2. 2
Central Board of Irrigation & Power (CBIP) had
awarded as Best Performing Thermal Power Station in
State Sector by Hon'ble Cabinet Minister for Power
&NRE , SHRI. R.K.Singh at New Delhi on 03-03-2023.
STPP have been ranked 1st position in PLF among
the State power sector in India FY 2022-23.
STPP have been ranked 7th position in PLF ranking
among best 25 power stations of the country
FY 2022-23 (up to Jan’23).
More than 90% station PLF is maintained for
consecutive for 06 months.
More than 95% station availability is maintained for
consecutive 06 months.
4. 4
UNIT#1
Unit achieved 100.03 % PLF.
Unit availability is 100%.
Specific oil consumption is Nil.
6. Performance Data FY 2022-23
6
S.
No
Description UOM Unit-1 Unit-2 Station till
31.03.23
Station till
31.03.22
1 Gross Generation MU 4854 4450 9304 9353
2 PLF % 92.34 84.67 88.51 88.97
3 Availability(DC) % 92.46 87.09 89.77 93.16
4
Auxiliary Power
Consumption
% 6.18 5.92 6.05 5.83
5
Forced Outage % 7.54 12.90 10.22 3.26
Reserve shutdown % 0 0 0 0
6 Planned Outage % 0 0 0 3.61
7 Oil Consumption
kl 1053 701 1754 1226
ml/kWh 0.22 0.16 0.19 0.13
*During FY 2022-23 SLDC backing down is 158.33 MU (1.51%)
7. Projected Vs Actual
Quarterly data (FY 2022-23)
7
2568 2597 2597 2540
2309 2430 2483
2085
0
500
1000
1500
2000
2500
3000
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Generation (MU)
Projection Actual
8. Projected Vs Actual
Quarterly data (FY 2022-23)
8
98.00 98.00 98.00 98.00
88.09 91.72
93.72
80.43
50.00
60.00
70.00
80.00
90.00
100.00
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
PLF (%)
Projection Actual
9. Projected Vs Actual
Quarterly data (FY 2022-23)
9
98.00 98.00 98.00 98.00
88.21
93.66 96.19
80.83
50.00
60.00
70.00
80.00
90.00
100.00
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Availability (%)
Projection Actual
10. Projected Vs Actual
Quarterly data (FY 2022-23)
10
0.50 0.50 0.50 0.50
0.19 0.18
0.09
0.32
0.00
0.10
0.20
0.30
0.40
0.50
0.60
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
SOC (ml/kWh)
Projection Actual
11. Projected Vs Actual
Quarterly data (FY 2022-23)
11
3.00 3.00 3.00 3.00
2.96
2.72 2.74
2.82
2.00
2.20
2.40
2.60
2.80
3.00
3.20
3.40
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Sp. Raw water consumption(m3/MW))
Projection Actual
12. 12
Unit Outage details
March’2023
Unit
No.
Outage Synchronisation Outa
ge
durat
ion
hrs:
min
Gen
Loss
(MU)
Reason of Tripping
Responsibil
ity
Date
Time
(hrs:mi
n)
Date
Time
(hrs:min)
2
19.03.2
023
00:17
19.03.20
23
2:54
2:37:
00
2.14
Unit-2 tripped due to GT
2Y sudden pressure
relay cable damaged.
EMD
17. Water Management
Mrach’2023
17
S.No Description UOM Actual
1
Total raw water
drawn
Lm3
23.35
2 Reservoir capacity Lm3
25
3 Reservoir level m 151.2
4
Specific raw water
consumption
M3
/MW 2.65
18. Safety
Safety Statistics for the month of March-2023
Number of recorded incidents : Safe/ Nil
Lost Time due to Injury : 00
Near Miss :00
Fire calls : Safe/Nil
Target – Zero accident
Measures : 03 Days Training for Each Employee
18
20. Overhead Electrification to STPP siding:
An amount of Rs. 23.825 Crores deposited with SCR and MoU
concluded on 27.10.2021. Work awarded on 17.02.2022.
