Water Distribution System
Final Report
Submitted By:: Muhammad Zohair
B-15086
SEC# A
6th
Semester
19/5/2014
Department Of Civil Engineering
University of South Asia Lahore (Rawind Campus)
Letter of Transmittal
Date: 19 May ,2014
Prof.Dr. Javed Anwar Aziz
Department Of Civil Engineering
University of South Asia, Lahore
Subject:- Water Distribution System Report Of Future Vision Housing Society
Respected Sir,
I am presenting you the final report of water distribution
system of “Future vision Housing Society” that is located on left side of Jehulm
road near upper Chenab. This report contains complete informations of the
design. This design is prepared by using Loop Software and AZIZ, J.A (2014)
class notes.
I am fully confident that the design of water distribution system will full fill all
the requirements of the housing society.
Yours Sincerely,
Muhammad Zohair
B-15086 (Sec# A)
TABLE OF CONTENTS
1. Introduction
2. Design Criteria
2.1. Design Period
2.2. Design Population
2.3. Water Consumption
2.4. Max day Consumption
2.5. Peak Hour Consumption
2.6. Water Requirement For
o School
o Dispensary
o Commercial Area
o Open Spaces
2.7. Capacity of OHR
2.8. Design Pressure
2.9. Capacity of the Pump
2.10. Max and Min Velocity
2.11. Size of Pipes and Types Of Pipes
2.12. Placing Of Pipes
3. Water Distribution System Design
3.1. Loop Method
3.2. Procedure for Design
3.3. Tracing
Chapter 1. INTRODUCTION
1.1. Brief Description Of Housing Scheme:
The name of the scheme is “Future Vision Housing Society”. The scheme
consist of 282 plots of different sizes e.g. 5 Marla’s, 10 Marla’s and 1 Kanal.
This scheme also has 3 flats of double story, 3 apartments, 2 parks, open
spaces, graveyard, school and 4 commercial areas.
The estimated population of the society is 7587 persons.
2 tube wells are provided at the central park of the society with over head
reservoir (OHR) which 20m high from the ground surface.
1.2. Location:
The Future Vision Housing Society Situated at Left side of Jehlum road near
upper Chenab canal.
1.3. Important Salient Features:
In this housing society following important salient features are provided.
 School
 Dispensary
 Parks
 Commercial Areas
 Treatment Plant
 Plots
 Flats
 Apartments
 Graveyard
1.4. Climate:
Climate of the area in summer season is very hot. Temperature ranges
from 30˚C to 45˚C.While in winter season the temperature fall up to 0˚C.
Due to hot condition in summer the water consumption is very high and in
winter water consumption is low.
1.5. Topography of the area:
The surface area of the society is almost flat. The maximum reduce level is
100.8m and minimum reduce level is 98.0m.There is very small difference
in level.
Chapter2. Assumptions
2.1. Design Period:
The design period of water distribution system of “Future Vision
Housing Society” is 25 years.
2.2. Design Population:
Present (2014) population of the society is 4374 persons.
Future (2039) population of the society is 7587persons.
2.3. Water Consumption:
It is the amount of water in volume that is consumed for different
purposes.Generally it is expressed in liter/capita/day (lpcd).
Per capita water consumption = 500+20(14)
= 500+20(8+6) = 780 lpcd
Where Y = Sum of digits of my registration No.
Average day W.C : Max day W.C = 1 : 1.5
Average day W.C : Peak Hour W.C= 1: 2.25
2.4. Maximum Day Consumption:
Max day water consumption = 1.5 X avg. day W.C
= 8949638 L/d
2.5. Peak Hour Consumption:
Peak hour water consumption = 2.25 X avg. day W.C
=13424456 L/d
2.6. Water Requirement For;
o School:
Water consumption for school = 60 X 200 = 12000 L/d
Present (2014) Future (2039)
Persons/Plot 7 11
Persons/Apartment 400 645
Persons/Flat 200 425
o Commercial Area:
Commercial Area = 5.5 cm2
=550 m2
Water consumption for commercial area = 3 X 550 = 1650 L/d
o Dispensary:
Water consumption for dispensary = 50 X 20 =1000 L/d
o Open Spaces/Parks:
Water consumption for open spaces/parks = 4845 X 7 = 33915 L/d
o Total W.C:
Total W.C = 48565 L/d
2.7. Maximum Head Loss Per Km:
In design the assumption for maximum head loss is 10 m/km.
Chapter3. Design Criteria
3.1. Design Flows for WDS:
Average design Flow = (7587 X 780) + 48565
= 5966425 L/d
Design Flow For T/W = 1.5 X 5966425
=8949638 L/d
3.2. Design Equation Used:
Here “Hazen William” Equation is used to findout Head losses.
HL = 10.65 (Q/C)1.85
L/(D)4.87
Where,
H = Head loss (m/km)
Q = Discharge (m/sec)
C = Roughness Coefficient
L = Length of pipe (m)
D = Diameter of pipe (m)
3.3. Height Of OHR And Capacity of OHR:
Height of over head reservoir is 20 m from the ground surface.
Capacity of over head reservoir is 1/6 of the daily avg. W.C.
