By Gerrit Maess | Lovelyn George| Ramon Rios R | Zainab Sayyed
Project:
Automation of Business Process
Management System
Service Provider Client
WNS Introduction
• Business process management
company (Software and Web Services)
• Headquarter is in Mumbai, India
• The company serves over 200 Fortune
500 companies worldwide
1
2
Financial Models – Net Present Value and Payback Method
Selected Methods
2
Non-Financial Models - Multi Weighted Scoring Matrix
Selected Methods
2
Project Portfolio Matrix
Selected Methods
Net Present Value
Why WNS Selected BPM Automation
(Global Star Travels Project)?
 Strategic Project with the highest Net Present Value (NPV) of $196,338
 We can recover the investment in 10.9 months
 Having the highest weight score of 72
 This project is technological breakthrough with highest commercial payoff
3
Defining  Planning  Executing  Delivering
2
Project Life Cycle
Defining the Project
4
Defining Project Scope
Objective:
To design an automated Business Process Management System using MS SQL
Server and BI system within `12 months at a cost not to exceed $700,000.
Priority Matrix:
4
Specification
Hardware:
 Setup Database server
 Setup Web Server
 System down time < 4 hours
Software:
 BI system (middle and top
management)
 Web application system
4
Task
Deliverables:
 BI reports (Analytics tools) for
middle and top management
 Backend database system
 Interfaces / Middleware compatible
with existing front end solutions
 Technical reference document
Project Scope Checklist
5
Work Break Down Structure
3
Integration of WBS and OBS
Cost Account
The intersection of WP- Hardware
Service and Organization IT
department creates a cost account.
By rolling up Hardware Service and
Software License WP System
(deliverable) cost is calculated.
Planning
4
Bottom Up: Support Cost Est
6
Top-Down: Function Point
Contract Bid
Time and Cost Estimations
Contract Bid Summary Costs
Total Direct Cost $540,000.00
G&A overhead (10%) $54,000.00
Total Costs $594,000.00
Profit(17.5%) $103,950.00
Total Bid $697,950.00
PERT
6
Time and Cost Estimations
6
Managing Risk
6
Gantt Chart
Resource Allocation
Before Levelling: 230 days
6
After Leveling: 237 days
Executing
4
3
Tracking Gantt Chart (Jul-16)
Earned Value Chart
6
Indexes Period
$0.00
$50,000.00
$100,000.00
$150,000.00
$200,000.00
$250,000.00
$300,000.00
Jan'16
Feb'16
Mar'16
Apr'16
May'16
Jun'16
Jul'16
Aug'16
Sep'16
Oct'16
Nov'16
Dec'16
ACWP BCWP BCWS
Actual Cost Linear (ACWP)
0
0.2
0.4
0.6
0.8
1
1.2
Jan'16
Feb'16
Mar'16
Apr'16
May'16
Jun'16
Jul'16
Aug'16
Sep'16
Oct'16
Nov'16
Dec'16
SPI CPI
CPI <1 indicates over cost, SPI <1 indicates behind scheduled.
Status Report (Jul-16)
Forecast EAC (July 16)
EAC: $452,130
The final project projected cost forecast is
$452,130 versus $ 240,256 originally
planned.
To Complete Performance Index TCPI:
TCPI: 1.05
6
3
Crashing Activity
Activity 52, 53, 93, 97 are crashed. It cost
$7,400 and Project duration will be reduce
by 8days.
3
Control Chart
Period
Status
Report Task Name
Finish
Actual Finish Baseline
Start
Variance
Finish
Variance
Total
Variance
1 March 1st BPM Automation Mon 11/28/16 Mon 11/28/16 0 days 0 days 0
2 July 1st BPM Automation Thu 12/8/16 Mon 11/28/16 0 days 8 days -8
3 Oct 1st BPM Automation Mon 11/28/16 Thu 12/8/16 0 days -8 days 8
-20020
1 2 3
Variance
Time Period
3
Conclusion
 More time and cost should be spend in Planning Phase to avoid problems in later
stages
 Resource allocation might need to be reconsidered in Planning Phase
 Through out project life cycle objectives should always be at the center of attention
and decision making
 Once project starts, a dedicated team has to monitor project performance for cost and
schedule evaluation periodically - If required revise time phased schedule
 Based on status report and performance indices, actions like crashing or scope creep
have to be taken into consideration
Thank you for your attention!
Questions?
7