Status:
S.
N
o
Description Chaina
ge
(Km)
Approx
. Track
KM
Status PDC
1 Phase-I,
SRP CHP
yard
4 to 6 6.50 Completed.
2 Phase-II,
upto OC
yard
6 to 14 14.50 Completed.
3 Phase-III,
upto STPP
14 to
25
16.00 Masts foundation
completed for
467/484.
Masts erection
completed for
91/415.
31.05.2023
21. S&T to STPP siding:
Note approved to take up Signalling &
Telecommunications to STPP siding (from
Mancherial to STPP including LTC siding at SRP
CHP) at an estimated cost of Rs.44 Crores.
(Cont. to Note No. STPP/CVL/A/255/156/151
Dt.21.11.2022)
PMC work, at (+) 6.25% on execution cost of S&T
works, awarded to M/s RITES Ltd. on Dt.
25.03.2023.
Time period: 2 Years
26. Modification of power line crossings along the STPP
railway siding between SRP CHP and STPP.
Work awarded to M/s Madhu Electricals on
08.09.2022.
Value of the work: Rs.91.00 Lakhs.
Due date of completion: 07.11.2022 (Two months),
EOT granted upto: 07.12.2022 (One month).
Work completed except connections which will be
done on getting clearance from NPDCL.
Line clearance (LC) is being pursued with NPDCL.
26
30. Engineering works
1. Critical drawings of limestone silo, gypsum storage shed,
ECR-1 building and ball mill building are submitted, which
are committed for submission in March-23.
2. Remaining critical drawings of gypsum dewatering building,
ECR-2, ball mill and BRU are planned for submission by 10-
04-2023.
Bought out items(BOI’s) ordering:
1. Ordering of Critical BOI’s like Mist eliminator, gypsum
dewatering system, process and slurry pumps and absorber
cladded plate material are completed, which are committed
for ordering in March-23.
2. Remaining critical BOI’s like piping, spray header,
transformer & absorber agitator are planned for ordering by
10-04-2023.
31. 31
Civil works:
Chimney-1 shell concerting: 100% completed.
Chimney-2 shell concreting: 88 % completed.
Booster fan-1, 2 & 3 foundation: 100 %
completed.
Common system tanks foundation : 100%
completed.
Flue gas ducting foundation for Unit-1 & 2:
100 % completed
Civil works are under progress for booster fan-
4, unit-1 & 2 fan handling system, limestone
conveyor, gypsum storage shed, ECR-1
building and ball mill building.
32. Structural works :
1. Bi plane damper support structure and unit-1 chimney
platforms
fabrication completed and supplied to site.
2. Chimney flue can fabrication at STPP, flue gas duct and
unit-2 chimney platforms fabrication at M/s PES
workshop is under progress.
Capital Expenditure:
1. Total project cost(Including taxes) : Rs. 696.50 Crores
2. Capital expenditure for FY 2022-23 : Rs. 164.74 Crores
3. Expected Capital expenditure
for FY 2023-24 : Rs. 300 Crores
33. 33
Government of Telangana accorded permission for
expansion of 2x600 MW STPP by adding additional 3rd
Unit (Stage-II) 1X800 MW Super critical Unit.
MoEF &CC awarded EC clearance for the expansion of
additional unit.
NOC obtained from Airports Authority of India for
Construction of Chimney.
1x800 MW 3RD Unit (Stag-II) NIT floated on 19-11-2022 .
bid opened on 02-03-2023.
M/s BHEL should L1, Price negotiations TCR is under
circulation.
Expansion of the Project (1x800MW) Stage-2
34. Power dues as on 31.03.2023 (Rs in cr)
Power bills submitted 23,915.37
LPS amount upto
28.02.2023
6,097.84
Total bills including LPS 30,013.21
Payment received 11,852.77
Total dues as on date 18,160.44
LPS amount upto
28.02.2023
6,097.84
Dues towards power
bills
12,062.61
Bills submitted and due 11,373.54
Bills submitted but not
due
689.07