SlideShare ist ein Scribd-Unternehmen logo
1 von 4
What is earned value analysis?
At the root of earned value analysis are three fundamental values calculated for each task:
 The budgeted cost of tasks as scheduled in the project plan, based on the costs of resources assigned to those tasks, plus any fixed
costs associated with the tasks. Called "the budgeted cost of work scheduled," BCWS is the baseline cost up to the status date you
choose. For example, the total planned budget for a 4-day task is $100 and it starts on a Monday. If the status date is set to the
following Wednesday, the BCWS is $75.
 The actual cost required to complete all or some portion of the tasks, up to the status date. This is the actual cost of work performed
(ACWP). For example, if the 4-day task actually incurs a total cost of $35 during each of the first 2 days, the ACWP for this period is $70
(but the BCWS is still $75).
 The value of the work performed by the status date, measured in currency. This is literally the value earned by the work performed and
is called the budgeted cost of work performed (BCWP). For example, if after 2 days 60% percent of the work on a task has been
completed, you might expect to have spent 60 percent of the total task budget, or $60.
With me, so far? Let's go on.
Earned value analysis is always specific to a status date you choose. You may select the current date, a date in the past, or a date in the
future. Most of the time, you'll set the status date to the date you last updated project progress. For example, if the current day is
Tuesday, 9/12, but the project was last updated with progress on Friday, 9/8, you'd set the status date to Friday, 9/8.
Here is one example of how to analyze project performance with earned value analysis. Let's say a task has a budgeted cost (B CWS) of
$100, and by the status date it is 40 percent complete. The earned value (BCWP) is $40, but the scheduled value (BCWS) at the status
date is $50. This tells you that the task is behind schedule—less value has been earned than was planned. Let's also say that the task's
actual cost (ACWP) at the status date is $60, perhaps because a more expensive resource was assigned to the task. This tells you that the
task is also over budget—more cost has been incurred than was planned. You can see how powerful such an analysis can be. The earlier
in a project's life cycle you identify such discrepancies between ACWP, BCWP and BCWS, the sooner you can take steps to remedy the
problem.
One common way of visualizing the key values of earned value analysis is to use a chart. Start with a simple chart showing a steady
accumulation of cost over the lifetime of a project:
The vertical y-axis shows the projected cumulative cost for a project.
The horizontal x-axis shows time.
The planned budget for this project shows a steady expenditure over the lifetime of the project. This line represents the cumulative
baseline cost.
After work on the project has begun, a chart of the key values of earned value analysis may look like this:
The status date determines the values Project calculates.
The actual cost (ACWP) of this project has exceeded the budgeted cost.
The earned value (BCWP) reflects the true value of the work performed. In this case, the value of the work performed is less than the
amount spent to perform that work.
What else does earned value measure?
In addition to measuring BCWS, ACWP, and BCWP, earned value analysis measures:
 Cost variance (CV)—the difference between a task's estimated cost and its actual cost (the formula CV = BCWP - ACWP). Take our
earlier example where the total planned budget for a 4-day task is $100 and it starts on a Monday. When the status date is set to the
following Wednesday, the BCWS is $75, the ACWP for this period is $70, and the BCWP is $60. In that case, the task's CV is -$10.
 Schedule variance (SV)—the difference between the current progress and the scheduled progress of a task, in terms of cost (the formula
SV = BCWP - BCWS). In the example above, the task's SV is -$15.
 The cost performance index (CPI)—the ratio of budgeted costs to actual costs (the formula CPI = BCWP / ACWP). In the example above,
the task's CPI is about .86, or 86 percent.
 The schedule performance index (SPI)—the ratio of work performed to work scheduled (the formula SPI = BCWP / BCWS). In the
example above, the task's SPI is .80, or 80 percent.
 The to complete performance index (TCPI)—the ratio of the work remaining to be done to funds remaining to be spent as of the status
date, or budget at completion (the formula TCPI = [BAC - BCWP] / [BAC - ACWP]).
How do I interpret earned value?
Earned value indicators that are variances or ratios can help you determine if there is enough money left in the budget and if the project
will finish on time.
Variances, such as a cost variance (CV), can be either positive or negative:
 A positive variance indicates that the project is ahead of schedule or under budget. Positive variances might enable you to reallocate
money and resources from tasks or projects with positive variances to tasks or projects with negative variances.
 A negative variance indicates that the project is behind schedule or over budget and you need to take action. If a task or project has a
negative CV, you might have to increase your budget or accept reduced profit margins.
Ratios, such as the cost performance index (CPI) and the schedule performance index (SPI), can be greater than 1 or less than 1:
 A value that's greater than 1 indicates that the project is ahead of schedule or under budget.
 A value that's less than 1 indicates that you're behind schedule or over budget. For example, an SPI of 1.5 means that you've taken only
67 percent of the planned time to complete a portion of a task in a given time period, and a CPI of 0.8 means that you've spent
25 percent more time on a task than was planned.
How does % complete versus physical % complete
affect earned value?
