18 | Canadian Mining Journal • May 2012	 www.canadianminingjournal.com
| Oil and Gas
I
nternational trade is a fickle busi-
ness, and no more so than in China.
The near collapse of its burgeoning
trade economy in the 1990s had
Canadian shippers shifting their business
back to traditional U.S. markets, where it
would remain until the Asian economy
rebounded a decade later.
But beyond the varying market condi-
tions,shippersalreadyhadtheireyestrained
on something else; namely, container ships,
the key elements in the entire offshore ship-
ping scenario. These were now the shipping
modeofchoice,representingarealopportu-
nity for those few North American ports
with the capacity to handle the vessel’s mas-
sive dimensions.
Other ports, like Prince Rupert, says
Shaun Stevenson, Vice-president of Trade
Development and Public Affairs for the
Prince Rupert Port Authority, could only
look on with envy.
“We couldn’t participate in that busi-
ness so it meant changing to meet the
evolving needs of shippers and exporters
in Canada, but also creating new capaci-
ties where the growth opportunity was,”
says Stevenson.
Prince Rupert’s unique position in
North America seemed to make increased
trade with Asia a no-brainer. Up to a day-
and-a- half closer to Asia than Los Angeles
and Seattle with the deepest natural har-
bour on the continent, the port knew it
could compete. Problem was its main
Fairview Terminal consisted of a traditional
general cargo and break bulk terminals. It
had to expand, and expand quickly.
Build it bigger, built it better…
The announcement came in April 2005:
The Port of Prince Rupert would con-
vert its Fairview Terminal into an inter-
modal container shipping terminal,
with a major expansion of the port’s
wharf and investments in rail infra-
structure connecting Toronto, Montreal
and Chicago to Asian markets.
Under Phase One, public and private
sector investors would contribute $170
million to increase the terminal’s design
capacity to 500,000 TEUs (6.2-m equiva-
lent units).
Designs complete, construction crews
set to increasing the dock area to 56 hect-
ares by stripping out about a metre of the
terminal’s existing surface area, laying
down a new sub base and fresh paving.
The biggest challenge, says Lorne
Keller, Vice-president of Project
Development for the Prince Rupert Port
Authority: the weather.
“While you’re moving all that material
around you’ve got a lot of rain. Sediment
PORT
PRINCE
A
OFA
MAJOR EXPANSION DESIGNED TO HANDLE
FUTURE EXPORTS OF CANADA’S OIL AND GAS
By Correspondent David Godkin
May 2012 • Canadian Mining Journal | 19
controls and those sorts of things were a
major construction challenge,” says Keller.
The biggest challenge on the design
side was extending the berth. The
15-metre draft alongside the existing
berth was insufficient for the 12,000 TEU
container vessels the port hoped to attract.
A decision was made to push the berth
face out 20 metres into deeper water and
increase the draft from 4.7 to 5.6 metres.
Solid rock provided a stable foundation in
which to anchor the pylons, says Keller.
“The last few metres we ran into some
fractured rock, which was a bit of an
installation issue, but other than that it
went really smoothly.”
Under Phase Two of the expansion, the
existing terminal will grow north and
south, quadrupling its capacity. That will
require extending the terminal area to the
northern tip of Fairview Terminal and
underwater blasting.
“We’re still going to have the eighteen
and a half meters alongside from the
berth face back towards the shore, but it’s
a relatively shallow piece of property. So
it’ll be easier to work in,” says Keller.
Currently, container ship cargo at
Prince Rupert is offloaded using three
1,800 tonne super post panamax cranes
with a reach of 22 containers. Up to 10
cranes will be on site at the completion of
the Phase Two expansion, says Keller.
“So they’ll have options. If there’s only
one vessel, they can have four to five
cranes working that vessel if they want.”
Assuming environmental and com-
mercial conditions make it practical to
proceed, the northern expansion will
begin construction this fall, says Keller.
This will add an additional berth and
increase the number of vessel calls per
week to 10.
How much container activity has the
expansion generated so far? Plenty, says
Shaun Stevenson. In fact, the terminal has
enjoyed record-breaking growth from
approximately four million tonnes to 20
million tonnes in the past four to five years.
Today, major shippers Cosco and Hanjin
Shipping of the CKYH Alliance operate
three weekly import services into Prince
Rupert – delivering everything from auto
parts to consumer-based electronics.
“Outbound we’re seeing forest and
agriculture products and mineral concen-
trates,” says Stevenson. It’s a trend he sees
continuing: “We expect to push the num-
ber of containers again this year and set
another record.”
More efficient on and off site…
If port officials undertook ambitious tasks
under Phase One, their plans for Phase
Two are downright Herculean. When it’s
completed in 2013, the container terminal
will quadruple to two million TEU capac-
ity, making it the second largest handling
facility on the West Coast.
Included in those ambitious plans is
expansion of Ridley Island Terminal, called
by port officials “a world leader” in the
transportation of coal from unit trains onto
