Seven Basic Steps to
Build Realistic Schedule
    in Project 2010

         B Sai Prasad
  PMP, PMI-SP, MCTS Project 2007,
        MCTS Project 2010
        www.sainivas.com
“Microsoft Project is the enhanced
   version of Microsoft Excel”
               Anonymous




          Seven Steps To Success - Microsoft Project   2
Takeaways
• Forecast scheduling with Project 2010
  1. Realistic
  2. Dynamic
  3. Presentable




                   Seven Steps To Success - Microsoft Project   3
Seven Steps To Success
1.   Enter project information
2.   Create work breakdown structure
3.   Sequence tasks
4.   Estimate resources
5.   Optimize schedule
6.   Baseline schedule
7.   Record Progress

                 Seven Steps To Success - Microsoft Project   4
Step 1: Enter Project Information
Set the project start date
   Don’t: Type project start date in Gantt Chart view.
   Do: Set Project Information in Project ribbon
Set working time, holidays
   Don’t: Change Calendar settings in Options dialog
   Do: Use Change Working time in Project ribbon




                  Seven Steps To Success - Microsoft Project   5
Step 2: Create work breakdown
                structure
 Display project objective and estimates
   Don’t: Insert summary task in Gantt Chart
   Do: Show Project Summary task using Format ribbon
 Add deliverables and detail tasks
   Don’t: Auto schedule tasks, combine tasks into one
   Do: Manually schedule tasks, insert tasks using Task
    ribbon
 Check WBS granularity
   Don’t: Expand/collapse the summary tasks
   Do: Use Outline button in View ribbon
                  Seven Steps To Success - Microsoft Project   6
Step 3: Sequence tasks
 Set dependencies
   Don’t: Enter the task dates, drag the task bar
   Do: Set dependencies using Task forms
 Validate network
   Don’t: Use Gantt Chart view
   Do: Use Task forms, Network diagram in Task ribbon
 Compare top-down and bottom-up estimates
   Don’t: Set constraints on low-level tasks
   Do: Manually schedule summary tasks, auto schedule
    detail tasks
                   Seven Steps To Success - Microsoft Project   7
Step 4: Estimate resources
 Add resource details
   Don’t: Type resource name in Gantt Chart
   Do: Use Resource Sheet in Resource ribbon
 Assign resources
   Don’t: Select resource name in Gantt Chart
   Do: Use Assign Resources, Team planner in Resource
    ribbon
 Fix task duration or work or resource assignment
   Don’t: Change the work or duration
   Do: Use the task type to control the behavior
                  Seven Steps To Success - Microsoft Project   8
Step 5: Optimize schedule
Identify critical path
   Don’t: Have broken critical path
   Do: Check slack, critical path using Format ribbon
Level resources
   Don’t: Use Gantt chart view
   Do: Use Resource Usage, Team planner in
    Resource ribbon



                 Seven Steps To Success - Microsoft Project   9
Step 6: Baseline schedule
Set baseline
   Don’t: Copy the file (or) fields to custom fields
   Do: Set Baseline using Project ribbon
View baseline
   Don’t: Insert columns in view
   Do: Use Baseline table, Show baseline bar using
    Format ribbon



                  Seven Steps To Success - Microsoft Project   10
Step 7: Record progress
 Record actual
   Don’t: Use the Entry table for recording actual
   Do: Use the Tracking table with % complete in Task
    ribbon
 Slippage
   Don’t: Write formula to calculate variance
   Do: Use Slippage of Format ribbon, Variance table
 Report progress
   Don’t: Use the standard reports, copy picture
   Do: Print views, copy timeline view
                  Seven Steps To Success - Microsoft Project   11
Seven Steps To Success
1.   Enter Project Information
2.   Create Work breakdown structure
3.   Sequence tasks
4.   Estimate resources
5.   Optimize schedule
6.   Baseline schedule
7.   Record Progress

                 Seven Steps To Success - Microsoft Project   12
Thank you

Email: sai@sainivas.com
Web: www.sainivas.com



    Seven Steps To Success - Microsoft Project   13

More Related Content

What's hot

Task Tracking in SharePoint
Task Tracking in SharePointTask Tracking in SharePoint
Task Tracking in SharePointBrightWork
 
