Process Design and Facility Layout
Chapter 6
Process Design
and
Facility Layout
6-2
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Process Selection and System Design
Forecasting
Product and
service design
Capacity
planning
Facilities and
Equipment
Layout
Work
design
Process
selection
Technological
change
6-3
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Introduction
• Outsourcing, trend, reasons
• Make or Buy?
– Available capacity
– Expertise
– Quality Consideration
– The nature of demand
– Cost
6-4
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
• Variety
– How much
• Flexibility
– What degree
• Volume
– Expected output
• The key trade-off
Process Selection
6-5
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Process Types
• Projects
• Job Shops
• Batch Processing
• Repetitive/Assembly
• Continuous Processing
6-6
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Figure 3.6
Product-Process Matrix for Processes
(1) (2) (3) (4) (5)
One of a kind Low volume, Multiple Few major High volume
products, made low products products, high
to customer standardization moderate higher standardization,
order volume volume commodity
products
Process
Characteristics
(1)
Complex and
highly customized
process, unique
sequence of tasks
(2)
Jumbled flows,
complex work with
many exceptions
(3)
Disconnected line
flows, moderately
complex work
(4)
Connected line,
routine work
(5)
Continuous
flows, highly
repetitive work
LessComplexity,LessDivergence,MoreLineFlows
Less Customization and Higher Volume
Product Design
Continuous
process
Project
process
Line
process
Batch
process
Job
process
6-7
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Product-Process Matrix
Flexibility-Quality Dependability-Cost
Continuous
Flow
Assembly
Line
Batch
Job
Shop
Low
Volume
One of a
Kind
Multiple
Products,
Low
Volume
Few
Major
Products,
Higher
Volume
High
Volume,
High
Standard-
ization
Commercial
Printer
Heavy
Equipment
Automobile
Assembly
Sugar
Refinery
Flexibility-
Quality
Dependability
Cost
6-8
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
• Automation: Machinery that has
sensing and control devices that
enables it to operate
Automation
6-9
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Automation
• Numerically controlled (NC) machines
• Robot
• Computer-aided design and
manufacturing systems (CAD/CAM)
• Flexible manufacturing systems
• Computer-integrated manufacturing
(CIM)
6-10
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
• Layout: the configuration of
departments, work centers, and
equipment, with particular emphasis
on movement of work (customers or
materials) through the system
Layout
6-11
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
• Requires substantial investments of
money and effort
• Involves long-term commitments
• Has significant impact on cost and
efficiency of short-term operations
Importance of Layout Decisions
6-12
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Basic Layout Types
• Product Layouts
• Process Layouts
• Fixed-Position
• Combination Layouts
6-13
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Basic Layout Types
• Product Layout
– Layout that uses standardized processing
operations to achieve smooth, rapid, high-
volume flow
– Group equipments according to the sequential
steps of operations of a specific product
• Process Layout
– Layout that can handle varied processing
requirements
– Group equipments according to their functions
6-14
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
A Flow Line for Production or Service
Flow Shop or Assembly Line Work Flow
Raw
materials
or customer
Finished
item
Station
2
Station
3
Station
4
Material
and/or
labor
Statio
n
1
Material
and/or
labor
Material
and/or
labor
Material
and/or
labor
6-15
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Process Layout
Process Layout - work travels
to dedicated process centers
Milling
Assembly
& Test
Grinding
Drilling Plating
6-16
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Functional Layout
Gear
cutting
Mill Drill
Lathes
Grind
Heat
treat
Assembly
111
333
222
444
222
111
444
111 333
1111 2222
222
3333
111
444
111
6-17
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Basic Layout Formats
• Group Technology Layout
• Cellular Layout
• Fixed Position Layout
– e.g. Shipbuilding
Part Family W Part Family X
Part Family Y Part Family Z
6-18
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Cellular Layouts
• Cellular Manufacturing
– Layout in which machines are grouped into
a cell that can process items that have
similar processing requirements
• Group Technology
– The grouping into part families of items with
similar design or manufacturing
characteristics
6-19
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
A U-Shaped Production Line
1 2 3 4
5
6
78910
In
Out
Workers
6-20
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Cellular Manufacturing Layout
-1111 -1111
222222222 - 2222
Assembly
3333333333 - 3333
44444444444444 - 4444
Lathe
Lathe
Mill
Mill
Mill
Mill
Drill
Drill
Drill
Heat
treat
Heat
treat
Heat
treat
Gear
cut
Gear
cut
Grind
Grind
6-21
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Design Product Layouts: Line Balancing
Line Balancing is the process of assigning
tasks to workstations in such a way that
the workstations have approximately
equal time requirements.
6-22
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Cycle Time
Cycle time is the maximum time
allowed at each workstation to
complete its set of tasks on a unit.
6-23
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Determine Maximum Output
Output capacity =
OT
CT
OT operating time per day
D = Desired output rate
CT = cycle time =
OT
D
6-24
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Determine the Minimum Number
of Workstations Required: Efficiency
N =
(D)( t)
OT
t = sum of task times
6-25
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Precedence Diagram
Precedence diagram: Tool used in line balancing
to display elemental tasks and sequence
requirements
A Simple Precedence
Diagrama b
c d e
0.1 min.
0.7 min.
1.0 min.
0.5 min. 0.2 min.
6-26
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Example 1: Assembly Line Balancing
• Arrange tasks shown in the previous
slide into workstations.
– Use a cycle time of 1.0 minute
– Assign tasks in order of the most number of
followers
6-27
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Solution to Example 1
Work-
Station
Time
Remaining Eligible
Assign
Task
Station
Idle Time
1 1.0
.9
.2
a
c
none
a
c
- .2
2 1.0
0
b
none
b
- 0
3 1.0
.5
.3
d
e
-
d
e
- .3
.5
6-28
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Calculate Percent Idle Time
Percent idle time =
Idle time per cycle
(N)(CT)
6-29
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Line Balancing Rules
• Assign tasks in order of most
following tasks.
• Assign tasks in order of greatest
positional weight.
– Positional weight is the sum of each
task’s time and the times of all
following tasks.
Some Heuristic (intuitive) Rules:
6-30
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Solution to Example 2
Station 1 Station 2 Station 3 Station 4
a b e
f
d
g h
c
6-31
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Parallel Workstations
1 min.2 min.1 min.1 min.
30/hr. 30/hr. 30/hr. 30/hr.
1 min.
1 min.
1 min.1 min.
60/hr.
30/hr. 30/hr.
60/hr.
1 min.
30/hr.
30/hr.
Bottleneck
Parallel Workstations

