THE NORTHERN COLLECTOR WATER TUNNEL
PHASE 1 PROJECT
Nairobi City is the international, regional, administrative and economic
hub for Kenya. The city generates approximately 60% GDP. Nairobi,
the capital of Republic of Kenya, is facing chronic water shortage
including its surrounding area. This is because the proposed additional
water source, the Northern Collector Scheme, was not implemented as
proposed in 1998. The scheme was initially planned as part of Third
Nairobi Water Supply Project. The target year for implementation
of the Northern Collector Phase 1 was year 2010. The expected
average production capacity of the now proposed Northern Collector
tunnel Phase 1 project is 1.6m3/sec (140,000m3/day) with an 84%
reliability. The safe yield at Ndakaini dam will however be 1.24m3/
day with a 90% reliability.
The present water deficit in Nairobi City is 125,000m3/day. In line with
the National Development Plan, Vision 2030, the Government of Kenya
has prioritized improvement of water services in Nairobi City and the
surrounding areas. To achieve this objectives the Northern Collector
Tunnel Phase 1 project is a priority project.
A number of studies have been carried out on the Northern
Collector System, which have involved detailed data
collection and analysis to assess its viability.
The initial studies are documented in Feasibility Reports
of 1998, carried out by M/S Howard Humphreys and
Partners Ltd under the Third Nairobi Water Supply
Project. The 1998 report investigated to greater detail
the technical and economic viability of the Northern
Collector Scheme as a source of water after Ndakaini
Dam. The report recommended implementation of the
Northern Water Collector Tunnel Phase 1 project by the
year 2010. Due to funding challenges the project was not
implemented as planned.
In the year 2012, Athi Water Services Board through
Egis/MIBP JV carried out the Feasibility Study and Master
Plan for Developing New Water Sources for Nairobi and
Satellite Towns. This study validated the 1998 report and
further recommended implementation of the Northern
Collector Tunnel project.
Additional hydrological reviews for the project were
undertaken by M/s GIBB Africa as part of the ESIA Study
process further validating the hydrological and ecological
viability of the project.
BACKGROUND
FEASIBILITY AND VALIDATION OF 1998
PROJECT PROPOSAL
2
1
The NCT 1 project is located along the eastern fringes of the Aberdare
Conservation Area approximately 60 km North of Nairobi City. The
works are located in Kangema and Kigumo Sub-Counties of Muranga
County.
The project involves:
• Construction of river intake structures at Maragua, Gikie and Irati 	
rivers
• Construction of access adits at Gikigie, Irati and Kaanja;
• Construction of 11km long, 3.0 diameter main water tunnel from 	
Maragua intake to Githika outfall. The tunnel will be fully concrete 	
lined. A valuation roll completed in December 2015 indicate that 	
221 people currently live on top of the tunnel.
The other program components involve:
• Construction of high level Water Treatment Plant at Kigoro and the	
water transmission pipelines to Nairobi City of capacity of 		
140,000m3/day
• Construction of Muranga and Kiambu County community water 	
supply projects to ensure water supply to host communities is also	
improved.
• Construction of Nairobi city water distribution network to ensure 	
equitable distribution.
• Improvement of water services in Nairobi Satellite towns within 	
Kiambu and Kajiado Counties.
PROJECT DEFINITION AND SCOPE
3
View of Project Area
Viewofprojectare a
The detailed design for the Northern Collector
Water Transfer Project phase 1, has considered all
findings of the hydrological and ecological studies
to ensure that the project shall neither result in low
river flows nor divert water during low river flow
seasons. The flows used for the design are such that
the environmental and ecological requirements as
defined by Trout Fish habitat, downstream water
rights and compensation flow as a whole are
guaranteed.
The river flow data for the previous 40 years for
each of the rivers was obtained and analysed in
the hydrological study. The ecological requirements
have been defined following analysis of ecological
evidence for all flora and fauna including Trout
fish. The reserve flows for the three rivers have
therefore not only been defined as per the
Water Resource Management Authority (WRMA)
guidelines but also the findings of these analytical
studies. Cumulatively the reserve flows for the
three rivers adopted for design is 141,696.00
m3/day against the WRMA standard definition of
93,744.00 m3/day.
The design of the intake structures is such that an
unregulated compensation flow channel is provided
for at an invert level lower than the tunnel invert
level to ensure water only gets into the tunnel after
the reserve flows for current/future downstream
users and river environmental flows has been
released. That means the NCT will not have impact
on the frequency of rivers experiencing low flow
conditions or drying up, because before these
conditions occur, the abstraction will automatically
stop because water will only flow through the
unregulated compensation flow channel into the
river and not into the tunnel which is at a higher
level. Certainly as per the design they will be
absolutely no abstraction during low river flows.
ENVIRONMENTAL AND SOCIAL IMPACT
4
A consultative environmental and social impact assessment for the project was undertaken. The ESIA
study report defined the probable project impacts and mitigation measures. A detailed Environmental
Management Plan has been developed and a Monitoring plan drawn. Modalities of ensuring compliance
with the Environmental Management Plan have been put in place. Notable areas include:-
Water Flows in Rivers Maragua, Gikigie and Irati
In the calculation of downstream water needs, the abstraction
capacities of all existing downstream consumptive demands
which include domestic, industrial, irrigation and other
miscellaneous abstractors which are distributed along the
river profiles were taken as occurring at the proposed NCT1
intakes. Details of the existing and planned water abstraction
capacities, including information on current irrigation and
hydro-power projects within the river systems, were obtained
from WRMA offices and abstraction licences, Water Service
Providers in Murang’a County as well as design reports
obtained from Tana Water Services Board (TWSB). A minimum
factor of safety of 1.2 was then used in carrying out the water
balance analysis.
Although Section 32 (2) of the Kenyan Water Act, 2002
states that “the use of water for domestic purposes shall take
precedence over the use of water for any other purpose…”
the potential impact of the project on existing hydro-power
generation schemes was also studied. The cumulative impacts of
the project on existing hydro power generation was found to be
a reduction of 2.32% of the Mean Annual Inflow to Masinga
reservoir.
Proposed Access Road to Outfall portal site
Downstream water rights and Future demand
	
  
	
  	
  	
  	
  Kaanja Adit Portal
	
  
Irati Intake & Shaft
Irati River	
  	
   	
   	
  
Thika River 	
   	
   	
  	
  	
  	
  	
  	
  Thika Dam
	
  
Gikigie Intake/Access Adit
Gikigie River	
   	
   	
  	
  	
  
	
  
Maragua Intake
	
   Maragua River	
   	
   	
  
Figure	
  2:	
  Diagram	
  showing	
  the	
  project	
  schematic	
  
	
  
	
  
	
   	
  
	
  
	
  
	
  
	
  
	
   	
   	
