ID Res.
Name
Task Name % Complete Duration Start Finish Prede
1 B91-Raw Material Sampling Upgrade 73% 469.5 days 12/11/13 10/26/15
14 Project Documents 76% 469.5 days 12/11/13 10/26/15
308 Regulatory Affairs 0% 70 days 6/30/15 10/9/15
309 RA Submission 0% 20 days 6/30/15 7/29/15 934
310 RA Approval 0% 50 days 7/29/15 10/9/15 309
311 PTOP 0% 20 days 9/25/15 10/26/15
312 PTOP Preparation & Submission 0% 15 days 9/25/15 10/19/15 310F
313 PTOP Approval 0% 5 days 10/19/15 10/26/15 312
359 GEM Procurement 89% 194.5 days 5/2/14 2/12/15
360 Equipments 85% 188.5 days 5/12/14 2/12/15
361 Walk-in Down Flow Booth 62% 185.5 days 5/15/14 2/12/15
374 Fabrication 0% 72.5 days 10/27/14 2/11/15
375 Complete Fabrication 0% 14.5 wks 10/27/14 2/11/15373F
381 Delivery of Walk-in Down Flow Booth 0% 0 days 2/12/15 2/12/15 375F
432 SS Pump Truck & Pallets 79% 65 days 9/29/14 1/5/15
439 Fabrication 57% 40 days 10/24/14 12/18/14
440 Complete Fabrication 57% 7 wks 10/24/14 12/18/14 437F
442 Delivery of SS Pallets 0% 0 days 1/5/15 1/5/15 440F
486 Procurement Complete 0% 0 days 2/12/15 2/12/15 485,4
487 COM Construction 74% 161.5 days 6/23/14 2/17/15
488 B91 - Raw Material Sampling - Preliminary Schedule
Update 4, July 29,2014
82% 151 days 6/23/14 1/30/15
503 Construction 83% 146 days 6/30/14 1/30/15
504 Structure 95% 129.6 days 6/30/14 1/8/15
561 Epoxy Floor - Level 1 70% 10 days 11/15/14 12/18/14 557S
563 Electrical Finishes - Level 1 F/A, airlock control
devices, misc. electrical
90% 4 days 11/27/14 12/19/14 561
564 Epoxy Floor - Level 2 80% 5 days 12/4/14 1/7/15 561S
567 Washroom Accessories 0% 4 days 12/9/14 12/12/14 561S
569 Electrical Finishes - Level 2 F/A, airlock control
devices, misc. electrical
80% 3 days 12/1/14 1/8/15 564
604 Finishes 90% 40.14 days 11/7/14 1/9/15
607 Controls 94% 40 days 11/7/14 1/9/15
608 Unit Start-ups 8% 15.75 days 1/5/15 1/26/15
609 AHS_92 25% 5 days 1/5/15 1/12/15
610 AHS_91 0% 5 days 1/19/15 1/26/15 609F
611 Exhaust Fans 0% 1 day 1/23/15 1/26/15 610F
612 Unit Heaters 0% 1 day 1/23/15 1/26/15 610F
613 Fan Coils 0% 1 day 1/25/15 1/26/15 612F
614 Heating Coils 0% 1 day 1/23/15 1/26/15 613F
615 Chiller / Condenser 0% 1 day 1/23/15 1/26/15 614F
644 Roof Top Units: 4% 38 days 12/2/14 1/30/15
648 Unit Start-up & Commissioning 0% 3 days 1/26/15 1/29/15 543F
649 Siemens Static & Dynamic Testing 0% 1 day 1/29/15 1/30/15 648F
651 Honeywell Controls 80% 115 days 8/7/14 1/23/15
657 Execution 0% 13.6 days 1/6/15 1/23/15
658 Programming 0% 4 days 1/6/15 1/10/15 694S
0%
0%
Procurement
Equipments
Walk-in Down Flow Booth
0% Fabrication
2/12 Delivery of Walk-in Down Flow Booth
79% SS Pump Truck & Pallets
57% Fabrication
1/5 Delivery of SS Pallets
2/12 Procurement Complete
Construction
B91 - Raw Material Sampling - Preliminary Schedule Update 4, July
Construction
Structure
90% Finishes
8% Unit Start-ups
4% Roof Top Units:
0% Honeywell Controls
0% Execution
22 27 2 7 13 18 23 31 6 11 17 22
Jul 27, '14 Oct 12, '14 Dec 28, '14 Mar 15, '15 May 31, '15 Aug 16
Task
Split
Milestone
Summary
Project Summary
Baseline Milestone
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Critical
Critical Split
Progress
Deadline
Summary Progress
