SlideShare ist ein Scribd-Unternehmen logo
1 von 24
Report: Final Account & The Significance and Implications
of the Omission of Works
 Procedure of Final Account
 Adjustment of the essential elements in preparation of
Final Account
 In the Bills of Quantities
 Not allowed as Provisional Sums or Prime Cost Sums
Content Page no
1. Introduction 1
2. Definitions 2
3. Procedure of Final Account 3-4
4. Adjustmentof the essential elementsinpreparationof the Final Account 5-9
5. ComparisonbetweenProvisional SumsandPrime CostSums 10
6. Implicationsof Omissionof Provisional Sums
6.1 From the standpointof a Client 11-12
6.2 From the standpointof a Contractor 13-14
7. Conclusion 15
1. Introduction
This report is briefly explaining the adjustment of the essential elements in
preparation of the Final Account. However, this report is prepared to identify the
significance and implications if some works are entirely left out in the Bills of
Quantities and also not picked out as provisional sums or P.C sums.
The conditions of the situation mentioned includes works like structural steel roof
trusses in which are shown on the drawings but not sufficiently designed for
measurement of quantities.
This report will cover the definition, procedure and adjustment essential element in
preparation of the Final Account. Besides that, it also defines and comparison of the
provisional and P.C sums relating to the situation presumed and later discuss on the
significance and implications from two points of view, consisting of the client and the
contractor. Lastly is the conclusion.
2. Definitions
Final Account
According to SMM2 (Clause 30.10) defines the Contractor shall send all document
within 6 Months after the Practical Completion of the Work for preparing the Final
Account.
Provisional Sums
According to SMM2 (Clause A.8.1.a.) defines provisional sum as a sum provided for
work or for costs which cannot entirely be foreseen, defined or detailed at the time the
tender documents are issued.
P.C. Sums
According to SMM2 (Clause A.8.1.b.) defines prime cost sums as a sum provided for
works or services to be executed by a nominated sub-contractor, a government or a
statutory authority or for materials or goods to be obtained from a nominated supplier.
Such sum shall be deemed to be exclusive of any profits required and/ or attendance to
be provided by the main contractor and provision shall be made for the addition thereof
where applicable.
3. Procedure of final account
Generally, Article 7 (ab) of PAM Contract 2006 defines Final Account as the
document showing the adjustment of the Contract Sum issued under Clause 30.10.
Clause 30.10 stated the Contractor shall send all document within 6 Months after the
Practical Completion of the Work for preparing the Final Account. The Final Account
must be completed within 6 Months from receipt of all the document from the
Contractor. All document including all documents relating to the accounts of
Nominated Sub-Contractors and Nominated Suppliers. Such document shall contain all
the latest construction drawings and details, details of all quantities, rates and prices
and any adjustment of the Contract Sum and additional payment or compensation
claimed by the Contractor under the Contract together with any explanation and
supporting vouchers, documents and calculations. If there is any delay by the
Contractor, the period for the completion of Final Account shall be adjusted. In the
event, the Contractor fail to submit all documents the Architect or Quantity Survey shall
nevertheless complete and issue the same based on the information available within the
Period to complete the Final Account stated in the Appendix. When the Final Account
is completed, a copy would need to be sent to both the Employer and the Contractor to
obtain their agreement.
Clause 30.10(a) Sometimes, they may not respond with any
agreement/disagreement to the Final account. In that event, this clause expressly
provides that if both the Employer and Contractor fail to notify any dispute on the Final
Account within 3 Months from the data of receipt of Account, the Final Account shall
be conclusive and deemed agreed by the parties.
Clause 30.10(b) If either party disputes the Final Account, the party disputing
the Final Account shall by written notice to the other party (with copies to the Architect
and Quantity Surveyor) set out any disagreement complete with particulars within three
(3) Months of the date of receipt of the Final Account from the Architect or Quantity
Surveyor.
The Architect or Quantity Surveyor within three (3) Months from the date of receipt
of the grounds of dispute shall either amend or not amend the Final Account. Any party
disagreeing with the amended Final Account or decision not to amend the Final
Account shall refer the dispute to arbitration under Clause 34.0 with three (3) Months
from the date of receipt of the amended Final Account or decision not to amend the
Final Account. Failure to refer the dispute to arbitration within the stipulated time, the
Final Account or amended Final Account shall deem to be conclusive and agreed by
the parties. To be more precise, it is a financial document indicating the final value of
the works executed by the Contractor and his NSCs and NSs.
4. Adjustment of the essential elements in preparation of the Final Account
A well prepared Final account is able to establish the final construction cost of
project. There are a few essential elements which constitute a complete Final Account
and the relevant elements are as per stated below:
• Variation works (clause 11.6)
• Remeasurement of Provisional Quantities (clause 11.6 (f))
• Omission of Prime cost and Provisional sum (clause 30.11 (c))
• Adding-back of NSC’s and NS’s Final Accounts (clause 30.11 (c))
• Adjustment of Profit and Attendance (clause 30.11 (c))
• Adjustment of Provisional Sum based on actual expended and omitted if not
expended (clause 30.11 (d))
• Additional Expenses Claims (clause 11.7)
• Loss and Expenses Claims (clause 24.4)
The first essential element in preparing final account is variation works under
clause 11.6. The valuation of variation and work executed by the contractor for which
a provisional quantity is included in the contract and the expenditure of provisional sum
shall be based on 11.6(a), (b), (c), (d), (e) & (f). Clause 11.6(a) stated the rates and
prices in the Contract Documents shall be the basis of valuation where the Variation
work is similar in character to, and is executed under similar conditions set out in the
Contract Documents, and where there is no significant change to the quantity of work
indicated in the Contract Bill.
Clause 11.6(b) the rates and prices in the Contract Documents shall be the basis
of valuation, and shall include a fair adjustment in the rates to take into account same
cost differences where the Variation work is of a similar character to, but is not executed
under similar conditions set out in the Contract Documents. Similarly, the rates and
prices shall also be appropriately adjusted where the Variation work is of a similar
character and is executed under similar conditions, but there is a significant change in
the quantity of work as compared to the quantity indicated in the Contract Bill.
Clause 11.6(c) stated the Contractor shall be entitled to a fair valuation which
will not give the Contractor more than his actual cost, reasonably and necessarily
incurred, plus similar allowance for overhead and profit. Clause 11.6(d) stated the
Contractor can applicable ‘where work cannot be properly measured and valued.’ The
Contractor has to comply with the procedure when recording the day works, and should
have it verified by the Site Staff and progressively sent to the Architect and Consultant.
Clause 11.6(e) stated that the rate and prices in the Contract Documents shall
determine the valuation of items omitted. If omissions substantially vary the conditions
under which any remaining items of work are carried out, the price of such remaining
items shall be valued under Clause 11.6(a), (b) or (c). Clause 11.6(f) if the Works have
been measured on a Provisional basis, the Works shall be re-measured based on the
actual quantities executed, and the rates and price in the Contract Documents shall be
the basis to arrive at a Final Account.
This shall exclude the work for which a tender had been accepted under clause
27.14 – Contractor permitted to tender for P.C Sums. For example, variation may occur
in situation such as the architect gives instruction to change the floor layout. If there is
no provision for variation, the employer may need to get the agreement of contractor
and the contractor may negotiate for higher price. This variation clause is to allow
changes to be made and subsequently adjust or amend the contract sum. Besides, the
valuation rules can be applied where the works are carried out by the contractor for
which the provisional quantities and provisional sum had been included in the contract
bills.
Besides that, remeasurement of provisional quantities is also an important
element according to clause 11.6(f). In respect of Provisional Quantity, the quantities
stated in the Contract Document shall be re-measured by the Quantity Surveyor based
on the actual quantities executed. The provisional quantities are estimated quantities
only, for instance the quantities for excavation works, piling works and infrastructure.
It is not possible to know the actual quantities for the works mentioned at the early stage
and thus, the quantities shall be remeasured by Quantity Surveyor in-charged based on
the actual Works that completed. The quantities are subjected to changes but the rates
priced in the Contract Documents will remain constant.
In addition, Prime Cost sums and Provisional Sums are also part of the essential
elements in Final Account. Basically, Prime Cost sums are the sum of the specialist
works carried out by the sub-contractor which normally inclusive of profits and
attendance whereas Provisional Sums are the sum of work done that can be identified
but with no detailed drawing provided and thus, the sum cannot be itemized in bills of
quantities (BQ).
The question worth to be raised up is that, why is there a need to allow
provisional sum in the BQ since adjustment is to be made at the final stage? Let’s take
guard house as an example and the possible reasons are as stated below:
• For instance, contractually, a guard house is to be built but with very limited details
of drawings. In this case, the provisional sums need to be added into BQ so that
client will be aware of the budget of the project as it allows an approximate
contract amount for the purpose of cost control.
• Contractor needs to include the provisional sum works in order to plan his work
program and to finish the works on time. It will easily cause disputes if
provisional sum is not added into the contract document. In this case, contractor
can easily claim for extension of time (EOT) as architect will have to issue
Architect’s Instruction for variation works which are against the requirements
as per agreed in contract document, for instance, guard house.
Prime cost sums and provisional sums with related profit shall be omitted
from the final account based on clause 30.11(c). This is because the prime cost sums
and provisional sums are just estimated sum and act as estimated allowance but both
prime cost sums and provisional sums are subjected to changes. Since the prime cost
sums and provisional sums with related profit are omitted from the final account, the
nominated sub-contractors’ and nominated suppliers’ final account shall be added
back. Every Nominated Sub-Contractors and Nominated Suppliers need submit the
Final Account together with the pro-rata amount for profit. In short, the adjustment is
made after completion of works and final cost is ascertained.
Provisional sums and prime cost sums that are not being used shall be deducted
out from the contract sum. The profit shall be adjusted basedon the amount of final
account whereas for attendance shall be remain unchanged. This is because the
attendance is a fixed amount or lump sum amount and it is provided for supervision
works and hence, it is not subjected to changes. However, for profit it is based on a
certain amount of percentage, for instance 2% of the total cost of project. The reason of
charging of profits and attendance by main contractor is because the main contractor is
required to provide the general lighting, general hoisting material and general power
and many more for sub-contractors to work.
Furthermore, the other essential element of Final Account is adjustment of
Provisional Sum based on actual expended and omitted if not expended stated
under clause 30.11(d) in PAM Contract 2006. Adjustment of Provisional Sum is
basically for the things which did not have any design, details, specification, but needed
to construct within the project. The Provisional Sum needed to adjust during the Final
Account because there is no accurate sum that Contractor place at the Contract
Document. Basically it means any adjustment of Provisional Sum will be measured
based on all the actual expended of Provisional Sum by the Contractor. If some
Provisional Sum is not expended, such amount shall be deemed to omit from the
contract bill during the Final Account.
Next, the Additional Expenses claims shall also be considered in the Final
Account which is stated under clause 11.7 in PAM Contract 2006. The objective of this
clause is to enable the Contractor to be reimbursed as part of the cost of variation, for
the additional expenses he has incurred carrying out the Variation, and for which he
would not be compensated under Clause 11.6. However, the Contractor is allowed to
claim for the additional expenses in accordance to the clause 11.7 (a) provided the
contractor shall give written notice to the Architect of his intention to claim for such
additional expenses and the contractor shall send to the Architect and QS complete
particulars of his claim clause 11.7 (b). Eventually, the additional expenses claim will
be added into the Final Account. The final essential element of Final Account is Loss
and Expense claims which stated under clause 24.4 in PAM Contract 2006. The clause
explains that any Loss and Expense incurred by the Contractor which complying with
Clause 24.1, the Architect and Quantity Surveyor shall make certain and include such
amount of loss and expenses into the Final Account. The words “shall ascertain” stated
in the clause basically means that the Architect or the Quantity Surveyor must access
the claim based on particulars and calculations submitted by the Contractor but not
merely rely on a general assessment before including the amount into the final account.
Any claim under common law is outside the jurisdiction of the Architect and Quantity
Surveyor, and the Contractor has to resolve this with the Employer.
However, there are 3 elements which shall be excluded from Final account
based on clauses 30.11(e) to (g). The first element to be excluded is any liquidated
