Location decisions are strategic:-
Liable to affect the entire organization
Operative over longer time spans
Difficult to reverse
Capital intensive
HIERARCHY OF LOCATION
PROBLEMS
 Location of ‘plant’
 Plant lay out (location of ‘Depts’)
 Physical arrangements of M/cs
 Work place layout (location of ‘tools’ or ‘raw
materials’)
 The term ‘facility location’ emphasizes the generalized
approach that handles the variety of above mentioned
problems.
LOCATION DECISIONS ARE
DYNAMIC
 Owing to changing technology, competition, change
of consumer tastes, decisions like
 new plants
Expansion
Decentralization
Plant shut down
Are constantly under review.
IMPORTANT FACTORS IN LOCATION
 Market
 Raw materials
 Transportation
 Power
 Climate and fuel
 Labour and wages
 Laws and taxation
 Community services
 Water and waste
 Government incentives
Raw materials
• Pure materials
 Weight losing materials
 Ubiquities
ANNUAL OPERATION EXPENSES
 Consist of:-
o Materials
o Transportation
o Real estate taxes
o Fuel costs
o Sundry state taxes
o Electric power.
FIXED AND VARIABLE COST
ANNUAL
COST
• LOCATION A
LOCATION B
• VOLUME OF PRODUCTION
MECHANICAL ANALOGUE FOR
FINDING BEST LOCATION OF A
MANUFACTURING PLANT
 (also known as Varignon’s Frame after the inventor)
In the absence of friction
the common knot P of
(m+n) strings comes to
equilibrium at least cost
location.
{ here we draw an analogy
between
Min potential energy
&
Min travel cost}
ASSUMPTIONS
_ R1, R2……Rn locations of
raw material sources.
_ M1, M2 ….Mn locations of
markets.
_ Euclidean (straight line
travel)
_ each weight (there are m+n
in all)
_ Wi- No: of annual trips
between P and that pt X
(cost per unit distance)
 MULTI OBJECTIVE CONSIDERATIONS IN
LOCATION DECISIONS
FACTORS AFFECTING LOCATION ARE:-
SUBJECTIVE OBJECTIVE
(labour attitudes) eg: costs
INTANGIBLE TANGIBLE
INCOMMENSURATE UNITS
 A decision matrix approach with proper evaluation of
weights of factors. Normalization of scores can help in
ranking alternative locations.
 (THIS IS DEMONSTRATEDTHROUGH A CASE
STUDY)
MULTI PLANT OPERATION-AN
EXAMPLE OF PLANT ADDITION
P1 existing plant
P2 existing plant
A,B,C,D,E- ware houses
X,Y,Z-possible locations for
new plant
P1
P2
A
B
C
D
E
X
Z
Y
 Owing to increase of weekly demand to 72000 there is
a capacity deficit of 25000 per week and it is felt that a
plant of capacity 25000 could be set up X, Y or Z
DATA SHEET
P1 P2 X Y Z Weekly
Forecast
of
market
demand
A 0.42 0.32 0.44 0.44 0.41 10000
B
C
D
E
CAPACITY
UNIT
PROD
OPTIMUM PRODUCTION-
DISTRIBUTING SOLUTIONS
Product cost= 192500 Distn cost=26450 Total=218950
P1 P2 X
A 10 10
B 8 7 15
C 16 16
D 19 19
E 10 2 12
27 20 25 72
OPTIMUM PRODUCTION-
DISTRIBUTING SOLUTIONS
Product cost= 193750 Distn cost=26960 Total=220710
P1 P2 Y
A 10 10
B 15 15
C 8 8 16
D 19 19
E 10 2 12
27 20 25 72
OPTIMUM PRODUCTION-DISTRIBUTING SOLUTIONS
Product cost= 192000 Distn cost=26400 Total=218400
Hence choose plant at site Z(since Z cost is minimum)
P1 P2 Z
A 10 10
B 15 15
C 10 6 16
D 12 7 19
E 12 12
27 20 25 72
LOCATIONAL DYNAMICS
 Suppose third plant is set up at site z
 After some time demand drops from 72000 to 56000
per week.
 Which plant to shut down?
 Which plant to run at partial capacity?
(these are location decisions)
ALTERNATIVES FOR INVESTIGATION
 1. Run all plants at partial capacity
 2.shut down P1 .use overtime in others
 3. shut down P2. use overtime in others
 4. shut down Z. use overtime in others.
PROBLEM DATA:- ware house demands A-9000, B-13000,
C-11000, D-15000, E-8000
PLANTS P1 P2 Z
Over time production cost 3.37 3.33 3.27
O.T capacity 7000 5000 6000
Fixed costs (per week)
(Don’t depend on production volume)
While operating 12000 9000 13000
While shut down 5000 4000 6000
EVALUATING SHUT DOWN OPTIONS
P1 P2 Z
A 9 9
B 13 13
C 11 11
D 14 1 15
E 8 8
F 11 5 16
27 20 25 72
EVALUATING SHUT DOWN OPTIONS
P2 Z OT2 OTz
A 9 9
B 8 5 13
C 11 11
D 9 6 15
E 8 8
20 25 56
EVALUATING SHUT DOWN OPTIONS
P1 Z OT1 OTz
A 6 3 9
B 13 13
C 11 11
D 14 1 15
E 8 8
F 7 2
27 25 7 6 65
EVALUATING SHUT DOWN OPTIONS
P1 p2 OT1 OT2
A 9 9
B 9 4 13
C 3 8 11
D 15 15
E 3 5 8
F 3 3
27 20 7 5 65
EVALUATING SHUT DOWN OPTIONS
Min cost for alternative 3 . Hence shut down plant 3
1 2 3 4
FIXED
VARIABLE
34000
169650
27000
177730
29000
173750
27000
178400
TOTAL COST 203650 204730 202150 205400
summary
 The strategic importance of location decisions
 Hierarchy of location decisions
 Analogue model for facility location
 Important factors in plant location
 A case study on new plant location and shut down
under dynamic conditions.

