Strategic Product Development and Cost
Estimates for Futuristic Products
Vedant Borse (HCL AXON)
 Understand Product Costing and Challenges with
estimating cost of Future Product
 Eliminate Manual/ Excel based calculations and
reduces the risk of estimation variance
 Closed loop Solution Approach for accurate Product
Costing, Planning and Execution
LEARNING POINTS
How do I estimate Cost?
Detailed Level Estimates
BOM with
Detailed
Part List
•Travel
•Freight
•Contract
•Labor
•Vehicle
•Parts
•Test
CostManpower
+
Executive Advance Planning Departments/ Project
- 6Years - 4Years - 3Years
High Level #1 Estimates
Buildable Combinations
Matrix (BCM)
•Travel
•Freight
•Contract
•Labor
•Vehicle
•Parts
•Test
CostManpower
+
• Development Complexity Known
• Feature List Unknown
• Parts List Unknown
High Level #2 Estimates
Features and Parts
List (High Level)
Features List
•Travel
•Freight
•Contract
•Labor
•Vehicle
•Parts
•Test
CostManpower
+
• Feature List Known
• Parts List Partial
• Development Complexity Calculated
• Parts List Known
• Feature List Known
• Development Complexity Calculated
Reduce Estimation
Accuracy to: +/- 5%
Reduce Estimation
Accuracy to: +/- 0.5%
Challenge 1: Varying YoY Cost Estimates
-10%
-5%
0%
5%
10%
15%
20%
0
50
100
150
200
250
300
Year 6 Year 5 Year 4 Year 3 Year 2 Year 1 Actual
Cost
Variance
Cause
 Development Assumption Not Clear in Early Stage
 Estimator include Buffer in budget
 Detail Spending Is not clear
Sample Lifetime Cost History for a Single Vehicle Development Estimates
Variance
~20% Variance
Year on Year Estimation Est. Vs Actual
~5% Var.
Challenge 2: High Consolidated Variance
(80.00)
(60.00)
(40.00)
(20.00)
-
20.00
40.00
60.00
Year 6 Year 5 Year 4 Year 3 Year 2 Year 1 Actual
Product F
Product E
Product D
Product C
Product B
Product A
Total Variance
Issues
 Poor Estimation Accuracy occurs in all projects.
 Poor Spending Control occurs in all projects.
Year on Year Estimation Est. Vs Actual
Actual
 No Part List/ BOM data results in to estimate cost Long estimation process
 Varying range of complexities, type of development, its flow, duration, etc leads
to hundreds of permutation and combination to estimate a product cost for
Labor, Parts, Products, Design, Build, Test, Prototype Cost, Whitebody, etc.
 Unclear varying factors forces use of weak resource estimates technique
resulting in Inaccuracy in Project Resource Planning for future Products (Eg. 20%
avg. variance/Prj )
 Shorter time to market and increasing variant launch (Minor Model, Major
Model, NPDI) adds to more pressure on estimates and product development,
resulting in incorrect estimates
 Use of custom tools or Excels adds difficulty in collating estimates from multiple
business units
 Unavailability of robust estimation technique limits alternatives/ estimates
scenarios (Eg. 3/Prj), thus Limiting alternatives/ estimates scenarios for Lineup
Planning of multiple vehicle and multiple launch years projects
Future Product Cost Estimates Challenges
 Microsoft Excel
 Custom Home Grown Solution
 MS Access
 Highly customized PLM Solution
 Guestimates/ Person Dependent
Current Estimation Tools
 Varying Year on Year costing estimates results
in Bad Image to investor
 More reporting requests, thus requiring large
pool of planning resources required for
estimation and report preparation
 Inability to created multiple estimates
scenarios for each vehicle, while creating
single lineup for all vehicles across globe for
each variant becomes distant possibility
Consequence
HCL AXON PLM Practice
• Resource expertise in SAP PLM
PLM Highlight:
 Leader in SAP PLM Implementation (12+ years practice, 40+ implementation)
 HCL AXON has amongst the highest number of PLM client references
 SAP PLM/PPM Practice COE’s in US, Asia and Europe
Unique Industry Specialization:
 Pharmaceuticals, Consumer Healthcare, Consumer Packaged Goods, Discrete Manufacturing and Professional Services. Delivered the
largest PPM user in Pharma and the most complex project in CPG
Platform Pioneer
 Developed an accelerator for PLM/PPM in Consumer Healthcare
 First SAP partner globally for the Rapid Deployment Solution (RDS) of Portfolio and Project Management (SAP PPM)
