SlideShare a Scribd company logo
1 of 34
Slope Stability
Slope
• Mathematicians have developed a useful
measure of the steepness of a line, called the
slope of the line.
• Slope compares the vertical change (the rise)
to the horizontal change (the run) when
moving from one fixed point to another along
the line
Slope is expressed by
1. An angle from horizontal i.e 24°45°
2. As a gradient i.e 1 in 4as a vertical fall
3. centimetre per meter
Gradient
• The method to calculate the Gradient is:
• Divide the change in height by the change in
horizontal distance
• Gradient = Change in Y/Change in X
•
Types of open pit slopes
• Slopes in quarries can result from a range of activities associated with the
working of the site. There are three principal types of slope to be
considered:
1. Excavated slopes (in which in situ ground is exposed);
2. Tipped slopes (where loose material is formed into mounds either
above ground in placed in existing voids); and
3. Natural slopes (which may be affected by excavations or placement of
loose materials).
On the basis of duration pit slopes can be
1. Short term slopes – stockpiles and soil mounds, intermediate quarry
faces;
2. Medium term slopes – soil mounds, quarry faces, screening bunds, etc.;
and
3. Long term slopes – quarry faces, spoil mounds, lagoon embankments,
screening bunds.
Types of open pit slopes
• Unimportant slope
• Average slope
• Critical slope
• Unimportant slope;- slope angles unimportant
economically and flat slopes can be used
• Average slope;- slopes angles are important but not
critical in determining economics of mining
• Critical slope;- slope angle critical in terms of both
economics of mining and safety of operations
Types of open pit slopes
• In open pit mining, mineral deposits are mined from
the ground surface and downward. Consequently,
pit slopes are formed as the ore is being extracted.
• The various types of pit slopes are
1. Bench slope
2. Overall pit slope
3. Current overall pit slope
4. Haul road slope,
5. Ramp slope
6. Inter ramp slope
7. dump slope
Types of Slope Failure
• Bench slope or bank angle: it the angle measured in degree between the
horizontal and an imaginary line connecting bench toe to the bench crest.
It is an inclined plane of the bench which limits it on the side worked out
space.
• overall pit slope angle: it the angle measured in degree between the
horizontal and an imaginary line connecting bottom bench toe to the top
bench crest.
• Current overall pit slope;- it the angle measured in degree between the
horizontal and an imaginary line connecting existing bottom bench toe to
the existing top bench crest at a given time.
• Ramp slope;-The gradient on a ramp is the grade line profile along the road
centre line, in the vertical plane.
• Dump slope;- it the angle measured in degree between the horizontal and
an imaginary line connecting toe of dump to the existing top crest at a
given time.
• The interramp slope angle is measured from toe to toe or crest to crest
exclusive of any ramps. By excluding ramps or other offsets the interramp
angle is kept static no matter how many benches are measured. The
interramp angle is similar to the face angle because it is static.
PIT SLOPE GEOMETRIES
• There are numbers of slope which inters into pit design. Care is needed so that there is no
confusion as to how they are calculated and what they mean . The main are bench slope, overall
pit slope , , ramp slope, interramp slope etc.
• There are three major component of a pit slope
1. Bench configuration
2. Interramp slope
3. Overall slope
• The bench configuration is defined by bench face angle, the bench height and bench width.
• The interramp angle is the slope angle produced by a number of benches. Where there are haul
roads ,working levels or other wide benches
• The overall pit slope is the angle of the line from the toe to the crest of the pit.and will be flatter
than interramp slope.
• It is important to consider all three components in slope design
• In order to make a quantities estimate of the stability of aslope analytical models amenable to
mathematical solutions must be used
• The requrements of these modeles are the failure geometry and assumption regarding materila
properties and stress distributions.
• While active mining is under way ,some working benches would be included in the overall slope.
• At the end of mining it is desired to leave the final pit slope as steep as possible, some of safety
benches will be reduced in width while others may be eliminated entirely.`
Types of Slope Failure
PIT SLOPE GEOMETRIES
• The primary components of a pit design are as follows:
1. Bench Geometry –
• The height of the benches is typically determined by the size of the shovel chosen
for the mining operation.
• The bench face angle is usually selected in such a way as to reduce, to an
acceptable level, the amount of material that will likely fall from the face or crest.
• The bench width is sized to prevent small wedges and blocks from the bench
faces falling down the slope and potentially impacting men and equipment.
• The bench geometry that results from the bench face angle and bench width will
ultimately dictate the inter-ramp slope angle. Double or triple benches can be
used in certain circumstances to steepen inter-ramp slopes.
2.Inter-ramp Slope – The maximum inter-ramp slope angle is typically dictated by the
bench geometry. However, it is also necessary to evaluate the potential for multiple
bench scale instabilities due to large-scale structural features such as faults, shear
zones, bedding planes, foliation etc. In some cases, these persistent features may
completely control the achievable inter-ramp angles and the slope may have to be
flattened to account for their presence
3. Overall Slope – The overall slope angle that is achieved in a pit is typically flatter
than the maximum inter-ramp angle due to the inclusion of haulage ramps. Other
factors that may reduce the overall slope angles are things such as rock mass
strength, groundwater pressures, blasting vibration, stress conditions and mine
equipment requirements
Mechanism of pit slope failure
• Mechanism of slope failure; when driving force exceed the
resisting force
• Factor of safety; the ratio of resisting force to the driving force, if
FS≤1 the slope will fail, if FS >the slope is theoretically stable
shear stress is a stress state where the stress is parallel to the surface of the material,
as opposed to normal stress when the stress is vertical to the surface. Shear stress is
relevant to the motion of fluids upon surfaces, which result in the generation of shear
stress.
A shear load is a force that tends to produce a sliding failure on a material along a
plane that is parallel to the direction of the force.
Shear strength is a material's ability to resist forces that can cause the internal structure of
the material to slide against itself. Adhesives tend to have high shear strength.
In engineering, shear strength is the strength of a material or component against the type
of yield or structural failure where the material or component fails in shear.
Shear strength is a term used in soil mechanics to describe the magnitude of the shear
stress that a soil can sustain.
Strength ;-the ability to resist being moved or broken by a force
Stress ;-pressure or tension exerted on a material objec
• Before mining the horizontal stress flows horizontal and vertical stresses due to
weight downward and are in equilibrium state. when an excavation is made the
flows horizontal and vertical stresses disturbed and equilibrium state break.