More Related Content

What's hot

Facility location and layout planning
Facility location and layout planningFacility location and layout planning
Facility location and layout planning
Birodh Adhikari
 
Aggregate Production Planning
Aggregate Production PlanningAggregate Production Planning
Aggregate Production Planning
3abooodi
 
Capacity planning
Capacity planningCapacity planning
Capacity planning
Akhil Lal
 
3 Inventory Management And Risk Pooling
3 Inventory Management And Risk Pooling3 Inventory Management And Risk Pooling
3 Inventory Management And Risk Pooling
pirama2000
 
Operation management-notes
Operation management-notesOperation management-notes
Operation management-notes
ismatullahzazai
 

What's hot (20)

Warehouse location
Warehouse locationWarehouse location
Warehouse location
 
AGGREGATE PRODUCTION PLANNING
AGGREGATE PRODUCTION PLANNING AGGREGATE PRODUCTION PLANNING
AGGREGATE PRODUCTION PLANNING
 
Facility location and layout planning
Facility location and layout planningFacility location and layout planning
Facility location and layout planning
 
CAPACITY PLANNING
CAPACITY PLANNINGCAPACITY PLANNING
CAPACITY PLANNING
 
Aggregate Production Planning
Aggregate Production PlanningAggregate Production Planning
Aggregate Production Planning
 
ความเข้ากันได้เชิงกลยุทธ์ Strategic fit
ความเข้ากันได้เชิงกลยุทธ์ Strategic fit ความเข้ากันได้เชิงกลยุทธ์ Strategic fit
ความเข้ากันได้เชิงกลยุทธ์ Strategic fit
 
facility location and planning layout
facility location and planning layoutfacility location and planning layout
facility location and planning layout
 
Location Planning
Location PlanningLocation Planning
Location Planning
 
Capacity planning
Capacity planningCapacity planning
Capacity planning
 
Location decision
Location decisionLocation decision
Location decision
 
Design of process layout
Design of process layoutDesign of process layout
Design of process layout
 
3 Inventory Management And Risk Pooling
3 Inventory Management And Risk Pooling3 Inventory Management And Risk Pooling
3 Inventory Management And Risk Pooling
 
Aggregate planning
Aggregate planningAggregate planning
Aggregate planning
 
Operation Management
Operation ManagementOperation Management
Operation Management
 