B91‐ Raw Material Sampling Upgrade
Page 1
Project: B91 Raw Material Sampling U
1/7/15
ID Res.
Name
Task Name % Complete Duration Start Finish Prede
660 HANDOVER TASKS 0% 34 days 12/9/14 1/30/15
661 Deficiency Correction 0% 14 days 1/13/15 1/30/15 567
662 Airlock verification 0% 3 days 12/9/14 12/11/14561S
663 F/A Verifications 0% 2 days 12/12/14 12/15/14 662
664 Final ESA Inspection 0% 1 day 1/9/15 1/12/15 547,5
665 Consultant Walkthrough for Compliance 0% 2 days 1/12/15 1/13/15 662F
666 Occupancy Inspection 0% 1 day 1/13/15 1/13/15 663,6
667 Construction Clean - 2 0% 1 day 12/16/14 12/16/14 663
668 Air Bal - Initial Balance - design values &
pressurization
0% 3 days 12/17/14 12/19/14 667
669 Siemens documented testing & final submittal 0% 7 days 1/22/15 1/29/15 649
670 HEPA Integrity Testing 0% 2 days 1/21/15 1/23/15 668F
671 Remove hoarding/fencing 0% 1 day 1/14/15 1/14/15
672 Substantial Completion 0% 0 days 1/30/15 1/30/15 662,6
673 Sanofi Supplied Equipment Installations 0% 72.5 days 10/29/14 2/17/15
676 Install Down Flow Booth 0% 0 days 2/17/15 2/17/15 381F
678 Honeywell Schedule 48% 116 days 8/8/14 1/27/15
693 Execution 0% 15.6 days 1/6/15 1/27/15
694 Programming 0% 4 days 1/6/15 1/10/15 607F
695 Testing and commissioning 0% 10 days 1/12/15 1/23/15 694
699 HEPA Integrity Testing 0% 0 days 1/23/15 1/23/15 670F
700 Construction completion( Compass Part) 0% 0 days 1/30/15 1/30/15 662,6
701 Construction finally Complete( 100%) 0% 0 days 2/17/15 2/17/15 672,4
702 ST/KS C & Q Development 63% 225.5 days 3/31/14 2/25/15
723 KS HVAC including Ex. Fans 16% 39.5 days 11/17/14 1/16/15
724 Commissioning Protocol Development 75% 5 days 11/17/14 12/17/14 405F
725 Commissioning Protocol Review 0% 5 days 12/17/14 12/29/14 724
726 Commissioning Protocol Approval 0% 2 days 12/29/14 12/31/14 725
782 KS C&Q Execution 0% 116.5 days 11/7/14 4/29/15
787 KS HVAC 0% 36 days 1/30/15 3/24/15
788 SAT / Commissioning Execution 0% 5 days 1/30/15 2/6/15 699F
789 NC Closures 0% 2 days 2/6/15 2/10/15 788
790 Raw data audit 0% 3 days 2/10/15 2/13/15 789
791 Commissioning Report Development 0% 3 days 2/13/15 2/19/15 790
792 Commissioning Report Sign-Off 0% 2 days 2/19/15 2/23/15 791
793 HVAC IQ execution 0% 3 days 2/23/15 2/26/15 792,7
794 NC Closures 0% 1 day 2/26/15 2/27/15 793
795 Raw data audit 0% 2 days 2/27/15 3/3/15 794
796 OQ execution 0% 5 days 3/3/15 3/10/15 795,2
797 NC Closures 0% 2 days 3/10/15 3/12/15 796
798 Raw data audit 0% 3 days 3/12/15 3/17/15 797
799 OQ Report Development 0% 3 days 3/17/15 3/20/15 798
800 OQ Report Approval 0% 2 days 3/20/15 3/24/15 799
801 KS Walk in Down Flow Booth 0% 43 days 2/19/15 4/22/15
807 Down Flow Booth IQ execution 0% 3 days 3/24/15 3/27/15 806,7
0% HANDOVER TASKS
1/30 Substantial Completion
0% Sanofi Supplied Equipment Installations
2/17 Install Down Flow Booth
8% Honeywell Schedule
0% Execution
1/23 HEPA Integrity Testing
1/30 Construction completion( Compass Part)
2/17 Construction finally Complete( 100%)
C & Q Development
16% HVAC including Ex. Fans
0% C&Q Execution
0% HVAC
0% Walk in Down Flow Booth
22 27 2 7 13 18 23 31 6 11 17 22
Jul 27, '14 Oct 12, '14 Dec 28, '14 Mar 15, '15 May 31, '15 Aug 16
