Project Dynamics: Emerging
Insights & Opportunities for the
Future of Project Management
Theory & Practice




Mark D. Choudhari
THE LOTUS GROUP
Contents
   1.1      Abstract                                            3
   1.2      Keyword                                             3
   1.3      Introduction                                        3
   1.4      The Project Dynamics Approach                       6 
   1.4.1    Project Features                                    6 
   1.4.2    Rework Cycles                                       7 
   1.4.3    Project Control Strategies                          8 
   1.4.4    Cascading and Subsequent Effects                    10 
   1.4.5.  Ripple Effects                                       10 
   1.4.6.  Knock-on Effects                                     11 
   1.5      Applications of Project Dynamics                    12 
   1.5.1    Estimation and Risk Assessment                      12 
   1.5.2    Project Control                                     12 
   1.5.3    Risk Management                                     12 
   1.5.4    Project Evaluations and Dispute Resolution          13 
   1.5.5    Change Management                                   13 
   1.5.6    Individual and Organisational Learning              13 
   1.6.     Insights and Directions for Future Work             13 
   1.7      Project Dynamics Integration Study                  14 
   1.8      Conclusions                                         15 
   1.9      References                                          16
   1.10     Authors Profile                                     17 




2|Page
1.1 Abstract
         Companies and individuals searching for revolutionary advances to enhancing their
         project management competencies have started applying project dynamics concepts
         and tools on their projects both across the world and increasingly in India. Project
         Dynamics, as emerging from the field of system dynamics, provides a radical, exciting
         approach that has begun to create new insights and initiate new advances in project
         management. This paper emphasizes the growth of project dynamics in setting new
         standards for excellence in project management through a transformation of the
         understanding of dynamics resulting from project features, rework cycles, reinforcing
         and balancing feedback, and the unintended consequences of project control
         strategies that create adverse dynamics. The paper (a) discusses the project
         dynamics approach from a structural and behavioural perspective, (b) highlights
         applications of project dynamics like post-mortem project evaluations and dispute
         resolution, estimation and risk assessment, project control, change management, and
         organisational learning, (c) presents strategic policy insights and directions for the
         future of project management theory and practice, and (d) presents the agenda and
         initial findings of a new study to integrate project dynamics within the PMI project
         management framework. The results of this study will help project management
         professionals and managers incorporate project dynamics concepts and tools in their
         practice and succeed in implementing the insights gained from a greater
         understanding of dynamics for superior performance on projects.


         1.2 Keywords:
         project management, project dynamics, project strategy, system dynamics, PMBoK


         1.3 Introduction
         In recent times, project management has been gaining in strategic importance for both
         industry and government. The importance of being able to manage projects well has
         never been greater in these times of increased industrial density, globalisation, foreign
         investment, and the use of advanced technologies making projects larger in scope,
         technically more complex, and financially more critical. However, only one out of three
         projects achieve all four of their initial project requirements of budget, duration, quality
         and scope (McKinsey & Company, 2008). Projects frequently face cost overruns,
         completion delays, compromised quality, and reduced scope. A recent example is the
         Mumbai Sea-link project that was not only over-budget (project budget increased more
         than five-fold from Rs. 300 crores to over Rs. 1,634 crores), was significantly delayed
         (by 5 years from a launch date of 2004 to 2009) and had to manage scope delivery to
         make the project launch in 2009 with 4 lanes instead of 8; the further four lanes were
         finally launched yet another year later in 2010. International examples of poor project
         performance, like the Channel Tunnel and the Boston Big Dig, demonstrate that poor
         project success rates are not endemic to a particular region but are a universal
         phenomenon.

         In a recent online project management forum, when asked what was the biggest
         problem facing project management, managers across the world provided over 900
         responses indicating that projects usually failed to meet their initial success criteria
         due to contributing factors like poor estimation during planning, changes in scope
         throughout execution, underestimating the complexity of implementation, and rework


3|Page
(due to errors) that is discovered while monitoring the project. Even with the best laid
         plans, managers need to continually exercise control decisions to address deviations
         of the project from its plan. Therefore, managers look for combinations of project
         control interventions to bring a project back to meeting its targets with the least
         adverse consequences. However, different amounts, durations and orders of
         application of such project control decisions impact project performance in different
         ways and cause problems of their own.

         Some of the commonly recurring war stories from project managers are shared below:

             Even after well defined plans, managers find that due to unanticipated errors a
             significant amount of rework is generated that also needs to be completed in
             addition to the initial estimates of work. Such rework, when discovered in time,
             can still however be addressed but when it goes undiscovered causes even
             further rework downstream in subsequent phases of projects. To further
             compound the problem, fixing the errors often requires more work than doing the
             work in the first place – this is especially true when downstream work is
             contaminated by undiscovered upstream errors.
             Common interventions possible when project deadlines begin to slip are to
             increase overtime, hire additional people onto the project team, and to increase
             the pressure on the team to speed up the work being completed. In practice,
             various combinations of these three options are used as considered appropriate
             by project managers. However, it is often noticed by managers that these
             interventions cause other unintended effects as well. Overtime often works well in
             the short term to accelerate work done but in the longer term it leads to fatigue of
             the team. Errors then begin to increase leading to additional rework and therefore
             lower productivity. Using overtime even beyond this leads to worker burnout and
             often attrition.
             Increasing the project team size is a another popularly used intervention when
             projects find themselves behind schedule. However, adding people midway
             through a project can dilute experience as workers with less skill or less familiarity
             with the project are brought on, they require time from experienced team members
             to bring them up to speed, and communication overheads grow exponentially with
             the number of stakeholders. Sometimes the unavailability of experienced persons
             to bring onto the project precludes the use of this option itself. Experience dilution
             and increased communications often increase errors, decrease the pace of work
             and decrease productivity.
             The third option of increasing work pressure also often leads to increasing errors
             as haste makes waste – thereby increasing rework and reducing productivity. It is
             clear from the above that the very decisions intended to increase productivity and
             speed up progress by increasing overtime, adding people, or increasing work
             intensity often achieve exactly the opposite result due to the unintended
             consequences of these decisions. Project managers often relate that their
             projects seem to be a system with ‘a mind of its own’ where the system itself
             offers resistance to their efforts to control it.
             Another interesting intervention by project managers to combat milestone slippage
             is to try and increase the concurrency of activities on projects over and above the
             initial plan. However, as the initial project plan is modified and more
             concurrencies are attempted, often work starts to be done out of sequence leading
             to increasing errors and rework, and reducing productivity. These errors then
             cause further errors downstream if not discovered and corrected in time.



4|Page
External factors, like changes in scope or requirements by the client, often activate
             a variety of project control interventions by managers leading to internal dynamics
             as described above thereby ruining projects that were otherwise successful.
         The unintended consequences of managerial decisions like increasing error rates,
         increasing rework and worker fatigue leads to morale and motivation problems, which
         when unchecked, sometimes leads to a sense of frustration and hopelessness on
         projects and eventually turnover leading to further workforce issues.

         While managers are quick to recognise the effects described above as commonly
         occurring on projects, they find it difficult to understand the nature and strength of the
         interrelationships within the project ‘system’ and how they differ both within a particular
         project phase, between two different phases or on different projects. Moreover, this
         has led to managers seeking better approaches to measure the impact of different
         decisions to help them design superior interventions that achieve project milestones
         with greater speed, less cost, and better quality without compromising scope.

         We look at the issues and challenges that managers have to deal with on projects
         along the two dimensions of detail complexity and dynamic complexity.

         1.3.1 Detail complexity

         Project managers, especially on large, complex projects, routinely use the existing
         state-of-the-art in project management tools, techniques and decision support
         software. While existing project management tools are pervasive in their usage, they
         largely deal with the static features, i.e. detail complexity, of projects. However, most
         project managers do not effectively understand or utilise the dynamic features of
         project processes like feedback, time delays, and non-linear cause-effect relationships
         between project components (Sterman 1992; Brooks 1978).

         Commonly used tools like the Program Evaluation and Review Technique (PERT), the
         Critical Path Method (CPM), related work breakdown structure (WBS) tools and
         component cost estimating are widely used to manage development projects.
         However the limitations of such tools to address project issues like undiscovered
         rework, bilaterally coupled activities involving feedback and iteration, and time-varying
         and endogenous factors (like skill, training and coordination) make them inadequate to
         model the highly coupled aspects and dynamic nature of the development process
         (Ford 1995).

         Apart from industry tools, the existing project management literature, e.g. the Project
         Management Body of Knowledge (PMBOK®) by the Project Management Institute
         (PMI) and world recognised professional certifications like the Project Management
         Professional (PMP®) offer excellent frameworks to manage detail complexity on
         projects (Project Management Institute 2008). The PMI provides a common language
         of project management that promotes learning, communication, creation of insights,
         and replication of successes on projects. Wide acceptance of this common language
         has led to huge advances in thought leadership and the project management field has
         now reached the stage where exponential growth and significant advances are
         possible in the way projects are managed in practice.

         1.3.2 Dynamic complexity

         In addition to the detail complexities of multiple resources, timelines, technologies, and
         targets, now we can also address the interdependencies between them and examine



5|Page
how those interdependencies change over time – leading to a transformation in our
         understanding of the dynamic complexity on projects as well.

         Similar to the advances in the theory of project management, areas of research from
         other disciplines, like system dynamics and systems thinking, explicitly study the
         dynamic behaviour that arises from process structures (Choudhari 1997). These
         disciplines have helped in the development of new tools and techniques to help study
         the dynamic aspects of project behaviour (Forrester 1961, 1968; Senge 1990). These
         new tools often include the use of computer software and simulation to aid managers
         in coping with problems that arise from dynamic complexity. The project dynamics
         approach provides a new, promising approach to understanding the dynamics of
         change on projects, and we discuss this approach next and how it can be used to
         inform the theory and practice of project management.


         1.4 The Project Dynamics Approach
         Project dynamics is the study of the dynamics that occurs on projects. Project
         dynamics presents a rigorous way to help thinking, visualising, sharing, and
         communicating the relationships and interdependencies between various components
         of a project and how these causal relationships determine behaviour of the project
         over time. By creating operational maps and simulation models which articulate
         manager’s ‘mental models’ and capture the interrelationships of physical and
         behavioural processes, internal and external factors, policies, information feedback
         and time delays, and by using these models to test alternative strategies, project
         dynamics helps solve project problems and create more robust project management
         architectures.

         Project dynamics and related system dynamics literature provides a rich source of
         research and studies into the performance of projects with emphasis on dynamic
         behaviour and the underlying structural determinants of behaviour. The studies in
         project dynamics could be grouped into four primary classes or meta-structures of
         models that cover project features, rework cycles, project control strategies including
         their anticipated and unintended consequences, and the cascading and subsequent
         effects of decisions during projects.

         We discuss these four classes of models and present some of them in the form of
         causal loop diagrams to provide the means for dialogue and communication of the
         project issues and relate the project dynamics models to the aforementioned war
         stories of project managers.

         1.4.1 Project Features

         Projects generally comprise of activities that are performed sequentially and
         concurrently. Therefore, like most project models, project dynamics models also
         include a representation of the actual activities and tasks on projects. Specific
         processes within a phase, various phases of a project, multiple projects in a program
         and their interdependencies can be modelled as they would exist in practice. Material
         flows, like lines of code, and information flows, like information available for decision
         making at a point in the system, are modelled explicitly along with the business
         policies that determine how that information is used to make decisions. Based on
         management perception of conditions at that point, resources are applied to manage
         the development processes on a project (Ford and Sterman 1998; Joglekar and Ford
         2005).



