Case Study (1)
- Sharon
Construction
Corporation
April 16, 2013
Case situation
• Project- 200,000 seat stadium
• Start from Feb. 15, expected finish time: 1 year
• Overhead cost of $500 per week for any delay after 52 weeks
• Penalty of $15,000 per week of delay beyond next Feb. 15
• Uncertainties: Strike and Weather in December (42th weeks).
1.) Possible labor strike in Dec.:
No Strike, P=50%;
Strike:+8 weeks , P=35%; +12 weeks , P=15%
2.) Possible heating need: 33% with extra heating cost $500
per week, 67% with no heating need.
Five proposals
• 1. Expedite the pouring of seat gallery supports with extra cost
$20,000 and cut 6 weeks
• 2. The same as proposal 1, but in addition, expediting filling of
the field with extra cost $10,000 and cut 5 weeks
• 3. Expedite the roofing with extra cost $9,000 and cut 6 weeks
• 4. Do nothing until Dec. 1. If it is cold, delay the pouring or
heating; If a strike occurs, expedite all activities after strike
over with extra cost $3000 per activity per week.
• 5. Do nothing until Dec. 1.
A
clean site
B
Subsurface
drainage
C
Field &
Truck
filling
D
Turf
installation
E
Excavation
F
Pouring
concrete
footing
G
Pouring
seat
gallery
support
H
Pre cast
galleries
I
Pouring
concrete seats
J
Installing
steel
structure
K
Roof
erection
L
Building
dressing
room
M
Seat
painting
FINISH
N
Light
installation
O
Scoreboard &
facilities
Precedence Network
8
80
8
8
8
16
4
12
16
14
30
12
4
16
16
30
12
12
28
16
4
8
20 20 28
28
42
41
13
41 45
4
28
4
32
45 48
3
28
28
5
4
33
48
32
Critical Path: A E F G H I M
A
clean site
B
Subsurface
drainage
C
Field &
Truck
filling
D
Turf
installation
E
Excavation
F
Pouring
concrete
footing
G
Pouring
seat
gallery
support
H
Pre cast
galleries
I
Pouring
concrete seats
J
Installing
steel
structure
K
Roof
erection
L
Building
dressing
room
M
Seat
painting
FINISH
N
Light
installation
O
Scoreboard &
facilities
8
80
8
8
8
16
4
12
16
14
30
12
4
16
16
30
12
6
22
16
4
8
20 20 28
22
42+X
35
13
35 39
4
28
4
32
39 42+X
3
28
28
5
4
33
42+X
32
Proposal 1 Possible strike occurs in 42th week
Possible strike occurs in 42th week
Actual Cost
P(Strike) No heating
(P=67%)
Heating
(P=33%)
No strike, P=50% $20,000 $20,000
Strike +8w, P=35% $20,000 $20,000
Strike +12w, P=15% $51,000 $51,000
$20,000[Expediting cost]+(42+12-52) x
($15,000[Penalty]+$500[Overhead]) =$51,000
A
clean site
B
Subsurface
drainage
C
Field &
Truck
filling
D
Turf
installation
E
Excavation
F
Pouring
concrete
footing
G
Pouring
seat
gallery
support
H
Pre cast
galleries
I
Pouring
concrete seats
J
Installing
steel
structure
K
Roof
erection
L
Building
dressing
room
M
Seat
painting
FINISH
N
Light
installation
O
Scoreboard &
facilities
8
80
8
8
8
16
4
12
16
9
25
12
4
16
16
25
12
6
22
16
4
8
20 20 28
22
37
35
13
35 39
4
28
4
32
39 42+X
3
28
28
5
4
33
42+X
32
Proposal 2
Possible strike occurs in 42th week
Actual Cost
$30,000[Expediting cost] +(42+12-52)x
($15,000[Penalty]+$500[Overhead cost]) = $61,000
P(Strike) No heating
(P=67%)
Heating
(P=33%)
No strike, P=50% $30,000 $30,000
Strike +8w, P=35% $30,000 $30,000
Strike +12w, P=15% $61,000 $61,000
Scenario of Proposal 3
scenario
No Strike
Good weather
no heating
needed, done within 48
weeks
Bad weather, delay 4
weeks, no heating
needed, done within 52
weeks.
Bad weather, heating
needed, done within 48
weeks
Strike
+8 weeks strike, no
heating needed, done
within 56 weeks
+12 weeks strike, no
heating needed, done
within 60 weeks
A
clean site
B
Subsurface
drainage
C
Field &
Truck
filling
D
Turf
installation
E
Excavation
F
Pouring
concrete
footing
G
Pouring
seat
gallery
support
H
Pre cast
galleries
I
Pouring
concrete seats
J
Installing
steel
structure
K
Roof
erection
L
Building
dressing
room
M
Seat
painting
FINISH
N
Light
installation
O
Scoreboard &
facilities
8
80
8
8
8
16
4
12
16
14
30
12
4
16
16
30
12
12
28
16
4
2
20 20 22
28
42+X
41
13
41 45+X
4
22
4
36
45+X 48+X
3
22
22
5
4
27
48+X
26
Proposal 3 Possible strike and cold weather occur in 42th week
Possible strike and cold weather occur in 42th week
Actual Cost
P(Strike) No heating
(P=67%)
Heating
(P=33%)
No strike, P=50% $9,000 $11,000
Strike +8w, P=35% $71,000 $71,000
Strike +12w, P=15% $133,000 $133,000
$9,000[Expediting cost] +(48+12-52) x
($500[Overhead cost] + $15,000[Penalty]) =$133,000
Scenario of Proposal 4
scenario
No Strike
Good weather,
no heating
needed, done within 48
weeks
Bad weather, delay 4
weeks, no heating
needed, done within 52
weeks
Bad weather, heating
needed, done within
48 weeks
Strike
+8 weeks strike, Crash 4
weeks, no heating
needed, done within 52
weeks
+12 weeks strike, Crash
4 weeks , no heating
needed, done within 56
weeks
A
clean site
B
Subsurface