   	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  
	
  Makomboki Outfall
	
  
DRYWEATHERFLOW WETWEATHERFLOW
Maraguariverfacingdownstreamfromthebridge Maraguariverview
Iratiriverview(pipesubmerged)Iratiriverviewupstreamfrombridge
As per the design philosophy of the intake
structures explained in (a) above it’s clear
that the Northern Collector Tunnel Project will
mostly abstract flood waters. This will help in
mitigating the negative impacts of flooding
downstream and related landslides.
To ensure that positive impacts such as
irrigation and storage reservoirs downstream
and other water uses during heavy rains
are not jeopardized, the Northern Collector
Tunnel Phase 1 project design has been
restricted to cumulatively abstract only
43% of the maximum flood waters leaving
57% available for investments in storage
infrastructure. From drainage patterns, the
average maximum flood water at the three
rivers abstraction points is 1,198,368m3/
day, NCT1 will abstract 513,388 m3/
day. Since existing and known plans for
future irrigation schemes were considered in
defining the compensation flows, this covers
any other future and unknown possible
abstraction. Further, the balance of flood
passed downstream of the weirs of about
684,980 m3/day is expected to increase
downstream due to increase in water shed
areas.
Abstraction of Flood waters
In addition to ensuring sufficient water requirements for the aquatic
flora and fauna, the river structures have been designed to ensure
free migration of the evidenced trout fish in all the three rivers.
Fish ladders and fish passes have been provided for and sized
accordingly.
Sustainability of Aquatic Life
To ensure there are no effects to ground water sources, a
fully lined tunnel will be constructed. This will ensure there’s no
infiltration of underground water into the tunnel or exfiltration out
of the tunnel. During construction contact grouting will be done to
the outside rock to ensure structural integrity and to avoid flow of
groundwater from an aquifer into and around the outside of the
tunnel.
Although the tunnel is ultimately not expected to have any
impacts on ground and surface water resources, Athi Water
Services Board (AWSB) has undertaken a baseline study of the
resources on top of the tunnel and surrounding the tunnel corridor.
The baseline survey report is available in our website at http://
awsboard.go.ke/2016/01/06/baseline-survey-for-wells-and-
boreholes-along-the-nct-1-corridor. AWSB will monitor these
water resources during and after construction. Should there be
any negative impact on these water resources during construction
while the lining and grouting is still ongoing, AWSB will supply
all impacted people with water free of charge. Should there be
any unexpected negative impact on these water resources after
construction, AWSB would implement alternative water supply
schemes for all impacted people. The water resource monitoring
results will be made available to Muranga County and the
public. A valuation roll completed in December 2015 indicate
that 221 people currently live on top of the tunnel.
Water resource management and environmental conservation
are the mandate of the Water Resource Management
Authority (WRMA) and Water Resource User Associations
(WRUAs). AWSB as a user department, is however very
keen on environmental conservation. As such AWSB has been
assisting the Chania WRUA in following up on the proposal
for Lower Chania Catchment Protection to ensure it’s submitted
to World Bank through WRMA for financing under the Water
Security and Climate Resilience Project.
In consultation with the Water Resources Management
Authority, Maragua WRUA and Murang’a County Government
AWSB will support Upper Maragua WRUA in the updating of
the Maragua Sub-Catchment Management Strategy.
AWSB is and will also continue to support and be involved in
tree planting together with Water Resource User Associations.
It should be noted that no deforestation will carried out in
order to pave way for the tunnel construction.
In addition, AWSB has committed to undertake an integrated
water masterplan for Muranga County.
Ground Water aquifers and surface water resources Environmental sustainability and Catchment Protection
Social Considerations
As part of the Northern Collector Tunnel Phase 1 project, the GOK through Athi Water will undertake the following
activities that will improve the living standards and increase water supply to communities along the tunnel and its
surrounding:
•	 Purchase an Ambulance for Gikoe dispensary to be used by the project and the surrounding communities along 	
	 the tunnel
•	 Give priority for employment in the Project to people from Murang’a County.
•	 Construct permanent residency for the supervision team in Kinyona, Gikoe and Mununga which will revert to the 	
	 Muranga County government
•	 Ensure excavated material that is not utilized by the project will be committed for use by Muranga County 		
	government
•	 Ensure roads are maintained during construction
•	 Engage Muranga University in project activities like geotechnical investigation and supervision of specialized 	
	works.
Host Community Benefit Projects in Muranga County
No Project Name Scope and Target Areas Status Status
1. Muranga Bulk Water
Supply
(undertaken by
TWSB)
Laid 81Km water pipelines, Constructed 11000m3/day water tworks and 2000m3/day
concrete tank, Augmented sewerage system in Muranga town to serve 189,000 persons in
Muranga South and Muranga Town. The system is designed/ expected to serve 417,000
persons by 2030.
Completed Kshs
1.6 Billion
2. Muranga Community
Water Project
Construction of two 4000m3/day water treatment units and laying of 147Km water pipe-
lines to improve water supply service from 10hrs to 24hrs to 400,000 people by 2030 in
Kandara, Kigumo, Kangema, Kiharu, and Maragua constituencies of Muranga County.
Works are
85% done.
Completion in
April 2016
Kshs 749
million
3. Gatanga Community
water project
Construct intakes along the Kiama and Kimakia rivers, 2 No. 3000 m3/day water treatment
plant and lay 35km pipelines boosting water supply from 6hrs to 16hrs to 70,000 people in
the lower areas of Kiunyu and Gatunyu areas of Gatanga Constituency.
Works at 70%
done. Comple-
tion in March
2016
Kshs 264
million
4. Gatango water
project
construction of intake works, 30km water mainlines and 4 no storage tanks to improve water
supply to 140,000 people in Gaturi and Kamacharia wards
Tender docu-
mentation
Kshs 170
million
5 Ithanga Water
Project
Construction of river intake weir on Thika river, 47Km water mains, 6000m3/day water treat-
ment plant to improve supply in Ithanga
Awaiting sign-
ing of FC
Kshs 1.4
Billion
6 Gatagwagwa stor-
age tank
Construction of 225m3 clear water storage tank to complement gatagwagwa community
water project
Completion in
April 2016
Kshs 3.3
Million
7 Gikoe Community Dis-
pensary
Improvement of Gikoe dispensary and purchase of an ambulance to serve people from
Kigumo constituency and surrounding areas.
Ongoing.
Completion in
March 2016
Part of
NCT1
works
8 Ichichi, Kiruri and
Makomboki
Rehabilitation of 3 intake weirs, construction of 225m3 storage tanks, water pipeline exten-
sion to serve approximately 50,000 people in Gitwe-Kanderendu in Kugumo upstream of
Thika Dam, Makomboki, Ichichi/Githaini, Karurumo and Kiruri communities along the tunnel.
Design Stage Kshs 170
Million
No Project Name Scope and Target Areas Status Cost
1 Independent Mataara and Komothai Water
Production Plants
Construction of 32,000m3/day 5No. water
treatment plants to benefits 128,000 people
in Karimenu, Karure, Ndarugu/Gatundu South
Operational Kshs 800 Million
2 Improvement of community water supply
schemes
Drilling and Equipping of 15 No. boreholes to
serve 1000 people in Kiambu, Thika, Limuru
and Kikuyu
Completion in
March 2016
Kshs 200 Million
3 Kiambu Water Supply Works (Wassip AF) Construct intakes along the Kiama and Kima-
kia rivers, 2 No. 3000 m3/day water treat-
ment plant and lay 35km pipelines boosting
water supply from 6hrs to 16hrs to 70,000
people in the lower areas of Kiunyu and Ga-
tunyu areas of Gatanga Constituency.
Works at 70%
done. Comple-
tion in March
2016
Kshs 264 million
4 Ruiru Water Supply Project: Works 60% done. Completion in April 2016 Kshs 530Million Kshs 170 million
Construct 13,000m3/d WTP, River Intake weir
of 4000m3/day, transmission Pipelines and
5,000m3 Tank to benefit 68,000 residents of
Ruiru and Juja Towns
Main works operational. Tank to be complete
in February 2016
Kshs 970Million Kshs 1.4 Billion
5 Tigoni, Githunguri and Komothai Water Sup-
ply Schemes
Construction of 1000m3/day treatment
plant, laying of 145km pipeline to benefit
10,000 people in Tigoni and Githunguri
areas
Completion in
March 2017
Kshs 300 million
6 Jacaranda-Githurai Water Supply Project Construction of 135km water mains to
improve water supply to 188,000 people
in ruiru, Githurai 45, part of Mwiki and
Mwihoko
Advance
procurement
of consultant
ongoing
Kshs 1.3 Billion
Host Community Benefit Projects in Kiambu County
Following completion of the detailed designs and obtaining the
necessary regulatory approvals, implementation of the Northern
Collector Tunnel Phase 1 project commenced on 24th February 2015.
To facilitate speedy implementation an implementation framework
has been prepared for the project to ensure continued consultations
with stakeholders, quality assurance, continuous technical and
environmental soundness and that the project does not result in
adverse environmental effects.
PROJECT IMPLEMENTATION
6
The Ministry of Water and Irrigation is establishing a project steering
committee comprising representatives from National and County
governments to oversee the implementation of the project. In addition,
Athi Water Services Board is currently supporting the recruitment of a
high level Independent Panel of experts comprising of tunnel expert,
geotechnical expert, hydraulic/hydrology expert, dam expert, community
water supplies expert and an environment/ecological expert. Selection of
the independent panel of experts will be coordinated by the Kenya Water
Services Regulatory Board (WASREB). The selection panel will constitute
independent relevant professionals from the Institute of Engineers of Kenya,
the Geological Society of Kenya, the Hydrological Society of Kenya and
the Environment Institute of Kenya. This panel will play an independent
advisory role to the project steering committee on project implementation
modalities.
The Northern Collector Water Transfer Tunnel Phase 1 is the first inter-basin
water transfer project following the enactment of the new constitution and
formulation of county governments. It is considered that there’s potential for
future additional benefit sharing between the County of origin, Muranga
County, and the water receiving county, Nairobi City, once the country
has established a legal framework for inter-county water transfers. More
information on the 4th Nairobi water supply program and the Northern
collector tunnel Phase 1 project can be obtained from our website:
www.awsboard.go.ke
www.awsboard.go.ke
Our Contacts
3rd Floor, Africa Re Centre, Hospital Rd-Upper Hill,
P.O. Box 45283-00100, Nairobi, Kenya
Tel: +254-20-274292/3, +254-20-2727439-42
GSM: +254-715-688 272
Email: Info@awsboard.go.ke
1 von 12

