions – It Starts with Data and Establishing a Baseline 13 CHAPTER 5: The Software Production Equation and Rayleigh Staffing Model 21 CHAPTER 6: Single Release Estimation Using the Software Production Equation and the Rayleigh Staffing Model 27 CHAPTER 7: Multiple Release and Complex Program Estimation 35 CHAPTER 8: Capacity Planning and Demand Management 39 CHAPTER 9: Tracking, Forecasting, Execution, and Post Mortem 51 CHAPTER 10: Understanding Quality and Reliability 55 CHAPTER 11: What does it take to Successfully Implement Estimation? 63 CHAPTER 12: Summing It Up 67 CONTRIBUTING AUTHORS 69
  • 6.
  • 7. i FOREWORD Larry Putnam Sr., President Emeritus of QSM, Inc. ______________________________________________ Thirty five years ago, people who were involved with software development were frustrated because they did not have a good method to determine the cost and schedule for their projects. The typical approach was to use a number for software productivity, such as source lines of code per person-month (SLOC/PM), obtained from a previous project, from a friend, or from a magazine article, and then divide this number, say 200 SLOC/PM, into the best guess for the size of the project, say 50,000 SLOC (COBOL), to obtain 250 person months of effort. This did not address the schedule or how long it was going to take, and it gave uniformly poor results time after time. Bosses were not happy. They couldn’t plan this way. I was on active duty in the Army at the time, and in charge of the Army’s Data Processing budget. I had some historical data available to me to analyze. There was a pattern to how software systems behaved in their demand for people at different points in time during the project. A project had a typical staffing buildup, peak, and tail off as the project progressed. Errors were made that had to be found and fixed and the project’s environment changed, making changes to the software system necessary. It was a dynamic, time varying process that needed to be treated as such. Fortunately, over the next year or so, by looking at approximately 50 Army systems we found a time varying model, a Rayleigh curve, that had the buildup, peak and tail off that we saw in the budget data. The parameters of this curve could be expressed in terms the bosses wanted to deal with – effort and schedule. We also found that these parameters could be related to the product size of the system (the functionality). This led to what we called the software equation. We have used this software equation effectively now since 1978 and it has been built into a comprehensive system to deal with most of the management issues related to software development in nearly every domain (business, engineering, real-time embedded) and industry sector (finance, telecom, medical, aerospace, defense, government, etc.). It works well, gets good results, and has stood the test of time for three generations. In fact, the fundamental software equation that I used to estimate COBOL programs running on a mainframe in the 1970s, is the same one my son, Doug (now Co-CEO of QSM, Inc.), used to estimate object- oriented C++ programs that ran on a PC client-server platform in the 1990s. It is also the same equation that my granddaughter, Taylor (now a consulting analyst at QSM, Inc.), uses to estimate modern software projects that are written in Java using Agile methods, and run on a cloud computing platform.
  • 8. ii So the book that follows entitled, Software Estimation, Negotiation and Enterprise Demand Management – An Executive Primer, tells that story and shows the many ways these methods can be used by management to plan and control software development with the opportunity to save lots of money in the process. Lawrence H. Putnam, Sr. Jan 1, 2015
  • 9. 1 CHAPTER 1. THE JOURNEY FORWARD _______________________________________________ The news of another failed software project causes many to roll their eyes. As an industry that has been around since the 1940’s, and with all the technological advancements made over the years, one would think that by now we would have figured out how long it takes to build software applications. What many do not understand is that software development is very complicated and not nearly as intuitive as society would like to think. Although this notion is not fully understood, many organizations are feeling pressure to do better. By picking up this book, you have begun your journey towards better decision making in controlling individual software projects, as well as in long-term process improvements at the portfolio level. There are many reasons why process improvement may interest you. Perhaps you want to learn how to best utilize the resources available to you. Or perhaps, you feel as though you do not have the right resources necessary to ensure the success of your software development projects. Maybe you want to be in a better position to negotiate schedules and budgets with business stakeholders or vendors. Whatever your reason, I want to commend you for educating yourself on a better way to achieve successful project outcomes. You may or may not have a background in software development, yet you find yourself currently responsible for that function in your organization. While learning the ins and outs of software development may be useful, it’s likely that you don’t have enough time to do that in addition to all your other responsibilities. Your main concerns probably include the following: 1. What is the status of the current project? 2. What can be done to make long-term improvements to our organization? 3. What options are available right now in the current development process? In this book, we will help you answer those questions by providing a basic explanation of the methods involved in the overall software management process including demand management, software estimation and risk mitigation, as well as overall process improvement strategies. SOFTWARE DEVELOPMENT IS NOT MANUFACTURING One common mistake made when initiating a development project is that most businesses assume software development mirrors manufacturing. In reality, the two behave very differently. Manufacturing strives to gain predictability in production by eliminating any variance. Resources are often carefully distributed so as to ensure that production is not only controllable, but also controlled. In manufacturing, the relationship between time and cost is linear. If one wants to double the output, you invest in a second manufacturing line and produce twice the volume of product in half the time (see Figure 1.1).
  • 10. 2 Figure 1.1. The cost of a manufacturing project over time. However, software development is much more abstract. You cannot physically touch a software project like you would a manufactured item, which makes it especially hard to judge its status towards completion. In manufacturing, the tasks are mostly dependent, meaning one task must be completed before another task may be started. In software development, it is possible for there to be both independent as well as dependent tasks, making it unique from traditional manufacturing. Additionally, the relationship between time and cost is non-linear in software development (see Figure 1.2). Figure 1.2. The cost of a software development project over time. If you attempt to shorten the schedule by adding people, you will find rapid diminishing returns on the schedule with corresponding large increases in cost and decreases in quality. Why, you might ask? The reason is quite simple, and relates to the basic laws of acceleration. Acceleration requires energy. Energy efficiency decreases as acceleration increases. A simple analogy that
  • 11. 3 most people can relate to is a gasoline powered automobile. Suppose you are at a stop light and the light turns green. If you stomp on the gas to get to the next stop light as quickly as possible, the miles per gallon meter will immediately drop to a lower efficiency rating. In the same situation, you can be more conservative by accelerating at a slower rate. It takes slightly longer to get to the next light but you do it in a much more fuel efficient manner. Software development staffing behaves in a similar manner. The “fuel” is the human effort “hours”. If you add more people, the human communication complexity increases which manifests itself in more defects, all of which need to be found and fixed. This creates more rework cycles and is one of the reasons why using larger teams only achieves marginal schedule compression. From a management standpoint, this means that leaders have a direct influence on cost and quality by simply controlling the project’s staffing levels. As a leader, this can be very empowering. SUMMARY Understanding the non-linear relationship between schedule and cost can be extremely useful in project planning. Additionally, knowledge of the software development lifecycle will facilitate the logistics of how to staff projects. The following section describes the high-level phases of software development and how they can be applied to project staffing.
  • 12. 4
  • 13. 5 CHAPTER 2. THE IT INNOVATION CYCLE _______________________________________ When faced with a problem, regardless of what it is, humans will attempt to solve it using a common process. First, we will determine if their desired course of action is even feasible. Next they will formulate a design of action. The third step is to actually carry out the planned activities, and finally, the fourth step is to clean up and fine tune the finished product. This problem-solving process is applicable to software development as well. Regardless of the development methodology that you use, all software projects have four high level phases: Phase 1 - Feasibility, Phase 2 - Requirements & High-Level Design, Phase 3 - Build and Test, and Phase 4 - Post Delivery Stabilize and Deploy (see Figure 2.1). While various methodologies may further subdivide the development activities and increase or decrease the amount of overlap and concurrency, these are the overarching phases used in estimation and project management. Figure 2.1. High-level software development phases
  • 14. 6 PHASE 1: THE ‘WHAT?’ PHASE This is the earliest phase in the software development lifecycle, in which individuals determine what it is that they hope to achieve by developing this software. This phase is extremely high-level and the main focus is to brainstorm whether or not building an application is even feasible. Typically these activities include: a statement of need or list of the capabilities that the user expects from the system, a feasibility analysis assessing whether or not the project can and should be done, and a set of high-level plans documenting the management approach. This phase typically results in a go or no-go decision. PHASE 2: THE ‘HOW?’ PHASE The second high-level phase focuses primarily on how the work is going to get done. Many equate this with planning because many decisions about the requirements and design are made. Typical activities for this phase include: defining the interfaces between the system-level components, specifying software architecture and requirements by describing inputs and outputs, and finalizing the project plans. A design review may be held at the end of this phase or it may be iterative in an agile-like development process. Phase 2 typically overlaps with the end of Phase 1, as well as the beginning of Phase 3. PHASE 3: THE ‘BUILD IT’ PHASE The third phase of the software development lifecycle is the longest because it involves actually carrying out the plans made in Phase 2. The phase begins with detailed design and coding. The final portion of the phase includes system testing and hardening of the product prior to general availability. Phase 3 ends at the first customer release, which is typically when the system is 95% defect free and can run for about one day without encountering a critical defect. PHASE 4: THE POST DELIVERY STABILIZATION PHASE The last phase of the software development lifecycle begins after the software has been released to customers. Typical activities include correcting latent defects found after general availability. The purpose of this phase is to provide product support to the customer base, and stabilize the existing product. This phase may be considered complete once the project reaches a particular reliability milestone or certification level. The duration of this phase varies depending on the needs of the users. Prior to the conclusion of this phase, the base product often transitions to long-term operations and maintenance. The next innovation cycle begins as new capabilities are added to the base product. An advantage of using a four-phase macro model of the innovation cycle is that it can be easily adapted to any software development methodology. Given the introduction and change rate of new methodologies, the ability to maintain some continuity with estimation techniques provides great benefits as the industry adapts to the most effective development approaches. The following table maps the four phases to some of the more popular methodologies used today.