damages imposed by the Employer as stated in the clause 30.11(e). Secondly, set-off
by the Employer shall also deem to exclude from final account under the clause 30.11(f).
Lastly, Interest payable by either Employer or Contractor shall also be excluded from
Final Account under the clause 30.11(g). The main concern is that, why are the 3 items
mentioned above are to be solved separately between employer and contractor? Why
are the 3 items excluded from Final Account? This is due to the following reasons:
• Architects are certifiers and they certify work done only and not the parties to the
Contract. They need to be fair and independent and it is not their duties to
determine the party who is in dispute and hence, these 3 items are to be excluded
from the Final Account.
• Disputes may easily arise from either party with such elements being included in the
Final account, causing the final account hardly to be completed at the end of the
day. The main intention is not to delay the timely conclusion of the Final
Contract and it simply means without a final account, the Architect and QS
cannot be discharged.
5. Comparison between Provisional Sums and Prime Cost Sums
Basically, as defined in SMM2, Provisional Sums is of the supply of materials with
profits and attendance also labour cost whereas the Prime Cost Sums only consists of
the supply of the materials.
Common examples of Provisional Sums consist of landscaping, piling, earthworks
or scaffolding. Common examples of Prime Cost Sums are supply of cook tops and
ovens, sanitary wares, furniture or floor coverings.
In this case, the structural steel roof trusses are provisional sum as the works will
include the supply of the steel roof trusses and the installation which takes into account
the profits and attendance. Other than that, the situation clearly shown that drawings
are available to identify sum of works to be carried out but the later states that no details
for measurement shows that the sum cannot be itemized in the Bills of Quantities, hence
allowance of Provisional Sums should be given.
6. Implications of Omission of Provisional Sums
Having the condition as below,
(a) The works omitted is the structural steel roof trusses
(b) Shown on drawing but not sufficiently designed for measurement of quantities
(c) Works entirely left out in Bills of Quantities
(d) Not allowed as Provisional or Prime Cost Sums
(e) Using the PAM Contract 2006(with quantities)
(f) Variable assumptions made accordingly
6.1 From the standpoint of a client
(f) At pre-tender stage
Should the quantity surveyor omitted the steel roof trusses, which is
supposed to be an allowance as Provisional Sum, this means that the Contract
Sum excludes the works of the structural steel roof trusses.
When the works are not included in the estimates, this would affect the
cost control process due to omission of works and the budget established will
not be accurate. The client will rely on the budget estimates to derive the
approximate contract sum. Client might tend to spend more on other works such
as specifications relating to the quality of the building if the estimates shows a
budget lower than anticipated. This would cause disputes arising in the future
when the actual contract sum is way too high over the clients’ budget.
(f) After contract awarded
Clause 11.1(a) defines the term “Variation” as the alteration or
modification of the design, quality or quantity of the Works including the
addition, omission or substitution of any work. In this case, the Variation will
be regarding the omission of the structural steel roof trusses.
Upon awarding of Contract, provided if the parties are still unaware of
this omission, the works would be left out. When discovered, this means that
the client has the options whether to enter a separate contract which only
consists of the structural works of steel roof trusses or the client would have to
treat this part of omitted work as variation according to clause 11.2 in PAM
Contract 2006 that the Architect may issue an AI ordering or sanctioning the
variation in order for the contractor to carry out all the variations with due
diligence and expedition.
If the client goes for option 1, it might be time-consuming and the
overall cost will be higher due to the lengthy tender process and sudden
involvement of works. However, option 2 is also not as good as 1 due to the
instruction of AI to variation may give the contractor a ground to claim for EOT
which is in accordance with clause 23.8(g) and meaning that the client would
have lesser imposed liquidated damages.
6.2 From the standpoint of a contractor
(f) At tender stage
If the contractor found out the part of structural steel roof has been
omitted in the tender document, the Contractor may inform the quantity
surveyor and upon confirmation of the omission, there might be a revised tender
or tender amendment. This would be better as it prevents disputes arising in the
future.
(f) Provided if the contractor is to carry out the works due to AI of variation clause
11.2
The omission of provisional sum would affect the contractor’s master
work programme which would also affects the completion date of the project.
The contractor, unaware of the works of provisional sum at the early stage
would have to submit a new master work programme and this would cost more
to the contractor if he had insufficient plants and machinery or even experience
to carry out the works.
Insufficient experience in specified works (here is the supply and
installation of steel roof trusses) may cost higher due to unfamiliarity with
market prices and suppliers causing higher material costs. Moreover, contractor
would have to bear the defects within the Defects Liability Period which would
cost more to a contractor to rectify the defects should the works carried out
contains defect.
(f) Provide the contractor unknowingly did the part of works
If the contractor is to make a contractual claim, Clause 11.7 under
variations, provisional and prime cost sums will entitle the contractor to claim
additional expenses other than provision in clause 11.6 provided the contractor
has meet the procedural condition stated in the contract. The contractor has to
give a written notice to the Architect regarding his intention to claim for such
additional expenses together with an initial estimate of his claim duly supported
with all necessary calculations within 28 Days from the date of AI or CAI which
is a condition precedent for his entitlement to claim. Within 28 Days of
completing such variation, the contractor has to send his actual claim together
with complete particulars and all necessary calculations to substantiate his
claims. Should he failed to do so within the time stated or within the period
agreed by the Architect, the contractor has deemed to waived his rights to any
additional expenses.
According to Clause 11.9, as soon as the Architect ascertained the
amount claimed by contractor under Clause 11.7, the amount will be added to
the Contract Sum.
However, if the contractor unknowingly supplied and installed the steel
roof trusses which are not included in the Contract and he did not follow the
procedural contractual claim as per Clause 11.7, this might cause the contractor
to seek for extra-contractual claim where the claim is made under quantum merit.
This is a claim where a reasonable sum is claimed for work is done where the
contract is silence on how the work is to be paid.
7. Conclusion
There are essential elements needed to adjust during the Final Account.
However, owing the presence of provisional sums due to the error made by the
quantity surveyor would imply consequences to both the client and contractor.
Moreover, the quantity surveying consultant firm would also suffer loss in both
monetary and accountability. This report mainly focuses on implications to the
client and the contractor involving the project.
DECLARATION OF AGREEMENT
We, the undersigned, hereby confirmed our agreement to the attached Final Account
as follows:
1. That the Final Account is correct and is in accordance with the Conditions of
Contract.
2. That the Final Contract Value of RM 31,060,000.00 is correct.
3. That we have no further claims whatsoever against each other.
Employer Contractor
Date: Date:
Witness Witness
Date: Date:
Question 3(a):
Relocation of an already installed timber door including sealing up the wall
opening. Agreed at the site meeting for Contractor to claim based on Dayworks
for labour, material and plant.
Answer:
Diagram 1.0: Items that should be priced based on daywork rates
PAM Contract 2006 (With Quantities), Clause 11.6(d) stated that, where work cannot
be properly measured and valued in accordance with 11.6(a), (b) or (c), the Contractor
shall be allowed to claim based on daywork rates in the Contract Documents for labour,
material and plant as agreed at the site meeting. Based on this scenario, the items that
should be priced based on daywork rates are the removal of the timber door, sealing up
of the door opening and making of a new opening for the timber door.
For the removal of the timber door, making of a new opening for the timber door and
installation of the timber door, the labour rates shall be priced in accordance with the
general labour rate provided in the schedule of daywork rates. While for the sealing up
of the door opening, the labour rates shall be based on bricklayer, plasterer and painter.
Items that should
be priced based on
daywork rates
Removal of the
timber door
Labour:
General labour
Making of a new
opening for the
timber door
Sealing up of the
dooropening
Labour:
Bricklayer,
plasterer and
painter
Materials:
bricks, sand,
cement and paint
(refer to the
breakdown rate
provided in BQ)
Apart from that, QS shall refer to the breakdown rate provided in Bill of Quantities as
a basis to derive the new rates for the material used in sealing up the door opening such
as bricks, sand, cement and paint. In this case, there is no payment for plant due to no
plant is needed to execute the variation works.
Contractor should prepare a daywork record in order to claim for daywork. The
daywork record shall include the time spent daily upon the variation works, the
worker’s details, scope of works, materials used, transportation as well as other
necessary evidence. The daywork record shall be signed by the client’s representative
or Site Agent and verified by the Site Staff for validation purpose. Then, the document
shall be delivered to the Architect and Quantity Surveyor at weekly intervals with the
final records delivered not later than fourteen (14) Days after the work has been
completed.
Question 3(b)
Omission of the need to provide computer equipment in the Preliminaries section
but item was left unpriced, i.e. BQ item was left black in the rate/amount column
in the contract document.
Answer:
Computer equipment in the Preliminaries is left unpriced, it shall be deemed that the
Main Contractor has included such item in his tender with a Lump Sum price. Therefore,
the Consultant Quantity Surveyor shall identify the price of the computer equipment;
and the Employer has the rights to omit the price of the computer equipment as stated
in Architect’s Instruction if necessary.
According to PAM Contract 2006, in Clause 11.6, the valuation of Variations and work
executed by the Contractor for which a Provisional Quantity is included in the Contract
and the expenditure of Provisional Sums (other than for work for which a tender had
been accepted under Clause 27.14) shall be made in accordance with the following rules:
Clause 11.6(c), where work is not of a similar character to work as set out in the
Contract Documents, the valuation shall be priced at current fair market rates and prices
are to be determined by the Quantity Surveyor. Therefore, in this scenario, the
Consultant Quantity Surveyor has the rights to omit the price of computer equipment
based on fair market rate. Besides that, the Consultant Quantity Surveyor may obtain
the rate of the computer equipment from previous contract documents of a similar
project.
Question 3(d)
Mistake was made in rate for 50mm thick concrete blinding is RM 10 per m3.
Item was not rationalized during contract documentation. However, original
quantity in BQ is 100 m3 but re-measured quantity is 2,000 m3.
Answer:
According to case law Henry Boot Construction v Alstom Combined Cycles Ltd [2000]
BLR 247, the Court of Appeal found that the relevant variations had to be priced using
the contract bill rate, notwithstanding the apparent mistake which meant the Contractor
was likely to receive a windfall profit. In another manner, it also meant that if the
contractor priced a lower rate, he most likely would receive a windfall lost.
PAM Contract 2006 (with Quantities) Clause 11.6(b) had stated that “where work is of
a similar character to work as set out in the Contract Documents but is not executed
under similar conditions or is executed under similar conditions but there is a significant
change in the quantity of work carried out, the rates and prices in the Contract
Documents shall be the basis for determining the valuation which shall include a fair
adjustment in the rates to take into account such difference”, therefore, the contractor
can claim for the re-measured quantity of element with a fair adjustment in rates that
stated in the Contract Documents.
Based on the above scenario, the contractor will faced a windfall lost due to the
irrationalized rates priced during the contract documentation, this is because the final
account rates will follow the rates that initially priced in the agreed contract document
between two parties. As for the re-measurement quantity, contractor have the rights to
claim for a fair adjusted rates of the elements due to the mistakes done by the consultant
team in preparing for drawings and taking-off.
By following the price of RM10 per m3 for the 50mm think concrete blinding using the
initial quantity of 100m3, the total cost will be RM 1,000, whereas in the new quantity
of 2,000 per m3, the new total cost will be RM 20,000, and the different is RM 19,000.
Consequently, the contractor can only claim an additional of RM 19,000 for the total
cost of the 50mm thick concrete blinding.
Project: ApartmentProject Appendix 1
Employer:Eddie SdnBhd
Contractor : TaylorsBuilderSdnBhd
FINALACCOUNT
RM RM
1.0 Original ContractSum 29,160,000.00
2.0 Less: P.C & Provisional Sums 4,660,000.00
Total Builder'sWorks 24,500,000.00
3.0 Add: Variationworks(V.O.Nos1-4)
Total
Additions 2,050,000.00
Total
Omissions 1,000,000.00
NettAdditions 1,050,000.00 1,050,000.00
4.0 Add:
NSCs'final
account
LiftServices 1,500,000.00
AirConditioningServices 1,200,000.00
Electrical
Services 2,300,000.00
5,000,000.00 5,000,000.00
5.0 Constractual Claims:
5.1
Additional
Expenses 10,000.00
5.2
Loss and
Expense 500,000.00
510,000.00 510,000.00
FINALCONTRACTVALUE 31,060,000.00
Project: ApartmentProject Appendix 2
Employer:Eddie SdnBhd
Contractor : TaylorsBuilderSdnBhd
STATEMENT OF FINALACCOUNT
Final ContractValue 31,060,000.00
Deduct: Amountpreviouslycertified 29,160,000.00
BALANCEDUE TO CONTRACTOR 1,900,000.00