Recomendados

Strategic Action Planning for Revival of Bangalore Lakes _ESG von
Strategic Action Planning for Revival of Bangalore Lakes _ESGStrategic Action Planning for Revival of Bangalore Lakes _ESG
Strategic Action Planning for Revival of Bangalore Lakes _ESGEkonnect
1.6K views21 Folien
Management of the River Tees von
Management of the River TeesManagement of the River Tees
Management of the River TeesBourne Grammar School
11.6K views4 Folien
Sluice gates von
Sluice gatesSluice gates
Sluice gatesKaran Patel
2.8K views15 Folien
Puducherry von
Puducherry Puducherry
Puducherry hydrologyproject0
821 views26 Folien
Design mannual for small scale irrigation scheme book von
Design mannual for small scale irrigation scheme bookDesign mannual for small scale irrigation scheme book
Design mannual for small scale irrigation scheme bookSurendra Maharjan
23.1K views131 Folien
CAMBRIDGE AS GEOGRAPHY - CASE STUDY: RIVER HARBOURNE von
CAMBRIDGE AS GEOGRAPHY - CASE STUDY: RIVER HARBOURNECAMBRIDGE AS GEOGRAPHY - CASE STUDY: RIVER HARBOURNE
CAMBRIDGE AS GEOGRAPHY - CASE STUDY: RIVER HARBOURNEGeorge Dumitrache
2.1K views15 Folien

Más contenido relacionado

Was ist angesagt?

Helvetas Ethiopia trail bridge experience von
Helvetas Ethiopia trail bridge experience Helvetas Ethiopia trail bridge experience
Helvetas Ethiopia trail bridge experience walkafine
1.6K views29 Folien
Hydro power plant von
Hydro power plantHydro power plant
Hydro power plantSkFarhadHasan
544 views51 Folien
Waterfront development von
Waterfront developmentWaterfront development
Waterfront developmentmisschand
28.3K views22 Folien
Storm water drainage problem of Surat city & its solutions due to flood in ri... von
Storm water drainage problem of Surat city & its solutions due to flood in ri...Storm water drainage problem of Surat city & its solutions due to flood in ri...
Storm water drainage problem of Surat city & its solutions due to flood in ri...Kishan Bhadiyadra
1K views54 Folien
Ch#1 ADVANCED OPEN CHANNEL HYDRAULICS.pdf von
Ch#1 ADVANCED OPEN CHANNEL HYDRAULICS.pdfCh#1 ADVANCED OPEN CHANNEL HYDRAULICS.pdf
Ch#1 ADVANCED OPEN CHANNEL HYDRAULICS.pdfHadiqa Qadir
152 views18 Folien
2170609 irrigation engineering cross drainage works von
2170609 irrigation engineering cross drainage works2170609 irrigation engineering cross drainage works
2170609 irrigation engineering cross drainage worksJaydeep Dave
739 views19 Folien

Was ist angesagt?(20)