drainage
C
Field &
Truck
filling
D
Turf
installation
E
Excavation
F
Pouring
concrete
footing
G
Pouring
seat
gallery
support
H
Pre cast
galleries
I
Pouring
concrete seats
J
Installing
steel
structure
K
Roof
erection
L
Building
dressing
room
M
Seat
painting
FINISH
N
Light
installation
O
Scoreboard &
facilities
8
80
8
8
8
16
4
12
16
14
30
12
4
16
16
30
12
12
28
16
4
8
20 20 28
28
42+8
41
13
41 49+2
4-2=2
28
4
32
51 51+1
3-2=1
28
28
5
4
33
52
32
Proposal 4 Possible strike and cold weather occur in 42th week
Possible strike and cold weather occur in 42th week
Actual Cost
P(Strike) No heating
(P=67%)
Heating
(P=33%)
No strike, P=50% $0 $2,000
Strike +8w, P=35% $12,000 $12,000
Strike +12w, P=15% $74,000 $74,000
42+12
53+2
55 55+1
56
$3,000[crash cost]x4 +(56-52) x ($500[Overhead
cost] + $15,000[Penalty]) = $74,000
$3,000[ Expediting cost] x 4 weeks= $12,000
Scenario of Proposal 5
scenario
No Strike
Good weather,
no heating
needed, done within 48
weeks
Bad weather, delay 4
weeks, no heating
needed, done within 52
weeks
Bad weather, heating
needed, done within 48
weeks
Strike
+8 weeks strike,
no heating
needed, done within 56
weeks
+12 weeks strike,
no heating
needed, done within 60
weeks
A
clean site
B
Subsurface
drainage
C
Field &
Truck
filling
D
Turf
installation
E
Excavation
F
Pouring
concrete
footing
G
Pouring
seat
gallery
support
H
Pre cast
galleries
I
Pouring
concrete seats
J
Installing
steel
structure
K
Roof
erection
L
Building
dressing
room
M
Seat
painting
FINISH
N
Light
installation
O
Scoreboard &
facilities
8
80
8
8
8
16
4
12
16
14
30
12
4
16
16
30
12
12
28
16
4
8
20 20 28
28
42+X
41
13
41+X 45+X
4
28
4
32
45+X 48+X
3
28
28
5
4
33
48+X
32
Proposal 5 Possible strike and cold weather occur in 42th week
Possible strike and cold weather occur in 42th week
Actual Cost
P(Strike) No heating
(P=67%)
Heating
(P=33%)
No strike, P=50% $0 $2,000
Strike +8w, P=35% $62,000 $62,000
Strike +12w, P=15% $124,000 $124,000
(48+8-52)x ($500[Overhead
cost]+$15,000[Penalty])= $62,000
Cost Analysis
No heating Scenario (67%)
Heating needed Scenario (33%)
Probability Strike Proposal
1
Proposal
2
Proposal
3
Proposal
4
Proposal
5
No Strike- 50% $20,000 $30,000 $9,000 $0 $0
+8 weeks- 35% $20,000 $30,000 $71,000 $12,000 $62,000
+12 weeks- 15% $51,000 $61,000 $133,000 $74,000 $124,000
EMV $24,650 $34,650 $49,300 $15,300 $40,300
Probability Strike Proposal
1
Proposal
2
Proposal
3
Proposal
4
Proposal
5
No Strike- 50% $20,000 $30,000 $11,000 $2000 $2000
+8 weeks- 35% $20,000 $30,000 $71,000 $12,000 $62,000
+12 weeks- 15% $51,000 $61,000 $133,000 $74,000 $124,000
EMV $24,650 $34,650 $49,330 $15, 630 $40, 630
Recommendation
basedonCostAnalysis-EMVmethod
• Choose proposal 4
• Proposal 1 would be the second choice
Reason
• Proposal 4 has the lowest EMV, and it can end up with no
extra cost.
• Proposal 1 would be the second choice because it has
second lowest EMV and is better than 2, 3 and 5 if a
strike happens.
• If the CEO is adverse to risk, then select proposal 1
which has smaller loss range (from $20,000 to $ 51,000)
Time Analysis
Probability Strike Proposal
1
Proposal
2
Proposal
3
Proposal
4
Proposal
5
No Strike- 50% 42 42 48 48 48
+8 weeks- 35% 50 50 56 52 56
+12 weeks- 15% 54 54 60 56 60
Make span 46.6 46.6 52.6 50.6 52.6
Recommendation
basedonTimeAnalysis
• Take proposal 1
• Proposal 4 would be the second choice
Reason
• Proposal 1 & 2 has the shortest average duration, but
proposal 2 costs more.
• Proposal 4 would be the second choice because it has
second shortest average duration and is better than
proposal 1 if the cost-time ratio is considered.
• If the CEO cares time the most, then select proposal 1.
Other factors
• Behavioral – Employee morale and enthusiasm if a strike
occurs. Is this company brand oriented?
• Organizational – Will a strike and falling behind schedule lead
to layoffs or low morale? Does the sub-contractor have the
capacity to work in an expedited scenario?
• Political- Will local or state government become involved in a
labor dispute
• Financial- how urgently does the firm need cash flow? Will
early completion lead to financial benefits?
• Cultural – If labor force is mostly of the same
background, they may be more culturally or less culturally
likely to strike.
Decision making as the
president
• I will choose proposal 4.
• The first reason is obvious that it has the lowest EMV. I am a
risk seeker so I do not think the broader loss rang would be a
big problem.
• Although proposal 4 has longer duration than proposal 1
based on Time Analysis. Besides, there is no extra bonus if we
get it done earlier. For financial reason, I will choose proposal
4 for sure.

