Technical Assumptions Used in PV
Financial Models: Review of Current
Practices and Recommendations
Mauricio Richter (3E), Jan Vedde (SiCon),
Mike Green (M.G.Lightning Electrical Engineering),
Ulrike Jahn, Magnus Herz (TÜV Rheinland)
IEA PVPS TASK 13 WEBINAR, 5 JULY 2017
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Outline
• Mitigating the Risks Inherent with Technical Assumptions Used in PV
Financial Models (Mauricio Richter)
• Mitigating Financial Risks in a PV Investment (Mike Green)
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Mitigating the Risks Inherent with
Technical Assumptions Used in PV
Financial Models
Mauricio Richter (3E), Jan Vedde (SiCon),
Mike Green (M.G.Lightning Electrical Engineering),
Ulrike Jahn, Magnus Herz (TÜV Rheinland)
IEA PVPS TASK 13 WEBINAR, 5 JULY 2017
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Outline
• Introduction
• Technical Assumptions used in PV Financial Models - Weaknesses
& Recommendations:
– PV Plant Design
– Procurement Process
– Plant Construction
– Plant Acceptance
– O&M
• Long-Term Yield Estimates & Their Level of Confidence
• Risk Quantification and Economic Impact
• Conclusions
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Introduction
• Survey of current practices (questionnaire)
– 84 PV projects
– 9 countries
– Different business concepts
• Complemented with:
– Results from the Solar Bankability project [1]
– General & public domain industry knowledge
[1] The Solar Bankability project is funded by the European Union’s Horizon 2020 research and innovation
programme under the grant agreement No 649997.
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Technical Assumptions Used in PV
Financial Models
Energy flow from sunlight to consumer of electrical power:
Several sub-models
& assumptions
=
Uncertainties
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Technical Assumptions Used in PV
Financial Models
PV plant design
• Solar
Resource
• P50/P90
• Degradation
behavior
• Availability
Procurement
process
• Technical
specifications
• Specific
requirements
• Factory
inspections
• Product
testing
Plant
construction
• Transportation
& handling
• Storage of
components
on-site
• Construction
supervision
Plant
acceptance
• Protocol for
visual
inspection
• Relevant
equipment (IR
/ EL)
• Provisional
acceptance
• Protocol for
data collection
and KPIs
calculation
Operations &
Maintenance
• Monitoring
capabilities
• Preventive &
corrective
maintenance
protocols
• Relevant
equipment (IR
/ EL)
Weaknesses when dealing with technical assumptions and risks in PV
financial models:
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Weaknesses: PV Plant Design
Solar Resource Assessment
Effect of long-term trends in the solar resource is often not fully
accounted for
Forecast of future long-term irradiation based on the average of 32 meteo stations in the Netherlands
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Weaknesses: PV Plant Design
Uncertainties calculation
Exceedance probabilities (e.g. P90) are often calculated assuming a
normal distribution for all elements contributing to the overall
uncertainty
Cumulative distribution function for the long-term (58 years) GHI average of 32 meteo stations in NL
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Weaknesses: PV Plant Design
• Incorrect degradation rate and inaccurate rendering of the system
behavior over time
• Incorrect availability assumptions used to calculate the initial
yield for the project investment financial model as opposed to the
O&M plant availability guarantee
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Recommendations: PV Plant Design
• Project Pre-Feasibility
– Re-run financial models as the plant takes physical shape on the design
table
• Plant Design
– Quality control is critical for enabling realization of financial plan
– Finding and correcting errors at design phase are inexpensive (x 10 rule)
– Ensure back to back guarantees between EPC and O&M
– Minimize events uncovered by guarantees
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Weaknesses: Procurement Process
• Technical specification of the PV plant components usually
consists only of a high-level description
• Project specific requirements such as salt-mist, ammonia or
resistance to PID, with the relevant IEC certification testing, are not
always specified
• Lack of specifications requiring factory inspection or product
testing
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Weaknesses: Plant Construction
• Absence of standardized transportation & handling protocol
• Inadequate quality procedures in component un-packaging and
handling during construction
• Lack of construction supervision
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Weaknesses: Plant Acceptance
• Inadequate protocol for data collection, KPIs calculation and
visual inspection
• Lack of relevant equipment (IR / EL)
• No short-term performance test at provisional acceptance
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Recommendations
• Procurement & Construction
– Ensure quality control for the hardware, the workmanship, and software
– Apply quality control before leaving manufacturing factory and upon site arrival
• Acceptance
– EPC warranty should ideally be 24-months to enable discovery of deficiencies
during the first year and the effect of their correction during the 2nd year
– Deficiencies found during acceptance may cost:
• 10 times more than during construction
• 1/10 of what would cost to rectify during O&M
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Weaknesses: Operations
• Selected monitoring system is not capable of advanced fault
detection and identification
• Missing or inadequate maintenance of the monitoring system
• Preventive & corrective maintenance protocols
• Inadequate or absent relevant equipment (IR / EL)
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Recommendations: Operations
• Operations
– Ensure advanced monitoring system and O&M operators ,who act on the
monitoring system's signals
– Without accurate and advanced monitoring, there is little possibility for
optimizing operational activities
– First years of operation are critical for meeting the financial model:
• 1st year for finding faults and repairing them
• 2nd year for verifying that the faults have been rectified
• 3rd year of contractual obligation to enable a smooth transition from
warranty period to the “bottom of the bathtub” curve.
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Long-Term Yield Estimates & Their
Level of Confidence
Initial P50 and P90 yield estimates vs actual electricity production for a
portfolio of 41 PV plants
Outliers ?
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Long-Term Yield Estimates & Their
Level of Confidence
• Deviations below the confidence margin (P90) disappear after
correction
• 1.13% over-estimation (or under-performance?)
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Long-Term Yield Estimates & Their
Level of Confidence
• Results at plant level:
– For most of the PV plants across the analyzed portfolio the actual
electricity production during first year of operation lies within expected
uncertainty ranges
– Actual availability is lower than initial estimates in LTYA
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Long-Term Yield Estimates & Their
Level of Confidence
• Results at portfolio level:
– The yield is slightly lower than initially estimated during the design
phase (-1.15%)
– The dispersion (nRMSE) is around 4.4% for the analyzed portfolio
– These deviations are typically expected to be mainly due to the
variability of the solar resource and other site specific losses that
are not precisely modelled during the design phase
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Risk Quantification
Risk
OPEX
high
low
Risk
lowlow
CAPEX
OPEX
high high high
low lowlow
Systematical approach required
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Risk Quantification
• Long-Term Yield Estimate with level of confidence
• Feasibility study based on project-specific assumptions 1
• Cost-based FMEA based on historical and statistical data2
– Cost Priority Number (CPN)
1 Mitigating Financial Risks in a PV Investment, Mike Green (next
presentation)
2 www.solarbankability.org
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Risk Quantification by CPN
• First approach to implement a cost-based FMEA to the
PV sector
• Based on statistical analysis and assumptions
• Cost of loss from system downtime (Costloss)
• Cost for detection and mitigation (Costfix)
• Further factors: occurrence, irradiance, power loss, PPA,
etc…
 Tool to benchmark mitigation measures:
www.solarbankability.org
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Conclusions
• Main areas of weakness in a PV project:
– Inaccurate assumptions for the future behavior of the PV
plant
– Lack of methods to enable these assumptions during
design, building, commissioning, and O&M
– Lack of quality control throughout the plant’s life
• The benefit of individual mitigation measures can be
calculated using e.g. CPN method 1
1 www.solarbankability.org
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Conclusions
• Keys to ensure that the financial model holds true:
– Accurate assumptions for the future behaviour of the PV
plant
– Ensure these assumptions are enabled during design,
building, commissioning, and O&M
• Need of high-level of quality control throughout the plant’s
lifetime
• Focus on the technical aspects of the EPC and O&M scopes of
work to manage the technical risks linked to the CAPEX
and OPEX of PV investments.
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Find more results in Task 13 Report
TECHNICAL ASSUMPTIONS USED IN PV FINANCIAL MODELS
REVIEW OF CURRENT PRACTICES AND RECOMMENDATIONS
Download the report:
http://www.iea-pvps.org/index.php?id=426
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Task 13 Workshop at EU PVSEC 2017
Save the date!
Learn more about our work during the IEA PVPS Task 13 Workshop at
EU PVSEC 2017 in Amsterdam, The Netherlands
PV System Performance and PV Module Reliability
Day: Tuesday, 26th September 2017
Time: 08:30 – 12:30
Site: RAI Convention & Exhibition Centre, Amsterdam
Access:Open to all registered participants
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Thank you
Presented by:
Mauricio Richter
MRI@3e.eu
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Mitigating Financial Risks in a PV Investment
Mike Green (M.G.Lightning Electrical Engineering),
Mauricio Richter (3E), Jan Vedde (SiCon)
TASK 13: PERFORMANCE AND RELIABILITY OF PV SYSTEMS
Download the report:
http://www.iea-pvps.org/index.php?id=426
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Financial Risks to a PV Investment
A PV project can be divided into 2 distinct stages:
1. FeasibilityDesignLicenseFinance
Shovel Ready
2. BiddingBuildingCommisioningMaintaining
PV project risk can be divided into 2 distinct causes:
• Uncertainties in the design data
• Lack of Quality Control
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Feasibility – based on parameters:
http://www.iea-pvps.org/index.php?id=423
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Feasibility – based on parameters:
Short list of some PRODUCTION parameters:
System Parameters
1. Module power
2. Solar Resource
3. Ground/roof coverage
4. Module tilt
5. Array azimuth
Loss Parameters:
1. Shading
2. Soiling
3. Temperature
4. Initial degradation
5. Annual degradation
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Feasibility – based on parameters:
Short list of some PROJECT parameters:
Project Parameters
1. Licencing costs
2. Installation costs
3. Unavailability
4. O&M fixed costs
5. O&M contingencies
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Feasibility – based on parameters:
Primary Equations:
𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑇 𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸 = 𝑆𝑆𝑆𝑆𝑆𝑆𝑆𝑆𝑆𝑆 𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸 − � 𝐿𝐿𝐿𝐿𝐿𝐿𝐿𝐿𝐿𝐿𝐿𝐿
𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃 = 𝒇𝒇(𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑇 𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸, 𝑇𝑇𝑇𝑇 𝑇𝑇𝑇𝑇, 𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶, 𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡)
 What is the real Solar Resource over 20+ years?
 What are the accurate values for each of the losses?
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Feasibility – based on parameters:
Garbage In Garbage Out=
An energy simulation
is only as good as the
input data
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Feasibility – based on parameters:
Most parameters used in simulations are accompanied by a variance:
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Feasibility – based on parameters:
Uniform Distribution -0/+3%
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Feasibility – based on parameters:
P90
P50
Normal Distribution
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Feasibility – based on parameters:
Triangular Distribution
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Feasibility – based on parameters:
P90
P50
Triangular Distribution
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
0,0%
0,3%
0,6%
0,9%
1,2%
1,5%
1,8%
2,1%
2,4%
Probability
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Cumulativeprobability
270 271 272 273 274 275 276 277 278 279
Module Power [Wp]
Pareto Plot for Module Power [Wp]
10,00000%(x=270,81)
50,00000%(x=274,03)
0%
1%
2%
3%
4%
5%
6%
7%
Probability
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Cumulativeprobability
850 900 950 1.000 1.050 1.100 1.150 1.200 1.250
Horizontal global irradiation [kWh/m2/year]
Pareto Plot for Horizontal global irradiation [kWh/m2/year]
10,00000%(x=984,49)
90,00000%(x=1116,28)
10,00000% 80,00000% 10,00000%
0%
1%
2%
3%
4%
5%
6%
7%
Probability
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Cumulativeprobability
0,138 0,141 0,144 0,147 0,150 0,153 0,156 0,159 0,162
Irradiation increase due to tilt angle [%]
Pareto Plot for Irradiation increase due to tilt angle [%]
10,00000%(x=0,15)
90,00000%(x=0,15)
10,00000% 80,00000% 10,00000%
0,0%
0,5%
1,0%
1,5%
2,0%
2,5%
3,0%
3,5%
4,0%
4,5%
Probability
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Cumulativeprobability
30% 32% 34% 36% 38% 40% 42% 44% 46% 48% 50%
Ground Coverage Ratio [%]
Pareto Plot for Ground Coverage Ratio [%]
10,00000%(x=34,71%)
90,00000%(x=45,68%)
10,00000% 80,00000% 10,00000%
a
)
b
)
c
)
d
)
0%
1%
2%
3%
4%
5%
6%
7%
Probability
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Cumulativeprobability
1,86% 1,89% 1,92% 1,95% 1,98% 2,01% 2,04% 2,07% 2,10% 2,13%
Irradiation loss due to shading [%]
Pareto Plot for Irradiation loss due to shading [%]
10,00000%(x=1,96%)
90,00000%(x=2,04%)
10,00000% 80,00000% 10,00000%
0,0%
0,3%
0,6%
0,9%
1,2%
1,5%
1,8%
2,1%
2,4%
Probability
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Cumulativeprobability
0,0% 0,3% 0,6% 0,9% 1,2% 1,5% 1,8% 2,1% 2,4% 2,7% 3,0%
Irradiation loss due to soiling [%]
Pareto Plot for Irradiation loss due to soiling [%]
10,00000%(x=0,31%)
90,00000%(x=2,70%)
0%
1%
2%
3%
4%
5%
6%
7%
Probability
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Cumulativeprobability
1,44% 1,46% 1,48% 1,50% 1,52% 1,54% 1,56% 1,58%
Module loss due to temperature [%]
Pareto Plot for Module loss due to temperature [%]
10,00000%(x=1,48%)
90,00000%(x=1,52%)
10,00000% 80,00000% 10,00000%
0,0%
0,5%
1,0%
1,5%
2,0%
2,5%
3,0%
3,5%
4,0%
Probability
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Cumulativeprobability
0,0% 0,5% 1,0% 1,5% 2,0% 2,5% 3,0% 3,5% 4,0% 4,5% 5,0%
Module loss due to LID/deviation from nominal power [%]
Pareto Plot for Module loss due to LID/deviation from nominal power [%]
10,00000%(x=0,99%)
90,00000%(x=3,78%)
10,00000% 80,00000% 10,00000%
a
)
c
)
d
)
0,0%
0,3%
0,6%
0,9%
1,2%
1,5%
1,8%
2,1%
2,4%
Probability
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Cumulativeprobability
600 620 640 660 680 700 720 740 760
Turn-key installation cost in total [EUR/kWp]
Pareto Plot for Turn-key installation cost in total [EUR/kWp]
10,00000%(x=614,97)
90,00000%(x=734,66)
0,0%
0,5%
1,0%
1,5%
2,0%
2,5%
3,0%
3,5%
4,0%
Probability
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Cumulativeprobability
0,0% 0,3% 0,6% 0,9% 1,2% 1,5% 1,8% 2,1% 2,4% 2,7% 3,0%
Technical unavailability [%]
Pareto Plot for Technical unavailability [%]
10,00000%(x=0,54%)
90,00000%(x=2,22%)
10,00000% 80,00000% 10,00000%
0,0%
0,5%
1,0%
1,5%
2,0%
2,5%
3,0%
3,5%
4,0%
4,5%
Probability
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Cumulativeprobability
0,0% 0,1% 0,2% 0,3% 0,4% 0,5% 0,6% 0,7% 0,8%
PV system (module) degradation [%/yr]
Pareto Plot for PV system (module) degradation (%/yr)
10,00000%(x=0,20%)
90,00000%(x=0,64%)
10,00000% 80,00000% 10,00000%
0%
1%
2%
3%
4%
5%
6%
7%
Probability
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Cumulativeprobability
30.000 32.000 34.000 36.000 38.000 40.000 42.000 44.000 46.000 48.000 50.000
O&M - fixed yearly fee [EUR/year]
Pareto Plot for O&M - fixed yearly fee
10,00000%(x=37480,90)
90,00000%(x=42566,23)
10,00000% 80,00000% 10,00000%
a
)
b
)
c
)
d
)
Feasibility – based on parameters:
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
A Feasible Outcome
First Year Energy Production Revenue from Energy Sales
Project IRR by CAPEX Leveraged IRR after Tax
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
A Feasible Outcome
First Year Energy Production
P90
P50
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
ing operation (conversion efficiency) [%]
Irradiation loss due to shading [%]
Turn-key installation cost in total [EUR/kWp]
B1. O&M - fixed yearly fee [EUR/year]
Ground Coverage Ratio [%]
Module loss due to temperature [%]
Irradiation increase due to tilt angle [%]
Technical unavailability [%]
Irradiation loss due to soiling [%]
Module Power [Wp]
ue to LID/deviation from nominal power [%]
PV system (module) degradation (%/yr)
Horizontal global irradiation [kWh/m2/year]
250 260 270 280 290 300 310 320
Conditional Mean. (scale factor = thousands)
Tornado Plot for Power production delivered to the grid [MWh]
Visual Aids
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Horizontal global irradiation [kWh/m2/year]
Irradiation loss due to soiling [%]
Module loss due to LID/deviation from nominal power [%]
PV system (module) degradation (%/yr)
12,9
13,2
13,5
13,8
14,1
14,4
14,7
15,0
15,3
15,6
ConditionalMean.scalefactor=millions
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Spider Plot for Revenue from power sales [EUR]
Visual Aids
Mean
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Financial Risks to a PV Investment
A PV project can be divided into 2 distinct stages:
1. FeasibilityDesignLicenseFinance
Shovel Ready
2. BiddingBuildingCommisioningMaintaining
PV project risk can be divided into 2 distinct causes:
 Uncertainties in the design data
• Lack of Quality Control
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Financial Risks to a PV Investment
A PV project can be divided into 2 distinct stages:
1. FeasibilityDesignLicenseFinance