Economic Order Quantity - EOQ
Economic Order Quantity - EOQEconomic Order Quantity - EOQ
Economic Order Quantity - EOQ
 
Facility layout
Facility layoutFacility layout
Facility layout
 
capacity planning om
capacity planning omcapacity planning om
capacity planning om
 
Plant location and layout
Plant location and layoutPlant location and layout
Plant location and layout
 
Capacity planning
Capacity planning Capacity planning
Capacity planning
 
Operation management-notes
Operation management-notesOperation management-notes
Operation management-notes
 

Viewers also liked (7)

Tn11 facility location
Tn11 facility locationTn11 facility location
Tn11 facility location
 
Facility location problem
Facility location problemFacility location problem
Facility location problem
 
facility location ( operations and quality management)
facility location ( operations and quality management)facility location ( operations and quality management)
facility location ( operations and quality management)
 
Facility location
Facility locationFacility location
Facility location
 
KFC
KFCKFC
KFC
 
Operation management presentation
Operation management presentationOperation management presentation
Operation management presentation
 
MBA Operations Management Assignment
MBA Operations Management AssignmentMBA Operations Management Assignment
MBA Operations Management Assignment
 

Similar to Facility location

Optimising Efficiency & Capacity Sep 04 Rev 0
Optimising Efficiency & Capacity Sep 04 Rev 0Optimising Efficiency & Capacity Sep 04 Rev 0
Optimising Efficiency & Capacity Sep 04 Rev 0
Raja Ratnam
 
Bnef university solar_wind_bioenergy_geothermal_ccs_energy_smart_technologie
Bnef university solar_wind_bioenergy_geothermal_ccs_energy_smart_technologieBnef university solar_wind_bioenergy_geothermal_ccs_energy_smart_technologie
Bnef university solar_wind_bioenergy_geothermal_ccs_energy_smart_technologie
MARIANO ORTULAN
 
Project green buildings (be)
Project green buildings (be)Project green buildings (be)
Project green buildings (be)
husein
 
Lunch N Learn Ppt 09 01
Lunch N Learn Ppt 09 01Lunch N Learn Ppt 09 01
Lunch N Learn Ppt 09 01
rpekowski
 

Similar to Facility location (20)

Factory Infrastructure for PV Manufacturing
Factory Infrastructure for PV ManufacturingFactory Infrastructure for PV Manufacturing
Factory Infrastructure for PV Manufacturing
 
Optimising Efficiency & Capacity Sep 04 Rev 0
Optimising Efficiency & Capacity Sep 04 Rev 0Optimising Efficiency & Capacity Sep 04 Rev 0
Optimising Efficiency & Capacity Sep 04 Rev 0
 
Bnef university solar_wind_bioenergy_geothermal_ccs_energy_smart_technologie
Bnef university solar_wind_bioenergy_geothermal_ccs_energy_smart_technologieBnef university solar_wind_bioenergy_geothermal_ccs_energy_smart_technologie
Bnef university solar_wind_bioenergy_geothermal_ccs_energy_smart_technologie
 
Practically Delivering Energy-Reducing Technology To Optimise Efficiency On T...
Practically Delivering Energy-ReducingTechnology To Optimise Efficiency On T...Practically Delivering Energy-ReducingTechnology To Optimise Efficiency On T...
Practically Delivering Energy-Reducing Technology To Optimise Efficiency On T...
 
Project green buildings (be)
Project green buildings (be)Project green buildings (be)
Project green buildings (be)
 
A practical approach to pharmaceutical HVAC energy reduction
A practical approach to pharmaceutical HVAC energy reductionA practical approach to pharmaceutical HVAC energy reduction
A practical approach to pharmaceutical HVAC energy reduction
 
Converting Demand Side Operation in to an Accurate Tool for the Transmission ...
Converting Demand Side Operation in to an Accurate Tool for the Transmission ...Converting Demand Side Operation in to an Accurate Tool for the Transmission ...
Converting Demand Side Operation in to an Accurate Tool for the Transmission ...
 
