KGHM Polska Miedz:
Sierra Gorda Project
www.quadrafnx.com
Strength in numbers
As the Sierra Gorda Project enters an exciting new phase of its life, Senior Vice President of the project, Joseph Tis
reflects on how the collective efforts and achievements of its workforce made 2013 such an important year
words by Will Daynes research by Abi Abagun
KGHM Polska Miedz - Sierra Gorda Project
Strength in numbers
s Joseph Tis, Senior Vice President,
explains, 2013 was an important year
for the Sierra Gorda open pit copper
mine project. “In February of last year the
project budget, valued at $4,000 million was
updated. In the months that followed the
project went on to complete a consolidated
advance of 52.9 percent, reaching 91.2
percent in February 2014.”
Located within Northern Chile’s Atacama
Desert, the Sierra Gorda Project is a joint
venture between KGHM International Ltd.,
Sumitomo Metal Mining and Sumitomo
Corporation, and possesses deposits that
total up to 2.2 billion tonnes of measured
and indicated resources, and reserves
amounting to some 1.3 billion tonnes.
In addition to completing detailed
A
Secondary
crusher & HPGR
KGHM Polska Miedź - Sierra Gorda Project
“We have made a number
of great advances in the
construction plant over the
last year or more”
engineering and locking down the purchasing
of equipment, 2013 also saw Sierra Gorda
benefit from the completion of infrastructure
works designed to supply the site with
electricity and water. Both 110Kv and 220kV
electricity lines are now positioned on site,
with the 110kV line going live during March
of this year and the 220kV being brought
into action the following month. In addition
Scancontrols, control valve specialists, provides
and advise our clients in Chile, on all matters
relating to valves and fluid control.
This, seen as the core of our development, has
made us leaders in the industry, thanks to our fast
response, performance and reliability.
Founded in 2001 with the aim of providing the
market with the best solutions for handling fluids via
control valves, including engineering for selecting
the type and size of valve, actuators and materials
for each case.
Our company has a full line of control valves and on
/ off valves, as well as manual valves for all types
of processes. Also we offer diagnostic, maintenance
and repair services of the valves in the city of
Antofagasta. This service has allowed Scancontrols
to make a difference and obtain a good position in
the local market as one of the few companies able to
offer integral solutions for fluid handling with valves.
Scancontrols represents in Chile top brands such
as SOMAS (Sweden), RF VALVES (USA) and Ringo
Válvulas (Spain), which added to our Help Desk,
Maintenance and Repair Team, leads to excellence
and guaranteed results.
Our services cover all industries including Mining,
Pulp & Paper, Refineries, Petrochemicals, Power
Plants, and others.
“With a sustained growth in over 10 years of
existence, Scancontrols is in a very strong position
to continue expanding the services and products to
new projects and markets”
www.scancontrols.cl
Scancontrols, control valve specialists, provides
and advise our clients in Chile, on all matters
relating to valves and fluid control.
This, seen as the core of our development, has
made us leaders in the industry, thanks to our
fast response, performance and reliability.
Founded in 2001 with the aim of providing the
market with the best solutions for handling
fluids via control valves, including engineering
for selecting the type and size of valve,
actuators and materials for each case.
Our company has a full line of control valves
and on / off valves, as well as manual valves for
all types of processes. Also we offer diagnostic,
maintenance and repair services of the valves in
the city of Antofagasta. This service has allowed
Scancontrols to make a difference and obtain a
good position in the local market as one of the
few companies able to offer integral solutions
for fluid handling with valves.
Scancontrols represents in Chile top brands
such as SOMAS (Sweden), RF VALVES (USA)
and Ringo Válvulas (Spain), which added to our
Help Desk, Maintenance and Repair Team, leads
to excellence and guaranteed results.
Our services cover all industries including
Mining, Pulp & Paper, Refineries,
Petrochemicals, Power Plants, and others.
“With a sustained growth in over 10 years of
existence, Scancontrols is in a very strong
position to continue expanding the services and
products to new projects and markets”
www.scancontrols.cl
SCANCONTROLS
Sierra Gorda feature text
to go here......Lorem ipsum
dolor sit amet, consectetur
adipisicing elit, sed do
eiusmod tempor incididunt
ut labore et dolore magna
aliqua. Ut enim ad minim
veniam, quis nostrud
exercitation ullamco laboris
nisi ut aliquip ex ea commodo
consequat. Duis aute irure
dolor in reprehenderit in
voluptate velit esse cillum
dolore eu fugiat nulla pariatur. Excepteur
sint occaecat cupidatat non proident, sunt
in culpa qui officia deserunt mollit anim
id est laborum. feature text to go here......
Lorem ipsum dolor sit amet,
consectetur adipisicing elit,
sed do eiusmod tempor
incididunt ut labore et dolore
magna aliqua. Ut enim ad
minim veniam, quis nostrud
exercitation ullamco laboris
nisi ut aliquip ex ea commodo
consequat. Duis aute irure
dolor in reprehenderit in
voluptate velit esse cillum
doloreeufugiatnullapariatur.
Excepteur sint occaecat
cupidatat non proident, sunt in culpa qui
officia deserunt mollit anim id est laborum.
feature text to go here......Lorem ipsum dolor
sit amet, consectetur adipisicing elit, sed do
This is a caption this is a caption
With over 400 knife gate valves
in Sierra Gorda, Scancontrols with our