  • 15. 7 Methodology Phase 1: What? Phase 2: How? Phase 3: Build & Test Phase 4: Deploy & Stabilize Waterfall Concept Requirements & Design Construct & Test Deploy RUP Initiation Elaboration Construction Transition Agile Initiation Iteration Planning Iteration Development Production SAP ASAP Project Preparation Business Blueprint Realization & Final Prep Go Live SUMMARY In summary, humans follow a distinctive process that they apply to innovation projects. Initially they identify problems and potential solutions. The following step is to determine the most feasible solution to the problem. Next they conceptualize the solution and implement it. Finally, they put the solution to use and fine tune it. This flexible macro model with four high-level phases is adaptable and can be applied to any development methodology.
  • 16. 8
  • 17. 9 CHAPTER 3. THE MOST COMMON REASONS WHY SOFTWARE PROJECTS FAIL AND WHAT YOU CAN DO ABOUT IT _______________________________________ An article based on this chapter is scheduled to appear in an upcoming edition of the online journal InfoQ. Knowing the basics of software development can greatly improve the project outcome. However, that alone is not enough from preventing project failures. Projects can be categorized as failures for a number of reasons. Cost overruns, late deliveries, poor quality, and developing the wrong product are a few of the reasons why projects can be viewed unfavorably. When faced with a failure, project managers often find themselves wondering where it went wrong. More often than not, software developers bear the brunt of the responsibility for such situations; after all, they’re the ones who built the application. However, closer examinations of the projects do not always show evidence of incompetence. When asked to assess these projects, QSM compares the completed projects with our industry trends, and often finds that they performed “reasonably”. So then why are these projects considered failures? Our experience shows that the overwhelming majority of the problems can be tied to flawed estimation or poor business decision making. It is important to make sure that everyone understands a common set of terms because we often find that individuals and organizations use them interchangeably when they each have a unique meaning. Targets, constraints, estimates, commitments, and plans have distinct definitions and can be reviewed below.  Target – A goal, what we would like to do or achieve.  Constraint – Some internal or external limitation on what we are able to do.  Estimate – A technical calculation of what we might be able to do at some level of scope, cost, schedule, staff, and probability.  Commitment – A business decision made to select one estimate scenario and assign appropriate resources to meet a target within some constraints.  Plan – A set of project tasks and activities that (we calculate) will give us some probability of meeting a commitment at a defined level of scope, budget, schedule, and staff. In other words, decisions made based off of unrealistic targets or constraints can send a project on a death march from the start. Here is our list of the top five reasons why IT projects fail: 1. Accepting a forced schedule or mandated completion/ milestone dates without substantial data and analysis. How many times have you found yourself in a situation in which you’ve been given an unreasonably short deadline? Someone in your organization publicly speculates that the project will be done by a particular date, thus unintentionally committing the team to that deadline. Perhaps your budget cycle dictates that the money allocated to this project
  • 18. 10 must be spent by the end of the year or the next release will not get funded. Maybe the stakeholder wants the project finished by Christmas so that he/she can enjoy the holiday in peace, knowing that the project is complete. Or maybe the stakeholder just really likes round numbers and wants the project to release the 1st of the month. There are numerous reasons why a development team would be given an arbitrary project completion deadline. The unfortunate reality of an overzealous schedule often results in overstaffing the project, the next reason why software projects fail. 2. Adding excessive personnel to achieve unrealistic schedule compression. How do project managers deal with an overly optimistic schedule? One common response is to staff up the project, often adding way more people than necessary to complete the project. Not only does this drastically increase the cost of a project, but it also decreases the quality. Having more people involved in the project increases opportunities for miscommunications and also makes it more challenging to integrate the different sections of code together. Additionally, Frederick Brooks (1975) would argue that “adding people to a late project only makes it later,” which makes sense. The people have to come from somewhere, often from other projects. This puts the other projects further behind schedule and requires that the new staff get caught up by veteran staff, thus decreasing productivity across the board. 3. Failing to account and adjust for requirements growth or change into schedule and budget forecasts. “Wouldn’t it be great if…?” Those five words can be some of the most dreaded, especially when heard halfway through the construction portion of a project. While there is certainly a time and a place for brainstorming, those activities should take place in Phases 1 and 2. In fact, the purpose of these two phases is to determine whether or not a project is feasible, and what features the application should have. If you think of it this way, Phase 2 helps you figure out what you are building, while in Phase 3, you build whatever you decided upon in Phase 2. While some overlap may exist between the two high-level phases, by the time you’re in the Phase 3, the scope of required functionality for a given product release should be clear.  Requirements growth is a problem if you’re adding functionality without allotting more time and budget for development. In essence, you’re asking for more work in a shorter amount of time, a technique that we’ve already found does not work.  Changes to existing requirements can also be a problem depending on the nature and timing of the change. Projects using Agile methods can manage changes to requirements details, as long as they occur before construction of a given iteration. However, any changes to requirements of software architecture that cause rework of code already written will almost certainly have an impact to the schedule and budget. 4. Emotional or “intuition-based” stakeholder negotiation that ignores facts and statistics. At some point or another we’ve all become attached to a particular project that we’ve worked on. It may not have been related to software development, but at some point we’ve all become emotionally invested in a project’s outcome. For many, this may be the
  • 19. 11 project where your reputation is on the line; the one that is too-big-to-fail, and often we let our emotions get the best of us. When the pending success or failure of a software project puts an individual’s career on the line, it’s likely that any related business decisions will be impacted. Stress can cloud one’s thinking, especially when the stakes are high. A stakeholder may call for a 12 month schedule in order to impress a customer despite the fact that reports from previous projects of similar sizes all show a 15 month lifecycle. The stakeholder may dismiss advice from team members, stating that he has “a feeling” that the team will be able to pull through. In such situations, following your gut could be extremely detrimental and potentially lead to project failures. 5. False, but common belief that the proverbial IT silver bullet alone can solve project throughput or process issues. When all else fails, a common next approach is a change of strategy. “We must be doing it all wrong” and “What are our competitors doing?” are common thoughts at this point. This is when musings of an “IT silver bullet” may start circulating around the office. For instance, someone may suggest that the organization needs to adopt the latest bandwagon development approach. While that might be a great direction in which to take the organization, a decision like this should not be taken lightly. Whichever development methodology your organization decides to use, it’s only as good as your implementation. Merely switching development methodologies is not enough to transform your development operation. Regardless of what you decide, in order to make the implementation successful, there needs to be buy-in from all sides, individuals need to be trained, and everyone needs to be held accountable to the same standards. Otherwise, your development strategy will be roughly equivalent to waiting for the stars to align perfectly and hoping for a miracle each time you begin a project. If implemented without thought, this strategy is not only incredibly risky, but also reduces opportunities for team members to give feedback mid-project. SUMMARY In short, software projects fail for a number of reasons. Take a moment to reflect on whether any of the above reasons may have been the cause of a project failure in your organization. Now what can you do about it? As an executive leader you can do a lot, but it will require courage and a backbone to support your development operation. They need to function within a reasonable set of expectations. Obviously, they will still have to be held accountable, so you will also need historic performance data as evidence of their capability. Doing this will put you in a much more powerful position to negotiate with customers and business stakeholders. A successful outcome is one in which every entity can be successful. In all likelihood this will require some compromise, but through this process you will be sowing the seeds of success. We will discuss this further in the coming chapters.
  • 20. 12 References Brooks, F. P. (1975). The Mythical Man-Month. Addison-Wesley.
  • 21. 13 CHAPTER 4. FACT-BASED DECISIONS IT STARTS WITH DATA AND ESTABLISHING A BASELINE _______________________________________ This article originally appeared in the May 20, 2015 online edition of Project Management Times and is reprinted here with permission. One of the best ways to assure realistic expectations for a project is to observe the past. Before getting started with any process improvement endeavors, it is important to understand the big picture and establish an initial baseline with your projects. To do this, you will want to collect data on your completed projects. While it may sound overwhelming to collect data on completed projects, there are actually only a few pieces of information that your need to collect: 1. Size: A measure of the amount of functionality or value delivered in a system. It can be measured in Source Lines of Code (SLOC), Function Points, User Stories, Business or Technical Requirements, or any other quantifiable artifact of product size. 2. Time: The duration required to complete the system (i.e. schedule). This is typically measured in months, weeks or days. 3. Effort: A measure of the resources expended. This is typically measured in Person Hours or Person Months of work and is related to staffing as well as cost. The total effort multiplied by the labor rate is typically used to determine the project cost. 4. Quality: The reliability of the system is typically measured in the number of errors injected into a system, or the Mean Time to Defect (MTTD), which measures the amount of elapsed time that the system can run between the discoveries of new errors. Once the size, schedule, effort, and quality data have been collected a 5th metric, the Productivity Index (PI), can be calculated. The PI is a measure that determines the capability and complexity of a system. It is measured in Index Points ranging from 0.1 to 40 and takes into account a variety of factors including personnel, skills and methods, process factors and reuse. See Chapter 6 for more information on PI. Together, these 5 metrics give a complete view of the project which can be used to assess its performance. In order to establish a true baseline; a broad reaching sample of historic performances is preferred (see Figure 4.1). However, it is better to start with something rather than nothing at all, so begin by creating your baseline with whatever is practical, and then build on that as you realize success from newly completed projects.