MS Project 2010 Getting Started
MS Project 2010 Getting StartedMS Project 2010 Getting Started
MS Project 2010 Getting Startedmsprojectpros
 
Understanding Microsoft Project 'Calendars' ‘Working Time’, etc
Understanding Microsoft Project 'Calendars' ‘Working Time’, etcUnderstanding Microsoft Project 'Calendars' ‘Working Time’, etc
Understanding Microsoft Project 'Calendars' ‘Working Time’, etcKhalid Noor Mohammed
 
MICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIALMICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIALVismay Shah
 
Ms project 2016 overview
Ms project 2016 overviewMs project 2016 overview
Ms project 2016 overviewMaher Almohamad
 
MS Project 2016
MS Project 2016MS Project 2016
MS Project 2016Tuan Yang
 
Ms project training ppt
Ms project training pptMs project training ppt
Ms project training pptglobalp7
 
How to Create S-Curve by MS Project 2010
How to Create S-Curve by MS Project 2010How to Create S-Curve by MS Project 2010
How to Create S-Curve by MS Project 2010Ong-Art Sanpinit
 
Www.7aramy kotob.tk-planning.scheduling.using.primavera
Www.7aramy kotob.tk-planning.scheduling.using.primaveraWww.7aramy kotob.tk-planning.scheduling.using.primavera
Www.7aramy kotob.tk-planning.scheduling.using.primaveraYasser Nassr
 
Ms Project 2010 Application For PMP
Ms Project 2010 Application For PMPMs Project 2010 Application For PMP
Ms Project 2010 Application For PMPAndy Pham, PMP
 
Ms project management
Ms  project managementMs  project management
Ms project managementchinunki4
 
44259126 ms-project-presentation
44259126 ms-project-presentation44259126 ms-project-presentation
44259126 ms-project-presentationFarrukh Raja
 
Microsoft project calender
Microsoft project calenderMicrosoft project calender
Microsoft project calenderMaheep Gupta
 
Initialization microsoft project 2010
Initialization microsoft project  2010Initialization microsoft project  2010
Initialization microsoft project 2010Wipro
 
Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project WorkshopEder Alves
 
MPUG Webinar - Creating a Portfolio KPI Report in Project Online
MPUG Webinar - Creating a Portfolio KPI Report in Project OnlineMPUG Webinar - Creating a Portfolio KPI Report in Project Online
MPUG Webinar - Creating a Portfolio KPI Report in Project OnlineRaphael Santos
 

What's hot (20)

Microsot project basics
Microsot project basicsMicrosot project basics
Microsot project basics
 
Task Tracking in SharePoint
Task Tracking in SharePointTask Tracking in SharePoint
Task Tracking in SharePoint
 
MS Project 2010 Getting Started
MS Project 2010 Getting StartedMS Project 2010 Getting Started
MS Project 2010 Getting Started
 
SharePoint - Stay on Track
SharePoint - Stay on TrackSharePoint - Stay on Track
SharePoint - Stay on Track
 
Understanding Microsoft Project 'Calendars' ‘Working Time’, etc
Understanding Microsoft Project 'Calendars' ‘Working Time’, etcUnderstanding Microsoft Project 'Calendars' ‘Working Time’, etc
Understanding Microsoft Project 'Calendars' ‘Working Time’, etc
 
MICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIALMICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIAL
 
Ms project 2016 overview
Ms project 2016 overviewMs project 2016 overview
Ms project 2016 overview
 
MS Project 2016
MS Project 2016MS Project 2016
MS Project 2016
 
Ms project training ppt
Ms project training pptMs project training ppt
Ms project training ppt
 
How to Create S-Curve by MS Project 2010
How to Create S-Curve by MS Project 2010How to Create S-Curve by MS Project 2010
How to Create S-Curve by MS Project 2010
 
Ms Project 2010
Ms Project 2010Ms Project 2010
Ms Project 2010
 
Www.7aramy kotob.tk-planning.scheduling.using.primavera
Www.7aramy kotob.tk-planning.scheduling.using.primaveraWww.7aramy kotob.tk-planning.scheduling.using.primavera
Www.7aramy kotob.tk-planning.scheduling.using.primavera
 
4 - Updating Task Progress
4 - Updating Task Progress4 - Updating Task Progress
4 - Updating Task Progress
 