partner RF Valves keeps providing high
quality for the mining industry.
RF Valves for Heavy Duty operations, are
designed to control abrasive fluids, specially
for adverse conditions where common
valves are no good.
Scancontrols is also in other large mining
projects in Chile, continuing contributing
to the quality of the processes with our
represented brands.
Email: info@scancontrols.cl
www.scancontrols.cl
Weworkwiththe
BEST!
Conveyor
belts
to the completion of these power lines, the
assembly and welding of the project’s sea
water aqueduct has also been finished.
A particularly striking example of the
progress made at Sierra Gorda over the last
12-18 months comes in the form of the project’s
processing plant. “We have made a number
of great advances in the construction plant
over the last year or more,” Tis agrees, “going
from eight to twelve percentage points during
the months between August and December
2013 alone. Particular milestones achieved
during 2013 included the delivery of the
Truck Shop to operations, delivery of shovels
4 and 5, and the delivery of 17 haul trucks
for use in Prestripping extraction operations.
scancontrols
“Particular milestones
achieved during 2013
included the delivery of the
Truck Shop to operations”
KGHM Polska Miedź - Sierra Gorda Project
SCM Sierra Gorda has chosen Ingeniería de Transportes
Javier Cortés S.A. as his support for the transport of all their necessary supplies
for the construction and start up of the SIERRA GORDA project located in the
Antofagasta region.
No doubt this is a great recognition for Ingeniería de Transportes Javier Cortés
S.A. a company of a large and historical trajectory in the movement of oversize
and overweight transport in the Chilean mining.
The history of the company is certainly confusing with the growth of the
Chilean mining after it started as a transport company for general cargo it is
now specialized in the transport and operation of special cargo according to the
development of the Chilean mining beyond of the 70’s.
Ingeniería de Transportes Javier Cortés S.A., with more than 50 years in this
business,hasbeenstandouttotransportthemostheaviestanddifficultcargoes
in Chile, and that the transport on off-road trails to locations at 5,000 m.o.s.l.
hasn´t been an obstacle to his successful career.
For the construction of the Sierra Gorda project it was necessary to perform
more than 5.000 voyages with import cargoes and domestic supplies.
In order to address adequately this project, Ingeniería de Transportes Javier
Cortés S.A. increased its fleet of modular equipments and trucks in order to fully
meet the expectations of the client.
With the result of this project we are very optimistic to keep and strengthen
a long-term relationship with Sierra Gorda in order to participate in their
upcoming projects in Chile.
We take this opportunity to wish Sierra Gorda the best of success in the start up
of the mine.
Ingeniería de Transportes Javier Cortés S.A. is also actively involved in the
development of wind farm, photovoltaic, thermoelectric, hydroelectric,
cellulose, refineries and others projects as well in the consulting prior to project
implementation phases.
What makes that a certain company
has been selected as a support in
the development of a great mining
project in Chile?
www.javiercortes.com
KGHM Polska Miedź - Sierra Gorda Project
Furthermore, 2013 saw the installation of all
critical plant equipment.”
Tis is keen to add that all of the
achievements already mentioned have been
as a result of the tireless work of the project’s
workforce performed in the field. During
the month of October, 2013, employment
activity on site reached a peak of 9500
workers, while 2013 as a whole saw a total of
11,236,934 man hours earned.
“As of January 2014, we have calculated
that more than 44,000 people have directly
“As of January 2014, we have calculated that more than
44,000 people have directly contributed to the construction
of the project and its various elements”
contributed to the construction of the project
and its various elements,” Tis states. “Each
and every one of these people have at all times
remained committed to our “Zero Harm”
ethos, our most fundamental value which
enforces our commitment to the health and
safety of our employees and the communities
in which we operate, and in doing so have not
only met, but often exceeded expectations.”
As a company KGHM has long been proud
of the fact that it acts as a major contributor
towards employment generation, regardless
Sea water pond
Hatch supporting Sierra Gorda from the beginning
Sierra Gorda retained Hatch since mid 2012 to
develop the detail engineering of their Molybdenum
plant. The project has been a success from the
engineering and procurement stand point and is
currently well under way in construction. Hatch
has not only done detail engineering to the Sierra
Gorda Molybdenum plant but has supported Sierra
Gorda as a key client and continued helping Sierra
GordawiththeMolyplantFieldEngineeringServices,
Pre-Commissioning & Commissioning support
services for the entire Copper-Moly Concentrator,
procurement support services and has as well
reviewed the Basic Engineering of their concentrator
future expansion. For Hatch, Sierra Gorda has been
an excellent client, and one very good example of
client engagement and commitment of our core
values,allrequiredtocreateandenhancealongterm
relationship adding the best possible value to our
clients. The multidiscipline capabilities available at
Hatch and the global availability of our experts have
given us the strength to commit with Sierra Gorda in
one of the largest mining projects of the continent.
www.hatch.cl
Stock pile
of where it is based. This is very much the
case with the Sierra Gorda Project, what
