Project Charter

                                                                                       for

     Electronic Health Record
System for University Student
                 Health Care

                                                                 Version 1.2 approved




                                                                              Prepared by

                                                          Sunil Kumar Gunasekaran


Copyright © 2007 by Karl E. Wiegers. Permission is granted to use and modify this template.
04 December 2012
Project Charter for <Project>                                                                                               Page iii




       Revision History

Name               Date                  Changes                        Reason For Changes                                    Version


Sunil Kumar        12/05/2012            Out of scope and New phase was introduced 1.2
                                         Milestones       requiring extension   of
                                                          milestone




       Table of Contents
        Revision History................................................................................................................iii
       1. Project Description..........................................................................................................1
       2. Business Objectives and Success Criteria.......................................................................1
       3. Stakeholders.....................................................................................................................1
       4. Project Scope...................................................................................................................1
       5. Out of Scope....................................................................................................................2
       6. Assumptions and Dependencies......................................................................................2
       7. Constraints.......................................................................................................................2
       8. Milestones........................................................................................................................3
       9. Resources.........................................................................................................................4
       10. Costs .............................................................................................................................5
       11. Risks .............................................................................................................................5
       12. Benefits .........................................................................................................................5
        Approvals............................................................................................................................6
           7
Project Charter for <Project>                                                             Page 1



1. Project Description
    The University Student Health Care (hereafter USHC) is implementing Electronic Health
    Record System using Server obtained from PyraMED Vendor. This enhances the data
    transfer and universal and quick access of data and significantly reduces the operating costs
    and maintenance costs.

2. Business Objectives and Success Criteria
   1) Have installed a working version of the EHR (hereafter Electronic Health Record) in both
       the PyraMed Production and Test environments.
   2) Complete each phase of the project outlined in attachment.
   3) Interface with existing LIS.
   4) Install and interface with a CR/PACS.
   5) Create a sub-department of the Medical Records department that coordinates the
       scanning and indexing of paper documents into electronic health records stored in
       PyraMED.
   6) Interface with University’s Pharmacy system.
   7) The building and implementation of Forms in the PyraMED EHR for use by the
       Providers.
   8) Training of Pilot Group and “Go Live” of Pilot Group for each phase.
   9) Feedback sessions with Pilot Group of each phase.
   10) Training of Clinic and “Go Live” of Clinic for each phase.

3. Stakeholders
   1)   Students who are enrolled in the university.
   2)   University Executive Steering Committee.
   3)   Steering Committee elected by the student body.
   4)   Project Development and Quality Assurance Team.
   5)   Pilot Group created for each phase
   6)   Maintenance and employees of Student Health Center and Pharmacy.
   7)   The Director and financial team of university.

4. Project Scope
   1) The Student Health Center will be responsible to manage the information between
      Campus departments that are needed to accomplish this project. The University Student
      Health Center (USHC) will supply the other campus department a schedule and timeline.
   2) Student Services Workstation and Technology will provide resources and manpower to
      implement workstation–side software and hardware components that are required by
      EHR module to function properly.
   3) SSWT and USHC will work together to test and verify software and hardware builds and
      installs.
Project Charter for <Project>                                                             Page 2


   4) The Infrastructure of Information Technology (IIT) will consult with USHC on a minimal
      number of phases during the project. IIT will work with USHC to help determine the
      storage growth of the EHR database and Document imaging. IIT will also be asked to
      house the Picture Archive Communication System (PACS) for power backup options and
      possibly data backup solutions.
   5) Information Technology Security and Privacy and Internal Audit will verify the security
      and privacy of the HER module and other sub-systems included in the project.
   6) Media Highway, vendor and supplier of the HER module, will fill the roles as provider of
      software and documentation, support center, installer and trainer.
   7) Radiation Services of Indiana, vendor and supplier of the CR/PACS component of the
      system, will fill the roles as provider of software and documentation, support center,
      installer (server-side) and trainer.


5. Out of Scope
   1) The co-ordination of the respective deliverables of the respective department is done by
      the department themselves and USHC will not be responsible for micro managing the
      inner workings of the department for the respective deliverable.
   2) The update of the EHR to the latest version will not be done in this project.
   3) Enhanced Data backup services using PACS - II is being considered to increase the safety
      of EHR documents but is not part of the current process.


6. Assumptions and Dependencies
   1) Institute of Information Technology will continue to support the PyraMED databse on the
      Oracle servers, A ne wSLA to be drawn up for phase 3, Computerized Radiology and the
      Picture Archiving Communications System.
   2) Media Highway, the vendor, will continue to support and help maintain PyraMED, along
      with the new EHR, within their abilities to access the system. Their level of focus will
      remain constant.
   3) Student Services Workstation Technology will ontinue to provide workstation support to
      the point that the PyraMED client installed on Student Health Center workstations will
      run without issue that result in negligible loss of system effectiveness and functionality.
   4) The Computer Services department of the Student Health Center will continue to support
      the PyraMED Health Information System as system administrators and work as liasons
      between the aforementioned departments to help during software upgrades, running
      maintenance, determining resolutions to issues, and other activities that ensure the
      continued availability of the system.