Weitere ähnliche Inhalte

Ähnlich wie projectmanagement-WNS

OpenText Live: Modeling your business processes to new ways of working
OpenText Live: Modeling your business processes to new ways of workingOpenText Live: Modeling your business processes to new ways of working
OpenText Live: Modeling your business processes to new ways of workingOpenText Portfolio
 
VMWorld 2009 - Gebelin Getting To Yes!
VMWorld 2009 -  Gebelin Getting To Yes!VMWorld 2009 -  Gebelin Getting To Yes!
VMWorld 2009 - Gebelin Getting To Yes!cgebelin
 
Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control CostAnand Bobade
 
Effective Cost Measurement through DMAIC.
Effective Cost Measurement through DMAIC.Effective Cost Measurement through DMAIC.
Effective Cost Measurement through DMAIC.Kaustav Lahiri
 
Nagios Conference 2014 - Jose Marroquin - How Revenue Increased After Impleme...
Nagios Conference 2014 - Jose Marroquin - How Revenue Increased After Impleme...Nagios Conference 2014 - Jose Marroquin - How Revenue Increased After Impleme...
Nagios Conference 2014 - Jose Marroquin - How Revenue Increased After Impleme...Nagios
 
desai_wharton2002
desai_wharton2002desai_wharton2002
desai_wharton2002Vijay Desai
 
Board Deck Template for SaaS Companies
 Board Deck Template for SaaS Companies Board Deck Template for SaaS Companies
Board Deck Template for SaaS Companiesserenacapital
 
PF_EarnedValuePresentation.ppt
PF_EarnedValuePresentation.pptPF_EarnedValuePresentation.ppt
PF_EarnedValuePresentation.pptyogeshagrawal84
 
EARNED VALUE MANAGEMENT ANALYS 1.ppt
EARNED VALUE MANAGEMENT ANALYS 1.pptEARNED VALUE MANAGEMENT ANALYS 1.ppt
EARNED VALUE MANAGEMENT ANALYS 1.pptBetshaTizazu1
 
agilefinancenarrated-190414134302.pptx
agilefinancenarrated-190414134302.pptxagilefinancenarrated-190414134302.pptx
agilefinancenarrated-190414134302.pptxssuser1ecf25
 
Maximizing the Impact of Your Projects
Maximizing the Impact of Your ProjectsMaximizing the Impact of Your Projects
Maximizing the Impact of Your ProjectsBrandon Olson
 
Encoursa Webinar: Developing Your First Cost and Price Proposal
Encoursa Webinar: Developing Your First Cost and Price ProposalEncoursa Webinar: Developing Your First Cost and Price Proposal
Encoursa Webinar: Developing Your First Cost and Price ProposalRobert E Jones
 
Vocera investordeck web january 2018
Vocera investordeck  web january 2018Vocera investordeck  web january 2018
Vocera investordeck web january 2018vocera2016ir
 
Financial Modeling for HCI/Cloud
Financial Modeling for HCI/CloudFinancial Modeling for HCI/Cloud
Financial Modeling for HCI/CloudNEXTtour
 
Making driver-based planning and budgeting work
Making driver-based planning and budgeting workMaking driver-based planning and budgeting work
Making driver-based planning and budgeting workAnaplan
 
Project Performance Measurement Earned Value A Starter
Project Performance Measurement   Earned Value   A StarterProject Performance Measurement   Earned Value   A Starter
Project Performance Measurement Earned Value A StarterSimonRobertson
 
Amazon case presentation
Amazon case presentation Amazon case presentation
Amazon case presentation Samuel Lee
 