6|Page
Where project dynamics models get interesting and add new value is when they
         represent the perception gaps for managers, underestimation of scope and resources
         required, and include features that represent the human aspects of projects. There is
         often a difference between real progress and perceived progress of a project due to
         perception delays, lack of accurate information and undiscovered errors. Such errors
         also cause misallocation of resources that lead to performance problems. Human
         aspects like employee motivation when explicitly modelled add a new dimension of
         planning to projects. Modelling important components of actual projects increases the
         ability to simulate realistic project dynamics that relate directly to the experiences of
         practicing managers.

         Finally, companies are now using project dynamics models with increasing levels of
         sophistication and detail by including features like distinguishing work done correctly
         from work done incorrectly, multiple project phases, separate quality assurance efforts,
         nonlinear constraints of work availability on progress, development projects as value-
         adding aging chains, overlapping activities and concurrence constraints, design
         changes and uncertainties, releasing of completed work with unrecognised errors to
         downstream phases, the use of contingency funds, schedule buffers and various
         resource allocation policies.

         When used in a complementary manner to the PMI frameworks, these project feature
         models add significantly to the understanding of the dynamic complexities on projects
         and enhance the ability of managers to make decisions when confronted with
         perception gaps, delays in processes, and nonlinear relationships that change over
         the course of the project.

         1.4.2 Rework Cycles

         Rework cycles are one of the most important features of project dynamics models.
         The rework cycle occurs on projects when errors caused by doing work incorrectly
         results in having to do additional work to correct the errors or in redoing the work
         completely. However, as rework is done, the rework itself also tends to have errors
         causing further rework. Rework cycles are caused by this recursive nature of rework
         in which errors create rework which generates more errors that creates further rework,
         thereby creating problematic behaviours that often stretch out over most of a project’s
         duration and are the source of many project management challenges (Ford and
         Sterman 2003).

         Whether rework arrives unanticipated, or it is expected and estimated, or it is suddenly
         generated by external factors, it causes severe challenges for project managers.
         When rework is caused by unanticipated errors, project managers find that their
         project estimates have not accounted for or budgeted for this rework. Even when the
         fraction of rework is estimated and planned for on a project usually from past
         experiences with similar projects or statistical baselines from data collected on
         previous projects, the recursive compounding of rework is often underestimated.
         Furthermore, even with anticipated rates of rework, errors are seldom discovered
         immediately and there is usually a time delay between errors being generated and
         being detected either during testing or downstream at subsequent stages on a project.
         Finally, rework is very often triggered by external factors, like client changes in
         requirements. In this case, a project that was well on track earlier could easily be
         derailed due to the additional rework cycles created due to the externally generated
         changes.

         Project dynamics provides the concepts to better understand the cyclical nature of
         rework and the methodology to estimate more accurately the effort required due to


7|Page
rework cycles. Current models of rework include quality assurance activities, parallel
                         cycles to distinguish between whether rework was created by current or upstream
                         phases and whether rework occurs due to correcting flawed work or is initiated to
                         respond to externally generated changes.

                         As an introductory example to the use of a common diagramming technique of project
                         dynamics called causal loop diagramming, we present Figure 1: Project Rework
                         Structure. The causal loop diagram below represents the cause and effect
                         relationships on a project that interrelate to create dependencies and generate the
                         rework cycles on projects.


                                                                                        p r e s s u r e o n
                                                                                  S        s c h e d ule
                                                                                                                                                                 S
                                                                                                                                                               e rr o r g e n e r a ti o n
                                                                                                                                                     R 2                 r at e
                                                                                                                                 S
                                                                                                B
                                                   w o rk r e m ainin g t o                                              p e rc eiv e d w o rk
                                                          b e d o n e                                                   c o m p l e ti o n r a t e
                                                                      O
                                                                S
                                                                                      w o rk c o m plet e d         S
                                                                                                                                                           S       S
                                                                                        w it h o u t e rr o r s
                                                                                                                                         w o r k c o m p l e t e d w it h
                                                                                                                                          u n dis c o v e r e d e rr o rs
                                                                                                              R 1
                                                                        w o r k w it h e rr o r s
                                                                            dis c o v e r e d           S




                                                  Figure 1: Project Rework Structure

                         The first feedback cycle is a balancing loop (labelled B) where a larger amount of work
                         remaining to be done causes an increased work pressure on schedule which in turn
                         causes the perceived work completion rate also to increase similarly leading to an
                         increased amount of work completed without errors and this has an opposite effect, i.e.
                         it decreases the work remaining to be done. 1 The second feedback cycle is a
                         reinforcing loop (labelled R1) that shows that while the perceived work completion rate
                         is increasing the work completed with undiscovered errors is also increasing similarly
                         (‘s’ on the arrowhead) which after a time delay during which testing and quality
                         assurance is carried out the amount of work with errors discovered increases. This
                         leads to more work remaining to be done, i.e. rework. The additional work remaining
                         to be done leads to further pressure on schedule which leads to more work being
                         completed albeit with undiscovered errors creating this reinforcing cycle. The final
                         reinforcing loop R2 indicates that when pressure on schedule increases, this leads to
                         additional stress on the team and the error generation rate increases leading to an
                         increase in the work completed with undiscovered errors. While the first balancing
                         loop B represents the progress of work being done on a project without errors or
                         rework, the reinforcing loops R1 and R2 represent the effects of rework being created
                         and the effects of schedule pressure to increase errors (and therefore rework) on a
                         project respectively.

                         1.4.3 Project Control Strategies

                         The performance of a project is typically measured along the dimensions of schedule,
                         cost, and quality for the scope to be delivered. Through the course of project,
                         managers make decisions to control the performance gap between actual progress of

   1
    An ‘s’ near the arrowhead indicates that two factors mentioned at both ends of that arrow move in similar
   directions, while an ‘o’ indicates that the two factors move in opposite directions.


8|Page
the project and the performance targets set for the dimensions above (Lyneis et. al
         2001; Abdel-Hamid and Madnick 1991). However, as human beings, managers make
         decisions based on what they perceive and what information is available to them at
         that point in time. A unique aspect of project dynamics models is that they
         differentiate between perceived conditions and actual conditions on a project. The
         perceived conditions drive project control actions by managers and the actual
         conditions drive actual progress on projects. Project dynamics models that include
         aspects of information availability and human decision making help managers make
         better forecasts of project performance, and thereby make more informed project
         control actions.

         An example from our previous discussion on rework shows that managers generally
         include undiscovered rework in the work they perceive as completed as the errors are
         as yet undetected at that point in time. This often leads to overestimating progress
         and productivity at the early stages of a project. So while the actual progress made is
         less than it seems due to work completed containing undetected errors, future
         decisions and forecasts are made based on the amount of work that is incorrectly
         perceived to be completed.

         A causal loop diagram is shown in Figure 2 to represent common control actions by
         managers to address schedule slippage by increasing the labour resources on a
         project by using various interventions like increasing the work intensity, increasing
         overtime, and increasing the headcount on a project.
                                                       p r oje c t s c h e d ule
                                                         ti m e a v a il a b l e

                                                                                                        O
                                                                                            S      p r oje c t s c h e d ul e
                                               e s ti m a t e o f ti m e                                  p r e s s u r e
                                        r e q u ir e d f o r c o m p l e ti o n

                                                   S
                                                                                                                S
                                                                              B 2                                                B 3
                                 w o rk r e m ai ni n g                                         l a b o u r o v e rti m e                                       S
                                               O                                                                                           S              w o r k i n t e n s it y
                                                                                                        S                   la b o u r h e a d c o u nt
                                                                                                                      S
                                                                                    l a b o u r q u a n tit y
                                               r at e o f w o rk          S
                                                 c o m p l e ti o n
                                                                      S
                                                                                                                    B 1




                          Figure 2: Project Labour Control Interventions


         The balancing loop B1 shows that when project schedule pressure increases on a
         project due to the gap between project schedule time available and the estimate of
         time required for completion, as an intervention option, managers increase pressure
         on the project team to increase work intensity which then over time increases the rate
         of work completion leading to less work remaining. This in turn leads to a lower
         estimate of time required for completion of work and less project schedule pressure.
         The second type of intervention, viz. increasing overtime, is shown by the balancing
         loop B2, where an increase in project schedule pressure leads to increasing labour
         overtime which increases the effective amount of labour quantity available for the
         project leading to an increasing rate of work completion, less work remaining, a lower
         estimate of time required for completion, and subsequently less project schedule
         pressure. The third intervention of increasing headcount by adding people is shown
         by the balancing loop B3 where an increase in project schedule pressure leads to an
         increase in labour headcount leading to an increased labour quantity available to work


9|Page
on the project leading to more work being done and subsequently less schedule
               slippage.

               Figure 2 above illustrates how project control actions, like labour control actions, act
               through the system to control the performance gaps (in this case the schedule
               pressure that arises from a gap between estimate of time required for completion and
               project schedule time available). However, a variety of project control strategies can
               be modelled explicitly in models and the subsequent results can be seen. While the
               causal loop diagram above illustrates conceptually how control actions work,
               managers also need to know the size and speed of the adjustments they should make,
               an indication of the costs vs. benefits of each intervention and tools to assist them with
               designing superior strategies to control schedule slippage. For the design of
               intervention strategies, we will later discuss how project dynamics provides additional
               methodologies and tools to build simulation models of the project where such
               strategies can be designed and tested.

               1.4.4 Cascading and Subsequent Effects

               From the common war stories of project managers, we’ve seen how frequently used
               project control actions like increasing overtime, adding people and increasing work
               pressures on a team can have counterintuitive and unintended consequences of
               exacerbating the very project conditions of schedule slippage that they seek to
               alleviate due to the feedback effects of increasing errors, increasing rework,
               experience dilution, communication overheads, fatigue, burnout and worker turnover.

               Project dynamics literature often calls these cascading and subsequent effects ripple
               effects and knock-on effects and helps managers understand how these effects are
               created and how to avoid and alleviate them.

               1.4.5 Ripple Effects

               Ripple effects are the primary impacts of project control actions on rework and
               productivity and often include the dilution of experience levels, increased
               communication requirements, reduced productivity, lower quality and increased errors,
               and worker fatigue (Abdel-Hamid and Madnick 1991). We’ll use the same example of
               labour control interventions as in Figure 2 to illustrate how well meaning project control
               actions create these undesired effects.