2. BiddingBuildingCommisioningMaintaining
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Quality Control
The Anderson Rule of 10:
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
 Strategize
 Classify
 Understand
 Manage
Mitigating the Financial Risks - QC
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Strategize:
 Top level decision makers MUST take ownership of the QC
management for ensuring CONTINUETY from the
BEGGINING
 Define what must be done to ensure
 Continuity
 Desired level of product
 Assign the resources to achieve these goals
Mitigating the Financial Risks - QC
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Classify:
 Ensure a wide variety of skill sets in the design team
 Brainstorm
 Checklists to ensure all potential risks are identified
 Classify risks in terms of occurrence frequency and severity
in terms of financial impact
Mitigating the Financial Risks - QC
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
Understand:
 Analyze the root cause(s) of the various risk factors and
interrelations between them
 Identify the most important influencers that may challenge
the financial performance of the project.
Manage!
Mitigating the Financial Risks - QC
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
 Analyzed the technical assumptions used in a financial
model
 We have analyzed the areas of weakness in a PV project
 We have seen some levels of accuracy between design
calculations and finished project
 Quantified the cost of a technical risk
 We have seen new methodology for calculating the benefit of a
mitigating measure using cost-based FMEA
 Use of CPN for evaluating the cost of a mitigating action
Conclusions:
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
 Mitigating financial risk in the business plan
 Challenge the operators of the simulation program used for
calculating first year energy generation
 Calculate the major indices of the business plan using both the
parameter and its variance
 Use graphing tools to visualize the interdependence of these
variables
 Ensure that a rigid QC regimen exists that will enable the design
parameters on which the business plan was built remain intact
from feasibility through to O&M
Conclusions:
IEA INTERNATIONAL ENERGY AGENCY
PHOTOVOLTAIC POWER SYSTEMS PROGRAMME
IEA-PVPS Task 13