You can specify whether Project should use each task's percent complete value or physical percent complete value for earned value
calculations related to BCWP. (Remember, other values are calculated from BCWP, so your decision affects the entire earned value
analysis.)
 Percent complete may be calculated by Project or entered directly by you, depending on how you track actual work.
 Physical percent complete is always entered directly by you. Use physical percent complete when percent complete would not be an
accurate measure of real work performed or remaining.
Here's a simple example of how the two values may differ: a project of building a stone wall that consists of 100 stones stacked 5 high.
The first row of 20 stones can be laid in 20 minutes, but the second row would take 25 minutes because you have to lift the stones up
one row higher, so it takes a little longer. The third row would take 30 minutes, the fourth 35 minutes, and the last row would take
40 minutes to lay—150 minutes total. After laying the first three rows, the project could be said to be 60 percent physically complete
(you laid 60 of 100 stones). However, you only spent 75 of 150 minutes; so in terms of duration, the job is only 50 percent complete.
Depending on how you get paid for the work—how the value is earned (by the stone or by the hour)—you may choose the percent
complete value or the physical percent complete value to properly reflect this in the earned value analysis.
Which earned value quantities can I show or
calculate in Project?
With Project, you can show:
 Actual cost of work performed (ACWP) shows actual costs incurred for work already performed by a resource on a task, up to the
project status date or today's date. Normally Project correlates actual costs with actual work. Only if you enter actual costs independent
of actual work or change resource pay rates will actual cost be out of step with scheduled cost.
 Budget at completion (BAC) shows an estimate of the total project cost.
 Budgeted cost of work performed (BCWP) shows how much of the budget should have been spent given the actual duration of the task.
BCWP is also referred to as "earned value." Note that Project calculates BCWP at the task level differently than it does at the assignment
level. For best results, use the task-level BCWP values, which are the values Project rolls up to summary task and the project summary
task BCWP values. This value is calculated for each individual task but analyzed at an aggregate level (typically at the project level).
 Budgeted cost of work scheduled (BCWS) shows how much of the budget should have been spent in view of the baseline cost of the
task, assignment, or resource. BCWS is calculated as the cumulative timephased baseline costs up to the status date or today's date.
(Budgeted cost values are stored in the baseline fields, or if you've saved multiple baselines, in fields Baseline1 through Baseline10.)
 Cost variance (CV) shows the difference between the budgeted cost of work performed (BCWP) on a task and its actual cost (actual cost
of work performed or ACWP). If the CV is positive, the cost is currently under the budgeted (or baseline) amount; if the CV is negative,
the task is currently over budget.
 Schedule variance (SV) shows the difference between the budgeted cost of work performed (BCWP) and the budgeted cost of work
scheduled (BCWS). If the SV is positive, the project is ahead of schedule in cost terms; if the SV is negative, the project is behind
schedule in cost terms.
 Variance at completion (VAC) shows the difference between the budget at completion (BAC) and the estimate at completion (EAC). In
Project, the EAC is the Total Cost field and the BAC is the Baseline Cost field from the associated baseline.
 Cost performance index (CPI) is the ratio of budgeted, or baseline, costs of work performed to actual costs of work performed
(BCWP/ACWP).
 Cumulative cost performance index (CPI) is the sum of the BCWP for all tasks divided by the sum of the actual costs of work performed
(ACWP) for all tasks. Cumulative CPI is often used to predict whether a project will go over budget and by how much.
 Schedule performance index (SPI) is the ratio of work performed to work scheduled (BCWP/BCWS). SPI is often used to estimate the
project completion date.
 Estimate at completion (EAC) is the expected total cost of a task or project, based on performance as of the status date. EAC is also
called forecast at completion, and is calculated like this: EAC = ACWP + (BAC - BCWP) / CPI.
 To complete performance index (TCPI) is the ratio of remaining available budget to be spent to the remaining scheduled cost as of the
status date. TCPI is calculated like this: TCPI = (BAC - BCWP) / (BAC - ACWP). A TCPI value greater than 1 indicates good projected
performance for remaining work; less than 1 indicates poor projected performance.
Where in Project do I see earned value data?
You can see earned value information in any sheet view by applying the Earned Value table or the Earned Value Cost Indicators table.
 The Earned Value table shows you BCWS, BCWP, ACWP, SV, CV, EAC, BAC, and VAC. Use this table to see consolidated earned value
information, including the key variance fields. Use EAC, BAC, and VAC to evaluate the difference between your scheduled and budgeted
costs. Compare CV, which shows the difference between your budgeted and actual cost?of work, with SV, which shows the difference
between the budgeted cost of work and the actual cost of work.
 The Earned Value Cost Indicators table shows you BCWS, BCWP, CV, CV%, CPI, BAC, EAC, VAC, and TCPI. Use this table to analyze cost
variances. Check the CPI and TCPI to see how the project is progressing against its budget and how the rate of work compares with the
expected rate. If CPI is less than than 1, you are getting less work per dollar than planned. The TCPI tells you how much of an increase in
performance you'll need on the remaining tasks in order to keep within budget.