More Related Content

What's hot

Sumantra Ghoshal: Bad management theories are destroying good management prac...
Sumantra Ghoshal: Bad management theories are destroying good management prac...Sumantra Ghoshal: Bad management theories are destroying good management prac...
Sumantra Ghoshal: Bad management theories are destroying good management prac...Arlind Rexhepi
 
EY Digital Deal Economy - Nederland
EY Digital Deal Economy - NederlandEY Digital Deal Economy - Nederland
EY Digital Deal Economy - Nederlandreichske
 
Natural Gas Value Chain, Opportunities, and Challenges - Lebanon
Natural Gas Value Chain, Opportunities, and Challenges - LebanonNatural Gas Value Chain, Opportunities, and Challenges - Lebanon
Natural Gas Value Chain, Opportunities, and Challenges - LebanonIhab Ouaida
 
Introduction to Carbon Capture and Storage
Introduction to Carbon Capture and Storage Introduction to Carbon Capture and Storage
Introduction to Carbon Capture and Storage The Climate Institute
 
Complete Business Frameworks Reference Guide
Complete Business Frameworks Reference GuideComplete Business Frameworks Reference Guide
Complete Business Frameworks Reference GuideFlevy.com Best Practices
 
canadian oil and gas industry
canadian oil and gas industrycanadian oil and gas industry
canadian oil and gas industryvishal gupta
 
Basic technology & solutions of LNG
Basic technology & solutions of LNGBasic technology & solutions of LNG
Basic technology & solutions of LNGAbu Bakar Siddiqui
 
Tracxn - Electric Vehicles Startup Landscape
Tracxn - Electric Vehicles Startup LandscapeTracxn - Electric Vehicles Startup Landscape
Tracxn - Electric Vehicles Startup LandscapeTracxn
 
Petroleum industry final
Petroleum industry finalPetroleum industry final
Petroleum industry finalMickey Otterlei
 