Weitere ähnliche Inhalte

Was ist angesagt?

The architect as contract administrator a legal perspective - presentation ...
The architect as contract administrator   a legal perspective - presentation ...The architect as contract administrator   a legal perspective - presentation ...
The architect as contract administrator a legal perspective - presentation ...Zainab Zainordin
 
Smm2 second edition
Smm2 second editionSmm2 second edition
Smm2 second editionBt Lee
 
Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in MalaysiaDayat Mohamad
 
Professional practice 1 report
Professional practice 1 reportProfessional practice 1 report
Professional practice 1 reportNgo Jia Haur
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2ahmong4
 
Professional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentProfessional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentHaziq1511
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017DarrenTofu
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System ashleyyeap
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006Melvin Lim
 
ECA Workshop - Brief
ECA Workshop - BriefECA Workshop - Brief
ECA Workshop - BriefKai Yun Pang
 
PP2 - Assignment
PP2 - AssignmentPP2 - Assignment
PP2 - AssignmentQuo Ming
 
Assignment - Final Account
Assignment - Final AccountAssignment - Final Account
Assignment - Final AccountKai Yun Pang
 
Provisional sum prime cost sum
Provisional sum  prime cost sumProvisional sum  prime cost sum
Provisional sum prime cost sumEst
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1Sow Wei Henn
 
Measurement 4 Tender Document
Measurement 4 Tender Document Measurement 4 Tender Document
Measurement 4 Tender Document xingxin_GOh
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1Lee Pei Gie
 

Was ist angesagt? (20)

The architect as contract administrator a legal perspective - presentation ...
The architect as contract administrator   a legal perspective - presentation ...The architect as contract administrator   a legal perspective - presentation ...
The architect as contract administrator a legal perspective - presentation ...
 