• With the excavation of the pit , the pre existing horizontal stresses are forced to
flow beneath the pit bottom an and around the pit
• The vertical stresses are also reduced through the removal of the rock overlying the
final slopes. This means that the rock lying between the pit outline and theses flow
lines largely distressed
• As a result of stress removal cracks/joints can open with a subsequent reduction in
cohesive and friction forces restraining the rock in place
• Further more ground water can more easily flow through these zones reducing the
effective normal force on potential
Failure plane
• As the pit is deepened the extend
of this distressed zone increases and
The consequence of failure becomes
more severe .the presence of adverse
structure like fault, dykes, weak zones
Etc further reduce resisting force
As soon as driving force exceed the
resisting force slope failure takes place
• Slope stability problem is greatest problem faced by the
open pit mining industry.
• The scale of slope stability problem is divided in to two
types:
1. Gross stability problem: It refer to large volumes of
materials which come down the slopes due to large
rotational type of shear failure and it involves deeply
weathered rock and soil.
2. Local stability problem: This problem which refers to much
smaller volume of material and these type of failure effect
one or two benches at a time due to shear plane jointing,
slope erosion due to surface drainage.
TYPES OF ROCK SLOPE FAILURES
• Failure in Earth and Rock mass
1. Plane Failure
2. Wedge Failure
3. Circular Failure
4. Toppling Failure Rock fall Fail
Failure in Earth, rock fill and spoil dumps and Embankments
1. Circular
2. Non-circular
3. semi-infinite slope
4. Multiple block plane wedge
5. Log spiral (bearing capacity of foundations)
6. Flow slides and Mud flow
7. Cracking
8. Gulling
9. Erosion Slide or Slump Figure.
Plane failure
• Simple plane failure is the easiest form of rock slope failure to analyze. It occurs when a discontinuity
striking approximately parallel to the slope face and dipping at a lower angle intersects the slope face,
enabling the material above the discontinuity to slide.
• A rock slope undergoes this mode of failure when combinations of discontinuities in the rock mass form
blocks or wedges within the rock which are free to move. The pattern of the discontinuities may be
comprised of a single discontinuity or a pair of discontinuities that intersect each other, or a
combination of multiple discontinuities that are linked together to form a failure mode.
• A planar failure of rock slope occurs when a mass of rock in a slope slides down along a relatively planar
failure surface. The failure surfaces are usually structural discontinuities such as bedding planes, faults,
joints or the interface between bedrock and an overlying layer of weathered rock.
• Plane failure can occur on the bench scale ,interramp scale and Pit wall scale
• The favorable conditions of plane failure are as follows:
1.The dip direction of the planar discontinuity must be within ( ±20o) of the dip direction of the slope face
2. The dip of the planar discontinuity must be less than the dip of the slope face (Daylight)
3.The dip of the planar discontinuity must be greater than the angle of friction of
the surface
• In open pit mining, mineral deposits are mined
from the ground surface and downward.
Consequently, pit slopes are formed as the ore is
being extracted.
• It is seldom, not to say never, possible to
maintain stable vertical slopes or pit walls of
substantial height even in very hard and strong
rock.
• The pit slopes must thus be inclined at some
angle to prevent failure of the rock mass
Wedge Failure:
• Wedge failure can occur in rock masses with two or more sets of discontinuities
whose lines of intersection are approximately perpendicular to the strike of the slope and
dip toward the plane of the slope.
• Wedge failure of rock slope results when rock mass slides along two intersecting
discontinuities, both of which dip out of the cut slope at an oblique angle to the cut face,
thus forming a wedge-shaped block
• Wedge failure can occur in rock mass with two or more sets of discontinuities whose lines of
intersection are approximately perpendicular to the strike of the slope and dip towards the
plane of the slope. This mode of failure requires that the dip angle of at least one joint
intersect is greater than the friction angle of the joint surfaces and that the line of joint
intersection intersects the plane of the slope.
• The necessary structural conditions for this failure are summarized as follows:
1. The trend of the line of intersection must approximate the dip direction of the slope face.
2. The plunge of the line of intersection must be less than the dip of the slope face. The line
of intersection under this
condition is said to daylight on
the slope.
3. The plunge of the line of
intersection must be greater
than the angle of friction of the
surface
Circular Failure
• Circular failures are generally occur in weak rock or soil slopes. Failures of this type do not necessarily occur along a
purely circular arc, some form of curved failure surface is normally apparent
• This failure can occurs in soil slopes, the circular method occurs when the joint sets are not very well defined. When
the material of the spoil dump slopes are weak such as soil, heavily jointed or broken rock mass
• The conditions under which circular failure occurs are follows:
1. When the individual particles of soil or rock mass, comprising the slopes are
small as compared to the slope.
2. When the particles are not locked as a result of their shape and tend to behave as soil.
• Types of circular failure
Circular failure is classified in three types depending on the area that is affected by the failure
surface. They are:-
(a) Slope failure: In this type of failure, the arc of the rupture surface meets the slope above the toe of the slope. This
happens when the slope angle is very high and the soil close to the toe posses the high strength.
(b) Toe failure: In this type of failure, the arc of the rupture surface meets the slope at the toe.
(c) Base failure: In this type of failure, the arc of the failure passes below the toe and in to base of the slope. This happens
when the slope angle is low and the soil below the base is softer and more plastic than the soil above the base.
Toppling failure
• Toppling failures occur when columns of rock, formed by steeply dipping
discontinuities in the rock structure and it involves overturning or rotation of rock
layers
• Toppling failures occur when columns of rock, formed by steeply dipping
discontinuities in the rock rotates about an essentially fixed point at or near the
base of the slope followed by slippage between the layers
• . The centre of gravity of the column or slab must fall outside the dimension of its
base in toppling failure. Jointed rock mass closely spaced and steeply dipping
discontinuity sets that dip away from the slope surface are necessary
prerequisites for toppling failure. The removal of overburden and the confining
rock, as is the case in mining excavations, can result in a partial relief of the
constraining stresses within the rock structure, resulting in a toppling failure
FACTORS AFFECTING SLOPE FAILURE
• Slope failure are often caused by processes that increase shear stress or decrease the shear strength of soil or rock mass. Residual soil and
weathered bed rock can be weekend by pre-existing discontinuities such as fault, bedding surface, foliation, cleavages, sheared zone, elict
joints ,dikes and sills.