Risk Management Toolkit - Framework, Best Practices and Templates
Risk Management Toolkit - Framework, Best Practices and TemplatesRisk Management Toolkit - Framework, Best Practices and Templates
Risk Management Toolkit - Framework, Best Practices and TemplatesAurelien Domont, MBA
 
Project Term Report - Lucky Cement, Strengthen the Dreams
Project Term Report - Lucky Cement, Strengthen the Dreams Project Term Report - Lucky Cement, Strengthen the Dreams
Project Term Report - Lucky Cement, Strengthen the Dreams Sajjad Sayed
 
Scope 3 Emissions
Scope 3 EmissionsScope 3 Emissions
Scope 3 EmissionsKarl Letten
 
My presentation - THE OIL INDUSTRY OF PAKISTAN
My presentation - THE OIL INDUSTRY OF PAKISTANMy presentation - THE OIL INDUSTRY OF PAKISTAN
My presentation - THE OIL INDUSTRY OF PAKISTANMuhammad Ibad Siddiqui
 
Ogdcl strategy planning
Ogdcl strategy planningOgdcl strategy planning
Ogdcl strategy planningAbdulBaseer T
 
Oil refinery processes
Oil refinery processesOil refinery processes
Oil refinery processesJithu John
 
City gas distribution
City gas distributionCity gas distribution
City gas distributionSneha Santra
 
operatingmodelandorganizationdesigntoolkit-overviewandapproach-211220031125.pdf
operatingmodelandorganizationdesigntoolkit-overviewandapproach-211220031125.pdfoperatingmodelandorganizationdesigntoolkit-overviewandapproach-211220031125.pdf
operatingmodelandorganizationdesigntoolkit-overviewandapproach-211220031125.pdfddr95827
 
Carbon Capture and Storage breakfast seminar
Carbon Capture and Storage breakfast seminarCarbon Capture and Storage breakfast seminar
Carbon Capture and Storage breakfast seminarBlake Morgan
 
Petroleum companies of pakistan
Petroleum companies of pakistanPetroleum companies of pakistan
Petroleum companies of pakistanQunber Bilal
 

What's hot (20)

Sumantra Ghoshal: Bad management theories are destroying good management prac...
Sumantra Ghoshal: Bad management theories are destroying good management prac...Sumantra Ghoshal: Bad management theories are destroying good management prac...
Sumantra Ghoshal: Bad management theories are destroying good management prac...
 
EY Digital Deal Economy - Nederland
EY Digital Deal Economy - NederlandEY Digital Deal Economy - Nederland
EY Digital Deal Economy - Nederland
 
Natural Gas Value Chain, Opportunities, and Challenges - Lebanon
Natural Gas Value Chain, Opportunities, and Challenges - LebanonNatural Gas Value Chain, Opportunities, and Challenges - Lebanon
Natural Gas Value Chain, Opportunities, and Challenges - Lebanon
 
Introduction to Carbon Capture and Storage
Introduction to Carbon Capture and Storage Introduction to Carbon Capture and Storage
Introduction to Carbon Capture and Storage
 
Complete Business Frameworks Reference Guide
Complete Business Frameworks Reference GuideComplete Business Frameworks Reference Guide
Complete Business Frameworks Reference Guide
 
canadian oil and gas industry
canadian oil and gas industrycanadian oil and gas industry
canadian oil and gas industry
 
Basic technology & solutions of LNG
Basic technology & solutions of LNGBasic technology & solutions of LNG
Basic technology & solutions of LNG
 
The Peterhead Carbon Capture and Storage Project - plenary presentation given...
The Peterhead Carbon Capture and Storage Project - plenary presentation given...The Peterhead Carbon Capture and Storage Project - plenary presentation given...
The Peterhead Carbon Capture and Storage Project - plenary presentation given...
 
Tracxn - Electric Vehicles Startup Landscape
Tracxn - Electric Vehicles Startup LandscapeTracxn - Electric Vehicles Startup Landscape
Tracxn - Electric Vehicles Startup Landscape
 
Petroleum industry final
Petroleum industry finalPetroleum industry final
Petroleum industry final
 
Risk Management Toolkit - Framework, Best Practices and Templates
Risk Management Toolkit - Framework, Best Practices and TemplatesRisk Management Toolkit - Framework, Best Practices and Templates
Risk Management Toolkit - Framework, Best Practices and Templates
 
Project Term Report - Lucky Cement, Strengthen the Dreams
Project Term Report - Lucky Cement, Strengthen the Dreams Project Term Report - Lucky Cement, Strengthen the Dreams
Project Term Report - Lucky Cement, Strengthen the Dreams
 
