SlideShare a Scribd company logo
1 of 19
Risk Analysis
SHOWAIB AHMED CHOWDHURY
Lecturer
Department of Building Engineering & Construction Management
Rajshahi University of Engineering & Technology(RUET)
Risk Analysis
Once you have identified the risks that could affect your project, you need to
determine which ones you will spend time and money on.
Risk analysis is the process of prioritizing risks based on the probability of the
risk occurring and the impact it would have on the project.
There are two primary methods of risk analysis you can use on your project...
•Qualitative Risk Analysis
•Quantitative Risk Analysis
The main difference between these two methods of risk analysis is
that qualitative risk analysis uses a relative or descriptive scale to measure the
probability of occurrence whereas quantitative risk analysis uses a numerical
scale.
Qualitative Risk Analysis
Studying the identify risks process should ideally lead to a question –
How long should I keep identifying risks?
Perform Qualitative Risk Analysis is all about analyzing the risks to
figure out two things,
How likely is it to occur?
What would its impact be?
All the risks can be categorized into 4 divisions,
• High Probability – High Impact
• Low Probability – High Impact
• Low Probability – Low Impact
• High Probability – Low Impact
At the end of the day, Perform Qualitative Risk Analysis process
helps you prioritize or rank risks for further analysis and action.
Risk Probability and Impact Assessment
“How do you determine if a risk is big or small?
How do you figure out how likely the risk is going to occur or
materialize?”
In order to handle risks,
1. You need to figure out how likely is it that the risk is going to
materialize by assigning a probability value based on the likelihood
of the risk’s occurrence
2. Once you have the probability figured out, you then work towards
estimating the cost or the impact of the risk if it does materialize
Using these values, you will be able to interpret which risks need a
pretty solid mitigation plan while which ones can be monitored as the
project progresses
Risk Probability Scale
RATING LIKELIHOOD DESCRIPTION
1 Very Low Highly unlikely to occur. May occur in
exceptional situations.
2 Low Most likely will not occur. Infrequent
occurrence in past projects.
3 Moderate Possible to occur.
4 High Likely to occur. Has occurred in past
projects.
5 Very High Highly likely to occur. Has occurred in
past projects and conditions exist for it
to occur on this project.
1.
2.
Impact Assessment Scale
RATING IMPACT COST SCHEDULE
1 Very Low No increase in
budget
No change to
schedule
2 Low < 5% increase in
budget
< 1 week delay to
schedule
3 Moderate 5-10% increase in
budget
1 - 2 weeks delay to
schedule
4 High 10-20% increase in
budget
2 - 4 weeks delay to
schedule
5 Very High > 20% increase in
budget
> 4 weeks delay to
schedule
1.
2.
These scales are very dependent on the specific details of your project.
A "Low" likelihood of occurrence for one project may mean a risk event
is unlikely to occur within the next 10 deployments. With another type
of project "Low" may mean that a risk event is unlikely to occur within
the next year.
The impact scale for your project could also include other
considerations such as scope, political, and employee impacts.
With your rating scales prepared, you can create a Risk Assessment
Matrix to help you categorize the Risk Level for each risk event.
Risk Appetites, Risk Tolerance, Risk Threshold
Risk Appetites is a general and subjective description of acceptable risk level.
Risk Tolerance is a measurable and specific level of risks.
Risk Threshold is a particular point at which risks become unacceptable.
The outputs of Qualitative Risk Analysis
• A prioritized list of risks.
• List of risks grouped by categories.
• List of risk for additional analysis and investigation.
• List of urgent risks.
• Watch List
Quantitative Risk Analysis
Qualitative risk analysis is a numeric estimate of the overall effect of
risk on the project objectives such as cost and schedule objectives.
‘Numerically’ being the keyword here.
Why Perform Quantitative Risk Analysis
• Better Overall Project Risk Analysis
• Better Business Decisions
• Better Estimates
Qualitative Risk Analysis Techniques
1. Expected Monetary Value Analysis
2. Sensitivity Analysis
3. Modeling and Simulation
Expected Monetary Value Analysis
With the help of EMV analysis you will be able to calculate the costs of all
the paths you might take during the course of your project.
Risk Probability Impact
Server hardware failure 15% Costs $300 for maintenance
A dependent coding module is
completed early
8%
Saves 2 days of work and an overall
$500 in cost
Procurement stuck at customs 10%
Can cost up to $100 for additional
paperwork
To begin with, you will calculate the Expected Monetary Value (EMV) for each risk,
Risk 1: 15% x $300 = $45 (-$45)
Risk 2: 8% x $500 = $40
Risk 3: 10% x $100 = $10 (-$10)
Now add all these values for total EMV
(-45) + 40 + (-10) = -15
Comment: This $15 is the extra money that you need to add to your budget to account for
all the project risks.
QUESTION
Solution:
Risk Probability Cost Impact EMV
A (Threat) 20% $100,000 -$20,000
B (Opportunity) 40% ($10,000) +($4,000)
C (Threat) 30% $50,000 -$15,000
Total EMV -$31,000
02
Decision Tree Analysis