with a great many of the 44,000 people
who have contributed to its development
coming from regions surrounding it. The
largest contributor to date has been the
VIII Biobío Region, from which the project
has employed some 9,557 people, or
21.6 percent of the 44,000. Other major
contributors have been the II Antofagasta
Region, the Santiago Metropolitan Region
XIII and the V Valparaíso Region, with 7,505,
7,085 and 6,306 residents employed on the
project respectively. On top of these figures,
no fewer than eleven other regions, from the
XV Region of Arica and Parinacota, through
to the XII Region of Magallanes have also
contributed employees to the project.
In addition to the creation of jobs, the
Sierra Gorda Project has also contributed in
hatch
“In addition to the creation of jobs, the Sierra Gorda
Project has also contributed in other vital ways to the
local and national economies of Chile”
KGHM Polska Miedź - Sierra Gorda Project
Valves – Automation – Instrumentation
• Control Valves
• Positioners
• Hydraulic / Electric Actuators
• Field Instrumentation
• Heat Exchangers
Technical Services:
Branch offices with highly
qualified workshops for the
maintenance and configuration
of equipment.
Field Services:
Visits projects to make
preventive check-ups to
avoid halts in the productive
processes.
Technical Consultancies:
Highly qualified professionals
who advise and guide the
purchase of equipment
and/or services.
Training:
Technical and usage
training orientated to
obtain better performance
of the equipment.
POST-SALES SERVICES:
QUALITY AT YOUR DISPOSAL
Instruvalve, dedicated to providing quality products and services to the Mining, Energy,
Oil & Gas, and general processes industries, provides its clients with world-class brands,
excellent after-sales service and a highly qualified team.
other vital ways to the local and national
economies of Chile. “The existence of this
project has not only helped strengthen
the local mining industry, but also will
contribute to the increased supply of copper
on a national and international scale,” Tis
says. “In doing so we have also played our
part in ensuring that the country remains a
leading global player when it comes to the
production of copper, and in showcasing
“The existence of this project has not only helped
strengthen the local mining industry, but also will
contribute to the increased supply of copper on
a national and international scale”
the professional quality and expertise of
workforce, taking a massive development
project from start to finish, we have helped
send out a message to investors that Chile
is a country worth taking notice of.”
Giving back to the community is a
trait that in many ways has characterised
the project since its inception. To this
day it arguable remains best reflected
in the development, construction and
“Instruvalve”, a Chilean Company with
ten years of experience when it comes to
the control of fluids and automation, supplied a
package of electric actuators from Limitorque
USA to the Sierra Gorda Mine project. The
Limitorque actuators are used to operate ball
and gate valves in the raw water sea pumping
stations of the mine’s plant. Instruvalve also
assisted in the implementation of the system.
Instruvalve is grateful and thankful for the
confidence shown by Sierra Gorda and is
proud of be a technological partner of the mine,
wishing it great success in its future operations.
In its portfolio of products, “Instruvalve”
also offer hydraulic/electric actuators, valve
positioners, field instrumentation and heat
exchangers.
Instruvalve Ltda
Quality at your disposal
(55) 2944 369
ventas@instruvalve.cl
www.instruvalve.cl
Primary
crusher
KGHM Polska Miedź - Sierra Gorda Project
implementation of numerous infrastructure
projects that have helped improve quality of
life within the region. Such projects include
the construction of a wastewater treatment
plant, the expansion of security checkpoints
and the installation of CCTV to provide a
safer environment, and the implementation
of programmes designed to protect native
flora and fauna.
While 2013 was certainly an important year
for the Sierra Gorda, 2014 could prove to be an
even greater milestone, what with production
at its processing plant due to commence
this year, thus ushering in a new phase for
the project. “In the short term our efforts
are very much focused on completing the
construction and pre-commissioning phases
of the processing plant, and subsequently
bringing it online, all the while fulfilling our
Zero Harm commitments” Tis concludes.
“Throughout the remainder of the year we
will be bringing several other projects online
and by December 2014 we expect to have
completed the ramping up of production to
bring it up to 110,000 tonnes per day.”
Process
plant
“In the short term our efforts are
very much focused on completing the
construction and pre-commissioning
phases of the processing plant”
Progress
on construction
(at 31 December 2013)
Project will be
completed on time,
planned completion of
construction and
commissioning
in mid-2014
Total project
progress is
86% complete
Construction of
sea water pipeline
94% complete,
final hydraulic testing
in progress
Construction of
tailings pond approx.
86% complete
and processing
plant approx.
80% complete
Pre-stripping at
81% of the amount
required before
commissioning
Around 96%
of the CAPEX
committed
Around
USD 3.4B of the
committed amount
has been incurred
Did you know?
KGHM Polska Miedź - Sierra Gorda Project
562-336-5200
	info@kghminternational.com
www.quadrafnx.com
KGHM Polska Miedź -
Sierra Gorda Project
Tailings
thickener
Produced by:
www.bus-ex.com
562-336-5200
	info@kghminternational.com
www.quadrafnx.com
KGHM Polska Miedz:
Sierra Gorda Project