Scope 3 Emissions
Scope 3 EmissionsScope 3 Emissions
Scope 3 Emissions
 
My presentation - THE OIL INDUSTRY OF PAKISTAN
My presentation - THE OIL INDUSTRY OF PAKISTANMy presentation - THE OIL INDUSTRY OF PAKISTAN
My presentation - THE OIL INDUSTRY OF PAKISTAN
 
Ogdcl strategy planning
Ogdcl strategy planningOgdcl strategy planning
Ogdcl strategy planning
 
Oil refinery processes
Oil refinery processesOil refinery processes
Oil refinery processes
 
City gas distribution
City gas distributionCity gas distribution
City gas distribution
 
operatingmodelandorganizationdesigntoolkit-overviewandapproach-211220031125.pdf
operatingmodelandorganizationdesigntoolkit-overviewandapproach-211220031125.pdfoperatingmodelandorganizationdesigntoolkit-overviewandapproach-211220031125.pdf
operatingmodelandorganizationdesigntoolkit-overviewandapproach-211220031125.pdf
 
Carbon Capture and Storage breakfast seminar
Carbon Capture and Storage breakfast seminarCarbon Capture and Storage breakfast seminar
Carbon Capture and Storage breakfast seminar
 
Petroleum companies of pakistan
Petroleum companies of pakistanPetroleum companies of pakistan
Petroleum companies of pakistan
 

Similar to Sharon Construction Case Study

Stadium Project
Stadium ProjectStadium Project
Stadium Projectlakvij
 
Deep Retrofit: The Contractor's Perspective
Deep Retrofit: The Contractor's PerspectiveDeep Retrofit: The Contractor's Perspective
Deep Retrofit: The Contractor's PerspectiveSustainableEnergyAut
 
Real Estate Construction Proposal PowerPoint Presentation Slides
Real Estate Construction Proposal PowerPoint Presentation SlidesReal Estate Construction Proposal PowerPoint Presentation Slides
Real Estate Construction Proposal PowerPoint Presentation SlidesSlideTeam
 
Building and Grounds Presentation to BOF
Building and Grounds Presentation to BOFBuilding and Grounds Presentation to BOF
Building and Grounds Presentation to BOFLynn McMullin
 

Similar to Sharon Construction Case Study (7)

Shaft Construction
Shaft ConstructionShaft Construction
Shaft Construction
 
P25
P25P25
P25
 
Shaft Construction
Shaft ConstructionShaft Construction
Shaft Construction
 
Stadium Project
Stadium ProjectStadium Project
Stadium Project
 
Deep Retrofit: The Contractor's Perspective
Deep Retrofit: The Contractor's PerspectiveDeep Retrofit: The Contractor's Perspective
Deep Retrofit: The Contractor's Perspective
 
Real Estate Construction Proposal PowerPoint Presentation Slides
Real Estate Construction Proposal PowerPoint Presentation SlidesReal Estate Construction Proposal PowerPoint Presentation Slides
Real Estate Construction Proposal PowerPoint Presentation Slides
 
Building and Grounds Presentation to BOF
Building and Grounds Presentation to BOFBuilding and Grounds Presentation to BOF
Building and Grounds Presentation to BOF
 

Recently uploaded

Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfchloefrazer622
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfAyushMahapatra5
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactPECB
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfagholdier
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
General AI for Medical Educators April 2024
General AI for Medical Educators April 2024General AI for Medical Educators April 2024
General AI for Medical Educators April 2024Janet Corral
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhikauryashika82
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...fonyou31
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDThiyagu K
 

Recently uploaded (20)

Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdf
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
General AI for Medical Educators April 2024
General AI for Medical Educators April 2024General AI for Medical Educators April 2024
General AI for Medical Educators April 2024
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 