ships. By the middle of last year, Ridley
Terminal had enjoyed a whopping 21 per
cent increase in activity, placing added pres-
sure on Ridley Terminals Inc. to expand.
“They’re well underway in terms of
their expansion,” says Keller. “They’ve
cleared their 35 acre parcel east of their
existing storage yard so some time next
year they’ll be able to extend their opera-
tions into that area and increase their stor-
age capacity.”
A fully automated facility, the 55 hect-
are terminal loads at an hourly rate of
9,000 tonnes of mostly metallurgical and
thermal coal, but also petroleum coke and
wood pellets. With an annual shipping
capacity for coal of 12 million tonnes and
storage capacity of 1.2 million tonnes, the
port expects its shipping capacity to grow
to 24 million tonnes. A big help will be the
two-car barrel dumper installed in
December, with a stacker reclaimer to be
installed some time next year.
Before that could happen, crews first
had to prepare the new 35 acre storage
site; their main obstacle - heavy, water-
laden muskeg. “Trying to scoop up water
with a back hoe is a bit of a challenge,”
Lorne Keller chuckles. “It’s highly saturat-
ed, so you’re moving as much water as you
are dirt.” Keller estimates contractor
Arctic Construction from Fort St. John,
B.C. had 60 work vehicles on site to
remove the overburden, including up to
40 rock trucks and about a dozen back
hoes.
By job’s end, crews had removed about
300,000 m3
of overburden, depositing it at
the port’s organic disposal site.
With the overburden gone, contractors
are now blasting rock within the high
points of the site, then crushing it and
Aerial photo show massive
storage areas and a network
of railway and conveyor
systems designed to make
shipping of coal and oil to
offshore customers.
Staging area for
supplies destined
for shipping.
20 | Canadian Mining Journal • May 2012	 www.canadianminingjournal.com
| Oil and Gas
using it as a sub base to create the new
storage yard.
Of course it’s one thing to increase
storage and loading capacity, quite
another to make sure trucks can get on
and off the new site. Currently, truck
traffic travels through Prince Rupert’s
downtown core. The answer is a brand
new $90-million Road Rail Utility
Corridor, consisting of three inbound
and two outbound tracks for coal, pot-
ash and other bulk terminal develop-
ments. Two additional tracks will form
a loop around the main part of Ridley
Island and one new track will extend off
the rail loop toward Ridley Terminals.
“This will introduce a whole new level
of efficiency to our container-handling
processes,” says Stevenson, “and further
integrate the existing coal and grain
facilities on Ridley Island.”
Road construction is set to begin this
summer, with the corridor open for busi-
ness in 2014. Even more exciting are
futurepossibilitiesfortheRidleyTerminal,
says Stevenson. The port is waiting on an
investment decision by Canpotex
Terminal Ltd for construction of a potash
export terminal, a decision Stevenson says
is imminent.
Put this in your pipe…
Much has also been made by reports
about Enbridge Inc.’s plans to possibly
ship oil from Alberta to container ships
on B.C.’s coast.
Environmentalists, and many First
Nations, staunchly oppose building the
pipeline, but what seems to have fallen
belowtheirradaristheenormousinterestin
Liquified Natural Gas (LNG). In fact, no
fewerthaneightprojectproposalshavebeen
announced for new LNG facilities in north
eastern B.C., mostly in or around Kitimat.
According to Shaun Stevenson, how-
ever, “there’s a lot more going on in the
LNG space than Kitimat.”
“BG Group is the second or third largest
player in the world in LNG. They’re in their
first phase of their site assessment and proj-
ectfeasibilityworkforanLBGsiteatRidley.”
The Port has provided BG Group with
200 acres to help it advance the LNG proj-
ect, says Stevenson. As for oil, the port has
a broad mandate to support Canada’s
trade agenda which has resulted in all
kinds of terminal proposals develop-
ments, he says.
His port could provide “a solution” for
Canada’s oil sector “as is being contem-
plated right now with the Northern
Gateway Project that Enbridge is pursuing
with Kitimat.”
“If that is a capacity that is going to be
required on the B.C. coast, then there’s no
doubt you’d look at Prince Rupert as one
of the safest places to do that.”
The one hitch could be Prince Rupert
City Council. In late February, Council
voted unanimously to formally oppose the
Enbridge Northern Gateway Pipeline, the
third northern local government to do so.
Is Shaun Stevenson still bullish about
the port’s future? Unquestionably. He calls
the outlook for the Port of Prince Rupert
“extraordinary.”
“That’s in the growth that we see happen-
ing in our existing terminal, but also in capi-
tal investments that are starting to line up. In
the next six to seven years we could see in
excess of $10 billion in capital expansion.”
Lorne Keller is just as excited going to
his job every day as Shaun Stevenson.
“I certainly am. It’s not often you can
work in a port that’s expanding and creat-
ing an enhanced gateway for goods
between North America and Asia.”	 CMJ
Coal has long been
a mainstay for port
operators on
Canada’s west coast.
Modern port facilities
enable huge ocean-going
ships to take on cargo
delivered to the docks by
road or rail.