Ms Project 2010 Application For PMP
Ms Project 2010 Application For PMPMs Project 2010 Application For PMP
Ms Project 2010 Application For PMP
 
Ms project management
Ms  project managementMs  project management
Ms project management
 
44259126 ms-project-presentation
44259126 ms-project-presentation44259126 ms-project-presentation
44259126 ms-project-presentation
 
Microsoft project calender
Microsoft project calenderMicrosoft project calender
Microsoft project calender
 
Initialization microsoft project 2010
Initialization microsoft project  2010Initialization microsoft project  2010
Initialization microsoft project 2010
 
Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project Workshop
 
MPUG Webinar - Creating a Portfolio KPI Report in Project Online
MPUG Webinar - Creating a Portfolio KPI Report in Project OnlineMPUG Webinar - Creating a Portfolio KPI Report in Project Online
MPUG Webinar - Creating a Portfolio KPI Report in Project Online
 

Similar to Seven Basic Steps to Build Realistic Schedule in Project 2010

Homework 8.docxHomework 8 (50 Points)AssignmentWrite .docx
Homework 8.docxHomework 8 (50 Points)AssignmentWrite .docxHomework 8.docxHomework 8 (50 Points)AssignmentWrite .docx
Homework 8.docxHomework 8 (50 Points)AssignmentWrite .docxadampcarr67227
 
No matter how hard we try, planning is not perfect, and sometimes .docx
No matter how hard we try, planning is not perfect, and sometimes .docxNo matter how hard we try, planning is not perfect, and sometimes .docx
No matter how hard we try, planning is not perfect, and sometimes .docxhenrymartin15260
 
PRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptxPRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptxGracePentinio1
 
5927 ms office project 2007 - managing projects
5927   ms office project 2007 - managing projects5927   ms office project 2007 - managing projects
5927 ms office project 2007 - managing projectsbestip
 
Tableau Course Content.docx
Tableau Course Content.docxTableau Course Content.docx
Tableau Course Content.docxLeotrainings
 
Quick and Easy Guide to Planning & Scheduling with Microsoft Project
Quick and Easy Guide to Planning & Scheduling with Microsoft ProjectQuick and Easy Guide to Planning & Scheduling with Microsoft Project
Quick and Easy Guide to Planning & Scheduling with Microsoft ProjectDeepak Alse
 
Lecture 05 project_time_and_schedule_management
Lecture 05 project_time_and_schedule_managementLecture 05 project_time_and_schedule_management
Lecture 05 project_time_and_schedule_managementSayed Ahmed
 
Project management
Project managementProject management
Project managementnethisip13
 
Initial Project Meeting Agenda PowerPoint Presentation Slides
Initial Project Meeting Agenda PowerPoint Presentation Slides Initial Project Meeting Agenda PowerPoint Presentation Slides
Initial Project Meeting Agenda PowerPoint Presentation Slides SlideTeam
 
Mgt 402 Success Begins / snaptutorial.com
Mgt 402  Success Begins / snaptutorial.comMgt 402  Success Begins / snaptutorial.com
Mgt 402 Success Begins / snaptutorial.comWilliamsTaylor33
 
Ga 09 G2 Charles Tatum Portfolio
Ga 09 G2 Charles Tatum PortfolioGa 09 G2 Charles Tatum Portfolio
Ga 09 G2 Charles Tatum PortfolioCtatum
 
Easily Create your Project WBS in MS-Excel with Simple Forward Scheduling usi...
Easily Create your Project WBS in MS-Excel with Simple Forward Scheduling usi...Easily Create your Project WBS in MS-Excel with Simple Forward Scheduling usi...
Easily Create your Project WBS in MS-Excel with Simple Forward Scheduling usi...Project Partners LLC
 
TaskYou are required to prepare for this Assessment Item by.docx
TaskYou are required to prepare for this Assessment Item by.docxTaskYou are required to prepare for this Assessment Item by.docx
TaskYou are required to prepare for this Assessment Item by.docxerlindaw
 
Web design process client presentation
Web design process client presentationWeb design process client presentation
Web design process client presentationTroy Philis
 
Using the-one-page-project-manager-1233449659402110-1
Using the-one-page-project-manager-1233449659402110-1Using the-one-page-project-manager-1233449659402110-1
Using the-one-page-project-manager-1233449659402110-1Nguyen Huy Toan
 