                                                                  p r oj e c t s c h e d ule
                                                                    ti m e a v a il a b l e

                                                                                                                  O
                                                                                                       S      p r oje c t s c h e d ule
                                                          e s ti m a t e o f ti m e                                  p r e s s u r e
                                                   r e q u ir e d f o r c o m pl e ti o n

                                                              S
                                                                                                                                                                                              c ommunic at ion
                                                                                                                           S
                                                                                                                                                                                                 ov erheads
                                            w o rk r e m ai nin g                                          l a b o u r o v e rti m e                                     S
                                                                                                                                                  S
                                                          O                                                                                                        w o r k i n t e n s it y
                                                                                                                                   l a b o u r h e a d c o u n t
                                                                                                                   S
                                                                                                                               S
                                                                                               l a b o u r q u a n tit y
                                                         r at e o f w o rk
                                                                                                                                                              ex perienc e
                                                           c o m p l e ti o n
                                    f at igue
                                                                                                    error generat ion

                                                                                                             produc t iv it y




                  Figure 3: Cascading Ripple Effects of Project Labour Control Interventions




10 | P a g e
Figure 3 contains the same project control interventions as Figure 2. However, the
               unintended consequences of experience dilution, communication overheads and
               fatigue on error generation rates and productivity are added in the bolder links. By
               increasing labour headcount, i.e. adding new people midway on a project that either
               have less experience or at a minimum unfamiliar with the project, the experience
               levels of the team decreases leading to lower overall productivity and often increased
               error generation rates.      Also, increasing headcount increases communication
               overheads exponentially and this leads to similar effects on productivity and error
               generation rates. Increasing labour overtime can be a suitable short term strategy but
               eventually leads to fatigue which then leads to lower productivity and increased error
               generation rates. Increased work intensity leads to increases in error generation rates
               as well. These compounding increases in error generation rates increases the
               additional rework required to be done and lower productivity decreases the rate of
               work completion thereby defeating the very intent of managers behind the project
               control interventions. From Figure 3, it is easy to see how these ripple effects add to
               the dynamic complexities of the project and make such projects difficult to manage.

               1.4.6 Knock-on Effects

               Project dynamics models further analyze the impacts of the above ripple effects as
               they in turn cause secondary and tertiary effects that include out-of-sequence work,
               error contamination, additional work and lower employee morale (Lyneis and Ford
               2007) as shown in Figure 4.

                                                    project schedule
                                                     time available
                                                                                   O
                                                                           S
                                                                                project schedule
                                               estimate of time                     pressure
                                            required for completion
                                                   S
                                                                                                                                       communication
                                                                                           S
                                  morale                                                                                                 overheads

                                                                               labour overtime             S              S
                                        work remaining
                                                O
                                                                                                                      work intensity
                                                                                       S           labour headcount
                                                                                               S

                                                                      labour quantity
                                                rate of work                                                      experience
                                  fatigue        completion

                                                                          error generation

                                                                                 productivity




               Figure 4: Subsequent Knock-on Effects of Project Labour Control Interventions


               Figure 4 shows as an illustration one of these four subsequent knock-on effects of
               employee morale as affected by the impact of project control actions. As fatigue
               increases and the work remaining increases due to rework, employee morale begins
               to decrease leading to lower productivity and higher error generation rates. If low
               employee morale continues unchecked, it eventually results in employee turnover and
               lower experienced labour headcount on projects leading to further project problems.
               Other knock-on effects that are not shown in Figure 4 would include the impacts of
               using concurrency and overlapping activities on projects to reduce schedule slippage,
               knock-on effects of upstream errors causing errors downstream and tipping point
               effects where errors require more effort to fix than the original work required. If these
               causal loops were added to Figure 4, it is easy to see how the causal loop diagram,
               which is only a mapped representation of the project system, would be more complex
               and difficult to understand for managers.



11 | P a g e
While human beings are adept at specifying individual relationships between parts of a
               system, the human mind is not suited to understanding how all these parts interact
               simultaneously to create system performance. This is precisely one of the most
               significant contributions of project dynamics models where several relationships can
               be modelled by eliciting the information gained from managers’ experience and
               resident in the mental models of the managers’ mind and then simulated using
               computers to understand and plan for project performance. The models are only
               represented as causal loop diagrams above for transparency but using the language
               of project dynamics, these causal loop diagrams are meant to be modelled
               mathematically using stocks and flows on a computer. Models so developed can then
               be simulated on a computer and experimentation with a wide variety of inputs and
               policies are possible. The actual simulations reveal the working of the system
               behaviourally, and the underlying structures of the model can be studied by managers
               to understand the structural determinants of project behaviour. The models and
               simulations can be used by managers for experimentation to aid understanding and
               also to design specific project architectures, policies and interventions.


               1.5 Applications of Project Dynamics
               Project dynamics is growing in its usage both worldwide and in India and finds several
               applications in project management and allied activities on projects due to the depth of
               the investigation that is made possible because of these models. We discuss these
               applications here and, in the next section, we present directions for future work.

               1.5.1 Estimation and Risk Assessment

               The experiences of project managers and project data suggest strongly that often
               adverse project dynamics is caused by underestimating scope or under-budgeting for
               the estimated scope of work. Project dynamics models are now being used in
               conjunction with more traditional estimation approaches at three stages during a
               project: (1) Upfront, to adjust traditional estimates based on known or expected
               deviations (risks) from typical projects; (2) during the project, to determine the degree
               of any project underestimation earlier than would typically occur; and (3) after the
               project, to assess what the project should have cost had other decisions been taken,
               including better initial estimates.

               Project dynamics has been used for risk assessment in two ways: (1) Post-project
               evaluations that determine the magnitude of changes that actually occurred on
               projects as a guide for what might occur on future projects; and (2) pre-project
               simulations that test the consequences of similar risks for the current project.

               1.5.2 Project Control

               Even with improved estimation, risk assessment and planning, projects will rarely go
               exactly as planned. Project dynamics helps managers understand how they should
               best respond with their project control actions when problems occur. As seen from our
               discussion above on labour project control strategies, project dynamics provides key
               lessons and insights for managers in areas like managing the rework and minimizing
               the ripple and knock-on effects of the project control interventions.

               1.5.3 Risk Management

               Project dynamics models have helped managers develop insights by focusing on risk
               management approaches instead of specific policies, e.g. models have been used to


12 | P a g e
operationalise real options theory in projects for risk management. Project managers
               simultaneously seek project structures and policies that maximize project performance
               yet perform well when faced with a range of uncertainties that reflect risks. Project
               dynamics models show that managers who tailor polices for specific project
               assumptions can outperform those that manage for a wide range of conditions, if
               those project assumptions materialize. But if conditions deviate from those assumed
               by management, tailored policies generate much worse performance. Through
               simulation across various scenarios, these models help identify and address this
               fundamental trade-off between project robustness, i.e. the ability to perform well
               across a range of uncertain conditions, and performance under known specific
               conditions.

               1.5.4 Project Evaluations and Dispute Resolution

               Project dynamics models are often used for post-project assessment of projects to
               understand how and why the project deviated from the original plan. Most of these
               models are applied in situations involving disputes between the owner/financer of the
               project and the contractor/executer of the project. In many cases, such disputes
               involve claims of “delay and disruption” or in the project dynamics terminology, ripple
               and knock-on effects that result from problems on projects. These models are then
               used to quantify and explain the impact of deviations of the project on its final cost.
               The model can be set up to represent the project as it actually occurred, including the
               direct impacts, and calibrated to the actual performance of the project. It can also
               apportion costs to the client, to other parties, and to the contractor through simulations
               that involve removing different groups of direct impacts.

               1.5.5 Change Management

               When customers make changes to projects, the original plan almost always becomes
               infeasible. Change management entails pricing and mitigating proposed changes as
               they occur on an ongoing project (rather than waiting for disputes to occur after the
               project ends). Companies have used project dynamics models to assess optimal
               schedule extensions when changes are introduced on a project, examine the
               consequences of attempting to compress a project’s schedule, at the request of the
               client, and to forecast and mitigate change impacts, including quantifying the changes’
               effects, diagnosing the causes, and planning and testing mitigating actions to reduce
               project costs

               1.5.6 Individual and Organisational Learning

               The ability of project dynamics models to clearly and richly explain how project
               structures and behaviour interact makes them effective for teaching project
               management. A number of the project models have been converted into gaming
               simulators for use in management training. After such a simulation, the reasons for
               simulated project performance are analyzed, usually with causal loop diagrams such
               as those developed above, and the diagnostic output from the models is used to
               understand the dynamic complexity of projects that the many causal relations create
               and to appreciate the challenges of project management.


               1.6 Insights and Directions for Future Work
               From the body of knowledge that is emerging from the various applications where
               project dynamics models are being built, managers are seeing several insights
               emerge from both the models as well as possibilities to incorporate the project


13 | P a g e
dynamics approach into routine project management activities. These insights include
               a new awareness that project plans themselves sow the seeds for project success or
               failure even prior to execution, trying to achieve an overly aggressive plan often
               actually makes the performance of the project worse, recognising the existence of
               undiscovered rework and finding new ways to avoid its consequences, increasing
               early quality assurance even at lower initial productivity is generally beneficial to
               project outcomes, and prioritizing rework detection and correction over starting new
               work helps avoid downstream problems even though projects then seem to progress
               slower initially.

               Where managers have used these models, they have learned that even if recognised
               and designed well, the project control actions (like those discussed above) are often
               difficult to implement because implementation initiates worse-before-better project
               behaviour. By effectively demonstrating any worse-before-better dynamics and the
               eventual benefits of implementation, a formal model can give managers the courage
               to stay the course with the execution of innovative and counterintuitive project plans
               (Graham et al, 2002).

               While managers find the use of the project dynamics approach valuable when
               implemented, they sometimes find it difficult to initiate use of the approach for the first
               time with their project teams. One of the primary limitations in the practical and
               extensive use of project dynamics modelling is that many of the tools (which are
               usually computer-based) are often found by managers to be both complicated to
               understand and difficult to use in practice. So there is a need to be able to simplify
               and translate from this field of study to create practical and easily usable frameworks,
               and develop insights and ‘lessons learned’ to assist managers on their daily
               managerial decisions. Furthermore, managers see the need to integrate the project
               dynamics approach within the more familiar and traditionally accepted approaches
               and frameworks for project management like, for example, work breakdown structures,
               critical path modelling, and component cost estimating.

               Therefore, as directions for future work, we propose that the theory of project
               management would be enhanced by integrating research from the two different areas
               of traditional project management and project dynamics and that the practice of
               project management could be better informed by developing a model that can be used
               for experimentation and to develop insights that can aid managers’ decisions during
               actual project situations. In the next section, we outline the agenda and initial findings
               of a new study that proposes to meet these two objectives by integrating project
               dynamics insights within the PMI project management framework.


               1.7 Project Dynamics Integration Study
               To meet the two needs of developing a better understanding of the dynamic
               complexities on projects and augmenting the decision making ability of managers in
               practice, the utility of the study proposed is three-fold: (a) To improve the
               understanding of project management by incorporating insights from project dynamics
               within the commonly used PMI project management frameworks, (b) to build a model
               that can be used for experimentation and development of strategic decision making
               insights that will help managers improve performance on projects, and (c) to obtain
               experiential industry feedback and contextual support for the model and its findings
               through field studies with project managers.

               The initial findings of this project dynamics integration study can be grouped under
               three areas:


14 | P a g e
1.7.1 Improved Understanding of Project Dynamics
               The insights from project dynamics, and their relevance to the practice of project
               management, are enhanced by integrating the findings of research from project
               dynamics into the body of knowledge that is used by project management practitioners.
               By relating the varied project processes, resources, decisions, scope and performance
               targets into a single model, this study has begun the groundwork to present a new tool
               for project managers to investigate the dynamics of projects.