Task
Split
Milestone
Summary
Project Summary
Baseline Milestone
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Critical
Critical Split
Progress
Deadline
Summary Progress
B91‐ Raw Material Sampling Upgrade
Page 2
Project: B91 Raw Material Sampling U
1/7/15
ID Res.
Name
Task Name % Complete Duration Start Finish Prede
808 NC Closures 0% 1 day 3/27/15 3/30/15 807
809 Raw data audit 0% 2 days 3/30/15 4/1/15 808
810 OQ execution / Smoke Study 0% 5 days 4/1/15 4/9/15 809,2
859 KS Smoke Study 0% 14 days 4/9/15 4/29/15
860 Smoke Study Execution 0% 5 days 4/9/15 4/16/15 441,8
889 PQ Development 0% 9 days 4/16/15 4/29/15
890 KS EM Protocols Development 0% 9 days 4/16/15 4/29/15
891 EM Protocol Development 0% 5 days 4/16/15 4/23/15 860
892 EM Protocol Review 0% 2 days 4/23/15 4/27/15 891
893 EM Protocol Approval 0% 2 days 4/27/15 4/29/15 892,8
894 PQ Execution 0% 43 days 4/29/15 6/30/15
895 EM Execution 0% 43 days 4/29/15 6/30/15
896 Cleaning 0% 7 days 4/29/15 5/8/15
897 Gross Cleaning 0% 3 days 4/29/15 5/4/15 864S
898 Pre GMP Cleaning 0% 1 day 5/4/15 5/5/15 897
899 GMP Cleaning 0% 2 days 5/5/15 5/7/15 898
900 Material Prep After GMP Cleaning 0% 1 day 5/7/15 5/8/15 899
901 Execution static 0% 7 days 5/8/15 5/20/15
902 Static #1 0% 1 day 5/8/15 5/11/15900,1
903 Clean 0% 1 day 5/8/15 5/11/15902F
905 Static #2 0% 1 day 5/14/15 5/15/15 904
906 Clean 0% 1 day 5/14/15 5/15/15 905F
907 Static #3 0% 1 day 5/15/15 5/19/15 906
908 Clean 0% 1 day 5/15/15 5/19/15 907F
909 Clean efficacy sampling #1 0% 1 day 5/15/15 5/19/15 908F
910 Cleaning 0% 1 day 5/19/15 5/20/15 909
911 Static - Data Analysis 0% 6 days 5/20/15 5/28/15
913 NC Closure (For non Microbials) 0% 3 days 5/25/15 5/28/15 912
914 Execution dynamic 0% 8 days 5/28/15 6/9/15
915 Cleaning 0% 1 day 5/28/15 5/29/15 913
917 Dynamic #1 0% 1 day 6/1/15 6/2/15 916
918 Cleaning 0% 1 day 6/1/15 6/2/15 917F
920 Dynamic #2 0% 1 day 6/5/15 6/8/15 919
921 Cleaning 0% 1 day 6/5/15 6/8/15 920F
922 Clean efficacy sampling #2 0% 1 day 6/5/15 6/8/15 921F
923 Cleaning 0% 1 day 6/5/15 6/8/15 922F
924 Dynamic #3 0% 1 day 6/8/15 6/9/15 923
925 Cleaning 0% 1 day 6/8/15 6/9/15 924F
926 Clean efficacy sampling #3 0% 1 day 6/8/15 6/9/15 925F
928 Dynamic - Data Analysis for EM 0% 15 days 6/9/15 6/30/15
930 NC Closure (For non Microbials) 0% 4 days 6/16/15 6/22/15 929
931 Audit of executed EM package 0% 3 days 6/22/15 6/25/15 930
932 Final Report Review 0% 2 days 6/25/15 6/29/15 931
933 Final Report Approval 0% 1 day 6/29/15 6/30/15 932
934 EM Complete 0% 0 days 6/30/15 6/30/15 927,9
935 Project Complete 0% 0 days 10/26/15 10/26/15 313
0% Smoke Study
0% PQ Development
0% EM Protocols Development
0% PQ Execution
0% EM Execution
0% Cleaning
0% Execution static
0% Static - Data Analysis
0% Execution dynamic
0% Dynamic - Data Analysis
6/30 EM Complete
22 27 2 7 13 18 23 31 6 11 17 22
Jul 27, '14 Oct 12, '14 Dec 28, '14 Mar 15, '15 May 31, '15 Aug 16
Task
Split
Milestone
Summary
Project Summary
Baseline Milestone
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Critical
Critical Split
Progress
Deadline
Summary Progress
B91‐ Raw Material Sampling Upgrade
Page 3
Project: B91 Raw Material Sampling U
1/7/15