Smm2 second edition
Smm2 second editionSmm2 second edition
Smm2 second edition
 
Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in Malaysia
 
Site Possession
Site PossessionSite Possession
Site Possession
 
Professional practice 1 report
Professional practice 1 reportProfessional practice 1 report
Professional practice 1 report
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
Professional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentProfessional Practice 1 Group Assignment
Professional Practice 1 Group Assignment
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
 
ECA Workshop - Brief
ECA Workshop - BriefECA Workshop - Brief
ECA Workshop - Brief
 
PP2 - Assignment
PP2 - AssignmentPP2 - Assignment
PP2 - Assignment
 
Pp2 final report
Pp2 final reportPp2 final report
Pp2 final report
 
Assignment - Final Account
Assignment - Final AccountAssignment - Final Account
Assignment - Final Account
 
Provisional sum prime cost sum
Provisional sum  prime cost sumProvisional sum  prime cost sum
Provisional sum prime cost sum
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 
Cl compilation
Cl compilationCl compilation
Cl compilation
 
Defects liability
Defects liabilityDefects liability
Defects liability
 
Measurement 4 Tender Document
Measurement 4 Tender Document Measurement 4 Tender Document
Measurement 4 Tender Document
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 

Andere mochten auch

Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)Hasif Alias
 
PM Final Assignment Report
PM Final Assignment ReportPM Final Assignment Report
PM Final Assignment ReportMelvin Lim
 
Software Application Group Assignment
Software Application Group AssignmentSoftware Application Group Assignment
Software Application Group AssignmentHaziq1511
 
Measurement 4 Assignment Presentation
Measurement 4 Assignment PresentationMeasurement 4 Assignment Presentation
Measurement 4 Assignment PresentationHaziq1511
 
Pp group assignment
Pp group assignmentPp group assignment
Pp group assignmentwendyteosy
 
Estimating letters
Estimating lettersEstimating letters
Estimating lettersZIyeeTan
 
Measurement 4 ooompa loompa
Measurement 4   ooompa loompaMeasurement 4   ooompa loompa
Measurement 4 ooompa loompaHasif Alias
 
Management science assignment report.
Management science assignment report.Management science assignment report.
Management science assignment report.lucaschinsheng
 
Professional Practice 1 Assignment
Professional Practice 1 AssignmentProfessional Practice 1 Assignment
Professional Practice 1 AssignmentMelvin Lim
 
Estimating tender presentation
Estimating tender presentation Estimating tender presentation
Estimating tender presentation seenyeeyong
 
Assignment - Tender Documentation (Presentation Slide)
Assignment - Tender Documentation (Presentation Slide)Assignment - Tender Documentation (Presentation Slide)
Assignment - Tender Documentation (Presentation Slide)Kai Yun Pang
 
PP1 presentation slide.
PP1 presentation slide.PP1 presentation slide.
PP1 presentation slide.lucaschinsheng
 
Assignment 2 - Buildsoft Software
Assignment 2 - Buildsoft SoftwareAssignment 2 - Buildsoft Software
Assignment 2 - Buildsoft SoftwareKai Yun Pang
 
Estimating presentation
Estimating presentationEstimating presentation
Estimating presentationHasif Alias
 
Estimating presentation
Estimating presentationEstimating presentation
Estimating presentationkohwenqi
 
Estimating Presentation Slides - To Client
Estimating Presentation Slides - To ClientEstimating Presentation Slides - To Client
Estimating Presentation Slides - To ClientPang Khai Shuen
 
Tender Presentation ( Estimating )
Tender Presentation ( Estimating )Tender Presentation ( Estimating )
Tender Presentation ( Estimating )Lee Pei Gie
 

Andere mochten auch (20)

Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)
 
PM Final Assignment Report
PM Final Assignment ReportPM Final Assignment Report
PM Final Assignment Report
 
Software Application Group Assignment
Software Application Group AssignmentSoftware Application Group Assignment
Software Application Group Assignment
 
Measurement 4 Assignment Presentation
Measurement 4 Assignment PresentationMeasurement 4 Assignment Presentation
Measurement 4 Assignment Presentation
 
Pp group assignment
Pp group assignmentPp group assignment
Pp group assignment
 
Estimating
EstimatingEstimating
Estimating
 
Estimating letters
Estimating lettersEstimating letters
Estimating letters
 
Measurement 4 ooompa loompa
Measurement 4   ooompa loompaMeasurement 4   ooompa loompa
Measurement 4 ooompa loompa
 
Group Component
Group ComponentGroup Component
Group Component
 
Management science assignment report.
Management science assignment report.Management science assignment report.
Management science assignment report.
 
Professional Practice 1 Assignment
Professional Practice 1 AssignmentProfessional Practice 1 Assignment
Professional Practice 1 Assignment
 
Estimating tender presentation
Estimating tender presentation Estimating tender presentation
Estimating tender presentation
 
Assignment - Tender Documentation (Presentation Slide)
Assignment - Tender Documentation (Presentation Slide)Assignment - Tender Documentation (Presentation Slide)
Assignment - Tender Documentation (Presentation Slide)
 
M4 presentation slides
M4 presentation slidesM4 presentation slides
M4 presentation slides
 
PP1 presentation slide.
PP1 presentation slide.PP1 presentation slide.
PP1 presentation slide.
 
Assignment 2 - Buildsoft Software
Assignment 2 - Buildsoft SoftwareAssignment 2 - Buildsoft Software
Assignment 2 - Buildsoft Software
 
Estimating presentation
Estimating presentationEstimating presentation
Estimating presentation
 
Estimating presentation
Estimating presentationEstimating presentation
Estimating presentation
 
Estimating Presentation Slides - To Client
Estimating Presentation Slides - To ClientEstimating Presentation Slides - To Client
Estimating Presentation Slides - To Client
 
Tender Presentation ( Estimating )
Tender Presentation ( Estimating )Tender Presentation ( Estimating )
Tender Presentation ( Estimating )
 

Ähnlich wie Professional Practice 2: Group Assignment

Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2Shze Hwa Lee
 
Professional Practice II
Professional Practice IIProfessional Practice II
Professional Practice IIseenyeeyong
 
Pp2 coursework 2
Pp2 coursework  2Pp2 coursework  2
Pp2 coursework 2tfkc1212
 
PP2 final report
PP2 final reportPP2 final report
PP2 final reportArissa Loh
 
Pp2 group assignment
Pp2 group assignmentPp2 group assignment
Pp2 group assignmentlohwenjun
 
Pp2 assignment
Pp2 assignmentPp2 assignment
Pp2 assignmentfareezsham
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-finalashleyyeap
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-finalashleyyeap
 
Issues in s. 43CA of Income Tax Act
Issues in s. 43CA of Income Tax ActIssues in s. 43CA of Income Tax Act
Issues in s. 43CA of Income Tax ActDharmesh Shah
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7Farah Sham
 
Irish Public Works Contract - Clause 10.6 - Practical Application
Irish Public Works Contract - Clause 10.6 - Practical ApplicationIrish Public Works Contract - Clause 10.6 - Practical Application
Irish Public Works Contract - Clause 10.6 - Practical ApplicationMark Wearen
 
CE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfCE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfChelDems
 
ICDS - IIIConstruction contract
ICDS - IIIConstruction contract ICDS - IIIConstruction contract
ICDS - IIIConstruction contract Madhuri Devi
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-ContractsNikhil Kumar
 
Bearing Point REV RECOGNITION Project
Bearing Point REV RECOGNITION ProjectBearing Point REV RECOGNITION Project
Bearing Point REV RECOGNITION ProjectJim Gremillion Jr
 
Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...
Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...
Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...tdartnell
 

Ähnlich wie Professional Practice 2: Group Assignment (20)

Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
Pp2 asignment-1
Pp2 asignment-1Pp2 asignment-1
Pp2 asignment-1
 
Professional Practice II
Professional Practice IIProfessional Practice II
Professional Practice II
 
PP2 COMPILCATION
PP2 COMPILCATIONPP2 COMPILCATION
PP2 COMPILCATION
 
Pp2 coursework 2
Pp2 coursework  2Pp2 coursework  2
Pp2 coursework 2
 
PP2 final report
PP2 final reportPP2 final report
PP2 final report
 
Pp2 group assignment
Pp2 group assignmentPp2 group assignment
Pp2 group assignment
 
Pp2 assignment
Pp2 assignmentPp2 assignment
Pp2 assignment
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-final
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-final
 
Issues in s. 43CA of Income Tax Act
Issues in s. 43CA of Income Tax ActIssues in s. 43CA of Income Tax Act
Issues in s. 43CA of Income Tax Act
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
 
Irish Public Works Contract - Clause 10.6 - Practical Application
Irish Public Works Contract - Clause 10.6 - Practical ApplicationIrish Public Works Contract - Clause 10.6 - Practical Application
Irish Public Works Contract - Clause 10.6 - Practical Application
 
CE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfCE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdf
 
ICDS - IIIConstruction contract
ICDS - IIIConstruction contract ICDS - IIIConstruction contract
ICDS - IIIConstruction contract
 
Practice notes for_quantity_surveyors_fi
Practice notes for_quantity_surveyors_fiPractice notes for_quantity_surveyors_fi
Practice notes for_quantity_surveyors_fi
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-Contracts
 
Cl report final
Cl report finalCl report final
Cl report final
 
Bearing Point REV RECOGNITION Project
Bearing Point REV RECOGNITION ProjectBearing Point REV RECOGNITION Project
Bearing Point REV RECOGNITION Project
 
Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...
Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...
Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...
 