More Related Content

What's hot

Chapter 1 risk management (3)
Chapter 1  risk management (3)Chapter 1  risk management (3)
Chapter 1 risk management (3)rafeeqameen
 
Risk mangement
Risk mangementRisk mangement
Risk mangementcollege
 
Operational risk ppt
Operational risk pptOperational risk ppt
Operational risk pptNehaKamboj10
 
Risk Overview & Risk management
Risk Overview & Risk managementRisk Overview & Risk management
Risk Overview & Risk managementSubhendu Datta
 
Risk identification
Risk identificationRisk identification
Risk identificationmurukkada
 
Risk management concepts and learning
Risk management   concepts and learningRisk management   concepts and learning
Risk management concepts and learningVanita Ahuja
 
Risk & Risk Management
Risk & Risk ManagementRisk & Risk Management
Risk & Risk Managementansula
 
Enterprise Risk Management
Enterprise Risk ManagementEnterprise Risk Management
Enterprise Risk ManagementPYA, P.C.
 
Risk Management Overview
Risk Management OverviewRisk Management Overview
Risk Management OverviewJIGNESH PADIA
 
the importance of risk management
the importance of risk management the importance of risk management
the importance of risk management cesmy
 
Risk Management Process And Procedures PowerPoint Presentation Slides
Risk Management Process And Procedures PowerPoint Presentation SlidesRisk Management Process And Procedures PowerPoint Presentation Slides
Risk Management Process And Procedures PowerPoint Presentation SlidesSlideTeam
 

What's hot (20)

Chapter 1 risk management (3)
Chapter 1  risk management (3)Chapter 1  risk management (3)
Chapter 1 risk management (3)
 
Risk management
Risk managementRisk management
Risk management
 
Risk mangement
Risk mangementRisk mangement
Risk mangement
 
Risk management
Risk managementRisk management
Risk management
 
Risk analysis
Risk analysisRisk analysis
Risk analysis
 
Risk management
Risk managementRisk management
Risk management
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Operational risk ppt
Operational risk pptOperational risk ppt
Operational risk ppt
 
Risk Overview & Risk management
Risk Overview & Risk managementRisk Overview & Risk management
Risk Overview & Risk management
 
Risk identification
Risk identificationRisk identification
Risk identification
 
Risk management concepts and learning
Risk management   concepts and learningRisk management   concepts and learning
Risk management concepts and learning
 
Risk
RiskRisk
Risk
 
Risk & Risk Management
Risk & Risk ManagementRisk & Risk Management
Risk & Risk Management
 
Risk Management Framework
Risk Management FrameworkRisk Management Framework
Risk Management Framework
 
Enterprise Risk Management
Enterprise Risk ManagementEnterprise Risk Management
Enterprise Risk Management
 
Risk Management Overview
Risk Management OverviewRisk Management Overview
Risk Management Overview
 
