5. project execution procedure
1. СЭА QUALITY MANAGEMENT SYSTEM
The document
name
Procedure of building of objects
Effective date:
Code: SEA-P707 14.03.2006 years
THE MAINTENANCE:
1. THE PURPOSE
2. SCOPE OF APPLICATION
3. REFERENCES TO DOCUMENTS
4. THE PROCEDURE DESCRIPTION
5. RESPONSIBILITY AND POWERS
6. DESIGNATIONS AND REDUCTIONS
7. APPENDICES
THE HAS PREPARED: HAS CHECKED UP: HAS CONFIRMED:
DOCUMENT
Post: Chief ПТО The chief engineer The general director
FIRST NAME,
MIDDLE
INITIAL, LAST
Varakin O. Lerner B. Lobach A.
NAME:
The signature:
№ 1. 2. 3. 4. 5.
SEA P707 Sheet 1 1from 6
2. СЭА QUALITY MANAGEMENT SYSTEM
The document
name
Procedure of building of objects
Effective date:
Code: SEA-P707 14.03.2006 years
Changes Date:
The signature:
Sheet of mailing of the document
№ The name Date The
Post
пп Divisions Receptions signature
1 The top management The general director 16.03.06
2 The chief engineer 16.03.06 г
3 Head СМК 16.03.06 г
4 The chief accountant 16.03.06 г
5 The agent on supply 16.03.06 г
6 The manager on the personnel 16.03.06 г
7 Technological The chief of department 16.03.06 г
department
8 The mechanic 16.03.06 г
9 Industrial site №1 The chief of a site 17.03.06г.
10 Industrial site №2 The chief of a site 17.03.06г.
SEA P707 Sheet 1 2from 6
3. СЭА QUALITY MANAGEMENT SYSTEM
The document
name
Procedure of building of objects
Effective date:
Code: SEA-P707 14.03.2006 years
1. The procedure purpose.
The present procedure regulates an order of the organisation of building of objects under
contracts and Electrical Instrumentation Construction Corporationcontracts.
2. Scope of application
The present process is obligatory for use by all structural divisions of the company.
3. The reference to documents
ISO 9001:2000, section 7;
Quality manual of SEA QM-01
SNI П 111-4-80;
SNI П 3.01.03-84;:
ВСН 004-88;
ВСН 005-88;
ВСН 011-88;
ВСН 012-88
4. The procedure description
In the primary activity – the organisation of building of petro-gas pipelines and their
infrastructure carries out Electrical Instrumentation Construction Corporationby means of attraction
to this work of the specialised building companies on conditions субподряда.
The organisation and performance of works on building of objects develops of separate
processes, the block which scheme is presented in the appendix №1.
4.1. The contract or contract conclusion on building.
The order of the conclusion of the contract contract on building is stated in procedure of
SEA П702.
4.2 Selection and appointment as orders of a management of Electrical Instrumentation
Construction Corporationof the curator of building of object and leaders ИТР.
Nominees steal up from among employees of the company taking into account their know-
how work, personal qualities and vocational training.
SEA P707 Sheet 1 3from 6
4. СЭА QUALITY MANAGEMENT SYSTEM
The document
name
Procedure of building of objects
Effective date:
Code: SEA-P707 14.03.2006 years
4.3. Performance of mobilisation actions.
Are carried out together with the involved subcontract organisations and includes a little in
parallel carried out actions, namely:
It is developed by technological department PPR (the project of manufacture of works);
Get out and certified by chief specialists of Electrical Instrumentation Construction
Corporationof technology of performance of works (welding, изоляционных, etc.);
On a building site heads of building with pilot group leave and will organise an
infrastructure of a site of building.
4.4. Working out and the coordination with the Customer of the schedule of building of
object.
According to requirements of contract ПТО under the direction of the Chief engineer
develop the schedule of building of object and co-ordinate it with the Customer.
4.5. Purchase of materials and the equipment for object building
According to contract specifications, and also after positive results of certification of the
basic technological processes the agent on supply under the demand given out ПТО carries
out purchase of materials and the equipment according to procedure of SEA P704.
4.6. Performance of civil and erection works.
Works on object are carried out by production teams on the certified technologies and
typical technological instructions. It is simultaneously carried out quality of performance of
works is supervised, realisation of the schedule of building is analyzed.
4.7. Registration of the executive documentation «as is constructed».
All stages of works come to the end with registration of intermediate certificates. From the
specified documents the executive documentation which on building end is transferred to the
Customer is formed. Forms of certificates are certificated, resulted in СНиП or ВСН.
4.8. Tests and object pusko-adjustment.
It is carried out by the personnel of building division under the direction of Electrical
Instrumentation Construction Corporation with participation of the Customer, under
requirements of standards or special requirements of the Customer.
4.9. Transfer of the constructed object to the Customer.
The process end
5. Responsibility and powers.
SEA P707 Sheet 1 4from 6
5. СЭА QUALITY MANAGEMENT SYSTEM
The document
name
Procedure of building of objects
Effective date:
Code: SEA-P707 14.03.2006 years
This procedure is applied by all divisions of the company participating in preparation
and the organisation of process of building of objects. The general control over correct
application of the present procedure is assigned to the Chief engineer.
6. Designations and reductions
ППР – the Project of manufacture of works
ПТО – Technological department
СНиП – Building norms and rules
7. Appendices
The appendix № 1 – the Block the process scheme
SEA P707 Sheet 1 5from 6
6. СЭА QUALITY MANAGEMENT SYSTEM
The document
name
Procedure of building of objects
Effective date:
Code: SEA-P707 14.03.2006 years
The The appendix № 1 Block the scheme of processes of the organisation of building of objects
beginning
The SEA П702 4.1.
contract conclusion Gene. The director
4.2
Selection руков. Buildings Гл. The engineer.
Orders Directors
4.3
Mobilisation Company
management
СниП,
ВСН
GPS П501
Working out ППР Certification of technologies Creation инфрастр.
(ПТО) (Chief specialists) Platforms (Hands. st-va)
The Треб. Контр. 4.4.
coordination of the schedule ПТО
of building
The SEA П704 4.5
Purchase of materials and agent on supply
the equipment
ППР, ВСН,
СНиП Performance of all kinds of Contractors
4.6
works on building
The
Quality assurance of schedule analysis builds.
works
Оформл. Will execute. Manufacturers of
4.7
Documentation works of
contractors
Tests, starting-up and 4.8 Гл. The engineer
adjustment works also Builds. A site
Commissioning 4.9 Гл. The engineer
also Builds. A site
The
end
SEA P707 Sheet 1 6from 6