               1.7.2 Development of Model for Decision Making
               To cross the bridge from research to practice, this study will provide utility to the
               practice of project management by developing a model for experimentation that is
               intended to help managers make better project control and management decisions.
               The model presented in this study represents several detailed hypotheses (like
               tradeoffs of cost vs. schedule, impact of rework, and the like) and assumptions about
               policies and decision making – these can be validated or alternative policies can be
               defined and experimented with using the model developed in this study. The model is
               expected to have significant utility for field managers as through the use of and
               experimentation with the model, managers will enrich their mental models by giving
               them insights into the systemic causes of success and failure on projects (Senge,
               1990).

               1.7.3 Contextual Feedback
               Project management is required in a variety of classes of projects, like construction,
               software, new product development, and the like; however, the empirical portion of
               this study has focused on one industry, viz., the construction industry and aims to
               enumerate the contextual and situational factors that determine the utility of the model
               and its findings for project managers in this industry. The findings of this study will be
               used to obtain contextual feedback from project managers on construction projects,
               and by doing so, enhance the applicability of the lessons learned within the context of
               the construction industry. The model so developed will eventually be converted into a
               management simulator and provided to all participants of the study to benefit from the
               opportunity to experiment with and develop their own insights from the model
               developed.


               1.8 Conclusions
               Project dynamics represents an exciting approach to transform the way project
               managers think about their projects, transform their ability to direct and control
               projects, and transform the levels of eventual project performance. The applications
               of project dynamics models are increasing as is evidenced from the fact that models
               are increasingly being built and used by companies for a variety of purposes from
               defining project strategy to estimation to post-mortem evaluations to dispute resolution.
               The usage of the project dynamics approach by managers can be enhanced by
               integration of the project dynamics approach within the widely accepted PMI
               frameworks and the PMBOK. The study to integrate these approaches and
               frameworks is currently underway and promises to help both academicians and
               managers better understand the emerging insights and opportunities for the future of
               project management theory and practice.




15 | P a g e
1.9 References

               1.   Abdel-Hamid TK, Madnick SE. 1991. Software Project Dynamics: An Integrated
                    Approach. Prentice-Hall: Englewood Cliffs, NJ.
               2.   Choudhari, M. D. 2007. The Dynamics of Competitive Strategy. SM Thesis,
                    Massachusetts Institute of Technology, February 1997.
               3.   Forrester JW. 1961. Industrial Dynamics. MIT Press: Cambridge, MA.
               4.   Forrester JW. 1968. Principles of Systems. MIT Press: Cambridge, MA.
               5.   Ford, D.N. The Dynamics of Project Management: An Investigation of the
                    Impacts of Project Process and Coordination on Performance. Ph.D.
                    Dissertation, Massachusetts Institute of Technology, August 1995.
               6.   Ford, D.N and Sterman, J.D. 2003. “The liar’s club: impacts of concealment in
                    concurrent development projects.” Concurrent Engineering Research and
                    Applications 111(3): 211–219.
               7.   Ford, D.N and Sterman, J.D. 1998. “Modeling Dynamic Development
                    Processes.” System Dynamics Review. 14(1): 31-68.
               8.   Graham AK, Moore J, Choi CY. 2002. “How robust are conclusions from a
                    complex calibrated model, really? A project management model benchmark
                    using fit constrained Monte Carlo analysis.” Proceedings of the 2002
                    International System Dynamics Conference: Palermo, Italy.
               9.   Joglekar N, Ford DN. 2005. “Product development resource allocation with
                    foresight.” European Journal of Operational Research 160(1): 72–87.
               10. Lyneis, James M, and David N Ford. "System Dynamics Applied to Project
                   Management: A Survey, Assessment and Directions for Future Research."
                   System Dynamics Review 23, no. 2/3 (Summer/Fall 2007): 157-189.
               11. Lyneis, James M., Cooper, Kenneth G., and Els, Sharon A., 2001. “Strategic
                   Management of Complex Projects: A Case Study Using System Dynamics.”
                   System Dynamics Review 17(3), 237–260.
               12. McKinsey & Company, Financial Services Practice. 2008. Building India:
                   Financing and Investing in Infrastructure. 9-13.
               13. Project Management Institute (PMI), 2008. A Guide to the Project Management
                   Body of Knowledge, PMBOK Guide - Fourth Edition.
               14. Senge P. 1990. The Fifth Discipline, the Art and Practice of the Learning
                   Organization. Doubleday/Currency: New York.
               15. Sterman, John. 1992. System Dynamics Modelling for Project Management, pp
                   12.




16 | P a g e
1.10 Author’s Profile




               Mark D. Choudhari is a Director and Chief Strategy Officer at the Lotus
               Group. He has 16 years of global business experience and has worked with
               clients in North America, Europe, and the Asia-Pacific region. Mark has
               assisted companies in multiple industries and government and advises senior
               management in the areas of strategy, market and competitive dynamics,
               private equity, product development, performance improvement, change
               management and technology assimilation. Prior to the Lotus Group, Mark was
               co-founder and director at the Machintel Corporation, USA and Nathan Ark
               Software (P) Ltd. in India, was an expert consultant in system dynamics at the
               Arthur Andersen Business Consulting group, Chicago, and has led a research
               group at the MIT Sloan School of Management. He has several publications
               in strategy and finance and is a regular speaker at conferences. He is an
               active participant in community service and has established trusts in the USA
               and India for education. Mark holds undergraduate and graduate degrees in
               engineering, computer science and economics from the Massachusetts
               Institute of Technology.

               E-mail: mark@lotusprojects.com




17 | P a g e

Weitere ähnliche Inhalte

Was ist angesagt?

SDPM - Lecture 2 -The STEP WISE Approach to Project Planning
SDPM - Lecture 2 -The STEP WISE Approach to Project PlanningSDPM - Lecture 2 -The STEP WISE Approach to Project Planning
SDPM - Lecture 2 -The STEP WISE Approach to Project PlanningOpenLearningLab
 
Project Management Diploma
Project Management DiplomaProject Management Diploma
Project Management DiplomaTheunis Venter
 
Project Re-Alignment by Teambuilding
Project Re-Alignment by TeambuildingProject Re-Alignment by Teambuilding
Project Re-Alignment by TeambuildingDr. Thomas Juli
 
Agile project management is systems management
Agile project management is systems managementAgile project management is systems management
Agile project management is systems managementGlen Alleman
 
Project mangement chp 1 12
Project mangement chp 1 12Project mangement chp 1 12
Project mangement chp 1 12Dreams Design
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project ManagementAnil Singh
 
Project Management for IT-related Projects (Logitrain)
Project Management for IT-related Projects (Logitrain)Project Management for IT-related Projects (Logitrain)
Project Management for IT-related Projects (Logitrain)Logitrain: New Zealand
 
Pressman ch-21-project-management-concepts
Pressman ch-21-project-management-conceptsPressman ch-21-project-management-concepts
Pressman ch-21-project-management-conceptsseethaveera
 
Agile project management framework
Agile project management frameworkAgile project management framework
Agile project management frameworkstefanhenry
 
How to Avoid Project Train Wrecks
How to Avoid Project Train WrecksHow to Avoid Project Train Wrecks
How to Avoid Project Train WrecksPete Luan
 
Old definition of project management
Old definition of project managementOld definition of project management
Old definition of project managementArlen Mark
 
6455922 project-management-teacher-notes
6455922 project-management-teacher-notes6455922 project-management-teacher-notes
6455922 project-management-teacher-notesBhanu Singh
 
A Beginner's Guide to IT Project Management
A Beginner's Guide to IT Project ManagementA Beginner's Guide to IT Project Management
A Beginner's Guide to IT Project ManagementWorkfront
 
Epm7e slides ch10 agile project management
Epm7e slides ch10 agile project managementEpm7e slides ch10 agile project management
Epm7e slides ch10 agile project managementRishabhAgarwal823918
 
An Introduction to Agile Project Management
An Introduction to Agile Project ManagementAn Introduction to Agile Project Management
An Introduction to Agile Project ManagementMarcello Brivio
 
Project Planning in Software Engineering
Project Planning in Software EngineeringProject Planning in Software Engineering
Project Planning in Software EngineeringFáber D. Giraldo
 
5 Key Chart Project Management (TM) Methodology
5 Key Chart Project Management (TM) Methodology5 Key Chart Project Management (TM) Methodology
5 Key Chart Project Management (TM) Methodologyjmcmahon89
 

Was ist angesagt? (20)

SDPM - Lecture 2 -The STEP WISE Approach to Project Planning
SDPM - Lecture 2 -The STEP WISE Approach to Project PlanningSDPM - Lecture 2 -The STEP WISE Approach to Project Planning
SDPM - Lecture 2 -The STEP WISE Approach to Project Planning
 
Project Management Diploma
Project Management DiplomaProject Management Diploma
Project Management Diploma
 
Pmp hr chapter 9
Pmp hr chapter 9Pmp hr chapter 9
Pmp hr chapter 9
 
Project Re-Alignment by Teambuilding
Project Re-Alignment by TeambuildingProject Re-Alignment by Teambuilding
Project Re-Alignment by Teambuilding
 
Agile project management is systems management
Agile project management is systems managementAgile project management is systems management
Agile project management is systems management
 
Project mangement chp 1 12
Project mangement chp 1 12Project mangement chp 1 12
Project mangement chp 1 12
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
Project Management for IT-related Projects (Logitrain)
Project Management for IT-related Projects (Logitrain)Project Management for IT-related Projects (Logitrain)
Project Management for IT-related Projects (Logitrain)
 
Pressman ch-21-project-management-concepts
Pressman ch-21-project-management-conceptsPressman ch-21-project-management-concepts
Pressman ch-21-project-management-concepts
 
Agile project management framework
Agile project management frameworkAgile project management framework
Agile project management framework
 
How to Avoid Project Train Wrecks
How to Avoid Project Train WrecksHow to Avoid Project Train Wrecks
How to Avoid Project Train Wrecks
 
Old definition of project management
Old definition of project managementOld definition of project management
Old definition of project management
 
6455922 project-management-teacher-notes
6455922 project-management-teacher-notes6455922 project-management-teacher-notes
6455922 project-management-teacher-notes
 
Project managemen concept
Project managemen conceptProject managemen concept
Project managemen concept
 
A Beginner's Guide to IT Project Management
A Beginner's Guide to IT Project ManagementA Beginner's Guide to IT Project Management
A Beginner's Guide to IT Project Management
 
Epm7e slides ch10 agile project management
Epm7e slides ch10 agile project managementEpm7e slides ch10 agile project management
Epm7e slides ch10 agile project management
 
An Introduction to Agile Project Management
An Introduction to Agile Project ManagementAn Introduction to Agile Project Management
An Introduction to Agile Project Management
 
Project Planning in Software Engineering
Project Planning in Software EngineeringProject Planning in Software Engineering
Project Planning in Software Engineering
 
Project Management Concepts
Project Management ConceptsProject Management Concepts
Project Management Concepts
 
5 Key Chart Project Management (TM) Methodology
5 Key Chart Project Management (TM) Methodology5 Key Chart Project Management (TM) Methodology
5 Key Chart Project Management (TM) Methodology
 

Andere mochten auch

Advancing The Project Management Profession
Advancing The Project Management ProfessionAdvancing The Project Management Profession
Advancing The Project Management Professionpmief
 
How to summarize a research paper
How to summarize a research paperHow to summarize a research paper
How to summarize a research paperEssayAcademy
 
Sector textil y confecciones peruanas
Sector textil y confecciones peruanasSector textil y confecciones peruanas
Sector textil y confecciones peruanasEduPeru
 
FGD konservasi air di DAS prioritas
FGD konservasi air di DAS prioritasFGD konservasi air di DAS prioritas
FGD konservasi air di DAS prioritasDasapta Erwin Irawan
 
R programming language: conceptual overview
R programming language: conceptual overviewR programming language: conceptual overview
R programming language: conceptual overviewMaxim Litvak
 
Tejido conectivo y adiposo
Tejido conectivo y adiposoTejido conectivo y adiposo
Tejido conectivo y adiposoTomás Calderón
 
Tipos de Placa-Mãe
Tipos de Placa-MãeTipos de Placa-Mãe
Tipos de Placa-MãeAirin A.
 