Weitere ähnliche Inhalte

Andere mochten auch (8)

Prepa americas-oil&gas-apr14-bro-s
Prepa americas-oil&gas-apr14-bro-sPrepa americas-oil&gas-apr14-bro-s
Prepa americas-oil&gas-apr14-bro-s
 
Pemex americas-o&g-apr14-bro-s
Pemex americas-o&g-apr14-bro-sPemex americas-o&g-apr14-bro-s
Pemex americas-o&g-apr14-bro-s
 
Lmm americas-t&l-may14-bro-s
Lmm americas-t&l-may14-bro-sLmm americas-t&l-may14-bro-s
Lmm americas-t&l-may14-bro-s
 
Pyhäsalmi europe-mining-may14-bro-s
Pyhäsalmi europe-mining-may14-bro-sPyhäsalmi europe-mining-may14-bro-s
Pyhäsalmi europe-mining-may14-bro-s
 
Camanchaca americas-f&d-apr14-bro-s
Camanchaca americas-f&d-apr14-bro-sCamanchaca americas-f&d-apr14-bro-s
Camanchaca americas-f&d-apr14-bro-s
 
Lanka asia.manu-jan13-bro-s Researched Abi Abagun
Lanka asia.manu-jan13-bro-s Researched Abi AbagunLanka asia.manu-jan13-bro-s Researched Abi Abagun
Lanka asia.manu-jan13-bro-s Researched Abi Abagun
 
Tile Industry
Tile IndustryTile Industry
Tile Industry
 
Lanka Tiles PLC
Lanka Tiles PLCLanka Tiles PLC
Lanka Tiles PLC
 

Ähnlich wie Kghm.sierra gorda americas-mining-may14-bro-s-0

DAC Presentation - 150927
DAC Presentation - 150927DAC Presentation - 150927
DAC Presentation - 150927
Brian Davison
 
Insights 2016 - Interview at page 46 - M.Mata
Insights 2016 - Interview at page 46 - M.MataInsights 2016 - Interview at page 46 - M.Mata
Insights 2016 - Interview at page 46 - M.Mata
Marcelo Mata
 
IPI Company Profile
IPI Company ProfileIPI Company Profile
IPI Company Profile
Philip Diwan
 
ORA_6_2015_Final 34
ORA_6_2015_Final 34ORA_6_2015_Final 34
ORA_6_2015_Final 34
James Rowley
 
SRL_IN_July2015_ToEmail
SRL_IN_July2015_ToEmailSRL_IN_July2015_ToEmail
SRL_IN_July2015_ToEmail
Memuna Forna
 
GE&F Bus Profile Summary 6 2016
GE&F Bus Profile Summary  6   2016GE&F Bus Profile Summary  6   2016
GE&F Bus Profile Summary 6 2016
James Whitsitt
 
Company Profile - ETSS
Company Profile - ETSSCompany Profile - ETSS
Company Profile - ETSS
Mina Moussa
 
Service solahart pondok labu 087777888338
Service solahart pondok labu 087777888338Service solahart pondok labu 087777888338
Service solahart pondok labu 087777888338
hasian service
 

Ähnlich wie Kghm.sierra gorda americas-mining-may14-bro-s-0 (20)

TSC Group Holdings
TSC Group HoldingsTSC Group Holdings
TSC Group Holdings
 
DAC Presentation - 150927
DAC Presentation - 150927DAC Presentation - 150927
DAC Presentation - 150927
 
Mseals
MsealsMseals
Mseals
 
Insights 2016 - Interview at page 46 - M.Mata
Insights 2016 - Interview at page 46 - M.MataInsights 2016 - Interview at page 46 - M.Mata
Insights 2016 - Interview at page 46 - M.Mata
 
The Interview - Steve Gill - MIDSTREAM Business nov/dec 2016
The Interview - Steve Gill - MIDSTREAM Business nov/dec 2016The Interview - Steve Gill - MIDSTREAM Business nov/dec 2016
The Interview - Steve Gill - MIDSTREAM Business nov/dec 2016
 
F&g presentation general...
F&g presentation  general...F&g presentation  general...
F&g presentation general...
 
IPI Company Profile
IPI Company ProfileIPI Company Profile
IPI Company Profile
 
TSC featured in Energy Digital
TSC featured in Energy DigitalTSC featured in Energy Digital
TSC featured in Energy Digital
 
ORA_6_2015_Final 34
ORA_6_2015_Final 34ORA_6_2015_Final 34
ORA_6_2015_Final 34
 
SRL_IN_July2015_ToEmail
SRL_IN_July2015_ToEmailSRL_IN_July2015_ToEmail
SRL_IN_July2015_ToEmail
 
GE&F Bus Profile Summary 6 2016
GE&F Bus Profile Summary  6   2016GE&F Bus Profile Summary  6   2016
GE&F Bus Profile Summary 6 2016
 
SARL Algeoland
SARL AlgeolandSARL Algeoland
SARL Algeoland
 
Corporate Profile CorpGN
Corporate Profile CorpGNCorporate Profile CorpGN
Corporate Profile CorpGN
 
An introduction of Marquard & Bahls
An introduction of Marquard & Bahls An introduction of Marquard & Bahls
An introduction of Marquard & Bahls
 
index
indexindex
index
 
Minera elbrocal am-mining-nov13-bro-s
Minera elbrocal am-mining-nov13-bro-sMinera elbrocal am-mining-nov13-bro-s
Minera elbrocal am-mining-nov13-bro-s
 
Company Profile - ETSS
Company Profile - ETSSCompany Profile - ETSS
Company Profile - ETSS
 
Service solahart pondok labu 087777888338
Service solahart pondok labu 087777888338Service solahart pondok labu 087777888338
Service solahart pondok labu 087777888338
 
Service solahart pondok labu 081261101170 | Slideshare
Service solahart pondok labu 081261101170 | SlideshareService solahart pondok labu 081261101170 | Slideshare
Service solahart pondok labu 081261101170 | Slideshare
 