More Related Content

What's hot

Freewire Berkeley final presentation
Freewire Berkeley final presentationFreewire Berkeley final presentation
Freewire Berkeley final presentation
Stanford University
 
Automatic Vehicle Entry Exit Log - Senior Year Project
Automatic Vehicle Entry Exit Log - Senior Year ProjectAutomatic Vehicle Entry Exit Log - Senior Year Project
Automatic Vehicle Entry Exit Log - Senior Year Project
Ahmad Azhar
 
THE CHANGING LANDSCAPE OF EV INFRASTRUCTURE, WHAT’S THE RIGHT SOLUTION?
THE CHANGING LANDSCAPE OF EV INFRASTRUCTURE, WHAT’S THE RIGHT SOLUTION?THE CHANGING LANDSCAPE OF EV INFRASTRUCTURE, WHAT’S THE RIGHT SOLUTION?
THE CHANGING LANDSCAPE OF EV INFRASTRUCTURE, WHAT’S THE RIGHT SOLUTION?
iQHub
 

What's hot (20)

Freewire Berkeley final presentation
Freewire Berkeley final presentationFreewire Berkeley final presentation
Freewire Berkeley final presentation
 
Energy in pakistan
Energy in pakistanEnergy in pakistan
Energy in pakistan
 
Smart Charging: How to scale adoption
Smart Charging: How to scale adoption  Smart Charging: How to scale adoption
Smart Charging: How to scale adoption
 
EV (PASSENGER, LCVS, TRUCKS, AND BUSES) AND EV CHARGING INFRASTRUCTURE FORECASTS
EV (PASSENGER, LCVS, TRUCKS, AND BUSES) AND EV CHARGING INFRASTRUCTURE FORECASTSEV (PASSENGER, LCVS, TRUCKS, AND BUSES) AND EV CHARGING INFRASTRUCTURE FORECASTS
EV (PASSENGER, LCVS, TRUCKS, AND BUSES) AND EV CHARGING INFRASTRUCTURE FORECASTS
 
EV station.pptx
EV station.pptxEV station.pptx
EV station.pptx
 
Automatic Vehicle Entry Exit Log - Senior Year Project
Automatic Vehicle Entry Exit Log - Senior Year ProjectAutomatic Vehicle Entry Exit Log - Senior Year Project
Automatic Vehicle Entry Exit Log - Senior Year Project
 
EV CHARGING INFRASTRUCTURE - INDUSTRY TRENDS
EV CHARGING INFRASTRUCTURE - INDUSTRY TRENDSEV CHARGING INFRASTRUCTURE - INDUSTRY TRENDS
EV CHARGING INFRASTRUCTURE - INDUSTRY TRENDS
 
Economics of Solar Park
Economics of Solar ParkEconomics of Solar Park
Economics of Solar Park
 
Autonomous and electric vehicles
Autonomous and electric vehiclesAutonomous and electric vehicles
Autonomous and electric vehicles
 
THE CHANGING LANDSCAPE OF EV INFRASTRUCTURE, WHAT’S THE RIGHT SOLUTION?
THE CHANGING LANDSCAPE OF EV INFRASTRUCTURE, WHAT’S THE RIGHT SOLUTION?THE CHANGING LANDSCAPE OF EV INFRASTRUCTURE, WHAT’S THE RIGHT SOLUTION?
THE CHANGING LANDSCAPE OF EV INFRASTRUCTURE, WHAT’S THE RIGHT SOLUTION?
 