Weitere ähnliche Inhalte

Was ist angesagt?

location planning and analysis
location planning and analysislocation planning and analysis
location planning and analysisjanyne aguilar
 
Operations management notes
Operations management notesOperations management notes
Operations management notesSomashekar S.M
 
Chapter 6 Managing Quality.ppt
Chapter 6 Managing Quality.pptChapter 6 Managing Quality.ppt
Chapter 6 Managing Quality.pptssuser7d3776
 
operation management chapter 2
operation management chapter 2operation management chapter 2
operation management chapter 2jhoy1221
 
Chapter 8 Location Strategy.ppt
Chapter 8 Location Strategy.pptChapter 8 Location Strategy.ppt
Chapter 8 Location Strategy.pptssuser7d3776
 
Facility location and techniques
Facility location and techniquesFacility location and techniques
Facility location and techniquesPiyush Sharma
 
Methods Of plant Location
Methods Of plant LocationMethods Of plant Location
Methods Of plant LocationAyusmanSahu
 
Design of Goods and Services
Design of Goods and ServicesDesign of Goods and Services
Design of Goods and ServicesUly Jr Maniago
 
Methods of facility location selection
Methods of facility location selectionMethods of facility location selection
Methods of facility location selectionStudsPlanet.com
 
Classification and Purpose of Production and Operations Management
Classification and Purpose of Production and Operations ManagementClassification and Purpose of Production and Operations Management
Classification and Purpose of Production and Operations ManagementRaymund Sanchez
 
introduction to operation management
introduction to operation managementintroduction to operation management
introduction to operation managementMrs Azamine
 