ERIKS Group 2013 corporate profile
ERIKS Group  2013 corporate profileERIKS Group  2013 corporate profile
ERIKS Group 2013 corporate profile
 

Mehr von Abi Abagun

Petromoc africa-o&g-feb14-bro-s (1)
Petromoc africa-o&g-feb14-bro-s (1)Petromoc africa-o&g-feb14-bro-s (1)
Petromoc africa-o&g-feb14-bro-s (1)
Abi Abagun
 
Alp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-sAlp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-s
Abi Abagun
 
Coresa am-manu-aug13-bro-s
Coresa am-manu-aug13-bro-sCoresa am-manu-aug13-bro-s
Coresa am-manu-aug13-bro-s
Abi Abagun
 
Llx am-t&l-july13-bro-s
Llx am-t&l-july13-bro-sLlx am-t&l-july13-bro-s
Llx am-t&l-july13-bro-s
Abi Abagun
 
Atico am-mining-may13-bro-s
Atico am-mining-may13-bro-sAtico am-mining-may13-bro-s
Atico am-mining-may13-bro-s
Abi Abagun
 
Minera am-mining-may13-bro-s
Minera am-mining-may13-bro-sMinera am-mining-may13-bro-s
Minera am-mining-may13-bro-s
Abi Abagun
 
Tarcon africa-const-may13-bro-s
Tarcon africa-const-may13-bro-sTarcon africa-const-may13-bro-s
Tarcon africa-const-may13-bro-s
Abi Abagun
 
Rda Zambia Africa&l-mar13-bro-s Researched by Abi Abagun
Rda Zambia Africa&l-mar13-bro-s Researched by Abi AbagunRda Zambia Africa&l-mar13-bro-s Researched by Abi Abagun
Rda Zambia Africa&l-mar13-bro-s Researched by Abi Abagun
Abi Abagun
 
Jindal africa africa.mining-mar13-bro-s
Jindal africa africa.mining-mar13-bro-sJindal africa africa.mining-mar13-bro-s
Jindal africa africa.mining-mar13-bro-s
Abi Abagun
 
Colombo dockyard may11_emea-bro-s_ Abi Abagun
Colombo dockyard may11_emea-bro-s_ Abi AbagunColombo dockyard may11_emea-bro-s_ Abi Abagun
Colombo dockyard may11_emea-bro-s_ Abi Abagun
Abi Abagun
 
Inmet mining emea-mar12-bro-s-0 Researched Abi Abagun
Inmet mining emea-mar12-bro-s-0 Researched Abi AbagunInmet mining emea-mar12-bro-s-0 Researched Abi Abagun
Inmet mining emea-mar12-bro-s-0 Researched Abi Abagun
Abi Abagun
 

Mehr von Abi Abagun (20)

Petromoc africa-o&g-feb14-bro-s (1)
Petromoc africa-o&g-feb14-bro-s (1)Petromoc africa-o&g-feb14-bro-s (1)
Petromoc africa-o&g-feb14-bro-s (1)
 
Petromoc africa-o&g-feb14-bro-s
Petromoc africa-o&g-feb14-bro-sPetromoc africa-o&g-feb14-bro-s
Petromoc africa-o&g-feb14-bro-s
 
Vale brazil americas.mining-feb13-bro-s
Vale brazil americas.mining-feb13-bro-sVale brazil americas.mining-feb13-bro-s
Vale brazil americas.mining-feb13-bro-s
 
Qatargas me-oil gas-july13-bro-s
Qatargas me-oil gas-july13-bro-sQatargas me-oil gas-july13-bro-s
Qatargas me-oil gas-july13-bro-s
 
Renélagos am-cont-sep13-bro-s
Renélagos am-cont-sep13-bro-sRenélagos am-cont-sep13-bro-s
Renélagos am-cont-sep13-bro-s
 
Alp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-sAlp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-s
 
Hyderabad apac-const-dec13-bro-s
Hyderabad apac-const-dec13-bro-sHyderabad apac-const-dec13-bro-s
Hyderabad apac-const-dec13-bro-s
 
Alp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-sAlp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-s
 
Alp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-sAlp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-s
 
Coresa am-manu-aug13-bro-s
Coresa am-manu-aug13-bro-sCoresa am-manu-aug13-bro-s
Coresa am-manu-aug13-bro-s
 
Llx am-t&l-july13-bro-s
Llx am-t&l-july13-bro-sLlx am-t&l-july13-bro-s
Llx am-t&l-july13-bro-s
 
Atico am-mining-may13-bro-s
Atico am-mining-may13-bro-sAtico am-mining-may13-bro-s
Atico am-mining-may13-bro-s
 
Minera am-mining-may13-bro-s
Minera am-mining-may13-bro-sMinera am-mining-may13-bro-s
Minera am-mining-may13-bro-s
 
Tarcon africa-const-may13-bro-s
Tarcon africa-const-may13-bro-sTarcon africa-const-may13-bro-s
Tarcon africa-const-may13-bro-s
 
Rda Zambia Africa&l-mar13-bro-s Researched by Abi Abagun
Rda Zambia Africa&l-mar13-bro-s Researched by Abi AbagunRda Zambia Africa&l-mar13-bro-s Researched by Abi Abagun
Rda Zambia Africa&l-mar13-bro-s Researched by Abi Abagun
 