Capacity of OHR = 1/6 X 5966425
= 994404.17 L/d
= 994.4 m3
/d
3.4. Number of T/w Installed:
There are two tube wells are installed in the central park of the society.
One of them runs on electricity and other on diesel.
3.5. Types of Pipes Used in the Scheme:
In this design two types of pipes are used for the water supply system.
o Cast Iron Pipes:
These pipes are from tubewell to OHR and from OHR to node #1.
The HWC for cast iron pipe is 100.
Cast Iron Pipe
o Asbestos Cement Pipe:
From node #1 to node #23 all the pipes that are used are asbestos
cement pipes.
The HWC for asbestos cement pipe is 140.
3.6. Diameter of Pipes:
In water supply system pipes of various diameter are used.The minimum
diameter of the pipe is 80mm.And also pipes of various diameter are used
in this water supply system i.e. 100mm,150mm,200mm,250mm,300mm,
350mm,400mm and 450mm.
3.7. Increment in dia size:
The increment in diameter size of the pipe is about 50mm.
3.8. Max and Min Velocity in W/S Pipes:
The maxium velocity in this water supply system is in pipe no.22 which
2.21m/sec
and minimum velocity is in pipe no.10 which is 0.33 m/sec
3.9. Pressure in Pipes:
In water supply system the minimum pressure in pipes is 15 and max
Pressure is 20.
In this design
Max Pressure =
Min Pressure =
3.10. Cover on Pipes:
Cover on pipes are provided for the safety of the pipes.For water supply
System the pipes are installed in 1m depth of ground.
3.11. Placing of Valves:
Valves are provided to regulate the flow,control of pressure and to cut
off of the water supply. There are 2 valves are provided at each node
and one valve for fire hydrent.
3.12. Placing of Fire Hydrant:
Fire hydrants are used to supply water for fire fighting.
Fire hydrants should have at least 2 hose outlets and a larger pump
outlet.Fire hydrant is provided at 1m from the edge of the road.
In this design there is one fire hydrant is provided.
Chapter4. Design of Water Distribution System
4.1 Loop Programme:
Loop is a computer program in BASIC for Hydraulic Simulation of Looped
Water Distribution Networks.
o Brief History:
Loop programme is the computer software developed by the University
of North California, USA.This software is developed in 1986. This software uses
the algorithm of Hardy Cross which is based on two principles
Inflow at node = Out flow at node
o Limitations:
This software has following limitations
a. Max Number of nodes = 400
b. Max Number of pipes = 500
c. Can handle 10 nodes with known HGL
o Input Data Required:
Following input data is required to run the programme.
a. Pipe number
b. Node number
c. Diameter of pipe
d. Pipe number
e. HWC of the pipe
o Output Informations Provided:
Following output informations are provided by the programme.
a. Head loss in pipes
b. Pressure at nodes
c. Flow in pipes
d. Velocity in pipes
e. Direction of flow
o Units Employed in Loop for Various Parameters:
The units used in this software are
a. Length in m
b. Diameter in mm
c. Flow in L/sec
d. Velocity in m/sec
e. Elevation in m
f. HGL in m
g. Head Loss in m
o Node Fixation:
In this loop programme node #100 is fixed due to constant discharge.
o Signs applied for input and output flows:
Here ,
+ve sign indicates input flow
-ve sign indicates output flow
4.2. Procedure:
 First of all draw the layout of water distribution system.
 Represent each node with the help of a dot.
 Allocate plots or area to each node. The allocation of plots to the
nodes should be as realistic and balanced as possible.
 Using per capita water consumption value (lpcd), calculate avg. water
consumption at each node in liter/second.
 Take a tracing paper equal in size to your map and trace the pipe and
nodes network on it. Now represent each node with a small circle.
 Give number to each pipe and node (inside the circle). Give such
numbers to T/W and OHR so that these two nodes can easily be
distinguished from other network nodes.
 Measure the lengths of pipes according to the scale and write the
lengths on the tracing sheet. Also write reduce levels with each node
on tracing sheet.
 Write nodal flows in lit/sec on tracing sheet using an arrow head.
4.2. Design Input Data:
4.3. Design output Sheet:
Size of pipes and lenghts of pipes are given below in table
Pipe Number Length (m) Diameter (mm)
1 28 150
2 37 150
3 43 150
4 54 150
5 45 250
6 42 150
7 20 250
8 47 200
9 160 150
10 160 250
11 47 150
12 62 250
13 88 250
14 23 250
15 38 200
16 41 250
17 36 80
18 38 250
19 100 150
20 39 250
21 100 150
22 36 150
23 100 150
24 38 150
25 113 80
26 36 150
27 113 80
28 43 80
29 113 150
30 54 350
31 113 500
Water distribution system design report