Mehr von 마 이환

Research Methodology:Literature Review (Chapter 2)
Research Methodology:Literature Review (Chapter 2)Research Methodology:Literature Review (Chapter 2)
Research Methodology:Literature Review (Chapter 2)마 이환
 
Research Methodology:Introduction (Chapter 1)
Research Methodology:Introduction (Chapter 1)Research Methodology:Introduction (Chapter 1)
Research Methodology:Introduction (Chapter 1)마 이환
 
Sustainable Housing Development
Sustainable Housing DevelopmentSustainable Housing Development
Sustainable Housing Development마 이환
 
Assignment:Major Water Issue (revised)
Assignment:Major Water Issue (revised)Assignment:Major Water Issue (revised)
Assignment:Major Water Issue (revised)마 이환
 
Chapter 10a Insurance:Contractor's Indemnity to Employer
Chapter 10a   Insurance:Contractor's Indemnity to EmployerChapter 10a   Insurance:Contractor's Indemnity to Employer
Chapter 10a Insurance:Contractor's Indemnity to Employer마 이환
 
Financial Management:Presentation Slides
Financial Management:Presentation SlidesFinancial Management:Presentation Slides
Financial Management:Presentation Slides마 이환
 
Financial Report:Comments & Evaluations
Financial Report:Comments & EvaluationsFinancial Report:Comments & Evaluations
Financial Report:Comments & Evaluations마 이환
 
Financial Report:Cash Budget, Income Statement & Balance Sheet
Financial Report:Cash Budget, Income Statement & Balance SheetFinancial Report:Cash Budget, Income Statement & Balance Sheet
Financial Report:Cash Budget, Income Statement & Balance Sheet마 이환
 
Building Economics:Tender Report
Building Economics:Tender ReportBuilding Economics:Tender Report
Building Economics:Tender Report마 이환
 
Building Economics:Individual Assessment
Building Economics:Individual AssessmentBuilding Economics:Individual Assessment
Building Economics:Individual Assessment마 이환
 
Measurement 4:presentation slides
Measurement 4:presentation slidesMeasurement 4:presentation slides
Measurement 4:presentation slides마 이환
 
Schedule of agreed datelines
Schedule of agreed datelinesSchedule of agreed datelines
Schedule of agreed datelines마 이환
 
Reply for queries (architect)
Reply for queries (architect)Reply for queries (architect)
Reply for queries (architect)마 이환
 
Request for queries (architect)
Request for queries (architect)Request for queries (architect)
Request for queries (architect)마 이환
 
Lembayung impian sdn bhd
Lembayung impian sdn bhdLembayung impian sdn bhd
Lembayung impian sdn bhd마 이환
 
Software application:appendices
Software application:appendicesSoftware application:appendices
Software application:appendices마 이환
 
Software application:assignment
Software application:assignmentSoftware application:assignment
Software application:assignment마 이환
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14마 이환
 

Mehr von 마 이환 (20)

Measurement V
Measurement VMeasurement V
Measurement V
 
Research Methodology:Literature Review (Chapter 2)
Research Methodology:Literature Review (Chapter 2)Research Methodology:Literature Review (Chapter 2)
Research Methodology:Literature Review (Chapter 2)
 
Research Methodology:Introduction (Chapter 1)
Research Methodology:Introduction (Chapter 1)Research Methodology:Introduction (Chapter 1)
Research Methodology:Introduction (Chapter 1)
 
Sustainable Housing Development
Sustainable Housing DevelopmentSustainable Housing Development
Sustainable Housing Development
 
Assignment:Major Water Issue (revised)
Assignment:Major Water Issue (revised)Assignment:Major Water Issue (revised)
Assignment:Major Water Issue (revised)
 
Chapter 10a Insurance:Contractor's Indemnity to Employer
Chapter 10a   Insurance:Contractor's Indemnity to EmployerChapter 10a   Insurance:Contractor's Indemnity to Employer
Chapter 10a Insurance:Contractor's Indemnity to Employer
 
Financial Management:Presentation Slides
Financial Management:Presentation SlidesFinancial Management:Presentation Slides
Financial Management:Presentation Slides
 
Financial Report:Comments & Evaluations
Financial Report:Comments & EvaluationsFinancial Report:Comments & Evaluations
Financial Report:Comments & Evaluations
 
Financial Report:Cash Budget, Income Statement & Balance Sheet
Financial Report:Cash Budget, Income Statement & Balance SheetFinancial Report:Cash Budget, Income Statement & Balance Sheet
Financial Report:Cash Budget, Income Statement & Balance Sheet
 
Building Economics:Tender Report
Building Economics:Tender ReportBuilding Economics:Tender Report
Building Economics:Tender Report
 
Building Economics:Individual Assessment
Building Economics:Individual AssessmentBuilding Economics:Individual Assessment
Building Economics:Individual Assessment
 
Measurement 4:presentation slides
Measurement 4:presentation slidesMeasurement 4:presentation slides
Measurement 4:presentation slides
 
Schedule of agreed datelines
Schedule of agreed datelinesSchedule of agreed datelines
Schedule of agreed datelines
 
Reply for queries (architect)
Reply for queries (architect)Reply for queries (architect)
Reply for queries (architect)
 
Request for queries (architect)
Request for queries (architect)Request for queries (architect)
Request for queries (architect)
 
Internal memo
Internal memoInternal memo
Internal memo
 
Lembayung impian sdn bhd
Lembayung impian sdn bhdLembayung impian sdn bhd
Lembayung impian sdn bhd
 
Software application:appendices
Software application:appendicesSoftware application:appendices
Software application:appendices
 
Software application:assignment
Software application:assignmentSoftware application:assignment
Software application:assignment
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14
 

Kürzlich hochgeladen

Using Grammatical Signals Suitable to Patterns of Idea Development
Using Grammatical Signals Suitable to Patterns of Idea DevelopmentUsing Grammatical Signals Suitable to Patterns of Idea Development
Using Grammatical Signals Suitable to Patterns of Idea Developmentchesterberbo7
 
BIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptx
BIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptxBIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptx
BIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptxSayali Powar
 
ICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfVanessa Camilleri
 
Expanded definition: technical and operational
Expanded definition: technical and operationalExpanded definition: technical and operational
Expanded definition: technical and operationalssuser3e220a
 
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptxDecoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptxDhatriParmar
 
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfGrade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfJemuel Francisco
 
Active Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfActive Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfPatidar M
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptxmary850239
 
4.9.24 School Desegregation in Boston.pptx
4.9.24 School Desegregation in Boston.pptx4.9.24 School Desegregation in Boston.pptx
4.9.24 School Desegregation in Boston.pptxmary850239
 
ESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnv
ESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnvESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnv
ESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnvRicaMaeCastro1
 
Tree View Decoration Attribute in the Odoo 17
Tree View Decoration Attribute in the Odoo 17Tree View Decoration Attribute in the Odoo 17
Tree View Decoration Attribute in the Odoo 17Celine George
 
Grade Three -ELLNA-REVIEWER-ENGLISH.pptx
Grade Three -ELLNA-REVIEWER-ENGLISH.pptxGrade Three -ELLNA-REVIEWER-ENGLISH.pptx
Grade Three -ELLNA-REVIEWER-ENGLISH.pptxkarenfajardo43
 
Q-Factor HISPOL Quiz-6th April 2024, Quiz Club NITW
Q-Factor HISPOL Quiz-6th April 2024, Quiz Club NITWQ-Factor HISPOL Quiz-6th April 2024, Quiz Club NITW
Q-Factor HISPOL Quiz-6th April 2024, Quiz Club NITWQuiz Club NITW
 
DIFFERENT BASKETRY IN THE PHILIPPINES PPT.pptx
DIFFERENT BASKETRY IN THE PHILIPPINES PPT.pptxDIFFERENT BASKETRY IN THE PHILIPPINES PPT.pptx
DIFFERENT BASKETRY IN THE PHILIPPINES PPT.pptxMichelleTuguinay1
 
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...DhatriParmar
 
4.11.24 Mass Incarceration and the New Jim Crow.pptx
4.11.24 Mass Incarceration and the New Jim Crow.pptx4.11.24 Mass Incarceration and the New Jim Crow.pptx
4.11.24 Mass Incarceration and the New Jim Crow.pptxmary850239
 
Concurrency Control in Database Management system
Concurrency Control in Database Management systemConcurrency Control in Database Management system
Concurrency Control in Database Management systemChristalin Nelson
 
How to Manage Buy 3 Get 1 Free in Odoo 17
How to Manage Buy 3 Get 1 Free in Odoo 17How to Manage Buy 3 Get 1 Free in Odoo 17
How to Manage Buy 3 Get 1 Free in Odoo 17Celine George
 
Reading and Writing Skills 11 quarter 4 melc 1
Reading and Writing Skills 11 quarter 4 melc 1Reading and Writing Skills 11 quarter 4 melc 1
Reading and Writing Skills 11 quarter 4 melc 1GloryAnnCastre1
 

Kürzlich hochgeladen (20)

Using Grammatical Signals Suitable to Patterns of Idea Development
Using Grammatical Signals Suitable to Patterns of Idea DevelopmentUsing Grammatical Signals Suitable to Patterns of Idea Development
Using Grammatical Signals Suitable to Patterns of Idea Development
 
BIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptx
BIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptxBIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptx
BIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptx
 
ICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdf
 
Expanded definition: technical and operational
Expanded definition: technical and operationalExpanded definition: technical and operational
Expanded definition: technical and operational
 
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptxDecoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
 
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfGrade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
 
Active Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfActive Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdf
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx
 
4.9.24 School Desegregation in Boston.pptx
4.9.24 School Desegregation in Boston.pptx4.9.24 School Desegregation in Boston.pptx
4.9.24 School Desegregation in Boston.pptx
 
ESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnv
ESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnvESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnv
ESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnv
 
Tree View Decoration Attribute in the Odoo 17
Tree View Decoration Attribute in the Odoo 17Tree View Decoration Attribute in the Odoo 17
Tree View Decoration Attribute in the Odoo 17
 
Grade Three -ELLNA-REVIEWER-ENGLISH.pptx
Grade Three -ELLNA-REVIEWER-ENGLISH.pptxGrade Three -ELLNA-REVIEWER-ENGLISH.pptx
Grade Three -ELLNA-REVIEWER-ENGLISH.pptx
 
Q-Factor HISPOL Quiz-6th April 2024, Quiz Club NITW
Q-Factor HISPOL Quiz-6th April 2024, Quiz Club NITWQ-Factor HISPOL Quiz-6th April 2024, Quiz Club NITW
Q-Factor HISPOL Quiz-6th April 2024, Quiz Club NITW
 
DIFFERENT BASKETRY IN THE PHILIPPINES PPT.pptx
DIFFERENT BASKETRY IN THE PHILIPPINES PPT.pptxDIFFERENT BASKETRY IN THE PHILIPPINES PPT.pptx
DIFFERENT BASKETRY IN THE PHILIPPINES PPT.pptx
 
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
 
4.11.24 Mass Incarceration and the New Jim Crow.pptx
4.11.24 Mass Incarceration and the New Jim Crow.pptx4.11.24 Mass Incarceration and the New Jim Crow.pptx
4.11.24 Mass Incarceration and the New Jim Crow.pptx
 
Concurrency Control in Database Management system
Concurrency Control in Database Management systemConcurrency Control in Database Management system
Concurrency Control in Database Management system
 
How to Manage Buy 3 Get 1 Free in Odoo 17
How to Manage Buy 3 Get 1 Free in Odoo 17How to Manage Buy 3 Get 1 Free in Odoo 17
How to Manage Buy 3 Get 1 Free in Odoo 17
 
Reading and Writing Skills 11 quarter 4 melc 1
Reading and Writing Skills 11 quarter 4 melc 1Reading and Writing Skills 11 quarter 4 melc 1
Reading and Writing Skills 11 quarter 4 melc 1
 
Faculty Profile prashantha K EEE dept Sri Sairam college of Engineering
Faculty Profile prashantha K EEE dept Sri Sairam college of EngineeringFaculty Profile prashantha K EEE dept Sri Sairam college of Engineering
Faculty Profile prashantha K EEE dept Sri Sairam college of Engineering
 