Colakoglu euro.manu-mar13-bro-s Researched by Abi Abagun
Colakoglu euro.manu-mar13-bro-s Researched by Abi AbagunColakoglu euro.manu-mar13-bro-s Researched by Abi Abagun
Colakoglu euro.manu-mar13-bro-s Researched by Abi Abagun
 
Camipa am-bro-s
Camipa am-bro-sCamipa am-bro-s
Camipa am-bro-s
 
Jindal africa africa.mining-mar13-bro-s
Jindal africa africa.mining-mar13-bro-sJindal africa africa.mining-mar13-bro-s
Jindal africa africa.mining-mar13-bro-s
 
Colombo dockyard may11_emea-bro-s_ Abi Abagun
Colombo dockyard may11_emea-bro-s_ Abi AbagunColombo dockyard may11_emea-bro-s_ Abi Abagun
Colombo dockyard may11_emea-bro-s_ Abi Abagun
 
Inmet mining emea-mar12-bro-s-0 Researched Abi Abagun
Inmet mining emea-mar12-bro-s-0 Researched Abi AbagunInmet mining emea-mar12-bro-s-0 Researched Abi Abagun
Inmet mining emea-mar12-bro-s-0 Researched Abi Abagun
 

Kürzlich hochgeladen

Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
Nauman Safdar
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
daisycvs
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
daisycvs
 

Kürzlich hochgeladen (20)

How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
Pre Engineered Building Manufacturers Hyderabad.pptx
Pre Engineered  Building Manufacturers Hyderabad.pptxPre Engineered  Building Manufacturers Hyderabad.pptx
Pre Engineered Building Manufacturers Hyderabad.pptx
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptx
 
Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1
 
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
 
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGParadip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
Falcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business Growth
 
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
 
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
 
joint cost.pptx COST ACCOUNTING Sixteenth Edition ...
joint cost.pptx  COST ACCOUNTING  Sixteenth Edition                          ...joint cost.pptx  COST ACCOUNTING  Sixteenth Edition                          ...
joint cost.pptx COST ACCOUNTING Sixteenth Edition ...
 
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NSCROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
 
Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
 
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR ESCORTS
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR  ESCORTSJAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR  ESCORTS
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR ESCORTS
 
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service AvailableNashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
 
New 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck TemplateNew 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck Template
 