Helvetas Ethiopia trail bridge experience von walkafine
Helvetas Ethiopia trail bridge experience Helvetas Ethiopia trail bridge experience
Helvetas Ethiopia trail bridge experience
walkafine1.6K views
Waterfront development von misschand
Waterfront developmentWaterfront development
Waterfront development
misschand28.3K views
Storm water drainage problem of Surat city & its solutions due to flood in ri... von Kishan Bhadiyadra
Storm water drainage problem of Surat city & its solutions due to flood in ri...Storm water drainage problem of Surat city & its solutions due to flood in ri...
Storm water drainage problem of Surat city & its solutions due to flood in ri...
Ch#1 ADVANCED OPEN CHANNEL HYDRAULICS.pdf von Hadiqa Qadir
Ch#1 ADVANCED OPEN CHANNEL HYDRAULICS.pdfCh#1 ADVANCED OPEN CHANNEL HYDRAULICS.pdf
Ch#1 ADVANCED OPEN CHANNEL HYDRAULICS.pdf
Hadiqa Qadir152 views
2170609 irrigation engineering cross drainage works von Jaydeep Dave
2170609 irrigation engineering cross drainage works2170609 irrigation engineering cross drainage works
2170609 irrigation engineering cross drainage works
Jaydeep Dave739 views
Module 1 introduction von Ankit Patel
Module 1 introductionModule 1 introduction
Module 1 introduction
Ankit Patel1.5K views
14 Europian cities von EACT_COEP
14 Europian cities14 Europian cities
14 Europian cities
EACT_COEP1.3K views
Rainwater harvesting von shalu786
Rainwater harvestingRainwater harvesting
Rainwater harvesting
shalu7863.7K views
Gujarat International Finance Tech City - Gift von Andhra University
Gujarat International Finance Tech City - GiftGujarat International Finance Tech City - Gift
Gujarat International Finance Tech City - Gift
Andhra University380 views
Sustainable storm water management Presentation Slides von Arissa Loh
Sustainable storm water management Presentation SlidesSustainable storm water management Presentation Slides
Sustainable storm water management Presentation Slides
Arissa Loh 6.7K views
Potential of Sewage Treatment Plants in Bangalore_V C Kumar_2013 von India Water Portal
Potential of Sewage Treatment Plants in Bangalore_V C Kumar_2013Potential of Sewage Treatment Plants in Bangalore_V C Kumar_2013
Potential of Sewage Treatment Plants in Bangalore_V C Kumar_2013
India Water Portal8.6K views
Water, source of conflict ? von salmanmaslam
Water, source of conflict ?Water, source of conflict ?
Water, source of conflict ?
salmanmaslam3.2K views
Critical assesment of the Sustainable Urban Drainage component of the Church ... von Achim von Malotki
Critical assesment of the Sustainable Urban Drainage component of the Church ...Critical assesment of the Sustainable Urban Drainage component of the Church ...
Critical assesment of the Sustainable Urban Drainage component of the Church ...
Achim von Malotki1.1K views
Cross Drainage Work von holegajendra
Cross Drainage Work Cross Drainage Work
Cross Drainage Work
holegajendra994 views

Destacado

Kenya Railways SGR presentation von
Kenya Railways SGR presentationKenya Railways SGR presentation
Kenya Railways SGR presentationThe Star Newspaper
8.8K views22 Folien
Brisbane airport link & Canada Line von
Brisbane airport link & Canada LineBrisbane airport link & Canada Line
Brisbane airport link & Canada LineAudrey Mwala
726 views27 Folien
Beijing railway railway atation von
Beijing railway railway atationBeijing railway railway atation
Beijing railway railway atationSneha Lata
4.8K views5 Folien
Railway Station Design 251115 von
Railway Station Design 251115Railway Station Design 251115
Railway Station Design 251115David Jukes-Hughes
7.3K views41 Folien
planning of central railway station von
planning of central railway stationplanning of central railway station
planning of central railway stationUpasana Panchal
10K views19 Folien
Train Station: A Case Study von
Train Station: A Case StudyTrain Station: A Case Study
Train Station: A Case StudyNg Yuin Fung
7.1K views29 Folien

Destacado(8)

Brisbane airport link & Canada Line von Audrey Mwala
Brisbane airport link & Canada LineBrisbane airport link & Canada Line
Brisbane airport link & Canada Line
Audrey Mwala726 views
Beijing railway railway atation von Sneha Lata
Beijing railway railway atationBeijing railway railway atation
Beijing railway railway atation
Sneha Lata4.8K views
planning of central railway station von Upasana Panchal
planning of central railway stationplanning of central railway station
planning of central railway station
Upasana Panchal10K views
Train Station: A Case Study von Ng Yuin Fung
Train Station: A Case StudyTrain Station: A Case Study
Train Station: A Case Study
Ng Yuin Fung7.1K views
Acknowledge, list-of-figures-and-tables-sample-writing-report-and-other-docum... von Shashee Geeganage
Acknowledge, list-of-figures-and-tables-sample-writing-report-and-other-docum...Acknowledge, list-of-figures-and-tables-sample-writing-report-and-other-docum...
Acknowledge, list-of-figures-and-tables-sample-writing-report-and-other-docum...
Shashee Geeganage31.5K views
Tunnel making methods and tunnel boring machine von mohammadsalikali
Tunnel making methods and tunnel boring machine Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine
mohammadsalikali51.1K views

Similar a The Northern Collector Water Tunnel Project Report

Writing Sample - Draft EIR von
Writing Sample - Draft EIRWriting Sample - Draft EIR
Writing Sample - Draft EIRSharanya Ganesh
315 views16 Folien
Melamchi Water Supply Project von
Melamchi Water Supply ProjectMelamchi Water Supply Project
Melamchi Water Supply ProjectChandanGupta201
1.4K views31 Folien
Download-manuals-surface water-software-investigation&selectionofhydrologica... von
 Download-manuals-surface water-software-investigation&selectionofhydrologica... Download-manuals-surface water-software-investigation&selectionofhydrologica...
Download-manuals-surface water-software-investigation&selectionofhydrologica...hydrologyproject0
474 views31 Folien
Water Resources Management in Brantas River Basin von
Water Resources Management in Brantas River BasinWater Resources Management in Brantas River Basin
Water Resources Management in Brantas River BasinPutika Ashfar Khoiri
705 views15 Folien
Vijayakanth CV_ 27 Oct 15 von
Vijayakanth CV_ 27 Oct 15Vijayakanth CV_ 27 Oct 15
Vijayakanth CV_ 27 Oct 15Vijayakanth Muthukrishnan
545 views8 Folien
Seminar aparna von
Seminar aparnaSeminar aparna
Seminar aparnaANANDHU BALAN
78 views33 Folien

Similar a The Northern Collector Water Tunnel Project Report(20)