Weitere ähnliche Inhalte

Was ist angesagt?

Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)Harshit Mahajan
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value AnalysisSaqib Raza
 
Earned value analysis - presentation
Earned value analysis  -  presentationEarned value analysis  -  presentation
Earned value analysis - presentationProPM Academy
 
EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...Fahad Ali
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)Ejaz Bhatti
 
Earned value analysis training
Earned value analysis trainingEarned value analysis training
Earned value analysis trainingPaul King
 
Earned value management (EVM)
Earned value management (EVM)Earned value management (EVM)
Earned value management (EVM)Joshua Render
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)Glen Alleman
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysisNikhil Raj
 
Earned value
Earned valueEarned value
Earned valueOliver
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value ManagementMatt Stehling
 
Earned Value Reporting
Earned Value ReportingEarned Value Reporting
Earned Value Reportingcfreema7
 

Was ist angesagt? (20)

Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Earned value analysis - presentation
Earned value analysis  -  presentationEarned value analysis  -  presentation
Earned value analysis - presentation
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
 
EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...
 
Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Project Management EVM & SCBA
 
Earned Value
Earned ValueEarned Value
Earned Value
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)
 
Earned value analysis training
Earned value analysis trainingEarned value analysis training
Earned value analysis training
 
Earned value management (EVM)
Earned value management (EVM)Earned value management (EVM)
Earned value management (EVM)
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
 
Earned value management
Earned value managementEarned value management
Earned value management
 
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSISPROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
 
Earned value
Earned valueEarned value
Earned value
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Earned Value Reporting
Earned Value ReportingEarned Value Reporting
Earned Value Reporting
 

Andere mochten auch

Literate environment assignment
Literate environment assignmentLiterate environment assignment
Literate environment assignmentlschipper
 
Communication classroom talk
Communication classroom talkCommunication classroom talk
Communication classroom talktymchatyn
 
Estándares inalambricos
Estándares inalambricosEstándares inalambricos
Estándares inalambricosRIITMO
 