Professional Practice 2: Group Assignment

  • 1. Report: Final Account & The Significance and Implications of the Omission of Works  Procedure of Final Account  Adjustment of the essential elements in preparation of Final Account  In the Bills of Quantities  Not allowed as Provisional Sums or Prime Cost Sums
  • 2. Content Page no 1. Introduction 1 2. Definitions 2 3. Procedure of Final Account 3-4 4. Adjustmentof the essential elementsinpreparationof the Final Account 5-9 5. ComparisonbetweenProvisional SumsandPrime CostSums 10 6. Implicationsof Omissionof Provisional Sums 6.1 From the standpointof a Client 11-12 6.2 From the standpointof a Contractor 13-14 7. Conclusion 15
  • 3. 1. Introduction This report is briefly explaining the adjustment of the essential elements in preparation of the Final Account. However, this report is prepared to identify the significance and implications if some works are entirely left out in the Bills of Quantities and also not picked out as provisional sums or P.C sums. The conditions of the situation mentioned includes works like structural steel roof trusses in which are shown on the drawings but not sufficiently designed for measurement of quantities. This report will cover the definition, procedure and adjustment essential element in preparation of the Final Account. Besides that, it also defines and comparison of the provisional and P.C sums relating to the situation presumed and later discuss on the significance and implications from two points of view, consisting of the client and the contractor. Lastly is the conclusion.
  • 4. 2. Definitions Final Account According to SMM2 (Clause 30.10) defines the Contractor shall send all document within 6 Months after the Practical Completion of the Work for preparing the Final Account. Provisional Sums According to SMM2 (Clause A.8.1.a.) defines provisional sum as a sum provided for work or for costs which cannot entirely be foreseen, defined or detailed at the time the tender documents are issued. P.C. Sums According to SMM2 (Clause A.8.1.b.) defines prime cost sums as a sum provided for works or services to be executed by a nominated sub-contractor, a government or a statutory authority or for materials or goods to be obtained from a nominated supplier. Such sum shall be deemed to be exclusive of any profits required and/ or attendance to be provided by the main contractor and provision shall be made for the addition thereof where applicable.
  • 5. 3. Procedure of final account Generally, Article 7 (ab) of PAM Contract 2006 defines Final Account as the document showing the adjustment of the Contract Sum issued under Clause 30.10. Clause 30.10 stated the Contractor shall send all document within 6 Months after the Practical Completion of the Work for preparing the Final Account. The Final Account must be completed within 6 Months from receipt of all the document from the Contractor. All document including all documents relating to the accounts of Nominated Sub-Contractors and Nominated Suppliers. Such document shall contain all the latest construction drawings and details, details of all quantities, rates and prices and any adjustment of the Contract Sum and additional payment or compensation claimed by the Contractor under the Contract together with any explanation and supporting vouchers, documents and calculations. If there is any delay by the Contractor, the period for the completion of Final Account shall be adjusted. In the event, the Contractor fail to submit all documents the Architect or Quantity Survey shall nevertheless complete and issue the same based on the information available within the Period to complete the Final Account stated in the Appendix. When the Final Account is completed, a copy would need to be sent to both the Employer and the Contractor to obtain their agreement. Clause 30.10(a) Sometimes, they may not respond with any agreement/disagreement to the Final account. In that event, this clause expressly provides that if both the Employer and Contractor fail to notify any dispute on the Final Account within 3 Months from the data of receipt of Account, the Final Account shall be conclusive and deemed agreed by the parties. Clause 30.10(b) If either party disputes the Final Account, the party disputing the Final Account shall by written notice to the other party (with copies to the Architect and Quantity Surveyor) set out any disagreement complete with particulars within three (3) Months of the date of receipt of the Final Account from the Architect or Quantity Surveyor.
  • 6. The Architect or Quantity Surveyor within three (3) Months from the date of receipt of the grounds of dispute shall either amend or not amend the Final Account. Any party disagreeing with the amended Final Account or decision not to amend the Final Account shall refer the dispute to arbitration under Clause 34.0 with three (3) Months from the date of receipt of the amended Final Account or decision not to amend the Final Account. Failure to refer the dispute to arbitration within the stipulated time, the Final Account or amended Final Account shall deem to be conclusive and agreed by the parties. To be more precise, it is a financial document indicating the final value of the works executed by the Contractor and his NSCs and NSs.
  • 7. 4. Adjustment of the essential elements in preparation of the Final Account A well prepared Final account is able to establish the final construction cost of project. There are a few essential elements which constitute a complete Final Account and the relevant elements are as per stated below: • Variation works (clause 11.6) • Remeasurement of Provisional Quantities (clause 11.6 (f)) • Omission of Prime cost and Provisional sum (clause 30.11 (c)) • Adding-back of NSC’s and NS’s Final Accounts (clause 30.11 (c)) • Adjustment of Profit and Attendance (clause 30.11 (c)) • Adjustment of Provisional Sum based on actual expended and omitted if not expended (clause 30.11 (d)) • Additional Expenses Claims (clause 11.7) • Loss and Expenses Claims (clause 24.4) The first essential element in preparing final account is variation works under clause 11.6. The valuation of variation and work executed by the contractor for which a provisional quantity is included in the contract and the expenditure of provisional sum shall be based on 11.6(a), (b), (c), (d), (e) & (f). Clause 11.6(a) stated the rates and prices in the Contract Documents shall be the basis of valuation where the Variation work is similar in character to, and is executed under similar conditions set out in the Contract Documents, and where there is no significant change to the quantity of work indicated in the Contract Bill. Clause 11.6(b) the rates and prices in the Contract Documents shall be the basis of valuation, and shall include a fair adjustment in the rates to take into account same cost differences where the Variation work is of a similar character to, but is not executed under similar conditions set out in the Contract Documents. Similarly, the rates and prices shall also be appropriately adjusted where the Variation work is of a similar character and is executed under similar conditions, but there is a significant change in the quantity of work as compared to the quantity indicated in the Contract Bill.
  • 8. Clause 11.6(c) stated the Contractor shall be entitled to a fair valuation which will not give the Contractor more than his actual cost, reasonably and necessarily incurred, plus similar allowance for overhead and profit. Clause 11.6(d) stated the Contractor can applicable ‘where work cannot be properly measured and valued.’ The Contractor has to comply with the procedure when recording the day works, and should have it verified by the Site Staff and progressively sent to the Architect and Consultant. Clause 11.6(e) stated that the rate and prices in the Contract Documents shall determine the valuation of items omitted. If omissions substantially vary the conditions under which any remaining items of work are carried out, the price of such remaining items shall be valued under Clause 11.6(a), (b) or (c). Clause 11.6(f) if the Works have been measured on a Provisional basis, the Works shall be re-measured based on the actual quantities executed, and the rates and price in the Contract Documents shall be the basis to arrive at a Final Account. This shall exclude the work for which a tender had been accepted under clause 27.14 – Contractor permitted to tender for P.C Sums. For example, variation may occur in situation such as the architect gives instruction to change the floor layout. If there is no provision for variation, the employer may need to get the agreement of contractor and the contractor may negotiate for higher price. This variation clause is to allow changes to be made and subsequently adjust or amend the contract sum. Besides, the valuation rules can be applied where the works are carried out by the contractor for which the provisional quantities and provisional sum had been included in the contract bills. Besides that, remeasurement of provisional quantities is also an important element according to clause 11.6(f). In respect of Provisional Quantity, the quantities stated in the Contract Document shall be re-measured by the Quantity Surveyor based on the actual quantities executed. The provisional quantities are estimated quantities only, for instance the quantities for excavation works, piling works and infrastructure. It is not possible to know the actual quantities for the works mentioned at the early stage and thus, the quantities shall be remeasured by Quantity Surveyor in-charged based on the actual Works that completed. The quantities are subjected to changes but the rates priced in the Contract Documents will remain constant.
  • 9. In addition, Prime Cost sums and Provisional Sums are also part of the essential elements in Final Account. Basically, Prime Cost sums are the sum of the specialist works carried out by the sub-contractor which normally inclusive of profits and attendance whereas Provisional Sums are the sum of work done that can be identified but with no detailed drawing provided and thus, the sum cannot be itemized in bills of quantities (BQ). The question worth to be raised up is that, why is there a need to allow provisional sum in the BQ since adjustment is to be made at the final stage? Let’s take guard house as an example and the possible reasons are as stated below: • For instance, contractually, a guard house is to be built but with very limited details of drawings. In this case, the provisional sums need to be added into BQ so that client will be aware of the budget of the project as it allows an approximate contract amount for the purpose of cost control. • Contractor needs to include the provisional sum works in order to plan his work program and to finish the works on time. It will easily cause disputes if provisional sum is not added into the contract document. In this case, contractor can easily claim for extension of time (EOT) as architect will have to issue Architect’s Instruction for variation works which are against the requirements as per agreed in contract document, for instance, guard house. Prime cost sums and provisional sums with related profit shall be omitted from the final account based on clause 30.11(c). This is because the prime cost sums and provisional sums are just estimated sum and act as estimated allowance but both prime cost sums and provisional sums are subjected to changes. Since the prime cost sums and provisional sums with related profit are omitted from the final account, the nominated sub-contractors’ and nominated suppliers’ final account shall be added back. Every Nominated Sub-Contractors and Nominated Suppliers need submit the Final Account together with the pro-rata amount for profit. In short, the adjustment is made after completion of works and final cost is ascertained. Provisional sums and prime cost sums that are not being used shall be deducted out from the contract sum. The profit shall be adjusted basedon the amount of final account whereas for attendance shall be remain unchanged. This is because the attendance is a fixed amount or lump sum amount and it is provided for supervision
  • 10. works and hence, it is not subjected to changes. However, for profit it is based on a certain amount of percentage, for instance 2% of the total cost of project. The reason of charging of profits and attendance by main contractor is because the main contractor is required to provide the general lighting, general hoisting material and general power and many more for sub-contractors to work. Furthermore, the other essential element of Final Account is adjustment of Provisional Sum based on actual expended and omitted if not expended stated under clause 30.11(d) in PAM Contract 2006. Adjustment of Provisional Sum is basically for the things which did not have any design, details, specification, but needed to construct within the project. The Provisional Sum needed to adjust during the Final Account because there is no accurate sum that Contractor place at the Contract Document. Basically it means any adjustment of Provisional Sum will be measured based on all the actual expended of Provisional Sum by the Contractor. If some Provisional Sum is not expended, such amount shall be deemed to omit from the contract bill during the Final Account. Next, the Additional Expenses claims shall also be considered in the Final Account which is stated under clause 11.7 in PAM Contract 2006. The objective of this clause is to enable the Contractor to be reimbursed as part of the cost of variation, for the additional expenses he has incurred carrying out the Variation, and for which he would not be compensated under Clause 11.6. However, the Contractor is allowed to claim for the additional expenses in accordance to the clause 11.7 (a) provided the contractor shall give written notice to the Architect of his intention to claim for such additional expenses and the contractor shall send to the Architect and QS complete particulars of his claim clause 11.7 (b). Eventually, the additional expenses claim will be added into the Final Account. The final essential element of Final Account is Loss and Expense claims which stated under clause 24.4 in PAM Contract 2006. The clause explains that any Loss and Expense incurred by the Contractor which complying with Clause 24.1, the Architect and Quantity Surveyor shall make certain and include such amount of loss and expenses into the Final Account. The words “shall ascertain” stated in the clause basically means that the Architect or the Quantity Surveyor must access the claim based on particulars and calculations submitted by the Contractor but not merely rely on a general assessment before including the amount into the final account.