  • 22. 14 Figure 4.1. Build datasets to include a sample of historical data at a variety of project sizes. THE INTERNAL BASELINE Once a repository of an organization’s completed projects has been established, custom trend lines for schedule, effort, and productivity can be calculated to use for creating the baseline. These trend lines serve as a reference point which can be used for comparing projects within your organization. Where your projects fall relative to the trend line will indicate better or worse performance than the average. This will give insight into your organization’s current capabilities. Figure 4.2. Project baseline and outliers.
  • 23. 15 We can learn a lot about what we do well and what we can improve upon from looking at our projects relative to the baseline. Examining how far a project deviates from the various trends can help isolate best- or worst-in-class performances. Project outliers can also provide great insight into this. Figure 4.2 displays the company project portfolio against their baseline average productivity. Two of the projects stand out since they fall outside two standard deviations, one above the average and one below respectively. Further examining the factors that influenced these projects (i.e. new technology, tools and methods, personnel, or project complexity) will help shed some light on why these projects performed so well or so poorly. Mimicking what went well for best-in-class projects and avoiding what didn’t for the worst-in-class projects can help improve the performance of future projects. Understanding the baseline for your current development operation can help set reasonable expectations for future projects by showing what has been accomplished in the past. If the desired project parameters push the estimate into uncharted territory, you can use the historical baseline to negotiate for something more reasonable. This baseline can also be used for contract negotiation, evaluating bids and vendor performance, and navigating customer constraints, thus allowing you to achieve your cost reduction and process improvement goals. Chapters 5 and 6 discuss this in more detail. INDUSTRY COMPARISON While the internal baseline gives good insight into the practices of an individual organization, we have the market to think about as well. The internal project standings within an organization may not matter if they’re not competitive with the industry. Therefore, it is important to have an external comparison for your project data. QSM regularly collects and maintains project data that is used to create 17 different industry trend groups, ranging from Business IT systems of various industry sectors and development methods to engineering and real time systems. Since these industry trends are kept current, they can be a good reference point if you are new to estimation and do not have enough data from your own projects. When using these trend lines to determine performance, it is important to examine the project holistically. Judging a project’s performance based upon one metric can be very misleading because of the tradeoffs that occur in software development. For instance, a project may have been viewed favorably because it was delivered quickly. However, looking beyond the schedule, a project may not have performed well overall.
  • 24. 16 Figure 4.3. Project delivered 4.7 months earlier than average. Figure 4.3 shows a project that was delivered 4.7 months ahead of the industry average, an accomplishment that is often viewed favorably by management because it provides an advantage over market competition. While speed of delivery may be desirable in some circumstances, compressing the schedule unnecessarily can cause tradeoffs, which often result in higher costs and lower quality. Figure 4.4 shows how the project performed in other areas including productivity, staffing, effort expended, and the number of defects present during testing. These graphs tell a very different story.
  • 25. 17 Figure 4.4. Holistic view of project shows that the effort, staffing, and defects are higher than industry average. While the productivity of this project was comparable with the industry average, the peak staffing and effort expended were drastically higher than what is typical for other projects of similar scopes. This directly translates into higher project costs to pay for the additional labor hours. Additionally, the number of defects present in the system was also considerably higher than what is typical for the industry (see Figure 4.4). This is likely a result of the higher staffing. When more people work on a project, there is a greater chance that miscommunications between team members could lead to errors being injected into the system. Utilizing more people further divides the code base, which can result in more defects during integration. The following scenario helps illustrate the challenges of working with large teams. Suppose you and another team member were asked to write a book together. The two of you would have to brainstorm a plot and characters, figure out who would write each chapter, and make sure that all the chapters flow together. Now suppose that 20 more people were added to your book-writing team, and each of them was assigned to write one chapter. Each of the chapters might be really good on its own, but putting them together becomes increasingly challenging as the number of team members grows. When put together, the chapters may seem
  • 26. 18 fragmented, especially if the authors of the earlier chapters do not communicate well with the authors of the later chapters. The editing process introduces challenges of its own. Suppose an author makes a change in Chapter 2. This change has the potential to affect every chapter thereafter, thus creating a lot of rework. If the ultimate goal of the project was to have a completed book by the end of the allotted time, it may have actually been easier and faster for the two-person team to write the book than the 22-person team. The challenges of this scenario are similar to what it is like to develop software using large teams. Often, many large teams struggle with communication between team members, which is why we tend to see a higher degree of defects than those that use smaller teams. Overall, this example reinforces the need to examine a project holistically. While excelling in one area may make the project appear as though it was a top performer, further examination may indicate otherwise. By viewing the performance using multiple dimensions, one can determine or assess the strategy employed on a project and determine whether the strategy delivered what had been anticipated. Figure 4.5. The Five Star Report. Five Star Report views, like the one shown in Figure 4.5, can be used to rate the overall performance of a project or group of projects. For each metric, the project is given a rating of 1- 5 stars with one star being the worst performance and five stars being the best. The Composite Project Star Rating column on the right gives an overall grade to the project by factoring in the performance of all the individual metric scores. This value helps determine what effects adjusting the staffing or schedule will have on the overall project rating. Here it is easy to see when a project staffs up in order to decrease their schedule. In such a situation, the project would have a Duration rating of 4 or 5 stars but a staffing and effort rating around 1 or 2 stars. The opposite can also occur, thus indicating a project that used fewer than the average number of staff and lengthened the schedule duration. Ideally, project managers should shoot for an average of 3 or more stars for their projects.
  • 27. 19 SUMMARY Establishing a baseline will eliminate much of the up-front ambiguity and will provide detailed recommendations based on quantifiable data that define the range of the organization’s current capabilities. As various organizations strive for improvement, knowing where they stand relative to competition is important. A company with a lower than average productivity will have different goals and implement different process improvement measures than one that is average, or better than average. Knowing where you stand as an organization can help you determine the most appropriate measures to take, and decide the best method for moving forward. With this data you will empower the organization to move toward fact based decision making, thereby maximizing the possibility of having successful project outcomes.
  • 28. 20
  • 29. 21 CHAPTER 5. THE SOFTWARE PRODUCTION EQUATION AND THE RAYLEIGH STAFFING MODEL _______________________________________ SLIM® is the acronym for Software Lifecycle Management. It is a methodology as well as an estimation and measurement product suite. SLIM® is based on two fundamental equations that trace their origins to the seminal research of our founder Larry Putnam Sr. from the 1970’s. We believe that these equations capture the fundamental time and effort behaviors related to how people solve complex design problems. These equations are: 1. The Software Production Equation 2. The Rayleigh Equation The software production equation is composed of four terms, namely: Size, Schedule, Effort and Productivity. The equation is described below. Size = Productivity × Time4/3 × Effort1/3 Notice the exponents attached to the time and effort variables. The schedule variable, or time, has been raised to the 4/3rd power, while the effort variable has been raised to the 1/3rd power. Without getting too technical, it means that there is a diminishing return of schedule compression as people are added to a software project. In the most extreme conditions, it means that spending a lot of money in labor costs can get little to no schedule compression (see Figure 5.1). Figure 5.1. Utilizing more people requires exponentially more effort.
  • 30. 22 However, what’s nice is that this phenomenon also works in reverse. If a project can afford to lengthen the schedule, it can be accomplished significantly cheaper by using fewer people (see Figure 5.2). In today’s economic environment this is a very attractive option. Figure 5.2. Lengthening the schedule drastically reduces the cost. The software production equation is simply a quantification of “Brooks’ Law,” which states that throwing people at a late project only makes it later. Fundamentally the software production equation models the complexity of human communication and how that manifests itself in defect creation and rework cycles. As more people are added to a project, human communication complexity grows exponentially. The communication complexity results in larger volumes of defects being created, and more rework cycles to fix the problems (see Figure 5.3). Figure 5.3. Communication complexities increase as people are added to a project.
  • 31. 23 Figure 5.4. The Rayleigh curve occurs because of both dependent and independent tasks. The Rayleigh equation uses the schedule and effort variables from the software production equation to produce time-based predictions of effort, staffing, and cost. Software projects typically begin with fewer resources during Phases 1 and 2. The necessary resources quickly increase during Phase 3 when more people are needed to build the application due to the arrival of independent work tasks, and then declines in the second half during testing when more of the tasks become dependent. After delivery, a few staff remain to assist with fixing latent defects and maintaining the application (see Figure 5.4). The Rayleigh equation also produces cumulative curves to provide estimates of total effort and cost, and rate curves to provide monthly or weekly estimates of staffing, effort or cash flow. These are all important variables in the estimation, planning and negotiation process. It is important to note that resource allocation in software development differs from traditional manufacturing. In software development, the ideal work arrival rate follows the Rayleigh curve, meaning the amount of available work is not always constant. Manufacturing, on the other hand, tends to have a more stable amount of work, utilizing the same number of people working from start to finish (see Figure 5.5).