ASAP_Business_One___Project_Kickoff_Presentation.ppt.pdf
ASAP_Business_One___Project_Kickoff_Presentation.ppt.pdfASAP_Business_One___Project_Kickoff_Presentation.ppt.pdf
ASAP_Business_One___Project_Kickoff_Presentation.ppt.pdfJoewelDRamirez
 

Similar to Seven Basic Steps to Build Realistic Schedule in Project 2010 (20)

Homework 8.docxHomework 8 (50 Points)AssignmentWrite .docx
Homework 8.docxHomework 8 (50 Points)AssignmentWrite .docxHomework 8.docxHomework 8 (50 Points)AssignmentWrite .docx
Homework 8.docxHomework 8 (50 Points)AssignmentWrite .docx
 
No matter how hard we try, planning is not perfect, and sometimes .docx
No matter how hard we try, planning is not perfect, and sometimes .docxNo matter how hard we try, planning is not perfect, and sometimes .docx
No matter how hard we try, planning is not perfect, and sometimes .docx
 
PRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptxPRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptx
 
5927 ms office project 2007 - managing projects
5927   ms office project 2007 - managing projects5927   ms office project 2007 - managing projects
5927 ms office project 2007 - managing projects
 
WBS PROJECT
WBS PROJECTWBS PROJECT
WBS PROJECT
 
Tableau Course Content.docx
Tableau Course Content.docxTableau Course Content.docx
Tableau Course Content.docx
 
Quick and Easy Guide to Planning & Scheduling with Microsoft Project
Quick and Easy Guide to Planning & Scheduling with Microsoft ProjectQuick and Easy Guide to Planning & Scheduling with Microsoft Project
Quick and Easy Guide to Planning & Scheduling with Microsoft Project
 
Lecture 05 project_time_and_schedule_management
Lecture 05 project_time_and_schedule_managementLecture 05 project_time_and_schedule_management
Lecture 05 project_time_and_schedule_management
 
Project management
Project managementProject management
Project management
 
Initial Project Meeting Agenda PowerPoint Presentation Slides
Initial Project Meeting Agenda PowerPoint Presentation Slides Initial Project Meeting Agenda PowerPoint Presentation Slides
Initial Project Meeting Agenda PowerPoint Presentation Slides
 
Mgt 402 Success Begins / snaptutorial.com
Mgt 402  Success Begins / snaptutorial.comMgt 402  Success Begins / snaptutorial.com
Mgt 402 Success Begins / snaptutorial.com
 
Ga 09 G2 Charles Tatum Portfolio
Ga 09 G2 Charles Tatum PortfolioGa 09 G2 Charles Tatum Portfolio
Ga 09 G2 Charles Tatum Portfolio
 
Activity7
Activity7Activity7
Activity7
 
Easily Create your Project WBS in MS-Excel with Simple Forward Scheduling usi...
Easily Create your Project WBS in MS-Excel with Simple Forward Scheduling usi...Easily Create your Project WBS in MS-Excel with Simple Forward Scheduling usi...
Easily Create your Project WBS in MS-Excel with Simple Forward Scheduling usi...
 
TaskYou are required to prepare for this Assessment Item by.docx
TaskYou are required to prepare for this Assessment Item by.docxTaskYou are required to prepare for this Assessment Item by.docx
TaskYou are required to prepare for this Assessment Item by.docx
 
Web design process client presentation
Web design process client presentationWeb design process client presentation
Web design process client presentation
 
9505 (1).doc
9505 (1).doc9505 (1).doc
9505 (1).doc
 
Using The One Page Project Manager
Using The One Page Project ManagerUsing The One Page Project Manager
Using The One Page Project Manager
 
Using the-one-page-project-manager-1233449659402110-1
Using the-one-page-project-manager-1233449659402110-1Using the-one-page-project-manager-1233449659402110-1
Using the-one-page-project-manager-1233449659402110-1
 
ASAP_Business_One___Project_Kickoff_Presentation.ppt.pdf
ASAP_Business_One___Project_Kickoff_Presentation.ppt.pdfASAP_Business_One___Project_Kickoff_Presentation.ppt.pdf
ASAP_Business_One___Project_Kickoff_Presentation.ppt.pdf
 