• Slope failure occurs when the downward movements of material due to gravity and shear stresses exceeds the shear strength.
• Therefore, factors that tend to increase the shear stresses or decrease the shear strength increase the chances of failure of a slope.
• factors that tend to increase the shear stresses
1.REMOVAL OF SUPPORT
A. Erosions
1. By streams and rivers,
2. By glacial
3. By action of wave of water bodies and ocean
4. By successive wetting and drying(e.g winds ,freezing)
B. Natural slope movements(e.g falls, slides, settlements)
C. Human activity
1. Cuts and excavation
2. Removal of retaining wall or sheet piles
3. Drawdown's of bodies of water (e.g lakes ,lagoons)
2. OVERLOADING
A. By natural causes
1. Weight of precipitation(e.g rains and snow)
2. Accumulation of material because of past slides
B. By human activity
1. Construction of fill
2. Building and other overload on the crest
3. Water leakage in culverts, water pipes and sewers
3. TRANSITORY EFFECT ( EARTH QUACKS)
4. REMOVAL OF UNDER LYING MATERIAL THAT PROVIDES SUPPORT
1. By rivers and sea
2. By weathering
3. By underground erosion due to seepage, solvent action
4. By human activity e.g mining or excavation
5. By loss of strength of underlying material
5. INCRESE IN LATERAL PRESSURE
1. By water in crack and fissures
2. By freezing of water in cracks
3. By expansion of clay
FACTORS AFFECTING SLOPE FAILURE
• factors that tend to decrease the shear strength increase
1. Factors inherent in the nature of the material
• Composition
• Structure
• Secondary or inherited structures
• Stratification
2. Changes caused by weathering and physicochemical activities
• Wetting and drying processes
• Hydration
• Removal of cementing material
3. Effect of pore pressure
4. Change in structure
• Stress release
• Structural degradation
Prediction of slope failure
• Forecasting potential slope failure in open pit mines is integral to maintaining safety and mine productivity
1.Bulging ground appears at the base of a slope or a retaining wall *
2. Water breaks through the ground surface or appears in a location near or at the
base of a slope *
3. Fences, retaining walls, utility poles, or trees tilt or move *
4. Cracks appear on the slope *
5. Water pipes break *
6. Cracks appear on the ground or in the foundation *
7. Structures on slopes moving away from their original position
8. Doors or windows start to stick or jam *
9. Sunken or down-dropped road beds
10. Slowly developing, widening cracks on the ground or paved areas such as streets
or driveways *
11. Land movement and small slides could indicate unstable condition of the slope
that may lead to bigger failures *
12. Outside walls, walks, or stairs begin pulling away from building.
Signs of immediate danger
• THE signs of slope failure can materialise days, weeks, or
months before failure actually occurs. However, there are
some unmistakeable signs that manifest moments before a
landslide occurs. These should never be ignored and
evacuative action needs to be taken. Simply put, a landslide
is coming and you need to get out of its way immediately.
• A sudden decrease in creek water levels although rain is
still falling or has just stopped.
• A faint rumbling sound that increases in volume which
indicates the landslide is coming closer.
• Unusual sounds, such as trees cracking or boulders
knocking together, which could indicate moving debris.
Short-term prediction of mass movement
• Springs, seeps, or saturated ground in areas that have not typically been wet
before.
• New cracks or unusual bulges in the ground, street pavements or sidewalks.
• Soil moving away from foundations.
• Ancillary structures such as decks and patios tilting and/or moving relative to the
main house.
• Tilting or cracking of concrete floors and foundations.
• Broken water lines and other underground utilities.
• Leaning telephone poles, trees, retaining walls or fences
• Offset fence lines.
• Sunken or down-dropped road beds.
• Rapid increase in creek water levels, possibly accompanied by increased turbidity
(soil content).
• Sudden decrease in creek water levels though rain is still falling or just recently
stopped.
• Sticking doors and windows, and visible open spaces indicating jambs and frames
out of plumb.
• A faint rumbling sound that increases in volume is noticeable as the landslide
nears.
• Unusual sounds, such as trees cracking or boulders knocking together, might
indicate moving debris.
Slope Movement Monitoring
• Slope movement monitoring, even in its simplest form, should be carried out in all
mining situations.
• Regular visual inspection for signs of tension cracking, rock fall activity, slope
raveling, bulging in the slope face or heaving at the toe of a slope can provide
advanced warning of potential instability.
1. Visual slope monitoring by routine walkover inspections by the Geotechnical
Engineer. The Engineer compares the last visit observations with the latest one and
records any deleterious slope stability changes that may have occurred. The
recording of any changes that occur on the open pit slope faces by production
personnel during the shift is another way of visual slope monitoring. To this end,
slope hazard awareness lessons are conducted twice a year for all pit workers from
supervisor to operator.
2. Slope monitoring using the Geodetic Monitoring System (Geomos) survey
technique.
3. A slope monitoring report is issued containing the results of the visual monitoring
and the Geomos monitoring systems. The report has an action list of critical slope
stability issues requiring attention with time lines and responsible individuals
indicated. The report is issued to production, management and technical officials.
Depending on the duration of mining and the heights of the proposed mine slopes, an
array of reflective survey prisms located near the pit crest provides a baseline of
slope displacements, from which potential changes in slope behaviour can be
assessed. In potentially unstable areas where tension cracks or slope
Hazard of slope failure
• Physical impact can be of three types
1. Direct;- are those consequences incurred by direct physical contact with land slide itself
2. Indirect ;-are change brought about properties and behaviour of natural system as a result of landslide activity
3. Acute ;- immediate , short lived
4. Chronic;- delayed, long period
• Hazard to human life and property
• Injury and loss of life
• Property damage
• Failure of communication system
• Social and economic disruption
• Loss of productive land
• Ecological impact
• Change in hydrology
• Change in ground profile (topography)and land use pattern
• Change in soil and rock structure
• Loss of scenic beauty
• Loss of production,
• extra stripping costs to remove failed material,
• DGMS may close the mine
Aim of slope stability:
1. To understand the development and form of natural and man made
slopes and the processes responsible for different features.
2. To assess the stability of slopes under short-term (often during
construction) and long-term conditions.
3. To assess the possibility of slope failure involving natural or existing
engineered slopes.
4. To analyze slope stability and to understand failure mechanisms and the
influence of environmental factors.
5. To enable the redesign of failed slopes and the planning and design of
preventive and remedial measures, where necessary.
6. To study the effect of seismic loadings on slopes and embankments.
7. Safe, properly designed, scientifically engineered slope.
8. Profitability of open cast mines.
9. Design engineer/ scientist