  • 32. 24 Figure 5.5. Level loaded staffing shape is used in manufacturing. Traditional project management has attempted to level load projects. However, this strategy is often unsuccessful because it does not effectively utilize the available resources. It tends to overstaff projects in the beginning and at the end of the lifecycle, thus wasting resources that could be available to other projects. By using a Rayleigh curve to model the staffing buildup, software projects can use their available resources more efficiently, and prevent some staff from sitting idly at points in the project when there is not enough work to be done. THE IMPOSSIBLE ZONE QSM also uses historical data to determine the productivity of an organization and to identify “The Impossible Zone”. “The Impossible Zone” is a schedule that no project has ever been able to achieve (see Figure 5.6). It turns out that IT consumers and stakeholders love to demand project schedules in the impossible zone. Figure 5.6. ‘The Impossible Zone’ vs. ‘The Impractical Zone.’
  • 33. 25 QSM has over 10,000 historic projects in our repository which can be used to support clients that have no history but we encourage our clients to collect their own data because it is more powerful, especially when one needs to negotiate out of the impossible zone. SUMMARY The SLIM equations are field proven with over 35 years of practical application on real world systems. The Software Equation allows one to predict both time and effort alternatives, while the Rayleigh curve uses these outputs to create a staffing plan. One especially nice characteristic of these algorithms is that they are applicable, even in the earliest phases of the software development lifecycle, when little data is available but critical business decisions are often made.
  • 34. 26
  • 35. 27 CHAPTER 6. SINGLE-RELEASE ESTIMATION USING THE SOFTWARE PRODUCTION EQUATION AND THE RAYLEIGH STAFFING MODEL _______________________________________ So how would one actually do an estimate on a single release using our two equations? We like to start with the software production equation, where the required inputs are size and productivity. We rearrange our equations algebraically such that our inputs are on one side of the equation and we can solve for effort (measured in labor hours) and time (schedule). 𝑆𝑖𝑧𝑒 𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑣𝑖𝑡𝑦 = (𝐸𝑓𝑓𝑜𝑟𝑡)1/3 (𝑇𝑖𝑚𝑒)4/3 PRODUCTIVITY ASSUMPTIONS The first major input is Productivity, which is measured using the Productivity Index (PI). PI is a calculated macro measure of the total development environment, and embraces many factors in software development, including: management influence, development methods, tools, techniques, skill and experience of the development team, and application type complexity. It is measured on a normalized scale that ranges from 0.1 – 40. In general, low values are associated with poor environments and tools, and complex systems. High values, on the other hand, are typically associated with good environments, tools and management, and well- understood, straightforward projects. Business IT systems tend to have the highest PI’s because their projects generally have well understood algorithms. Engineering systems have the next highest PI’s followed by Real Time systems, because their increased algorithm complexity and higher quality standards tend to lengthen the project durations. Selecting the right Productivity Index is critical to producing a good estimate. As system size increases, productivity typically also increases. Therefore, the PI selected will be size-dependent. The best way to select your PI is from history. By rearranging the software production equation we can calculate the actual productivity from past projects. This requires that we input actual performance data on size produced, schedule months required and hours of effort expended. 𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑣𝑖𝑡𝑦 = 𝑆𝑖𝑧𝑒 (𝐸𝑓𝑓𝑜𝑟𝑡)1/3(𝑇𝑖𝑚𝑒)4/3 Using a database of your historical projects, a productivity trend will be created from the average PI at each project size. To use this method, simply select the PI that corresponds with your desired project size. If the project being estimated has 3-5 similar projects, we will have a good idea of the developer’s average capability. We can then modify this productivity assumption based on whether the project is expected to be more or less complicated than the historical baseline.
  • 36. 28 If no historical data is available there is another option. Simply use the PI from the QSM Industry Trend that most closely corresponds with the type of project being built. The Industry Trends are created from historical project data in the QSM Database. Project data and their corresponding trends are regularly collected and updated to reflect what is currently typical in the industry. SIZING ASSUMPTIONS The other major assumption in estimation is sizing. Estimating the size of a software application can be challenging. One must translate abstract requirements into a technical size quantity. It’s like trying to determine the square footage for a new construction project. An architect might use the number of floors to calculate the square footage of a house. In software development we use sizing units such as Business Requirements, Agile Epics, Agile Stories, Function Points, or Use Cases to calculate the number of programming constructs. As the design matures, component based units like screens, reports, interfaces, scripts, and modules become more common and can be used to help refine the estimate (see Figure 6.1). Figure 6.1. Top-down estimation and the cone of uncertainty. Top-down estimation is especially effective when used in the earlier phases of the software development lifecycle. At the beginning of the lifecycle, the actual size can be as much as ±4 times the estimated size because there is much more uncertainty. The sizing units available at this point in the lifecycle often measure the project’s functions (i.e. Business Requirements, Function Points, Use Cases, etc.) and can vary somewhat. As the project progresses, the uncertainty decreases until the project is complete. At this point it is easier to count the number of programming constructs (i.e. Source Lines of Code, Configurations, etc.). Often, when an initial estimate is needed, there is little sizing information available. Additionally, the sizing information available may not be in the unit that is familiar to the developers who are building the application. In such cases, we use a gearing factor to map the functional
  • 37. 29 requirements to the desired programming constructs. The gearing factor is simply the average number of lines of code or configuration actions required to produce an average component. It behaves similarly to the Rosetta Stone which translated the same text into three different scripts (see Figure 6.2). In essence, gearing factors translate the high-level, abstract units, known at the time of the estimate, into units more familiar to the developers. The gearing factors have been calculated and validated from our clients’ historical project data. Figure 6.2. Similar to the Rosetta Stone which translated the same meaning into three different scripts, gearing factors translate the same functionality into different sizing methodologies. For further information on sizing please refer to the included infographic. THE INITIAL ESTIMATE & ALTERNATIVES Now that you understand the inputs, size and productivity, you are able to begin your estimate. SLIM takes the assumed inputs and uses them to estimate a range of potential schedule and effort solutions. There are a finite but large number of schedule and effort combinations for any set of inputs, so it is important to understand the available options (see Figure 6.3). For example,
  • 38. 30 one could use fewer people and lengthen the schedule, or they could shorten the schedule and use more people. If you move the solution far enough in either direction you will eventually hit a roadblock. Shortening the schedule too much could put the project into the impossible zone, overstretch the budget constraint, or require more people than are available. Moving too far in the other direction could also cause roadblocks. Lengthening the schedule too much could cause the project to miss its deadline or go below the minimum staffing constraint. Figure 6.3. The SLIM estimation process. Once the project and organizational constraints are imposed they create a practical alternatives region. Any combination of schedule and staffing within this region would be a reasonable solution to select. The next step would then be to identify the solution with the highest probability of success. This optimum solution would then be used as the inputs to the Rayleigh equation to generate the staffing, effort, cash flow, and cumulative cost plans (see Figure 6.4). Figure 6.4. Standard estimation solution graphs.
  • 39. 31 DEALING WITH UNCERTAINTY AND RISK Of course, our knowledge of size and productivity are imperfect since they are assumptions. They are our best guess given the information available. How can we realistically manage uncertainty? A Monte Carlo Simulation is a technique that solves the equation thousands of times using variations of size and productivity to produce a range of potential outcomes based on the current understanding of the system. More importantly it allows us to build a probability curve. We have an expected value – our estimate and the uncertainty distribution. Now the business decision makers need to decide how much risk they are willing to take while executing this project. If the outcome has the potential to tarnish the reputation of the corporation, it is probably worthwhile to commit to a 99% probability of reaching the expected value. If the outcome is less critical, perhaps 80% would be more appropriate (see Figure 6.5). Figure 6.5. Risk probability charts for schedule and effort. It is important to deal with uncertainty in a realistic and scientific manner. One particularly effective method for managing risk is planning the project to the 50% risk solution, but make commitments to stakeholders at the 99% solution to be very sure of not exceeding your commitment. This builds in a buffer should the project deviate slightly from the original plan.