Weitere Àhnliche Inhalte

Was ist angesagt?

Design water supply scheme
Design water supply schemeDesign water supply scheme
Design water supply schemeAby Mundackal
 
Design of barrages
Design of barragesDesign of barrages
Design of barragesVishal Jolaniya
 
05 water supply system
05 water supply system05 water supply system
05 water supply systemAkepati S. Reddy
 
Design of Lined Canal and Canal Lining
Design of Lined Canal and Canal LiningDesign of Lined Canal and Canal Lining
Design of Lined Canal and Canal LiningRamanuj Jaldhari
 
Storage and distribution reservoirs
Storage and distribution reservoirsStorage and distribution reservoirs
Storage and distribution reservoirsfarooq husain
 
Collection and estimation of sewage
Collection and estimation of sewageCollection and estimation of sewage
Collection and estimation of sewageBibhabasu Mohanty
 
Canal irrigation
Canal irrigationCanal irrigation
Canal irrigationSAGAR RAUT
 
Chapter 7 spillway and energy dissipators
Chapter 7 spillway and energy dissipatorsChapter 7 spillway and energy dissipators
Chapter 7 spillway and energy dissipatorsMohsin Siddique
 
sewers and sewer netwrok - design construction and maintenance
sewers and sewer netwrok - design construction and maintenancesewers and sewer netwrok - design construction and maintenance
sewers and sewer netwrok - design construction and maintenanceManish Goyal
 
Water supply appurtenances
Water supply appurtenancesWater supply appurtenances
Water supply appurtenancesAjay B.K
 
Irrigation Engineering
Irrigation EngineeringIrrigation Engineering
Irrigation EngineeringGAURAV. H .TANDON
 
Water distribution system
Water distribution system Water distribution system
Water distribution system Mood Naik
 
Rain water harvesting ppt
Rain water harvesting pptRain water harvesting ppt
Rain water harvesting pptPalash Jain
 
Analysis of runoff for vishwamitri river watershed using scs cn method and ge...
Analysis of runoff for vishwamitri river watershed using scs cn method and ge...Analysis of runoff for vishwamitri river watershed using scs cn method and ge...
Analysis of runoff for vishwamitri river watershed using scs cn method and ge...vishvam Pancholi
 
Chapter 4 seepage theories
Chapter 4 seepage theoriesChapter 4 seepage theories
Chapter 4 seepage theoriesMohsin Siddique
 
design of weirs
design of weirsdesign of weirs
design of weirsSANJEEV Wazir
 
Highway Drainage (Highway Engineering)
Highway Drainage (Highway Engineering)Highway Drainage (Highway Engineering)
Highway Drainage (Highway Engineering)Kiranmoy Samanta
 

Was ist angesagt? (20)

SEWER DESIGN:
SEWER DESIGN:SEWER DESIGN:
SEWER DESIGN:
 