Sharon Construction Case Study

  • 1. Case Study (1) - Sharon Construction Corporation April 16, 2013
  • 2. Case situation • Project- 200,000 seat stadium • Start from Feb. 15, expected finish time: 1 year • Overhead cost of $500 per week for any delay after 52 weeks • Penalty of $15,000 per week of delay beyond next Feb. 15 • Uncertainties: Strike and Weather in December (42th weeks). 1.) Possible labor strike in Dec.: No Strike, P=50%; Strike:+8 weeks , P=35%; +12 weeks , P=15% 2.) Possible heating need: 33% with extra heating cost $500 per week, 67% with no heating need.
  • 3. Five proposals • 1. Expedite the pouring of seat gallery supports with extra cost $20,000 and cut 6 weeks • 2. The same as proposal 1, but in addition, expediting filling of the field with extra cost $10,000 and cut 5 weeks • 3. Expedite the roofing with extra cost $9,000 and cut 6 weeks • 4. Do nothing until Dec. 1. If it is cold, delay the pouring or heating; If a strike occurs, expedite all activities after strike over with extra cost $3000 per activity per week. • 5. Do nothing until Dec. 1.
  • 4. A clean site B Subsurface drainage C Field & Truck filling D Turf installation E Excavation F Pouring concrete footing G Pouring seat gallery support H Pre cast galleries I Pouring concrete seats J Installing steel structure K Roof erection L Building dressing room M Seat painting FINISH N Light installation O Scoreboard & facilities Precedence Network 8 80 8 8 8 16 4 12 16 14 30 12 4 16 16 30 12 12 28 16 4 8 20 20 28 28 42 41 13 41 45 4 28 4 32 45 48 3 28 28 5 4 33 48 32 Critical Path: A E F G H I M
  • 5. A clean site B Subsurface drainage C Field & Truck filling D Turf installation E Excavation F Pouring concrete footing G Pouring seat gallery support H Pre cast galleries I Pouring concrete seats J Installing steel structure K Roof erection L Building dressing room M Seat painting FINISH N Light installation O Scoreboard & facilities 8 80 8 8 8 16 4 12 16 14 30 12 4 16 16 30 12 6 22 16 4 8 20 20 28 22 42+X 35 13 35 39 4 28 4 32 39 42+X 3 28 28 5 4 33 42+X 32 Proposal 1 Possible strike occurs in 42th week Possible strike occurs in 42th week Actual Cost P(Strike) No heating (P=67%) Heating (P=33%) No strike, P=50% $20,000 $20,000 Strike +8w, P=35% $20,000 $20,000 Strike +12w, P=15% $51,000 $51,000 $20,000[Expediting cost]+(42+12-52) x ($15,000[Penalty]+$500[Overhead]) =$51,000
  • 6. A clean site B Subsurface drainage C Field & Truck filling D Turf installation E Excavation F Pouring concrete footing G Pouring seat gallery support H Pre cast galleries I Pouring concrete seats J Installing steel structure K Roof erection L Building dressing room M Seat painting FINISH N Light installation O Scoreboard & facilities 8 80 8 8 8 16 4 12 16 9 25 12 4 16 16 25 12 6 22 16 4 8 20 20 28 22 37 35 13 35 39 4 28 4 32 39 42+X 3 28 28 5 4 33 42+X 32 Proposal 2 Possible strike occurs in 42th week Actual Cost $30,000[Expediting cost] +(42+12-52)x ($15,000[Penalty]+$500[Overhead cost]) = $61,000 P(Strike) No heating (P=67%) Heating (P=33%) No strike, P=50% $30,000 $30,000 Strike +8w, P=35% $30,000 $30,000 Strike +12w, P=15% $61,000 $61,000
  • 7. Scenario of Proposal 3 scenario No Strike Good weather no heating needed, done within 48 weeks Bad weather, delay 4 weeks, no heating needed, done within 52 weeks. Bad weather, heating needed, done within 48 weeks Strike +8 weeks strike, no heating needed, done within 56 weeks +12 weeks strike, no heating needed, done within 60 weeks
  • 8. A clean site B Subsurface drainage C Field & Truck filling D Turf installation E Excavation F Pouring concrete footing G Pouring seat gallery support H Pre cast galleries I Pouring concrete seats J Installing steel structure K Roof erection L Building dressing room M Seat painting FINISH N Light installation O Scoreboard & facilities 8 80 8 8 8 16 4 12 16 14 30 12 4 16 16 30 12 12 28 16 4 2 20 20 22 28 42+X 41 13 41 45+X 4 22 4 36 45+X 48+X 3 22 22 5 4 27 48+X 26 Proposal 3 Possible strike and cold weather occur in 42th week Possible strike and cold weather occur in 42th week Actual Cost P(Strike) No heating (P=67%) Heating (P=33%) No strike, P=50% $9,000 $11,000 Strike +8w, P=35% $71,000 $71,000 Strike +12w, P=15% $133,000 $133,000 $9,000[Expediting cost] +(48+12-52) x ($500[Overhead cost] + $15,000[Penalty]) =$133,000
  • 9. Scenario of Proposal 4 scenario No Strike Good weather, no heating needed, done within 48 weeks Bad weather, delay 4 weeks, no heating needed, done within 52 weeks Bad weather, heating needed, done within 48 weeks Strike +8 weeks strike, Crash 4 weeks, no heating needed, done within 52 weeks +12 weeks strike, Crash 4 weeks , no heating needed, done within 56 weeks