Risk management
Risk managementRisk management
Risk management
 
the importance of risk management
the importance of risk management the importance of risk management
the importance of risk management
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Risk Management Process And Procedures PowerPoint Presentation Slides
Risk Management Process And Procedures PowerPoint Presentation SlidesRisk Management Process And Procedures PowerPoint Presentation Slides
Risk Management Process And Procedures PowerPoint Presentation Slides
 

Similar to Risk analysis techniques

Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Dhamo daran
 
Online PMP Training Material for PMP Exam - Risk Management Knowledge Area
Online PMP Training Material for PMP Exam - Risk Management Knowledge AreaOnline PMP Training Material for PMP Exam - Risk Management Knowledge Area
Online PMP Training Material for PMP Exam - Risk Management Knowledge AreaGlobalSkillup
 
Project Risk Management
 Project Risk Management Project Risk Management
Project Risk ManagementHayat Denzi
 
How to Prioritize Risks with Qualitative and Quantitative Risk analysis
How to Prioritize Risks with Qualitative and Quantitative Risk analysisHow to Prioritize Risks with Qualitative and Quantitative Risk analysis
How to Prioritize Risks with Qualitative and Quantitative Risk analysisiZenBridge Consultancy Pvt. Ltd.
 
اهم برزنتيشن لجنك2222
اهم برزنتيشن لجنك2222اهم برزنتيشن لجنك2222
اهم برزنتيشن لجنك2222nashaat algrara
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk ManagementMarkos Mulat G
 
PMI-RMP Exam Prep Presentation
PMI-RMP Exam Prep PresentationPMI-RMP Exam Prep Presentation
PMI-RMP Exam Prep Presentationscottdreynolds
 
Project Risk Management (10)
 Project Risk Management (10) Project Risk Management (10)
Project Risk Management (10)Serdar Temiz
 
Project risk management
Project risk managementProject risk management
Project risk managementBarnatuCoffee
 
Construction project management &amp; risk mitigation
Construction project management &amp; risk mitigationConstruction project management &amp; risk mitigation
Construction project management &amp; risk mitigationrajlaxmipardeshi
 
Risk Management Best Practices
Risk Management Best PracticesRisk Management Best Practices
Risk Management Best PracticesPMILebanonChapter
 
Presentation Project managment
Presentation Project managmentPresentation Project managment
Presentation Project managmentMalan Bothma
 
For Ch -6 == Risk Monitoring & Controlling.pptx
For Ch -6 == Risk Monitoring & Controlling.pptxFor Ch -6 == Risk Monitoring & Controlling.pptx
For Ch -6 == Risk Monitoring & Controlling.pptxAbhinavRJ1
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk ManagementKaustubh Gupta
 
Critical role of_risk_assessment_in_international_projects_en
Critical role of_risk_assessment_in_international_projects_enCritical role of_risk_assessment_in_international_projects_en
Critical role of_risk_assessment_in_international_projects_enVyacheslav Guzovsky
 

Similar to Risk analysis techniques (20)

Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Projectriskmanagement pmbok5
Projectriskmanagement pmbok5
 
Online PMP Training Material for PMP Exam - Risk Management Knowledge Area
Online PMP Training Material for PMP Exam - Risk Management Knowledge AreaOnline PMP Training Material for PMP Exam - Risk Management Knowledge Area
Online PMP Training Material for PMP Exam - Risk Management Knowledge Area
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Project Risk Management
 Project Risk Management Project Risk Management
Project Risk Management
 
How to Prioritize Risks with Qualitative and Quantitative Risk analysis
How to Prioritize Risks with Qualitative and Quantitative Risk analysisHow to Prioritize Risks with Qualitative and Quantitative Risk analysis
How to Prioritize Risks with Qualitative and Quantitative Risk analysis
 
اهم برزنتيشن لجنك2222
اهم برزنتيشن لجنك2222اهم برزنتيشن لجنك2222
اهم برزنتيشن لجنك2222
 