 SAP partner globally for the Rapid Deployment Solution (RDS) for Visual Enterprise (VE)
 SAP Ramp up Partner with dedicated SAP PLM Lab (PPM 6.0, PLM 7.0)
SAP Endorsement
 Co-authored R&D whitepapers with SAP
 More Sapphire conference success stories than any other partner
 Top collaborator with SAP for PLM in Life Sciences
Manufacturers pursuing integrated PLM/MES/ERP
environments in HCL's primary industries - particularly
those with SAP as their ERP platform - should consider HCL
for PLM services.
“
Solution options
 Easy Cost Planning
 PDCE
 iPPE
 BOBJ PCM
Criteria
 No Material Master, varying range of complexities, type of development, its
flow, duration,
 Show possible permutation and combination
 Calculate 2.5 Billion data combination and generate results for
 Cost: Labor, Parts, Products, Design, Build, Test, Prototype Cost, etc.
 Quantity: Manpower, Products, BOM/MM, etc
Solution Options
 Combination of Process improvement with enablement
via right technology should be the mantra
 Build a closed loop estimation process
Closed loop Solution: SAP PPM+PCM+ECC
f(x)
Approval
Workflow
PCM
Profitability & Cost Management
PPM
Portfolio & Project Management
Project Execution
FinancialTime Reporting
Features and Parts
Project System
Project Highlights
 First PPM-PCM Integration
 First Unified UI Integration
 First PCM-BODS-PCM Real-
time Integration
 Automotive Estimation formulas are very complex
 They involve varying parameters
 Type of development (Minor Model, Major Model Change MMC),
Full Model (FMC) or New Product (NPDI))
 Varying range of complexities (Carryover, Modify, New)
 Build Lot (Stages of Development) and duration
 Development flow
 Departments (Body, chassis, Interior, Electrical, Transmission, etc
 While estimating the process Crash test vehicles has further complex
dimension
 Every Company has a complex formula for estimation
 N_Motor CFM: Common Module Family
 F_Motor BCM: Buildable Combinations Matrix
 T and Y Motor has similar methods
Define Formula
BOBJ-PCM Formula and Lookup
Super User can control
Formula Tables, Condition to
apply specific Table, Structure
of Table and Formula
 Build Estimation Projects
 Extent Project for Next Levels of Estimation
 Extent Estimation Project to Execution Project
 Variance Analysis between estimates and Actuals to
improve the formula via a Closed Loop process
(PCM-PPM-ECC Integration)
 Build a Lineup view of all the projects stacked
together
Define Project and Lineup
Project Planning and Estimation Inputs
Calculation in PCM
Underlying Calculation in
PCM from inputs from PPM
Rollup Estimation to Project and Lineup
Lineup Summarization
SAP Implementation (Old vs New)NewSystem(SAP)OldSystem(Manual)
Resource Estimation and
Formula
Project Resource
Estimation
Lineup Scenario
Resource Simulation
Financial
Manual Process
Project Estimates
Project Lineup
f(x)
Approval
Workflow
PCM
Profitability & Cost Management
PPM
Portfolio & Project Management
Project System
Project Execution
Financial
Time Reporting
TTP Project
Benefits
-Improved Accuracy from 20% to
5% due to formula PDCA
-Best Decision Making due to
Alternatives: 3 scenarios to10
scenarios
- Huge Annual Saving in terms of
Estimation House and Cost
Issues:
-Manual Repeat process
-Low Accuracy
-More Efforts
Timesheet
Calculation via
spreadsheets
Calculation via
spreadsheets
Parts
System
Parts
System
High Efforts/ yrs for
Estimation
Lower Simulation/
Project
High Efforts/ Project for
Estimation
Higher Simulation/
Project
Lower Efforts/ Project
for Estimation
 Better Planning decisions, by providing:
 More accurate estimates. Accuracy improvement from
 20% avg./Prj → 5% avg./Prj
(If condition change, clear analysis reasons)
 More lineup alternatives. Increase Alternatives from:
 3 scenarios→10 scenarios
 Time Saving
 Forecasters time: 130hrs/Prj→10hrs/Project (About $0.4M
Saving)
Benefits
THANK YOU
THANK YOU FOR PARTICIPATING
Vedant Borse
Solution Architect, PLM / PPM / PCM
HCL AXON
EAS Division – HCL Technologies
15 Exchange Place, Suite 730, Jersey City, NJ 07302
Mob: +1 919 744 6166
www.hcl-axon.com
www.hcltech.com
www.hcl.com
HCL Booth #213