The Electric Vehicle Market
The Electric Vehicle MarketThe Electric Vehicle Market
The Electric Vehicle Market
 
E-mobility | Part 4 - EV charging and the next frontier (English)
E-mobility | Part 4 - EV charging and the next frontier (English)E-mobility | Part 4 - EV charging and the next frontier (English)
E-mobility | Part 4 - EV charging and the next frontier (English)
 
Open access ppt
Open access pptOpen access ppt
Open access ppt
 
Wireless charging: Qualcomm and Bosch
Wireless charging: Qualcomm and BoschWireless charging: Qualcomm and Bosch
Wireless charging: Qualcomm and Bosch
 
Experience of GCCIA in developing GCC Regional Electricity Market
Experience of GCCIA in developing GCC Regional Electricity MarketExperience of GCCIA in developing GCC Regional Electricity Market
Experience of GCCIA in developing GCC Regional Electricity Market
 
Bain Covid 19 situation report & action agenda
Bain   Covid 19 situation report & action agendaBain   Covid 19 situation report & action agenda
Bain Covid 19 situation report & action agenda
 
Report on Studies of Electric Vehicle Technologies
Report on Studies of Electric Vehicle TechnologiesReport on Studies of Electric Vehicle Technologies
Report on Studies of Electric Vehicle Technologies
 
EV Charging Infrastructure: Littelfuse Solutions to Enhance Safety, Efficienc...
EV Charging Infrastructure: Littelfuse Solutions to Enhance Safety, Efficienc...EV Charging Infrastructure: Littelfuse Solutions to Enhance Safety, Efficienc...
EV Charging Infrastructure: Littelfuse Solutions to Enhance Safety, Efficienc...
 
Energy Community: Yasuyuki Watanabe - Battery Energy Storage Systems (BESS)
Energy Community: Yasuyuki Watanabe - Battery Energy  Storage Systems (BESS)Energy Community: Yasuyuki Watanabe - Battery Energy  Storage Systems (BESS)
Energy Community: Yasuyuki Watanabe - Battery Energy Storage Systems (BESS)
 
Peer-to-peer energy trading using blockchains
Peer-to-peer energy trading using blockchainsPeer-to-peer energy trading using blockchains
Peer-to-peer energy trading using blockchains
 

Similar to Technical Assumptions Used in PV Financial Models: Review of Current Practices and Recommendations

Celedonia Power Consulting
Celedonia Power ConsultingCeledonia Power Consulting
Celedonia Power Consulting
Gil Celedonia
 
Poster_EGY_TE_Anas Momen_Hilal-Failure Modes and Effects Analysis
Poster_EGY_TE_Anas Momen_Hilal-Failure Modes and Effects AnalysisPoster_EGY_TE_Anas Momen_Hilal-Failure Modes and Effects Analysis
Poster_EGY_TE_Anas Momen_Hilal-Failure Modes and Effects Analysis
Anas Momen
 
D4 Combining Scada data and Lidar to recitfy under performance
D4 Combining Scada data and Lidar to recitfy under performanceD4 Combining Scada data and Lidar to recitfy under performance
D4 Combining Scada data and Lidar to recitfy under performance
Kelly Dallas, MBA
 
EPC_Enterprise_Systems_Deck
EPC_Enterprise_Systems_DeckEPC_Enterprise_Systems_Deck
EPC_Enterprise_Systems_Deck
Jaswin Sood
 
ICP Europe Technical Forum 24 September 2015
ICP Europe Technical Forum 24 September 2015ICP Europe Technical Forum 24 September 2015
ICP Europe Technical Forum 24 September 2015
Luis Castanheira
 

Similar to Technical Assumptions Used in PV Financial Models: Review of Current Practices and Recommendations (20)

2014 PV Reliability, Operations & Maintenance Workshop: Commissioning PV Syst...
2014 PV Reliability, Operations & Maintenance Workshop: Commissioning PV Syst...2014 PV Reliability, Operations & Maintenance Workshop: Commissioning PV Syst...
2014 PV Reliability, Operations & Maintenance Workshop: Commissioning PV Syst...
 
Operational Efficiency Based on Innovative Automation, Industry Expertise, En...
Operational Efficiency Based on Innovative Automation, Industry Expertise, En...Operational Efficiency Based on Innovative Automation, Industry Expertise, En...
Operational Efficiency Based on Innovative Automation, Industry Expertise, En...
 
Technical evaluation in cpv systems
Technical evaluation in cpv systemsTechnical evaluation in cpv systems
Technical evaluation in cpv systems
 
2014 PV Reliability, Operations & Maintenance Workshop: An O&M Perspective
2014 PV Reliability, Operations & Maintenance Workshop: An O&M Perspective2014 PV Reliability, Operations & Maintenance Workshop: An O&M Perspective
2014 PV Reliability, Operations & Maintenance Workshop: An O&M Perspective
 
2020-06_Webinar-IBR_Modeling_Studies_Report.pdf
2020-06_Webinar-IBR_Modeling_Studies_Report.pdf2020-06_Webinar-IBR_Modeling_Studies_Report.pdf
2020-06_Webinar-IBR_Modeling_Studies_Report.pdf
 
Rinkesh 17012017
Rinkesh 17012017Rinkesh 17012017
Rinkesh 17012017
 
Case studies: Predictive maintenance in the petrochemical industry
Case studies: Predictive maintenance in the petrochemical industryCase studies: Predictive maintenance in the petrochemical industry
Case studies: Predictive maintenance in the petrochemical industry
 
Celedonia Power Consulting
Celedonia Power ConsultingCeledonia Power Consulting
Celedonia Power Consulting
 
Poster_EGY_TE_Anas Momen_Hilal-Failure Modes and Effects Analysis
Poster_EGY_TE_Anas Momen_Hilal-Failure Modes and Effects AnalysisPoster_EGY_TE_Anas Momen_Hilal-Failure Modes and Effects Analysis
Poster_EGY_TE_Anas Momen_Hilal-Failure Modes and Effects Analysis
 
Investigating Business Models for Building Integrated Photovoltaics (BIPV)
Investigating Business Models for Building Integrated Photovoltaics (BIPV)Investigating Business Models for Building Integrated Photovoltaics (BIPV)
Investigating Business Models for Building Integrated Photovoltaics (BIPV)
 
Nidec asi service capabilities overview
Nidec asi service capabilities overviewNidec asi service capabilities overview
Nidec asi service capabilities overview
 
D4 Combining Scada data and Lidar to recitfy under performance
D4 Combining Scada data and Lidar to recitfy under performanceD4 Combining Scada data and Lidar to recitfy under performance
D4 Combining Scada data and Lidar to recitfy under performance
 
EPC_Enterprise_Systems_Deck
EPC_Enterprise_Systems_DeckEPC_Enterprise_Systems_Deck
EPC_Enterprise_Systems_Deck
 
Equota Pitch Deck EN 2015
Equota Pitch Deck EN 2015Equota Pitch Deck EN 2015
Equota Pitch Deck EN 2015
 
AESP_Spring
AESP_SpringAESP_Spring
AESP_Spring
 
The Key to Sustainable Energy Optimization: A Data-Driven Approach for Manufa...
The Key to Sustainable Energy Optimization: A Data-Driven Approach for Manufa...The Key to Sustainable Energy Optimization: A Data-Driven Approach for Manufa...
The Key to Sustainable Energy Optimization: A Data-Driven Approach for Manufa...
 