Project mngmnt risks3.2
Project mngmnt risks3.2Project mngmnt risks3.2
Project mngmnt risks3.2
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
PMI-RMP Exam Prep Presentation
PMI-RMP Exam Prep PresentationPMI-RMP Exam Prep Presentation
PMI-RMP Exam Prep Presentation
 
Li Rmp Prep
Li Rmp PrepLi Rmp Prep
Li Rmp Prep
 
Project Risk Management (10)
 Project Risk Management (10) Project Risk Management (10)
Project Risk Management (10)
 
Project risk management
Project risk managementProject risk management
Project risk management
 
Construction project management &amp; risk mitigation
Construction project management &amp; risk mitigationConstruction project management &amp; risk mitigation
Construction project management &amp; risk mitigation
 
Risk Management Best Practices
Risk Management Best PracticesRisk Management Best Practices
Risk Management Best Practices
 
Presentation Project managment
Presentation Project managmentPresentation Project managment
Presentation Project managment
 
For Ch -6 == Risk Monitoring & Controlling.pptx
For Ch -6 == Risk Monitoring & Controlling.pptxFor Ch -6 == Risk Monitoring & Controlling.pptx
For Ch -6 == Risk Monitoring & Controlling.pptx
 
Project Risk Management Methods Comparison
Project Risk Management Methods ComparisonProject Risk Management Methods Comparison
Project Risk Management Methods Comparison
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Critical role of_risk_assessment_in_international_projects_en
Critical role of_risk_assessment_in_international_projects_enCritical role of_risk_assessment_in_international_projects_en
Critical role of_risk_assessment_in_international_projects_en
 

More from BECM, RUET, Bangladesh

More from BECM, RUET, Bangladesh (6)

BECM 4103: Lecture 2 On site human waste management
BECM 4103: Lecture 2 On site human waste managementBECM 4103: Lecture 2 On site human waste management
BECM 4103: Lecture 2 On site human waste management
 
Introduction to environmental sanitation
Introduction to environmental sanitationIntroduction to environmental sanitation
Introduction to environmental sanitation
 
Introduction to sustainability
Introduction to sustainabilityIntroduction to sustainability
Introduction to sustainability
 
Project Auditing
Project AuditingProject Auditing
Project Auditing
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
Project monitoring lecture 1
Project monitoring lecture 1Project monitoring lecture 1
Project monitoring lecture 1
 

Recently uploaded

Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Piping Basic stress analysis by engineering
Piping Basic stress analysis by engineeringPiping Basic stress analysis by engineering
Piping Basic stress analysis by engineeringJuanCarlosMorales19600
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction managementMariconPadriquez1
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptJasonTagapanGulla
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 

Recently uploaded (20)

Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Piping Basic stress analysis by engineering
Piping Basic stress analysis by engineeringPiping Basic stress analysis by engineering
Piping Basic stress analysis by engineering
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction management
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.ppt
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 