Download-manuals-surface water-software-investigation&selectionofhydrologica... von hydrologyproject0
 Download-manuals-surface water-software-investigation&selectionofhydrologica... Download-manuals-surface water-software-investigation&selectionofhydrologica...
Download-manuals-surface water-software-investigation&selectionofhydrologica...
hydrologyproject0474 views
Water resources planning & environmental considerations von AMIE(I) Study Circle
Water resources planning & environmental considerationsWater resources planning & environmental considerations
Water resources planning & environmental considerations
water-resources-development-dam-engineering-water-resources-and-dam-engineeri... von LeenaMujahed
water-resources-development-dam-engineering-water-resources-and-dam-engineeri...water-resources-development-dam-engineering-water-resources-and-dam-engineeri...
water-resources-development-dam-engineering-water-resources-and-dam-engineeri...
LeenaMujahed2 views
Rate of sediment yield in the conveyance canals of kano river irrigation proj... von Alexander Decker
Rate of sediment yield in the conveyance canals of kano river irrigation proj...Rate of sediment yield in the conveyance canals of kano river irrigation proj...
Rate of sediment yield in the conveyance canals of kano river irrigation proj...
Alexander Decker181 views
Rate of sediment yield in the conveyance canals of kano river irrigation proj... von Alexander Decker
Rate of sediment yield in the conveyance canals of kano river irrigation proj...Rate of sediment yield in the conveyance canals of kano river irrigation proj...
Rate of sediment yield in the conveyance canals of kano river irrigation proj...
Alexander Decker704 views
Pader SCAP100 Stakeholder Engagement Report von Festo Wasukira
Pader SCAP100 Stakeholder Engagement ReportPader SCAP100 Stakeholder Engagement Report
Pader SCAP100 Stakeholder Engagement Report
Festo Wasukira137 views
NY: A Green Infrastructure Approach - Onondaga Creek Water Quality von Sotirakou964
NY: A Green Infrastructure Approach - Onondaga Creek Water QualityNY: A Green Infrastructure Approach - Onondaga Creek Water Quality
NY: A Green Infrastructure Approach - Onondaga Creek Water Quality
Sotirakou964777 views
Sustainable Water Security at a time of Climate Change: India's 12th Five Yea... von Global Water Partnership
Sustainable Water Security at a time of Climate Change: India's 12th Five Yea...Sustainable Water Security at a time of Climate Change: India's 12th Five Yea...
Sustainable Water Security at a time of Climate Change: India's 12th Five Yea...
Field visit report of Moragahakanda reservoir project von Deshan Arachchige
Field visit report of Moragahakanda reservoir project Field visit report of Moragahakanda reservoir project
Field visit report of Moragahakanda reservoir project
Deshan Arachchige8.5K views
RIVER INTERLINKING (BY CANAL AND TUNNELS) von IRJET Journal
RIVER INTERLINKING (BY CANAL AND TUNNELS)RIVER INTERLINKING (BY CANAL AND TUNNELS)
RIVER INTERLINKING (BY CANAL AND TUNNELS)
IRJET Journal11 views

Más de The Star Newspaper

Kenya Rural Roads Authority von
Kenya Rural Roads AuthorityKenya Rural Roads Authority
Kenya Rural Roads AuthorityThe Star Newspaper
1.2K views1 Folie
CS Rotich speaks on Arror and Kimwarer dams von
CS Rotich speaks on Arror and Kimwarer damsCS Rotich speaks on Arror and Kimwarer dams
CS Rotich speaks on Arror and Kimwarer damsThe Star Newspaper
6.6K views6 Folien
Personal statement on implementation of arror and kimwarer dams in emc von
Personal statement on implementation of arror and kimwarer dams in emcPersonal statement on implementation of arror and kimwarer dams in emc
Personal statement on implementation of arror and kimwarer dams in emcThe Star Newspaper
11.8K views8 Folien
Gazette vol. 17 8 2-19 special (appointments) von
Gazette vol. 17 8 2-19 special (appointments)Gazette vol. 17 8 2-19 special (appointments)
Gazette vol. 17 8 2-19 special (appointments)The Star Newspaper
21.3K views10 Folien
Impending strike by clinical officers von
Impending strike by clinical officersImpending strike by clinical officers
Impending strike by clinical officersThe Star Newspaper
2.9K views3 Folien
Impending strike by clinical officers von
Impending strike by clinical officersImpending strike by clinical officers
Impending strike by clinical officersThe Star Newspaper
252 views3 Folien

Más de The Star Newspaper(20)

CS Rotich speaks on Arror and Kimwarer dams von The Star Newspaper
CS Rotich speaks on Arror and Kimwarer damsCS Rotich speaks on Arror and Kimwarer dams
CS Rotich speaks on Arror and Kimwarer dams
The Star Newspaper6.6K views
Personal statement on implementation of arror and kimwarer dams in emc von The Star Newspaper
Personal statement on implementation of arror and kimwarer dams in emcPersonal statement on implementation of arror and kimwarer dams in emc
Personal statement on implementation of arror and kimwarer dams in emc
The Star Newspaper11.8K views
Gazette vol. 17 8 2-19 special (appointments) von The Star Newspaper
Gazette vol. 17 8 2-19 special (appointments)Gazette vol. 17 8 2-19 special (appointments)
Gazette vol. 17 8 2-19 special (appointments)
The Star Newspaper21.3K views
President Uhuru Kenyatta Speech on fuel tax von The Star Newspaper
President Uhuru Kenyatta Speech on fuel taxPresident Uhuru Kenyatta Speech on fuel tax
President Uhuru Kenyatta Speech on fuel tax
The Star Newspaper1.4K views

Último

Uforest Innovation Challenge - UNIFOREST von
Uforest Innovation Challenge - UNIFORESTUforest Innovation Challenge - UNIFOREST
Uforest Innovation Challenge - UNIFORESTEtifor srl
28 views44 Folien
10th Roundtable on Financing Water–PPT Session 5-Antoine Godin von
10th Roundtable on Financing Water–PPT Session 5-Antoine Godin10th Roundtable on Financing Water–PPT Session 5-Antoine Godin
10th Roundtable on Financing Water–PPT Session 5-Antoine GodinOECD Environment
11 views3 Folien
Climate Change 2022: Mitigation of Climate Change von
Climate Change 2022: Mitigation of Climate ChangeClimate Change 2022: Mitigation of Climate Change
Climate Change 2022: Mitigation of Climate Changeipcc-media
50 views13 Folien
Where is global warming in relation to the long-term temperature goal? von
Where is global warming in relation to the long-term temperature goal?Where is global warming in relation to the long-term temperature goal?
Where is global warming in relation to the long-term temperature goal?ipcc-media
29 views30 Folien
Energy System Transitions in the context of sustainable development: Findings... von
Energy System Transitions in the context of sustainable development: Findings...Energy System Transitions in the context of sustainable development: Findings...
Energy System Transitions in the context of sustainable development: Findings...ipcc-media
59 views9 Folien
Unveiling the Depths: Exploring the Enigmatic World of Deep Sea Ecology von
Unveiling the Depths: Exploring the Enigmatic World of Deep Sea EcologyUnveiling the Depths: Exploring the Enigmatic World of Deep Sea Ecology
Unveiling the Depths: Exploring the Enigmatic World of Deep Sea Ecologyssuserf0a0fe1
22 views25 Folien

Último(20)