Design water supply scheme
Design water supply schemeDesign water supply scheme
Design water supply scheme
 
Design of barrages
Design of barragesDesign of barrages
Design of barrages
 
river training work
river training workriver training work
river training work
 
05 water supply system
05 water supply system05 water supply system
05 water supply system
 
Design of Lined Canal and Canal Lining
Design of Lined Canal and Canal LiningDesign of Lined Canal and Canal Lining
Design of Lined Canal and Canal Lining
 
Storage and distribution reservoirs
Storage and distribution reservoirsStorage and distribution reservoirs
Storage and distribution reservoirs
 
Diversion Headworks
Diversion HeadworksDiversion Headworks
Diversion Headworks
 
Collection and estimation of sewage
Collection and estimation of sewageCollection and estimation of sewage
Collection and estimation of sewage
 
Canal irrigation
Canal irrigationCanal irrigation
Canal irrigation
 
Chapter 7 spillway and energy dissipators
Chapter 7 spillway and energy dissipatorsChapter 7 spillway and energy dissipators
Chapter 7 spillway and energy dissipators
 
sewers and sewer netwrok - design construction and maintenance
sewers and sewer netwrok - design construction and maintenancesewers and sewer netwrok - design construction and maintenance
sewers and sewer netwrok - design construction and maintenance
 
Water supply appurtenances
Water supply appurtenancesWater supply appurtenances
Water supply appurtenances
 
Irrigation Engineering
Irrigation EngineeringIrrigation Engineering
Irrigation Engineering
 
Water distribution system
Water distribution system Water distribution system
Water distribution system
 
Rain water harvesting ppt
Rain water harvesting pptRain water harvesting ppt
Rain water harvesting ppt
 
Analysis of runoff for vishwamitri river watershed using scs cn method and ge...
Analysis of runoff for vishwamitri river watershed using scs cn method and ge...Analysis of runoff for vishwamitri river watershed using scs cn method and ge...
Analysis of runoff for vishwamitri river watershed using scs cn method and ge...
 
Chapter 4 seepage theories
Chapter 4 seepage theoriesChapter 4 seepage theories
Chapter 4 seepage theories
 
design of weirs
design of weirsdesign of weirs
design of weirs
 
Highway Drainage (Highway Engineering)
Highway Drainage (Highway Engineering)Highway Drainage (Highway Engineering)
Highway Drainage (Highway Engineering)
 

Ähnlich wie Water distribution system design report

IRJET- Hydraulic and Structural Design of Water Treatment Plant
IRJET- Hydraulic and Structural Design of Water Treatment PlantIRJET- Hydraulic and Structural Design of Water Treatment Plant
IRJET- Hydraulic and Structural Design of Water Treatment PlantIRJET Journal
 
odun dgdgf_125332.pptx
odun dgdgf_125332.pptxodun dgdgf_125332.pptx
odun dgdgf_125332.pptxAgohaChinonso
 
Group Project to Design Water Infrastructure for a Theoretical Small Town.
Group Project to Design Water Infrastructure for a Theoretical Small Town.Group Project to Design Water Infrastructure for a Theoretical Small Town.
Group Project to Design Water Infrastructure for a Theoretical Small Town.Jonathan Damora
 
IRJET - Design of Water Distribution Network using EPANET Software
IRJET -  	  Design of Water Distribution Network using EPANET SoftwareIRJET -  	  Design of Water Distribution Network using EPANET Software
IRJET - Design of Water Distribution Network using EPANET SoftwareIRJET Journal
 
ch4-part-2.pdf
ch4-part-2.pdfch4-part-2.pdf
ch4-part-2.pdffaisalhussin1
 
RESEARCH PAPER ARPIT
RESEARCH PAPER ARPITRESEARCH PAPER ARPIT
RESEARCH PAPER ARPITArpit Chaudhary
 
HYDRAULIC MODELING OF A RURAL DRINKING WATER DISTRIBUTION {ju}.pptx
HYDRAULIC MODELING OF A RURAL DRINKING WATER DISTRIBUTION {ju}.pptxHYDRAULIC MODELING OF A RURAL DRINKING WATER DISTRIBUTION {ju}.pptx
HYDRAULIC MODELING OF A RURAL DRINKING WATER DISTRIBUTION {ju}.pptxINDRANIL BANERJEE
 