बस्तर में पत्रकारिता के समक्ष चुनौतियां
बस्तर में पत्रकारिता के समक्ष चुनौतियांबस्तर में पत्रकारिता के समक्ष चुनौतियां
बस्तर में पत्रकारिता के समक्ष चुनौतियांPeople's Archive of Rural India
 
Metabolic acidosis by akram
Metabolic acidosis by akramMetabolic acidosis by akram
Metabolic acidosis by akramFateh Dolon
 
Pengolahan Data Geolistrik KARSAM 2012
Pengolahan Data Geolistrik KARSAM 2012Pengolahan Data Geolistrik KARSAM 2012
Pengolahan Data Geolistrik KARSAM 2012Fajar Perdana
 

Andere mochten auch (20)

Rsc 06
Rsc 06Rsc 06
Rsc 06
 
Advancing The Project Management Profession
Advancing The Project Management ProfessionAdvancing The Project Management Profession
Advancing The Project Management Profession
 
Csf earpdf
Csf earpdfCsf earpdf
Csf earpdf
 
Step into Siren
Step into SirenStep into Siren
Step into Siren
 
Bellringer match
Bellringer matchBellringer match
Bellringer match
 
Kjgherjff
KjgherjffKjgherjff
Kjgherjff
 
Practica 2 niveles
Practica 2 nivelesPractica 2 niveles
Practica 2 niveles
 
Travel World
Travel WorldTravel World
Travel World
 
How to summarize a research paper
How to summarize a research paperHow to summarize a research paper
How to summarize a research paper
 
Counseling Resume
Counseling ResumeCounseling Resume
Counseling Resume
 
Milk and egg major states 2005 06 to 2009-10
Milk and egg major states 2005 06 to 2009-10Milk and egg major states 2005 06 to 2009-10
Milk and egg major states 2005 06 to 2009-10
 
Sector textil y confecciones peruanas
Sector textil y confecciones peruanasSector textil y confecciones peruanas
Sector textil y confecciones peruanas
 
FGD konservasi air di DAS prioritas
FGD konservasi air di DAS prioritasFGD konservasi air di DAS prioritas
FGD konservasi air di DAS prioritas
 
R programming language: conceptual overview
R programming language: conceptual overviewR programming language: conceptual overview
R programming language: conceptual overview
 
Obesidad
ObesidadObesidad
Obesidad
 
Tejido conectivo y adiposo
Tejido conectivo y adiposoTejido conectivo y adiposo
Tejido conectivo y adiposo
 
Tipos de Placa-Mãe
Tipos de Placa-MãeTipos de Placa-Mãe
Tipos de Placa-Mãe
 
बस्तर में पत्रकारिता के समक्ष चुनौतियां
बस्तर में पत्रकारिता के समक्ष चुनौतियांबस्तर में पत्रकारिता के समक्ष चुनौतियां
बस्तर में पत्रकारिता के समक्ष चुनौतियां
 
Metabolic acidosis by akram
Metabolic acidosis by akramMetabolic acidosis by akram
Metabolic acidosis by akram
 
Pengolahan Data Geolistrik KARSAM 2012
Pengolahan Data Geolistrik KARSAM 2012Pengolahan Data Geolistrik KARSAM 2012
Pengolahan Data Geolistrik KARSAM 2012
 

Ähnlich wie Trn 05

Project management practices the criteria for success or failure
Project management practices the criteria for success or failureProject management practices the criteria for success or failure
Project management practices the criteria for success or failureTa Ngoc
 
Critical thinking Project Management.docx
Critical thinking Project Management.docxCritical thinking Project Management.docx
Critical thinking Project Management.docxwrite22
 
Critical thinking Project Management.docx
Critical thinking Project Management.docxCritical thinking Project Management.docx
Critical thinking Project Management.docxwrite31
 
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...IRJET Journal
 
Mega project not mega problems session 1
Mega project not mega problems session 1Mega project not mega problems session 1
Mega project not mega problems session 1Aconex
 
Project Management, Perspective, Planning And Implementation
Project Management, Perspective, Planning And ImplementationProject Management, Perspective, Planning And Implementation
Project Management, Perspective, Planning And ImplementationCamella Taylor
 
Strategies for successful_engineering_management
Strategies for successful_engineering_managementStrategies for successful_engineering_management
Strategies for successful_engineering_managementSociety of Women Engineers
 
Project Management: A Critical Examination of the PPARS Project
Project Management: A Critical Examination of the PPARS ProjectProject Management: A Critical Examination of the PPARS Project
Project Management: A Critical Examination of the PPARS ProjectOlivia Moran
 
Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.Renee Jones
 
Chapter 3 Lecture Slides
Chapter 3 Lecture SlidesChapter 3 Lecture Slides
Chapter 3 Lecture Slidesdotesch
 
Advanced concept of project risk management project report
Advanced concept of project risk management project reportAdvanced concept of project risk management project report
Advanced concept of project risk management project reportramesh roy
 
100 Project Management-Success Factor
100 Project Management-Success Factor100 Project Management-Success Factor
100 Project Management-Success FactorDr Fereidoun Dejahang
 
Why projects fail avoiding the classic pitfalls
Why projects fail avoiding the classic pitfallsWhy projects fail avoiding the classic pitfalls
Why projects fail avoiding the classic pitfallsTa Ngoc
 
5 project management project planning
5 project management  project planning5 project management  project planning
5 project management project planningYasirHamour
 

Ähnlich wie Trn 05 (20)

Project management practices the criteria for success or failure
Project management practices the criteria for success or failureProject management practices the criteria for success or failure
Project management practices the criteria for success or failure
 
Critical thinking Project Management.docx
Critical thinking Project Management.docxCritical thinking Project Management.docx
Critical thinking Project Management.docx
 
Critical thinking Project Management.docx
Critical thinking Project Management.docxCritical thinking Project Management.docx
Critical thinking Project Management.docx
 
Iss 02
Iss 02Iss 02
Iss 02
 
PMC4
PMC4PMC4
PMC4
 
MCP3
MCP3MCP3
MCP3
 
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
 
PM 01 - Introduction to Project Management
PM 01 - Introduction to Project ManagementPM 01 - Introduction to Project Management
PM 01 - Introduction to Project Management
 
Mega project not mega problems session 1
Mega project not mega problems session 1Mega project not mega problems session 1
Mega project not mega problems session 1
 
Entra lecture6 PM1.pdf
Entra lecture6 PM1.pdfEntra lecture6 PM1.pdf
Entra lecture6 PM1.pdf
 
Project Management, Perspective, Planning And Implementation
Project Management, Perspective, Planning And ImplementationProject Management, Perspective, Planning And Implementation
Project Management, Perspective, Planning And Implementation
 
Strategies for successful_engineering_management
Strategies for successful_engineering_managementStrategies for successful_engineering_management
Strategies for successful_engineering_management
 
Project Management: A Critical Examination of the PPARS Project
Project Management: A Critical Examination of the PPARS ProjectProject Management: A Critical Examination of the PPARS Project
Project Management: A Critical Examination of the PPARS Project
 
Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.
 
Chapter 3 Lecture Slides
Chapter 3 Lecture SlidesChapter 3 Lecture Slides
Chapter 3 Lecture Slides
 
Advanced concept of project risk management project report
Advanced concept of project risk management project reportAdvanced concept of project risk management project report
Advanced concept of project risk management project report
 
CIA_application award paper
CIA_application award paperCIA_application award paper
CIA_application award paper
 
100 Project Management-Success Factor
100 Project Management-Success Factor100 Project Management-Success Factor
100 Project Management-Success Factor
 
Why projects fail avoiding the classic pitfalls
Why projects fail avoiding the classic pitfallsWhy projects fail avoiding the classic pitfalls
Why projects fail avoiding the classic pitfalls
 
5 project management project planning
5 project management  project planning5 project management  project planning
5 project management project planning
 

Mehr von PMInstituteIndia (20)

Piyush govil archana_sharma
Piyush govil  archana_sharmaPiyush govil  archana_sharma
Piyush govil archana_sharma
 
D john peter
D john peterD john peter
D john peter
 
Trn 10
Trn 10Trn 10
Trn 10
 
Trn 11
Trn 11Trn 11
Trn 11
 
Trn 09
Trn 09Trn 09
Trn 09
 
Trn 08
Trn 08Trn 08
Trn 08
 
Trn 07
Trn 07Trn 07
Trn 07
 
Trn 06
Trn 06Trn 06
Trn 06
 
Trn 04
Trn 04Trn 04
Trn 04
 
Trn 03
Trn 03Trn 03
Trn 03
 
Trn 02
Trn 02Trn 02
Trn 02
 
Trn 01
Trn 01Trn 01
Trn 01
 
Trn 12
Trn 12Trn 12
Trn 12
 
Sps 01
Sps 01Sps 01
Sps 01
 
Sft 03
Sft 03Sft 03
Sft 03
 
Sft 02
Sft 02Sft 02
Sft 02
 
Sft 01
Sft 01Sft 01
Sft 01
 
Sft 04
Sft 04Sft 04
Sft 04
 
Rsc 05
Rsc 05Rsc 05
Rsc 05
 
Rsc 04
Rsc 04Rsc 04
Rsc 04
 

Kürzlich hochgeladen

KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...Any kyc Account
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyEthan lee
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurSuhani Kapoor
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdftbatkhuu1
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsApsara Of India
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 DelhiCall Girls in Delhi
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 

Kürzlich hochgeladen (20)

KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdf
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 