Archivo de tramite (libro enba)
Archivo de tramite (libro enba)Archivo de tramite (libro enba)
Archivo de tramite (libro enba)Monritas
 
Resolución CFE Nº 202/13.LA EDUCACIÓN DOMICILIARIA Y HOSPITALARIA
Resolución CFE Nº 202/13.LA EDUCACIÓN DOMICILIARIA Y HOSPITALARIAResolución CFE Nº 202/13.LA EDUCACIÓN DOMICILIARIA Y HOSPITALARIA
Resolución CFE Nº 202/13.LA EDUCACIÓN DOMICILIARIA Y HOSPITALARIAPedro Roberto Casanova
 

Andere mochten auch (7)

Literate environment assignment
Literate environment assignmentLiterate environment assignment
Literate environment assignment
 
Trombosis venosa profunda
Trombosis venosa profundaTrombosis venosa profunda
Trombosis venosa profunda
 
Communication classroom talk
Communication classroom talkCommunication classroom talk
Communication classroom talk
 
Escuela Hopitalaria Domiciliaria
Escuela Hopitalaria DomiciliariaEscuela Hopitalaria Domiciliaria
Escuela Hopitalaria Domiciliaria
 
Estándares inalambricos
Estándares inalambricosEstándares inalambricos
Estándares inalambricos
 
Archivo de tramite (libro enba)
Archivo de tramite (libro enba)Archivo de tramite (libro enba)
Archivo de tramite (libro enba)
 
Resolución CFE Nº 202/13.LA EDUCACIÓN DOMICILIARIA Y HOSPITALARIA
Resolución CFE Nº 202/13.LA EDUCACIÓN DOMICILIARIA Y HOSPITALARIAResolución CFE Nº 202/13.LA EDUCACIÓN DOMICILIARIA Y HOSPITALARIA
Resolución CFE Nº 202/13.LA EDUCACIÓN DOMICILIARIA Y HOSPITALARIA
 

Ähnlich wie What Is Earned Value Analysis

5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.pptProfDrAnbalaganChinn
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxsagarlesley
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisBECM, RUET, Bangladesh
 
Primavera Calender and Earned Value.pdf..
Primavera Calender and Earned Value.pdf..Primavera Calender and Earned Value.pdf..
Primavera Calender and Earned Value.pdf..EngrMuhammadJavidNaw
 
Your Projects May Be Robbing You Blind
Your Projects May Be Robbing You BlindYour Projects May Be Robbing You Blind
Your Projects May Be Robbing You BlindEd Kozak
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneWaleed Hamdy Albana
 
Earned Value Probabilistic Forecasting Using Monte Carlo Simulation
Earned Value Probabilistic Forecasting Using Monte Carlo SimulationEarned Value Probabilistic Forecasting Using Monte Carlo Simulation
Earned Value Probabilistic Forecasting Using Monte Carlo SimulationRicardo Viana Vargas
 
Mark blum ubc tool box execution - powerpoint presentation
Mark blum   ubc tool box execution - powerpoint presentationMark blum   ubc tool box execution - powerpoint presentation
Mark blum ubc tool box execution - powerpoint presentationCDN_Irony
 
Ch 9 project monitoring & control updated
Ch 9 project monitoring & control updatedCh 9 project monitoring & control updated
Ch 9 project monitoring & control updatedFarhana Rehman
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
Develop a network schedule for your project using either the arrow.docx
Develop a network schedule for your project using either the arrow.docxDevelop a network schedule for your project using either the arrow.docx
Develop a network schedule for your project using either the arrow.docxkhenry4
 
EARNED VALUE MANAGEMENT ANALYS 1.ppt
EARNED VALUE MANAGEMENT ANALYS 1.pptEARNED VALUE MANAGEMENT ANALYS 1.ppt
EARNED VALUE MANAGEMENT ANALYS 1.pptBetshaTizazu1
 
PF_EarnedValuePresentation.ppt
PF_EarnedValuePresentation.pptPF_EarnedValuePresentation.ppt
PF_EarnedValuePresentation.pptyogeshagrawal84
 

Ähnlich wie What Is Earned Value Analysis (20)

5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
Project monitoring lecture 1
Project monitoring lecture 1Project monitoring lecture 1
Project monitoring lecture 1
 
Primavera Calender and Earned Value.pdf..
Primavera Calender and Earned Value.pdf..Primavera Calender and Earned Value.pdf..
Primavera Calender and Earned Value.pdf..
 