7. Constraints
Project Charter for <Project>                                                             Page 3



Dimension      Constraint                   Driver                      Degree     of   Freedom

Features       Database backup;     EHR,                     70-80% of high priority
               Electronic Forms,    Interface for electronic features must be included
                                    signs,
               Computerized Radiology                        in release 1.2
                                    Document Indexing
Quality                                                      90-95% of user acceptance
               Amount of data to be Number of staff and tests must pass for release
               converted into EHR   robustness of software 1.0, 95-98% for release
                                    used                     1.1

Cost           Recurring     cost     for 3 times return in span of 5   budget overrun up to 15%
               electronic form and lack years and significant           acceptable        without
               of support from vendor     reduction of operating        executive review
                                          cost
Schedule                                  release 1.2 to be available
                                          by 10/1, release 1.1 by
                                          12/1
Staff          maximum team size is 6 30 Medical staff for EHR          On request the medical
               developers + 4 testers for document loading.             staff, radiology staff and
               EHR installation and Continued support from              department staff numbers
               interface creation and Computer                Science   increased by 10 percent.
               background support and department staff – 10
               maintenance

8. Milestones
The project milestones are divided into eight phases each phase requiring its own department,
resources and deliverables.

Phase 1 – Planning
Deliverables – Timeline, installation of EHR

Phase 2 - EHR – Move to EHR Coding
Deliverables – Old version converted into new version.

Phase 3 – Computerized Radiology
Deliverables – Installation and configuration of PACS and CR Systems.

Phase 4 – Notifications
Deliverables – Creation of intra – system messaging modules

Phase 5 – Document Indexing
Deliverables – Complete Scan of all patient paper records along with x-ray and other multimedia
documents.

Phase 6 – Transcription
Deliverables – Installation of Dragon Speak software and complete recording and transcription
of the records.
Project Charter for <Project>                                                                Page 4



Phase 7 – EHR forms and electronic SOAP Notes
Deliverables –Standardized documentation of EHR using the electronic forms

Phase 8 – Electronic Signature
Deliverables – Creation of Interface to obtain electronic signature of patients to be loaded into
EHR.


9. Resources

The respective resources committed by the USHC for various phases are given below.
Phase 1 – Planning
Description: The creation of the timeline, engagement of key players and installation of the
HER Module.
Resources: Medical Staff, Media Highway Training, Application of the EHR module to the
PyraMED Core System, USHC Computer Services.

Phase 2 – EHR – Move to EHR Coding
Description: The old coding screen is moved to the new EHR Coding screen. The process is the
same except the change in environment.
Resources: Medical Staff, USHC Computer Services.

Phase 3 – Computerized Radiology
Description: Installation and configuration of the PACS and CR systems as well as the interface
with the existing PyraMED Core systems.
Resources: Radiation Services, IIT Server and support group, Radiology Staff, USHC Computer
Services, Media Highway Interfacing.

Phase 4 – Notifications
Description: This is an intra-system messaging module at patient level that allows sign off and
other communications between staff.
Resources: Medical Staff, Nursing, Lab and Radiology, USHC Computer Services.

Phase 5 – Document Indexing
Description: This module allows multimedia images to be associated with patient records. This
includes the scanning of external documents and historical paper records as well as the
importation of anatomical graphics and digital photos.
Resources: Medical Staff, USHC Computer Services.

Phase 6 – Transcription
Description: Direct recording into the chart and transcription of this recording by means of
software such as Dragon Speak.
Resources: Medical Records Group, USHC Computer Services, Medical Staff, Nursing, Media
Highway.

Phase 7 – EHR Forms and Electronic SOAP Notes
Project Charter for <Project>                                                              Page 5


Description: This phase truly moves USHC into the electronic health record era. Having
completed the previous phases, we will be in a position to use the EHR module to the fullest
capacity. The electronic forms allow standardization of documentation on encounters.
Resources: Medical Records Group, USHC Computer Services, Medical Staff, Nursing.

Phase 8 – Electronic Signature
Description: Media Highway is developing an interface so that electronic signature pads can be
connected to the PyraMED system. This will allow patients and staff to electronically attach their
signature to encounters.
Resources: Medical Records Group, USHC Computer Services, Medical Staff, Nursing. SSWT
and Media Highway


10. Costs
   1) EHR coding – EHR Module provided free of cost; Training of staff: $7000
   2) Purchase price of PACs Equipment -$170000. Secured a contract with the vendor for the
      annual license fee including support.
   3) Costs from IIT to house the server – Unknown. IIT to define this by end of year.
   4) Media Highway costs to setup interface -$5000. $1000 added to annual licensure fee.
   5) IIT backup cost – approximately $3/GB of backed up data.
   6) Document Indexing – non recurring - $7940


11. Risks
   1) Currently, the Student Health Center uses a pneumatic tube system to convey paper
      medial charts throughout the building. This 40 year old system is in constant repair and
      All those are repairs done in-house as there is no longer any support from the original
      vendor.
   2) The backup for the database is not that efficient and better upgrade system currently not
      chosen in this setup. Hence the probability of losing data is little high.