  • 10. A clean site B Subsurface drainage C Field & Truck filling D Turf installation E Excavation F Pouring concrete footing G Pouring seat gallery support H Pre cast galleries I Pouring concrete seats J Installing steel structure K Roof erection L Building dressing room M Seat painting FINISH N Light installation O Scoreboard & facilities 8 80 8 8 8 16 4 12 16 14 30 12 4 16 16 30 12 12 28 16 4 8 20 20 28 28 42+8 41 13 41 49+2 4-2=2 28 4 32 51 51+1 3-2=1 28 28 5 4 33 52 32 Proposal 4 Possible strike and cold weather occur in 42th week Possible strike and cold weather occur in 42th week Actual Cost P(Strike) No heating (P=67%) Heating (P=33%) No strike, P=50% $0 $2,000 Strike +8w, P=35% $12,000 $12,000 Strike +12w, P=15% $74,000 $74,000 42+12 53+2 55 55+1 56 $3,000[crash cost]x4 +(56-52) x ($500[Overhead cost] + $15,000[Penalty]) = $74,000 $3,000[ Expediting cost] x 4 weeks= $12,000
  • 11. Scenario of Proposal 5 scenario No Strike Good weather, no heating needed, done within 48 weeks Bad weather, delay 4 weeks, no heating needed, done within 52 weeks Bad weather, heating needed, done within 48 weeks Strike +8 weeks strike, no heating needed, done within 56 weeks +12 weeks strike, no heating needed, done within 60 weeks
  • 12. A clean site B Subsurface drainage C Field & Truck filling D Turf installation E Excavation F Pouring concrete footing G Pouring seat gallery support H Pre cast galleries I Pouring concrete seats J Installing steel structure K Roof erection L Building dressing room M Seat painting FINISH N Light installation O Scoreboard & facilities 8 80 8 8 8 16 4 12 16 14 30 12 4 16 16 30 12 12 28 16 4 8 20 20 28 28 42+X 41 13 41+X 45+X 4 28 4 32 45+X 48+X 3 28 28 5 4 33 48+X 32 Proposal 5 Possible strike and cold weather occur in 42th week Possible strike and cold weather occur in 42th week Actual Cost P(Strike) No heating (P=67%) Heating (P=33%) No strike, P=50% $0 $2,000 Strike +8w, P=35% $62,000 $62,000 Strike +12w, P=15% $124,000 $124,000 (48+8-52)x ($500[Overhead cost]+$15,000[Penalty])= $62,000
  • 13. Cost Analysis No heating Scenario (67%) Heating needed Scenario (33%) Probability Strike Proposal 1 Proposal 2 Proposal 3 Proposal 4 Proposal 5 No Strike- 50% $20,000 $30,000 $9,000 $0 $0 +8 weeks- 35% $20,000 $30,000 $71,000 $12,000 $62,000 +12 weeks- 15% $51,000 $61,000 $133,000 $74,000 $124,000 EMV $24,650 $34,650 $49,300 $15,300 $40,300 Probability Strike Proposal 1 Proposal 2 Proposal 3 Proposal 4 Proposal 5 No Strike- 50% $20,000 $30,000 $11,000 $2000 $2000 +8 weeks- 35% $20,000 $30,000 $71,000 $12,000 $62,000 +12 weeks- 15% $51,000 $61,000 $133,000 $74,000 $124,000 EMV $24,650 $34,650 $49,330 $15, 630 $40, 630
  • 14. Recommendation basedonCostAnalysis-EMVmethod • Choose proposal 4 • Proposal 1 would be the second choice Reason • Proposal 4 has the lowest EMV, and it can end up with no extra cost. • Proposal 1 would be the second choice because it has second lowest EMV and is better than 2, 3 and 5 if a strike happens. • If the CEO is adverse to risk, then select proposal 1 which has smaller loss range (from $20,000 to $ 51,000)
  • 15. Time Analysis Probability Strike Proposal 1 Proposal 2 Proposal 3 Proposal 4 Proposal 5 No Strike- 50% 42 42 48 48 48 +8 weeks- 35% 50 50 56 52 56 +12 weeks- 15% 54 54 60 56 60 Make span 46.6 46.6 52.6 50.6 52.6
  • 16. Recommendation basedonTimeAnalysis • Take proposal 1 • Proposal 4 would be the second choice Reason • Proposal 1 & 2 has the shortest average duration, but proposal 2 costs more. • Proposal 4 would be the second choice because it has second shortest average duration and is better than proposal 1 if the cost-time ratio is considered. • If the CEO cares time the most, then select proposal 1.
  • 17. Other factors • Behavioral – Employee morale and enthusiasm if a strike occurs. Is this company brand oriented? • Organizational – Will a strike and falling behind schedule lead to layoffs or low morale? Does the sub-contractor have the capacity to work in an expedited scenario? • Political- Will local or state government become involved in a labor dispute • Financial- how urgently does the firm need cash flow? Will early completion lead to financial benefits? • Cultural – If labor force is mostly of the same background, they may be more culturally or less culturally likely to strike.
  • 18. Decision making as the president • I will choose proposal 4. • The first reason is obvious that it has the lowest EMV. I am a risk seeker so I do not think the broader loss rang would be a big problem. • Although proposal 4 has longer duration than proposal 1 based on Time Analysis. Besides, there is no extra bonus if we get it done earlier. For financial reason, I will choose proposal 4 for sure.