  • 40. 32 LEVERAGING ESTIMATES IN BUSINESS DECISIONS – LET THE FUN BEGIN! The initial estimate rarely satisfies all of the targets and constraints that are imposed on the project. When this happens, some negotiations need to take place. In such situations, the developers, business stakeholders and executive management are faced with a few practical options. 1. Relax the schedule. Working with stakeholders to extend the schedule to include the additional time necessary is typically a good first step. In many cases, the stakeholders find that it’s perfectly acceptable to live without the system for a short period of time. In general, this option is the most ideal as it tends to be the least expensive and requires fewer resources than other options. 2. Reduce capability. If the amount of time needed greatly exceeds the desired deadline, another strategy is to reduce the capability of the system. An initial release can be delivered to the stakeholder, giving them the basic functionality at the desired deadline. A second release can then be integrated later which includes the additional functionality that the stakeholders initially wanted. While this strategy is more labor intensive and ultimately requires more resources than building the system in one release (the integration requires much testing), it also satisfies stakeholders by delivering some working software while also keeping development costs fairly consistent. 3. Add additional personnel. This strategy involves adding as many people as possible in order to meet the desired deadline. While commonly utilized in businesses, this strategy is the least effective of the three, and is almost never a good alternative when the stakeholder expectations are off by more than three months. Due to the non-linear relationship between effort and duration, the amount of schedule compression achieved is minimal compared with all the negative consequences, such as higher costs and decreased quality. 4. A combination of options 1 – 3. In such situations, estimates should be used as a negotiation and communication tool. Presenting the flawed estimate to a stakeholder will help them realize that their expectations are unreasonable. Sharing alternative solutions and their predicted outcomes will provide options that facilitate the decision-making process. This strategy can help improve the chances of a successful project outcome while also making the stakeholders feel more involved in the selection process. SUMMARY Flawed estimation can drive ill-informed business decisions resulting in unrealistic expectations and disappointing outcomes before the project even begins. It is well known that early in a project lifecycle, information can be incomplete and undefined with a reduced ability to forecast results. However, the core value of a good estimate is identifying and contending with that uncertainty in a legitimate, objective and useful way – rather than speculating and hoping for a positive outcome. It is not a good reason to forego data and measurement altogether.
  • 41. 33 The prevailing, critical flaw for countless software initiatives is that they are inherently destined to disappoint because of ill-advised or overly optimistic expectations. Exposing such liabilities before they cause an adverse, or disastrous, outcome will shed some light on current processes and prevent future failures. Parametric estimation helps reveal probable scenarios and ongoing considerations to guide and course-correct once the projects are underway. Those two core principles are at the heart of the SLIM philosophy: to allow projects not only to begin on solid ground, but to move, in control, more predictably through the full system development lifecycle. Inherently non-deterministic estimates, after all, are still guesses. You can reduce uncertainty, but can never completely eliminate it. How well you contend with that reality can be proportionate to how well your projects meet their objectives.
  • 42. 34
  • 43. 35 CHAPTER 7. MULTIPLE RELEASE AND COMPLEX PROGRAM ESTIMATION _______________________________________ The previous two chapters outlined the basics for creating a single-release estimate. However, sometimes due to budget or schedule constraints a project may need to be completed in two or more releases. Additionally, some projects may have some non-development related components such as training programs, hardware purchases or infrastructure cost, etc. This chapter will discuss the various strategies for creating multiple-release and complex program estimates. There are several reasons why a project may be delivered in multiple releases. Perhaps the project is larger than the allocated schedule and must be broken into smaller releases so that the stakeholder is able to use a portion of the software by a certain date. It is also possible that the project has a series of maintenance updates built into the overall schedule. Whatever the reason, multiple release estimation can be much more difficult than basic single- release estimation because of dependencies. Many organizations struggle with estimating one release, so estimating beyond that can be particularly challenging, especially if very little information is known. The strategy here is not terribly different from that of the single-release estimate. If unsure about the size or productivity inputs for your multi-release projects, examine the historical data and use the averages. If none are available, use your best judgment. It is always possible to update the estimates as more information becomes available. COMPLEX SYSTEM INTEGRATION PROJECT Once you have the basic estimates for each release, they can be aggregated into one view using SLIM-MasterPlan. In this format (see Figure 7.1), it is easy to see how each contractor’s portion and each release fits together with the project’s overall schedule. Additionally, it’s now possible to assess the number of staff needed on a project at a particular point in time.
  • 44. 36 Figure 7.1. Multi-Release Complex Project View. SLIM-MasterPlan allows users to view the complex estimate at both the high-level and detailed levels. In Figure 7.1 the upper left chart shows the high-level total monthly average staff utilized over the lifecycle of the project. Meanwhile, the lower left chart shows the monthly average staff of each component in a greater level of detail. The chart in the upper right shows some blue lines connecting all of the development and integration components between the first and second release. These lines represent the dependencies present in this multi-release project, meaning the status of one release depends on the outcome of a prior release. The dependencies can be set up so that Release 2 begins 20% before the end of Release 1. If Release 1 has a delayed start, these dependencies update the start date for Release 2, thus preventing it from starting before there is a solid enough code foundation from Release 1. ITERATIVE RELEASE EXAMPLE Another benefit to using SLIM-MasterPlan is that it has the ability to help manage your product line release schedule. With this tool, it is easy to determine the resources necessary for executing complex, multi-release projects.
  • 45. 37 Figure 7.2. Incremental Build Project Estimate. Figure 7.2 shows a project with several releasable builds. While the staffing initially starts out slowly, it quickly ramps up as the number of concurrent builds increases. The project reaches its peak staff of 22 FTE’s in July of 2010. Start dates and their respective dependencies for each release can be updated in this view to create alternative options if the necessary resources are not available. Slipping the schedule creates less overlap between the releases, thus reducing the overall staffing for the multi-release project. Multiple product lines within an organization can also be modeled in SLIM, resulting in improved abilities to manage product demand and organizational resources. Suppose that an organization is planning the development activities of 5 product lines during the next fiscal year that will be released at staggered intervals. Similar to the multi-release estimate scenario, these individual estimates can be combined into one view to allow for resource totals to be appropriately distributed among all the 5 applications. If running too many projects simultaneously requires more staff than are currently available, this view facilitates deciding which projects need to be prioritized or delayed. Additionally, this view can also accommodate other tasks, such as management, training, etc., which may not impact the development schedule, but may have an effect on the overall budget costs or personnel estimates. By examining the staffing and schedule for all of the applications simultaneously, one can easily determine the company’s busy periods, and when there are opportunities to take on more work. The following chapter examines this concept in more detail.
  • 46. 38 An added benefit to examining an entire portfolio rather than individual projects is that if you want to make adjustments to the estimates and try out some “what if?” scenarios, you can see how they’ll impact not just an individual project but the overall schedule, staffing, and cost of the entire portfolio (see Figure 7.3). Figure 7.3. The Master What If Feature. For many projects, scope creep is not only probable, it’s typical. With some projects increasing their size as much as 15%, creating estimates with multiple sizing scenarios provides beneficial insight into plausible ranges for staffing, cost, and effort. The sizes of each project can be adjusted either by the total size or by a percentage increase and will illustrate how these adjustments could affect the entire product line. Similar “what-if” scenarios can be run by adjusting the productivity and staffing as well. This type of insight can be particularly useful when it comes to complex decision-making. By understanding the impact that changes to an individual application can have on an entire product line, more informed decisions and effective project planning can result. SUMMARY To summarize, multi-release estimation builds on the skills acquired from single-release estimation and adds a degree of complexity. This method provides a more holistic view of your project portfolio and allows estimators to gain greater insight into how their individual projects impact the overall software development practices. The next chapter will focus on how users can utilize this information to make informed decisions regarding their development capacity and demand.
  • 47. 39 CHAPTER 8. CAPACITY PLANNING AND DEMAND MANAGEMENT _______________________________________ This article originally appeared in the March 20, 2015 online edition of Software Magazine and is reprinted here with permission. If you think about it, enterprise application capacity planning can be a difficult juggling act. On one side of the equation you have business demand. The business exists in a fluid, competitive environment. With stakeholders hoping to gain an edge over their competitors, they are constantly looking to innovation and technology to help them improve business performance and increase their profitability. The IT organization stands on the other side of the equation, and is responsible for satisfying the demands of the stakeholders. Their capacity is limited by their facilities, the volume of developers and their specific skills, and the infrastructure that is in place to enhance their productivity. This leaves the business and technology executives in the unenviable position of trying to balance the demand for IT development with their current capacity levels. Figure 8.1. Conflicting demands on executive management. Moreover, in a large enterprise there are thousands of projects moving through the development pipeline, making the balancing process that much more difficult. In order to address these complexities many organizations have implemented enterprise Project and Portfolio
  • 48. 40 Management (PPM) systems. These PPM systems are great for allocating known resources against approved projects, and aggregating the data into a portfolio to give a current picture of how the IT capacity satisfies business demands. In order for the capacity planning process to work, it is important to have a robust demand estimation capability. This is a discipline that has proven to be difficult for many organizations. Why is it so difficult? There are many reasons, but two stand out. The first is that most organizations only estimate an aggregate number of hours by skill category and have no estimate of the schedule or how the skills are applied over time on the project. The most common practice today is based on using a detailed task-based estimation method. Imagine a spreadsheet with a generic list of hundreds of tasks that typically are performed on any given project. It is the estimator’s job to review the requirements and estimate the number of labor hours required for each task. The task estimates are rolled up into a total labor estimate which is then allocated out to labor categories. The problem is that this method does not provide details for how the skilled labor categories are required to ramp on or taper off the project. This is an important component of capacity planning process. So using today’s most common estimation practices, one ends up with a project estimate that looks something like Figure 8.2: Unfortunately, this method also does not include a schedule. The schedule is usually decided arbitrarily by the stakeholders and often does not align with the estimated effort. QSM research shows that unrealistic schedule expectations are the number one reason why projects fail. This is clearly a big deficiency. The second issue is that task- based estimation is not well matched for the information that is available during the early stages of a project when the estimates and business decisions are typically made. The initial estimates are typically performed when there are only a few pages of business requirements. This clearly is not sufficient information to do a detailed task-level estimate. Moreover, doing a task- based estimate requires a lot of time and energy, so it would not be appropriate if numerous alternative scenarios are requested. TOP-DOWN ESTIMATION IS VERY EFFECTIVE IN THE EARLY STAGES OF THE PROJECT LIFECYCLE Top-down parametric estimation is particularly effective in the early stages of the lifecycle. It utilizes gross sizing and productivity assumptions to produce schedule and effort estimates. If the estimates do not match expectations, top-down estimation tools can quickly evaluate what can be accomplished with the available resources or determine how much additional time and effort will be required to achieve the business objectives (see Figure 8.3). Figure 8.2. Typical bottoms-up estimate without project schedule.