Design of Fire Systems in Nanjing Research Institute of Huawei’s New Rent Eng...
Design of Fire Systems in Nanjing Research Institute of Huawei’s New Rent Eng...Design of Fire Systems in Nanjing Research Institute of Huawei’s New Rent Eng...
Design of Fire Systems in Nanjing Research Institute of Huawei’s New Rent Eng...IJRES Journal
 
EM DESIGN_CR-WASH_ uytrrfucgu PROJECTS.pptx
EM DESIGN_CR-WASH_ uytrrfucgu PROJECTS.pptxEM DESIGN_CR-WASH_ uytrrfucgu PROJECTS.pptx
EM DESIGN_CR-WASH_ uytrrfucgu PROJECTS.pptx2cd
 
odunlami prese_033552.pptx
odunlami prese_033552.pptxodunlami prese_033552.pptx
odunlami prese_033552.pptxAgohaChinonso
 
Sewerage design
Sewerage designSewerage design
Sewerage designSharifah Ain
 
The simultaneous loop flow correction analysis in the water feed network of M...
The simultaneous loop flow correction analysis in the water feed network of M...The simultaneous loop flow correction analysis in the water feed network of M...
The simultaneous loop flow correction analysis in the water feed network of M...IJERA Editor
 
Thesis present voeng soavandara
Thesis  present  voeng soavandaraThesis  present  voeng soavandara
Thesis present voeng soavandaravoengsovandara
 
Sewage treatment plant design calculation
Sewage treatment plant design calculationSewage treatment plant design calculation
Sewage treatment plant design calculationSharifah Ain
 
Design and implementation of micro hydro turbine for power generation and its...
Design and implementation of micro hydro turbine for power generation and its...Design and implementation of micro hydro turbine for power generation and its...
Design and implementation of micro hydro turbine for power generation and its...IRJET Journal
 
"Design Criteria of Lift Irrigation Scheme"
"Design Criteria of Lift Irrigation Scheme""Design Criteria of Lift Irrigation Scheme"
"Design Criteria of Lift Irrigation Scheme"IRJET Journal
 

Ähnlich wie Water distribution system design report (20)

IRJET- Hydraulic and Structural Design of Water Treatment Plant
IRJET- Hydraulic and Structural Design of Water Treatment PlantIRJET- Hydraulic and Structural Design of Water Treatment Plant
IRJET- Hydraulic and Structural Design of Water Treatment Plant
 
bro.pptx
bro.pptxbro.pptx
bro.pptx
 
odun dgdgf_125332.pptx
odun dgdgf_125332.pptxodun dgdgf_125332.pptx
odun dgdgf_125332.pptx
 
Group Project to Design Water Infrastructure for a Theoretical Small Town.
Group Project to Design Water Infrastructure for a Theoretical Small Town.Group Project to Design Water Infrastructure for a Theoretical Small Town.
Group Project to Design Water Infrastructure for a Theoretical Small Town.
 
IRJET - Design of Water Distribution Network using EPANET Software
IRJET -  	  Design of Water Distribution Network using EPANET SoftwareIRJET -  	  Design of Water Distribution Network using EPANET Software
IRJET - Design of Water Distribution Network using EPANET Software
 
ch4-part-2.pdf
ch4-part-2.pdfch4-part-2.pdf
ch4-part-2.pdf
 
8445806
84458068445806
8445806
 
RESEARCH PAPER ARPIT
RESEARCH PAPER ARPITRESEARCH PAPER ARPIT
RESEARCH PAPER ARPIT
 
wheel
wheelwheel
wheel
 
Narendra parmar
Narendra parmarNarendra parmar
Narendra parmar
 
HYDRAULIC MODELING OF A RURAL DRINKING WATER DISTRIBUTION {ju}.pptx
HYDRAULIC MODELING OF A RURAL DRINKING WATER DISTRIBUTION {ju}.pptxHYDRAULIC MODELING OF A RURAL DRINKING WATER DISTRIBUTION {ju}.pptx
HYDRAULIC MODELING OF A RURAL DRINKING WATER DISTRIBUTION {ju}.pptx
 
Design of Fire Systems in Nanjing Research Institute of Huawei’s New Rent Eng...
Design of Fire Systems in Nanjing Research Institute of Huawei’s New Rent Eng...Design of Fire Systems in Nanjing Research Institute of Huawei’s New Rent Eng...
Design of Fire Systems in Nanjing Research Institute of Huawei’s New Rent Eng...
 