Weitere ähnliche Inhalte

Was ist angesagt?

Managing Agile Software Development Quantitatively
Managing Agile Software Development QuantitativelyManaging Agile Software Development Quantitatively
Managing Agile Software Development QuantitativelyJayGray
 
Building Envelope Design - Kristian GJOKA, Enrico SALCUNI
Building Envelope Design - Kristian GJOKA, Enrico SALCUNIBuilding Envelope Design - Kristian GJOKA, Enrico SALCUNI
Building Envelope Design - Kristian GJOKA, Enrico SALCUNIKristian Gjoka
 
Predictive maintenance thermograph in gis 500 kv unit 4
Predictive maintenance thermograph in gis 500 kv unit 4Predictive maintenance thermograph in gis 500 kv unit 4
Predictive maintenance thermograph in gis 500 kv unit 4Adityan Putra
 
Production Operation Maintenance & Mechanical Engineering
Production Operation Maintenance & Mechanical EngineeringProduction Operation Maintenance & Mechanical Engineering
Production Operation Maintenance & Mechanical EngineeringEva Susiani
 
Maximize Compliance & Cost Savings with Regular PM
Maximize Compliance & Cost Savings with Regular PMMaximize Compliance & Cost Savings with Regular PM
Maximize Compliance & Cost Savings with Regular PMTriumvirate Environmental
 
A - Production Operation Maintenance Mechanical Engineering
A - Production Operation Maintenance Mechanical EngineeringA - Production Operation Maintenance Mechanical Engineering
A - Production Operation Maintenance Mechanical EngineeringPT. Wisnu Inter Sains Hakiki
 
ROSS DUGAS OQReport_28716500
ROSS DUGAS OQReport_28716500ROSS DUGAS OQReport_28716500
ROSS DUGAS OQReport_28716500Ross Dugas
 

Was ist angesagt? (10)

Managing Agile Software Development Quantitatively
Managing Agile Software Development QuantitativelyManaging Agile Software Development Quantitatively
Managing Agile Software Development Quantitatively
 
NNP Shutdown 2014 Plans - Scurve and npt graph
NNP Shutdown 2014 Plans - Scurve and npt graphNNP Shutdown 2014 Plans - Scurve and npt graph
NNP Shutdown 2014 Plans - Scurve and npt graph
 
Building Envelope Design - Kristian GJOKA, Enrico SALCUNI
Building Envelope Design - Kristian GJOKA, Enrico SALCUNIBuilding Envelope Design - Kristian GJOKA, Enrico SALCUNI
Building Envelope Design - Kristian GJOKA, Enrico SALCUNI
 
COMPL OF WORKS1
COMPL OF WORKS1COMPL OF WORKS1
COMPL OF WORKS1
 
F gas logbook Mitie
F gas logbook Mitie F gas logbook Mitie
F gas logbook Mitie
 
Predictive maintenance thermograph in gis 500 kv unit 4
Predictive maintenance thermograph in gis 500 kv unit 4Predictive maintenance thermograph in gis 500 kv unit 4
Predictive maintenance thermograph in gis 500 kv unit 4
 
Production Operation Maintenance & Mechanical Engineering
Production Operation Maintenance & Mechanical EngineeringProduction Operation Maintenance & Mechanical Engineering
Production Operation Maintenance & Mechanical Engineering
 
Maximize Compliance & Cost Savings with Regular PM
Maximize Compliance & Cost Savings with Regular PMMaximize Compliance & Cost Savings with Regular PM
Maximize Compliance & Cost Savings with Regular PM
 
A - Production Operation Maintenance Mechanical Engineering
A - Production Operation Maintenance Mechanical EngineeringA - Production Operation Maintenance Mechanical Engineering
A - Production Operation Maintenance Mechanical Engineering
 
ROSS DUGAS OQReport_28716500
ROSS DUGAS OQReport_28716500ROSS DUGAS OQReport_28716500
ROSS DUGAS OQReport_28716500
 

Ähnlich wie CPM

WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)  WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015) Ali Yousef
 
Lean six sigma black belt project by iftakhar
Lean six sigma black belt project   by iftakharLean six sigma black belt project   by iftakhar
Lean six sigma black belt project by iftakharMohammad IFTAKHAR
 
Flow Product Development
Flow Product DevelopmentFlow Product Development
Flow Product DevelopmentPablo Domingo
 
week 3 August Prod.report rev 2.pptx
week 3 August Prod.report rev 2.pptxweek 3 August Prod.report rev 2.pptx
week 3 August Prod.report rev 2.pptxAbdurRahman990630
 