Stork Presentation on Migration (Willem Hazenberg)
Stork Presentation on Migration (Willem Hazenberg)Stork Presentation on Migration (Willem Hazenberg)
Stork Presentation on Migration (Willem Hazenberg)
 
Solar O&M Presentation Intersolar 2013
Solar O&M Presentation Intersolar 2013Solar O&M Presentation Intersolar 2013
Solar O&M Presentation Intersolar 2013
 
ICP Europe Technical Forum 24 September 2015
ICP Europe Technical Forum 24 September 2015ICP Europe Technical Forum 24 September 2015
ICP Europe Technical Forum 24 September 2015
 
Responding to Fukushima: Real-Time, Interactive, Beyond Design Basis Modeling...
Responding to Fukushima: Real-Time, Interactive, Beyond Design Basis Modeling...Responding to Fukushima: Real-Time, Interactive, Beyond Design Basis Modeling...
Responding to Fukushima: Real-Time, Interactive, Beyond Design Basis Modeling...
 

More from Leonardo ENERGY

More from Leonardo ENERGY (20)

A new generation of instruments and tools to monitor buildings performance
A new generation of instruments and tools to monitor buildings performanceA new generation of instruments and tools to monitor buildings performance
A new generation of instruments and tools to monitor buildings performance
 
Addressing the Energy Efficiency First Principle in a National Energy and Cli...
Addressing the Energy Efficiency First Principle in a National Energy and Cli...Addressing the Energy Efficiency First Principle in a National Energy and Cli...
Addressing the Energy Efficiency First Principle in a National Energy and Cli...
 
Auctions for energy efficiency and the experience of renewables
 Auctions for energy efficiency and the experience of renewables Auctions for energy efficiency and the experience of renewables
Auctions for energy efficiency and the experience of renewables
 
Energy efficiency first – retrofitting the building stock final
Energy efficiency first – retrofitting the building stock finalEnergy efficiency first – retrofitting the building stock final
Energy efficiency first – retrofitting the building stock final
 
How auction design affects the financing of renewable energy projects
How auction design affects the financing of renewable energy projects How auction design affects the financing of renewable energy projects
How auction design affects the financing of renewable energy projects
 
Energy Efficiency Funds in Europe (updated)
Energy Efficiency Funds in Europe (updated)Energy Efficiency Funds in Europe (updated)
Energy Efficiency Funds in Europe (updated)
 
Energy Efficiency Funds in Europe
Energy Efficiency Funds in EuropeEnergy Efficiency Funds in Europe
Energy Efficiency Funds in Europe
 
Five actions fit for 55: streamlining energy savings calculations
Five actions fit for 55: streamlining energy savings calculationsFive actions fit for 55: streamlining energy savings calculations
Five actions fit for 55: streamlining energy savings calculations
 
Recent energy efficiency trends in the EU
Recent energy efficiency trends in the EURecent energy efficiency trends in the EU
Recent energy efficiency trends in the EU
 
Energy and mobility poverty: Will the Social Climate Fund be enough to delive...
Energy and mobility poverty: Will the Social Climate Fund be enough to delive...Energy and mobility poverty: Will the Social Climate Fund be enough to delive...
Energy and mobility poverty: Will the Social Climate Fund be enough to delive...
 
Does the EU Emission Trading Scheme ETS Promote Energy Efficiency?
Does the EU Emission Trading Scheme ETS Promote Energy Efficiency?Does the EU Emission Trading Scheme ETS Promote Energy Efficiency?
Does the EU Emission Trading Scheme ETS Promote Energy Efficiency?
 
Energy efficiency, structural change and energy savings in the manufacturing ...
Energy efficiency, structural change and energy savings in the manufacturing ...Energy efficiency, structural change and energy savings in the manufacturing ...
Energy efficiency, structural change and energy savings in the manufacturing ...
 
Energy Sufficiency Indicators and Policies (Lea Gynther, Motiva)
Energy Sufficiency Indicators and Policies (Lea Gynther, Motiva)Energy Sufficiency Indicators and Policies (Lea Gynther, Motiva)
Energy Sufficiency Indicators and Policies (Lea Gynther, Motiva)
 
The Super-efficient Equipment and Appliance Deployment (SEAD) Initiative Prod...
The Super-efficient Equipment and Appliance Deployment (SEAD) Initiative Prod...The Super-efficient Equipment and Appliance Deployment (SEAD) Initiative Prod...
The Super-efficient Equipment and Appliance Deployment (SEAD) Initiative Prod...
 
Modelling and optimisation of electric motors with hairpin windings
Modelling and optimisation of electric motors with hairpin windingsModelling and optimisation of electric motors with hairpin windings
Modelling and optimisation of electric motors with hairpin windings
 
Casting zero porosity rotors
Casting zero porosity rotorsCasting zero porosity rotors
Casting zero porosity rotors
 
Direct coil cooling through hollow wire
Direct coil cooling through hollow wireDirect coil cooling through hollow wire
Direct coil cooling through hollow wire
 
Motor renovation - Potential savings and views from various EU Member States
Motor renovation - Potential savings and views from various EU Member StatesMotor renovation - Potential savings and views from various EU Member States
Motor renovation - Potential savings and views from various EU Member States
 
The need for an updated European Motor Study - key findings from the 2021 US...
The need for  an updated European Motor Study - key findings from the 2021 US...The need for  an updated European Motor Study - key findings from the 2021 US...
The need for an updated European Motor Study - key findings from the 2021 US...
 
Efficient motor systems for a Net Zero world, by Conrad U. Brunner - Impact E...
Efficient motor systems for a Net Zero world, by Conrad U. Brunner - Impact E...Efficient motor systems for a Net Zero world, by Conrad U. Brunner - Impact E...
Efficient motor systems for a Net Zero world, by Conrad U. Brunner - Impact E...
 

Recently uploaded

Recently uploaded (20)

Enterprise Knowledge Graphs - Data Summit 2024
Enterprise Knowledge Graphs - Data Summit 2024Enterprise Knowledge Graphs - Data Summit 2024
Enterprise Knowledge Graphs - Data Summit 2024
 
Demystifying gRPC in .Net by John Staveley
Demystifying gRPC in .Net by John StaveleyDemystifying gRPC in .Net by John Staveley
Demystifying gRPC in .Net by John Staveley
 
10 Differences between Sales Cloud and CPQ, Blanka Doktorová
10 Differences between Sales Cloud and CPQ, Blanka Doktorová10 Differences between Sales Cloud and CPQ, Blanka Doktorová
10 Differences between Sales Cloud and CPQ, Blanka Doktorová
 
IoT Analytics Company Presentation May 2024
IoT Analytics Company Presentation May 2024IoT Analytics Company Presentation May 2024
IoT Analytics Company Presentation May 2024
 
The UX of Automation by AJ King, Senior UX Researcher, Ocado
The UX of Automation by AJ King, Senior UX Researcher, OcadoThe UX of Automation by AJ King, Senior UX Researcher, Ocado
The UX of Automation by AJ King, Senior UX Researcher, Ocado
 
Buy Epson EcoTank L3210 Colour Printer Online.pdf
Buy Epson EcoTank L3210 Colour Printer Online.pdfBuy Epson EcoTank L3210 Colour Printer Online.pdf
Buy Epson EcoTank L3210 Colour Printer Online.pdf
 
Unpacking Value Delivery - Agile Oxford Meetup - May 2024.pptx
Unpacking Value Delivery - Agile Oxford Meetup - May 2024.pptxUnpacking Value Delivery - Agile Oxford Meetup - May 2024.pptx
Unpacking Value Delivery - Agile Oxford Meetup - May 2024.pptx
 
ECS 2024 Teams Premium - Pretty Secure
ECS 2024   Teams Premium - Pretty SecureECS 2024   Teams Premium - Pretty Secure
ECS 2024 Teams Premium - Pretty Secure
 
The Metaverse: Are We There Yet?
The  Metaverse:    Are   We  There  Yet?The  Metaverse:    Are   We  There  Yet?
The Metaverse: Are We There Yet?
 