More Related Content

What's hot

Developing Product Configurator Tool Using CADs’ API with the help of Paramet...
Developing Product Configurator Tool Using CADs’ API with the help of Paramet...Developing Product Configurator Tool Using CADs’ API with the help of Paramet...
Developing Product Configurator Tool Using CADs’ API with the help of Paramet...ijcax
 
RichardStephensResume2
RichardStephensResume2RichardStephensResume2
RichardStephensResume2Shane Stephens
 
]project-open[ Budget Planning and Tracking
]project-open[ Budget Planning and Tracking]project-open[ Budget Planning and Tracking
]project-open[ Budget Planning and TrackingKlaus Hofeditz
 

What's hot (7)

Punya_Resume
Punya_ResumePunya_Resume
Punya_Resume
 
CAS Aviation Suite
CAS Aviation SuiteCAS Aviation Suite
CAS Aviation Suite
 
Developing Product Configurator Tool Using CADs’ API with the help of Paramet...
Developing Product Configurator Tool Using CADs’ API with the help of Paramet...Developing Product Configurator Tool Using CADs’ API with the help of Paramet...
Developing Product Configurator Tool Using CADs’ API with the help of Paramet...
 
C a1 fin_10
C a1 fin_10C a1 fin_10
C a1 fin_10
 
RichardStephensResume2
RichardStephensResume2RichardStephensResume2
RichardStephensResume2
 
Loading cost in primavera schedule using resources and expenses r01
Loading cost in primavera schedule using resources and expenses r01Loading cost in primavera schedule using resources and expenses r01
Loading cost in primavera schedule using resources and expenses r01
 
]project-open[ Budget Planning and Tracking
]project-open[ Budget Planning and Tracking]project-open[ Budget Planning and Tracking
]project-open[ Budget Planning and Tracking
 

Similar to Strategic Product Development and Cost Estimates for Automotive Industry

2012 connectionpoint pcammisa_hpcm
2012 connectionpoint pcammisa_hpcm2012 connectionpoint pcammisa_hpcm
2012 connectionpoint pcammisa_hpcmInnovusPartners
 
1. Profile Presentation - CostICon
1. Profile Presentation - CostICon1. Profile Presentation - CostICon
1. Profile Presentation - CostIConSuyash Shah
 
Sudheer_SAP_ABAP_Resume
Sudheer_SAP_ABAP_ResumeSudheer_SAP_ABAP_Resume
Sudheer_SAP_ABAP_ResumeSudheer babu
 
Priyanka Shrivastava - Career Snapshot
Priyanka Shrivastava - Career SnapshotPriyanka Shrivastava - Career Snapshot
Priyanka Shrivastava - Career Snapshotpriyanka shrivastava
 
Six sigma ajal
Six sigma ajalSix sigma ajal
Six sigma ajalAJAL A J
 
Experience Snap Shot Presentation (Design 3)
Experience Snap Shot Presentation (Design 3)Experience Snap Shot Presentation (Design 3)
Experience Snap Shot Presentation (Design 3)rdebgupta
 
CS8494 SOFTWARE ENGINEERING Unit-5
CS8494 SOFTWARE ENGINEERING Unit-5CS8494 SOFTWARE ENGINEERING Unit-5
CS8494 SOFTWARE ENGINEERING Unit-5SIMONTHOMAS S
 
Concept development using Optimization, DFM & CAE - In DFSS Way
Concept development using Optimization, DFM & CAE - In DFSS WayConcept development using Optimization, DFM & CAE - In DFSS Way
Concept development using Optimization, DFM & CAE - In DFSS Waynsahay
 
Measure phase lean six sigma tollgate template
Measure phase   lean six sigma tollgate templateMeasure phase   lean six sigma tollgate template
Measure phase lean six sigma tollgate templateSteven Bonacorsi
 
Measure phase lean six sigma tollgate template
Measure phase   lean six sigma tollgate templateMeasure phase   lean six sigma tollgate template
Measure phase lean six sigma tollgate templateSteven Bonacorsi
 
Demantra Case Study Doug
Demantra Case Study DougDemantra Case Study Doug
Demantra Case Study Dougsichie
 
21UCAE52 Software Project Management.ppt
21UCAE52 Software Project Management.ppt21UCAE52 Software Project Management.ppt
21UCAE52 Software Project Management.pptssuser7f90ae
 
Estimation maturity model using function points
Estimation maturity  model using function pointsEstimation maturity  model using function points
Estimation maturity model using function pointsBhupinder Singh
 
Pm Scheduling Cost Pricing
Pm Scheduling Cost PricingPm Scheduling Cost Pricing
Pm Scheduling Cost Pricingjonathan077070
 
Raymond V. Joos resume
Raymond V. Joos resumeRaymond V. Joos resume
Raymond V. Joos resumeJoos Ray
 
Joc Saber Idiq And You December 2nd 2010 Web Cast Final
Joc Saber Idiq  And You December 2nd 2010    Web Cast   FinalJoc Saber Idiq  And You December 2nd 2010    Web Cast   Final
Joc Saber Idiq And You December 2nd 2010 Web Cast Finalpcholakis30
 
How to estimate the cost of a Maximo migration project with a high level of c...
How to estimate the cost of a Maximo migration project with a high level of c...How to estimate the cost of a Maximo migration project with a high level of c...
How to estimate the cost of a Maximo migration project with a high level of c...Mariano Zelaya Feijoo
 

Similar to Strategic Product Development and Cost Estimates for Automotive Industry (20)

2012 connectionpoint pcammisa_hpcm
2012 connectionpoint pcammisa_hpcm2012 connectionpoint pcammisa_hpcm
2012 connectionpoint pcammisa_hpcm
 
Rnd
RndRnd
Rnd
 
1. Profile Presentation - CostICon
1. Profile Presentation - CostICon1. Profile Presentation - CostICon
1. Profile Presentation - CostICon
 
Sudheer_SAP_ABAP_Resume
Sudheer_SAP_ABAP_ResumeSudheer_SAP_ABAP_Resume
Sudheer_SAP_ABAP_Resume
 
Priyanka Shrivastava - Career Snapshot
Priyanka Shrivastava - Career SnapshotPriyanka Shrivastava - Career Snapshot
Priyanka Shrivastava - Career Snapshot
 
Ranjeev Kumar Chaudhary
Ranjeev Kumar ChaudharyRanjeev Kumar Chaudhary
Ranjeev Kumar Chaudhary
 
Six sigma ajal
Six sigma ajalSix sigma ajal
Six sigma ajal
 
Experience Snap Shot Presentation (Design 3)
Experience Snap Shot Presentation (Design 3)Experience Snap Shot Presentation (Design 3)
Experience Snap Shot Presentation (Design 3)
 
Intake Process Itpmo
Intake Process ItpmoIntake Process Itpmo
Intake Process Itpmo
 
CS8494 SOFTWARE ENGINEERING Unit-5
CS8494 SOFTWARE ENGINEERING Unit-5CS8494 SOFTWARE ENGINEERING Unit-5
CS8494 SOFTWARE ENGINEERING Unit-5
 
Concept development using Optimization, DFM & CAE - In DFSS Way
Concept development using Optimization, DFM & CAE - In DFSS WayConcept development using Optimization, DFM & CAE - In DFSS Way
Concept development using Optimization, DFM & CAE - In DFSS Way
 