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
 

Kghm.sierra gorda americas-mining-may14-bro-s-0

  • 1. KGHM Polska Miedz: Sierra Gorda Project www.quadrafnx.com Strength in numbers
  • 2. As the Sierra Gorda Project enters an exciting new phase of its life, Senior Vice President of the project, Joseph Tis reflects on how the collective efforts and achievements of its workforce made 2013 such an important year words by Will Daynes research by Abi Abagun KGHM Polska Miedz - Sierra Gorda Project Strength in numbers
  • 3. s Joseph Tis, Senior Vice President, explains, 2013 was an important year for the Sierra Gorda open pit copper mine project. “In February of last year the project budget, valued at $4,000 million was updated. In the months that followed the project went on to complete a consolidated advance of 52.9 percent, reaching 91.2 percent in February 2014.” Located within Northern Chile’s Atacama Desert, the Sierra Gorda Project is a joint venture between KGHM International Ltd., Sumitomo Metal Mining and Sumitomo Corporation, and possesses deposits that total up to 2.2 billion tonnes of measured and indicated resources, and reserves amounting to some 1.3 billion tonnes. In addition to completing detailed A Secondary crusher & HPGR KGHM Polska Miedź - Sierra Gorda Project “We have made a number of great advances in the construction plant over the last year or more” engineering and locking down the purchasing of equipment, 2013 also saw Sierra Gorda benefit from the completion of infrastructure works designed to supply the site with electricity and water. Both 110Kv and 220kV electricity lines are now positioned on site, with the 110kV line going live during March of this year and the 220kV being brought into action the following month. In addition
  • 4. Scancontrols, control valve specialists, provides and advise our clients in Chile, on all matters relating to valves and fluid control. This, seen as the core of our development, has made us leaders in the industry, thanks to our fast response, performance and reliability. Founded in 2001 with the aim of providing the market with the best solutions for handling fluids via control valves, including engineering for selecting the type and size of valve, actuators and materials for each case. Our company has a full line of control valves and on / off valves, as well as manual valves for all types of processes. Also we offer diagnostic, maintenance and repair services of the valves in the city of Antofagasta. This service has allowed Scancontrols to make a difference and obtain a good position in the local market as one of the few companies able to offer integral solutions for fluid handling with valves. Scancontrols represents in Chile top brands such as SOMAS (Sweden), RF VALVES (USA) and Ringo Válvulas (Spain), which added to our Help Desk, Maintenance and Repair Team, leads to excellence and guaranteed results. Our services cover all industries including Mining, Pulp & Paper, Refineries, Petrochemicals, Power Plants, and others. “With a sustained growth in over 10 years of existence, Scancontrols is in a very strong position to continue expanding the services and products to new projects and markets” www.scancontrols.cl Scancontrols, control valve specialists, provides and advise our clients in Chile, on all matters relating to valves and fluid control. This, seen as the core of our development, has made us leaders in the industry, thanks to our fast response, performance and reliability. Founded in 2001 with the aim of providing the market with the best solutions for handling fluids via control valves, including engineering for selecting the type and size of valve, actuators and materials for each case. Our company has a full line of control valves and on / off valves, as well as manual valves for all types of processes. Also we offer diagnostic, maintenance and repair services of the valves in the city of Antofagasta. This service has allowed Scancontrols to make a difference and obtain a good position in the local market as one of the few companies able to offer integral solutions for fluid handling with valves. Scancontrols represents in Chile top brands such as SOMAS (Sweden), RF VALVES (USA) and Ringo Válvulas (Spain), which added to our Help Desk, Maintenance and Repair Team, leads to excellence and guaranteed results. Our services cover all industries including Mining, Pulp & Paper, Refineries, Petrochemicals, Power Plants, and others. “With a sustained growth in over 10 years of existence, Scancontrols is in a very strong position to continue expanding the services and products to new projects and markets” www.scancontrols.cl SCANCONTROLS Sierra Gorda feature text to go here......Lorem ipsum dolor sit amet, consectetur adipisicing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat. Duis aute irure dolor in reprehenderit in voluptate velit esse cillum dolore eu fugiat nulla pariatur. Excepteur sint occaecat cupidatat non proident, sunt in culpa qui officia deserunt mollit anim id est laborum. feature text to go here...... Lorem ipsum dolor sit amet, consectetur adipisicing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat. Duis aute irure dolor in reprehenderit in voluptate velit esse cillum doloreeufugiatnullapariatur. Excepteur sint occaecat cupidatat non proident, sunt in culpa qui officia deserunt mollit anim id est laborum. feature text to go here......Lorem ipsum dolor sit amet, consectetur adipisicing elit, sed do This is a caption this is a caption With over 400 knife gate valves in Sierra Gorda, Scancontrols with our partner RF Valves keeps providing high quality for the mining industry. RF Valves for Heavy Duty operations, are designed to control abrasive fluids, specially for adverse conditions where common valves are no good. Scancontrols is also in other large mining projects in Chile, continuing contributing to the quality of the processes with our represented brands. Email: info@scancontrols.cl www.scancontrols.cl Weworkwiththe BEST! Conveyor belts to the completion of these power lines, the assembly and welding of the project’s sea water aqueduct has also been finished. A particularly striking example of the progress made at Sierra Gorda over the last 12-18 months comes in the form of the project’s processing plant. “We have made a number of great advances in the construction plant over the last year or more,” Tis agrees, “going from eight to twelve percentage points during the months between August and December 2013 alone. Particular milestones achieved during 2013 included the delivery of the Truck Shop to operations, delivery of shovels 4 and 5, and the delivery of 17 haul trucks for use in Prestripping extraction operations. scancontrols “Particular milestones achieved during 2013 included the delivery of the Truck Shop to operations” KGHM Polska Miedź - Sierra Gorda Project
  • 5. SCM Sierra Gorda has chosen Ingeniería de Transportes Javier Cortés S.A. as his support for the transport of all their necessary supplies for the construction and start up of the SIERRA GORDA project located in the Antofagasta region. No doubt this is a great recognition for Ingeniería de Transportes Javier Cortés S.A. a company of a large and historical trajectory in the movement of oversize and overweight transport in the Chilean mining. The history of the company is certainly confusing with the growth of the Chilean mining after it started as a transport company for general cargo it is now specialized in the transport and operation of special cargo according to the development of the Chilean mining beyond of the 70’s. Ingeniería de Transportes Javier Cortés S.A., with more than 50 years in this business,hasbeenstandouttotransportthemostheaviestanddifficultcargoes in Chile, and that the transport on off-road trails to locations at 5,000 m.o.s.l. hasn´t been an obstacle to his successful career. For the construction of the Sierra Gorda project it was necessary to perform more than 5.000 voyages with import cargoes and domestic supplies. In order to address adequately this project, Ingeniería de Transportes Javier Cortés S.A. increased its fleet of modular equipments and trucks in order to fully meet the expectations of the client. With the result of this project we are very optimistic to keep and strengthen a long-term relationship with Sierra Gorda in order to participate in their upcoming projects in Chile. We take this opportunity to wish Sierra Gorda the best of success