More Related Content

What's hot

Slope stability analysis methods
Slope stability analysis methodsSlope stability analysis methods
Slope stability analysis methodszaidalFarhan1
 
GEOTECHNICAL SLOPE STABILITY
GEOTECHNICAL SLOPE STABILITYGEOTECHNICAL SLOPE STABILITY
GEOTECHNICAL SLOPE STABILITYNgo Hung Long
 
Geotechnical investigations for tunnelling
Geotechnical  investigations for tunnellingGeotechnical  investigations for tunnelling
Geotechnical investigations for tunnellingProf. A.Balasubramanian
 
R16 41013.2 stability analysis of slopes
R16 41013.2 stability analysis of slopesR16 41013.2 stability analysis of slopes
R16 41013.2 stability analysis of slopesPoorna Nagidi
 
Rock mechanic. lecture.12
Rock mechanic. lecture.12Rock mechanic. lecture.12
Rock mechanic. lecture.12batbold113o
 
Importance of geological considerations while choosing tunnel sites and align...
Importance of geological considerations while choosing tunnel sites and align...Importance of geological considerations while choosing tunnel sites and align...
Importance of geological considerations while choosing tunnel sites and align...Buddharatna godboley
 
Rock slope stability analysis lec 1
Rock slope stability analysis lec 1Rock slope stability analysis lec 1
Rock slope stability analysis lec 1aquarius123
 
Percussion drilling
Percussion drillingPercussion drilling
Percussion drillingshaxee ali
 
Slope stability using flac
Slope stability using flacSlope stability using flac
Slope stability using flacSafdar Ali
 
Rock mechanics for engineering geology part 3
Rock mechanics for engineering geology part 3Rock mechanics for engineering geology part 3
Rock mechanics for engineering geology part 3Jyoti Khatiwada
 
Slope monitoring & instrumentation
Slope monitoring & instrumentationSlope monitoring & instrumentation
Slope monitoring & instrumentationRathin Biswas
 
Lecture 2 basic surface mining practise-2
Lecture 2  basic surface mining practise-2Lecture 2  basic surface mining practise-2
Lecture 2 basic surface mining practise-2IDHAMUKI
 

What's hot (20)

Rock mechanics
Rock mechanicsRock mechanics
Rock mechanics
 
Rock Mass Classification
Rock Mass ClassificationRock Mass Classification
Rock Mass Classification
 
Slope stability analysis methods
Slope stability analysis methodsSlope stability analysis methods
Slope stability analysis methods
 
GEOTECHNICAL SLOPE STABILITY
GEOTECHNICAL SLOPE STABILITYGEOTECHNICAL SLOPE STABILITY
GEOTECHNICAL SLOPE STABILITY
 
Geotechnical investigations for tunnelling
Geotechnical  investigations for tunnellingGeotechnical  investigations for tunnelling
Geotechnical investigations for tunnelling
 
Insitu stresses and measurement
Insitu stresses and measurementInsitu stresses and measurement
Insitu stresses and measurement
 
Rock failure criteria
Rock failure criteriaRock failure criteria
Rock failure criteria
 
R16 41013.2 stability analysis of slopes
R16 41013.2 stability analysis of slopesR16 41013.2 stability analysis of slopes
R16 41013.2 stability analysis of slopes
 
Rock mechanic. lecture.12
Rock mechanic. lecture.12Rock mechanic. lecture.12
Rock mechanic. lecture.12
 
Importance of geological considerations while choosing tunnel sites and align...
Importance of geological considerations while choosing tunnel sites and align...Importance of geological considerations while choosing tunnel sites and align...
Importance of geological considerations while choosing tunnel sites and align...
 
Geotechnical properties of rocks
Geotechnical  properties  of rocksGeotechnical  properties  of rocks
Geotechnical properties of rocks
 
Rock slope stability analysis lec 1
Rock slope stability analysis lec 1Rock slope stability analysis lec 1
Rock slope stability analysis lec 1
 
Percussion drilling
Percussion drillingPercussion drilling
Percussion drilling
 
2 tunnels
2 tunnels2 tunnels
2 tunnels
 
Slope stability using flac
Slope stability using flacSlope stability using flac
Slope stability using flac
 
Rock mechanics for engineering geology part 3
Rock mechanics for engineering geology part 3Rock mechanics for engineering geology part 3
Rock mechanics for engineering geology part 3
 
Surface mining planning and design of open pit mining
Surface mining planning and design of open pit miningSurface mining planning and design of open pit mining
Surface mining planning and design of open pit mining
 
Slope monitoring & instrumentation
Slope monitoring & instrumentationSlope monitoring & instrumentation
Slope monitoring & instrumentation
 
Lecture 2 basic surface mining practise-2
Lecture 2  basic surface mining practise-2Lecture 2  basic surface mining practise-2
Lecture 2 basic surface mining practise-2
 
Slope stability
Slope stabilitySlope stability
Slope stability
 

Viewers also liked (16)

Barriere Paramassi Etag027 e Norme Tecniche delle Cstruzioni
Barriere Paramassi Etag027 e Norme Tecniche delle CstruzioniBarriere Paramassi Etag027 e Norme Tecniche delle Cstruzioni
Barriere Paramassi Etag027 e Norme Tecniche delle Cstruzioni
 
Rockyfor3D - Rockfall simulation program
Rockyfor3D - Rockfall simulation programRockyfor3D - Rockfall simulation program
Rockyfor3D - Rockfall simulation program
 
Slope stabilty
Slope stabiltySlope stabilty
Slope stabilty
 
Slope stability ii 2
Slope stability ii 2Slope stability ii 2
Slope stability ii 2
 
Injury prevention and control
Injury prevention and controlInjury prevention and control
Injury prevention and control
 
4 Barrier Design 2008
4   Barrier Design 20084   Barrier Design 2008
4 Barrier Design 2008
 
Slope stability
Slope stabilitySlope stability
Slope stability
 
Rockyfor3 software
Rockyfor3 softwareRockyfor3 software
Rockyfor3 software
 
Slope Stability by GeoMads
Slope Stability by GeoMadsSlope Stability by GeoMads
Slope Stability by GeoMads
 
New design approach on rockfall Embankment
New design approach on rockfall Embankment New design approach on rockfall Embankment
New design approach on rockfall Embankment
 
slope stability and computers
 slope stability and computers slope stability and computers
slope stability and computers
 
1 Macro Intro 2008
1  Macro Intro 20081  Macro Intro 2008
1 Macro Intro 2008
 
Soil slope stability
Soil slope stabilitySoil slope stability
Soil slope stability
 
8 slope stability
8 slope stability8 slope stability
8 slope stability
 
AI for IA's: Machine Learning Demystified at IA Summit 2017 - IAS17
AI for IA's: Machine Learning Demystified at IA Summit 2017 - IAS17AI for IA's: Machine Learning Demystified at IA Summit 2017 - IAS17
AI for IA's: Machine Learning Demystified at IA Summit 2017 - IAS17
 
AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017
AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017
AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017
 

Similar to Slope stability

Structural Geology
Structural  GeologyStructural  Geology
Structural GeologyUsama Zia
 
UNIT-V Slope Stability - Land Slides.ppt
UNIT-V Slope Stability - Land Slides.pptUNIT-V Slope Stability - Land Slides.ppt
UNIT-V Slope Stability - Land Slides.pptmythili spd
 
Advance Construction Technology
Advance Construction Technology Advance Construction Technology
Advance Construction Technology GAURAV. H .TANDON
 