Project Presentation
Project PresentationProject Presentation
Project Presentation
 
Lunch N Learn Ppt 09 01
Lunch N Learn Ppt 09 01Lunch N Learn Ppt 09 01
Lunch N Learn Ppt 09 01
 
Gravitricity Ltd
Gravitricity LtdGravitricity Ltd
Gravitricity Ltd
 
Top 10 Products That Save Money - David McDougall, EnerNOC
Top 10 Products That Save Money - David McDougall, EnerNOCTop 10 Products That Save Money - David McDougall, EnerNOC
Top 10 Products That Save Money - David McDougall, EnerNOC
 
IRJET- An Approach to Offer Price (Generating Station) Arrival Process throug...
IRJET- An Approach to Offer Price (Generating Station) Arrival Process throug...IRJET- An Approach to Offer Price (Generating Station) Arrival Process throug...
IRJET- An Approach to Offer Price (Generating Station) Arrival Process throug...
 
Project Proposal on 10 MW Solar PV Power Plant
Project Proposal on 10 MW Solar PV Power PlantProject Proposal on 10 MW Solar PV Power Plant
Project Proposal on 10 MW Solar PV Power Plant
 
Projectproposalon10mwsolarpvpowerplant 160312085340 (2)
Projectproposalon10mwsolarpvpowerplant 160312085340 (2)Projectproposalon10mwsolarpvpowerplant 160312085340 (2)
Projectproposalon10mwsolarpvpowerplant 160312085340 (2)
 
C0 4 ricardo_revenues costs
C0 4 ricardo_revenues costsC0 4 ricardo_revenues costs
C0 4 ricardo_revenues costs
 
Toronto solvent reduction esr presentation 7 15-2008
Toronto solvent reduction esr presentation 7 15-2008 Toronto solvent reduction esr presentation 7 15-2008
Toronto solvent reduction esr presentation 7 15-2008
 
KEPCO's Demand Side Management Programs
KEPCO's Demand Side Management ProgramsKEPCO's Demand Side Management Programs
KEPCO's Demand Side Management Programs
 
Green Energy From Heat - Themo Electric Generation (TEG)
Green Energy From Heat  - Themo Electric Generation (TEG)Green Energy From Heat  - Themo Electric Generation (TEG)
Green Energy From Heat - Themo Electric Generation (TEG)
 
Demand-Side Flexibility for Reliable Ancillary Services in a Smart Grid: Elim...
Demand-Side Flexibility for Reliable Ancillary Services in a Smart Grid: Elim...Demand-Side Flexibility for Reliable Ancillary Services in a Smart Grid: Elim...
Demand-Side Flexibility for Reliable Ancillary Services in a Smart Grid: Elim...
 
Drivers and Barriers in the current CSP market
Drivers and Barriers in the current CSP marketDrivers and Barriers in the current CSP market
Drivers and Barriers in the current CSP market
 

More from Shifas ibrahim MBA student @ ILAHIA SCHOOL OF MANAGEMENT STUDIES

More from Shifas ibrahim MBA student @ ILAHIA SCHOOL OF MANAGEMENT STUDIES (20)

Types of manufacturing_systems
Types of manufacturing_systemsTypes of manufacturing_systems
Types of manufacturing_systems
 
Production planning and_control-an_introduction
Production planning and_control-an_introductionProduction planning and_control-an_introduction
Production planning and_control-an_introduction
 
Operations management overview
Operations management overviewOperations management overview
Operations management overview
 
Materials requirement planning
Materials requirement planningMaterials requirement planning
Materials requirement planning
 
Interaction of operations_management_with_other_functional_areas
Interaction of operations_management_with_other_functional_areasInteraction of operations_management_with_other_functional_areas
Interaction of operations_management_with_other_functional_areas
 
Improving the productivity_and_introducing_the_work_study
Improving the productivity_and_introducing_the_work_studyImproving the productivity_and_introducing_the_work_study
Improving the productivity_and_introducing_the_work_study
 
Forecasting and various_methods
Forecasting and various_methodsForecasting and various_methods
Forecasting and various_methods
 