Uforest Innovation Challenge - UNIFOREST von Etifor srl
Uforest Innovation Challenge - UNIFORESTUforest Innovation Challenge - UNIFOREST
Uforest Innovation Challenge - UNIFOREST
Etifor srl28 views
10th Roundtable on Financing Water–PPT Session 5-Antoine Godin von OECD Environment
10th Roundtable on Financing Water–PPT Session 5-Antoine Godin10th Roundtable on Financing Water–PPT Session 5-Antoine Godin
10th Roundtable on Financing Water–PPT Session 5-Antoine Godin
OECD Environment11 views
Climate Change 2022: Mitigation of Climate Change von ipcc-media
Climate Change 2022: Mitigation of Climate ChangeClimate Change 2022: Mitigation of Climate Change
Climate Change 2022: Mitigation of Climate Change
ipcc-media50 views
Where is global warming in relation to the long-term temperature goal? von ipcc-media
Where is global warming in relation to the long-term temperature goal?Where is global warming in relation to the long-term temperature goal?
Where is global warming in relation to the long-term temperature goal?
ipcc-media29 views
Energy System Transitions in the context of sustainable development: Findings... von ipcc-media
Energy System Transitions in the context of sustainable development: Findings...Energy System Transitions in the context of sustainable development: Findings...
Energy System Transitions in the context of sustainable development: Findings...
ipcc-media59 views
Unveiling the Depths: Exploring the Enigmatic World of Deep Sea Ecology von ssuserf0a0fe1
Unveiling the Depths: Exploring the Enigmatic World of Deep Sea EcologyUnveiling the Depths: Exploring the Enigmatic World of Deep Sea Ecology
Unveiling the Depths: Exploring the Enigmatic World of Deep Sea Ecology
ssuserf0a0fe122 views
Uforest Innovation Challenge - The Meandering Forest von Etifor srl
Uforest Innovation Challenge - The Meandering ForestUforest Innovation Challenge - The Meandering Forest
Uforest Innovation Challenge - The Meandering Forest
Etifor srl58 views
Carbon Dioxide Removal to reach net-zero and return from overshoot von ipcc-media
Carbon Dioxide Removal to reach net-zero and return from overshootCarbon Dioxide Removal to reach net-zero and return from overshoot
Carbon Dioxide Removal to reach net-zero and return from overshoot
ipcc-media216 views
IPCC TFI work on Methodology Report on Short-lived Climate Forcers (SLCFs) von ipcc-media
IPCC TFI work on  Methodology Report on Short-lived Climate Forcers (SLCFs)IPCC TFI work on  Methodology Report on Short-lived Climate Forcers (SLCFs)
IPCC TFI work on Methodology Report on Short-lived Climate Forcers (SLCFs)
ipcc-media27 views
Climate Change, Biodiversity & Health - IPBES Perspectives von ipcc-media
Climate Change, Biodiversity & Health - IPBES PerspectivesClimate Change, Biodiversity & Health - IPBES Perspectives
Climate Change, Biodiversity & Health - IPBES Perspectives
ipcc-media67 views
Lessons learned and impacts of enhancing participation of young scientists in... von ipcc-media
Lessons learned and impacts of enhancing participation of young scientists in...Lessons learned and impacts of enhancing participation of young scientists in...
Lessons learned and impacts of enhancing participation of young scientists in...
ipcc-media66 views
Opportunities for Early Career Scientists to Contribute to IPCC work & the IP... von ipcc-media
Opportunities for Early Career Scientists to Contribute to IPCC work & the IP...Opportunities for Early Career Scientists to Contribute to IPCC work & the IP...
Opportunities for Early Career Scientists to Contribute to IPCC work & the IP...
ipcc-media69 views
Uforest innovation Challenge - Diversity as an Urban Recipe von Etifor srl
Uforest innovation Challenge - Diversity as an Urban RecipeUforest innovation Challenge - Diversity as an Urban Recipe
Uforest innovation Challenge - Diversity as an Urban Recipe
Etifor srl22 views
IPCC Working Group II von ipcc-media
IPCC Working Group II IPCC Working Group II
IPCC Working Group II
ipcc-media51 views
Panoramica sulle certificazioni di sostenibilità - Mazzaglia, Vireo von Etifor srl
Panoramica sulle certificazioni di sostenibilità - Mazzaglia, VireoPanoramica sulle certificazioni di sostenibilità - Mazzaglia, Vireo
Panoramica sulle certificazioni di sostenibilità - Mazzaglia, Vireo
Etifor srl15 views
Adaptation-Mitigation Synergies and Trade-offs von ipcc-media
Adaptation-Mitigation Synergies and Trade-offsAdaptation-Mitigation Synergies and Trade-offs
Adaptation-Mitigation Synergies and Trade-offs
ipcc-media137 views
Climate Change and Health von ipcc-media
Climate Change and HealthClimate Change and Health
Climate Change and Health
ipcc-media79 views