  • 49. 41 Figure 8.3. Desired schedule and cost compared against historical data and benchmark trends. The beauty of the top-down method is that it uses crude size measures like Business Requirements, Agile Epics, Use Cases or Function Points as a direct input. Coincidentally, these are the design artifacts that are most likely to be available during the early stages of estimation. With this basic information, top-down methods can quickly identify both high risk and conservative expectations, and if appropriate, suggest more reasonable alternatives. Let’s take a look at a typical estimation situation early in the lifecycle. Suppose, for example, that a business has identified some new capabilities that they would like to have implemented. They have a 5 page document that describes 19 business requirements or capabilities. They would like to have the capabilities available within 3 months and have a budget of $250,000. Figure 8.4 shows their desired outcome.
  • 50. 42 Figure 8.4. Risky desired outcome compared with the recommended, more realistic estimate. When compared to historical data, the desired outcome is determined to be “Risky” and an alternative estimate of 5.7 months and $571,000 is recommended. Now a negotiation between the stakeholders and the IT department can take place to explore more viable options. For example, 11 business requirements could be completed in 3 months using the previously outlined resources, or all 19 requirements could be completed in 4 months using a team of 12 people and a budget of $1.8 million. The main purpose for estimating at this stage of the demand management process is to smoke out grossly unrealistic expectations and negotiate realistic options in order for all parties to be winners in this development. TURNING HOURS INTO SKILLS AND STAFFING REQUIREMENTS The most “common practice” labor estimates just aren’t good enough to support capacity planning. What is really needed is an estimate of how the various skills will ramp up and taper off over the course of the project (see Figure 8.5).
  • 51. 43 Figure 8.5. Staffing skill categories by month. With this information, PPM systems can match individuals with their respective skills to the project’s needs at the time they are required and free them up when their work is done. It is important to recognize that one size does not fit all projects. For a large enterprise there might be several skill profiles or templates to support the different project types and methodologies. Typical methodology and project examples today include Agile, Traditional Waterfall, Package Implementation, Infrastructure, etc. The key point is to have just enough flexibility to provide adequate coverage but not so much that the organization becomes a slave to template creation and maintenance. Configuration within the SLIM tool is flexible enough to add, change, and delete labor categories and rates. It is also intuitive enough to allocate the buildup and ramp down of skill categories over time (see Figure 8.6).
  • 52. 44 Figure 8.6. Configuring skill categories. With a method to produce estimated skill allocation over time, it is possible to incorporate realistic demand into the planning process and match demand with the available capacity. The SLIM estimation tool has a PPM integration framework which allows SLIM to integrate with any PPM program (see Figure 8.7).
  • 53. 45 Figure 8.7. SLIM integration with PPM tools. The PPM integration allows SLIM to assess and adjust the planned resources and/ or start dates to projects already present in the PPM system or to those prior to entry. This feature can be particularly useful for projects that require further evaluation and validation. MATCH DEMAND TO CAPACITY Now we have a way to realistically estimate schedule, effort, cost and skill requirements over the duration of a project, and can feed that information into a PPM system. By implementing this discipline throughout the enterprise, it is possible to evaluate how demand matches capacity and determine whether they are out of sync. If we discover that they are out of alignment, we can evaluate practical options for matching demand and capacity. Let’s use an example to illustrate the process: Our example enterprise has 3 different data centers: one is located in the U.S., while the other two are in India and Ireland. The total capacity for these three centers is limited to 250 IT developers, and there are currently 35 projects that have been approved for production (see Figure 8.8).
  • 54. 46 Figure 8.8. Peak staffing over time for individual projects and aggregated by development center. Each of these projects is in a different stage of production, with some in the early planning stages, others beginning coding, and some that are approaching delivery. At any point in time, it is fairly typical to have a portfolio with projects at all of these production stages. Additionally, it is common for a portfolio to have a wide range of project scopes, and team sizes. Each project can be estimated individually, and they can be rolled up to show the aggregate data at either the data center level or the enterprise level to help determine the capacity and demand levels. For simplicity sake, we’ll examine at the enterprise level in this example. When the data is aggregated at this level, we notice that for a 9 month period, between August 2014 and May 2015, the demand for developers exceeds capacity by 65 Full Time Equivalents (FTEs), see Figure 8.9.
  • 55. 47 Figure 8.9. Demand exceeded capacity by 65 people for 9 months. When the demand for developers exceeds its capacity there are usually 3 options: 1. Eliminate projects (usually not a practical option since there is a definitive business need), 2. Push back the start dates on projects that have not yet begun, or 3. Make a select staffing reduction on projects in-progress or those yet to begin and relax their respective delivery dates.
  • 56. 48 Figure 8.10. Project start date delayed. In this example case, we chose option 2 and pushed back the start dates. In a relatively short period of time we were able to optimize the staffing to meet the capacity limit of 250 people. The resulting impact this had on the eight projects was a delay that lasted anywhere from 2 to 8 months (see Figure 8.10). If we want to assess the skill requirements and match those to our pool of available resources, we need to aggregate the skill categories to match that to our skill capacity.
  • 57. 49 Figure 8.11. Staffing resource profile. Figure 8.11 gives a graphic depiction of the necessary resources at the enterprise level. It shows the aggregated demand for each of the skill sets at various times within a 28 month period. This information is useful to have because it lays out what you will need to successfully complete the approved projects and compare them with the resources currently available. If there are imbalances between supply and demand, you now know what areas need to be supported and can take actions such as hiring or training additional employees to help fill the void. By having this kind of information available and understanding its significance, great progress in capacity planning can be realized by the IT organization. SUMMARY Capacity planning and demand management go hand in hand. To manage them effectively, one needs to be able to: 1. Realistically forecast demand early in the lifecycle, 2. Negotiate functionality, schedule and effort with business stakeholders when their expectations are unrealistic, 3. Have the ability to forecast effort by skill category, by month, or by week, and feed this information to PPM systems, and 4. Be in a position to perform quick what-if analyses on the portfolio when demand exceeds capacity. If you take action to address these issues, then you can have a best-in-class IT capacity planning solution for the enterprise.
  • 58. 50
  • 59. 51 CHAPTER 9. TRACKING, FORECASTING, EXECUTION, AND POST MORTEM _______________________________________ The previous chapters discussed the best practices involved in creating estimates. While creating estimates is an important and necessary skill in improving productivity; that is only half the battle. The second half is tracking actual performance against the estimate and reforecasting when significant changes occur. TRACKING Suppose that after much consideration, an organization puts forth an estimate with the intention of carrying it out as a project plan. At this point, many estimators would believe that they are done. However, in order to maximize the benefits of the estimate, it will be necessary to track the project’s progress through completion. While this may seem like a tedious process, project tracking allows for organizations to gain the greatest insight into their software development lifecycles. To do this, estimators will want to collect data on the current actuals for the following metrics at regular intervals:  Cumulative Size Produced – this metric is customizable and can include but is not limited to Source Lines of Code, Agile Stories, Screens, etc.  Monthly Effort – the Person Months or Person Hours expended thus far  Staff – the number of Full Time Equivalents currently billing time to the project  Defects – how many errors were discovered Depending on the length of the project’s schedule, it’s recommended to collect data on the actuals at the end of each month, or for shorter projects at the end of each week. This data can then be compared against the original estimate to track the project’s in-flight progress, as well as any deviations from the estimate. Utilizing these practices can increase accountability within the organization because current statuses are regularly maintained. Additionally, tracking these various metrics over time can help identify areas for improvement within an organization. For example, if the project’s actual data match the projected values from the original estimate in staffing and cumulative effort but not cumulative size, this observation could indicate a couple of potential scenarios (see Figure 9.1). One possible explanation might be that the organization has staffed the project with the correct number of people at a given point in time, but has not appropriately accounted for the skills necessary to complete the project. An excessive number of management personnel may have been staffed for the project, resulting in a decreased staffing allotment for the developers. With fewer developers staffed or those lacking the skills needed for the project, producing code at the estimated rate would be impossible and deviations from the original estimate would be expected.