EM DESIGN_CR-WASH_ uytrrfucgu PROJECTS.pptx
EM DESIGN_CR-WASH_ uytrrfucgu PROJECTS.pptxEM DESIGN_CR-WASH_ uytrrfucgu PROJECTS.pptx
EM DESIGN_CR-WASH_ uytrrfucgu PROJECTS.pptx
 
odunlami prese_033552.pptx
odunlami prese_033552.pptxodunlami prese_033552.pptx
odunlami prese_033552.pptx
 
Sewerage design
Sewerage designSewerage design
Sewerage design
 
The simultaneous loop flow correction analysis in the water feed network of M...
The simultaneous loop flow correction analysis in the water feed network of M...The simultaneous loop flow correction analysis in the water feed network of M...
The simultaneous loop flow correction analysis in the water feed network of M...
 
Thesis present voeng soavandara
Thesis  present  voeng soavandaraThesis  present  voeng soavandara
Thesis present voeng soavandara
 
Sewage treatment plant design calculation
Sewage treatment plant design calculationSewage treatment plant design calculation
Sewage treatment plant design calculation
 
Design and implementation of micro hydro turbine for power generation and its...
Design and implementation of micro hydro turbine for power generation and its...Design and implementation of micro hydro turbine for power generation and its...
Design and implementation of micro hydro turbine for power generation and its...
 
"Design Criteria of Lift Irrigation Scheme"
"Design Criteria of Lift Irrigation Scheme""Design Criteria of Lift Irrigation Scheme"
"Design Criteria of Lift Irrigation Scheme"
 

KĂŒrzlich hochgeladen

Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
Designing pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptxDesigning pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptxErbil Polytechnic University
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgsaravananr517913
 
Crystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptxCrystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptxachiever3003
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating SystemRashmi Bhat
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Autonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.pptAutonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.pptbibisarnayak0
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm Systemirfanmechengr
 
National Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfNational Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfRajuKanojiya4
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating SystemRashmi Bhat
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
Engineering Drawing section of solid
Engineering Drawing     section of solidEngineering Drawing     section of solid
Engineering Drawing section of solidnamansinghjarodiya
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the weldingMuhammadUzairLiaqat
 
home automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadhome automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadaditya806802
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 

KĂŒrzlich hochgeladen (20)

Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
Designing pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptxDesigning pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptx
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
 
Crystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptxCrystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptx
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating System
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Autonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.pptAutonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.ppt
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm System
 
National Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfNational Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdf
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating System
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
Engineering Drawing section of solid
Engineering Drawing     section of solidEngineering Drawing     section of solid
Engineering Drawing section of solid
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the welding
 
home automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadhome automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasad
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 