Editor's Notes

  1. Expedite the pouring by paying extra $20,000 with 6 weeks deduction. Weather will not affect the activity I (pouring concrete)
  2. It is pretty much the same as the proposal 1 except adding the “field & truck filling cost” with extra $10,000.
  3. If there is no strike, let the cold weather happed without heating and delay 4 weeks, because there is no incentive to get it done earlier. It causes 4 weeks delay, so totally duration of the project is 52 which is still within 1 year.
  4. Cut six weeks of the roof erection with additional cost of $9,000. Pouring concrete would be affect by bad weather, so the extra heating cast $500/ week MIGHT happen.Lets take proposal 3 for example. If there is no strike, just delay 4 weeks and wait for the bad weather over. The total duration is still beyond 52 weeks. If there is a strike, no matter 8 weeks or 12 weeks, this strike period overlap with the bad weather forecast. Therefore, there is no need to use heating when pouring concrete.
  5. If there is no strike, let the cold weather happed without heating. It causes 4 weeks delay, so totally duration of the project is 52 which is still within 1 year.
  6. Wait for the strike over and then expedite the remaining works by cutting no less than 1/3 of its duration with extra cost $3,000/week. Cold weather and strike occur at the same timeIf there is a strike, then heating is no longer needed at all.
  7. Wait for the strike over and then expedite the remaining works by cutting no less than 1/3 of its duration with extra cost $3,000/week. Cold weather and strike occur at the same timeIf there is a strike, then heating is no longer needed at all.
  8. Based on each scenario, we generate EMV (expected money value) for each case. For proposal 1, we got EMV=$24,650 by add up fixed cost and possible extra cost. $20,000 which is the fixed cost of expediting the pouring process and ($51,000-20,000)*0.15.
  9. So based on the cost analysis EMV method, we recommend to choose Proposal 4 because it has the lowest EMV in both no heating and heating needed scenario. On the other hand, Proposal 1 would be The second choice. Not only because it has the second lowest EMV, but also smaller loss range compared to Proposal 4.
  10. And we do the Time Analysis to satisfy the question 2 ” what other basis might be used to make a decision besides expected costs?” So we do the calculation of each possible duration.As I said before, for proposal 3,4 5, there is no incentive to get the project done earlier than 52 weeks, so there are two option open (either do heating or not ) when no strike scenario.
  11. Based on the Time analysis, we recommend to choose proposal 1, for the shortest expected duration. Although Proposal 1& 2 have the same duration, proposal 1 is cheaper. On the other hand, proposal 4 would be the second choice if the cost-time ratio is considered.
  12. What other factors might enter into the decision such as behavioral, organizational, and political? Behavioral-Is my company brand oriented? For example, we have a good reputation of always being on time, we want to keep this reputation. So we might under more time pressure and then pick up the shortest duration even it costs more. Sometimes, there are many like 3~5 project doing simotaneously. They might financially sacrifice this time pressure project to finished it earlier as possible and bring more capacity to do other project and earn more money to make it up. Also for the CEO attitude like he is a risk seeker or adverse? Organizational-Do the subcontractors, or material, machine suppliers have to capacity to work in an expedited scenario? Political- will governer get involved to labor dispute? Or maybe the government want to lower down the unemplyee rate, so they change policy, like we can hire non un worker.Financial- there is no information about the financial structure in this case study, such as how does the owner pay us, monthly or at the end of the project, how would our cash flow be?. Do we have enough liquidity to expedite the project? Do we have bonus if the project is done earlier?