Recently uploaded

In-Depth Performance Testing Guide for IT Professionals
In-Depth Performance Testing Guide for IT ProfessionalsIn-Depth Performance Testing Guide for IT Professionals
In-Depth Performance Testing Guide for IT ProfessionalsExpeed Software
 
The architecture of Generative AI for enterprises.pdf
The architecture of Generative AI for enterprises.pdfThe architecture of Generative AI for enterprises.pdf
The architecture of Generative AI for enterprises.pdfalexjohnson7307
 
Measures in SQL (a talk at SF Distributed Systems meetup, 2024-05-22)
Measures in SQL (a talk at SF Distributed Systems meetup, 2024-05-22)Measures in SQL (a talk at SF Distributed Systems meetup, 2024-05-22)
Measures in SQL (a talk at SF Distributed Systems meetup, 2024-05-22)Julian Hyde
 
Introduction to Open Source RAG and RAG Evaluation
Introduction to Open Source RAG and RAG EvaluationIntroduction to Open Source RAG and RAG Evaluation
Introduction to Open Source RAG and RAG EvaluationZilliz
 
Transforming The New York Times: Empowering Evolution through UX
Transforming The New York Times: Empowering Evolution through UXTransforming The New York Times: Empowering Evolution through UX
Transforming The New York Times: Empowering Evolution through UXUXDXConf
 
Strategic AI Integration in Engineering Teams
Strategic AI Integration in Engineering TeamsStrategic AI Integration in Engineering Teams
Strategic AI Integration in Engineering TeamsUXDXConf
 
Powerful Start- the Key to Project Success, Barbara Laskowska
Powerful Start- the Key to Project Success, Barbara LaskowskaPowerful Start- the Key to Project Success, Barbara Laskowska
Powerful Start- the Key to Project Success, Barbara LaskowskaCzechDreamin
 
Behind the Scenes From the Manager's Chair: Decoding the Secrets of Successfu...
Behind the Scenes From the Manager's Chair: Decoding the Secrets of Successfu...Behind the Scenes From the Manager's Chair: Decoding the Secrets of Successfu...
Behind the Scenes From the Manager's Chair: Decoding the Secrets of Successfu...CzechDreamin
 
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...Jeffrey Haguewood
 
"Impact of front-end architecture on development cost", Viktor Turskyi
"Impact of front-end architecture on development cost", Viktor Turskyi"Impact of front-end architecture on development cost", Viktor Turskyi
"Impact of front-end architecture on development cost", Viktor TurskyiFwdays
 
Optimizing NoSQL Performance Through Observability
Optimizing NoSQL Performance Through ObservabilityOptimizing NoSQL Performance Through Observability
Optimizing NoSQL Performance Through ObservabilityScyllaDB
 
Motion for AI: Creating Empathy in Technology
Motion for AI: Creating Empathy in TechnologyMotion for AI: Creating Empathy in Technology
Motion for AI: Creating Empathy in TechnologyUXDXConf
 
ECS 2024 Teams Premium - Pretty Secure
ECS 2024   Teams Premium - Pretty SecureECS 2024   Teams Premium - Pretty Secure
ECS 2024 Teams Premium - Pretty SecureFemke de Vroome
 
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMsTo Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMsPaul Groth
 
A Business-Centric Approach to Design System Strategy
A Business-Centric Approach to Design System StrategyA Business-Centric Approach to Design System Strategy
A Business-Centric Approach to Design System StrategyUXDXConf
 
Server-Driven User Interface (SDUI) at Priceline
Server-Driven User Interface (SDUI) at PricelineServer-Driven User Interface (SDUI) at Priceline
Server-Driven User Interface (SDUI) at PricelineUXDXConf
 
Integrating Telephony Systems with Salesforce: Insights and Considerations, B...
Integrating Telephony Systems with Salesforce: Insights and Considerations, B...Integrating Telephony Systems with Salesforce: Insights and Considerations, B...
Integrating Telephony Systems with Salesforce: Insights and Considerations, B...CzechDreamin
 
Enterprise Security Monitoring, And Log Management.
Enterprise Security Monitoring, And Log Management.Enterprise Security Monitoring, And Log Management.
Enterprise Security Monitoring, And Log Management.Boni Yeamin
 