Your Projects May Be Robbing You Blind
Your Projects May Be Robbing You BlindYour Projects May Be Robbing You Blind
Your Projects May Be Robbing You Blind
 
Project cost control
Project cost controlProject cost control
Project cost control
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part One
 
Earned Value Probabilistic Forecasting Using Monte Carlo Simulation
Earned Value Probabilistic Forecasting Using Monte Carlo SimulationEarned Value Probabilistic Forecasting Using Monte Carlo Simulation
Earned Value Probabilistic Forecasting Using Monte Carlo Simulation
 
Mark blum ubc tool box execution - powerpoint presentation
Mark blum   ubc tool box execution - powerpoint presentationMark blum   ubc tool box execution - powerpoint presentation
Mark blum ubc tool box execution - powerpoint presentation
 
Basics of EVM.pdf
Basics of  EVM.pdfBasics of  EVM.pdf
Basics of EVM.pdf
 
Ch 9 project monitoring & control updated
Ch 9 project monitoring & control updatedCh 9 project monitoring & control updated
Ch 9 project monitoring & control updated
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Develop a network schedule for your project using either the arrow.docx
Develop a network schedule for your project using either the arrow.docxDevelop a network schedule for your project using either the arrow.docx
Develop a network schedule for your project using either the arrow.docx
 
Earned value
Earned valueEarned value
Earned value
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
EARNED VALUE MANAGEMENT ANALYS 1.ppt
EARNED VALUE MANAGEMENT ANALYS 1.pptEARNED VALUE MANAGEMENT ANALYS 1.ppt
EARNED VALUE MANAGEMENT ANALYS 1.ppt
 
PF_EarnedValuePresentation.ppt
PF_EarnedValuePresentation.pptPF_EarnedValuePresentation.ppt
PF_EarnedValuePresentation.ppt
 