Weitere ähnliche Inhalte

Mehr von Follow me on Twitter @Stockshaman

MONTORO RESOURCES ENTERS INTO FINANCING FACILITY UP TO $2-MILLION CAD AND APP...
MONTORO RESOURCES ENTERS INTO FINANCING FACILITY UP TO $2-MILLION CAD AND APP...MONTORO RESOURCES ENTERS INTO FINANCING FACILITY UP TO $2-MILLION CAD AND APP...
MONTORO RESOURCES ENTERS INTO FINANCING FACILITY UP TO $2-MILLION CAD AND APP...Follow me on Twitter @Stockshaman
 
Montoro NEWS release 03.12.19 doubles size estimate of Pecors Nickel copper p...
Montoro NEWS release 03.12.19 doubles size estimate of Pecors Nickel copper p...Montoro NEWS release 03.12.19 doubles size estimate of Pecors Nickel copper p...
Montoro NEWS release 03.12.19 doubles size estimate of Pecors Nickel copper p...Follow me on Twitter @Stockshaman
 
ZTEM 2D Synthetic Modelling - Pecors Magmatic Massive Sulphide Target - Power...
ZTEM 2D Synthetic Modelling - Pecors Magmatic Massive Sulphide Target - Power...ZTEM 2D Synthetic Modelling - Pecors Magmatic Massive Sulphide Target - Power...
ZTEM 2D Synthetic Modelling - Pecors Magmatic Massive Sulphide Target - Power...Follow me on Twitter @Stockshaman
 
International Montoro Res. Wicheeda North_Mag_Em_inv_interp_summary
International Montoro Res. Wicheeda North_Mag_Em_inv_interp_summaryInternational Montoro Res. Wicheeda North_Mag_Em_inv_interp_summary
International Montoro Res. Wicheeda North_Mag_Em_inv_interp_summaryFollow me on Twitter @Stockshaman
 
International Montoro Resources Inc. Wicheeda (Rare Earth Element, REE) proje...
International Montoro Resources Inc. Wicheeda (Rare Earth Element, REE) proje...International Montoro Resources Inc. Wicheeda (Rare Earth Element, REE) proje...
International Montoro Resources Inc. Wicheeda (Rare Earth Element, REE) proje...Follow me on Twitter @Stockshaman
 
International Montoro Res.(IMT.V) (IMTFF-OTC) (O4T1- Franfurt) Wicheeda North...
International Montoro Res.(IMT.V) (IMTFF-OTC) (O4T1- Franfurt) Wicheeda North...International Montoro Res.(IMT.V) (IMTFF-OTC) (O4T1- Franfurt) Wicheeda North...
International Montoro Res.(IMT.V) (IMTFF-OTC) (O4T1- Franfurt) Wicheeda North...Follow me on Twitter @Stockshaman
 
International Montoro Resources Inc. (IMTFF- USA) (IMT -TSXV) (O4T1-Frankfurt...
International Montoro Resources Inc. (IMTFF- USA) (IMT -TSXV) (O4T1-Frankfurt...International Montoro Resources Inc. (IMTFF- USA) (IMT -TSXV) (O4T1-Frankfurt...
International Montoro Resources Inc. (IMTFF- USA) (IMT -TSXV) (O4T1-Frankfurt...Follow me on Twitter @Stockshaman
 
International Montoro Res. Conductivity 2 d ztem inversion start model test ...
International Montoro Res. Conductivity  2 d ztem inversion start model test ...International Montoro Res. Conductivity  2 d ztem inversion start model test ...
International Montoro Res. Conductivity 2 d ztem inversion start model test ...Follow me on Twitter @Stockshaman
 
Montoro - Serpent River, Ontario Ni Cu PGE project 2D Geotech ZTEM survey r...
Montoro - Serpent River, Ontario  Ni Cu PGE project  2D Geotech ZTEM survey r...Montoro - Serpent River, Ontario  Ni Cu PGE project  2D Geotech ZTEM survey r...
Montoro - Serpent River, Ontario Ni Cu PGE project 2D Geotech ZTEM survey r...Follow me on Twitter @Stockshaman
 
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...Follow me on Twitter @Stockshaman
 
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...Follow me on Twitter @Stockshaman
 