05-Operations Management
05-Operations Management05-Operations Management
05-Operations ManagementWahyu Wijanarko
 
Ten strategic Operation Management Decision
Ten strategic Operation Management DecisionTen strategic Operation Management Decision
Ten strategic Operation Management DecisionSoe Lu Kyaw
 
Location Planning and Analysis
Location Planning and AnalysisLocation Planning and Analysis
Location Planning and AnalysisIza Marie
 

Was ist angesagt? (20)

location planning and analysis
location planning and analysislocation planning and analysis
location planning and analysis
 
Operations management notes
Operations management notesOperations management notes
Operations management notes
 
Chapter 6 Managing Quality.ppt
Chapter 6 Managing Quality.pptChapter 6 Managing Quality.ppt
Chapter 6 Managing Quality.ppt
 
Introduction To Operation Management
Introduction To Operation ManagementIntroduction To Operation Management
Introduction To Operation Management
 
operation management chapter 2
operation management chapter 2operation management chapter 2
operation management chapter 2
 
OPERATION STRATEGY
OPERATION STRATEGYOPERATION STRATEGY
OPERATION STRATEGY
 
Chapter 8 Location Strategy.ppt
Chapter 8 Location Strategy.pptChapter 8 Location Strategy.ppt
Chapter 8 Location Strategy.ppt
 
Operations Strategy
Operations StrategyOperations Strategy
Operations Strategy
 
David ppt exp_ch04
David ppt exp_ch04David ppt exp_ch04
David ppt exp_ch04
 
Operations Strategy Handbook
Operations Strategy HandbookOperations Strategy Handbook
Operations Strategy Handbook
 
Facility location and techniques
Facility location and techniquesFacility location and techniques
Facility location and techniques
 
Methods Of plant Location
Methods Of plant LocationMethods Of plant Location
Methods Of plant Location
 
Design of Goods and Services
Design of Goods and ServicesDesign of Goods and Services
Design of Goods and Services
 
Operations management
Operations managementOperations management
Operations management
 
Methods of facility location selection
Methods of facility location selectionMethods of facility location selection
Methods of facility location selection
 
Classification and Purpose of Production and Operations Management
Classification and Purpose of Production and Operations ManagementClassification and Purpose of Production and Operations Management
Classification and Purpose of Production and Operations Management
 
introduction to operation management
introduction to operation managementintroduction to operation management
introduction to operation management
 
05-Operations Management
05-Operations Management05-Operations Management
05-Operations Management
 
Ten strategic Operation Management Decision
Ten strategic Operation Management DecisionTen strategic Operation Management Decision
Ten strategic Operation Management Decision
 
Location Planning and Analysis
Location Planning and AnalysisLocation Planning and Analysis
Location Planning and Analysis
 

Andere mochten auch

Facility Layout in production management
Facility Layout in production managementFacility Layout in production management
Facility Layout in production managementJoshua Miranda
 
Process design layout
Process design layoutProcess design layout
Process design layoutAL Kindi
 
Production and Operations Management- Chapters 1-8
Production and Operations Management- Chapters 1-8Production and Operations Management- Chapters 1-8
Production and Operations Management- Chapters 1-8vc_santos
 
MRP Systems
MRP SystemsMRP Systems
MRP SystemsNsbmUcd
 
Process dsign and facility layout
Process dsign and facility layoutProcess dsign and facility layout
Process dsign and facility layoutNsbmUcd
 
Chapter 1 introduction to production management
Chapter 1  introduction to production managementChapter 1  introduction to production management
Chapter 1 introduction to production managementalpha flores
 
Managing production across supply chain
Managing production across supply chainManaging production across supply chain
Managing production across supply chainSushant Kumar Sinha
 
Production and Operations Management
Production and Operations ManagementProduction and Operations Management
Production and Operations ManagementRoyce G Chua
 
Aggregat planning stevenson
Aggregat planning stevensonAggregat planning stevenson
Aggregat planning stevensonPiyush Vanjani
 