12. Benefits
   1) Immediate and universal access to the patient record through predetermined levels of
      security, thus ensuring HIPAA compliance.
   2) Easier and quicker navigation through the patient record.
   3) The elimination of misdirected physical paper charts.
   4) The standardization of visit documentation among providers within the organization.
   5) Clinical data formatted so to easily read and analyze.
   6) The reduction of paperwork, documentation errors, and filing activities and the associated
      costs.
   7) Greater efficiency in completed visit documentation.
   8) The possibility to electronically transmit to other providers on request.
Project Charter for <Project>                                                                  Page 6


    9) The availability of clinical data for use in quality, risk, utilization, auditing and return on
       investment analyses.



    Approvals
Approval Decision:

   Approved, development of detailed project plan is authorized
   Approved, project execution is authorized
   Approved, but project is on hold until future notice
   Revise charter and resubmit for approval
   Charter and project proposal are rejected

Role or Title                        Name and Signature                             Date

Excecutive Sponsor                   Lee Gordon



Project Manager                      Steve Baker



Business Analyst                     James Westman
Project Charter for <Project>   Page 7

Weitere ähnliche Inhalte

Was ist angesagt?

Estimating with story points
Estimating with story pointsEstimating with story points
Estimating with story pointsWalid Farag
 
Helpdesk and ticketing
Helpdesk and ticketingHelpdesk and ticketing
Helpdesk and ticketingSyAM Software
 
ERP/SAP Project Charter
ERP/SAP Project CharterERP/SAP Project Charter
ERP/SAP Project CharterBogdan Gorka
 
Agile practices using jira atlassian
Agile practices using jira atlassianAgile practices using jira atlassian
Agile practices using jira atlassianMichal Epstein
 
Jira as a Project Management Tool
Jira as a Project Management ToolJira as a Project Management Tool
Jira as a Project Management ToolPaolo Mottadelli
 
Agile IT Service Management
Agile IT Service ManagementAgile IT Service Management
Agile IT Service ManagementIan Jones
 
Project status reporting with Confluence
Project status reporting with ConfluenceProject status reporting with Confluence
Project status reporting with ConfluenceAndrew Makar
 
Project Management Kickoff Meeting Template Powerpoint Presentation Slides
Project Management Kickoff Meeting Template Powerpoint Presentation SlidesProject Management Kickoff Meeting Template Powerpoint Presentation Slides
Project Management Kickoff Meeting Template Powerpoint Presentation SlidesSlideTeam
 
Software Project Proposal- Result Analysis Tool
Software Project Proposal- Result Analysis ToolSoftware Project Proposal- Result Analysis Tool
Software Project Proposal- Result Analysis ToolMinhas Kamal
 
Michael Bolton - Heuristics: Solving Problems Rapidly
Michael Bolton - Heuristics: Solving Problems RapidlyMichael Bolton - Heuristics: Solving Problems Rapidly
Michael Bolton - Heuristics: Solving Problems RapidlyTEST Huddle
 
Project Planning with Jira
Project Planning with JiraProject Planning with Jira
Project Planning with JiraParvez Misarwala
 
Mobile App Development Proposal PowerPoint Presentation Slides
Mobile App Development Proposal PowerPoint Presentation SlidesMobile App Development Proposal PowerPoint Presentation Slides
Mobile App Development Proposal PowerPoint Presentation SlidesSlideTeam
 
Adopting SAFe with JIRA
Adopting SAFe with JIRAAdopting SAFe with JIRA
Adopting SAFe with JIRACprime
 
Agile and waterfall
Agile and waterfallAgile and waterfall
Agile and waterfallJohn Morse
 
Introduction to scaled agile framework
Introduction to scaled agile frameworkIntroduction to scaled agile framework
Introduction to scaled agile frameworkITEM
 

Was ist angesagt? (20)

Jira Dashboards
Jira DashboardsJira Dashboards
Jira Dashboards
 
Confluence
ConfluenceConfluence
Confluence
 
Estimating with story points
Estimating with story pointsEstimating with story points
Estimating with story points
 
Helpdesk and ticketing
Helpdesk and ticketingHelpdesk and ticketing
Helpdesk and ticketing
 
ERP/SAP Project Charter
ERP/SAP Project CharterERP/SAP Project Charter
ERP/SAP Project Charter
 
Agile practices using jira atlassian
Agile practices using jira atlassianAgile practices using jira atlassian
Agile practices using jira atlassian
 
Jira as a Project Management Tool
Jira as a Project Management ToolJira as a Project Management Tool
Jira as a Project Management Tool
 