What Is Earned Value Analysis

  • 1. What is earned value analysis? At the root of earned value analysis are three fundamental values calculated for each task:  The budgeted cost of tasks as scheduled in the project plan, based on the costs of resources assigned to those tasks, plus any fixed costs associated with the tasks. Called "the budgeted cost of work scheduled," BCWS is the baseline cost up to the status date you choose. For example, the total planned budget for a 4-day task is $100 and it starts on a Monday. If the status date is set to the following Wednesday, the BCWS is $75.  The actual cost required to complete all or some portion of the tasks, up to the status date. This is the actual cost of work performed (ACWP). For example, if the 4-day task actually incurs a total cost of $35 during each of the first 2 days, the ACWP for this period is $70 (but the BCWS is still $75).  The value of the work performed by the status date, measured in currency. This is literally the value earned by the work performed and is called the budgeted cost of work performed (BCWP). For example, if after 2 days 60% percent of the work on a task has been completed, you might expect to have spent 60 percent of the total task budget, or $60. With me, so far? Let's go on. Earned value analysis is always specific to a status date you choose. You may select the current date, a date in the past, or a date in the future. Most of the time, you'll set the status date to the date you last updated project progress. For example, if the current day is Tuesday, 9/12, but the project was last updated with progress on Friday, 9/8, you'd set the status date to Friday, 9/8. Here is one example of how to analyze project performance with earned value analysis. Let's say a task has a budgeted cost (B CWS) of $100, and by the status date it is 40 percent complete. The earned value (BCWP) is $40, but the scheduled value (BCWS) at the status date is $50. This tells you that the task is behind schedule—less value has been earned than was planned. Let's also say that the task's actual cost (ACWP) at the status date is $60, perhaps because a more expensive resource was assigned to the task. This tells you that the task is also over budget—more cost has been incurred than was planned. You can see how powerful such an analysis can be. The earlier in a project's life cycle you identify such discrepancies between ACWP, BCWP and BCWS, the sooner you can take steps to remedy the problem. One common way of visualizing the key values of earned value analysis is to use a chart. Start with a simple chart showing a steady accumulation of cost over the lifetime of a project: The vertical y-axis shows the projected cumulative cost for a project. The horizontal x-axis shows time. The planned budget for this project shows a steady expenditure over the lifetime of the project. This line represents the cumulative baseline cost. After work on the project has begun, a chart of the key values of earned value analysis may look like this:
  • 2. The status date determines the values Project calculates. The actual cost (ACWP) of this project has exceeded the budgeted cost. The earned value (BCWP) reflects the true value of the work performed. In this case, the value of the work performed is less than the amount spent to perform that work. What else does earned value measure? In addition to measuring BCWS, ACWP, and BCWP, earned value analysis measures:  Cost variance (CV)—the difference between a task's estimated cost and its actual cost (the formula CV = BCWP - ACWP). Take our earlier example where the total planned budget for a 4-day task is $100 and it starts on a Monday. When the status date is set to the following Wednesday, the BCWS is $75, the ACWP for this period is $70, and the BCWP is $60. In that case, the task's CV is -$10.  Schedule variance (SV)—the difference between the current progress and the scheduled progress of a task, in terms of cost (the formula SV = BCWP - BCWS). In the example above, the task's SV is -$15.  The cost performance index (CPI)—the ratio of budgeted costs to actual costs (the formula CPI = BCWP / ACWP). In the example above, the task's CPI is about .86, or 86 percent.  The schedule performance index (SPI)—the ratio of work performed to work scheduled (the formula SPI = BCWP / BCWS). In the example above, the task's SPI is .80, or 80 percent.  The to complete performance index (TCPI)—the ratio of the work remaining to be done to funds remaining to be spent as of the status date, or budget at completion (the formula TCPI = [BAC - BCWP] / [BAC - ACWP]). How do I interpret earned value? Earned value indicators that are variances or ratios can help you determine if there is enough money left in the budget and if the project will finish on time. Variances, such as a cost variance (CV), can be either positive or negative:  A positive variance indicates that the project is ahead of schedule or under budget. Positive variances might enable you to reallocate money and resources from tasks or projects with positive variances to tasks or projects with negative variances.  A negative variance indicates that the project is behind schedule or over budget and you need to take action. If a task or project has a negative CV, you might have to increase your budget or accept reduced profit margins. Ratios, such as the cost performance index (CPI) and the schedule performance index (SPI), can be greater than 1 or less than 1:  A value that's greater than 1 indicates that the project is ahead of schedule or under budget.  A value that's less than 1 indicates that you're behind schedule or over budget. For example, an SPI of 1.5 means that you've taken only 67 percent of the planned time to complete a portion of a task in a given time period, and a CPI of 0.8 means that you've spent 25 percent more time on a task than was planned.