Measure phase lean six sigma tollgate template
Measure phase   lean six sigma tollgate templateMeasure phase   lean six sigma tollgate template
Measure phase lean six sigma tollgate template
 
Measure phase lean six sigma tollgate template
Measure phase   lean six sigma tollgate templateMeasure phase   lean six sigma tollgate template
Measure phase lean six sigma tollgate template
 
Demantra Case Study Doug
Demantra Case Study DougDemantra Case Study Doug
Demantra Case Study Doug
 
21UCAE52 Software Project Management.ppt
21UCAE52 Software Project Management.ppt21UCAE52 Software Project Management.ppt
21UCAE52 Software Project Management.ppt
 
Estimation maturity model using function points
Estimation maturity  model using function pointsEstimation maturity  model using function points
Estimation maturity model using function points
 
Pm Scheduling Cost Pricing
Pm Scheduling Cost PricingPm Scheduling Cost Pricing
Pm Scheduling Cost Pricing
 
Raymond V. Joos resume
Raymond V. Joos resumeRaymond V. Joos resume
Raymond V. Joos resume
 
Joc Saber Idiq And You December 2nd 2010 Web Cast Final
Joc Saber Idiq  And You December 2nd 2010    Web Cast   FinalJoc Saber Idiq  And You December 2nd 2010    Web Cast   Final
Joc Saber Idiq And You December 2nd 2010 Web Cast Final
 
How to estimate the cost of a Maximo migration project with a high level of c...
How to estimate the cost of a Maximo migration project with a high level of c...How to estimate the cost of a Maximo migration project with a high level of c...
How to estimate the cost of a Maximo migration project with a high level of c...
 

More from Vedant Borse

SAP Sapphire 2019: WEEE- SAP Recycling Administration
SAP Sapphire 2019: WEEE- SAP Recycling AdministrationSAP Sapphire 2019: WEEE- SAP Recycling Administration
SAP Sapphire 2019: WEEE- SAP Recycling AdministrationVedant Borse
 
2901_ASUG_SAP_BOUC_iGPL_Perrigo_v3
2901_ASUG_SAP_BOUC_iGPL_Perrigo_v32901_ASUG_SAP_BOUC_iGPL_Perrigo_v3
2901_ASUG_SAP_BOUC_iGPL_Perrigo_v3Vedant Borse
 
3803_Strategic Product Development_ASUG v4
3803_Strategic Product Development_ASUG v43803_Strategic Product Development_ASUG v4
3803_Strategic Product Development_ASUG v4Vedant Borse
 
Packaging, Labeling and Artwork Management
Packaging, Labeling and Artwork ManagementPackaging, Labeling and Artwork Management
Packaging, Labeling and Artwork ManagementVedant Borse
 
SAP Sapphire 2012: Integrated Global Packaging, Artwork and Labeling
SAP Sapphire 2012: Integrated Global Packaging, Artwork and LabelingSAP Sapphire 2012: Integrated Global Packaging, Artwork and Labeling
SAP Sapphire 2012: Integrated Global Packaging, Artwork and LabelingVedant Borse
 
White Paper: Product Regulatory Compliance
White Paper: Product Regulatory ComplianceWhite Paper: Product Regulatory Compliance
White Paper: Product Regulatory ComplianceVedant Borse
 

More from Vedant Borse (7)

Vedant Borse
Vedant BorseVedant Borse
Vedant Borse
 
SAP Sapphire 2019: WEEE- SAP Recycling Administration
SAP Sapphire 2019: WEEE- SAP Recycling AdministrationSAP Sapphire 2019: WEEE- SAP Recycling Administration
SAP Sapphire 2019: WEEE- SAP Recycling Administration
 
2901_ASUG_SAP_BOUC_iGPL_Perrigo_v3
2901_ASUG_SAP_BOUC_iGPL_Perrigo_v32901_ASUG_SAP_BOUC_iGPL_Perrigo_v3
2901_ASUG_SAP_BOUC_iGPL_Perrigo_v3
 
3803_Strategic Product Development_ASUG v4
3803_Strategic Product Development_ASUG v43803_Strategic Product Development_ASUG v4
3803_Strategic Product Development_ASUG v4
 
Packaging, Labeling and Artwork Management
Packaging, Labeling and Artwork ManagementPackaging, Labeling and Artwork Management
Packaging, Labeling and Artwork Management
 
SAP Sapphire 2012: Integrated Global Packaging, Artwork and Labeling
SAP Sapphire 2012: Integrated Global Packaging, Artwork and LabelingSAP Sapphire 2012: Integrated Global Packaging, Artwork and Labeling
SAP Sapphire 2012: Integrated Global Packaging, Artwork and Labeling
 
White Paper: Product Regulatory Compliance
White Paper: Product Regulatory ComplianceWhite Paper: Product Regulatory Compliance
White Paper: Product Regulatory Compliance
 

Recently uploaded

Is Your Mercedes Benz Trunk Refusing To Close Here's What Might Be Wrong
Is Your Mercedes Benz Trunk Refusing To Close Here's What Might Be WrongIs Your Mercedes Benz Trunk Refusing To Close Here's What Might Be Wrong
Is Your Mercedes Benz Trunk Refusing To Close Here's What Might Be WrongMomentum Motorworks
 