Water distribution system design report

  • 1. Water Distribution System Final Report Submitted By:: Muhammad Zohair B-15086 SEC# A 6th Semester 19/5/2014 Department Of Civil Engineering University of South Asia Lahore (Rawind Campus)
  • 2. Letter of Transmittal Date: 19 May ,2014 Prof.Dr. Javed Anwar Aziz Department Of Civil Engineering University of South Asia, Lahore Subject:- Water Distribution System Report Of Future Vision Housing Society Respected Sir, I am presenting you the final report of water distribution system of “Future vision Housing Society” that is located on left side of Jehulm road near upper Chenab. This report contains complete informations of the design. This design is prepared by using Loop Software and AZIZ, J.A (2014) class notes. I am fully confident that the design of water distribution system will full fill all the requirements of the housing society. Yours Sincerely, Muhammad Zohair B-15086 (Sec# A)
  • 3. TABLE OF CONTENTS 1. Introduction 2. Design Criteria 2.1. Design Period 2.2. Design Population 2.3. Water Consumption 2.4. Max day Consumption 2.5. Peak Hour Consumption 2.6. Water Requirement For o School o Dispensary o Commercial Area o Open Spaces 2.7. Capacity of OHR 2.8. Design Pressure 2.9. Capacity of the Pump 2.10. Max and Min Velocity 2.11. Size of Pipes and Types Of Pipes 2.12. Placing Of Pipes 3. Water Distribution System Design 3.1. Loop Method 3.2. Procedure for Design 3.3. Tracing
  • 4. Chapter 1. INTRODUCTION 1.1. Brief Description Of Housing Scheme: The name of the scheme is “Future Vision Housing Society”. The scheme consist of 282 plots of different sizes e.g. 5 Marla’s, 10 Marla’s and 1 Kanal. This scheme also has 3 flats of double story, 3 apartments, 2 parks, open spaces, graveyard, school and 4 commercial areas. The estimated population of the society is 7587 persons. 2 tube wells are provided at the central park of the society with over head reservoir (OHR) which 20m high from the ground surface. 1.2. Location: The Future Vision Housing Society Situated at Left side of Jehlum road near upper Chenab canal. 1.3. Important Salient Features: In this housing society following important salient features are provided.  School  Dispensary  Parks  Commercial Areas  Treatment Plant  Plots  Flats  Apartments  Graveyard 1.4. Climate: Climate of the area in summer season is very hot. Temperature ranges from 30˚C to 45˚C.While in winter season the temperature fall up to 0˚C. Due to hot condition in summer the water consumption is very high and in winter water consumption is low. 1.5. Topography of the area: The surface area of the society is almost flat. The maximum reduce level is 100.8m and minimum reduce level is 98.0m.There is very small difference in level.
  • 5. Chapter2. Assumptions 2.1. Design Period: The design period of water distribution system of “Future Vision Housing Society” is 25 years. 2.2. Design Population: Present (2014) population of the society is 4374 persons. Future (2039) population of the society is 7587persons. 2.3. Water Consumption: It is the amount of water in volume that is consumed for different purposes.Generally it is expressed in liter/capita/day (lpcd). Per capita water consumption = 500+20(14) = 500+20(8+6) = 780 lpcd Where Y = Sum of digits of my registration No. Average day W.C : Max day W.C = 1 : 1.5 Average day W.C : Peak Hour W.C= 1: 2.25 2.4. Maximum Day Consumption: Max day water consumption = 1.5 X avg. day W.C = 8949638 L/d 2.5. Peak Hour Consumption: Peak hour water consumption = 2.25 X avg. day W.C =13424456 L/d 2.6. Water Requirement For; o School: Water consumption for school = 60 X 200 = 12000 L/d Present (2014) Future (2039) Persons/Plot 7 11 Persons/Apartment 400 645 Persons/Flat 200 425
  • 6. o Commercial Area: Commercial Area = 5.5 cm2 =550 m2 Water consumption for commercial area = 3 X 550 = 1650 L/d o Dispensary: Water consumption for dispensary = 50 X 20 =1000 L/d o Open Spaces/Parks: Water consumption for open spaces/parks = 4845 X 7 = 33915 L/d o Total W.C: Total W.C = 48565 L/d 2.7. Maximum Head Loss Per Km: In design the assumption for maximum head loss is 10 m/km.
  • 7. Chapter3. Design Criteria 3.1. Design Flows for WDS: Average design Flow = (7587 X 780) + 48565 = 5966425 L/d Design Flow For T/W = 1.5 X 5966425 =8949638 L/d 3.2. Design Equation Used: Here “Hazen William” Equation is used to findout Head losses. HL = 10.65 (Q/C)1.85 L/(D)4.87 Where, H = Head loss (m/km) Q = Discharge (m/sec) C = Roughness Coefficient L = Length of pipe (m) D = Diameter of pipe (m) 3.3. Height Of OHR And Capacity of OHR: Height of over head reservoir is 20 m from the ground surface. Capacity of over head reservoir is 1/6 of the daily avg. W.C. Capacity of OHR = 1/6 X 5966425 = 994404.17 L/d = 994.4 m3 /d 3.4. Number of T/w Installed: There are two tube wells are installed in the central park of the society. One of them runs on electricity and other on diesel. 3.5. Types of Pipes Used in the Scheme: In this design two types of pipes are used for the water supply system. o Cast Iron Pipes: These pipes are from tubewell to OHR and from OHR to node #1. The HWC for cast iron pipe is 100.