  • 60. 52 Another possible explanation for the decreased code production is that the actual productivity of the organizations is in fact lower than originally estimated. There are a number of explanations for why this occurs. Introducing new tools, development methodologies, or team members impacts the development environment and can require additional time for developers to perform at the previous productivity level. The next section describes some potential solutions if this happens to your project. Figure 9.1. Tracking actuals against the planned values: Consumption vs. construction. FORECASTING AND EXECUTION Life is rarely predictable, and that holds true in software estimation as well. Even the best estimates cannot anticipate some of the curveballs that life throws at them. For instance, if several team members are pulled off the project and temporarily reassigned to another, it is unlikely that the project will progress as originally planned. In such situations, the best suggestion would be to reforecast the estimate. Similar to a GPS, SLIM is able to recalculate a new trajectory, or roadmap, if the project gets off track. It factors in what has already been done and re-estimates a new productivity based on the actual values entered. If a project drifts so far off course that the original plan is no longer feasible, a new plan can be implemented and briefed to stakeholders so that everyone has similar expectations (see Figure 9.2). In this chart we see the project’s plan in blue compared with the actual data collected in monthly intervals in red. In January, the amount of code produced was slightly below the quota outlined in the plan, yet the cumulative effort expended was above the allotted amount. Additionally,
  • 61. 53 they were finding more defects in the system than initially predicted. Since the project has begun to get off track from the original estimate, the wise choice would be to reforecast the project plan. The new forecast is displayed in white and shows that based on the current trajectory, the project should end about 2.5 months later and require 6,600 more person hours of effort than the original plan. Knowing this information early can allow time for orderly changes while still underway. Figure 9.2. Forecasting chart. One of the greatest benefits of this technique is that it provides transparency into the development process by showing the project’s progress at regular intervals. Development teams know how much functionality will have to be delivered at each interval, and can plan accordingly. If a project begins to drift off course, it’s much easier to determine this from the start and take measures to mitigate risk early. Additionally, as new data is added, SLIM reforecasts the plan like a GPS would recalculate the roadmap. If the new data shows improvements, it will be reflected in the forecast going forward, thus creating a refined learning system. By having this kind of insight and level of detail up front can dramatically improve accountability across the organization. POST MORTEM Once a project has reached completion, it’s very easy to move onto the next without a second thought. Regardless of whether the project went really well and the momentum is continuing or if the project was so utterly painful that the wounds are still fresh, a post mortem assessment is SEI Core Metrics Schedule 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 Oct '02 Dec Feb '03 Apr Jun Aug Oct Dec Feb '04 Apr Jun Aug Oct Dec Feb '05 Apr Jun Requiremts & D... Construct and T... Test & Evaluate Phases 87654321 321 87654 Milestones 1 - PDR 2 - INC_1 3 - INC_2 4 - INC_3 5 - ST 6 - TRR 7 - FAT 8 - 99R Milestones 1 - PDR 2 - INC_1 3 - INC_2 4 - INC_3 5 - ST 6 - TRR 7 - FAT 8 - 99R Cum Effort C&T 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 Oct '02 Dec Feb '03 Apr Jun Aug Oct Dec Feb '04 Apr Jun Aug Oct Dec Feb '05 Apr Jun 0 10 20 30 40 PHR(thousands) 87654321 321 Defects Found Moderate 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 Oct '02 Dec Feb '03 Apr Jun Aug Oct Dec Feb '04 Apr Jun Aug Oct Dec Feb '05 Apr Jun 0 5 10 15 20 25 30 35 Defects 87654321 321 Cum Eff SLOC 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 Oct '02 Dec Feb '03 Apr Jun Aug Oct Dec Feb '04 Apr Jun Aug Oct Dec Feb '05 Apr Jun 0 10 20 30 40 50 60 SLOC(thousands) 87654321 321 Current Plan Actuals Current Forecast Project: TechPro 5.0
  • 62. 54 always a valuable exercise. Post mortems provide opportunities for teams to discuss what went well and what areas could be improved. Additionally, post mortems allow teams to reconvene at the end of the project to collect the final data for the project repository. This newly completed project can be entered into SLIM along with the rest of the completed project data. A new set of custom trends can then be created using the most recently added historical data, which can be used for more accurate estimates in the future. You will find that over time, this process of collecting historical data, updating trends, and using those trends to estimate future projects allows the estimation process to come full circle, refining itself each time. SUMMARY While creating estimates is a great way to start a project off on the right foot, using parametric methods to track and monitor your project’s progress provides even greater insight into the development of your project. Knowing the status of a project inflight and having the ability to share that with developers and stakeholders, when most can merely guess, is extremely beneficial and puts project managers in a much more powerful position. The project can be tracked all the way through completion, at which point, a post mortem assessment can be done to collect data and further refine the estimation process. Using this model creates a refinement cycle whereby collecting accurate data leads to creating more accurate estimates.
  • 63. 55 CHAPTER 10. UNDERSTANDING QUALITY AND RELIABILITY _______________________________________ One of the most overlooked but important areas of software estimation, measurement, and assessment is quality. It often is not considered or even discussed during the early planning stages of a development project, but it’s almost always the ultimate criteria for when a product is ready to ship or deploy. Therefore, it needs to be part of the expectation-setting conversation from the outset of the project. So how can we talk about quality? It can be measured a number of ways but two in particular give excellent insights into the stability of the product. They are: 1. The number of errors discovered in the system during testing, and 2. The Mean Time to Defect (MTTD), or the amount of time between errors discovered prior to and after delivery. The reason we like these two measures is that they both relate to product stability, a critical issue as the release date approaches. They are objective, measurable, and can usually be derived from most organizations’ current quality monitoring systems without too much trouble. Generally, having fewer errors and a higher MTTD is associated with better overall quality. While having the highest quality possible may not always be a primary concern for stakeholders, the reliability of the project must meet some minimum standards before it can be shipped to the customer. This means that at delivery, the project is about 95% defect free, or the application can run for about 1 day without crashing. Another good rule of thumb is that the software typically will be of minimum acceptable reliability when testers are finding fewer than 20 errors per month. In other words, the product will run about an 8 hour work day. Of course this rule of thumb is mostly applicable for commercial IT applications. Industrial and military embedded applications require a higher degree of reliability. THE RAYLEIGH DEFECT MODEL The QSM defect estimation approach uses the Rayleigh function to forecast the discovery rate of defects as a function of time throughout the software development process. The Rayleigh function was discovered by the English physicist Lord Rayleigh in his work related to scattering of acoustic and electro‐magnetic waves. We have found in our research that a Rayleigh reliability model closely approximates the actual profile of defect data collected from software development efforts. In the QSM reliability modeling approach, the Rayleigh equation is used to predict the number of defects discovered over time. The QSM application of the Rayleigh model has been formulated to cover the duration of time from the High Level Design Review (HLDR ‐ High Level Design is
  • 64. 56 Complete) until 99.9% of all the defects have been discovered. A sample Rayleigh defect estimate is shown in Figure 10.1. Figure 10.1. Sample Rayleigh defect estimate. Note that the peak of the curve occurs early in the build and test phase. This means that a large number of the total defects are created and discovered early in the project. These defects are mostly requirements, design and unit coding defects. If they are not found they will surface later in the project resulting in extensive rework. Milestone 10 is declared to be the point in time when 99.9% of the defects have been discovered. Less than 5% of the organizations that QSM has worked with record defect data during the detailed design phase. Industry researchers claim that it can cost 3‐10 times more to fix a defect found during system test rather than during design or coding, so one could make a compelling case to start measuring and taking action earlier in the process. Simple extensions of the model provide other useful information. For example, defect priority classes can be specified as percentages of the total curve. This allows the model to predict defects by severity categories over time. This is illustrated in Figure 10.2.
  • 65. 57 Figure 10.2. Rayleigh defect model broken out by defect severity class. A defect estimate could be thought of as a plan. For a particular set of conditions (size, complexity, efficiency, staffing, etc.) a planned curve could be generated. A manager could use this as a rough gauge of performance to see if his project is performing consistently with the plan and by association with comparable historic projects. If there are significant deviations, this would probably cause the manager to investigate and, if justified, take remedial action. Figure 10.3 shows how one can use the defect discovery estimate to track and compare actuals. Obviously, the actual measurements are a little noisier than the estimate but they track the general pattern nicely and give confidence that the error discovery rate will be below 20 per month, our minimum acceptable delivery criteria, at the schedule end of the project. Defect Rate Quick Estimate Wizard Solution 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 Jul '15 Aug Sep Oct Nov Dec Jan '16 Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 0 25 50 75 100 125 150 DefectRate 1098765432 Cosmetic Tolerable Moderate Serious Critical Project: Single Release Estimate
  • 66. 58 Figure 10.3. Defect discovery rate plan with actuals plotted. DEFECT MODEL DRIVERS There are specific inputs that determine the duration and magnitude of the Rayleigh defect model. The inputs enable the model to provide an accurate forecast for a given situation. There are three macro parameters that the QSM model uses:  Size (new and modified)  Productivity Index  Peak Staffing These driving factors impact the defect behavior patterns that we see with regards to software projects. Size Historically, we have seen that as project size increases, so do the number of defects present in the system (see Figure 10.4). Stated simply, building a larger project provides more opportunities for developers to inject defects into the system, and also requires more testing to be completed. This rate of defect increase is close to linear. Similarly, as size increases the MTTD decreases. This is due to the increased number of errors in the system. Larger projects tend to have lower reliabilities because there is less time between defects. These trends are typical for the industry. Total Defects Found 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 Oct '02 Nov Dec Jan '03 Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan '04 Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan '05 Feb Mar Apr May Jun 0 20 40 60 80 100 120 140 Defects 87654321 321 Current Plan Actuals Project: TechPro 5.0
  • 67. 59 Figure 10.4. As size increases so do the number of defects. Productivity Index Productivity also tends to have a great impact in the overall quality of a system. Historic data has shown that the number of defects discovered exponentially decreases as the Productivity Index increases. Figure 10.5 shows the cumulative number of defects discovered for the same sized software application using two different PI’s (17 and 21 respectively). The project with the higher PI not only delivers the application 9 months faster, but also discovers about 360 fewer errors in total. It makes sense that when development teams improve, they tend to make fewer errors to begin with, thus decreasing the number of errors found during testing. Operating at a higher productivity level can drastically increase software quality.