Changodar Call Girls Book Now 7737669865 Top Class Escort Service Available
Changodar Call Girls Book Now 7737669865 Top Class Escort Service AvailableChangodar Call Girls Book Now 7737669865 Top Class Escort Service Available
Changodar Call Girls Book Now 7737669865 Top Class Escort Service Availablegargpaaro
 
如何办理(NCL毕业证书)纽卡斯尔大学毕业证毕业证成绩单原版一比一
如何办理(NCL毕业证书)纽卡斯尔大学毕业证毕业证成绩单原版一比一如何办理(NCL毕业证书)纽卡斯尔大学毕业证毕业证成绩单原版一比一
如何办理(NCL毕业证书)纽卡斯尔大学毕业证毕业证成绩单原版一比一avy6anjnd
 
Electronic Stability Program. (ESP).pptx
Electronic Stability Program. (ESP).pptxElectronic Stability Program. (ESP).pptx
Electronic Stability Program. (ESP).pptxmohamedAabdeltwab
 
What Does The Engine Malfunction Reduced Power Message Mean For Your BMW X5
What Does The Engine Malfunction Reduced Power Message Mean For Your BMW X5What Does The Engine Malfunction Reduced Power Message Mean For Your BMW X5
What Does The Engine Malfunction Reduced Power Message Mean For Your BMW X5Bavarian Workshop
 
一比一原版(Greenwich毕业证书)格林威治大学毕业证如何办理
一比一原版(Greenwich毕业证书)格林威治大学毕业证如何办理一比一原版(Greenwich毕业证书)格林威治大学毕业证如何办理
一比一原版(Greenwich毕业证书)格林威治大学毕业证如何办理bd2c5966a56d
 
West Bengal Factories Rules, 1958.bfpptx
West Bengal Factories Rules, 1958.bfpptxWest Bengal Factories Rules, 1958.bfpptx
West Bengal Factories Rules, 1958.bfpptxPankajBhagat45
 
一比一原版(PU学位证书)普渡大学毕业证学历认证加急办理
一比一原版(PU学位证书)普渡大学毕业证学历认证加急办理一比一原版(PU学位证书)普渡大学毕业证学历认证加急办理
一比一原版(PU学位证书)普渡大学毕业证学历认证加急办理ezgenuh
 
Is Your Volvo XC90 Displaying Anti-Skid Service Required Alert Here's Why
Is Your Volvo XC90 Displaying Anti-Skid Service Required Alert Here's WhyIs Your Volvo XC90 Displaying Anti-Skid Service Required Alert Here's Why
Is Your Volvo XC90 Displaying Anti-Skid Service Required Alert Here's WhyBavarium Autoworks
 
Premium Call Girls Nagpur Call Girls (Adult Only) 💯Call Us 🔝 6378878445 🔝 💃 E...
Premium Call Girls Nagpur Call Girls (Adult Only) 💯Call Us 🔝 6378878445 🔝 💃 E...Premium Call Girls Nagpur Call Girls (Adult Only) 💯Call Us 🔝 6378878445 🔝 💃 E...
Premium Call Girls Nagpur Call Girls (Adult Only) 💯Call Us 🔝 6378878445 🔝 💃 E...vershagrag
 
如何办理多伦多大学毕业证(UofT毕业证书)成绩单原版一比一
如何办理多伦多大学毕业证(UofT毕业证书)成绩单原版一比一如何办理多伦多大学毕业证(UofT毕业证书)成绩单原版一比一
如何办理多伦多大学毕业证(UofT毕业证书)成绩单原版一比一opyff
 
John Deere Tractors 5415 Diagnostic Repair Service Manual.pdf
John Deere Tractors 5415 Diagnostic Repair Service Manual.pdfJohn Deere Tractors 5415 Diagnostic Repair Service Manual.pdf
John Deere Tractors 5415 Diagnostic Repair Service Manual.pdfExcavator
 
Top profile Call Girls In Thrissur [ 7014168258 ] Call Me For Genuine Models ...
Top profile Call Girls In Thrissur [ 7014168258 ] Call Me For Genuine Models ...Top profile Call Girls In Thrissur [ 7014168258 ] Call Me For Genuine Models ...
Top profile Call Girls In Thrissur [ 7014168258 ] Call Me For Genuine Models ...nirzagarg
 
如何办理新西兰林肯大学毕业证(Lincoln毕业证书)成绩单原版一比一
如何办理新西兰林肯大学毕业证(Lincoln毕业证书)成绩单原版一比一如何办理新西兰林肯大学毕业证(Lincoln毕业证书)成绩单原版一比一
如何办理新西兰林肯大学毕业证(Lincoln毕业证书)成绩单原版一比一opyff
 
Muslim Call Girls Churchgate WhatsApp +91-9930687706, Best Service
Muslim Call Girls Churchgate WhatsApp +91-9930687706, Best ServiceMuslim Call Girls Churchgate WhatsApp +91-9930687706, Best Service
Muslim Call Girls Churchgate WhatsApp +91-9930687706, Best Servicemeghakumariji156
 
Washim Call Girls 📞9332606886 Call Girls in Washim Escorts service book now C...
Washim Call Girls 📞9332606886 Call Girls in Washim Escorts service book now C...Washim Call Girls 📞9332606886 Call Girls in Washim Escorts service book now C...
Washim Call Girls 📞9332606886 Call Girls in Washim Escorts service book now C...Dipal Arora
 