International Montoro Resources (IMT-TSXV) Duhamel,Quebec - Ni, Cu, Co, Ti, ...
International Montoro Resources (IMT-TSXV) Duhamel,Quebec -  Ni, Cu, Co, Ti, ...International Montoro Resources (IMT-TSXV) Duhamel,Quebec -  Ni, Cu, Co, Ti, ...
International Montoro Resources (IMT-TSXV) Duhamel,Quebec - Ni, Cu, Co, Ti, ...Follow me on Twitter @Stockshaman
 
NEWS Montoro adds #Vanadium Titanium #Chromium ground@ Duhamel -#Nickel #Copp...
NEWS Montoro adds #Vanadium Titanium #Chromium ground@ Duhamel -#Nickel #Copp...NEWS Montoro adds #Vanadium Titanium #Chromium ground@ Duhamel -#Nickel #Copp...
NEWS Montoro adds #Vanadium Titanium #Chromium ground@ Duhamel -#Nickel #Copp...Follow me on Twitter @Stockshaman
 

Mehr von Follow me on Twitter @Stockshaman (20)

MONTORO RESOURCES ENTERS INTO FINANCING FACILITY UP TO $2-MILLION CAD AND APP...
MONTORO RESOURCES ENTERS INTO FINANCING FACILITY UP TO $2-MILLION CAD AND APP...MONTORO RESOURCES ENTERS INTO FINANCING FACILITY UP TO $2-MILLION CAD AND APP...
MONTORO RESOURCES ENTERS INTO FINANCING FACILITY UP TO $2-MILLION CAD AND APP...
 
Imt black fly mobilization and permit
Imt black fly mobilization and permitImt black fly mobilization and permit
Imt black fly mobilization and permit
 
PDAC 2020 ppp hand out 2020 [autosaved]
PDAC 2020 ppp hand out 2020 [autosaved]PDAC 2020 ppp hand out 2020 [autosaved]
PDAC 2020 ppp hand out 2020 [autosaved]
 
Lamontage down hole probe data pecors
Lamontage down hole probe data pecorsLamontage down hole probe data pecors
Lamontage down hole probe data pecors
 
Rich tv 2019 international montoro resources inc
Rich tv 2019 international montoro resources incRich tv 2019 international montoro resources inc
Rich tv 2019 international montoro resources inc
 
Montoro NEWS release 03.12.19 doubles size estimate of Pecors Nickel copper p...
Montoro NEWS release 03.12.19 doubles size estimate of Pecors Nickel copper p...Montoro NEWS release 03.12.19 doubles size estimate of Pecors Nickel copper p...
Montoro NEWS release 03.12.19 doubles size estimate of Pecors Nickel copper p...
 
ZTEM 2D Synthetic Modelling - Pecors Magmatic Massive Sulphide Target - Power...
ZTEM 2D Synthetic Modelling - Pecors Magmatic Massive Sulphide Target - Power...ZTEM 2D Synthetic Modelling - Pecors Magmatic Massive Sulphide Target - Power...
ZTEM 2D Synthetic Modelling - Pecors Magmatic Massive Sulphide Target - Power...
 
International Montoro Res. Wicheeda North_Mag_Em_inv_interp_summary
International Montoro Res. Wicheeda North_Mag_Em_inv_interp_summaryInternational Montoro Res. Wicheeda North_Mag_Em_inv_interp_summary
International Montoro Res. Wicheeda North_Mag_Em_inv_interp_summary
 
International Montoro Resources Inc. Wicheeda (Rare Earth Element, REE) proje...
International Montoro Resources Inc. Wicheeda (Rare Earth Element, REE) proje...International Montoro Resources Inc. Wicheeda (Rare Earth Element, REE) proje...
International Montoro Resources Inc. Wicheeda (Rare Earth Element, REE) proje...
 
International Montoro Res.(IMT.V) (IMTFF-OTC) (O4T1- Franfurt) Wicheeda North...
International Montoro Res.(IMT.V) (IMTFF-OTC) (O4T1- Franfurt) Wicheeda North...International Montoro Res.(IMT.V) (IMTFF-OTC) (O4T1- Franfurt) Wicheeda North...
International Montoro Res.(IMT.V) (IMTFF-OTC) (O4T1- Franfurt) Wicheeda North...
 
International Montoro Resources Inc. (IMTFF- USA) (IMT -TSXV) (O4T1-Frankfurt...
International Montoro Resources Inc. (IMTFF- USA) (IMT -TSXV) (O4T1-Frankfurt...International Montoro Resources Inc. (IMTFF- USA) (IMT -TSXV) (O4T1-Frankfurt...
International Montoro Resources Inc. (IMTFF- USA) (IMT -TSXV) (O4T1-Frankfurt...
 