The Northern Collector Water Tunnel Project Report

  • 1. THE NORTHERN COLLECTOR WATER TUNNEL PHASE 1 PROJECT
  • 2. Nairobi City is the international, regional, administrative and economic hub for Kenya. The city generates approximately 60% GDP. Nairobi, the capital of Republic of Kenya, is facing chronic water shortage including its surrounding area. This is because the proposed additional water source, the Northern Collector Scheme, was not implemented as proposed in 1998. The scheme was initially planned as part of Third Nairobi Water Supply Project. The target year for implementation of the Northern Collector Phase 1 was year 2010. The expected average production capacity of the now proposed Northern Collector tunnel Phase 1 project is 1.6m3/sec (140,000m3/day) with an 84% reliability. The safe yield at Ndakaini dam will however be 1.24m3/ day with a 90% reliability. The present water deficit in Nairobi City is 125,000m3/day. In line with the National Development Plan, Vision 2030, the Government of Kenya has prioritized improvement of water services in Nairobi City and the surrounding areas. To achieve this objectives the Northern Collector Tunnel Phase 1 project is a priority project. A number of studies have been carried out on the Northern Collector System, which have involved detailed data collection and analysis to assess its viability. The initial studies are documented in Feasibility Reports of 1998, carried out by M/S Howard Humphreys and Partners Ltd under the Third Nairobi Water Supply Project. The 1998 report investigated to greater detail the technical and economic viability of the Northern Collector Scheme as a source of water after Ndakaini Dam. The report recommended implementation of the Northern Water Collector Tunnel Phase 1 project by the year 2010. Due to funding challenges the project was not implemented as planned. In the year 2012, Athi Water Services Board through Egis/MIBP JV carried out the Feasibility Study and Master Plan for Developing New Water Sources for Nairobi and Satellite Towns. This study validated the 1998 report and further recommended implementation of the Northern Collector Tunnel project. Additional hydrological reviews for the project were undertaken by M/s GIBB Africa as part of the ESIA Study process further validating the hydrological and ecological viability of the project. BACKGROUND FEASIBILITY AND VALIDATION OF 1998 PROJECT PROPOSAL 2 1
  • 3. The NCT 1 project is located along the eastern fringes of the Aberdare Conservation Area approximately 60 km North of Nairobi City. The works are located in Kangema and Kigumo Sub-Counties of Muranga County. The project involves: • Construction of river intake structures at Maragua, Gikie and Irati rivers • Construction of access adits at Gikigie, Irati and Kaanja; • Construction of 11km long, 3.0 diameter main water tunnel from Maragua intake to Githika outfall. The tunnel will be fully concrete lined. A valuation roll completed in December 2015 indicate that 221 people currently live on top of the tunnel. The other program components involve: • Construction of high level Water Treatment Plant at Kigoro and the water transmission pipelines to Nairobi City of capacity of 140,000m3/day • Construction of Muranga and Kiambu County community water supply projects to ensure water supply to host communities is also improved. • Construction of Nairobi city water distribution network to ensure equitable distribution. • Improvement of water services in Nairobi Satellite towns within Kiambu and Kajiado Counties. PROJECT DEFINITION AND SCOPE 3 View of Project Area Viewofprojectare a
  • 4. The detailed design for the Northern Collector Water Transfer Project phase 1, has considered all findings of the hydrological and ecological studies to ensure that the project shall neither result in low river flows nor divert water during low river flow seasons. The flows used for the design are such that the environmental and ecological requirements as defined by Trout Fish habitat, downstream water rights and compensation flow as a whole are guaranteed. The river flow data for the previous 40 years for each of the rivers was obtained and analysed in the hydrological study. The ecological requirements have been defined following analysis of ecological evidence for all flora and fauna including Trout fish. The reserve flows for the three rivers have therefore not only been defined as per the Water Resource Management Authority (WRMA) guidelines but also the findings of these analytical studies. Cumulatively the reserve flows for the three rivers adopted for design is 141,696.00 m3/day against the WRMA standard definition of 93,744.00 m3/day. The design of the intake structures is such that an unregulated compensation flow channel is provided for at an invert level lower than the tunnel invert level to ensure water only gets into the tunnel after the reserve flows for current/future downstream users and river environmental flows has been released. That means the NCT will not have impact on the frequency of rivers experiencing low flow conditions or drying up, because before these conditions occur, the abstraction will automatically stop because water will only flow through the unregulated compensation flow channel into the river and not into the tunnel which is at a higher level. Certainly as per the design they will be absolutely no abstraction during low river flows. ENVIRONMENTAL AND SOCIAL IMPACT 4 A consultative environmental and social impact assessment for the project was undertaken. The ESIA study report defined the probable project impacts and mitigation measures. A detailed Environmental Management Plan has been developed and a Monitoring plan drawn. Modalities of ensuring compliance with the Environmental Management Plan have been put in place. Notable areas include:- Water Flows in Rivers Maragua, Gikigie and Irati
  • 5. In the calculation of downstream water needs, the abstraction capacities of all existing downstream consumptive demands which include domestic, industrial, irrigation and other miscellaneous abstractors which are distributed along the river profiles were taken as occurring at the proposed NCT1 intakes. Details of the existing and planned water abstraction capacities, including information on current irrigation and hydro-power projects within the river systems, were obtained from WRMA offices and abstraction licences, Water Service Providers in Murang’a County as well as design reports obtained from Tana Water Services Board (TWSB). A minimum factor of safety of 1.2 was then used in carrying out the water balance analysis. Although Section 32 (2) of the Kenyan Water Act, 2002 states that “the use of water for domestic purposes shall take precedence over the use of water for any other purpose…” the potential impact of the project on existing hydro-power generation schemes was also studied. The cumulative impacts of the project on existing hydro power generation was found to be a reduction of 2.32% of the Mean Annual Inflow to Masinga reservoir. Proposed Access Road to Outfall portal site Downstream water rights and Future demand          Kaanja Adit Portal   Irati Intake & Shaft Irati River         Thika River                Thika Dam   Gikigie Intake/Access Adit Gikigie River             Maragua Intake   Maragua River       Figure  2:  Diagram  showing  the  project  schematic                                                    Makomboki Outfall  
  • 6. DRYWEATHERFLOW WETWEATHERFLOW Maraguariverfacingdownstreamfromthebridge Maraguariverview Iratiriverview(pipesubmerged)Iratiriverviewupstreamfrombridge As per the design philosophy of the intake structures explained in (a) above it’s clear that the Northern Collector Tunnel Project will mostly abstract flood waters. This will help in mitigating the negative impacts of flooding downstream and related landslides. To ensure that positive impacts such as irrigation and storage reservoirs downstream and other water uses during heavy rains are not jeopardized, the Northern Collector Tunnel Phase 1 project design has been restricted to cumulatively abstract only 43% of the maximum flood waters leaving 57% available for investments in storage infrastructure. From drainage patterns, the average maximum flood water at the three rivers abstraction points is 1,198,368m3/ day, NCT1 will abstract 513,388 m3/ day. Since existing and known plans for future irrigation schemes were considered in defining the compensation flows, this covers any other future and unknown possible abstraction. Further, the balance of flood passed downstream of the weirs of about 684,980 m3/day is expected to increase downstream due to increase in water shed areas. Abstraction of Flood waters In addition to ensuring sufficient water requirements for the aquatic flora and fauna, the river structures have been designed to ensure free migration of the evidenced trout fish in all the three rivers. Fish ladders and fish passes have been provided for and sized accordingly. Sustainability of Aquatic Life