Time Series in Driverless AI by Marios Michailidis
Time Series in Driverless AI by Marios MichailidisTime Series in Driverless AI by Marios Michailidis
Time Series in Driverless AI by Marios MichailidisSri Ambati
 
Zero Defect Competition @ July 22.pptx
Zero Defect Competition  @ July 22.pptxZero Defect Competition  @ July 22.pptx
Zero Defect Competition @ July 22.pptxsonutyagi20
 
Review W24 & Plan Week 25 2022 MUM_BAS.pptx
Review W24 & Plan Week 25 2022 MUM_BAS.pptxReview W24 & Plan Week 25 2022 MUM_BAS.pptx
Review W24 & Plan Week 25 2022 MUM_BAS.pptxnoelmanroe1
 
Balloon Project Summary
Balloon Project SummaryBalloon Project Summary
Balloon Project Summaryrhlee46
 
UTC Aerospace System - Value Stream Mapping
UTC Aerospace System - Value Stream MappingUTC Aerospace System - Value Stream Mapping
UTC Aerospace System - Value Stream MappingLean6Sigma4all
 
Japanese 5 S System for Store of Power & Steel Plant
Japanese  5 S System for Store of Power & Steel Plant Japanese  5 S System for Store of Power & Steel Plant
Japanese 5 S System for Store of Power & Steel Plant Er. EHS & Fire Syed Ali
 
Pt hpm half yearly presentation on may
Pt hpm half yearly presentation on mayPt hpm half yearly presentation on may
Pt hpm half yearly presentation on mayaristomy
 
Production Schedule Report 2016-rv
Production Schedule Report 2016-rvProduction Schedule Report 2016-rv
Production Schedule Report 2016-rvJames Thomas
 

Ähnlich wie CPM (20)

Slide4 mp psht1of6
Slide4 mp psht1of6Slide4 mp psht1of6
Slide4 mp psht1of6
 
Cash Flow Portfolio
Cash Flow PortfolioCash Flow Portfolio
Cash Flow Portfolio
 
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)  WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)
 
Lean six sigma black belt project by iftakhar
Lean six sigma black belt project   by iftakharLean six sigma black belt project   by iftakhar
Lean six sigma black belt project by iftakhar
 
Flow Product Development
Flow Product DevelopmentFlow Product Development
Flow Product Development
 
week 3 August Prod.report rev 2.pptx
week 3 August Prod.report rev 2.pptxweek 3 August Prod.report rev 2.pptx
week 3 August Prod.report rev 2.pptx
 
Time Series in Driverless AI by Marios Michailidis
Time Series in Driverless AI by Marios MichailidisTime Series in Driverless AI by Marios Michailidis
Time Series in Driverless AI by Marios Michailidis
 
Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011
 
Zero Defect Competition @ July 22.pptx
Zero Defect Competition  @ July 22.pptxZero Defect Competition  @ July 22.pptx
Zero Defect Competition @ July 22.pptx
 
Review W24 & Plan Week 25 2022 MUM_BAS.pptx
Review W24 & Plan Week 25 2022 MUM_BAS.pptxReview W24 & Plan Week 25 2022 MUM_BAS.pptx
Review W24 & Plan Week 25 2022 MUM_BAS.pptx
 
Balloon Project Summary
Balloon Project SummaryBalloon Project Summary
Balloon Project Summary
 
Manish Engineering Works
Manish Engineering WorksManish Engineering Works
Manish Engineering Works
 
UTC Aerospace System - Value Stream Mapping
UTC Aerospace System - Value Stream MappingUTC Aerospace System - Value Stream Mapping
UTC Aerospace System - Value Stream Mapping
 
Japanese 5 S System for Store of Power & Steel Plant
Japanese  5 S System for Store of Power & Steel Plant Japanese  5 S System for Store of Power & Steel Plant
Japanese 5 S System for Store of Power & Steel Plant
 
Pt hpm half yearly presentation on may
Pt hpm half yearly presentation on mayPt hpm half yearly presentation on may
Pt hpm half yearly presentation on may
 
Lean Assessment 03-09-11
Lean Assessment 03-09-11Lean Assessment 03-09-11
Lean Assessment 03-09-11
 
Popop
PopopPopop
Popop
 
SMC CFT 2012-13-IInd Half.
SMC CFT 2012-13-IInd Half.SMC CFT 2012-13-IInd Half.
SMC CFT 2012-13-IInd Half.
 