International Montoro Res. Conductivity 2 d ztem inversion start model test ...
International Montoro Res. Conductivity  2 d ztem inversion start model test ...International Montoro Res. Conductivity  2 d ztem inversion start model test ...
International Montoro Res. Conductivity 2 d ztem inversion start model test ...
 
Montoro - Serpent River, Ontario Ni Cu PGE project 2D Geotech ZTEM survey r...
Montoro - Serpent River, Ontario  Ni Cu PGE project  2D Geotech ZTEM survey r...Montoro - Serpent River, Ontario  Ni Cu PGE project  2D Geotech ZTEM survey r...
Montoro - Serpent River, Ontario Ni Cu PGE project 2D Geotech ZTEM survey r...
 
Ppt 3 d geotechppp 3d_ztem_inversion_results_v4
Ppt 3 d geotechppp 3d_ztem_inversion_results_v4Ppt 3 d geotechppp 3d_ztem_inversion_results_v4
Ppt 3 d geotechppp 3d_ztem_inversion_results_v4
 
Geotech IMT ZTEM 3d ppp Nov.2018
Geotech IMT ZTEM 3d ppp Nov.2018Geotech IMT ZTEM 3d ppp Nov.2018
Geotech IMT ZTEM 3d ppp Nov.2018
 
Benchmark Megafactory Assessment exceeds 1 TWh by 2028
Benchmark Megafactory Assessment exceeds 1 TWh by 2028Benchmark Megafactory Assessment exceeds 1 TWh by 2028
Benchmark Megafactory Assessment exceeds 1 TWh by 2028
 
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
 
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
 
International Montoro Resources (IMT-TSXV) Duhamel,Quebec - Ni, Cu, Co, Ti, ...
International Montoro Resources (IMT-TSXV) Duhamel,Quebec -  Ni, Cu, Co, Ti, ...International Montoro Resources (IMT-TSXV) Duhamel,Quebec -  Ni, Cu, Co, Ti, ...
International Montoro Resources (IMT-TSXV) Duhamel,Quebec - Ni, Cu, Co, Ti, ...
 
NEWS Montoro adds #Vanadium Titanium #Chromium ground@ Duhamel -#Nickel #Copp...
NEWS Montoro adds #Vanadium Titanium #Chromium ground@ Duhamel -#Nickel #Copp...NEWS Montoro adds #Vanadium Titanium #Chromium ground@ Duhamel -#Nickel #Copp...
NEWS Montoro adds #Vanadium Titanium #Chromium ground@ Duhamel -#Nickel #Copp...
 

Kürzlich hochgeladen

WSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdfWSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdfJamesConcepcion7
 
EUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersEUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersPeter Horsten
 
How to Conduct a Service Gap Analysis for Your Business
How to Conduct a Service Gap Analysis for Your BusinessHow to Conduct a Service Gap Analysis for Your Business
How to Conduct a Service Gap Analysis for Your BusinessHelp Desk Migration
 
Introducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applicationsIntroducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applicationsKnowledgeSeed
 
Neha Jhalani Hiranandani: A Guide to Her Life and Career
Neha Jhalani Hiranandani: A Guide to Her Life and CareerNeha Jhalani Hiranandani: A Guide to Her Life and Career
Neha Jhalani Hiranandani: A Guide to Her Life and Careerr98588472
 
14680-51-4.pdf Good quality CAS Good quality CAS
14680-51-4.pdf  Good  quality CAS Good  quality CAS14680-51-4.pdf  Good  quality CAS Good  quality CAS
14680-51-4.pdf Good quality CAS Good quality CAScathy664059
 
Rakhi sets symbolizing the bond of love.pptx
Rakhi sets symbolizing the bond of love.pptxRakhi sets symbolizing the bond of love.pptx
Rakhi sets symbolizing the bond of love.pptxRakhi Bazaar
 
digital marketing , introduction of digital marketing
digital marketing , introduction of digital marketingdigital marketing , introduction of digital marketing
digital marketing , introduction of digital marketingrajputmeenakshi733
 
Interoperability and ecosystems: Assembling the industrial metaverse
Interoperability and ecosystems:  Assembling the industrial metaverseInteroperability and ecosystems:  Assembling the industrial metaverse
Interoperability and ecosystems: Assembling the industrial metaverseSiemens
 
Implementing Exponential Accelerators.pptx
Implementing Exponential Accelerators.pptxImplementing Exponential Accelerators.pptx
Implementing Exponential Accelerators.pptxRich Reba
 
Fundamentals Welcome and Inclusive DEIB
Fundamentals Welcome and  Inclusive DEIBFundamentals Welcome and  Inclusive DEIB
Fundamentals Welcome and Inclusive DEIBGregory DeShields
 
Unveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic ExperiencesUnveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic ExperiencesDoe Paoro
 