International logistics & global scm
International logistics & global scmInternational logistics & global scm
International logistics & global scmVishal Kaushik
 
Pengenalan kepada autocad
Pengenalan kepada autocadPengenalan kepada autocad
Pengenalan kepada autocadmohdfadil112279
 
Solution to chapter 04: Reliability
Solution to chapter 04: Reliability Solution to chapter 04: Reliability
Solution to chapter 04: Reliability Sazedul Ekab
 
Facility Capacity & Layout Planning
Facility Capacity & Layout PlanningFacility Capacity & Layout Planning
Facility Capacity & Layout PlanningNishant Agrawal
 
Automated Material Handling System
Automated Material Handling SystemAutomated Material Handling System
Automated Material Handling SystemRakesh Raki
 
Industrial Engineering unit 5. Facility Design Notes by badebhau.
Industrial Engineering unit 5. Facility Design Notes by badebhau.Industrial Engineering unit 5. Facility Design Notes by badebhau.
Industrial Engineering unit 5. Facility Design Notes by badebhau.Er. Bade Bhausaheb
 
Bài 7: Luồng công việc – Workflow
Bài 7: Luồng công việc – WorkflowBài 7: Luồng công việc – Workflow
Bài 7: Luồng công việc – WorkflowMasterCode.vn
 
MRP, MPS, Bill of Material, Numericals
MRP, MPS, Bill of Material, NumericalsMRP, MPS, Bill of Material, Numericals
MRP, MPS, Bill of Material, NumericalsSana Fatima
 

Andere mochten auch (20)

Chap003 Forecasting
Chap003    ForecastingChap003    Forecasting
Chap003 Forecasting
 
Facility Layout in production management
Facility Layout in production managementFacility Layout in production management
Facility Layout in production management
 
Process design layout
Process design layoutProcess design layout
Process design layout
 
Production and Operations Management- Chapters 1-8
Production and Operations Management- Chapters 1-8Production and Operations Management- Chapters 1-8
Production and Operations Management- Chapters 1-8
 
MRP Systems
MRP SystemsMRP Systems
MRP Systems
 
Process dsign and facility layout
Process dsign and facility layoutProcess dsign and facility layout
Process dsign and facility layout
 
Chapter 1 introduction to production management
Chapter 1  introduction to production managementChapter 1  introduction to production management
Chapter 1 introduction to production management
 
Managing production across supply chain
Managing production across supply chainManaging production across supply chain
Managing production across supply chain
 
Production and Operations Management
Production and Operations ManagementProduction and Operations Management
Production and Operations Management
 
Aggregat planning stevenson
Aggregat planning stevensonAggregat planning stevenson
Aggregat planning stevenson
 
International logistics & global scm
International logistics & global scmInternational logistics & global scm
International logistics & global scm
 
Pengenalan kepada autocad
Pengenalan kepada autocadPengenalan kepada autocad
Pengenalan kepada autocad
 
Solution to chapter 04: Reliability
Solution to chapter 04: Reliability Solution to chapter 04: Reliability
Solution to chapter 04: Reliability
 
Facility Capacity & Layout Planning
Facility Capacity & Layout PlanningFacility Capacity & Layout Planning
Facility Capacity & Layout Planning
 
Automated Material Handling System
Automated Material Handling SystemAutomated Material Handling System
Automated Material Handling System
 
Industrial Engineering unit 5. Facility Design Notes by badebhau.
Industrial Engineering unit 5. Facility Design Notes by badebhau.Industrial Engineering unit 5. Facility Design Notes by badebhau.
Industrial Engineering unit 5. Facility Design Notes by badebhau.
 