Structural Geology Folds
Structural Geology    FoldsStructural Geology    Folds
Structural Geology FoldsMazahir Haider
 
joints and its classification and its recognition
joints and its classification and its recognitionjoints and its classification and its recognition
joints and its classification and its recognitionShivam Jain
 
Folds and foldings
Folds and foldingsFolds and foldings
Folds and foldingsRAHUL SINHA
 
GEOLOGICAL CONDITIONS NECESSARY FOR CONSTRUCTION OF DAMS
GEOLOGICAL CONDITIONS NECESSARY FOR CONSTRUCTION OF DAMSGEOLOGICAL CONDITIONS NECESSARY FOR CONSTRUCTION OF DAMS
GEOLOGICAL CONDITIONS NECESSARY FOR CONSTRUCTION OF DAMSLorevieOlaes
 
Earthquake Terminology & causes
Earthquake Terminology & causes Earthquake Terminology & causes
Earthquake Terminology & causes RAMPRASAD KUMAWAT
 
Trenching & Excavation
Trenching & ExcavationTrenching & Excavation
Trenching & ExcavationShivananda Roy
 
Ch10 structuralgeologyfall2007-140429091340-phpapp02
Ch10 structuralgeologyfall2007-140429091340-phpapp02Ch10 structuralgeologyfall2007-140429091340-phpapp02
Ch10 structuralgeologyfall2007-140429091340-phpapp02Cleophas Rwemera
 

Similar to Slope stability (20)

Slope stability
Slope stabilitySlope stability
Slope stability
 
Structural Geology
Structural  GeologyStructural  Geology
Structural Geology
 
UNIT-V Slope Stability - Land Slides.ppt
UNIT-V Slope Stability - Land Slides.pptUNIT-V Slope Stability - Land Slides.ppt
UNIT-V Slope Stability - Land Slides.ppt
 
Fold .pptx
Fold .pptxFold .pptx
Fold .pptx
 
Mine waste dump
Mine waste dumpMine waste dump
Mine waste dump
 
Circular failure
Circular failureCircular failure
Circular failure
 
fault & faulting
fault & faultingfault & faulting
fault & faulting
 
Advance Construction Technology
Advance Construction Technology Advance Construction Technology
Advance Construction Technology
 
Circular slabs
Circular slabs Circular slabs
Circular slabs
 
Structural Geology Folds
Structural Geology    FoldsStructural Geology    Folds
Structural Geology Folds
 
joints and its classification and its recognition
joints and its classification and its recognitionjoints and its classification and its recognition
joints and its classification and its recognition
 
Shivam jain
Shivam jainShivam jain
Shivam jain
 
dcs ppt .pptx
dcs ppt .pptxdcs ppt .pptx
dcs ppt .pptx
 
Folds and foldings
Folds and foldingsFolds and foldings
Folds and foldings
 
GEOLOGICAL CONDITIONS NECESSARY FOR CONSTRUCTION OF DAMS
GEOLOGICAL CONDITIONS NECESSARY FOR CONSTRUCTION OF DAMSGEOLOGICAL CONDITIONS NECESSARY FOR CONSTRUCTION OF DAMS
GEOLOGICAL CONDITIONS NECESSARY FOR CONSTRUCTION OF DAMS
 
Earthquake Terminology & causes
Earthquake Terminology & causes Earthquake Terminology & causes
Earthquake Terminology & causes
 
footing file 2.ppt
footing file 2.pptfooting file 2.ppt
footing file 2.ppt
 
foundations.ppt
foundations.pptfoundations.ppt
foundations.ppt
 
Trenching & Excavation
Trenching & ExcavationTrenching & Excavation
Trenching & Excavation
 
Ch10 structuralgeologyfall2007-140429091340-phpapp02
Ch10 structuralgeologyfall2007-140429091340-phpapp02Ch10 structuralgeologyfall2007-140429091340-phpapp02
Ch10 structuralgeologyfall2007-140429091340-phpapp02
 

More from VIJAY KUMAR

Introduction to Civil Engg. Unit-II.pdf
Introduction to Civil Engg. Unit-II.pdfIntroduction to Civil Engg. Unit-II.pdf
Introduction to Civil Engg. Unit-II.pdfVIJAY KUMAR
 
Introduction to Civil Engg. Unit-IV.pdf
Introduction to Civil Engg. Unit-IV.pdfIntroduction to Civil Engg. Unit-IV.pdf
Introduction to Civil Engg. Unit-IV.pdfVIJAY KUMAR
 
Introduction to Civil Engg. Unit-III.pdf
Introduction to Civil Engg. Unit-III.pdfIntroduction to Civil Engg. Unit-III.pdf
Introduction to Civil Engg. Unit-III.pdfVIJAY KUMAR
 
Introduction to Civil Engg. Unit-I.pdf
Introduction to Civil Engg. Unit-I.pdfIntroduction to Civil Engg. Unit-I.pdf
Introduction to Civil Engg. Unit-I.pdfVIJAY KUMAR
 
Surface Mining dozer
Surface Mining dozerSurface Mining dozer
Surface Mining dozerVIJAY KUMAR
 
Ripper production
Ripper productionRipper production
Ripper productionVIJAY KUMAR
 
Environmental Audit in Mining
Environmental Audit in MiningEnvironmental Audit in Mining
Environmental Audit in MiningVIJAY KUMAR
 
Sustanable mining
Sustanable miningSustanable mining
Sustanable miningVIJAY KUMAR
 
Surface mining entry system
Surface mining entry systemSurface mining entry system
Surface mining entry systemVIJAY KUMAR
 
The continuous surface miner
The continuous surface minerThe continuous surface miner
The continuous surface minerVIJAY KUMAR
 

More from VIJAY KUMAR (12)

Introduction to Civil Engg. Unit-II.pdf
Introduction to Civil Engg. Unit-II.pdfIntroduction to Civil Engg. Unit-II.pdf
Introduction to Civil Engg. Unit-II.pdf
 
Introduction to Civil Engg. Unit-IV.pdf
Introduction to Civil Engg. Unit-IV.pdfIntroduction to Civil Engg. Unit-IV.pdf
Introduction to Civil Engg. Unit-IV.pdf
 
Introduction to Civil Engg. Unit-III.pdf
Introduction to Civil Engg. Unit-III.pdfIntroduction to Civil Engg. Unit-III.pdf
Introduction to Civil Engg. Unit-III.pdf
 
Introduction to Civil Engg. Unit-I.pdf
Introduction to Civil Engg. Unit-I.pdfIntroduction to Civil Engg. Unit-I.pdf
Introduction to Civil Engg. Unit-I.pdf
 
Surface Mining dozer
Surface Mining dozerSurface Mining dozer
Surface Mining dozer
 
Ripper production
Ripper productionRipper production
Ripper production
 
Environmental Audit in Mining
Environmental Audit in MiningEnvironmental Audit in Mining
Environmental Audit in Mining
 