Project charter-template
Project charter-templateProject charter-template
Project charter-template
 
Agile IT Service Management
Agile IT Service ManagementAgile IT Service Management
Agile IT Service Management
 
Jira fundamentals
Jira fundamentalsJira fundamentals
Jira fundamentals
 
Go Jira
Go JiraGo Jira
Go Jira
 
Project status reporting with Confluence
Project status reporting with ConfluenceProject status reporting with Confluence
Project status reporting with Confluence
 
Project Management Kickoff Meeting Template Powerpoint Presentation Slides
Project Management Kickoff Meeting Template Powerpoint Presentation SlidesProject Management Kickoff Meeting Template Powerpoint Presentation Slides
Project Management Kickoff Meeting Template Powerpoint Presentation Slides
 
Software Project Proposal- Result Analysis Tool
Software Project Proposal- Result Analysis ToolSoftware Project Proposal- Result Analysis Tool
Software Project Proposal- Result Analysis Tool
 
Michael Bolton - Heuristics: Solving Problems Rapidly
Michael Bolton - Heuristics: Solving Problems RapidlyMichael Bolton - Heuristics: Solving Problems Rapidly
Michael Bolton - Heuristics: Solving Problems Rapidly
 
Project Planning with Jira
Project Planning with JiraProject Planning with Jira
Project Planning with Jira
 
Mobile App Development Proposal PowerPoint Presentation Slides
Mobile App Development Proposal PowerPoint Presentation SlidesMobile App Development Proposal PowerPoint Presentation Slides
Mobile App Development Proposal PowerPoint Presentation Slides
 
Adopting SAFe with JIRA
Adopting SAFe with JIRAAdopting SAFe with JIRA
Adopting SAFe with JIRA
 
Agile and waterfall
Agile and waterfallAgile and waterfall
Agile and waterfall
 
Introduction to scaled agile framework
Introduction to scaled agile frameworkIntroduction to scaled agile framework
Introduction to scaled agile framework
 

Ähnlich wie Hw1 project charter electronic health record for university health care_sunil kumar gunasekaran_12042012

SCHOOL_MANAGEMENT_SYSTEM_This_Report_Pre.doc
SCHOOL_MANAGEMENT_SYSTEM_This_Report_Pre.docSCHOOL_MANAGEMENT_SYSTEM_This_Report_Pre.doc
SCHOOL_MANAGEMENT_SYSTEM_This_Report_Pre.docbosed0737
 
SRS for Ph.D. Student Portal (C.S.E.D., Thapar University)
SRS for Ph.D. Student Portal (C.S.E.D., Thapar University)SRS for Ph.D. Student Portal (C.S.E.D., Thapar University)
SRS for Ph.D. Student Portal (C.S.E.D., Thapar University)Akshit Arora
 
ITP-1 – Project CharterGroup 3 - The Project Management Masters .docx
ITP-1 – Project CharterGroup 3 - The Project Management Masters .docxITP-1 – Project CharterGroup 3 - The Project Management Masters .docx
ITP-1 – Project CharterGroup 3 - The Project Management Masters .docxpriestmanmable
 
Ignou MCA mini project report
Ignou MCA mini project reportIgnou MCA mini project report
Ignou MCA mini project reportHitesh Jangid
 
Team 4, Team PMP”IT Installation of the Adelphi V.docx
Team 4, Team PMP”IT Installation of the Adelphi V.docxTeam 4, Team PMP”IT Installation of the Adelphi V.docx
Team 4, Team PMP”IT Installation of the Adelphi V.docxmattinsonjanel
 
FEASIBILITY ANALYSIS REPORT
FEASIBILITY ANALYSIS REPORTFEASIBILITY ANALYSIS REPORT
FEASIBILITY ANALYSIS REPORTrabianasir8
 
Hospital management system
Hospital management systemHospital management system
Hospital management systemMehul Ranavasiya
 
Development of home health solution using ehr
Development of home health solution using ehrDevelopment of home health solution using ehr
Development of home health solution using ehrDr. Samir Sawli
 
44478167 hospital-management-system
44478167 hospital-management-system44478167 hospital-management-system
44478167 hospital-management-systemAkshay Iliger
 
WBS ExampleWBS #Task DescriptionDuration (hours)Milestone (YN)Sta.docx
WBS ExampleWBS #Task DescriptionDuration (hours)Milestone (YN)Sta.docxWBS ExampleWBS #Task DescriptionDuration (hours)Milestone (YN)Sta.docx
WBS ExampleWBS #Task DescriptionDuration (hours)Milestone (YN)Sta.docxendawalling
 
Phase 1 Documentation (Added System Req)
Phase 1 Documentation (Added System Req)Phase 1 Documentation (Added System Req)
Phase 1 Documentation (Added System Req)Reinier Eiman
 
Activity schedule and affective control of component based project
Activity schedule and affective control of component based projectActivity schedule and affective control of component based project
Activity schedule and affective control of component based projecteSAT Journals
 