Trn 05

  • 1. Aum gam ganapataye namya. Project Dynamics: Emerging Insights & Opportunities for the Future of Project Management Theory & Practice Mark D. Choudhari THE LOTUS GROUP
  • 2. Contents 1.1  Abstract 3 1.2 Keyword 3 1.3 Introduction 3 1.4  The Project Dynamics Approach 6  1.4.1  Project Features 6  1.4.2  Rework Cycles 7  1.4.3  Project Control Strategies 8  1.4.4  Cascading and Subsequent Effects 10  1.4.5.  Ripple Effects 10  1.4.6.  Knock-on Effects 11  1.5  Applications of Project Dynamics 12  1.5.1  Estimation and Risk Assessment 12  1.5.2  Project Control 12  1.5.3  Risk Management 12  1.5.4  Project Evaluations and Dispute Resolution 13  1.5.5  Change Management 13  1.5.6  Individual and Organisational Learning 13  1.6.  Insights and Directions for Future Work 13  1.7 Project Dynamics Integration Study 14  1.8 Conclusions 15  1.9 References 16 1.10 Authors Profile 17  2|Page
  • 3. 1.1 Abstract Companies and individuals searching for revolutionary advances to enhancing their project management competencies have started applying project dynamics concepts and tools on their projects both across the world and increasingly in India. Project Dynamics, as emerging from the field of system dynamics, provides a radical, exciting approach that has begun to create new insights and initiate new advances in project management. This paper emphasizes the growth of project dynamics in setting new standards for excellence in project management through a transformation of the understanding of dynamics resulting from project features, rework cycles, reinforcing and balancing feedback, and the unintended consequences of project control strategies that create adverse dynamics. The paper (a) discusses the project dynamics approach from a structural and behavioural perspective, (b) highlights applications of project dynamics like post-mortem project evaluations and dispute resolution, estimation and risk assessment, project control, change management, and organisational learning, (c) presents strategic policy insights and directions for the future of project management theory and practice, and (d) presents the agenda and initial findings of a new study to integrate project dynamics within the PMI project management framework. The results of this study will help project management professionals and managers incorporate project dynamics concepts and tools in their practice and succeed in implementing the insights gained from a greater understanding of dynamics for superior performance on projects. 1.2 Keywords: project management, project dynamics, project strategy, system dynamics, PMBoK 1.3 Introduction In recent times, project management has been gaining in strategic importance for both industry and government. The importance of being able to manage projects well has never been greater in these times of increased industrial density, globalisation, foreign investment, and the use of advanced technologies making projects larger in scope, technically more complex, and financially more critical. However, only one out of three projects achieve all four of their initial project requirements of budget, duration, quality and scope (McKinsey & Company, 2008). Projects frequently face cost overruns, completion delays, compromised quality, and reduced scope. A recent example is the Mumbai Sea-link project that was not only over-budget (project budget increased more than five-fold from Rs. 300 crores to over Rs. 1,634 crores), was significantly delayed (by 5 years from a launch date of 2004 to 2009) and had to manage scope delivery to make the project launch in 2009 with 4 lanes instead of 8; the further four lanes were finally launched yet another year later in 2010. International examples of poor project performance, like the Channel Tunnel and the Boston Big Dig, demonstrate that poor project success rates are not endemic to a particular region but are a universal phenomenon. In a recent online project management forum, when asked what was the biggest problem facing project management, managers across the world provided over 900 responses indicating that projects usually failed to meet their initial success criteria due to contributing factors like poor estimation during planning, changes in scope throughout execution, underestimating the complexity of implementation, and rework 3|Page
  • 4. (due to errors) that is discovered while monitoring the project. Even with the best laid plans, managers need to continually exercise control decisions to address deviations of the project from its plan. Therefore, managers look for combinations of project control interventions to bring a project back to meeting its targets with the least adverse consequences. However, different amounts, durations and orders of application of such project control decisions impact project performance in different ways and cause problems of their own. Some of the commonly recurring war stories from project managers are shared below: Even after well defined plans, managers find that due to unanticipated errors a significant amount of rework is generated that also needs to be completed in addition to the initial estimates of work. Such rework, when discovered in time, can still however be addressed but when it goes undiscovered causes even further rework downstream in subsequent phases of projects. To further compound the problem, fixing the errors often requires more work than doing the work in the first place – this is especially true when downstream work is contaminated by undiscovered upstream errors. Common interventions possible when project deadlines begin to slip are to increase overtime, hire additional people onto the project team, and to increase the pressure on the team to speed up the work being completed. In practice, various combinations of these three options are used as considered appropriate by project managers. However, it is often noticed by managers that these interventions cause other unintended effects as well. Overtime often works well in the short term to accelerate work done but in the longer term it leads to fatigue of the team. Errors then begin to increase leading to additional rework and therefore lower productivity. Using overtime even beyond this leads to worker burnout and often attrition. Increasing the project team size is a another popularly used intervention when projects find themselves behind schedule. However, adding people midway through a project can dilute experience as workers with less skill or less familiarity with the project are brought on, they require time from experienced team members to bring them up to speed, and communication overheads grow exponentially with the number of stakeholders. Sometimes the unavailability of experienced persons to bring onto the project precludes the use of this option itself. Experience dilution and increased communications often increase errors, decrease the pace of work and decrease productivity. The third option of increasing work pressure also often leads to increasing errors as haste makes waste – thereby increasing rework and reducing productivity. It is clear from the above that the very decisions intended to increase productivity and speed up progress by increasing overtime, adding people, or increasing work intensity often achieve exactly the opposite result due to the unintended consequences of these decisions. Project managers often relate that their projects seem to be a system with ‘a mind of its own’ where the system itself offers resistance to their efforts to control it. Another interesting intervention by project managers to combat milestone slippage is to try and increase the concurrency of activities on projects over and above the initial plan. However, as the initial project plan is modified and more concurrencies are attempted, often work starts to be done out of sequence leading to increasing errors and rework, and reducing productivity. These errors then cause further errors downstream if not discovered and corrected in time. 4|Page
  • 5. External factors, like changes in scope or requirements by the client, often activate a variety of project control interventions by managers leading to internal dynamics as described above thereby ruining projects that were otherwise successful. The unintended consequences of managerial decisions like increasing error rates, increasing rework and worker fatigue leads to morale and motivation problems, which when unchecked, sometimes leads to a sense of frustration and hopelessness on projects and eventually turnover leading to further workforce issues. While managers are quick to recognise the effects described above as commonly occurring on projects, they find it difficult to understand the nature and strength of the interrelationships within the project ‘system’ and how they differ both within a particular project phase, between two different phases or on different projects. Moreover, this has led to managers seeking better approaches to measure the impact of different decisions to help them design superior interventions that achieve project milestones with greater speed, less cost, and better quality without compromising scope. We look at the issues and challenges that managers have to deal with on projects along the two dimensions of detail complexity and dynamic complexity. 1.3.1 Detail complexity Project managers, especially on large, complex projects, routinely use the existing state-of-the-art in project management tools, techniques and decision support software. While existing project management tools are pervasive in their usage, they largely deal with the static features, i.e. detail complexity, of projects. However, most project managers do not effectively understand or utilise the dynamic features of project processes like feedback, time delays, and non-linear cause-effect relationships between project components (Sterman 1992; Brooks 1978). Commonly used tools like the Program Evaluation and Review Technique (PERT), the Critical Path Method (CPM), related work breakdown structure (WBS) tools and component cost estimating are widely used to manage development projects. However the limitations of such tools to address project issues like undiscovered rework, bilaterally coupled activities involving feedback and iteration, and time-varying and endogenous factors (like skill, training and coordination) make them inadequate to model the highly coupled aspects and dynamic nature of the development process (Ford 1995). Apart from industry tools, the existing project management literature, e.g. the Project Management Body of Knowledge (PMBOK®) by the Project Management Institute (PMI) and world recognised professional certifications like the Project Management Professional (PMP®) offer excellent frameworks to manage detail complexity on projects (Project Management Institute 2008). The PMI provides a common language of project management that promotes learning, communication, creation of insights, and replication of successes on projects. Wide acceptance of this common language has led to huge advances in thought leadership and the project management field has now reached the stage where exponential growth and significant advances are possible in the way projects are managed in practice. 1.3.2 Dynamic complexity In addition to the detail complexities of multiple resources, timelines, technologies, and targets, now we can also address the interdependencies between them and examine 5|Page
  • 6. how those interdependencies change over time – leading to a transformation in our understanding of the dynamic complexity on projects as well. Similar to the advances in the theory of project management, areas of research from other disciplines, like system dynamics and systems thinking, explicitly study the dynamic behaviour that arises from process structures (Choudhari 1997). These disciplines have helped in the development of new tools and techniques to help study the dynamic aspects of project behaviour (Forrester 1961, 1968; Senge 1990). These new tools often include the use of computer software and simulation to aid managers in coping with problems that arise from dynamic complexity. The project dynamics approach provides a new, promising approach to understanding the dynamics of change on projects, and we discuss this approach next and how it can be used to inform the theory and practice of project management. 1.4 The Project Dynamics Approach Project dynamics is the study of the dynamics that occurs on projects. Project dynamics presents a rigorous way to help thinking, visualising, sharing, and communicating the relationships and interdependencies between various components of a project and how these causal relationships determine behaviour of the project over time. By creating operational maps and simulation models which articulate manager’s ‘mental models’ and capture the interrelationships of physical and behavioural processes, internal and external factors, policies, information feedback and time delays, and by using these models to test alternative strategies, project dynamics helps solve project problems and create more robust project management architectures. Project dynamics and related system dynamics literature provides a rich source of research and studies into the performance of projects with emphasis on dynamic behaviour and the underlying structural determinants of behaviour. The studies in project dynamics could be grouped into four primary classes or meta-structures of models that cover project features, rework cycles, project control strategies including their anticipated and unintended consequences, and the cascading and subsequent effects of decisions during projects. We discuss these four classes of models and present some of them in the form of causal loop diagrams to provide the means for dialogue and communication of the project issues and relate the project dynamics models to the aforementioned war stories of project managers. 1.4.1 Project Features Projects generally comprise of activities that are performed sequentially and concurrently. Therefore, like most project models, project dynamics models also include a representation of the actual activities and tasks on projects. Specific processes within a phase, various phases of a project, multiple projects in a program and their interdependencies can be modelled as they would exist in practice. Material flows, like lines of code, and information flows, like information available for decision making at a point in the system, are modelled explicitly along with the business policies that determine how that information is used to make decisions. Based on management perception of conditions at that point, resources are applied to manage the development processes on a project (Ford and Sterman 1998; Joglekar and Ford 2005). 6|Page
