Taco Company observed variable utility costs at different activity levels. The lowest activity level was 12,000 machine hours at a total cost of $7,200, while the highest level was 20,000 machine hours costing $10,400 total. Using the formula that the change in total cost divided by the change in activity level equals the variable cost per unit, the document calculates the variable utility cost per machine hour is $0.40.