IRJET- Speech and Hearing
IRJET- Speech and HearingIRJET- Speech and Hearing
IRJET- Speech and HearingIRJET Journal
 
Leave management System
Leave management SystemLeave management System
Leave management Systempratikmahorey
 
IRJET- Course outcome Attainment Estimation System
IRJET-  	  Course outcome Attainment Estimation SystemIRJET-  	  Course outcome Attainment Estimation System
IRJET- Course outcome Attainment Estimation SystemIRJET Journal
 
What are data flow diagrams
What are data flow diagramsWhat are data flow diagrams
What are data flow diagramsAli Daniyal
 

Ähnlich wie Hw1 project charter electronic health record for university health care_sunil kumar gunasekaran_12042012 (20)

SCHOOL_MANAGEMENT_SYSTEM_This_Report_Pre.doc
SCHOOL_MANAGEMENT_SYSTEM_This_Report_Pre.docSCHOOL_MANAGEMENT_SYSTEM_This_Report_Pre.doc
SCHOOL_MANAGEMENT_SYSTEM_This_Report_Pre.doc
 
SRS for Ph.D. Student Portal (C.S.E.D., Thapar University)
SRS for Ph.D. Student Portal (C.S.E.D., Thapar University)SRS for Ph.D. Student Portal (C.S.E.D., Thapar University)
SRS for Ph.D. Student Portal (C.S.E.D., Thapar University)
 
ITP-1 – Project CharterGroup 3 - The Project Management Masters .docx
ITP-1 – Project CharterGroup 3 - The Project Management Masters .docxITP-1 – Project CharterGroup 3 - The Project Management Masters .docx
ITP-1 – Project CharterGroup 3 - The Project Management Masters .docx
 
Ignou MCA mini project report
Ignou MCA mini project reportIgnou MCA mini project report
Ignou MCA mini project report
 
Team 4, Team PMP”IT Installation of the Adelphi V.docx
Team 4, Team PMP”IT Installation of the Adelphi V.docxTeam 4, Team PMP”IT Installation of the Adelphi V.docx
Team 4, Team PMP”IT Installation of the Adelphi V.docx
 
FEASIBILITY ANALYSIS REPORT
FEASIBILITY ANALYSIS REPORTFEASIBILITY ANALYSIS REPORT
FEASIBILITY ANALYSIS REPORT
 
project plan
project planproject plan
project plan
 
Hospital management system
Hospital management systemHospital management system
Hospital management system
 
online banking system
online banking systemonline banking system
online banking system
 
Development of home health solution using ehr
Development of home health solution using ehrDevelopment of home health solution using ehr
Development of home health solution using ehr
 
44478167 hospital-management-system
44478167 hospital-management-system44478167 hospital-management-system
44478167 hospital-management-system
 
FinalReviewReport
FinalReviewReportFinalReviewReport
FinalReviewReport
 
WBS ExampleWBS #Task DescriptionDuration (hours)Milestone (YN)Sta.docx
WBS ExampleWBS #Task DescriptionDuration (hours)Milestone (YN)Sta.docxWBS ExampleWBS #Task DescriptionDuration (hours)Milestone (YN)Sta.docx
WBS ExampleWBS #Task DescriptionDuration (hours)Milestone (YN)Sta.docx
 
Phase 1 Documentation (Added System Req)
Phase 1 Documentation (Added System Req)Phase 1 Documentation (Added System Req)
Phase 1 Documentation (Added System Req)
 
Activity schedule and affective control of component based project
Activity schedule and affective control of component based projectActivity schedule and affective control of component based project
Activity schedule and affective control of component based project
 
Himanshu_Resume
Himanshu_ResumeHimanshu_Resume
Himanshu_Resume
 
IRJET- Speech and Hearing
IRJET- Speech and HearingIRJET- Speech and Hearing
IRJET- Speech and Hearing
 
Leave management System
Leave management SystemLeave management System
Leave management System
 
IRJET- Course outcome Attainment Estimation System
IRJET-  	  Course outcome Attainment Estimation SystemIRJET-  	  Course outcome Attainment Estimation System
IRJET- Course outcome Attainment Estimation System
 
What are data flow diagrams
What are data flow diagramsWhat are data flow diagrams
What are data flow diagrams
 

Mehr von Sunil Kumar Gunasekaran

Sample Technical Requirement Document (TRD)
Sample Technical Requirement Document (TRD)Sample Technical Requirement Document (TRD)
Sample Technical Requirement Document (TRD)Sunil Kumar Gunasekaran
 
Sql commands worked out in sql plus with screen shots
Sql commands worked out in sql plus with screen shotsSql commands worked out in sql plus with screen shots
Sql commands worked out in sql plus with screen shotsSunil Kumar Gunasekaran
 
Business Requirements Document for Acounts Payable System
Business Requirements Document for Acounts Payable SystemBusiness Requirements Document for Acounts Payable System
Business Requirements Document for Acounts Payable SystemSunil Kumar Gunasekaran
 