一比一原版西安大略大学毕业证(UWO毕业证)成绩单原件一模一样
一比一原版西安大略大学毕业证(UWO毕业证)成绩单原件一模一样一比一原版西安大略大学毕业证(UWO毕业证)成绩单原件一模一样
一比一原版西安大略大学毕业证(UWO毕业证)成绩单原件一模一样wsppdmt
 
What Does It Mean When Mercedes Says 'ESP Inoperative See Owner's Manual'
What Does It Mean When Mercedes Says 'ESP Inoperative See Owner's Manual'What Does It Mean When Mercedes Says 'ESP Inoperative See Owner's Manual'
What Does It Mean When Mercedes Says 'ESP Inoperative See Owner's Manual'Euromotive Performance
 
Top profile Call Girls In Ranchi [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Ranchi [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Ranchi [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Ranchi [ 7014168258 ] Call Me For Genuine Models We...gajnagarg
 

Recently uploaded (20)

Is Your Mercedes Benz Trunk Refusing To Close Here's What Might Be Wrong
Is Your Mercedes Benz Trunk Refusing To Close Here's What Might Be WrongIs Your Mercedes Benz Trunk Refusing To Close Here's What Might Be Wrong
Is Your Mercedes Benz Trunk Refusing To Close Here's What Might Be Wrong
 
Changodar Call Girls Book Now 7737669865 Top Class Escort Service Available
Changodar Call Girls Book Now 7737669865 Top Class Escort Service AvailableChangodar Call Girls Book Now 7737669865 Top Class Escort Service Available
Changodar Call Girls Book Now 7737669865 Top Class Escort Service Available
 
如何办理(NCL毕业证书)纽卡斯尔大学毕业证毕业证成绩单原版一比一
如何办理(NCL毕业证书)纽卡斯尔大学毕业证毕业证成绩单原版一比一如何办理(NCL毕业证书)纽卡斯尔大学毕业证毕业证成绩单原版一比一
如何办理(NCL毕业证书)纽卡斯尔大学毕业证毕业证成绩单原版一比一
 
Electronic Stability Program. (ESP).pptx
Electronic Stability Program. (ESP).pptxElectronic Stability Program. (ESP).pptx
Electronic Stability Program. (ESP).pptx
 
Abortion pills Dubai (+918133066128) Cytotec 200mg pills UAE Abudhabi
Abortion pills Dubai (+918133066128) Cytotec 200mg pills UAE AbudhabiAbortion pills Dubai (+918133066128) Cytotec 200mg pills UAE Abudhabi
Abortion pills Dubai (+918133066128) Cytotec 200mg pills UAE Abudhabi
 
What Does The Engine Malfunction Reduced Power Message Mean For Your BMW X5
What Does The Engine Malfunction Reduced Power Message Mean For Your BMW X5What Does The Engine Malfunction Reduced Power Message Mean For Your BMW X5
What Does The Engine Malfunction Reduced Power Message Mean For Your BMW X5
 
一比一原版(Greenwich毕业证书)格林威治大学毕业证如何办理
一比一原版(Greenwich毕业证书)格林威治大学毕业证如何办理一比一原版(Greenwich毕业证书)格林威治大学毕业证如何办理
一比一原版(Greenwich毕业证书)格林威治大学毕业证如何办理
 
West Bengal Factories Rules, 1958.bfpptx
West Bengal Factories Rules, 1958.bfpptxWest Bengal Factories Rules, 1958.bfpptx
West Bengal Factories Rules, 1958.bfpptx
 
一比一原版(PU学位证书)普渡大学毕业证学历认证加急办理
一比一原版(PU学位证书)普渡大学毕业证学历认证加急办理一比一原版(PU学位证书)普渡大学毕业证学历认证加急办理
一比一原版(PU学位证书)普渡大学毕业证学历认证加急办理
 
Is Your Volvo XC90 Displaying Anti-Skid Service Required Alert Here's Why
Is Your Volvo XC90 Displaying Anti-Skid Service Required Alert Here's WhyIs Your Volvo XC90 Displaying Anti-Skid Service Required Alert Here's Why
Is Your Volvo XC90 Displaying Anti-Skid Service Required Alert Here's Why
 
Premium Call Girls Nagpur Call Girls (Adult Only) 💯Call Us 🔝 6378878445 🔝 💃 E...
Premium Call Girls Nagpur Call Girls (Adult Only) 💯Call Us 🔝 6378878445 🔝 💃 E...Premium Call Girls Nagpur Call Girls (Adult Only) 💯Call Us 🔝 6378878445 🔝 💃 E...
Premium Call Girls Nagpur Call Girls (Adult Only) 💯Call Us 🔝 6378878445 🔝 💃 E...
 
如何办理多伦多大学毕业证(UofT毕业证书)成绩单原版一比一
如何办理多伦多大学毕业证(UofT毕业证书)成绩单原版一比一如何办理多伦多大学毕业证(UofT毕业证书)成绩单原版一比一
如何办理多伦多大学毕业证(UofT毕业证书)成绩单原版一比一
 
John Deere Tractors 5415 Diagnostic Repair Service Manual.pdf
John Deere Tractors 5415 Diagnostic Repair Service Manual.pdfJohn Deere Tractors 5415 Diagnostic Repair Service Manual.pdf
John Deere Tractors 5415 Diagnostic Repair Service Manual.pdf
 
Top profile Call Girls In Thrissur [ 7014168258 ] Call Me For Genuine Models ...
Top profile Call Girls In Thrissur [ 7014168258 ] Call Me For Genuine Models ...Top profile Call Girls In Thrissur [ 7014168258 ] Call Me For Genuine Models ...
Top profile Call Girls In Thrissur [ 7014168258 ] Call Me For Genuine Models ...
 