UiPath Test Automation using UiPath Test Suite series, part 2
UiPath Test Automation using UiPath Test Suite series, part 2UiPath Test Automation using UiPath Test Suite series, part 2
UiPath Test Automation using UiPath Test Suite series, part 2DianaGray10
 
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered QualitySoftware Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered QualityInflectra
 

Recently uploaded (20)

In-Depth Performance Testing Guide for IT Professionals
In-Depth Performance Testing Guide for IT ProfessionalsIn-Depth Performance Testing Guide for IT Professionals
In-Depth Performance Testing Guide for IT Professionals
 
The architecture of Generative AI for enterprises.pdf
The architecture of Generative AI for enterprises.pdfThe architecture of Generative AI for enterprises.pdf
The architecture of Generative AI for enterprises.pdf
 
Measures in SQL (a talk at SF Distributed Systems meetup, 2024-05-22)
Measures in SQL (a talk at SF Distributed Systems meetup, 2024-05-22)Measures in SQL (a talk at SF Distributed Systems meetup, 2024-05-22)
Measures in SQL (a talk at SF Distributed Systems meetup, 2024-05-22)
 
Introduction to Open Source RAG and RAG Evaluation
Introduction to Open Source RAG and RAG EvaluationIntroduction to Open Source RAG and RAG Evaluation
Introduction to Open Source RAG and RAG Evaluation
 
Transforming The New York Times: Empowering Evolution through UX
Transforming The New York Times: Empowering Evolution through UXTransforming The New York Times: Empowering Evolution through UX
Transforming The New York Times: Empowering Evolution through UX
 
Strategic AI Integration in Engineering Teams
Strategic AI Integration in Engineering TeamsStrategic AI Integration in Engineering Teams
Strategic AI Integration in Engineering Teams
 
Powerful Start- the Key to Project Success, Barbara Laskowska
Powerful Start- the Key to Project Success, Barbara LaskowskaPowerful Start- the Key to Project Success, Barbara Laskowska
Powerful Start- the Key to Project Success, Barbara Laskowska
 
Behind the Scenes From the Manager's Chair: Decoding the Secrets of Successfu...
Behind the Scenes From the Manager's Chair: Decoding the Secrets of Successfu...Behind the Scenes From the Manager's Chair: Decoding the Secrets of Successfu...
Behind the Scenes From the Manager's Chair: Decoding the Secrets of Successfu...
 
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
 
"Impact of front-end architecture on development cost", Viktor Turskyi
"Impact of front-end architecture on development cost", Viktor Turskyi"Impact of front-end architecture on development cost", Viktor Turskyi
"Impact of front-end architecture on development cost", Viktor Turskyi
 
Optimizing NoSQL Performance Through Observability
Optimizing NoSQL Performance Through ObservabilityOptimizing NoSQL Performance Through Observability
Optimizing NoSQL Performance Through Observability
 
Motion for AI: Creating Empathy in Technology
Motion for AI: Creating Empathy in TechnologyMotion for AI: Creating Empathy in Technology
Motion for AI: Creating Empathy in Technology
 
ECS 2024 Teams Premium - Pretty Secure
ECS 2024   Teams Premium - Pretty SecureECS 2024   Teams Premium - Pretty Secure
ECS 2024 Teams Premium - Pretty Secure
 
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMsTo Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
 
A Business-Centric Approach to Design System Strategy
A Business-Centric Approach to Design System StrategyA Business-Centric Approach to Design System Strategy
A Business-Centric Approach to Design System Strategy
 
Server-Driven User Interface (SDUI) at Priceline
Server-Driven User Interface (SDUI) at PricelineServer-Driven User Interface (SDUI) at Priceline
Server-Driven User Interface (SDUI) at Priceline
 
Integrating Telephony Systems with Salesforce: Insights and Considerations, B...
Integrating Telephony Systems with Salesforce: Insights and Considerations, B...Integrating Telephony Systems with Salesforce: Insights and Considerations, B...
Integrating Telephony Systems with Salesforce: Insights and Considerations, B...
 
Enterprise Security Monitoring, And Log Management.
Enterprise Security Monitoring, And Log Management.Enterprise Security Monitoring, And Log Management.
Enterprise Security Monitoring, And Log Management.
 