Test Life Cycle - Presentation - Important concepts covered
Test Life Cycle - Presentation - Important concepts coveredTest Life Cycle - Presentation - Important concepts covered
Test Life Cycle - Presentation - Important concepts coveredSunil Kumar Gunasekaran
 
PERL for QA - Important Commands and applications
PERL for QA - Important Commands and applicationsPERL for QA - Important Commands and applications
PERL for QA - Important Commands and applicationsSunil Kumar Gunasekaran
 
JAVA Notes - All major concepts covered with examples
JAVA Notes - All major concepts covered with examplesJAVA Notes - All major concepts covered with examples
JAVA Notes - All major concepts covered with examplesSunil Kumar Gunasekaran
 
Java programs - bubble sort, iterator, linked list, hash set, reverse string,...
Java programs - bubble sort, iterator, linked list, hash set, reverse string,...Java programs - bubble sort, iterator, linked list, hash set, reverse string,...
Java programs - bubble sort, iterator, linked list, hash set, reverse string,...Sunil Kumar Gunasekaran
 

Mehr von Sunil Kumar Gunasekaran (20)

CQL - Cassandra commands Notes
CQL - Cassandra commands NotesCQL - Cassandra commands Notes
CQL - Cassandra commands Notes
 
Java J2EE Complete Syllabus Checklist
Java J2EE Complete Syllabus ChecklistJava J2EE Complete Syllabus Checklist
Java J2EE Complete Syllabus Checklist
 
Amazon search test case document
Amazon search test case documentAmazon search test case document
Amazon search test case document
 
Actual test case document
Actual test case documentActual test case document
Actual test case document
 
Sample Technical Requirement Document (TRD)
Sample Technical Requirement Document (TRD)Sample Technical Requirement Document (TRD)
Sample Technical Requirement Document (TRD)
 
Sql reference from w3 schools
Sql reference from w3 schools Sql reference from w3 schools
Sql reference from w3 schools
 
Sql commands worked out in sql plus with screen shots
Sql commands worked out in sql plus with screen shotsSql commands worked out in sql plus with screen shots
Sql commands worked out in sql plus with screen shots
 
Wells fargo banking system ER Diagram
Wells fargo banking system ER DiagramWells fargo banking system ER Diagram
Wells fargo banking system ER Diagram
 
Business Requirements Document for Acounts Payable System
Business Requirements Document for Acounts Payable SystemBusiness Requirements Document for Acounts Payable System
Business Requirements Document for Acounts Payable System
 
Automation Testing Syllabus - Checklist
Automation Testing Syllabus - ChecklistAutomation Testing Syllabus - Checklist
Automation Testing Syllabus - Checklist
 
Unix short
Unix shortUnix short
Unix short
 
Unix made easy
Unix made easyUnix made easy
Unix made easy
 
Test process - Important Concepts
Test process - Important ConceptsTest process - Important Concepts
Test process - Important Concepts
 
Testing http methods using Telnet
Testing http methods using TelnetTesting http methods using Telnet
Testing http methods using Telnet
 
Test Life Cycle - Presentation - Important concepts covered
Test Life Cycle - Presentation - Important concepts coveredTest Life Cycle - Presentation - Important concepts covered
Test Life Cycle - Presentation - Important concepts covered
 
Scrum writeup - Agile
Scrum writeup - Agile Scrum writeup - Agile
Scrum writeup - Agile
 
Scrum, V Model and RUP Models Overview
Scrum, V Model and RUP Models OverviewScrum, V Model and RUP Models Overview
Scrum, V Model and RUP Models Overview
 
PERL for QA - Important Commands and applications
PERL for QA - Important Commands and applicationsPERL for QA - Important Commands and applications
PERL for QA - Important Commands and applications
 
JAVA Notes - All major concepts covered with examples
JAVA Notes - All major concepts covered with examplesJAVA Notes - All major concepts covered with examples
JAVA Notes - All major concepts covered with examples
 
Java programs - bubble sort, iterator, linked list, hash set, reverse string,...
Java programs - bubble sort, iterator, linked list, hash set, reverse string,...Java programs - bubble sort, iterator, linked list, hash set, reverse string,...
Java programs - bubble sort, iterator, linked list, hash set, reverse string,...
 