如何办理新西兰林肯大学毕业证(Lincoln毕业证书)成绩单原版一比一
如何办理新西兰林肯大学毕业证(Lincoln毕业证书)成绩单原版一比一如何办理新西兰林肯大学毕业证(Lincoln毕业证书)成绩单原版一比一
如何办理新西兰林肯大学毕业证(Lincoln毕业证书)成绩单原版一比一
 
Muslim Call Girls Churchgate WhatsApp +91-9930687706, Best Service
Muslim Call Girls Churchgate WhatsApp +91-9930687706, Best ServiceMuslim Call Girls Churchgate WhatsApp +91-9930687706, Best Service
Muslim Call Girls Churchgate WhatsApp +91-9930687706, Best Service
 
Washim Call Girls 📞9332606886 Call Girls in Washim Escorts service book now C...
Washim Call Girls 📞9332606886 Call Girls in Washim Escorts service book now C...Washim Call Girls 📞9332606886 Call Girls in Washim Escorts service book now C...
Washim Call Girls 📞9332606886 Call Girls in Washim Escorts service book now C...
 
一比一原版西安大略大学毕业证(UWO毕业证)成绩单原件一模一样
一比一原版西安大略大学毕业证(UWO毕业证)成绩单原件一模一样一比一原版西安大略大学毕业证(UWO毕业证)成绩单原件一模一样
一比一原版西安大略大学毕业证(UWO毕业证)成绩单原件一模一样
 
What Does It Mean When Mercedes Says 'ESP Inoperative See Owner's Manual'
What Does It Mean When Mercedes Says 'ESP Inoperative See Owner's Manual'What Does It Mean When Mercedes Says 'ESP Inoperative See Owner's Manual'
What Does It Mean When Mercedes Says 'ESP Inoperative See Owner's Manual'
 
Top profile Call Girls In Ranchi [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Ranchi [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Ranchi [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Ranchi [ 7014168258 ] Call Me For Genuine Models We...
 