Paul Turovsky - Real Estate Professional
Paul Turovsky - Real Estate ProfessionalPaul Turovsky - Real Estate Professional
Paul Turovsky - Real Estate ProfessionalPaul Turovsky
 
Psychic Reading | Spiritual Guidance – Astro Ganesh Ji
Psychic Reading | Spiritual Guidance – Astro Ganesh JiPsychic Reading | Spiritual Guidance – Astro Ganesh Ji
Psychic Reading | Spiritual Guidance – Astro Ganesh Jiastral oracle
 
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdfGUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdfDanny Diep To
 
Entrepreneurial ecosystem- Wider context
Entrepreneurial ecosystem- Wider contextEntrepreneurial ecosystem- Wider context
Entrepreneurial ecosystem- Wider contextP&CO
 
WSMM Technology February.March Newsletter_vF.pdf
WSMM Technology February.March Newsletter_vF.pdfWSMM Technology February.March Newsletter_vF.pdf
WSMM Technology February.March Newsletter_vF.pdfJamesConcepcion7
 
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...SOFTTECHHUB
 
Darshan Hiranandani (Son of Niranjan Hiranandani).pdf
Darshan Hiranandani (Son of Niranjan Hiranandani).pdfDarshan Hiranandani (Son of Niranjan Hiranandani).pdf
Darshan Hiranandani (Son of Niranjan Hiranandani).pdfShashank Mehta
 

Kürzlich hochgeladen (20)

WSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdfWSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdf
 
EUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersEUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exporters
 
How to Conduct a Service Gap Analysis for Your Business
How to Conduct a Service Gap Analysis for Your BusinessHow to Conduct a Service Gap Analysis for Your Business
How to Conduct a Service Gap Analysis for Your Business
 
Introducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applicationsIntroducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applications
 
WAM Corporate Presentation April 12 2024.pdf
WAM Corporate Presentation April 12 2024.pdfWAM Corporate Presentation April 12 2024.pdf
WAM Corporate Presentation April 12 2024.pdf
 
Neha Jhalani Hiranandani: A Guide to Her Life and Career
Neha Jhalani Hiranandani: A Guide to Her Life and CareerNeha Jhalani Hiranandani: A Guide to Her Life and Career
Neha Jhalani Hiranandani: A Guide to Her Life and Career
 
14680-51-4.pdf Good quality CAS Good quality CAS
14680-51-4.pdf  Good  quality CAS Good  quality CAS14680-51-4.pdf  Good  quality CAS Good  quality CAS
14680-51-4.pdf Good quality CAS Good quality CAS
 
Rakhi sets symbolizing the bond of love.pptx
Rakhi sets symbolizing the bond of love.pptxRakhi sets symbolizing the bond of love.pptx
Rakhi sets symbolizing the bond of love.pptx
 
digital marketing , introduction of digital marketing
digital marketing , introduction of digital marketingdigital marketing , introduction of digital marketing
digital marketing , introduction of digital marketing
 
Interoperability and ecosystems: Assembling the industrial metaverse
Interoperability and ecosystems:  Assembling the industrial metaverseInteroperability and ecosystems:  Assembling the industrial metaverse
Interoperability and ecosystems: Assembling the industrial metaverse
 
Implementing Exponential Accelerators.pptx
Implementing Exponential Accelerators.pptxImplementing Exponential Accelerators.pptx
Implementing Exponential Accelerators.pptx
 
Fundamentals Welcome and Inclusive DEIB
Fundamentals Welcome and  Inclusive DEIBFundamentals Welcome and  Inclusive DEIB
Fundamentals Welcome and Inclusive DEIB
 
Unveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic ExperiencesUnveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic Experiences
 
Paul Turovsky - Real Estate Professional
Paul Turovsky - Real Estate ProfessionalPaul Turovsky - Real Estate Professional
Paul Turovsky - Real Estate Professional
 
Psychic Reading | Spiritual Guidance – Astro Ganesh Ji
Psychic Reading | Spiritual Guidance – Astro Ganesh JiPsychic Reading | Spiritual Guidance – Astro Ganesh Ji
Psychic Reading | Spiritual Guidance – Astro Ganesh Ji
 
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdfGUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
 
Entrepreneurial ecosystem- Wider context
Entrepreneurial ecosystem- Wider contextEntrepreneurial ecosystem- Wider context
Entrepreneurial ecosystem- Wider context
 
WSMM Technology February.March Newsletter_vF.pdf
WSMM Technology February.March Newsletter_vF.pdfWSMM Technology February.March Newsletter_vF.pdf
WSMM Technology February.March Newsletter_vF.pdf
 
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
 
Darshan Hiranandani (Son of Niranjan Hiranandani).pdf
Darshan Hiranandani (Son of Niranjan Hiranandani).pdfDarshan Hiranandani (Son of Niranjan Hiranandani).pdf
Darshan Hiranandani (Son of Niranjan Hiranandani).pdf
 