UiPath Test Automation using UiPath Test Suite series, part 2
UiPath Test Automation using UiPath Test Suite series, part 2UiPath Test Automation using UiPath Test Suite series, part 2
UiPath Test Automation using UiPath Test Suite series, part 2
 
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered QualitySoftware Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
 

Seven Basic Steps to Build Realistic Schedule in Project 2010

  • 1. Seven Basic Steps to Build Realistic Schedule in Project 2010 B Sai Prasad PMP, PMI-SP, MCTS Project 2007, MCTS Project 2010 www.sainivas.com
  • 2. “Microsoft Project is the enhanced version of Microsoft Excel” Anonymous Seven Steps To Success - Microsoft Project 2
  • 3. Takeaways • Forecast scheduling with Project 2010 1. Realistic 2. Dynamic 3. Presentable Seven Steps To Success - Microsoft Project 3
  • 4. Seven Steps To Success 1. Enter project information 2. Create work breakdown structure 3. Sequence tasks 4. Estimate resources 5. Optimize schedule 6. Baseline schedule 7. Record Progress Seven Steps To Success - Microsoft Project 4
  • 5. Step 1: Enter Project Information Set the project start date  Don’t: Type project start date in Gantt Chart view.  Do: Set Project Information in Project ribbon Set working time, holidays  Don’t: Change Calendar settings in Options dialog  Do: Use Change Working time in Project ribbon Seven Steps To Success - Microsoft Project 5
  • 6. Step 2: Create work breakdown structure  Display project objective and estimates  Don’t: Insert summary task in Gantt Chart  Do: Show Project Summary task using Format ribbon  Add deliverables and detail tasks  Don’t: Auto schedule tasks, combine tasks into one  Do: Manually schedule tasks, insert tasks using Task ribbon  Check WBS granularity  Don’t: Expand/collapse the summary tasks  Do: Use Outline button in View ribbon Seven Steps To Success - Microsoft Project 6
  • 7. Step 3: Sequence tasks  Set dependencies  Don’t: Enter the task dates, drag the task bar  Do: Set dependencies using Task forms  Validate network  Don’t: Use Gantt Chart view  Do: Use Task forms, Network diagram in Task ribbon  Compare top-down and bottom-up estimates  Don’t: Set constraints on low-level tasks  Do: Manually schedule summary tasks, auto schedule detail tasks Seven Steps To Success - Microsoft Project 7
  • 8. Step 4: Estimate resources  Add resource details  Don’t: Type resource name in Gantt Chart  Do: Use Resource Sheet in Resource ribbon  Assign resources  Don’t: Select resource name in Gantt Chart  Do: Use Assign Resources, Team planner in Resource ribbon  Fix task duration or work or resource assignment  Don’t: Change the work or duration  Do: Use the task type to control the behavior Seven Steps To Success - Microsoft Project 8
  • 9. Step 5: Optimize schedule Identify critical path  Don’t: Have broken critical path  Do: Check slack, critical path using Format ribbon Level resources  Don’t: Use Gantt chart view  Do: Use Resource Usage, Team planner in Resource ribbon Seven Steps To Success - Microsoft Project 9
  • 10. Step 6: Baseline schedule Set baseline  Don’t: Copy the file (or) fields to custom fields  Do: Set Baseline using Project ribbon View baseline  Don’t: Insert columns in view  Do: Use Baseline table, Show baseline bar using Format ribbon Seven Steps To Success - Microsoft Project 10
  • 11. Step 7: Record progress  Record actual  Don’t: Use the Entry table for recording actual  Do: Use the Tracking table with % complete in Task ribbon  Slippage  Don’t: Write formula to calculate variance  Do: Use Slippage of Format ribbon, Variance table  Report progress  Don’t: Use the standard reports, copy picture  Do: Print views, copy timeline view Seven Steps To Success - Microsoft Project 11
  • 12. Seven Steps To Success 1. Enter Project Information 2. Create Work breakdown structure 3. Sequence tasks 4. Estimate resources 5. Optimize schedule 6. Baseline schedule 7. Record Progress Seven Steps To Success - Microsoft Project 12
  • 13. Thank you Email: sai@sainivas.com Web: www.sainivas.com Seven Steps To Success - Microsoft Project 13