How Red Hat Uses FDO in Device Lifecycle _ Costin and Vitaliy at Red Hat.pdf
How Red Hat Uses FDO in Device Lifecycle _ Costin and Vitaliy at Red Hat.pdfHow Red Hat Uses FDO in Device Lifecycle _ Costin and Vitaliy at Red Hat.pdf
How Red Hat Uses FDO in Device Lifecycle _ Costin and Vitaliy at Red Hat.pdf
 
IESVE for Early Stage Design and Planning
IESVE for Early Stage Design and PlanningIESVE for Early Stage Design and Planning
IESVE for Early Stage Design and Planning
 
Custom Approval Process: A New Perspective, Pavel Hrbacek & Anindya Halder
Custom Approval Process: A New Perspective, Pavel Hrbacek & Anindya HalderCustom Approval Process: A New Perspective, Pavel Hrbacek & Anindya Halder
Custom Approval Process: A New Perspective, Pavel Hrbacek & Anindya Halder
 
Integrating Telephony Systems with Salesforce: Insights and Considerations, B...
Integrating Telephony Systems with Salesforce: Insights and Considerations, B...Integrating Telephony Systems with Salesforce: Insights and Considerations, B...
Integrating Telephony Systems with Salesforce: Insights and Considerations, B...
 
Buy Epson EcoTank L3210 Colour Printer Online.pptx
Buy Epson EcoTank L3210 Colour Printer Online.pptxBuy Epson EcoTank L3210 Colour Printer Online.pptx
Buy Epson EcoTank L3210 Colour Printer Online.pptx
 
Strategic AI Integration in Engineering Teams
Strategic AI Integration in Engineering TeamsStrategic AI Integration in Engineering Teams
Strategic AI Integration in Engineering Teams
 
AI presentation and introduction - Retrieval Augmented Generation RAG 101
AI presentation and introduction - Retrieval Augmented Generation RAG 101AI presentation and introduction - Retrieval Augmented Generation RAG 101
AI presentation and introduction - Retrieval Augmented Generation RAG 101
 
UiPath Test Automation using UiPath Test Suite series, part 2
UiPath Test Automation using UiPath Test Suite series, part 2UiPath Test Automation using UiPath Test Suite series, part 2
UiPath Test Automation using UiPath Test Suite series, part 2
 
FDO for Camera, Sensor and Networking Device – Commercial Solutions from VinC...
FDO for Camera, Sensor and Networking Device – Commercial Solutions from VinC...FDO for Camera, Sensor and Networking Device – Commercial Solutions from VinC...
FDO for Camera, Sensor and Networking Device – Commercial Solutions from VinC...
 
What's New in Teams Calling, Meetings and Devices April 2024
What's New in Teams Calling, Meetings and Devices April 2024What's New in Teams Calling, Meetings and Devices April 2024
What's New in Teams Calling, Meetings and Devices April 2024
 
Speed Wins: From Kafka to APIs in Minutes
Speed Wins: From Kafka to APIs in MinutesSpeed Wins: From Kafka to APIs in Minutes
Speed Wins: From Kafka to APIs in Minutes
 

Technical Assumptions Used in PV Financial Models: Review of Current Practices and Recommendations