  • 7. To ensure there are no effects to ground water sources, a fully lined tunnel will be constructed. This will ensure there’s no infiltration of underground water into the tunnel or exfiltration out of the tunnel. During construction contact grouting will be done to the outside rock to ensure structural integrity and to avoid flow of groundwater from an aquifer into and around the outside of the tunnel. Although the tunnel is ultimately not expected to have any impacts on ground and surface water resources, Athi Water Services Board (AWSB) has undertaken a baseline study of the resources on top of the tunnel and surrounding the tunnel corridor. The baseline survey report is available in our website at http:// awsboard.go.ke/2016/01/06/baseline-survey-for-wells-and- boreholes-along-the-nct-1-corridor. AWSB will monitor these water resources during and after construction. Should there be any negative impact on these water resources during construction while the lining and grouting is still ongoing, AWSB will supply all impacted people with water free of charge. Should there be any unexpected negative impact on these water resources after construction, AWSB would implement alternative water supply schemes for all impacted people. The water resource monitoring results will be made available to Muranga County and the public. A valuation roll completed in December 2015 indicate that 221 people currently live on top of the tunnel. Water resource management and environmental conservation are the mandate of the Water Resource Management Authority (WRMA) and Water Resource User Associations (WRUAs). AWSB as a user department, is however very keen on environmental conservation. As such AWSB has been assisting the Chania WRUA in following up on the proposal for Lower Chania Catchment Protection to ensure it’s submitted to World Bank through WRMA for financing under the Water Security and Climate Resilience Project. In consultation with the Water Resources Management Authority, Maragua WRUA and Murang’a County Government AWSB will support Upper Maragua WRUA in the updating of the Maragua Sub-Catchment Management Strategy. AWSB is and will also continue to support and be involved in tree planting together with Water Resource User Associations. It should be noted that no deforestation will carried out in order to pave way for the tunnel construction. In addition, AWSB has committed to undertake an integrated water masterplan for Muranga County. Ground Water aquifers and surface water resources Environmental sustainability and Catchment Protection
  • 8. Social Considerations As part of the Northern Collector Tunnel Phase 1 project, the GOK through Athi Water will undertake the following activities that will improve the living standards and increase water supply to communities along the tunnel and its surrounding: • Purchase an Ambulance for Gikoe dispensary to be used by the project and the surrounding communities along the tunnel • Give priority for employment in the Project to people from Murang’a County. • Construct permanent residency for the supervision team in Kinyona, Gikoe and Mununga which will revert to the Muranga County government • Ensure excavated material that is not utilized by the project will be committed for use by Muranga County government • Ensure roads are maintained during construction • Engage Muranga University in project activities like geotechnical investigation and supervision of specialized works.
  • 9. Host Community Benefit Projects in Muranga County No Project Name Scope and Target Areas Status Status 1. Muranga Bulk Water Supply (undertaken by TWSB) Laid 81Km water pipelines, Constructed 11000m3/day water tworks and 2000m3/day concrete tank, Augmented sewerage system in Muranga town to serve 189,000 persons in Muranga South and Muranga Town. The system is designed/ expected to serve 417,000 persons by 2030. Completed Kshs 1.6 Billion 2. Muranga Community Water Project Construction of two 4000m3/day water treatment units and laying of 147Km water pipe- lines to improve water supply service from 10hrs to 24hrs to 400,000 people by 2030 in Kandara, Kigumo, Kangema, Kiharu, and Maragua constituencies of Muranga County. Works are 85% done. Completion in April 2016 Kshs 749 million 3. Gatanga Community water project Construct intakes along the Kiama and Kimakia rivers, 2 No. 3000 m3/day water treatment plant and lay 35km pipelines boosting water supply from 6hrs to 16hrs to 70,000 people in the lower areas of Kiunyu and Gatunyu areas of Gatanga Constituency. Works at 70% done. Comple- tion in March 2016 Kshs 264 million 4. Gatango water project construction of intake works, 30km water mainlines and 4 no storage tanks to improve water supply to 140,000 people in Gaturi and Kamacharia wards Tender docu- mentation Kshs 170 million 5 Ithanga Water Project Construction of river intake weir on Thika river, 47Km water mains, 6000m3/day water treat- ment plant to improve supply in Ithanga Awaiting sign- ing of FC Kshs 1.4 Billion 6 Gatagwagwa stor- age tank Construction of 225m3 clear water storage tank to complement gatagwagwa community water project Completion in April 2016 Kshs 3.3 Million 7 Gikoe Community Dis- pensary Improvement of Gikoe dispensary and purchase of an ambulance to serve people from Kigumo constituency and surrounding areas. Ongoing. Completion in March 2016 Part of NCT1 works 8 Ichichi, Kiruri and Makomboki Rehabilitation of 3 intake weirs, construction of 225m3 storage tanks, water pipeline exten- sion to serve approximately 50,000 people in Gitwe-Kanderendu in Kugumo upstream of Thika Dam, Makomboki, Ichichi/Githaini, Karurumo and Kiruri communities along the tunnel. Design Stage Kshs 170 Million
  • 10. No Project Name Scope and Target Areas Status Cost 1 Independent Mataara and Komothai Water Production Plants Construction of 32,000m3/day 5No. water treatment plants to benefits 128,000 people in Karimenu, Karure, Ndarugu/Gatundu South Operational Kshs 800 Million 2 Improvement of community water supply schemes Drilling and Equipping of 15 No. boreholes to serve 1000 people in Kiambu, Thika, Limuru and Kikuyu Completion in March 2016 Kshs 200 Million 3 Kiambu Water Supply Works (Wassip AF) Construct intakes along the Kiama and Kima- kia rivers, 2 No. 3000 m3/day water treat- ment plant and lay 35km pipelines boosting water supply from 6hrs to 16hrs to 70,000 people in the lower areas of Kiunyu and Ga- tunyu areas of Gatanga Constituency. Works at 70% done. Comple- tion in March 2016 Kshs 264 million 4 Ruiru Water Supply Project: Works 60% done. Completion in April 2016 Kshs 530Million Kshs 170 million Construct 13,000m3/d WTP, River Intake weir of 4000m3/day, transmission Pipelines and 5,000m3 Tank to benefit 68,000 residents of Ruiru and Juja Towns Main works operational. Tank to be complete in February 2016 Kshs 970Million Kshs 1.4 Billion 5 Tigoni, Githunguri and Komothai Water Sup- ply Schemes Construction of 1000m3/day treatment plant, laying of 145km pipeline to benefit 10,000 people in Tigoni and Githunguri areas Completion in March 2017 Kshs 300 million 6 Jacaranda-Githurai Water Supply Project Construction of 135km water mains to improve water supply to 188,000 people in ruiru, Githurai 45, part of Mwiki and Mwihoko Advance procurement of consultant ongoing Kshs 1.3 Billion Host Community Benefit Projects in Kiambu County
  • 11. Following completion of the detailed designs and obtaining the necessary regulatory approvals, implementation of the Northern Collector Tunnel Phase 1 project commenced on 24th February 2015. To facilitate speedy implementation an implementation framework has been prepared for the project to ensure continued consultations with stakeholders, quality assurance, continuous technical and environmental soundness and that the project does not result in adverse environmental effects. PROJECT IMPLEMENTATION 6 The Ministry of Water and Irrigation is establishing a project steering committee comprising representatives from National and County governments to oversee the implementation of the project. In addition, Athi Water Services Board is currently supporting the recruitment of a high level Independent Panel of experts comprising of tunnel expert, geotechnical expert, hydraulic/hydrology expert, dam expert, community water supplies expert and an environment/ecological expert. Selection of the independent panel of experts will be coordinated by the Kenya Water Services Regulatory Board (WASREB). The selection panel will constitute independent relevant professionals from the Institute of Engineers of Kenya, the Geological Society of Kenya, the Hydrological Society of Kenya and the Environment Institute of Kenya. This panel will play an independent advisory role to the project steering committee on project implementation modalities. The Northern Collector Water Transfer Tunnel Phase 1 is the first inter-basin water transfer project following the enactment of the new constitution and formulation of county governments. It is considered that there’s potential for future additional benefit sharing between the County of origin, Muranga County, and the water receiving county, Nairobi City, once the country has established a legal framework for inter-county water transfers. More information on the 4th Nairobi water supply program and the Northern collector tunnel Phase 1 project can be obtained from our website: www.awsboard.go.ke
  • 12. www.awsboard.go.ke Our Contacts 3rd Floor, Africa Re Centre, Hospital Rd-Upper Hill, P.O. Box 45283-00100, Nairobi, Kenya Tel: +254-20-274292/3, +254-20-2727439-42 GSM: +254-715-688 272 Email: Info@awsboard.go.ke