  • 3. How does % complete versus physical % complete affect earned value? You can specify whether Project should use each task's percent complete value or physical percent complete value for earned value calculations related to BCWP. (Remember, other values are calculated from BCWP, so your decision affects the entire earned value analysis.)  Percent complete may be calculated by Project or entered directly by you, depending on how you track actual work.  Physical percent complete is always entered directly by you. Use physical percent complete when percent complete would not be an accurate measure of real work performed or remaining. Here's a simple example of how the two values may differ: a project of building a stone wall that consists of 100 stones stacked 5 high. The first row of 20 stones can be laid in 20 minutes, but the second row would take 25 minutes because you have to lift the stones up one row higher, so it takes a little longer. The third row would take 30 minutes, the fourth 35 minutes, and the last row would take 40 minutes to lay—150 minutes total. After laying the first three rows, the project could be said to be 60 percent physically complete (you laid 60 of 100 stones). However, you only spent 75 of 150 minutes; so in terms of duration, the job is only 50 percent complete. Depending on how you get paid for the work—how the value is earned (by the stone or by the hour)—you may choose the percent complete value or the physical percent complete value to properly reflect this in the earned value analysis. Which earned value quantities can I show or calculate in Project? With Project, you can show:  Actual cost of work performed (ACWP) shows actual costs incurred for work already performed by a resource on a task, up to the project status date or today's date. Normally Project correlates actual costs with actual work. Only if you enter actual costs independent of actual work or change resource pay rates will actual cost be out of step with scheduled cost.  Budget at completion (BAC) shows an estimate of the total project cost.  Budgeted cost of work performed (BCWP) shows how much of the budget should have been spent given the actual duration of the task. BCWP is also referred to as "earned value." Note that Project calculates BCWP at the task level differently than it does at the assignment level. For best results, use the task-level BCWP values, which are the values Project rolls up to summary task and the project summary task BCWP values. This value is calculated for each individual task but analyzed at an aggregate level (typically at the project level).  Budgeted cost of work scheduled (BCWS) shows how much of the budget should have been spent in view of the baseline cost of the task, assignment, or resource. BCWS is calculated as the cumulative timephased baseline costs up to the status date or today's date. (Budgeted cost values are stored in the baseline fields, or if you've saved multiple baselines, in fields Baseline1 through Baseline10.)  Cost variance (CV) shows the difference between the budgeted cost of work performed (BCWP) on a task and its actual cost (actual cost of work performed or ACWP). If the CV is positive, the cost is currently under the budgeted (or baseline) amount; if the CV is negative, the task is currently over budget.  Schedule variance (SV) shows the difference between the budgeted cost of work performed (BCWP) and the budgeted cost of work scheduled (BCWS). If the SV is positive, the project is ahead of schedule in cost terms; if the SV is negative, the project is behind schedule in cost terms.  Variance at completion (VAC) shows the difference between the budget at completion (BAC) and the estimate at completion (EAC). In Project, the EAC is the Total Cost field and the BAC is the Baseline Cost field from the associated baseline.  Cost performance index (CPI) is the ratio of budgeted, or baseline, costs of work performed to actual costs of work performed (BCWP/ACWP).  Cumulative cost performance index (CPI) is the sum of the BCWP for all tasks divided by the sum of the actual costs of work performed (ACWP) for all tasks. Cumulative CPI is often used to predict whether a project will go over budget and by how much.  Schedule performance index (SPI) is the ratio of work performed to work scheduled (BCWP/BCWS). SPI is often used to estimate the project completion date.  Estimate at completion (EAC) is the expected total cost of a task or project, based on performance as of the status date. EAC is also called forecast at completion, and is calculated like this: EAC = ACWP + (BAC - BCWP) / CPI.  To complete performance index (TCPI) is the ratio of remaining available budget to be spent to the remaining scheduled cost as of the status date. TCPI is calculated like this: TCPI = (BAC - BCWP) / (BAC - ACWP). A TCPI value greater than 1 indicates good projected performance for remaining work; less than 1 indicates poor projected performance.
  • 4. Where in Project do I see earned value data? You can see earned value information in any sheet view by applying the Earned Value table or the Earned Value Cost Indicators table.  The Earned Value table shows you BCWS, BCWP, ACWP, SV, CV, EAC, BAC, and VAC. Use this table to see consolidated earned value information, including the key variance fields. Use EAC, BAC, and VAC to evaluate the difference between your scheduled and budgeted costs. Compare CV, which shows the difference between your budgeted and actual cost?of work, with SV, which shows the difference between the budgeted cost of work and the actual cost of work.  The Earned Value Cost Indicators table shows you BCWS, BCWP, CV, CV%, CPI, BAC, EAC, VAC, and TCPI. Use this table to analyze cost variances. Check the CPI and TCPI to see how the project is progressing against its budget and how the rate of work compares with the expected rate. If CPI is less than than 1, you are getting less work per dollar than planned. The TCPI tells you how much of an increase in performance you'll need on the remaining tasks in order to keep within budget.