Prince of a Port

  • 1. 18 | Canadian Mining Journal • May 2012 www.canadianminingjournal.com | Oil and Gas I nternational trade is a fickle busi- ness, and no more so than in China. The near collapse of its burgeoning trade economy in the 1990s had Canadian shippers shifting their business back to traditional U.S. markets, where it would remain until the Asian economy rebounded a decade later. But beyond the varying market condi- tions,shippersalreadyhadtheireyestrained on something else; namely, container ships, the key elements in the entire offshore ship- ping scenario. These were now the shipping modeofchoice,representingarealopportu- nity for those few North American ports with the capacity to handle the vessel’s mas- sive dimensions. Other ports, like Prince Rupert, says Shaun Stevenson, Vice-president of Trade Development and Public Affairs for the Prince Rupert Port Authority, could only look on with envy. “We couldn’t participate in that busi- ness so it meant changing to meet the evolving needs of shippers and exporters in Canada, but also creating new capaci- ties where the growth opportunity was,” says Stevenson. Prince Rupert’s unique position in North America seemed to make increased trade with Asia a no-brainer. Up to a day- and-a- half closer to Asia than Los Angeles and Seattle with the deepest natural har- bour on the continent, the port knew it could compete. Problem was its main Fairview Terminal consisted of a traditional general cargo and break bulk terminals. It had to expand, and expand quickly. Build it bigger, built it better… The announcement came in April 2005: The Port of Prince Rupert would con- vert its Fairview Terminal into an inter- modal container shipping terminal, with a major expansion of the port’s wharf and investments in rail infra- structure connecting Toronto, Montreal and Chicago to Asian markets. Under Phase One, public and private sector investors would contribute $170 million to increase the terminal’s design capacity to 500,000 TEUs (6.2-m equiva- lent units). Designs complete, construction crews set to increasing the dock area to 56 hect- ares by stripping out about a metre of the terminal’s existing surface area, laying down a new sub base and fresh paving. The biggest challenge, says Lorne Keller, Vice-president of Project Development for the Prince Rupert Port Authority: the weather. “While you’re moving all that material around you’ve got a lot of rain. Sediment PORT PRINCE A OFA MAJOR EXPANSION DESIGNED TO HANDLE FUTURE EXPORTS OF CANADA’S OIL AND GAS By Correspondent David Godkin
  • 2. May 2012 • Canadian Mining Journal | 19 controls and those sorts of things were a major construction challenge,” says Keller. The biggest challenge on the design side was extending the berth. The 15-metre draft alongside the existing berth was insufficient for the 12,000 TEU container vessels the port hoped to attract. A decision was made to push the berth face out 20 metres into deeper water and increase the draft from 4.7 to 5.6 metres. Solid rock provided a stable foundation in which to anchor the pylons, says Keller. “The last few metres we ran into some fractured rock, which was a bit of an installation issue, but other than that it went really smoothly.” Under Phase Two of the expansion, the existing terminal will grow north and south, quadrupling its capacity. That will require extending the terminal area to the northern tip of Fairview Terminal and underwater blasting. “We’re still going to have the eighteen and a half meters alongside from the berth face back towards the shore, but it’s a relatively shallow piece of property. So it’ll be easier to work in,” says Keller. Currently, container ship cargo at Prince Rupert is offloaded using three 1,800 tonne super post panamax cranes with a reach of 22 containers. Up to 10 cranes will be on site at the completion of the Phase Two expansion, says Keller. “So they’ll have options. If there’s only one vessel, they can have four to five cranes working that vessel if they want.” Assuming environmental and com- mercial conditions make it practical to proceed, the northern expansion will begin construction this fall, says Keller. This will add an additional berth and increase the number of vessel calls per week to 10. How much container activity has the expansion generated so far? Plenty, says Shaun Stevenson. In fact, the terminal has enjoyed record-breaking growth from approximately four million tonnes to 20 million tonnes in the past four to five years. Today, major shippers Cosco and Hanjin Shipping of the CKYH Alliance operate three weekly import services into Prince Rupert – delivering everything from auto parts to consumer-based electronics. “Outbound we’re seeing forest and agriculture products and mineral concen- trates,” says Stevenson. It’s a trend he sees continuing: “We expect to push the num- ber of containers again this year and set another record.” More efficient on and off site… If port officials undertook ambitious tasks under Phase One, their plans for Phase Two are downright Herculean. When it’s completed in 2013, the container terminal will quadruple to two million TEU capac- ity, making it the second largest handling facility on the West Coast. Included in those ambitious plans is expansion of Ridley Island Terminal, called by port officials “a world leader” in the transportation