  • 7. Where project dynamics models get interesting and add new value is when they represent the perception gaps for managers, underestimation of scope and resources required, and include features that represent the human aspects of projects. There is often a difference between real progress and perceived progress of a project due to perception delays, lack of accurate information and undiscovered errors. Such errors also cause misallocation of resources that lead to performance problems. Human aspects like employee motivation when explicitly modelled add a new dimension of planning to projects. Modelling important components of actual projects increases the ability to simulate realistic project dynamics that relate directly to the experiences of practicing managers. Finally, companies are now using project dynamics models with increasing levels of sophistication and detail by including features like distinguishing work done correctly from work done incorrectly, multiple project phases, separate quality assurance efforts, nonlinear constraints of work availability on progress, development projects as value- adding aging chains, overlapping activities and concurrence constraints, design changes and uncertainties, releasing of completed work with unrecognised errors to downstream phases, the use of contingency funds, schedule buffers and various resource allocation policies. When used in a complementary manner to the PMI frameworks, these project feature models add significantly to the understanding of the dynamic complexities on projects and enhance the ability of managers to make decisions when confronted with perception gaps, delays in processes, and nonlinear relationships that change over the course of the project. 1.4.2 Rework Cycles Rework cycles are one of the most important features of project dynamics models. The rework cycle occurs on projects when errors caused by doing work incorrectly results in having to do additional work to correct the errors or in redoing the work completely. However, as rework is done, the rework itself also tends to have errors causing further rework. Rework cycles are caused by this recursive nature of rework in which errors create rework which generates more errors that creates further rework, thereby creating problematic behaviours that often stretch out over most of a project’s duration and are the source of many project management challenges (Ford and Sterman 2003). Whether rework arrives unanticipated, or it is expected and estimated, or it is suddenly generated by external factors, it causes severe challenges for project managers. When rework is caused by unanticipated errors, project managers find that their project estimates have not accounted for or budgeted for this rework. Even when the fraction of rework is estimated and planned for on a project usually from past experiences with similar projects or statistical baselines from data collected on previous projects, the recursive compounding of rework is often underestimated. Furthermore, even with anticipated rates of rework, errors are seldom discovered immediately and there is usually a time delay between errors being generated and being detected either during testing or downstream at subsequent stages on a project. Finally, rework is very often triggered by external factors, like client changes in requirements. In this case, a project that was well on track earlier could easily be derailed due to the additional rework cycles created due to the externally generated changes. Project dynamics provides the concepts to better understand the cyclical nature of rework and the methodology to estimate more accurately the effort required due to 7|Page
  • 8. rework cycles. Current models of rework include quality assurance activities, parallel cycles to distinguish between whether rework was created by current or upstream phases and whether rework occurs due to correcting flawed work or is initiated to respond to externally generated changes. As an introductory example to the use of a common diagramming technique of project dynamics called causal loop diagramming, we present Figure 1: Project Rework Structure. The causal loop diagram below represents the cause and effect relationships on a project that interrelate to create dependencies and generate the rework cycles on projects. p r e s s u r e o n S s c h e d ule S e rr o r g e n e r a ti o n R 2 r at e S B w o rk r e m ainin g t o p e rc eiv e d w o rk b e d o n e c o m p l e ti o n r a t e O S w o rk c o m plet e d S S S w it h o u t e rr o r s w o r k c o m p l e t e d w it h u n dis c o v e r e d e rr o rs R 1 w o r k w it h e rr o r s dis c o v e r e d S Figure 1: Project Rework Structure The first feedback cycle is a balancing loop (labelled B) where a larger amount of work remaining to be done causes an increased work pressure on schedule which in turn causes the perceived work completion rate also to increase similarly leading to an increased amount of work completed without errors and this has an opposite effect, i.e. it decreases the work remaining to be done. 1 The second feedback cycle is a reinforcing loop (labelled R1) that shows that while the perceived work completion rate is increasing the work completed with undiscovered errors is also increasing similarly (‘s’ on the arrowhead) which after a time delay during which testing and quality assurance is carried out the amount of work with errors discovered increases. This leads to more work remaining to be done, i.e. rework. The additional work remaining to be done leads to further pressure on schedule which leads to more work being completed albeit with undiscovered errors creating this reinforcing cycle. The final reinforcing loop R2 indicates that when pressure on schedule increases, this leads to additional stress on the team and the error generation rate increases leading to an increase in the work completed with undiscovered errors. While the first balancing loop B represents the progress of work being done on a project without errors or rework, the reinforcing loops R1 and R2 represent the effects of rework being created and the effects of schedule pressure to increase errors (and therefore rework) on a project respectively. 1.4.3 Project Control Strategies The performance of a project is typically measured along the dimensions of schedule, cost, and quality for the scope to be delivered. Through the course of project, managers make decisions to control the performance gap between actual progress of 1 An ‘s’ near the arrowhead indicates that two factors mentioned at both ends of that arrow move in similar directions, while an ‘o’ indicates that the two factors move in opposite directions. 8|Page
  • 9. the project and the performance targets set for the dimensions above (Lyneis et. al 2001; Abdel-Hamid and Madnick 1991). However, as human beings, managers make decisions based on what they perceive and what information is available to them at that point in time. A unique aspect of project dynamics models is that they differentiate between perceived conditions and actual conditions on a project. The perceived conditions drive project control actions by managers and the actual conditions drive actual progress on projects. Project dynamics models that include aspects of information availability and human decision making help managers make better forecasts of project performance, and thereby make more informed project control actions. An example from our previous discussion on rework shows that managers generally include undiscovered rework in the work they perceive as completed as the errors are as yet undetected at that point in time. This often leads to overestimating progress and productivity at the early stages of a project. So while the actual progress made is less than it seems due to work completed containing undetected errors, future decisions and forecasts are made based on the amount of work that is incorrectly perceived to be completed. A causal loop diagram is shown in Figure 2 to represent common control actions by managers to address schedule slippage by increasing the labour resources on a project by using various interventions like increasing the work intensity, increasing overtime, and increasing the headcount on a project. p r oje c t s c h e d ule ti m e a v a il a b l e O S p r oje c t s c h e d ul e e s ti m a t e o f ti m e p r e s s u r e r e q u ir e d f o r c o m p l e ti o n S S B 2 B 3 w o rk r e m ai ni n g l a b o u r o v e rti m e S O S w o r k i n t e n s it y S la b o u r h e a d c o u nt S l a b o u r q u a n tit y r at e o f w o rk S c o m p l e ti o n S B 1 Figure 2: Project Labour Control Interventions The balancing loop B1 shows that when project schedule pressure increases on a project due to the gap between project schedule time available and the estimate of time required for completion, as an intervention option, managers increase pressure on the project team to increase work intensity which then over time increases the rate of work completion leading to less work remaining. This in turn leads to a lower estimate of time required for completion of work and less project schedule pressure. The second type of intervention, viz. increasing overtime, is shown by the balancing loop B2, where an increase in project schedule pressure leads to increasing labour overtime which increases the effective amount of labour quantity available for the project leading to an increasing rate of work completion, less work remaining, a lower estimate of time required for completion, and subsequently less project schedule pressure. The third intervention of increasing headcount by adding people is shown by the balancing loop B3 where an increase in project schedule pressure leads to an increase in labour headcount leading to an increased labour quantity available to work 9|Page
  • 10. on the project leading to more work being done and subsequently less schedule slippage. Figure 2 above illustrates how project control actions, like labour control actions, act through the system to control the performance gaps (in this case the schedule pressure that arises from a gap between estimate of time required for completion and project schedule time available). However, a variety of project control strategies can be modelled explicitly in models and the subsequent results can be seen. While the causal loop diagram above illustrates conceptually how control actions work, managers also need to know the size and speed of the adjustments they should make, an indication of the costs vs. benefits of each intervention and tools to assist them with designing superior strategies to control schedule slippage. For the design of intervention strategies, we will later discuss how project dynamics provides additional methodologies and tools to build simulation models of the project where such strategies can be designed and tested. 1.4.4 Cascading and Subsequent Effects From the common war stories of project managers, we’ve seen how frequently used project control actions like increasing overtime, adding people and increasing work pressures on a team can have counterintuitive and unintended consequences of exacerbating the very project conditions of schedule slippage that they seek to alleviate due to the feedback effects of increasing errors, increasing rework, experience dilution, communication overheads, fatigue, burnout and worker turnover. Project dynamics literature often calls these cascading and subsequent effects ripple effects and knock-on effects and helps managers understand how these effects are created and how to avoid and alleviate them. 1.4.5 Ripple Effects Ripple effects are the primary impacts of project control actions on rework and productivity and often include the dilution of experience levels, increased communication requirements, reduced productivity, lower quality and increased errors, and worker fatigue (Abdel-Hamid and Madnick 1991). We’ll use the same example of labour control interventions as in Figure 2 to illustrate how well meaning project control actions create these undesired effects. p r oj e c t s c h e d ule ti m e a v a il a b l e O S p r oje c t s c h e d ule e s ti m a t e o f ti m e p r e s s u r e r e q u ir e d f o r c o m pl e ti o n S c ommunic at ion S ov erheads w o rk r e m ai nin g l a b o u r o v e rti m e S S O w o r k i n t e n s it y l a b o u r h e a d c o u n t S S l a b o u r q u a n tit y r at e o f w o rk ex perienc e c o m p l e ti o n f at igue error generat ion produc t iv it y Figure 3: Cascading Ripple Effects of Project Labour Control Interventions 10 | P a g e
  • 11. Figure 3 contains the same project control interventions as Figure 2. However, the unintended consequences of experience dilution, communication overheads and fatigue on error generation rates and productivity are added in the bolder links. By increasing labour headcount, i.e. adding new people midway on a project that either have less experience or at a minimum unfamiliar with the project, the experience levels of the team decreases leading to lower overall productivity and often increased error generation rates. Also, increasing headcount increases communication overheads exponentially and this leads to similar effects on productivity and error generation rates. Increasing labour overtime can be a suitable short term strategy but eventually leads to fatigue which then leads to lower productivity and increased error generation rates. Increased work intensity leads to increases in error generation rates as well. These compounding increases in error generation rates increases the additional rework required to be done and lower productivity decreases the rate of work completion thereby defeating the very intent of managers behind the project control interventions. From Figure 3, it is easy to see how these ripple effects add to the dynamic complexities of the project and make such projects difficult to manage. 1.4.6 Knock-on Effects Project dynamics models further analyze the impacts of the above ripple effects as they in turn cause secondary and tertiary effects that include out-of-sequence work, error contamination, additional work and lower employee morale (Lyneis and Ford 2007) as shown in Figure 4. project schedule time available O S project schedule estimate of time pressure required for completion S communication S morale overheads labour overtime S S work remaining O work intensity S labour headcount S labour quantity rate of work experience fatigue completion error generation productivity Figure 4: Subsequent Knock-on Effects of Project Labour Control Interventions Figure 4 shows as an illustration one of these four subsequent knock-on effects of employee morale as affected by the impact of project control actions. As fatigue increases and the work remaining increases due to rework, employee morale begins to decrease leading to lower productivity and higher error generation rates. If low employee morale continues unchecked, it eventually results in employee turnover and lower experienced labour headcount on projects leading to further project problems. Other knock-on effects that are not shown in Figure 4 would include the impacts of using concurrency and overlapping activities on projects to reduce schedule slippage, knock-on effects of upstream errors causing errors downstream and tipping point effects where errors require more effort to fix than the original work required. If these causal loops were added to Figure 4, it is easy to see how the causal loop diagram, which is only a mapped representation of the project system, would be more complex and difficult to understand for managers. 11 | P a g e