  • 68. 60 Figure 10.5. Comparison of defects produced for the same size system using different PI’s. Staffing The size of the development team also can impact the quality of a system. As discussed previously in Chapters 3 and 4, using larger teams produces more errors than using smaller teams. As shown in Figure 10.6, when comparing a large team (red) with a small team (grey) at the same project sizes, the small teams produce between 50-65 fewer errors than large teams at all project sizes. Additionally, they paid little, if any, schedule penalty and used significantly less effort. This finding can be especially useful when looking to identify areas of waste within an organization, because it shows that adding resources to a project does not always improve its quality.
  • 69. 61 Figure 10.6. Small teams produce fewer errors than large teams at all project sizes. SUMMARY To conclude this section, software reliability and quality are two areas that should be addressed in the expectation setting and project negotiation stages of a project. As a leader there are several strategies that you can use to improve reliability. Keep the developed size as small as possible, use smaller teams of people, and make regular investments in your environment to improve the efficiency of your development shop. All of these actions will pay reliability and quality dividends.
  • 70. 62
  • 71. 63 CHAPTER 11. WHAT DOES IT TAKE TO SUCCESSFULLY IMPLEMENT ESTIMATION? _______________________________________ It doesn’t take long for an individual or small team to achieve quick wins implementing the estimation best practices outlined in the previous chapters. However, that initial success is always at risk of becoming derailed when a key individual leaves the organization, unless those best practices are institutionalized (i.e. fully embraced by the organizational culture, supported by a majority of stakeholders, and incorporated into the organizational process). So what needs to happen if you want to actually implement an effective estimation and measurement function? Well it is going to take some determination and hard work but the rewards are well worth it! An “Estimation Center of Excellence” (ECoE) is an excellent way to operationalize the concepts that we have been discussing to a structure that can support the needs of an enterprise. The ECoE encompasses aspects of People, Process, and Tools such that all three of these areas are incorporated into the planning and execution process. The most common organizational structures for an ECoE include centralized, distributed, and a hybrid “spoke and hub,” but the method selected really depends on the organization. It’s important to find a structure that will satisfy your culture and business decision making needs. Sometimes the function is housed in an existing part of the operation, like a project management office PMO, while others prefer that it be its own entity. Here are some implementation issues that need to be considered: 1. How will this fit into our organization? 2. What is the best structure to support our needs and decision making? 3. What people will be needed and what skills do they need to possess? 4. What tooling will be required? 5. How long will it take to stand up the operation? 6. What ROI can be expected from this endeavor? 7. How do you overcome the resistance to change? We have found that best implementations usually follow a 4 stage process. These four stages are: 1. Stage I – Requirement Definition 2. Stage II – Design and Implement 3. Stage III – Launch and Pilot Operation 4. Stage IV – Transition to Full Scale Operation During each stage, people, process, and tooling activities are addressed. Here is a brief description of what takes place during each of the implementation stages.
  • 72. 64 STAGE I – REQUIREMENTS DEFINITION During this stage, one identifies the major pain points and goals of the organization and builds a business case for addressing issues. A charter is developed to identify the major stakeholders in the ECoE implementation and the ground rules that they will follow. The current estimation process maturity is assessed to establish a baseline and starting point of departure. From there, the tooling as well as the various skill sets of the ECoE staff are identified and advertised. Finally, a change management strategy is designed. STAGE II – EcoE DESIGN AND DEVELOPMENT During this stage, the ECoE staff are hired and trained. Detailed business processes are defined and service level agreements are established. Next, the estimation tooling is customized and templates are created to support the estimation process. Additionally, a historical data repository is set up to support estimation and business case ROI analysis. Several pilot estimates will be performed to gain experience and fine tune the estimation methods. This stage will include regular information briefings to individuals throughout the organization to garner support and demonstrate the value of this solution. STAGE III – EcoE LAUNCH AND PILOT OPERATION During this phase the ECoE becomes operational. ECoE staff are mentored as they gain experience, working towards a formal estimation expert certification. The tooling templates and processes are adjusted as necessary based on feedback from operation use. Training sessions are conducted for new users, as required, if a distributed or hub and spoke model are implemented. Sharing circles are also implemented to share knowledge and practical experience throughout the estimation community. Case studies and other findings will continue to be briefed, thus showing the value of the ECoE. STAGE IV – FULL OPERATION The ECoE is fully operational. The tools and processes will continue to be improved based on newly completed projects and operational experience. Additional staff training and certification are conducted on an as-needed basis. In our experience it can take as little as 6 months or up to 15 months to complete the first three stages depending on size and complexity of the organization. Figure 11.1 is a good example of an ECoE implementation in a large organization.
  • 73. 65 Figure 11.1. Example Estimation Center of Excellence Implementation ECoE FOCUS AREAS The ECoE can have different areas of focus based on the needs of the organization. They are: 1. The Internal Development ECoE 2. The Acquisition and Vendor Management ECoE 3. The Oversight ECoE The Internal ECoE’s primary focus is on estimation, stakeholder negotiation, risk assessment, resource management, capacity planning, and business decision support. The Acquisition and Vendor Management ECoE focuses on ensuring successful procurements of outsourced projects. It does this by providing a framework for establishing a realistic “should cost” analysis and method for quantifying vendor bids. This can then be used to select vendors that put forth realistic proposals, and quantitatively monitor their execution so that there are no surprises along the way. The Oversight ECoE typically operates at the portfolio level and provides executive level oversight. It provides independent reviews at key points during the development lifecycle process, to ensure that the project has a realistic estimate and is proceeding under control. Often special emphasis is placed on high-risk and/ or high-visibility projects.
  • 74. 66 RETURN ON INVESTMENT Your return will depend on the size of your organization, and the size and volume of projects that are subject to ECoE analysis. Below is a chart that shows what others have achieved. Figure 11.2. Return on Investment for using SLIM. SUMMARY Adopting an Estimation Center of Excellence is a strategic, long-term investment rather than a quick fix. Leveraging defensible metrics and greater quantitative analysis will help your organization gain more insight into its own productivity, both internal and external, as well as its estimation maturity while better positioning it to plan, prioritize, track and empirically assess the interrelated variables of project size, cost, quality, and duration related to these projects. Before making drastic changes such as those needed to properly implement a similar change in development practices, invest time at all levels of the organization to fully understand the task at hand and assess how long it will take to reap the benefits and achieve the expected return on investment. Making deliberate, fully-informed decisions will ultimately lead to better outcomes.
  • 75. 67 CHAPTER 12. SUMMING IT UP _______________________________________ If you’ve stayed with us this far, you’ll know that there is a lot to be gained from incorporating top- down estimation into your current software development practices. Before leaving you, we wanted to recap some of our main points. In any type of project, software development or otherwise, accountability is essential for success. By establishing some expectations up front, the developers will know what they are responsible for and the stakeholders will know when the final product should be ready. However, without quantitative methods to measure productivity this task is much easier said than done. A good estimate will provide the framework necessary for establishing expectations and keeping everyone accountable. To get to that point, it’s critical to measure not just the consumption of the project (i.e. how much money has been spent), but also the construction (i.e. how much functionality has been built). Monitoring and tracking both of these together will provide a holistic view of the project’s progress and can allow teams to adapt to changes in-flight, should they be necessary. Understanding how the two SLIM algorithms function is key to making business decisions about your projects. The law of tradeoffs states that there are numerous ways that a project can be accomplished by adjusting the schedule and the effort. Estimators can create several what-if scenarios which can be presented as options to stakeholders and decision-makers. In essence, they become a vital negotiation tool because they back your proposals with quantitative data. Additionally, presenting multiple options to stakeholders inadvertently solicits their participation in the decision-making process, thus shaping better project outcomes overall. One of the greatest benefits of top-down estimation is that you can start creating more accurate estimates right away and the results are immediate. As you continue to estimate over time, the benefits compound even more (see Figure 12.1). Improving resource and demand management can free up staffing resources for other projects, thus increasing productivity and creating a higher utilization of staff. Figure 12.1. The benefits of top-down software estimation.