of coal from unit trains onto ships. By the middle of last year, Ridley Terminal had enjoyed a whopping 21 per cent increase in activity, placing added pres- sure on Ridley Terminals Inc. to expand. “They’re well underway in terms of their expansion,” says Keller. “They’ve cleared their 35 acre parcel east of their existing storage yard so some time next year they’ll be able to extend their opera- tions into that area and increase their stor- age capacity.” A fully automated facility, the 55 hect- are terminal loads at an hourly rate of 9,000 tonnes of mostly metallurgical and thermal coal, but also petroleum coke and wood pellets. With an annual shipping capacity for coal of 12 million tonnes and storage capacity of 1.2 million tonnes, the port expects its shipping capacity to grow to 24 million tonnes. A big help will be the two-car barrel dumper installed in December, with a stacker reclaimer to be installed some time next year. Before that could happen, crews first had to prepare the new 35 acre storage site; their main obstacle - heavy, water- laden muskeg. “Trying to scoop up water with a back hoe is a bit of a challenge,” Lorne Keller chuckles. “It’s highly saturat- ed, so you’re moving as much water as you are dirt.” Keller estimates contractor Arctic Construction from Fort St. John, B.C. had 60 work vehicles on site to remove the overburden, including up to 40 rock trucks and about a dozen back hoes. By job’s end, crews had removed about 300,000 m3 of overburden, depositing it at the port’s organic disposal site. With the overburden gone, contractors are now blasting rock within the high points of the site, then crushing it and Aerial photo show massive storage areas and a network of railway and conveyor systems designed to make shipping of coal and oil to offshore customers. Staging area for supplies destined for shipping.
  • 3. 20 | Canadian Mining Journal • May 2012 www.canadianminingjournal.com | Oil and Gas using it as a sub base to create the new storage yard. Of course it’s one thing to increase storage and loading capacity, quite another to make sure trucks can get on and off the new site. Currently, truck traffic travels through Prince Rupert’s downtown core. The answer is a brand new $90-million Road Rail Utility Corridor, consisting of three inbound and two outbound tracks for coal, pot- ash and other bulk terminal develop- ments. Two additional tracks will form a loop around the main part of Ridley Island and one new track will extend off the rail loop toward Ridley Terminals. “This will introduce a whole new level of efficiency to our container-handling processes,” says Stevenson, “and further integrate the existing coal and grain facilities on Ridley Island.” Road construction is set to begin this summer, with the corridor open for busi- ness in 2014. Even more exciting are futurepossibilitiesfortheRidleyTerminal, says Stevenson. The port is waiting on an investment decision by Canpotex Terminal Ltd for construction of a potash export terminal, a decision Stevenson says is imminent. Put this in your pipe… Much has also been made by reports about Enbridge Inc.’s plans to possibly ship oil from Alberta to container ships on B.C.’s coast. Environmentalists, and many First Nations, staunchly oppose building the pipeline, but what seems to have fallen belowtheirradaristheenormousinterestin Liquified Natural Gas (LNG). In fact, no fewerthaneightprojectproposalshavebeen announced for new LNG facilities in north eastern B.C., mostly in or around Kitimat. According to Shaun Stevenson, how- ever, “there’s a lot more going on in the LNG space than Kitimat.” “BG Group is the second or third largest player in the world in LNG. They’re in their first phase of their site assessment and proj- ectfeasibilityworkforanLBGsiteatRidley.” The Port has provided BG Group with 200 acres to help it advance the LNG proj- ect, says Stevenson. As for oil, the port has a broad mandate to support Canada’s trade agenda which has resulted in all kinds of terminal proposals develop- ments, he says. His port could provide “a solution” for Canada’s oil sector “as is being contem- plated right now with the Northern Gateway Project that Enbridge is pursuing with Kitimat.” “If that is a capacity that is going to be required on the B.C. coast, then there’s no doubt you’d look at Prince Rupert as one of the safest places to do that.” The one hitch could be Prince Rupert City Council. In late February, Council voted unanimously to formally oppose the Enbridge Northern Gateway Pipeline, the third northern local government to do so. Is Shaun Stevenson still bullish about the port’s future? Unquestionably. He calls the outlook for the Port of Prince Rupert “extraordinary.” “That’s in the growth that we see happen- ing in our existing terminal, but also in capi- tal investments that are starting to line up. In the next six to seven years we could see in excess of $10 billion in capital expansion.” Lorne Keller is just as excited going to his job every day as Shaun Stevenson. “I certainly am. It’s not often you can work in a port that’s expanding and creat- ing an enhanced gateway for goods between North America and Asia.” CMJ Coal has long been a mainstay for port operators on Canada’s west coast. Modern port facilities enable huge ocean-going ships to take on cargo delivered to the docks by road or rail.