Production Schedule Report 2016-rv
Production Schedule Report 2016-rvProduction Schedule Report 2016-rv
Production Schedule Report 2016-rv
 
Slide5 mp psht2of6
Slide5 mp psht2of6Slide5 mp psht2of6
Slide5 mp psht2of6
 

CPM

  • 1. ID Res. Name Task Name % Complete Duration Start Finish Prede 1 B91-Raw Material Sampling Upgrade 73% 469.5 days 12/11/13 10/26/15 14 Project Documents 76% 469.5 days 12/11/13 10/26/15 308 Regulatory Affairs 0% 70 days 6/30/15 10/9/15 309 RA Submission 0% 20 days 6/30/15 7/29/15 934 310 RA Approval 0% 50 days 7/29/15 10/9/15 309 311 PTOP 0% 20 days 9/25/15 10/26/15 312 PTOP Preparation & Submission 0% 15 days 9/25/15 10/19/15 310F 313 PTOP Approval 0% 5 days 10/19/15 10/26/15 312 359 GEM Procurement 89% 194.5 days 5/2/14 2/12/15 360 Equipments 85% 188.5 days 5/12/14 2/12/15 361 Walk-in Down Flow Booth 62% 185.5 days 5/15/14 2/12/15 374 Fabrication 0% 72.5 days 10/27/14 2/11/15 375 Complete Fabrication 0% 14.5 wks 10/27/14 2/11/15373F 381 Delivery of Walk-in Down Flow Booth 0% 0 days 2/12/15 2/12/15 375F 432 SS Pump Truck & Pallets 79% 65 days 9/29/14 1/5/15 439 Fabrication 57% 40 days 10/24/14 12/18/14 440 Complete Fabrication 57% 7 wks 10/24/14 12/18/14 437F 442 Delivery of SS Pallets 0% 0 days 1/5/15 1/5/15 440F 486 Procurement Complete 0% 0 days 2/12/15 2/12/15 485,4 487 COM Construction 74% 161.5 days 6/23/14 2/17/15 488 B91 - Raw Material Sampling - Preliminary Schedule Update 4, July 29,2014 82% 151 days 6/23/14 1/30/15 503 Construction 83% 146 days 6/30/14 1/30/15 504 Structure 95% 129.6 days 6/30/14 1/8/15 561 Epoxy Floor - Level 1 70% 10 days 11/15/14 12/18/14 557S 563 Electrical Finishes - Level 1 F/A, airlock control devices, misc. electrical 90% 4 days 11/27/14 12/19/14 561 564 Epoxy Floor - Level 2 80% 5 days 12/4/14 1/7/15 561S 567 Washroom Accessories 0% 4 days 12/9/14 12/12/14 561S 569 Electrical Finishes - Level 2 F/A, airlock control devices, misc. electrical 80% 3 days 12/1/14 1/8/15 564 604 Finishes 90% 40.14 days 11/7/14 1/9/15 607 Controls 94% 40 days 11/7/14 1/9/15 608 Unit Start-ups 8% 15.75 days 1/5/15 1/26/15 609 AHS_92 25% 5 days 1/5/15 1/12/15 610 AHS_91 0% 5 days 1/19/15 1/26/15 609F 611 Exhaust Fans 0% 1 day 1/23/15 1/26/15 610F 612 Unit Heaters 0% 1 day 1/23/15 1/26/15 610F 613 Fan Coils 0% 1 day 1/25/15 1/26/15 612F 614 Heating Coils 0% 1 day 1/23/15 1/26/15 613F 615 Chiller / Condenser 0% 1 day 1/23/15 1/26/15 614F 644 Roof Top Units: 4% 38 days 12/2/14 1/30/15 648 Unit Start-up & Commissioning 0% 3 days 1/26/15 1/29/15 543F 649 Siemens Static & Dynamic Testing 0% 1 day 1/29/15 1/30/15 648F 651 Honeywell Controls 80% 115 days 8/7/14 1/23/15 657 Execution 0% 13.6 days 1/6/15 1/23/15 658 Programming 0% 4 days 1/6/15 1/10/15 694S 0% 0% Procurement Equipments Walk-in Down Flow Booth 0% Fabrication 2/12 Delivery of Walk-in Down Flow Booth 79% SS Pump Truck & Pallets 57% Fabrication 1/5 Delivery of SS Pallets 2/12 Procurement Complete Construction B91 - Raw Material Sampling - Preliminary Schedule Update 4, July Construction Structure 90% Finishes 8% Unit Start-ups 4% Roof Top Units: 0% Honeywell Controls 0% Execution 22 27 2 7 13 18 23 31 6 11 17 22 Jul 27, '14 Oct 12, '14 Dec 28, '14 Mar 15, '15 May 31, '15 Aug 16 Task Split Milestone Summary Project Summary Baseline Milestone External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Critical Critical Split Progress Deadline Summary Progress B91‐ Raw Material Sampling Upgrade Page 1 Project: B91 Raw Material Sampling U 1/7/15