Risk analysis techniques

  • 1. Risk Analysis SHOWAIB AHMED CHOWDHURY Lecturer Department of Building Engineering & Construction Management Rajshahi University of Engineering & Technology(RUET)
  • 2. Risk Analysis Once you have identified the risks that could affect your project, you need to determine which ones you will spend time and money on. Risk analysis is the process of prioritizing risks based on the probability of the risk occurring and the impact it would have on the project. There are two primary methods of risk analysis you can use on your project... •Qualitative Risk Analysis •Quantitative Risk Analysis The main difference between these two methods of risk analysis is that qualitative risk analysis uses a relative or descriptive scale to measure the probability of occurrence whereas quantitative risk analysis uses a numerical scale.
  • 3. Qualitative Risk Analysis Studying the identify risks process should ideally lead to a question – How long should I keep identifying risks? Perform Qualitative Risk Analysis is all about analyzing the risks to figure out two things, How likely is it to occur? What would its impact be? All the risks can be categorized into 4 divisions, • High Probability – High Impact • Low Probability – High Impact • Low Probability – Low Impact • High Probability – Low Impact
  • 4. At the end of the day, Perform Qualitative Risk Analysis process helps you prioritize or rank risks for further analysis and action.
  • 5. Risk Probability and Impact Assessment “How do you determine if a risk is big or small? How do you figure out how likely the risk is going to occur or materialize?” In order to handle risks, 1. You need to figure out how likely is it that the risk is going to materialize by assigning a probability value based on the likelihood of the risk’s occurrence 2. Once you have the probability figured out, you then work towards estimating the cost or the impact of the risk if it does materialize Using these values, you will be able to interpret which risks need a pretty solid mitigation plan while which ones can be monitored as the project progresses
  • 6. Risk Probability Scale RATING LIKELIHOOD DESCRIPTION 1 Very Low Highly unlikely to occur. May occur in exceptional situations. 2 Low Most likely will not occur. Infrequent occurrence in past projects. 3 Moderate Possible to occur. 4 High Likely to occur. Has occurred in past projects. 5 Very High Highly likely to occur. Has occurred in past projects and conditions exist for it to occur on this project. 1. 2.
  • 7. Impact Assessment Scale RATING IMPACT COST SCHEDULE 1 Very Low No increase in budget No change to schedule 2 Low < 5% increase in budget < 1 week delay to schedule 3 Moderate 5-10% increase in budget 1 - 2 weeks delay to schedule 4 High 10-20% increase in budget 2 - 4 weeks delay to schedule 5 Very High > 20% increase in budget > 4 weeks delay to schedule 1. 2.
  • 8. These scales are very dependent on the specific details of your project. A "Low" likelihood of occurrence for one project may mean a risk event is unlikely to occur within the next 10 deployments. With another type of project "Low" may mean that a risk event is unlikely to occur within the next year. The impact scale for your project could also include other considerations such as scope, political, and employee impacts. With your rating scales prepared, you can create a Risk Assessment Matrix to help you categorize the Risk Level for each risk event.
  • 9.
  • 10.
  • 11.
  • 12.
  • 13. Risk Appetites, Risk Tolerance, Risk Threshold Risk Appetites is a general and subjective description of acceptable risk level. Risk Tolerance is a measurable and specific level of risks. Risk Threshold is a particular point at which risks become unacceptable. The outputs of Qualitative Risk Analysis • A prioritized list of risks. • List of risks grouped by categories. • List of risk for additional analysis and investigation. • List of urgent risks. • Watch List
  • 14. Quantitative Risk Analysis Qualitative risk analysis is a numeric estimate of the overall effect of risk on the project objectives such as cost and schedule objectives. ‘Numerically’ being the keyword here. Why Perform Quantitative Risk Analysis • Better Overall Project Risk Analysis • Better Business Decisions • Better Estimates
  • 15. Qualitative Risk Analysis Techniques 1. Expected Monetary Value Analysis 2. Sensitivity Analysis 3. Modeling and Simulation Expected Monetary Value Analysis With the help of EMV analysis you will be able to calculate the costs of all the paths you might take during the course of your project.
  • 16. Risk Probability Impact Server hardware failure 15% Costs $300 for maintenance A dependent coding module is completed early 8% Saves 2 days of work and an overall $500 in cost Procurement stuck at customs 10% Can cost up to $100 for additional paperwork To begin with, you will calculate the Expected Monetary Value (EMV) for each risk, Risk 1: 15% x $300 = $45 (-$45) Risk 2: 8% x $500 = $40 Risk 3: 10% x $100 = $10 (-$10) Now add all these values for total EMV (-45) + 40 + (-10) = -15 Comment: This $15 is the extra money that you need to add to your budget to account for all the project risks. QUESTION Solution:
  • 17. Risk Probability Cost Impact EMV A (Threat) 20% $100,000 -$20,000 B (Opportunity) 40% ($10,000) +($4,000) C (Threat) 30% $50,000 -$15,000 Total EMV -$31,000 02
  • 18.