Chain conveyor
Chain conveyorChain conveyor
Chain conveyor
 
Bài 7: Luồng công việc – Workflow
Bài 7: Luồng công việc – WorkflowBài 7: Luồng công việc – Workflow
Bài 7: Luồng công việc – Workflow
 
Reverse Logistics
Reverse LogisticsReverse Logistics
Reverse Logistics
 
MRP, MPS, Bill of Material, Numericals
MRP, MPS, Bill of Material, NumericalsMRP, MPS, Bill of Material, Numericals
MRP, MPS, Bill of Material, Numericals
 

Ähnlich wie S ch6

OPERATIONS MANAGEMENT FOR COMPETITIVE ADVANTAGE
OPERATIONS MANAGEMENT FOR COMPETITIVE ADVANTAGEOPERATIONS MANAGEMENT FOR COMPETITIVE ADVANTAGE
OPERATIONS MANAGEMENT FOR COMPETITIVE ADVANTAGEyosefhadiwibowo
 
Karl Zemlin resume 2017
Karl Zemlin resume 2017Karl Zemlin resume 2017
Karl Zemlin resume 2017Karl Zemlin
 
Craig Smith resume
Craig Smith resumeCraig Smith resume
Craig Smith resumeCraig Smith
 
Airtronics Metal Products Overview - Precision Sheet Metal Manufacturer/Desig...
Airtronics Metal Products Overview - Precision Sheet Metal Manufacturer/Desig...Airtronics Metal Products Overview - Precision Sheet Metal Manufacturer/Desig...
Airtronics Metal Products Overview - Precision Sheet Metal Manufacturer/Desig...guest1f814
 
Krontime overview may2013_en-ali_accio10
Krontime overview may2013_en-ali_accio10Krontime overview may2013_en-ali_accio10
Krontime overview may2013_en-ali_accio10Gokcin
 
A&M Tool-2016-Capabilities
A&M Tool-2016-CapabilitiesA&M Tool-2016-Capabilities
A&M Tool-2016-CapabilitiesAndrew Rogier
 
system analysis and design Chap009
 system analysis and design  Chap009 system analysis and design  Chap009
system analysis and design Chap009Nderitu Muriithi
 
Rick Hatlen Resume Oct 2016 A
Rick Hatlen Resume Oct 2016 ARick Hatlen Resume Oct 2016 A
Rick Hatlen Resume Oct 2016 ARick Hatlen
 
Prince Industries Inc
Prince Industries IncPrince Industries Inc
Prince Industries IncRick
 
Collaborative Discrete Automation Systems Define the Factory of the Future
Collaborative Discrete Automation Systems Define the Factory of the FutureCollaborative Discrete Automation Systems Define the Factory of the Future
Collaborative Discrete Automation Systems Define the Factory of the FutureARC Advisory Group
 

Ähnlich wie S ch6 (20)

OPERATIONS MANAGEMENT FOR COMPETITIVE ADVANTAGE
OPERATIONS MANAGEMENT FOR COMPETITIVE ADVANTAGEOPERATIONS MANAGEMENT FOR COMPETITIVE ADVANTAGE
OPERATIONS MANAGEMENT FOR COMPETITIVE ADVANTAGE
 
Precinmac
PrecinmacPrecinmac
Precinmac
 
chap012.ppt
chap012.pptchap012.ppt
chap012.ppt
 
Karl Zemlin resume 2017
Karl Zemlin resume 2017Karl Zemlin resume 2017
Karl Zemlin resume 2017
 
Craig Smith resume
Craig Smith resumeCraig Smith resume
Craig Smith resume
 
Airtronics Metal Products Overview - Precision Sheet Metal Manufacturer/Desig...
Airtronics Metal Products Overview - Precision Sheet Metal Manufacturer/Desig...Airtronics Metal Products Overview - Precision Sheet Metal Manufacturer/Desig...
Airtronics Metal Products Overview - Precision Sheet Metal Manufacturer/Desig...
 