  • 11. Any claim under common law is outside the jurisdiction of the Architect and Quantity Surveyor, and the Contractor has to resolve this with the Employer. However, there are 3 elements which shall be excluded from Final account based on clauses 30.11(e) to (g). The first element to be excluded is any liquidated damages imposed by the Employer as stated in the clause 30.11(e). Secondly, set-off by the Employer shall also deem to exclude from final account under the clause 30.11(f). Lastly, Interest payable by either Employer or Contractor shall also be excluded from Final Account under the clause 30.11(g). The main concern is that, why are the 3 items mentioned above are to be solved separately between employer and contractor? Why are the 3 items excluded from Final Account? This is due to the following reasons: • Architects are certifiers and they certify work done only and not the parties to the Contract. They need to be fair and independent and it is not their duties to determine the party who is in dispute and hence, these 3 items are to be excluded from the Final Account. • Disputes may easily arise from either party with such elements being included in the Final account, causing the final account hardly to be completed at the end of the day. The main intention is not to delay the timely conclusion of the Final Contract and it simply means without a final account, the Architect and QS cannot be discharged.
  • 12. 5. Comparison between Provisional Sums and Prime Cost Sums Basically, as defined in SMM2, Provisional Sums is of the supply of materials with profits and attendance also labour cost whereas the Prime Cost Sums only consists of the supply of the materials. Common examples of Provisional Sums consist of landscaping, piling, earthworks or scaffolding. Common examples of Prime Cost Sums are supply of cook tops and ovens, sanitary wares, furniture or floor coverings. In this case, the structural steel roof trusses are provisional sum as the works will include the supply of the steel roof trusses and the installation which takes into account the profits and attendance. Other than that, the situation clearly shown that drawings are available to identify sum of works to be carried out but the later states that no details for measurement shows that the sum cannot be itemized in the Bills of Quantities, hence allowance of Provisional Sums should be given.
  • 13. 6. Implications of Omission of Provisional Sums Having the condition as below, (a) The works omitted is the structural steel roof trusses (b) Shown on drawing but not sufficiently designed for measurement of quantities (c) Works entirely left out in Bills of Quantities (d) Not allowed as Provisional or Prime Cost Sums (e) Using the PAM Contract 2006(with quantities) (f) Variable assumptions made accordingly 6.1 From the standpoint of a client (f) At pre-tender stage Should the quantity surveyor omitted the steel roof trusses, which is supposed to be an allowance as Provisional Sum, this means that the Contract Sum excludes the works of the structural steel roof trusses. When the works are not included in the estimates, this would affect the cost control process due to omission of works and the budget established will not be accurate. The client will rely on the budget estimates to derive the approximate contract sum. Client might tend to spend more on other works such as specifications relating to the quality of the building if the estimates shows a budget lower than anticipated. This would cause disputes arising in the future when the actual contract sum is way too high over the clients’ budget.
  • 14. (f) After contract awarded Clause 11.1(a) defines the term “Variation” as the alteration or modification of the design, quality or quantity of the Works including the addition, omission or substitution of any work. In this case, the Variation will be regarding the omission of the structural steel roof trusses. Upon awarding of Contract, provided if the parties are still unaware of this omission, the works would be left out. When discovered, this means that the client has the options whether to enter a separate contract which only consists of the structural works of steel roof trusses or the client would have to treat this part of omitted work as variation according to clause 11.2 in PAM Contract 2006 that the Architect may issue an AI ordering or sanctioning the variation in order for the contractor to carry out all the variations with due diligence and expedition. If the client goes for option 1, it might be time-consuming and the overall cost will be higher due to the lengthy tender process and sudden involvement of works. However, option 2 is also not as good as 1 due to the instruction of AI to variation may give the contractor a ground to claim for EOT which is in accordance with clause 23.8(g) and meaning that the client would have lesser imposed liquidated damages.
  • 15. 6.2 From the standpoint of a contractor (f) At tender stage If the contractor found out the part of structural steel roof has been omitted in the tender document, the Contractor may inform the quantity surveyor and upon confirmation of the omission, there might be a revised tender or tender amendment. This would be better as it prevents disputes arising in the future. (f) Provided if the contractor is to carry out the works due to AI of variation clause 11.2 The omission of provisional sum would affect the contractor’s master work programme which would also affects the completion date of the project. The contractor, unaware of the works of provisional sum at the early stage would have to submit a new master work programme and this would cost more to the contractor if he had insufficient plants and machinery or even experience to carry out the works. Insufficient experience in specified works (here is the supply and installation of steel roof trusses) may cost higher due to unfamiliarity with market prices and suppliers causing higher material costs. Moreover, contractor would have to bear the defects within the Defects Liability Period which would cost more to a contractor to rectify the defects should the works carried out contains defect.
  • 16. (f) Provide the contractor unknowingly did the part of works If the contractor is to make a contractual claim, Clause 11.7 under variations, provisional and prime cost sums will entitle the contractor to claim additional expenses other than provision in clause 11.6 provided the contractor has meet the procedural condition stated in the contract. The contractor has to give a written notice to the Architect regarding his intention to claim for such additional expenses together with an initial estimate of his claim duly supported with all necessary calculations within 28 Days from the date of AI or CAI which is a condition precedent for his entitlement to claim. Within 28 Days of completing such variation, the contractor has to send his actual claim together with complete particulars and all necessary calculations to substantiate his claims. Should he failed to do so within the time stated or within the period agreed by the Architect, the contractor has deemed to waived his rights to any additional expenses. According to Clause 11.9, as soon as the Architect ascertained the amount claimed by contractor under Clause 11.7, the amount will be added to the Contract Sum. However, if the contractor unknowingly supplied and installed the steel roof trusses which are not included in the Contract and he did not follow the procedural contractual claim as per Clause 11.7, this might cause the contractor to seek for extra-contractual claim where the claim is made under quantum merit. This is a claim where a reasonable sum is claimed for work is done where the contract is silence on how the work is to be paid.
  • 17. 7. Conclusion There are essential elements needed to adjust during the Final Account. However, owing the presence of provisional sums due to the error made by the quantity surveyor would imply consequences to both the client and contractor. Moreover, the quantity surveying consultant firm would also suffer loss in both monetary and accountability. This report mainly focuses on implications to the client and the contractor involving the project.
  • 18. DECLARATION OF AGREEMENT We, the undersigned, hereby confirmed our agreement to the attached Final Account as follows: 1. That the Final Account is correct and is in accordance with the Conditions of Contract. 2. That the Final Contract Value of RM 31,060,000.00 is correct. 3. That we have no further claims whatsoever against each other. Employer Contractor Date: Date: Witness Witness Date: Date:
  • 19. Question 3(a): Relocation of an already installed timber door including sealing up the wall opening. Agreed at the site meeting for Contractor to claim based on Dayworks for labour, material and plant. Answer: Diagram 1.0: Items that should be priced based on daywork rates PAM Contract 2006 (With Quantities), Clause 11.6(d) stated that, where work cannot be properly measured and valued in accordance with 11.6(a), (b) or (c), the Contractor shall be allowed to claim based on daywork rates in the Contract Documents for labour, material and plant as agreed at the site meeting. Based on this scenario, the items that should be priced based on daywork rates are the removal of the timber door, sealing up of the door opening and making of a new opening for the timber door. For the removal of the timber door, making of a new opening for the timber door and installation of the timber door, the labour rates shall be priced in accordance with the general labour rate provided in the schedule of daywork rates. While for the sealing up of the door opening, the labour rates shall be based on bricklayer, plasterer and painter. Items that should be priced based on daywork rates Removal of the timber door Labour: General labour Making of a new opening for the timber door Sealing up of the dooropening Labour: Bricklayer, plasterer and painter Materials: bricks, sand, cement and paint (refer to the breakdown rate provided in BQ)
  • 20. Apart from that, QS shall refer to the breakdown rate provided in Bill of Quantities as a basis to derive the new rates for the material used in sealing up the door opening such as bricks, sand, cement and paint. In this case, there is no payment for plant due to no plant is needed to execute the variation works. Contractor should prepare a daywork record in order to claim for daywork. The daywork record shall include the time spent daily upon the variation works, the worker’s details, scope of works, materials used, transportation as well as other necessary evidence. The daywork record shall be signed by the client’s representative or Site Agent and verified by the Site Staff for validation purpose. Then, the document shall be delivered to the Architect and Quantity Surveyor at weekly intervals with the final records delivered not later than fourteen (14) Days after the work has been completed.
  • 21. Question 3(b) Omission of the need to provide computer equipment in the Preliminaries section but item was left unpriced, i.e. BQ item was left black in the rate/amount column in the contract document. Answer: Computer equipment in the Preliminaries is left unpriced, it shall be deemed that the Main Contractor has included such item in his tender with a Lump Sum price. Therefore, the Consultant Quantity Surveyor shall identify the price of the computer equipment; and the Employer has the rights to omit the price of the computer equipment as stated in Architect’s Instruction if necessary. According to PAM Contract 2006, in Clause 11.6, the valuation of Variations and work executed by the Contractor for which a Provisional Quantity is included in the Contract and the expenditure of Provisional Sums (other than for work for which a tender had been accepted under Clause 27.14) shall be made in accordance with the following rules: Clause 11.6(c), where work is not of a similar character to work as set out in the Contract Documents, the valuation shall be priced at current fair market rates and prices are to be determined by the Quantity Surveyor. Therefore, in this scenario, the Consultant Quantity Surveyor has the rights to omit the price of computer equipment based on fair market rate. Besides that, the Consultant Quantity Surveyor may obtain the rate of the computer equipment from previous contract documents of a similar project.
  • 22. Question 3(d) Mistake was made in rate for 50mm thick concrete blinding is RM 10 per m3. Item was not rationalized during contract documentation. However, original quantity in BQ is 100 m3 but re-measured quantity is 2,000 m3. Answer: According to case law Henry Boot Construction v Alstom Combined Cycles Ltd [2000] BLR 247, the Court of Appeal found that the relevant variations had to be priced using the contract bill rate, notwithstanding the apparent mistake which meant the Contractor was likely to receive a windfall profit. In another manner, it also meant that if the contractor priced a lower rate, he most likely would receive a windfall lost. PAM Contract 2006 (with Quantities) Clause 11.6(b) had stated that “where work is of a similar character to work as set out in the Contract Documents but is not executed under similar conditions or is executed under similar conditions but there is a significant change in the quantity of work carried out, the rates and prices in the Contract Documents shall be the basis for determining the valuation which shall include a fair adjustment in the rates to take into account such difference”, therefore, the contractor can claim for the re-measured quantity of element with a fair adjustment in rates that stated in the Contract Documents. Based on the above scenario, the contractor will faced a windfall lost due to the irrationalized rates priced during the contract documentation, this is because the final account rates will follow the rates that initially priced in the agreed contract document between two parties. As for the re-measurement quantity, contractor have the rights to claim for a fair adjusted rates of the elements due to the mistakes done by the consultant team in preparing for drawings and taking-off. By following the price of RM10 per m3 for the 50mm think concrete blinding using the initial quantity of 100m3, the total cost will be RM 1,000, whereas in the new quantity of 2,000 per m3, the new total cost will be RM 20,000, and the different is RM 19,000. Consequently, the contractor can only claim an additional of RM 19,000 for the total cost of the 50mm thick concrete blinding.
  • 23. Project: ApartmentProject Appendix 1 Employer:Eddie SdnBhd Contractor : TaylorsBuilderSdnBhd FINALACCOUNT RM RM 1.0 Original ContractSum 29,160,000.00 2.0 Less: P.C & Provisional Sums 4,660,000.00 Total Builder'sWorks 24,500,000.00 3.0 Add: Variationworks(V.O.Nos1-4) Total Additions 2,050,000.00 Total Omissions 1,000,000.00 NettAdditions 1,050,000.00 1,050,000.00 4.0 Add: NSCs'final account LiftServices 1,500,000.00 AirConditioningServices 1,200,000.00 Electrical Services 2,300,000.00 5,000,000.00 5,000,000.00 5.0 Constractual Claims: 5.1 Additional Expenses 10,000.00 5.2 Loss and Expense 500,000.00 510,000.00 510,000.00 FINALCONTRACTVALUE 31,060,000.00
  • 24. Project: ApartmentProject Appendix 2 Employer:Eddie SdnBhd Contractor : TaylorsBuilderSdnBhd STATEMENT OF FINALACCOUNT Final ContractValue 31,060,000.00 Deduct: Amountpreviouslycertified 29,160,000.00 BALANCEDUE TO CONTRACTOR 1,900,000.00