in the start up of the mine. Ingeniería de Transportes Javier Cortés S.A. is also actively involved in the development of wind farm, photovoltaic, thermoelectric, hydroelectric, cellulose, refineries and others projects as well in the consulting prior to project implementation phases. What makes that a certain company has been selected as a support in the development of a great mining project in Chile? www.javiercortes.com KGHM Polska Miedź - Sierra Gorda Project Furthermore, 2013 saw the installation of all critical plant equipment.” Tis is keen to add that all of the achievements already mentioned have been as a result of the tireless work of the project’s workforce performed in the field. During the month of October, 2013, employment activity on site reached a peak of 9500 workers, while 2013 as a whole saw a total of 11,236,934 man hours earned. “As of January 2014, we have calculated that more than 44,000 people have directly “As of January 2014, we have calculated that more than 44,000 people have directly contributed to the construction of the project and its various elements” contributed to the construction of the project and its various elements,” Tis states. “Each and every one of these people have at all times remained committed to our “Zero Harm” ethos, our most fundamental value which enforces our commitment to the health and safety of our employees and the communities in which we operate, and in doing so have not only met, but often exceeded expectations.” As a company KGHM has long been proud of the fact that it acts as a major contributor towards employment generation, regardless Sea water pond
  • 6. Hatch supporting Sierra Gorda from the beginning Sierra Gorda retained Hatch since mid 2012 to develop the detail engineering of their Molybdenum plant. The project has been a success from the engineering and procurement stand point and is currently well under way in construction. Hatch has not only done detail engineering to the Sierra Gorda Molybdenum plant but has supported Sierra Gorda as a key client and continued helping Sierra GordawiththeMolyplantFieldEngineeringServices, Pre-Commissioning & Commissioning support services for the entire Copper-Moly Concentrator, procurement support services and has as well reviewed the Basic Engineering of their concentrator future expansion. For Hatch, Sierra Gorda has been an excellent client, and one very good example of client engagement and commitment of our core values,allrequiredtocreateandenhancealongterm relationship adding the best possible value to our clients. The multidiscipline capabilities available at Hatch and the global availability of our experts have given us the strength to commit with Sierra Gorda in one of the largest mining projects of the continent. www.hatch.cl Stock pile of where it is based. This is very much the case with the Sierra Gorda Project, what with a great many of the 44,000 people who have contributed to its development coming from regions surrounding it. The largest contributor to date has been the VIII Biobío Region, from which the project has employed some 9,557 people, or 21.6 percent of the 44,000. Other major contributors have been the II Antofagasta Region, the Santiago Metropolitan Region XIII and the V Valparaíso Region, with 7,505, 7,085 and 6,306 residents employed on the project respectively. On top of these figures, no fewer than eleven other regions, from the XV Region of Arica and Parinacota, through to the XII Region of Magallanes have also contributed employees to the project. In addition to the creation of jobs, the Sierra Gorda Project has also contributed in hatch “In addition to the creation of jobs, the Sierra Gorda Project has also contributed in other vital ways to the local and national economies of Chile” KGHM Polska Miedź - Sierra Gorda Project
  • 7. Valves – Automation – Instrumentation • Control Valves • Positioners • Hydraulic / Electric Actuators • Field Instrumentation • Heat Exchangers Technical Services: Branch offices with highly qualified workshops for the maintenance and configuration of equipment. Field Services: Visits projects to make preventive check-ups to avoid halts in the productive processes. Technical Consultancies: Highly qualified professionals who advise and guide the purchase of equipment and/or services. Training: Technical and usage training orientated to obtain better performance of the equipment. POST-SALES SERVICES: QUALITY AT YOUR DISPOSAL Instruvalve, dedicated to providing quality products and services to the Mining, Energy, Oil & Gas, and general processes industries, provides its clients with world-class brands, excellent after-sales service and a highly qualified team. other vital ways to the local and national economies of Chile. “The existence of this project has not only helped strengthen the local mining industry, but also will contribute to the increased supply of copper on a national and international scale,” Tis says. “In doing so we have also played our part in ensuring that the country remains a leading global player when it comes to the production of copper, and in showcasing “The existence of this project has not only helped strengthen the local mining industry, but also will contribute to the increased supply of copper on a national and international scale” the professional quality and expertise of workforce, taking a massive development project from start to finish, we have helped send out a message to investors that Chile is a country worth taking notice of.” Giving back to the community is a trait that in many ways has characterised the project since its inception. To this day it arguable remains best reflected in the development, construction and “Instruvalve”, a Chilean Company with ten years of experience when it comes to the control of fluids and automation, supplied a package of electric actuators from Limitorque USA to the Sierra Gorda Mine project. The Limitorque actuators are used to operate ball and gate valves in the raw water sea pumping stations of the mine’s plant. Instruvalve also assisted in the implementation of the system. Instruvalve is grateful and thankful for the confidence shown by Sierra Gorda and is proud of be a technological partner of the mine, wishing it great success in its future operations. In its portfolio of products, “Instruvalve” also offer hydraulic/electric actuators, valve positioners, field instrumentation and heat exchangers. Instruvalve Ltda Quality at your disposal (55) 2944 369 ventas@instruvalve.cl www.instruvalve.cl Primary crusher KGHM Polska Miedź - Sierra Gorda Project
  • 8. implementation of numerous infrastructure projects that have helped improve quality of life within the region. Such projects include the construction of a wastewater treatment plant, the expansion of security checkpoints and the installation of CCTV to provide a safer environment, and the implementation of programmes designed to protect native flora and fauna. While 2013 was certainly an important year for the Sierra Gorda, 2014 could prove to be an even greater milestone, what with production at its processing plant due to commence this year, thus ushering in a new phase for the project. “In the short term our efforts are very much focused on completing the construction and pre-commissioning phases of the processing plant, and subsequently bringing it online, all the while fulfilling our Zero Harm commitments” Tis concludes. “Throughout the remainder of the year we will be bringing several other projects online and by December 2014 we expect to have completed the ramping up of production to bring it up to 110,000 tonnes per day.” Process plant “In the short term our efforts are very much focused on completing the construction and pre-commissioning phases of the processing plant” Progress on construction (at 31 December 2013) Project will be completed on time, planned completion of construction and commissioning in mid-2014 Total project progress is 86% complete Construction of sea water pipeline 94% complete, final hydraulic testing in progress Construction of tailings pond approx. 86% complete and processing plant approx. 80% complete Pre-stripping at 81% of the amount required before commissioning Around 96% of the CAPEX committed Around USD 3.4B of the committed amount has been incurred Did you know? KGHM Polska Miedź - Sierra Gorda Project 562-336-5200 info@kghminternational.com www.quadrafnx.com KGHM Polska Miedź - Sierra Gorda Project Tailings thickener