  • 8. Cast Iron Pipe o Asbestos Cement Pipe: From node #1 to node #23 all the pipes that are used are asbestos cement pipes. The HWC for asbestos cement pipe is 140.
  • 9. 3.6. Diameter of Pipes: In water supply system pipes of various diameter are used.The minimum diameter of the pipe is 80mm.And also pipes of various diameter are used in this water supply system i.e. 100mm,150mm,200mm,250mm,300mm, 350mm,400mm and 450mm. 3.7. Increment in dia size: The increment in diameter size of the pipe is about 50mm. 3.8. Max and Min Velocity in W/S Pipes: The maxium velocity in this water supply system is in pipe no.22 which 2.21m/sec and minimum velocity is in pipe no.10 which is 0.33 m/sec 3.9. Pressure in Pipes: In water supply system the minimum pressure in pipes is 15 and max Pressure is 20. In this design Max Pressure = Min Pressure = 3.10. Cover on Pipes: Cover on pipes are provided for the safety of the pipes.For water supply System the pipes are installed in 1m depth of ground. 3.11. Placing of Valves: Valves are provided to regulate the flow,control of pressure and to cut off of the water supply. There are 2 valves are provided at each node and one valve for fire hydrent.
  • 10. 3.12. Placing of Fire Hydrant: Fire hydrants are used to supply water for fire fighting. Fire hydrants should have at least 2 hose outlets and a larger pump outlet.Fire hydrant is provided at 1m from the edge of the road. In this design there is one fire hydrant is provided. Chapter4. Design of Water Distribution System 4.1 Loop Programme: Loop is a computer program in BASIC for Hydraulic Simulation of Looped Water Distribution Networks. o Brief History: Loop programme is the computer software developed by the University of North California, USA.This software is developed in 1986. This software uses the algorithm of Hardy Cross which is based on two principles Inflow at node = Out flow at node o Limitations: This software has following limitations a. Max Number of nodes = 400 b. Max Number of pipes = 500 c. Can handle 10 nodes with known HGL
  • 11. o Input Data Required: Following input data is required to run the programme. a. Pipe number b. Node number c. Diameter of pipe d. Pipe number e. HWC of the pipe o Output Informations Provided: Following output informations are provided by the programme. a. Head loss in pipes b. Pressure at nodes c. Flow in pipes d. Velocity in pipes e. Direction of flow o Units Employed in Loop for Various Parameters: The units used in this software are a. Length in m b. Diameter in mm c. Flow in L/sec d. Velocity in m/sec e. Elevation in m f. HGL in m g. Head Loss in m o Node Fixation: In this loop programme node #100 is fixed due to constant discharge. o Signs applied for input and output flows: Here , +ve sign indicates input flow -ve sign indicates output flow 4.2. Procedure:  First of all draw the layout of water distribution system.  Represent each node with the help of a dot.  Allocate plots or area to each node. The allocation of plots to the nodes should be as realistic and balanced as possible.
  • 12.  Using per capita water consumption value (lpcd), calculate avg. water consumption at each node in liter/second.  Take a tracing paper equal in size to your map and trace the pipe and nodes network on it. Now represent each node with a small circle.  Give number to each pipe and node (inside the circle). Give such numbers to T/W and OHR so that these two nodes can easily be distinguished from other network nodes.  Measure the lengths of pipes according to the scale and write the lengths on the tracing sheet. Also write reduce levels with each node on tracing sheet.  Write nodal flows in lit/sec on tracing sheet using an arrow head. 4.2. Design Input Data:
  • 13.
  • 14.
  • 15.
  • 17.
  • 18.
  • 19. Size of pipes and lenghts of pipes are given below in table Pipe Number Length (m) Diameter (mm) 1 28 150 2 37 150 3 43 150 4 54 150 5 45 250 6 42 150 7 20 250 8 47 200 9 160 150 10 160 250 11 47 150 12 62 250 13 88 250 14 23 250 15 38 200 16 41 250 17 36 80 18 38 250 19 100 150 20 39 250 21 100 150 22 36 150 23 100 150 24 38 150 25 113 80 26 36 150 27 113 80 28 43 80 29 113 150 30 54 350 31 113 500