  • 2. ID Res. Name Task Name % Complete Duration Start Finish Prede 660 HANDOVER TASKS 0% 34 days 12/9/14 1/30/15 661 Deficiency Correction 0% 14 days 1/13/15 1/30/15 567 662 Airlock verification 0% 3 days 12/9/14 12/11/14561S 663 F/A Verifications 0% 2 days 12/12/14 12/15/14 662 664 Final ESA Inspection 0% 1 day 1/9/15 1/12/15 547,5 665 Consultant Walkthrough for Compliance 0% 2 days 1/12/15 1/13/15 662F 666 Occupancy Inspection 0% 1 day 1/13/15 1/13/15 663,6 667 Construction Clean - 2 0% 1 day 12/16/14 12/16/14 663 668 Air Bal - Initial Balance - design values & pressurization 0% 3 days 12/17/14 12/19/14 667 669 Siemens documented testing & final submittal 0% 7 days 1/22/15 1/29/15 649 670 HEPA Integrity Testing 0% 2 days 1/21/15 1/23/15 668F 671 Remove hoarding/fencing 0% 1 day 1/14/15 1/14/15 672 Substantial Completion 0% 0 days 1/30/15 1/30/15 662,6 673 Sanofi Supplied Equipment Installations 0% 72.5 days 10/29/14 2/17/15 676 Install Down Flow Booth 0% 0 days 2/17/15 2/17/15 381F 678 Honeywell Schedule 48% 116 days 8/8/14 1/27/15 693 Execution 0% 15.6 days 1/6/15 1/27/15 694 Programming 0% 4 days 1/6/15 1/10/15 607F 695 Testing and commissioning 0% 10 days 1/12/15 1/23/15 694 699 HEPA Integrity Testing 0% 0 days 1/23/15 1/23/15 670F 700 Construction completion( Compass Part) 0% 0 days 1/30/15 1/30/15 662,6 701 Construction finally Complete( 100%) 0% 0 days 2/17/15 2/17/15 672,4 702 ST/KS C & Q Development 63% 225.5 days 3/31/14 2/25/15 723 KS HVAC including Ex. Fans 16% 39.5 days 11/17/14 1/16/15 724 Commissioning Protocol Development 75% 5 days 11/17/14 12/17/14 405F 725 Commissioning Protocol Review 0% 5 days 12/17/14 12/29/14 724 726 Commissioning Protocol Approval 0% 2 days 12/29/14 12/31/14 725 782 KS C&Q Execution 0% 116.5 days 11/7/14 4/29/15 787 KS HVAC 0% 36 days 1/30/15 3/24/15 788 SAT / Commissioning Execution 0% 5 days 1/30/15 2/6/15 699F 789 NC Closures 0% 2 days 2/6/15 2/10/15 788 790 Raw data audit 0% 3 days 2/10/15 2/13/15 789 791 Commissioning Report Development 0% 3 days 2/13/15 2/19/15 790 792 Commissioning Report Sign-Off 0% 2 days 2/19/15 2/23/15 791 793 HVAC IQ execution 0% 3 days 2/23/15 2/26/15 792,7 794 NC Closures 0% 1 day 2/26/15 2/27/15 793 795 Raw data audit 0% 2 days 2/27/15 3/3/15 794 796 OQ execution 0% 5 days 3/3/15 3/10/15 795,2 797 NC Closures 0% 2 days 3/10/15 3/12/15 796 798 Raw data audit 0% 3 days 3/12/15 3/17/15 797 799 OQ Report Development 0% 3 days 3/17/15 3/20/15 798 800 OQ Report Approval 0% 2 days 3/20/15 3/24/15 799 801 KS Walk in Down Flow Booth 0% 43 days 2/19/15 4/22/15 807 Down Flow Booth IQ execution 0% 3 days 3/24/15 3/27/15 806,7 0% HANDOVER TASKS 1/30 Substantial Completion 0% Sanofi Supplied Equipment Installations 2/17 Install Down Flow Booth 8% Honeywell Schedule 0% Execution 1/23 HEPA Integrity Testing 1/30 Construction completion( Compass Part) 2/17 Construction finally Complete( 100%) C & Q Development 16% HVAC including Ex. Fans 0% C&Q Execution 0% HVAC 0% Walk in Down Flow Booth 22 27 2 7 13 18 23 31 6 11 17 22 Jul 27, '14 Oct 12, '14 Dec 28, '14 Mar 15, '15 May 31, '15 Aug 16 Task Split Milestone Summary Project Summary Baseline Milestone External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Critical Critical Split Progress Deadline Summary Progress B91‐ Raw Material Sampling Upgrade Page 2 Project: B91 Raw Material Sampling U 1/7/15