Forecasting
ForecastingForecasting
Forecasting
 
Facility location
Facility locationFacility location
Facility location
 
Facility layout
Facility layoutFacility layout
Facility layout
 
Facilities planning _lay_out_and_location_analysis
Facilities planning _lay_out_and_location_analysisFacilities planning _lay_out_and_location_analysis
Facilities planning _lay_out_and_location_analysis
 
Basic inventory principles
Basic inventory principlesBasic inventory principles
Basic inventory principles
 
Classifying production processes
Classifying production processesClassifying production processes
Classifying production processes
 
Work sampling
Work samplingWork sampling
Work sampling
 
Module 2
Module 2Module 2
Module 2
 
Sources of finance
Sources of financeSources of finance
Sources of finance
 
Leverages
LeveragesLeverages
Leverages
 
Inventory mgt,s p k
Inventory mgt,s p kInventory mgt,s p k
Inventory mgt,s p k
 
Financial management intro,capital_budgeting,cost_of_capital_-_copy
Financial management intro,capital_budgeting,cost_of_capital_-_copyFinancial management intro,capital_budgeting,cost_of_capital_-_copy
Financial management intro,capital_budgeting,cost_of_capital_-_copy
 
Cash management
Cash managementCash management
Cash management
 

Recently uploaded

The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
daisycvs
 

Recently uploaded (20)

Pre Engineered Building Manufacturers Hyderabad.pptx
Pre Engineered  Building Manufacturers Hyderabad.pptxPre Engineered  Building Manufacturers Hyderabad.pptx
Pre Engineered Building Manufacturers Hyderabad.pptx
 
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business Potential
 
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR ESCORTS
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR  ESCORTSJAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR  ESCORTS
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR ESCORTS
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
Buy gmail accounts.pdf buy Old Gmail Accounts
Buy gmail accounts.pdf buy Old Gmail AccountsBuy gmail accounts.pdf buy Old Gmail Accounts
Buy gmail accounts.pdf buy Old Gmail Accounts
 
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
 
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
 
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service AvailableNashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
 
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
 
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NSCROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
 
Cannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 UpdatedCannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 Updated
 
Berhampur Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Berhampur Call Girl Just Call 8084732287 Top Class Call Girl Service AvailableBerhampur Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Berhampur Call Girl Just Call 8084732287 Top Class Call Girl Service Available
 
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
 
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGParadip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All TimeCall 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1
 
Berhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGBerhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentation
 