  • 1. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Technical Assumptions Used in PV Financial Models: Review of Current Practices and Recommendations Mauricio Richter (3E), Jan Vedde (SiCon), Mike Green (M.G.Lightning Electrical Engineering), Ulrike Jahn, Magnus Herz (TÜV Rheinland) IEA PVPS TASK 13 WEBINAR, 5 JULY 2017
  • 2. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Outline • Mitigating the Risks Inherent with Technical Assumptions Used in PV Financial Models (Mauricio Richter) • Mitigating Financial Risks in a PV Investment (Mike Green)
  • 3. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Mitigating the Risks Inherent with Technical Assumptions Used in PV Financial Models Mauricio Richter (3E), Jan Vedde (SiCon), Mike Green (M.G.Lightning Electrical Engineering), Ulrike Jahn, Magnus Herz (TÜV Rheinland) IEA PVPS TASK 13 WEBINAR, 5 JULY 2017
  • 4. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Outline • Introduction • Technical Assumptions used in PV Financial Models - Weaknesses & Recommendations: – PV Plant Design – Procurement Process – Plant Construction – Plant Acceptance – O&M • Long-Term Yield Estimates & Their Level of Confidence • Risk Quantification and Economic Impact • Conclusions
  • 5. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Introduction • Survey of current practices (questionnaire) – 84 PV projects – 9 countries – Different business concepts • Complemented with: – Results from the Solar Bankability project [1] – General & public domain industry knowledge [1] The Solar Bankability project is funded by the European Union’s Horizon 2020 research and innovation programme under the grant agreement No 649997.
  • 6. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Technical Assumptions Used in PV Financial Models Energy flow from sunlight to consumer of electrical power: Several sub-models & assumptions = Uncertainties
  • 7. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Technical Assumptions Used in PV Financial Models PV plant design • Solar Resource • P50/P90 • Degradation behavior • Availability Procurement process • Technical specifications • Specific requirements • Factory inspections • Product testing Plant construction • Transportation & handling • Storage of components on-site • Construction supervision Plant acceptance • Protocol for visual inspection • Relevant equipment (IR / EL) • Provisional acceptance • Protocol for data collection and KPIs calculation Operations & Maintenance • Monitoring capabilities • Preventive & corrective maintenance protocols • Relevant equipment (IR / EL) Weaknesses when dealing with technical assumptions and risks in PV financial models:
  • 8. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Weaknesses: PV Plant Design Solar Resource Assessment Effect of long-term trends in the solar resource is often not fully accounted for Forecast of future long-term irradiation based on the average of 32 meteo stations in the Netherlands
  • 9. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Weaknesses: PV Plant Design Uncertainties calculation Exceedance probabilities (e.g. P90) are often calculated assuming a normal distribution for all elements contributing to the overall uncertainty Cumulative distribution function for the long-term (58 years) GHI average of 32 meteo stations in NL
  • 10. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Weaknesses: PV Plant Design • Incorrect degradation rate and inaccurate rendering of the system behavior over time • Incorrect availability assumptions used to calculate the initial yield for the project investment financial model as opposed to the O&M plant availability guarantee
  • 11. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Recommendations: PV Plant Design • Project Pre-Feasibility – Re-run financial models as the plant takes physical shape on the design table • Plant Design – Quality control is critical for enabling realization of financial plan – Finding and correcting errors at design phase are inexpensive (x 10 rule) – Ensure back to back guarantees between EPC and O&M – Minimize events uncovered by guarantees
  • 12. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Weaknesses: Procurement Process • Technical specification of the PV plant components usually consists only of a high-level description • Project specific requirements such as salt-mist, ammonia or resistance to PID, with the relevant IEC certification testing, are not always specified • Lack of specifications requiring factory inspection or product testing
  • 13. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Weaknesses: Plant Construction • Absence of standardized transportation & handling protocol • Inadequate quality procedures in component un-packaging and handling during construction • Lack of construction supervision
  • 14. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Weaknesses: Plant Acceptance • Inadequate protocol for data collection, KPIs calculation and visual inspection • Lack of relevant equipment (IR / EL) • No short-term performance test at provisional acceptance
  • 15. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Recommendations • Procurement & Construction – Ensure quality control for the hardware, the workmanship, and software – Apply quality control before leaving manufacturing factory and upon site arrival • Acceptance – EPC warranty should ideally be 24-months to enable discovery of deficiencies during the first year and the effect of their correction during the 2nd year – Deficiencies found during acceptance may cost: • 10 times more than during construction • 1/10 of what would cost to rectify during O&M
  • 16. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Weaknesses: Operations • Selected monitoring system is not capable of advanced fault detection and identification • Missing or inadequate maintenance of the monitoring system • Preventive & corrective maintenance protocols • Inadequate or absent relevant equipment (IR / EL)
  • 17. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Recommendations: Operations • Operations – Ensure advanced monitoring system and O&M operators ,who act on the monitoring system's signals – Without accurate and advanced monitoring, there is little possibility for optimizing operational activities – First years of operation are critical for meeting the financial model: • 1st year for finding faults and repairing them • 2nd year for verifying that the faults have been rectified • 3rd year of contractual obligation to enable a smooth transition from warranty period to the “bottom of the bathtub” curve.
  • 18. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Long-Term Yield Estimates & Their Level of Confidence Initial P50 and P90 yield estimates vs actual electricity production for a portfolio of 41 PV plants Outliers ?
  • 19. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Long-Term Yield Estimates & Their Level of Confidence • Deviations below the confidence margin (P90) disappear after correction • 1.13% over-estimation (or under-performance?)
  • 20. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Long-Term Yield Estimates & Their Level of Confidence • Results at plant level: – For most of the PV plants across the analyzed portfolio the actual electricity production during first year of operation lies within expected uncertainty ranges – Actual availability is lower than initial estimates in LTYA
  • 21. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Long-Term Yield Estimates & Their Level of Confidence • Results at portfolio level: – The yield is slightly lower than initially estimated during the design phase (-1.15%) – The dispersion (nRMSE) is around 4.4% for the analyzed portfolio – These deviations are typically expected to be mainly due to the variability of the solar resource and other site specific losses that are not precisely modelled during the design phase
  • 22. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Risk Quantification Risk OPEX high low Risk lowlow CAPEX OPEX high high high low lowlow Systematical approach required
  • 23. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Risk Quantification • Long-Term Yield Estimate with level of confidence • Feasibility study based on project-specific assumptions 1 • Cost-based FMEA based on historical and statistical data2 – Cost Priority Number (CPN) 1 Mitigating Financial Risks in a PV Investment, Mike Green (next presentation) 2 www.solarbankability.org
  • 24. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Risk Quantification by CPN • First approach to implement a cost-based FMEA to the PV sector • Based on statistical analysis and assumptions • Cost of loss from system downtime (Costloss) • Cost for detection and mitigation (Costfix) • Further factors: occurrence, irradiance, power loss, PPA, etc…  Tool to benchmark mitigation measures: www.solarbankability.org
  • 25. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Conclusions • Main areas of weakness in a PV project: – Inaccurate assumptions for the future behavior of the PV plant – Lack of methods to enable these assumptions during design, building, commissioning, and O&M – Lack of quality control throughout the plant’s life • The benefit of individual mitigation measures can be calculated using e.g. CPN method 1 1 www.solarbankability.org
  • 26. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Conclusions • Keys to ensure that the financial model holds true: – Accurate assumptions for the future behaviour of the PV plant – Ensure these assumptions are enabled during design, building, commissioning, and O&M • Need of high-level of quality control throughout the plant’s lifetime • Focus on the technical aspects of the EPC and O&M scopes of work to manage the technical risks linked to the CAPEX and OPEX of PV investments.
  • 27. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Find more results in Task 13 Report TECHNICAL ASSUMPTIONS USED IN PV FINANCIAL MODELS REVIEW OF CURRENT PRACTICES AND RECOMMENDATIONS Download the report: http://www.iea-pvps.org/index.php?id=426
  • 28. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Task 13 Workshop at EU PVSEC 2017 Save the date! Learn more about our work during the IEA PVPS Task 13 Workshop at EU PVSEC 2017 in Amsterdam, The Netherlands PV System Performance and PV Module Reliability Day: Tuesday, 26th September 2017 Time: 08:30 – 12:30 Site: RAI Convention & Exhibition Centre, Amsterdam Access:Open to all registered participants
  • 29. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Thank you Presented by: Mauricio Richter MRI@3e.eu
  • 30. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Mitigating Financial Risks in a PV Investment Mike Green (M.G.Lightning Electrical Engineering), Mauricio Richter (3E), Jan Vedde (SiCon) TASK 13: PERFORMANCE AND RELIABILITY OF PV SYSTEMS Download the report: http://www.iea-pvps.org/index.php?id=426