  • 3. ID Res. Name Task Name % Complete Duration Start Finish Prede 808 NC Closures 0% 1 day 3/27/15 3/30/15 807 809 Raw data audit 0% 2 days 3/30/15 4/1/15 808 810 OQ execution / Smoke Study 0% 5 days 4/1/15 4/9/15 809,2 859 KS Smoke Study 0% 14 days 4/9/15 4/29/15 860 Smoke Study Execution 0% 5 days 4/9/15 4/16/15 441,8 889 PQ Development 0% 9 days 4/16/15 4/29/15 890 KS EM Protocols Development 0% 9 days 4/16/15 4/29/15 891 EM Protocol Development 0% 5 days 4/16/15 4/23/15 860 892 EM Protocol Review 0% 2 days 4/23/15 4/27/15 891 893 EM Protocol Approval 0% 2 days 4/27/15 4/29/15 892,8 894 PQ Execution 0% 43 days 4/29/15 6/30/15 895 EM Execution 0% 43 days 4/29/15 6/30/15 896 Cleaning 0% 7 days 4/29/15 5/8/15 897 Gross Cleaning 0% 3 days 4/29/15 5/4/15 864S 898 Pre GMP Cleaning 0% 1 day 5/4/15 5/5/15 897 899 GMP Cleaning 0% 2 days 5/5/15 5/7/15 898 900 Material Prep After GMP Cleaning 0% 1 day 5/7/15 5/8/15 899 901 Execution static 0% 7 days 5/8/15 5/20/15 902 Static #1 0% 1 day 5/8/15 5/11/15900,1 903 Clean 0% 1 day 5/8/15 5/11/15902F 905 Static #2 0% 1 day 5/14/15 5/15/15 904 906 Clean 0% 1 day 5/14/15 5/15/15 905F 907 Static #3 0% 1 day 5/15/15 5/19/15 906 908 Clean 0% 1 day 5/15/15 5/19/15 907F 909 Clean efficacy sampling #1 0% 1 day 5/15/15 5/19/15 908F 910 Cleaning 0% 1 day 5/19/15 5/20/15 909 911 Static - Data Analysis 0% 6 days 5/20/15 5/28/15 913 NC Closure (For non Microbials) 0% 3 days 5/25/15 5/28/15 912 914 Execution dynamic 0% 8 days 5/28/15 6/9/15 915 Cleaning 0% 1 day 5/28/15 5/29/15 913 917 Dynamic #1 0% 1 day 6/1/15 6/2/15 916 918 Cleaning 0% 1 day 6/1/15 6/2/15 917F 920 Dynamic #2 0% 1 day 6/5/15 6/8/15 919 921 Cleaning 0% 1 day 6/5/15 6/8/15 920F 922 Clean efficacy sampling #2 0% 1 day 6/5/15 6/8/15 921F 923 Cleaning 0% 1 day 6/5/15 6/8/15 922F 924 Dynamic #3 0% 1 day 6/8/15 6/9/15 923 925 Cleaning 0% 1 day 6/8/15 6/9/15 924F 926 Clean efficacy sampling #3 0% 1 day 6/8/15 6/9/15 925F 928 Dynamic - Data Analysis for EM 0% 15 days 6/9/15 6/30/15 930 NC Closure (For non Microbials) 0% 4 days 6/16/15 6/22/15 929 931 Audit of executed EM package 0% 3 days 6/22/15 6/25/15 930 932 Final Report Review 0% 2 days 6/25/15 6/29/15 931 933 Final Report Approval 0% 1 day 6/29/15 6/30/15 932 934 EM Complete 0% 0 days 6/30/15 6/30/15 927,9 935 Project Complete 0% 0 days 10/26/15 10/26/15 313 0% Smoke Study 0% PQ Development 0% EM Protocols Development 0% PQ Execution 0% EM Execution 0% Cleaning 0% Execution static 0% Static - Data Analysis 0% Execution dynamic 0% Dynamic - Data Analysis 6/30 EM Complete 22 27 2 7 13 18 23 31 6 11 17 22 Jul 27, '14 Oct 12, '14 Dec 28, '14 Mar 15, '15 May 31, '15 Aug 16 Task Split Milestone Summary Project Summary Baseline Milestone External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Critical Critical Split Progress Deadline Summary Progress B91‐ Raw Material Sampling Upgrade Page 3 Project: B91 Raw Material Sampling U 1/7/15