How to design RPA performance metrics
How to design RPA performance metricsHow to design RPA performance metrics
How to design RPA performance metricsARJUN S MEDA
 

Ähnlich wie projectmanagement-WNS (20)

OpenText Live: Modeling your business processes to new ways of working
OpenText Live: Modeling your business processes to new ways of workingOpenText Live: Modeling your business processes to new ways of working
OpenText Live: Modeling your business processes to new ways of working
 
VMWorld 2009 - Gebelin Getting To Yes!
VMWorld 2009 -  Gebelin Getting To Yes!VMWorld 2009 -  Gebelin Getting To Yes!
VMWorld 2009 - Gebelin Getting To Yes!
 
Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control Cost
 
Effective Cost Measurement through DMAIC.
Effective Cost Measurement through DMAIC.Effective Cost Measurement through DMAIC.
Effective Cost Measurement through DMAIC.
 
Project initiation
Project initiationProject initiation
Project initiation
 
ROI of Machine Learning In IoT
ROI of Machine Learning In IoTROI of Machine Learning In IoT
ROI of Machine Learning In IoT
 
Nagios Conference 2014 - Jose Marroquin - How Revenue Increased After Impleme...
Nagios Conference 2014 - Jose Marroquin - How Revenue Increased After Impleme...Nagios Conference 2014 - Jose Marroquin - How Revenue Increased After Impleme...
Nagios Conference 2014 - Jose Marroquin - How Revenue Increased After Impleme...
 
desai_wharton2002
desai_wharton2002desai_wharton2002
desai_wharton2002
 
Board Deck Template for SaaS Companies
 Board Deck Template for SaaS Companies Board Deck Template for SaaS Companies
Board Deck Template for SaaS Companies
 
PF_EarnedValuePresentation.ppt
PF_EarnedValuePresentation.pptPF_EarnedValuePresentation.ppt
PF_EarnedValuePresentation.ppt
 
EARNED VALUE MANAGEMENT ANALYS 1.ppt
EARNED VALUE MANAGEMENT ANALYS 1.pptEARNED VALUE MANAGEMENT ANALYS 1.ppt
EARNED VALUE MANAGEMENT ANALYS 1.ppt
 
agilefinancenarrated-190414134302.pptx
agilefinancenarrated-190414134302.pptxagilefinancenarrated-190414134302.pptx
agilefinancenarrated-190414134302.pptx
 
Maximizing the Impact of Your Projects
Maximizing the Impact of Your ProjectsMaximizing the Impact of Your Projects
Maximizing the Impact of Your Projects
 
Encoursa Webinar: Developing Your First Cost and Price Proposal
Encoursa Webinar: Developing Your First Cost and Price ProposalEncoursa Webinar: Developing Your First Cost and Price Proposal
Encoursa Webinar: Developing Your First Cost and Price Proposal
 
Vocera investordeck web january 2018
Vocera investordeck  web january 2018Vocera investordeck  web january 2018
Vocera investordeck web january 2018
 
Financial Modeling for HCI/Cloud
Financial Modeling for HCI/CloudFinancial Modeling for HCI/Cloud
Financial Modeling for HCI/Cloud
 
Making driver-based planning and budgeting work
Making driver-based planning and budgeting workMaking driver-based planning and budgeting work
Making driver-based planning and budgeting work
 
Project Performance Measurement Earned Value A Starter
Project Performance Measurement   Earned Value   A StarterProject Performance Measurement   Earned Value   A Starter
Project Performance Measurement Earned Value A Starter
 
Amazon case presentation
Amazon case presentation Amazon case presentation
Amazon case presentation
 