Hw1 project charter electronic health record for university health care_sunil kumar gunasekaran_12042012

  • 1. Project Charter for Electronic Health Record System for University Student Health Care Version 1.2 approved Prepared by Sunil Kumar Gunasekaran Copyright © 2007 by Karl E. Wiegers. Permission is granted to use and modify this template.
  • 3. Project Charter for <Project> Page iii Revision History Name Date Changes Reason For Changes Version Sunil Kumar 12/05/2012 Out of scope and New phase was introduced 1.2 Milestones requiring extension of milestone Table of Contents Revision History................................................................................................................iii 1. Project Description..........................................................................................................1 2. Business Objectives and Success Criteria.......................................................................1 3. Stakeholders.....................................................................................................................1 4. Project Scope...................................................................................................................1 5. Out of Scope....................................................................................................................2 6. Assumptions and Dependencies......................................................................................2 7. Constraints.......................................................................................................................2 8. Milestones........................................................................................................................3 9. Resources.........................................................................................................................4 10. Costs .............................................................................................................................5 11. Risks .............................................................................................................................5 12. Benefits .........................................................................................................................5 Approvals............................................................................................................................6 7
  • 4. Project Charter for <Project> Page 1 1. Project Description The University Student Health Care (hereafter USHC) is implementing Electronic Health Record System using Server obtained from PyraMED Vendor. This enhances the data transfer and universal and quick access of data and significantly reduces the operating costs and maintenance costs. 2. Business Objectives and Success Criteria 1) Have installed a working version of the EHR (hereafter Electronic Health Record) in both the PyraMed Production and Test environments. 2) Complete each phase of the project outlined in attachment. 3) Interface with existing LIS. 4) Install and interface with a CR/PACS. 5) Create a sub-department of the Medical Records department that coordinates the scanning and indexing of paper documents into electronic health records stored in PyraMED. 6) Interface with University’s Pharmacy system. 7) The building and implementation of Forms in the PyraMED EHR for use by the Providers. 8) Training of Pilot Group and “Go Live” of Pilot Group for each phase. 9) Feedback sessions with Pilot Group of each phase. 10) Training of Clinic and “Go Live” of Clinic for each phase. 3. Stakeholders 1) Students who are enrolled in the university. 2) University Executive Steering Committee. 3) Steering Committee elected by the student body. 4) Project Development and Quality Assurance Team. 5) Pilot Group created for each phase 6) Maintenance and employees of Student Health Center and Pharmacy. 7) The Director and financial team of university. 4. Project Scope 1) The Student Health Center will be responsible to manage the information between Campus departments that are needed to accomplish this project. The University Student Health Center (USHC) will supply the other campus department a schedule and timeline. 2) Student Services Workstation and Technology will provide resources and manpower to implement workstation–side software and hardware components that are required by EHR module to function properly. 3) SSWT and USHC will work together to test and verify software and hardware builds and installs.
  • 5. Project Charter for <Project> Page 2 4) The Infrastructure of Information Technology (IIT) will consult with USHC on a minimal number of phases during the project. IIT will work with USHC to help determine the storage growth of the EHR database and Document imaging. IIT will also be asked to house the Picture Archive Communication System (PACS) for power backup options and possibly data backup solutions. 5) Information Technology Security and Privacy and Internal Audit will verify the security and privacy of the HER module and other sub-systems included in the project. 6) Media Highway, vendor and supplier of the HER module, will fill the roles as provider of software and documentation, support center, installer and trainer. 7) Radiation Services of Indiana, vendor and supplier of the CR/PACS component of the system, will fill the roles as provider of software and documentation, support center, installer (server-side) and trainer. 5. Out of Scope 1) The co-ordination of the respective deliverables of the respective department is done by the department themselves and USHC will not be responsible for micro managing the inner workings of the department for the respective deliverable. 2) The update of the EHR to the latest version will not be done in this project. 3) Enhanced Data backup services using PACS - II is being considered to increase the safety of EHR documents but is not part of the current process. 6. Assumptions and Dependencies 1) Institute of Information Technology will continue to support the PyraMED databse on the Oracle servers, A ne wSLA to be drawn up for phase 3, Computerized Radiology and the Picture Archiving Communications System. 2) Media Highway, the vendor, will continue to support and help maintain PyraMED, along with the new EHR, within their abilities to access the system. Their level of focus will remain constant. 3) Student Services Workstation Technology will ontinue to provide workstation support to the point that the PyraMED client installed on Student Health Center workstations will run without issue that result in negligible loss of system effectiveness and functionality. 4) The Computer Services department of the Student Health Center will continue to support the PyraMED Health Information System as system administrators and work as liasons between the aforementioned departments to help during software upgrades, running maintenance, determining resolutions to issues, and other activities that ensure the continued availability of the system. 7. Constraints