  • 31. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Financial Risks to a PV Investment A PV project can be divided into 2 distinct stages: 1. FeasibilityDesignLicenseFinance Shovel Ready 2. BiddingBuildingCommisioningMaintaining PV project risk can be divided into 2 distinct causes: • Uncertainties in the design data • Lack of Quality Control
  • 32. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Feasibility – based on parameters: http://www.iea-pvps.org/index.php?id=423
  • 33. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Feasibility – based on parameters: Short list of some PRODUCTION parameters: System Parameters 1. Module power 2. Solar Resource 3. Ground/roof coverage 4. Module tilt 5. Array azimuth Loss Parameters: 1. Shading 2. Soiling 3. Temperature 4. Initial degradation 5. Annual degradation
  • 34. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Feasibility – based on parameters: Short list of some PROJECT parameters: Project Parameters 1. Licencing costs 2. Installation costs 3. Unavailability 4. O&M fixed costs 5. O&M contingencies
  • 35. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Feasibility – based on parameters: Primary Equations: 𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑇 𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸 = 𝑆𝑆𝑆𝑆𝑆𝑆𝑆𝑆𝑆𝑆 𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸 − � 𝐿𝐿𝐿𝐿𝐿𝐿𝐿𝐿𝐿𝐿𝐿𝐿 𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃 = 𝒇𝒇(𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑇 𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸, 𝑇𝑇𝑇𝑇 𝑇𝑇𝑇𝑇, 𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶, 𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡)  What is the real Solar Resource over 20+ years?  What are the accurate values for each of the losses?
  • 36. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Feasibility – based on parameters: Garbage In Garbage Out= An energy simulation is only as good as the input data
  • 37. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Feasibility – based on parameters: Most parameters used in simulations are accompanied by a variance:
  • 38. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Feasibility – based on parameters: Uniform Distribution -0/+3%
  • 39. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Feasibility – based on parameters: P90 P50 Normal Distribution
  • 40. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Feasibility – based on parameters: Triangular Distribution
  • 41. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Feasibility – based on parameters: P90 P50 Triangular Distribution
  • 42. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME 0,0% 0,3% 0,6% 0,9% 1,2% 1,5% 1,8% 2,1% 2,4% Probability 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Cumulativeprobability 270 271 272 273 274 275 276 277 278 279 Module Power [Wp] Pareto Plot for Module Power [Wp] 10,00000%(x=270,81) 50,00000%(x=274,03) 0% 1% 2% 3% 4% 5% 6% 7% Probability 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Cumulativeprobability 850 900 950 1.000 1.050 1.100 1.150 1.200 1.250 Horizontal global irradiation [kWh/m2/year] Pareto Plot for Horizontal global irradiation [kWh/m2/year] 10,00000%(x=984,49) 90,00000%(x=1116,28) 10,00000% 80,00000% 10,00000% 0% 1% 2% 3% 4% 5% 6% 7% Probability 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Cumulativeprobability 0,138 0,141 0,144 0,147 0,150 0,153 0,156 0,159 0,162 Irradiation increase due to tilt angle [%] Pareto Plot for Irradiation increase due to tilt angle [%] 10,00000%(x=0,15) 90,00000%(x=0,15) 10,00000% 80,00000% 10,00000% 0,0% 0,5% 1,0% 1,5% 2,0% 2,5% 3,0% 3,5% 4,0% 4,5% Probability 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Cumulativeprobability 30% 32% 34% 36% 38% 40% 42% 44% 46% 48% 50% Ground Coverage Ratio [%] Pareto Plot for Ground Coverage Ratio [%] 10,00000%(x=34,71%) 90,00000%(x=45,68%) 10,00000% 80,00000% 10,00000% a ) b ) c ) d ) 0% 1% 2% 3% 4% 5% 6% 7% Probability 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Cumulativeprobability 1,86% 1,89% 1,92% 1,95% 1,98% 2,01% 2,04% 2,07% 2,10% 2,13% Irradiation loss due to shading [%] Pareto Plot for Irradiation loss due to shading [%] 10,00000%(x=1,96%) 90,00000%(x=2,04%) 10,00000% 80,00000% 10,00000% 0,0% 0,3% 0,6% 0,9% 1,2% 1,5% 1,8% 2,1% 2,4% Probability 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Cumulativeprobability 0,0% 0,3% 0,6% 0,9% 1,2% 1,5% 1,8% 2,1% 2,4% 2,7% 3,0% Irradiation loss due to soiling [%] Pareto Plot for Irradiation loss due to soiling [%] 10,00000%(x=0,31%) 90,00000%(x=2,70%) 0% 1% 2% 3% 4% 5% 6% 7% Probability 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Cumulativeprobability 1,44% 1,46% 1,48% 1,50% 1,52% 1,54% 1,56% 1,58% Module loss due to temperature [%] Pareto Plot for Module loss due to temperature [%] 10,00000%(x=1,48%) 90,00000%(x=1,52%) 10,00000% 80,00000% 10,00000% 0,0% 0,5% 1,0% 1,5% 2,0% 2,5% 3,0% 3,5% 4,0% Probability 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Cumulativeprobability 0,0% 0,5% 1,0% 1,5% 2,0% 2,5% 3,0% 3,5% 4,0% 4,5% 5,0% Module loss due to LID/deviation from nominal power [%] Pareto Plot for Module loss due to LID/deviation from nominal power [%] 10,00000%(x=0,99%) 90,00000%(x=3,78%) 10,00000% 80,00000% 10,00000% a ) c ) d ) 0,0% 0,3% 0,6% 0,9% 1,2% 1,5% 1,8% 2,1% 2,4% Probability 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Cumulativeprobability 600 620 640 660 680 700 720 740 760 Turn-key installation cost in total [EUR/kWp] Pareto Plot for Turn-key installation cost in total [EUR/kWp] 10,00000%(x=614,97) 90,00000%(x=734,66) 0,0% 0,5% 1,0% 1,5% 2,0% 2,5% 3,0% 3,5% 4,0% Probability 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Cumulativeprobability 0,0% 0,3% 0,6% 0,9% 1,2% 1,5% 1,8% 2,1% 2,4% 2,7% 3,0% Technical unavailability [%] Pareto Plot for Technical unavailability [%] 10,00000%(x=0,54%) 90,00000%(x=2,22%) 10,00000% 80,00000% 10,00000% 0,0% 0,5% 1,0% 1,5% 2,0% 2,5% 3,0% 3,5% 4,0% 4,5% Probability 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Cumulativeprobability 0,0% 0,1% 0,2% 0,3% 0,4% 0,5% 0,6% 0,7% 0,8% PV system (module) degradation [%/yr] Pareto Plot for PV system (module) degradation (%/yr) 10,00000%(x=0,20%) 90,00000%(x=0,64%) 10,00000% 80,00000% 10,00000% 0% 1% 2% 3% 4% 5% 6% 7% Probability 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Cumulativeprobability 30.000 32.000 34.000 36.000 38.000 40.000 42.000 44.000 46.000 48.000 50.000 O&M - fixed yearly fee [EUR/year] Pareto Plot for O&M - fixed yearly fee 10,00000%(x=37480,90) 90,00000%(x=42566,23) 10,00000% 80,00000% 10,00000% a ) b ) c ) d ) Feasibility – based on parameters:
  • 43. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME A Feasible Outcome First Year Energy Production Revenue from Energy Sales Project IRR by CAPEX Leveraged IRR after Tax
  • 44. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME A Feasible Outcome First Year Energy Production P90 P50
  • 45. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME ing operation (conversion efficiency) [%] Irradiation loss due to shading [%] Turn-key installation cost in total [EUR/kWp] B1. O&M - fixed yearly fee [EUR/year] Ground Coverage Ratio [%] Module loss due to temperature [%] Irradiation increase due to tilt angle [%] Technical unavailability [%] Irradiation loss due to soiling [%] Module Power [Wp] ue to LID/deviation from nominal power [%] PV system (module) degradation (%/yr) Horizontal global irradiation [kWh/m2/year] 250 260 270 280 290 300 310 320 Conditional Mean. (scale factor = thousands) Tornado Plot for Power production delivered to the grid [MWh] Visual Aids
  • 46. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Horizontal global irradiation [kWh/m2/year] Irradiation loss due to soiling [%] Module loss due to LID/deviation from nominal power [%] PV system (module) degradation (%/yr) 12,9 13,2 13,5 13,8 14,1 14,4 14,7 15,0 15,3 15,6 ConditionalMean.scalefactor=millions 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Spider Plot for Revenue from power sales [EUR] Visual Aids Mean
  • 47. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Financial Risks to a PV Investment A PV project can be divided into 2 distinct stages: 1. FeasibilityDesignLicenseFinance Shovel Ready 2. BiddingBuildingCommisioningMaintaining PV project risk can be divided into 2 distinct causes:  Uncertainties in the design data • Lack of Quality Control
  • 48. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Financial Risks to a PV Investment A PV project can be divided into 2 distinct stages: 1. FeasibilityDesignLicenseFinance  2. BiddingBuildingCommisioningMaintaining
  • 49. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Quality Control The Anderson Rule of 10:
  • 50. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME  Strategize  Classify  Understand  Manage Mitigating the Financial Risks - QC
  • 51. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Strategize:  Top level decision makers MUST take ownership of the QC management for ensuring CONTINUETY from the BEGGINING  Define what must be done to ensure  Continuity  Desired level of product  Assign the resources to achieve these goals Mitigating the Financial Risks - QC
  • 52. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Classify:  Ensure a wide variety of skill sets in the design team  Brainstorm  Checklists to ensure all potential risks are identified  Classify risks in terms of occurrence frequency and severity in terms of financial impact Mitigating the Financial Risks - QC
  • 53. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Understand:  Analyze the root cause(s) of the various risk factors and interrelations between them  Identify the most important influencers that may challenge the financial performance of the project. Manage! Mitigating the Financial Risks - QC
  • 54. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME  Analyzed the technical assumptions used in a financial model  We have analyzed the areas of weakness in a PV project  We have seen some levels of accuracy between design calculations and finished project  Quantified the cost of a technical risk  We have seen new methodology for calculating the benefit of a mitigating measure using cost-based FMEA  Use of CPN for evaluating the cost of a mitigating action Conclusions:
  • 55. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME  Mitigating financial risk in the business plan  Challenge the operators of the simulation program used for calculating first year energy generation  Calculate the major indices of the business plan using both the parameter and its variance  Use graphing tools to visualize the interdependence of these variables  Ensure that a rigid QC regimen exists that will enable the design parameters on which the business plan was built remain intact from feasibility through to O&M Conclusions:
  • 56. IEA INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME IEA-PVPS Task 13