  • 12. While human beings are adept at specifying individual relationships between parts of a system, the human mind is not suited to understanding how all these parts interact simultaneously to create system performance. This is precisely one of the most significant contributions of project dynamics models where several relationships can be modelled by eliciting the information gained from managers’ experience and resident in the mental models of the managers’ mind and then simulated using computers to understand and plan for project performance. The models are only represented as causal loop diagrams above for transparency but using the language of project dynamics, these causal loop diagrams are meant to be modelled mathematically using stocks and flows on a computer. Models so developed can then be simulated on a computer and experimentation with a wide variety of inputs and policies are possible. The actual simulations reveal the working of the system behaviourally, and the underlying structures of the model can be studied by managers to understand the structural determinants of project behaviour. The models and simulations can be used by managers for experimentation to aid understanding and also to design specific project architectures, policies and interventions. 1.5 Applications of Project Dynamics Project dynamics is growing in its usage both worldwide and in India and finds several applications in project management and allied activities on projects due to the depth of the investigation that is made possible because of these models. We discuss these applications here and, in the next section, we present directions for future work. 1.5.1 Estimation and Risk Assessment The experiences of project managers and project data suggest strongly that often adverse project dynamics is caused by underestimating scope or under-budgeting for the estimated scope of work. Project dynamics models are now being used in conjunction with more traditional estimation approaches at three stages during a project: (1) Upfront, to adjust traditional estimates based on known or expected deviations (risks) from typical projects; (2) during the project, to determine the degree of any project underestimation earlier than would typically occur; and (3) after the project, to assess what the project should have cost had other decisions been taken, including better initial estimates. Project dynamics has been used for risk assessment in two ways: (1) Post-project evaluations that determine the magnitude of changes that actually occurred on projects as a guide for what might occur on future projects; and (2) pre-project simulations that test the consequences of similar risks for the current project. 1.5.2 Project Control Even with improved estimation, risk assessment and planning, projects will rarely go exactly as planned. Project dynamics helps managers understand how they should best respond with their project control actions when problems occur. As seen from our discussion above on labour project control strategies, project dynamics provides key lessons and insights for managers in areas like managing the rework and minimizing the ripple and knock-on effects of the project control interventions. 1.5.3 Risk Management Project dynamics models have helped managers develop insights by focusing on risk management approaches instead of specific policies, e.g. models have been used to 12 | P a g e
  • 13. operationalise real options theory in projects for risk management. Project managers simultaneously seek project structures and policies that maximize project performance yet perform well when faced with a range of uncertainties that reflect risks. Project dynamics models show that managers who tailor polices for specific project assumptions can outperform those that manage for a wide range of conditions, if those project assumptions materialize. But if conditions deviate from those assumed by management, tailored policies generate much worse performance. Through simulation across various scenarios, these models help identify and address this fundamental trade-off between project robustness, i.e. the ability to perform well across a range of uncertain conditions, and performance under known specific conditions. 1.5.4 Project Evaluations and Dispute Resolution Project dynamics models are often used for post-project assessment of projects to understand how and why the project deviated from the original plan. Most of these models are applied in situations involving disputes between the owner/financer of the project and the contractor/executer of the project. In many cases, such disputes involve claims of “delay and disruption” or in the project dynamics terminology, ripple and knock-on effects that result from problems on projects. These models are then used to quantify and explain the impact of deviations of the project on its final cost. The model can be set up to represent the project as it actually occurred, including the direct impacts, and calibrated to the actual performance of the project. It can also apportion costs to the client, to other parties, and to the contractor through simulations that involve removing different groups of direct impacts. 1.5.5 Change Management When customers make changes to projects, the original plan almost always becomes infeasible. Change management entails pricing and mitigating proposed changes as they occur on an ongoing project (rather than waiting for disputes to occur after the project ends). Companies have used project dynamics models to assess optimal schedule extensions when changes are introduced on a project, examine the consequences of attempting to compress a project’s schedule, at the request of the client, and to forecast and mitigate change impacts, including quantifying the changes’ effects, diagnosing the causes, and planning and testing mitigating actions to reduce project costs 1.5.6 Individual and Organisational Learning The ability of project dynamics models to clearly and richly explain how project structures and behaviour interact makes them effective for teaching project management. A number of the project models have been converted into gaming simulators for use in management training. After such a simulation, the reasons for simulated project performance are analyzed, usually with causal loop diagrams such as those developed above, and the diagnostic output from the models is used to understand the dynamic complexity of projects that the many causal relations create and to appreciate the challenges of project management. 1.6 Insights and Directions for Future Work From the body of knowledge that is emerging from the various applications where project dynamics models are being built, managers are seeing several insights emerge from both the models as well as possibilities to incorporate the project 13 | P a g e
  • 14. dynamics approach into routine project management activities. These insights include a new awareness that project plans themselves sow the seeds for project success or failure even prior to execution, trying to achieve an overly aggressive plan often actually makes the performance of the project worse, recognising the existence of undiscovered rework and finding new ways to avoid its consequences, increasing early quality assurance even at lower initial productivity is generally beneficial to project outcomes, and prioritizing rework detection and correction over starting new work helps avoid downstream problems even though projects then seem to progress slower initially. Where managers have used these models, they have learned that even if recognised and designed well, the project control actions (like those discussed above) are often difficult to implement because implementation initiates worse-before-better project behaviour. By effectively demonstrating any worse-before-better dynamics and the eventual benefits of implementation, a formal model can give managers the courage to stay the course with the execution of innovative and counterintuitive project plans (Graham et al, 2002). While managers find the use of the project dynamics approach valuable when implemented, they sometimes find it difficult to initiate use of the approach for the first time with their project teams. One of the primary limitations in the practical and extensive use of project dynamics modelling is that many of the tools (which are usually computer-based) are often found by managers to be both complicated to understand and difficult to use in practice. So there is a need to be able to simplify and translate from this field of study to create practical and easily usable frameworks, and develop insights and ‘lessons learned’ to assist managers on their daily managerial decisions. Furthermore, managers see the need to integrate the project dynamics approach within the more familiar and traditionally accepted approaches and frameworks for project management like, for example, work breakdown structures, critical path modelling, and component cost estimating. Therefore, as directions for future work, we propose that the theory of project management would be enhanced by integrating research from the two different areas of traditional project management and project dynamics and that the practice of project management could be better informed by developing a model that can be used for experimentation and to develop insights that can aid managers’ decisions during actual project situations. In the next section, we outline the agenda and initial findings of a new study that proposes to meet these two objectives by integrating project dynamics insights within the PMI project management framework. 1.7 Project Dynamics Integration Study To meet the two needs of developing a better understanding of the dynamic complexities on projects and augmenting the decision making ability of managers in practice, the utility of the study proposed is three-fold: (a) To improve the understanding of project management by incorporating insights from project dynamics within the commonly used PMI project management frameworks, (b) to build a model that can be used for experimentation and development of strategic decision making insights that will help managers improve performance on projects, and (c) to obtain experiential industry feedback and contextual support for the model and its findings through field studies with project managers. The initial findings of this project dynamics integration study can be grouped under three areas: 14 | P a g e
  • 15. 1.7.1 Improved Understanding of Project Dynamics The insights from project dynamics, and their relevance to the practice of project management, are enhanced by integrating the findings of research from project dynamics into the body of knowledge that is used by project management practitioners. By relating the varied project processes, resources, decisions, scope and performance targets into a single model, this study has begun the groundwork to present a new tool for project managers to investigate the dynamics of projects. 1.7.2 Development of Model for Decision Making To cross the bridge from research to practice, this study will provide utility to the practice of project management by developing a model for experimentation that is intended to help managers make better project control and management decisions. The model presented in this study represents several detailed hypotheses (like tradeoffs of cost vs. schedule, impact of rework, and the like) and assumptions about policies and decision making – these can be validated or alternative policies can be defined and experimented with using the model developed in this study. The model is expected to have significant utility for field managers as through the use of and experimentation with the model, managers will enrich their mental models by giving them insights into the systemic causes of success and failure on projects (Senge, 1990). 1.7.3 Contextual Feedback Project management is required in a variety of classes of projects, like construction, software, new product development, and the like; however, the empirical portion of this study has focused on one industry, viz., the construction industry and aims to enumerate the contextual and situational factors that determine the utility of the model and its findings for project managers in this industry. The findings of this study will be used to obtain contextual feedback from project managers on construction projects, and by doing so, enhance the applicability of the lessons learned within the context of the construction industry. The model so developed will eventually be converted into a management simulator and provided to all participants of the study to benefit from the opportunity to experiment with and develop their own insights from the model developed. 1.8 Conclusions Project dynamics represents an exciting approach to transform the way project managers think about their projects, transform their ability to direct and control projects, and transform the levels of eventual project performance. The applications of project dynamics models are increasing as is evidenced from the fact that models are increasingly being built and used by companies for a variety of purposes from defining project strategy to estimation to post-mortem evaluations to dispute resolution. The usage of the project dynamics approach by managers can be enhanced by integration of the project dynamics approach within the widely accepted PMI frameworks and the PMBOK. The study to integrate these approaches and frameworks is currently underway and promises to help both academicians and managers better understand the emerging insights and opportunities for the future of project management theory and practice. 15 | P a g e
  • 16. 1.9 References 1. Abdel-Hamid TK, Madnick SE. 1991. Software Project Dynamics: An Integrated Approach. Prentice-Hall: Englewood Cliffs, NJ. 2. Choudhari, M. D. 2007. The Dynamics of Competitive Strategy. SM Thesis, Massachusetts Institute of Technology, February 1997. 3. Forrester JW. 1961. Industrial Dynamics. MIT Press: Cambridge, MA. 4. Forrester JW. 1968. Principles of Systems. MIT Press: Cambridge, MA. 5. Ford, D.N. The Dynamics of Project Management: An Investigation of the Impacts of Project Process and Coordination on Performance. Ph.D. Dissertation, Massachusetts Institute of Technology, August 1995. 6. Ford, D.N and Sterman, J.D. 2003. “The liar’s club: impacts of concealment in concurrent development projects.” Concurrent Engineering Research and Applications 111(3): 211–219. 7. Ford, D.N and Sterman, J.D. 1998. “Modeling Dynamic Development Processes.” System Dynamics Review. 14(1): 31-68. 8. Graham AK, Moore J, Choi CY. 2002. “How robust are conclusions from a complex calibrated model, really? A project management model benchmark using fit constrained Monte Carlo analysis.” Proceedings of the 2002 International System Dynamics Conference: Palermo, Italy. 9. Joglekar N, Ford DN. 2005. “Product development resource allocation with foresight.” European Journal of Operational Research 160(1): 72–87. 10. Lyneis, James M, and David N Ford. "System Dynamics Applied to Project Management: A Survey, Assessment and Directions for Future Research." System Dynamics Review 23, no. 2/3 (Summer/Fall 2007): 157-189. 11. Lyneis, James M., Cooper, Kenneth G., and Els, Sharon A., 2001. “Strategic Management of Complex Projects: A Case Study Using System Dynamics.” System Dynamics Review 17(3), 237–260. 12. McKinsey & Company, Financial Services Practice. 2008. Building India: Financing and Investing in Infrastructure. 9-13. 13. Project Management Institute (PMI), 2008. A Guide to the Project Management Body of Knowledge, PMBOK Guide - Fourth Edition. 14. Senge P. 1990. The Fifth Discipline, the Art and Practice of the Learning Organization. Doubleday/Currency: New York. 15. Sterman, John. 1992. System Dynamics Modelling for Project Management, pp 12. 16 | P a g e
  • 17. 1.10 Author’s Profile Mark D. Choudhari is a Director and Chief Strategy Officer at the Lotus Group. He has 16 years of global business experience and has worked with clients in North America, Europe, and the Asia-Pacific region. Mark has assisted companies in multiple industries and government and advises senior management in the areas of strategy, market and competitive dynamics, private equity, product development, performance improvement, change management and technology assimilation. Prior to the Lotus Group, Mark was co-founder and director at the Machintel Corporation, USA and Nathan Ark Software (P) Ltd. in India, was an expert consultant in system dynamics at the Arthur Andersen Business Consulting group, Chicago, and has led a research group at the MIT Sloan School of Management. He has several publications in strategy and finance and is a regular speaker at conferences. He is an active participant in community service and has established trusts in the USA and India for education. Mark holds undergraduate and graduate degrees in engineering, computer science and economics from the Massachusetts Institute of Technology. E-mail: mark@lotusprojects.com 17 | P a g e