Sustanable mining
Sustanable miningSustanable mining
Sustanable mining
 
Mining dumper
Mining dumperMining dumper
Mining dumper
 
Surface mining entry system
Surface mining entry systemSurface mining entry system
Surface mining entry system
 
The continuous surface miner
The continuous surface minerThe continuous surface miner
The continuous surface miner
 
Sizing
SizingSizing
Sizing
 

Recently uploaded

Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...christianmathematics
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsTechSoup
 
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Shubhangi Sonawane
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.christianmathematics
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDThiyagu K
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactPECB
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Disha Kariya
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxDenish Jangid
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docxPoojaSen20
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...KokoStevan
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docxPoojaSen20
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhikauryashika82
 
Gardella_PRCampaignConclusion Pitch Letter
Gardella_PRCampaignConclusion Pitch LetterGardella_PRCampaignConclusion Pitch Letter
Gardella_PRCampaignConclusion Pitch LetterMateoGardella
 

Recently uploaded (20)

Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07
 
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docx
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docx
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
Gardella_PRCampaignConclusion Pitch Letter
Gardella_PRCampaignConclusion Pitch LetterGardella_PRCampaignConclusion Pitch Letter
Gardella_PRCampaignConclusion Pitch Letter
 

Slope stability

  • 2. Slope • Mathematicians have developed a useful measure of the steepness of a line, called the slope of the line. • Slope compares the vertical change (the rise) to the horizontal change (the run) when moving from one fixed point to another along the line
  • 3. Slope is expressed by 1. An angle from horizontal i.e 24°45° 2. As a gradient i.e 1 in 4as a vertical fall 3. centimetre per meter
  • 4. Gradient • The method to calculate the Gradient is: • Divide the change in height by the change in horizontal distance • Gradient = Change in Y/Change in X •
  • 5. Types of open pit slopes • Slopes in quarries can result from a range of activities associated with the working of the site. There are three principal types of slope to be considered: 1. Excavated slopes (in which in situ ground is exposed); 2. Tipped slopes (where loose material is formed into mounds either above ground in placed in existing voids); and 3. Natural slopes (which may be affected by excavations or placement of loose materials). On the basis of duration pit slopes can be 1. Short term slopes – stockpiles and soil mounds, intermediate quarry faces; 2. Medium term slopes – soil mounds, quarry faces, screening bunds, etc.; and 3. Long term slopes – quarry faces, spoil mounds, lagoon embankments, screening bunds.
  • 6. Types of open pit slopes • Unimportant slope • Average slope • Critical slope • Unimportant slope;- slope angles unimportant economically and flat slopes can be used • Average slope;- slopes angles are important but not critical in determining economics of mining • Critical slope;- slope angle critical in terms of both economics of mining and safety of operations
  • 7. Types of open pit slopes • In open pit mining, mineral deposits are mined from the ground surface and downward. Consequently, pit slopes are formed as the ore is being extracted. • The various types of pit slopes are 1. Bench slope 2. Overall pit slope 3. Current overall pit slope 4. Haul road slope, 5. Ramp slope 6. Inter ramp slope 7. dump slope
  • 8. Types of Slope Failure
  • 9. • Bench slope or bank angle: it the angle measured in degree between the horizontal and an imaginary line connecting bench toe to the bench crest. It is an inclined plane of the bench which limits it on the side worked out space. • overall pit slope angle: it the angle measured in degree between the horizontal and an imaginary line connecting bottom bench toe to the top bench crest. • Current overall pit slope;- it the angle measured in degree between the horizontal and an imaginary line connecting existing bottom bench toe to the existing top bench crest at a given time. • Ramp slope;-The gradient on a ramp is the grade line profile along the road centre line, in the vertical plane. • Dump slope;- it the angle measured in degree between the horizontal and an imaginary line connecting toe of dump to the existing top crest at a given time. • The interramp slope angle is measured from toe to toe or crest to crest exclusive of any ramps. By excluding ramps or other offsets the interramp angle is kept static no matter how many benches are measured. The interramp angle is similar to the face angle because it is static.
  • 10. PIT SLOPE GEOMETRIES • There are numbers of slope which inters into pit design. Care is needed so that there is no confusion as to how they are calculated and what they mean . The main are bench slope, overall pit slope , , ramp slope, interramp slope etc. • There are three major component of a pit slope 1. Bench configuration 2. Interramp slope 3. Overall slope • The bench configuration is defined by bench face angle, the bench height and bench width. • The interramp angle is the slope angle produced by a number of benches. Where there are haul roads ,working levels or other wide benches • The overall pit slope is the angle of the line from the toe to the crest of the pit.and will be flatter than interramp slope. • It is important to consider all three components in slope design • In order to make a quantities estimate of the stability of aslope analytical models amenable to mathematical solutions must be used • The requrements of these modeles are the failure geometry and assumption regarding materila properties and stress distributions. • While active mining is under way ,some working benches would be included in the overall slope. • At the end of mining it is desired to leave the final pit slope as steep as possible, some of safety benches will be reduced in width while others may be eliminated entirely.`
  • 11. Types of Slope Failure
  • 12. PIT SLOPE GEOMETRIES • The primary components of a pit design are as follows: 1. Bench Geometry – • The height of the benches is typically determined by the size of the shovel chosen for the mining operation. • The bench face angle is usually selected in such a way as to reduce, to an acceptable level, the amount of material that will likely fall from the face or crest. • The bench width is sized to prevent small wedges and blocks from the bench faces falling down the slope and potentially impacting men and equipment. • The bench geometry that results from the bench face angle and bench width will ultimately dictate the inter-ramp slope angle. Double or triple benches can be used in certain circumstances to steepen inter-ramp slopes. 2.Inter-ramp Slope – The maximum inter-ramp slope angle is typically dictated by the bench geometry. However, it is also necessary to evaluate the potential for multiple bench scale instabilities due to large-scale structural features such as faults, shear zones, bedding planes, foliation etc. In some cases, these persistent features may completely control the achievable inter-ramp angles and the slope may have to be flattened to account for their presence 3. Overall Slope – The overall slope angle that is achieved in a pit is typically flatter than the maximum inter-ramp angle due to the inclusion of haulage ramps. Other factors that may reduce the overall slope angles are things such as rock mass strength, groundwater pressures, blasting vibration, stress conditions and mine equipment requirements
  • 13. Mechanism of pit slope failure • Mechanism of slope failure; when driving force exceed the resisting force • Factor of safety; the ratio of resisting force to the driving force, if FS≤1 the slope will fail, if FS >the slope is theoretically stable