Strategic Product Development and Cost Estimates for Automotive Industry

  • 1. Orange County Convention Center Orlando, Florida | June 3-5, 2014 Strategic Product Development and Cost Estimates for Futuristic Products Vedant Borse (HCL AXON)
  • 2.  Understand Product Costing and Challenges with estimating cost of Future Product  Eliminate Manual/ Excel based calculations and reduces the risk of estimation variance  Closed loop Solution Approach for accurate Product Costing, Planning and Execution LEARNING POINTS
  • 3. How do I estimate Cost? Detailed Level Estimates BOM with Detailed Part List •Travel •Freight •Contract •Labor •Vehicle •Parts •Test CostManpower + Executive Advance Planning Departments/ Project - 6Years - 4Years - 3Years High Level #1 Estimates Buildable Combinations Matrix (BCM) •Travel •Freight •Contract •Labor •Vehicle •Parts •Test CostManpower + • Development Complexity Known • Feature List Unknown • Parts List Unknown High Level #2 Estimates Features and Parts List (High Level) Features List •Travel •Freight •Contract •Labor •Vehicle •Parts •Test CostManpower + • Feature List Known • Parts List Partial • Development Complexity Calculated • Parts List Known • Feature List Known • Development Complexity Calculated Reduce Estimation Accuracy to: +/- 5% Reduce Estimation Accuracy to: +/- 0.5%
  • 4. Challenge 1: Varying YoY Cost Estimates -10% -5% 0% 5% 10% 15% 20% 0 50 100 150 200 250 300 Year 6 Year 5 Year 4 Year 3 Year 2 Year 1 Actual Cost Variance Cause  Development Assumption Not Clear in Early Stage  Estimator include Buffer in budget  Detail Spending Is not clear Sample Lifetime Cost History for a Single Vehicle Development Estimates Variance ~20% Variance Year on Year Estimation Est. Vs Actual ~5% Var.
  • 5. Challenge 2: High Consolidated Variance (80.00) (60.00) (40.00) (20.00) - 20.00 40.00 60.00 Year 6 Year 5 Year 4 Year 3 Year 2 Year 1 Actual Product F Product E Product D Product C Product B Product A Total Variance Issues  Poor Estimation Accuracy occurs in all projects.  Poor Spending Control occurs in all projects. Year on Year Estimation Est. Vs Actual Actual
  • 6.  No Part List/ BOM data results in to estimate cost Long estimation process  Varying range of complexities, type of development, its flow, duration, etc leads to hundreds of permutation and combination to estimate a product cost for Labor, Parts, Products, Design, Build, Test, Prototype Cost, Whitebody, etc.  Unclear varying factors forces use of weak resource estimates technique resulting in Inaccuracy in Project Resource Planning for future Products (Eg. 20% avg. variance/Prj )  Shorter time to market and increasing variant launch (Minor Model, Major Model, NPDI) adds to more pressure on estimates and product development, resulting in incorrect estimates  Use of custom tools or Excels adds difficulty in collating estimates from multiple business units  Unavailability of robust estimation technique limits alternatives/ estimates scenarios (Eg. 3/Prj), thus Limiting alternatives/ estimates scenarios for Lineup Planning of multiple vehicle and multiple launch years projects Future Product Cost Estimates Challenges
  • 7.  Microsoft Excel  Custom Home Grown Solution  MS Access  Highly customized PLM Solution  Guestimates/ Person Dependent Current Estimation Tools
  • 8.  Varying Year on Year costing estimates results in Bad Image to investor  More reporting requests, thus requiring large pool of planning resources required for estimation and report preparation  Inability to created multiple estimates scenarios for each vehicle, while creating single lineup for all vehicles across globe for each variant becomes distant possibility Consequence
  • 9. HCL AXON PLM Practice • Resource expertise in SAP PLM PLM Highlight:  Leader in SAP PLM Implementation (12+ years practice, 40+ implementation)  HCL AXON has amongst the highest number of PLM client references  SAP PLM/PPM Practice COE’s in US, Asia and Europe Unique Industry Specialization:  Pharmaceuticals, Consumer Healthcare, Consumer Packaged Goods, Discrete Manufacturing and Professional Services. Delivered the largest PPM user in Pharma and the most complex project in CPG Platform Pioneer  Developed an accelerator for PLM/PPM in Consumer Healthcare  First SAP partner globally for the Rapid Deployment Solution (RDS) of Portfolio and Project Management (SAP PPM)  SAP partner globally for the Rapid Deployment Solution (RDS) for Visual Enterprise (VE)  SAP Ramp up Partner with dedicated SAP PLM Lab (PPM 6.0, PLM 7.0) SAP Endorsement  Co-authored R&D whitepapers with SAP  More Sapphire conference success stories than any other partner  Top collaborator with SAP for PLM in Life Sciences Manufacturers pursuing integrated PLM/MES/ERP environments in HCL's primary industries - particularly those with SAP as their ERP platform - should consider HCL for PLM services. “
  • 10. Solution options  Easy Cost Planning  PDCE  iPPE  BOBJ PCM Criteria  No Material Master, varying range of complexities, type of development, its flow, duration,  Show possible permutation and combination  Calculate 2.5 Billion data combination and generate results for  Cost: Labor, Parts, Products, Design, Build, Test, Prototype Cost, etc.  Quantity: Manpower, Products, BOM/MM, etc Solution Options
  • 11.  Combination of Process improvement with enablement via right technology should be the mantra  Build a closed loop estimation process Closed loop Solution: SAP PPM+PCM+ECC f(x) Approval Workflow PCM Profitability & Cost Management PPM Portfolio & Project Management Project Execution FinancialTime Reporting Features and Parts Project System Project Highlights  First PPM-PCM Integration  First Unified UI Integration  First PCM-BODS-PCM Real- time Integration
  • 12.  Automotive Estimation formulas are very complex  They involve varying parameters  Type of development (Minor Model, Major Model Change MMC), Full Model (FMC) or New Product (NPDI))  Varying range of complexities (Carryover, Modify, New)  Build Lot (Stages of Development) and duration  Development flow  Departments (Body, chassis, Interior, Electrical, Transmission, etc  While estimating the process Crash test vehicles has further complex dimension  Every Company has a complex formula for estimation  N_Motor CFM: Common Module Family  F_Motor BCM: Buildable Combinations Matrix  T and Y Motor has similar methods Define Formula
  • 13. BOBJ-PCM Formula and Lookup Super User can control Formula Tables, Condition to apply specific Table, Structure of Table and Formula
  • 14.  Build Estimation Projects  Extent Project for Next Levels of Estimation  Extent Estimation Project to Execution Project  Variance Analysis between estimates and Actuals to improve the formula via a Closed Loop process (PCM-PPM-ECC Integration)  Build a Lineup view of all the projects stacked together Define Project and Lineup
  • 15. Project Planning and Estimation Inputs
  • 16. Calculation in PCM Underlying Calculation in PCM from inputs from PPM
  • 17. Rollup Estimation to Project and Lineup
  • 19. SAP Implementation (Old vs New)NewSystem(SAP)OldSystem(Manual) Resource Estimation and Formula Project Resource Estimation Lineup Scenario Resource Simulation Financial Manual Process Project Estimates Project Lineup f(x) Approval Workflow PCM Profitability & Cost Management PPM Portfolio & Project Management Project System Project Execution Financial Time Reporting TTP Project Benefits -Improved Accuracy from 20% to 5% due to formula PDCA -Best Decision Making due to Alternatives: 3 scenarios to10 scenarios - Huge Annual Saving in terms of Estimation House and Cost Issues: -Manual Repeat process -Low Accuracy -More Efforts Timesheet Calculation via spreadsheets Calculation via spreadsheets Parts System Parts System High Efforts/ yrs for Estimation Lower Simulation/ Project High Efforts/ Project for Estimation Higher Simulation/ Project Lower Efforts/ Project for Estimation
  • 20.  Better Planning decisions, by providing:  More accurate estimates. Accuracy improvement from  20% avg./Prj → 5% avg./Prj (If condition change, clear analysis reasons)  More lineup alternatives. Increase Alternatives from:  3 scenarios→10 scenarios  Time Saving  Forecasters time: 130hrs/Prj→10hrs/Project (About $0.4M Saving) Benefits
  • 21. THANK YOU THANK YOU FOR PARTICIPATING Vedant Borse Solution Architect, PLM / PPM / PCM HCL AXON EAS Division – HCL Technologies 15 Exchange Place, Suite 730, Jersey City, NJ 07302 Mob: +1 919 744 6166 www.hcl-axon.com www.hcltech.com www.hcl.com HCL Booth #213