Krontime overview may2013_en-ali_accio10
Krontime overview may2013_en-ali_accio10Krontime overview may2013_en-ali_accio10
Krontime overview may2013_en-ali_accio10
 
jim. resume2015
jim. resume2015jim. resume2015
jim. resume2015
 
A&M Tool-2016-Capabilities
A&M Tool-2016-CapabilitiesA&M Tool-2016-Capabilities
A&M Tool-2016-Capabilities
 
system analysis and design Chap009
 system analysis and design  Chap009 system analysis and design  Chap009
system analysis and design Chap009
 
Process development
Process developmentProcess development
Process development
 
IS-Machinist2
IS-Machinist2IS-Machinist2
IS-Machinist2
 
SMT Sales 2011
SMT Sales 2011SMT Sales 2011
SMT Sales 2011
 
SMT 2011
SMT 2011SMT 2011
SMT 2011
 
SMT 2011
SMT  2011SMT  2011
SMT 2011
 
Rick Hatlen Resume Oct 2016 A
Rick Hatlen Resume Oct 2016 ARick Hatlen Resume Oct 2016 A
Rick Hatlen Resume Oct 2016 A
 
Chap006 (1) (1).ppt
Chap006 (1) (1).pptChap006 (1) (1).ppt
Chap006 (1) (1).ppt
 
Prince Industries Inc
Prince Industries IncPrince Industries Inc
Prince Industries Inc
 
CAD CAM CAE
CAD CAM CAECAD CAM CAE
CAD CAM CAE
 
Collaborative Discrete Automation Systems Define the Factory of the Future
Collaborative Discrete Automation Systems Define the Factory of the FutureCollaborative Discrete Automation Systems Define the Factory of the Future
Collaborative Discrete Automation Systems Define the Factory of the Future
 

Kürzlich hochgeladen

VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurSuhani Kapoor
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
Unlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfUnlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfOnline Income Engine
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetDenis Gagné
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaShree Krishna Exports
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 DelhiCall Girls in Delhi
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in managementchhavia330
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...Any kyc Account
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth MarketingShawn Pang
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsApsara Of India
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 

Kürzlich hochgeladen (20)

VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
Unlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfUnlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdf
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in India
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in management
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 