  • 14. shear stress is a stress state where the stress is parallel to the surface of the material, as opposed to normal stress when the stress is vertical to the surface. Shear stress is relevant to the motion of fluids upon surfaces, which result in the generation of shear stress. A shear load is a force that tends to produce a sliding failure on a material along a plane that is parallel to the direction of the force. Shear strength is a material's ability to resist forces that can cause the internal structure of the material to slide against itself. Adhesives tend to have high shear strength. In engineering, shear strength is the strength of a material or component against the type of yield or structural failure where the material or component fails in shear. Shear strength is a term used in soil mechanics to describe the magnitude of the shear stress that a soil can sustain. Strength ;-the ability to resist being moved or broken by a force Stress ;-pressure or tension exerted on a material objec
  • 15. • Before mining the horizontal stress flows horizontal and vertical stresses due to weight downward and are in equilibrium state. when an excavation is made the flows horizontal and vertical stresses disturbed and equilibrium state break. • With the excavation of the pit , the pre existing horizontal stresses are forced to flow beneath the pit bottom an and around the pit • The vertical stresses are also reduced through the removal of the rock overlying the final slopes. This means that the rock lying between the pit outline and theses flow lines largely distressed • As a result of stress removal cracks/joints can open with a subsequent reduction in cohesive and friction forces restraining the rock in place • Further more ground water can more easily flow through these zones reducing the effective normal force on potential Failure plane • As the pit is deepened the extend of this distressed zone increases and The consequence of failure becomes more severe .the presence of adverse structure like fault, dykes, weak zones Etc further reduce resisting force As soon as driving force exceed the resisting force slope failure takes place
  • 16. • Slope stability problem is greatest problem faced by the open pit mining industry. • The scale of slope stability problem is divided in to two types: 1. Gross stability problem: It refer to large volumes of materials which come down the slopes due to large rotational type of shear failure and it involves deeply weathered rock and soil. 2. Local stability problem: This problem which refers to much smaller volume of material and these type of failure effect one or two benches at a time due to shear plane jointing, slope erosion due to surface drainage.
  • 17. TYPES OF ROCK SLOPE FAILURES • Failure in Earth and Rock mass 1. Plane Failure 2. Wedge Failure 3. Circular Failure 4. Toppling Failure Rock fall Fail Failure in Earth, rock fill and spoil dumps and Embankments 1. Circular 2. Non-circular 3. semi-infinite slope 4. Multiple block plane wedge 5. Log spiral (bearing capacity of foundations) 6. Flow slides and Mud flow 7. Cracking 8. Gulling 9. Erosion Slide or Slump Figure.
  • 18.
  • 19.
  • 20. Plane failure • Simple plane failure is the easiest form of rock slope failure to analyze. It occurs when a discontinuity striking approximately parallel to the slope face and dipping at a lower angle intersects the slope face, enabling the material above the discontinuity to slide. • A rock slope undergoes this mode of failure when combinations of discontinuities in the rock mass form blocks or wedges within the rock which are free to move. The pattern of the discontinuities may be comprised of a single discontinuity or a pair of discontinuities that intersect each other, or a combination of multiple discontinuities that are linked together to form a failure mode. • A planar failure of rock slope occurs when a mass of rock in a slope slides down along a relatively planar failure surface. The failure surfaces are usually structural discontinuities such as bedding planes, faults, joints or the interface between bedrock and an overlying layer of weathered rock. • Plane failure can occur on the bench scale ,interramp scale and Pit wall scale • The favorable conditions of plane failure are as follows: 1.The dip direction of the planar discontinuity must be within ( ±20o) of the dip direction of the slope face 2. The dip of the planar discontinuity must be less than the dip of the slope face (Daylight) 3.The dip of the planar discontinuity must be greater than the angle of friction of the surface
  • 21. • In open pit mining, mineral deposits are mined from the ground surface and downward. Consequently, pit slopes are formed as the ore is being extracted. • It is seldom, not to say never, possible to maintain stable vertical slopes or pit walls of substantial height even in very hard and strong rock. • The pit slopes must thus be inclined at some angle to prevent failure of the rock mass
  • 22. Wedge Failure: • Wedge failure can occur in rock masses with two or more sets of discontinuities whose lines of intersection are approximately perpendicular to the strike of the slope and dip toward the plane of the slope. • Wedge failure of rock slope results when rock mass slides along two intersecting discontinuities, both of which dip out of the cut slope at an oblique angle to the cut face, thus forming a wedge-shaped block • Wedge failure can occur in rock mass with two or more sets of discontinuities whose lines of intersection are approximately perpendicular to the strike of the slope and dip towards the plane of the slope. This mode of failure requires that the dip angle of at least one joint intersect is greater than the friction angle of the joint surfaces and that the line of joint intersection intersects the plane of the slope. • The necessary structural conditions for this failure are summarized as follows: 1. The trend of the line of intersection must approximate the dip direction of the slope face. 2. The plunge of the line of intersection must be less than the dip of the slope face. The line of intersection under this condition is said to daylight on the slope. 3. The plunge of the line of intersection must be greater than the angle of friction of the surface
  • 23. Circular Failure • Circular failures are generally occur in weak rock or soil slopes. Failures of this type do not necessarily occur along a purely circular arc, some form of curved failure surface is normally apparent • This failure can occurs in soil slopes, the circular method occurs when the joint sets are not very well defined. When the material of the spoil dump slopes are weak such as soil, heavily jointed or broken rock mass • The conditions under which circular failure occurs are follows: 1. When the individual particles of soil or rock mass, comprising the slopes are small as compared to the slope. 2. When the particles are not locked as a result of their shape and tend to behave as soil. • Types of circular failure Circular failure is classified in three types depending on the area that is affected by the failure surface. They are:- (a) Slope failure: In this type of failure, the arc of the rupture surface meets the slope above the toe of the slope. This happens when the slope angle is very high and the soil close to the toe posses the high strength. (b) Toe failure: In this type of failure, the arc of the rupture surface meets the slope at the toe. (c) Base failure: In this type of failure, the arc of the failure passes below the toe and in to base of the slope. This happens when the slope angle is low and the soil below the base is softer and more plastic than the soil above the base.
  • 24. Toppling failure • Toppling failures occur when columns of rock, formed by steeply dipping discontinuities in the rock structure and it involves overturning or rotation of rock layers • Toppling failures occur when columns of rock, formed by steeply dipping discontinuities in the rock rotates about an essentially fixed point at or near the base of the slope followed by slippage between the layers • . The centre of gravity of the column or slab must fall outside the dimension of its base in toppling failure. Jointed rock mass closely spaced and steeply dipping discontinuity sets that dip away from the slope surface are necessary prerequisites for toppling failure. The removal of overburden and the confining rock, as is the case in mining excavations, can result in a partial relief of the constraining stresses within the rock structure, resulting in a toppling failure