Facility location

  • 1. Location decisions are strategic:- Liable to affect the entire organization Operative over longer time spans Difficult to reverse Capital intensive
  • 2. HIERARCHY OF LOCATION PROBLEMS  Location of ‘plant’  Plant lay out (location of ‘Depts’)  Physical arrangements of M/cs  Work place layout (location of ‘tools’ or ‘raw materials’)
  • 3.  The term ‘facility location’ emphasizes the generalized approach that handles the variety of above mentioned problems.
  • 4. LOCATION DECISIONS ARE DYNAMIC  Owing to changing technology, competition, change of consumer tastes, decisions like  new plants Expansion Decentralization Plant shut down Are constantly under review.
  • 5. IMPORTANT FACTORS IN LOCATION  Market  Raw materials  Transportation  Power  Climate and fuel  Labour and wages  Laws and taxation  Community services  Water and waste  Government incentives
  • 6. Raw materials • Pure materials  Weight losing materials  Ubiquities
  • 7. ANNUAL OPERATION EXPENSES  Consist of:- o Materials o Transportation o Real estate taxes o Fuel costs o Sundry state taxes o Electric power.
  • 8. FIXED AND VARIABLE COST ANNUAL COST • LOCATION A LOCATION B • VOLUME OF PRODUCTION
  • 9. MECHANICAL ANALOGUE FOR FINDING BEST LOCATION OF A MANUFACTURING PLANT  (also known as Varignon’s Frame after the inventor)
  • 10. In the absence of friction the common knot P of (m+n) strings comes to equilibrium at least cost location. { here we draw an analogy between Min potential energy & Min travel cost} ASSUMPTIONS _ R1, R2……Rn locations of raw material sources. _ M1, M2 ….Mn locations of markets. _ Euclidean (straight line travel) _ each weight (there are m+n in all) _ Wi- No: of annual trips between P and that pt X (cost per unit distance)
  • 11.  MULTI OBJECTIVE CONSIDERATIONS IN LOCATION DECISIONS FACTORS AFFECTING LOCATION ARE:- SUBJECTIVE OBJECTIVE (labour attitudes) eg: costs INTANGIBLE TANGIBLE INCOMMENSURATE UNITS
  • 12.  A decision matrix approach with proper evaluation of weights of factors. Normalization of scores can help in ranking alternative locations.  (THIS IS DEMONSTRATEDTHROUGH A CASE STUDY)
  • 13. MULTI PLANT OPERATION-AN EXAMPLE OF PLANT ADDITION P1 existing plant P2 existing plant A,B,C,D,E- ware houses X,Y,Z-possible locations for new plant P1 P2 A B C D E X Z Y
  • 14.  Owing to increase of weekly demand to 72000 there is a capacity deficit of 25000 per week and it is felt that a plant of capacity 25000 could be set up X, Y or Z
  • 15. DATA SHEET P1 P2 X Y Z Weekly Forecast of market demand A 0.42 0.32 0.44 0.44 0.41 10000 B C D E CAPACITY UNIT PROD
  • 16. OPTIMUM PRODUCTION- DISTRIBUTING SOLUTIONS Product cost= 192500 Distn cost=26450 Total=218950 P1 P2 X A 10 10 B 8 7 15 C 16 16 D 19 19 E 10 2 12 27 20 25 72
  • 17. OPTIMUM PRODUCTION- DISTRIBUTING SOLUTIONS Product cost= 193750 Distn cost=26960 Total=220710 P1 P2 Y A 10 10 B 15 15 C 8 8 16 D 19 19 E 10 2 12 27 20 25 72
  • 18. OPTIMUM PRODUCTION-DISTRIBUTING SOLUTIONS Product cost= 192000 Distn cost=26400 Total=218400 Hence choose plant at site Z(since Z cost is minimum) P1 P2 Z A 10 10 B 15 15 C 10 6 16 D 12 7 19 E 12 12 27 20 25 72
  • 19. LOCATIONAL DYNAMICS  Suppose third plant is set up at site z  After some time demand drops from 72000 to 56000 per week.  Which plant to shut down?  Which plant to run at partial capacity? (these are location decisions)
  • 20. ALTERNATIVES FOR INVESTIGATION  1. Run all plants at partial capacity  2.shut down P1 .use overtime in others  3. shut down P2. use overtime in others  4. shut down Z. use overtime in others.
  • 21. PROBLEM DATA:- ware house demands A-9000, B-13000, C-11000, D-15000, E-8000 PLANTS P1 P2 Z Over time production cost 3.37 3.33 3.27 O.T capacity 7000 5000 6000 Fixed costs (per week) (Don’t depend on production volume) While operating 12000 9000 13000 While shut down 5000 4000 6000
  • 22. EVALUATING SHUT DOWN OPTIONS P1 P2 Z A 9 9 B 13 13 C 11 11 D 14 1 15 E 8 8 F 11 5 16 27 20 25 72
  • 23. EVALUATING SHUT DOWN OPTIONS P2 Z OT2 OTz A 9 9 B 8 5 13 C 11 11 D 9 6 15 E 8 8 20 25 56
  • 24. EVALUATING SHUT DOWN OPTIONS P1 Z OT1 OTz A 6 3 9 B 13 13 C 11 11 D 14 1 15 E 8 8 F 7 2 27 25 7 6 65
  • 25. EVALUATING SHUT DOWN OPTIONS P1 p2 OT1 OT2 A 9 9 B 9 4 13 C 3 8 11 D 15 15 E 3 5 8 F 3 3 27 20 7 5 65
  • 26. EVALUATING SHUT DOWN OPTIONS Min cost for alternative 3 . Hence shut down plant 3 1 2 3 4 FIXED VARIABLE 34000 169650 27000 177730 29000 173750 27000 178400 TOTAL COST 203650 204730 202150 205400
  • 27. summary  The strategic importance of location decisions  Hierarchy of location decisions  Analogue model for facility location  Important factors in plant location  A case study on new plant location and shut down under dynamic conditions.