S ch6

  • 1. 6-1 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Chapter 6 Process Design and Facility Layout
  • 2. 6-2 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Process Selection and System Design Forecasting Product and service design Capacity planning Facilities and Equipment Layout Work design Process selection Technological change
  • 3. 6-3 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Introduction • Outsourcing, trend, reasons • Make or Buy? – Available capacity – Expertise – Quality Consideration – The nature of demand – Cost
  • 4. 6-4 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout • Variety – How much • Flexibility – What degree • Volume – Expected output • The key trade-off Process Selection
  • 5. 6-5 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Process Types • Projects • Job Shops • Batch Processing • Repetitive/Assembly • Continuous Processing
  • 6. 6-6 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Figure 3.6 Product-Process Matrix for Processes (1) (2) (3) (4) (5) One of a kind Low volume, Multiple Few major High volume products, made low products products, high to customer standardization moderate higher standardization, order volume volume commodity products Process Characteristics (1) Complex and highly customized process, unique sequence of tasks (2) Jumbled flows, complex work with many exceptions (3) Disconnected line flows, moderately complex work (4) Connected line, routine work (5) Continuous flows, highly repetitive work LessComplexity,LessDivergence,MoreLineFlows Less Customization and Higher Volume Product Design Continuous process Project process Line process Batch process Job process
  • 7. 6-7 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Product-Process Matrix Flexibility-Quality Dependability-Cost Continuous Flow Assembly Line Batch Job Shop Low Volume One of a Kind Multiple Products, Low Volume Few Major Products, Higher Volume High Volume, High Standard- ization Commercial Printer Heavy Equipment Automobile Assembly Sugar Refinery Flexibility- Quality Dependability Cost
  • 8. 6-8 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout • Automation: Machinery that has sensing and control devices that enables it to operate Automation
  • 9. 6-9 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Automation • Numerically controlled (NC) machines • Robot • Computer-aided design and manufacturing systems (CAD/CAM) • Flexible manufacturing systems • Computer-integrated manufacturing (CIM)
  • 10. 6-10 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout • Layout: the configuration of departments, work centers, and equipment, with particular emphasis on movement of work (customers or materials) through the system Layout
  • 11. 6-11 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout • Requires substantial investments of money and effort • Involves long-term commitments • Has significant impact on cost and efficiency of short-term operations Importance of Layout Decisions
  • 12. 6-12 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Basic Layout Types • Product Layouts • Process Layouts • Fixed-Position • Combination Layouts
  • 13. 6-13 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Basic Layout Types • Product Layout – Layout that uses standardized processing operations to achieve smooth, rapid, high- volume flow – Group equipments according to the sequential steps of operations of a specific product • Process Layout – Layout that can handle varied processing requirements – Group equipments according to their functions
  • 14. 6-14 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout A Flow Line for Production or Service Flow Shop or Assembly Line Work Flow Raw materials or customer Finished item Station 2 Station 3 Station 4 Material and/or labor Statio n 1 Material and/or labor Material and/or labor Material and/or labor
  • 15. 6-15 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Process Layout Process Layout - work travels to dedicated process centers Milling Assembly & Test Grinding Drilling Plating
  • 16. 6-16 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Functional Layout Gear cutting Mill Drill Lathes Grind Heat treat Assembly 111 333 222 444 222 111 444 111 333 1111 2222 222 3333 111 444 111
  • 17. 6-17 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Basic Layout Formats • Group Technology Layout • Cellular Layout • Fixed Position Layout – e.g. Shipbuilding Part Family W Part Family X Part Family Y Part Family Z
  • 18. 6-18 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Cellular Layouts • Cellular Manufacturing – Layout in which machines are grouped into a cell that can process items that have similar processing requirements • Group Technology – The grouping into part families of items with similar design or manufacturing characteristics
  • 19. 6-19 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout A U-Shaped Production Line 1 2 3 4 5 6 78910 In Out Workers
  • 20. 6-20 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Cellular Manufacturing Layout -1111 -1111 222222222 - 2222 Assembly 3333333333 - 3333 44444444444444 - 4444 Lathe Lathe Mill Mill Mill Mill Drill Drill Drill Heat treat Heat treat Heat treat Gear cut Gear cut Grind Grind
  • 21. 6-21 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Design Product Layouts: Line Balancing Line Balancing is the process of assigning tasks to workstations in such a way that the workstations have approximately equal time requirements.
  • 22. 6-22 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Cycle Time Cycle time is the maximum time allowed at each workstation to complete its set of tasks on a unit.
  • 23. 6-23 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Determine Maximum Output Output capacity = OT CT OT operating time per day D = Desired output rate CT = cycle time = OT D
  • 24. 6-24 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Determine the Minimum Number of Workstations Required: Efficiency N = (D)( t) OT t = sum of task times
  • 25. 6-25 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Precedence Diagram Precedence diagram: Tool used in line balancing to display elemental tasks and sequence requirements A Simple Precedence Diagrama b c d e 0.1 min. 0.7 min. 1.0 min. 0.5 min. 0.2 min.
  • 26. 6-26 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Example 1: Assembly Line Balancing • Arrange tasks shown in the previous slide into workstations. – Use a cycle time of 1.0 minute – Assign tasks in order of the most number of followers
  • 27. 6-27 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Solution to Example 1 Work- Station Time Remaining Eligible Assign Task Station Idle Time 1 1.0 .9 .2 a c none a c - .2 2 1.0 0 b none b - 0 3 1.0 .5 .3 d e - d e - .3 .5
  • 28. 6-28 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Calculate Percent Idle Time Percent idle time = Idle time per cycle (N)(CT)
  • 29. 6-29 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Line Balancing Rules • Assign tasks in order of most following tasks. • Assign tasks in order of greatest positional weight. – Positional weight is the sum of each task’s time and the times of all following tasks. Some Heuristic (intuitive) Rules:
  • 30. 6-30 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Solution to Example 2 Station 1 Station 2 Station 3 Station 4 a b e f d g h c
  • 31. 6-31 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Parallel Workstations 1 min.2 min.1 min.1 min. 30/hr. 30/hr. 30/hr. 30/hr. 1 min. 1 min. 1 min.1 min. 60/hr. 30/hr. 30/hr. 60/hr. 1 min. 30/hr. 30/hr. Bottleneck Parallel Workstations