How to design RPA performance metrics
How to design RPA performance metricsHow to design RPA performance metrics
How to design RPA performance metrics
 

projectmanagement-WNS

  • 1. By Gerrit Maess | Lovelyn George| Ramon Rios R | Zainab Sayyed Project: Automation of Business Process Management System Service Provider Client
  • 2. WNS Introduction • Business process management company (Software and Web Services) • Headquarter is in Mumbai, India • The company serves over 200 Fortune 500 companies worldwide 1
  • 3. 2 Financial Models – Net Present Value and Payback Method Selected Methods
  • 4. 2 Non-Financial Models - Multi Weighted Scoring Matrix Selected Methods
  • 5. 2 Project Portfolio Matrix Selected Methods Net Present Value
  • 6. Why WNS Selected BPM Automation (Global Star Travels Project)?  Strategic Project with the highest Net Present Value (NPV) of $196,338  We can recover the investment in 10.9 months  Having the highest weight score of 72  This project is technological breakthrough with highest commercial payoff 3
  • 7. Defining  Planning  Executing  Delivering 2 Project Life Cycle
  • 9. Defining Project Scope Objective: To design an automated Business Process Management System using MS SQL Server and BI system within `12 months at a cost not to exceed $700,000. Priority Matrix: 4
  • 10. Specification Hardware:  Setup Database server  Setup Web Server  System down time < 4 hours Software:  BI system (middle and top management)  Web application system 4 Task Deliverables:  BI reports (Analytics tools) for middle and top management  Backend database system  Interfaces / Middleware compatible with existing front end solutions  Technical reference document Project Scope Checklist
  • 11. 5 Work Break Down Structure
  • 12. 3 Integration of WBS and OBS Cost Account The intersection of WP- Hardware Service and Organization IT department creates a cost account. By rolling up Hardware Service and Software License WP System (deliverable) cost is calculated.
  • 14. Bottom Up: Support Cost Est 6 Top-Down: Function Point Contract Bid Time and Cost Estimations Contract Bid Summary Costs Total Direct Cost $540,000.00 G&A overhead (10%) $54,000.00 Total Costs $594,000.00 Profit(17.5%) $103,950.00 Total Bid $697,950.00
  • 15. PERT 6 Time and Cost Estimations
  • 18. Resource Allocation Before Levelling: 230 days 6 After Leveling: 237 days
  • 21. Earned Value Chart 6 Indexes Period $0.00 $50,000.00 $100,000.00 $150,000.00 $200,000.00 $250,000.00 $300,000.00 Jan'16 Feb'16 Mar'16 Apr'16 May'16 Jun'16 Jul'16 Aug'16 Sep'16 Oct'16 Nov'16 Dec'16 ACWP BCWP BCWS Actual Cost Linear (ACWP) 0 0.2 0.4 0.6 0.8 1 1.2 Jan'16 Feb'16 Mar'16 Apr'16 May'16 Jun'16 Jul'16 Aug'16 Sep'16 Oct'16 Nov'16 Dec'16 SPI CPI CPI <1 indicates over cost, SPI <1 indicates behind scheduled. Status Report (Jul-16)
  • 22. Forecast EAC (July 16) EAC: $452,130 The final project projected cost forecast is $452,130 versus $ 240,256 originally planned. To Complete Performance Index TCPI: TCPI: 1.05 6
  • 23. 3 Crashing Activity Activity 52, 53, 93, 97 are crashed. It cost $7,400 and Project duration will be reduce by 8days.
  • 24. 3 Control Chart Period Status Report Task Name Finish Actual Finish Baseline Start Variance Finish Variance Total Variance 1 March 1st BPM Automation Mon 11/28/16 Mon 11/28/16 0 days 0 days 0 2 July 1st BPM Automation Thu 12/8/16 Mon 11/28/16 0 days 8 days -8 3 Oct 1st BPM Automation Mon 11/28/16 Thu 12/8/16 0 days -8 days 8 -20020 1 2 3 Variance Time Period
  • 25. 3 Conclusion  More time and cost should be spend in Planning Phase to avoid problems in later stages  Resource allocation might need to be reconsidered in Planning Phase  Through out project life cycle objectives should always be at the center of attention and decision making  Once project starts, a dedicated team has to monitor project performance for cost and schedule evaluation periodically - If required revise time phased schedule  Based on status report and performance indices, actions like crashing or scope creep have to be taken into consideration
  • 26. Thank you for your attention! Questions? 7