  • 6. Project Charter for <Project> Page 3 Dimension Constraint Driver Degree of Freedom Features Database backup; EHR, 70-80% of high priority Electronic Forms, Interface for electronic features must be included signs, Computerized Radiology in release 1.2 Document Indexing Quality 90-95% of user acceptance Amount of data to be Number of staff and tests must pass for release converted into EHR robustness of software 1.0, 95-98% for release used 1.1 Cost Recurring cost for 3 times return in span of 5 budget overrun up to 15% electronic form and lack years and significant acceptable without of support from vendor reduction of operating executive review cost Schedule release 1.2 to be available by 10/1, release 1.1 by 12/1 Staff maximum team size is 6 30 Medical staff for EHR On request the medical developers + 4 testers for document loading. staff, radiology staff and EHR installation and Continued support from department staff numbers interface creation and Computer Science increased by 10 percent. background support and department staff – 10 maintenance 8. Milestones The project milestones are divided into eight phases each phase requiring its own department, resources and deliverables. Phase 1 – Planning Deliverables – Timeline, installation of EHR Phase 2 - EHR – Move to EHR Coding Deliverables – Old version converted into new version. Phase 3 – Computerized Radiology Deliverables – Installation and configuration of PACS and CR Systems. Phase 4 – Notifications Deliverables – Creation of intra – system messaging modules Phase 5 – Document Indexing Deliverables – Complete Scan of all patient paper records along with x-ray and other multimedia documents. Phase 6 – Transcription Deliverables – Installation of Dragon Speak software and complete recording and transcription of the records.
  • 7. Project Charter for <Project> Page 4 Phase 7 – EHR forms and electronic SOAP Notes Deliverables –Standardized documentation of EHR using the electronic forms Phase 8 – Electronic Signature Deliverables – Creation of Interface to obtain electronic signature of patients to be loaded into EHR. 9. Resources The respective resources committed by the USHC for various phases are given below. Phase 1 – Planning Description: The creation of the timeline, engagement of key players and installation of the HER Module. Resources: Medical Staff, Media Highway Training, Application of the EHR module to the PyraMED Core System, USHC Computer Services. Phase 2 – EHR – Move to EHR Coding Description: The old coding screen is moved to the new EHR Coding screen. The process is the same except the change in environment. Resources: Medical Staff, USHC Computer Services. Phase 3 – Computerized Radiology Description: Installation and configuration of the PACS and CR systems as well as the interface with the existing PyraMED Core systems. Resources: Radiation Services, IIT Server and support group, Radiology Staff, USHC Computer Services, Media Highway Interfacing. Phase 4 – Notifications Description: This is an intra-system messaging module at patient level that allows sign off and other communications between staff. Resources: Medical Staff, Nursing, Lab and Radiology, USHC Computer Services. Phase 5 – Document Indexing Description: This module allows multimedia images to be associated with patient records. This includes the scanning of external documents and historical paper records as well as the importation of anatomical graphics and digital photos. Resources: Medical Staff, USHC Computer Services. Phase 6 – Transcription Description: Direct recording into the chart and transcription of this recording by means of software such as Dragon Speak. Resources: Medical Records Group, USHC Computer Services, Medical Staff, Nursing, Media Highway. Phase 7 – EHR Forms and Electronic SOAP Notes
  • 8. Project Charter for <Project> Page 5 Description: This phase truly moves USHC into the electronic health record era. Having completed the previous phases, we will be in a position to use the EHR module to the fullest capacity. The electronic forms allow standardization of documentation on encounters. Resources: Medical Records Group, USHC Computer Services, Medical Staff, Nursing. Phase 8 – Electronic Signature Description: Media Highway is developing an interface so that electronic signature pads can be connected to the PyraMED system. This will allow patients and staff to electronically attach their signature to encounters. Resources: Medical Records Group, USHC Computer Services, Medical Staff, Nursing. SSWT and Media Highway 10. Costs 1) EHR coding – EHR Module provided free of cost; Training of staff: $7000 2) Purchase price of PACs Equipment -$170000. Secured a contract with the vendor for the annual license fee including support. 3) Costs from IIT to house the server – Unknown. IIT to define this by end of year. 4) Media Highway costs to setup interface -$5000. $1000 added to annual licensure fee. 5) IIT backup cost – approximately $3/GB of backed up data. 6) Document Indexing – non recurring - $7940 11. Risks 1) Currently, the Student Health Center uses a pneumatic tube system to convey paper medial charts throughout the building. This 40 year old system is in constant repair and All those are repairs done in-house as there is no longer any support from the original vendor. 2) The backup for the database is not that efficient and better upgrade system currently not chosen in this setup. Hence the probability of losing data is little high. 12. Benefits 1) Immediate and universal access to the patient record through predetermined levels of security, thus ensuring HIPAA compliance. 2) Easier and quicker navigation through the patient record. 3) The elimination of misdirected physical paper charts. 4) The standardization of visit documentation among providers within the organization. 5) Clinical data formatted so to easily read and analyze. 6) The reduction of paperwork, documentation errors, and filing activities and the associated costs. 7) Greater efficiency in completed visit documentation. 8) The possibility to electronically transmit to other providers on request.
  • 9. Project Charter for <Project> Page 6 9) The availability of clinical data for use in quality, risk, utilization, auditing and return on investment analyses. Approvals Approval Decision:  Approved, development of detailed project plan is authorized  Approved, project execution is authorized  Approved, but project is on hold until future notice  Revise charter and resubmit for approval  Charter and project proposal are rejected Role or Title Name and Signature Date Excecutive Sponsor Lee Gordon Project Manager Steve Baker Business Analyst James Westman
  • 10. Project Charter for <Project> Page 7