  • 25. FACTORS AFFECTING SLOPE FAILURE • Slope failure are often caused by processes that increase shear stress or decrease the shear strength of soil or rock mass. Residual soil and weathered bed rock can be weekend by pre-existing discontinuities such as fault, bedding surface, foliation, cleavages, sheared zone, elict joints ,dikes and sills. • Slope failure occurs when the downward movements of material due to gravity and shear stresses exceeds the shear strength. • Therefore, factors that tend to increase the shear stresses or decrease the shear strength increase the chances of failure of a slope. • factors that tend to increase the shear stresses 1.REMOVAL OF SUPPORT A. Erosions 1. By streams and rivers, 2. By glacial 3. By action of wave of water bodies and ocean 4. By successive wetting and drying(e.g winds ,freezing) B. Natural slope movements(e.g falls, slides, settlements) C. Human activity 1. Cuts and excavation 2. Removal of retaining wall or sheet piles 3. Drawdown's of bodies of water (e.g lakes ,lagoons) 2. OVERLOADING A. By natural causes 1. Weight of precipitation(e.g rains and snow) 2. Accumulation of material because of past slides B. By human activity 1. Construction of fill 2. Building and other overload on the crest 3. Water leakage in culverts, water pipes and sewers 3. TRANSITORY EFFECT ( EARTH QUACKS) 4. REMOVAL OF UNDER LYING MATERIAL THAT PROVIDES SUPPORT 1. By rivers and sea 2. By weathering 3. By underground erosion due to seepage, solvent action 4. By human activity e.g mining or excavation 5. By loss of strength of underlying material 5. INCRESE IN LATERAL PRESSURE 1. By water in crack and fissures 2. By freezing of water in cracks 3. By expansion of clay
  • 26. FACTORS AFFECTING SLOPE FAILURE • factors that tend to decrease the shear strength increase 1. Factors inherent in the nature of the material • Composition • Structure • Secondary or inherited structures • Stratification 2. Changes caused by weathering and physicochemical activities • Wetting and drying processes • Hydration • Removal of cementing material 3. Effect of pore pressure 4. Change in structure • Stress release • Structural degradation
  • 27.
  • 28. Prediction of slope failure • Forecasting potential slope failure in open pit mines is integral to maintaining safety and mine productivity
  • 29. 1.Bulging ground appears at the base of a slope or a retaining wall * 2. Water breaks through the ground surface or appears in a location near or at the base of a slope * 3. Fences, retaining walls, utility poles, or trees tilt or move * 4. Cracks appear on the slope * 5. Water pipes break * 6. Cracks appear on the ground or in the foundation * 7. Structures on slopes moving away from their original position 8. Doors or windows start to stick or jam * 9. Sunken or down-dropped road beds 10. Slowly developing, widening cracks on the ground or paved areas such as streets or driveways * 11. Land movement and small slides could indicate unstable condition of the slope that may lead to bigger failures * 12. Outside walls, walks, or stairs begin pulling away from building.
  • 30. Signs of immediate danger • THE signs of slope failure can materialise days, weeks, or months before failure actually occurs. However, there are some unmistakeable signs that manifest moments before a landslide occurs. These should never be ignored and evacuative action needs to be taken. Simply put, a landslide is coming and you need to get out of its way immediately. • A sudden decrease in creek water levels although rain is still falling or has just stopped. • A faint rumbling sound that increases in volume which indicates the landslide is coming closer. • Unusual sounds, such as trees cracking or boulders knocking together, which could indicate moving debris.
  • 31. Short-term prediction of mass movement • Springs, seeps, or saturated ground in areas that have not typically been wet before. • New cracks or unusual bulges in the ground, street pavements or sidewalks. • Soil moving away from foundations. • Ancillary structures such as decks and patios tilting and/or moving relative to the main house. • Tilting or cracking of concrete floors and foundations. • Broken water lines and other underground utilities. • Leaning telephone poles, trees, retaining walls or fences • Offset fence lines. • Sunken or down-dropped road beds. • Rapid increase in creek water levels, possibly accompanied by increased turbidity (soil content). • Sudden decrease in creek water levels though rain is still falling or just recently stopped. • Sticking doors and windows, and visible open spaces indicating jambs and frames out of plumb. • A faint rumbling sound that increases in volume is noticeable as the landslide nears. • Unusual sounds, such as trees cracking or boulders knocking together, might indicate moving debris.
  • 32. Slope Movement Monitoring • Slope movement monitoring, even in its simplest form, should be carried out in all mining situations. • Regular visual inspection for signs of tension cracking, rock fall activity, slope raveling, bulging in the slope face or heaving at the toe of a slope can provide advanced warning of potential instability. 1. Visual slope monitoring by routine walkover inspections by the Geotechnical Engineer. The Engineer compares the last visit observations with the latest one and records any deleterious slope stability changes that may have occurred. The recording of any changes that occur on the open pit slope faces by production personnel during the shift is another way of visual slope monitoring. To this end, slope hazard awareness lessons are conducted twice a year for all pit workers from supervisor to operator. 2. Slope monitoring using the Geodetic Monitoring System (Geomos) survey technique. 3. A slope monitoring report is issued containing the results of the visual monitoring and the Geomos monitoring systems. The report has an action list of critical slope stability issues requiring attention with time lines and responsible individuals indicated. The report is issued to production, management and technical officials. Depending on the duration of mining and the heights of the proposed mine slopes, an array of reflective survey prisms located near the pit crest provides a baseline of slope displacements, from which potential changes in slope behaviour can be assessed. In potentially unstable areas where tension cracks or slope
  • 33. Hazard of slope failure • Physical impact can be of three types 1. Direct;- are those consequences incurred by direct physical contact with land slide itself 2. Indirect ;-are change brought about properties and behaviour of natural system as a result of landslide activity 3. Acute ;- immediate , short lived 4. Chronic;- delayed, long period • Hazard to human life and property • Injury and loss of life • Property damage • Failure of communication system • Social and economic disruption • Loss of productive land • Ecological impact • Change in hydrology • Change in ground profile (topography)and land use pattern • Change in soil and rock structure • Loss of scenic beauty • Loss of production, • extra stripping costs to remove failed material, • DGMS may close the mine
  • 34. Aim of slope stability: 1. To understand the development and form of natural and man made slopes and the processes responsible for different features. 2. To assess the stability of slopes under short-term (often during construction) and long-term conditions. 3. To assess the possibility of slope failure involving natural or existing engineered slopes. 4. To analyze slope stability and to understand failure mechanisms and the influence of environmental factors. 5. To enable the redesign of failed slopes and the planning and design of preventive and remedial measures, where necessary. 6. To study the effect of seismic loadings on slopes and embankments. 7. Safe, properly designed, scientifically engineered slope. 8. Profitability of open cast mines. 9. Design engineer/ scientist