SlideShare a Scribd company logo
1 of 19
Primary Sedimentation
Dr. Akepati S. Reddy
School of Energy and Environment
Thapar University, Patiala
PUNJAB, INDIA
Flocculent Particle Settling
• Particles do not settle as discrete particles – instead during
sedimentation they coalesce and flocculate
• Extent of coalescence or flocculation depend on
– Overflow rate
– Depth of settling basin
– Velocity gradients in the system
– Concentration of particles
– Range of particle sizes
• Settling characteristics of a suspension of flocculent particles
can be obtained by a settling column test
• Settling column
– Height: equal to the depth of the proposed settling tank
– Diameter can be anything – influences of the wall should be
taken care off – sample required should be small enough
– Provided with sampling ports
• Settling column test
– To begin with ensure uniform distribution of particle size from
top to bottom of the column
– Duration of test should be equal to the settling time in the
proposed tank
– Draw samples from the ports at various time intervals, analyze
for TSS and compute % removal
– Plot % removal against time and depth and construct curves of
equal % removal
– Overflow rates for various settling are determined by noting
where the curve intersect the x-axis
Flocculent Particle Settling





 





 
 


2
(%) 1
1
nn
n
h
n RR
H
h
R
Settling Column Settling Profile Graph
Primary Sedimentation Tank
• Purpose is removal of readily settleable solids and floating
material from wastewater
• Usually give 50-70% suspended solids removal efficiency and
25-40% BOD removal (for municipal sewage)
• Rectangular or circular sedimentation tanks are used
– Two or more cylindrical or rectangular sedimentation tanks may
be used for allowing maintenance and repair
– Multiple rectangular tanks require less land area than multiple
circular tanks and common walls reduce construction cost
• Sedimentation tanks should include
– Inlet section and Outlet section
– Facilities and provisions for the settled sludge scrapping,
collection and removal
– Facilities and provisions for the floating material entrapment,
skimming, collection and removal
• Sedimentation tank can be considered to include Settling
zone and Sludge zone
Flow pattern is radial with central feed arrangement
• Has a center well of 15-20% of the tank diameter and 1.0 to 2.5 m
depth is used
• Center well has a tangential energy dissipating inlet
• wastewater is discharged into the well within the upper 0.5-0.7 m
at 0.3 to 0.45 m/sec flow velocity
Solids removal mechanisms
• Smaller tanks have hopper bottom with >45 inclination with the
horizontal
• 3.6-9.0 m diameter tanks have solids removal equipment supported
on beams spanning the tank
• Larger diameter tanks have a central pier supporting the
mechanism and is reached by a walkway or bridge
• Bottom of the tank is sloped at 1 in 12 to 64 or lesser
• Solids are scrapped to the center and removed
Clarified liquid is skimmed off over weirs into a collection trough
Circular Primary Sedimentation Tank
Clarified sewage
Collection trough
Scum retaining baffle
Distribution baffle
of central well
Scrapper arm
Skimmer bladeCentral well
Central pier
Influent pipe Sludge draw-off pipe
Central rotating
equipment
Sludge trough
Tangential openings in the pier
for the distribution of the influent
Slope 1 in 12
Side wall
of clarifier
0.5m
0.3m
0.3m
0.3m
0.6m Central pier Sludge trough
0.5 m
1.5 m
0.5 m
Sludge draw-off pipe
Influent pipe
Primary clarifier
Section to show side wall with
clarified sewage collection trough Bottom sludge trough and outlet
3.0 m
Inlet
• Full width inlet channels with inlet weirs – can introduce vertical
velocity component spreading into the sludge hoppers (provided at
the inlet end)
• Inlets with submerged ports/orifices (velocities in the ports/orifices
are in the range of 3-9 m/min.)
• Inlet channels with wide gates and slotted baffles
• Inlet baffles can be used to reduce high initial velocities and
distribute flow width wise – usually extend from 150 mm below and
300 mm above the water surface
Outlet
• Clarified effluent is collected into a collection trough through an
overflow weir
• Floating material or settled suspended solids should not be washed
out with the clarified effluent
• Floating material retaining or entrapping baffle is provided
• Weir length is designed to avoid washout out of sludge
Rectangular
Primary Sedimentation Tanks
Facilities and provisions for the settled sludge scrapping,
collection and removal
• Settled sludge is collected at the inlet end
• Chain and flight solids collectors
– Have a pair of endless conveyor chains
– Scraper flights of wood or fiberglass, running full width of the
tank and attached to the chains at 3 m interval
– The settled solids are scrapped
• to solids hoppers In case of small tanks – multiple hoppers are
used in larger tanks
• to a transverse trough in case of large tanks - troughs in turn have
cross collectors
Rectangular
Primary Sedimentation Tank
Traveling bridge type collectors
– Travel up and down the tank on rubber wheels or on rails
supported on the sidewalls
– Scrapper blades are suspended from the bridge (returning
scraper blades lifted free of the solids blanket)
Facilities and provisions for floating material entrapment,
skimming, collection and removal
• Floating scum is collected at the effluent end
• Floating scum is skimmed and carried to the effluent end and
entrapped for avoiding overflow into the clarified effluent trough
– Flights returning at the liquid surface can be used
– Water showers can be used to push forward the floating scum
– Baffle is provided in front of the overflow weir for the scum
entrapment until removed
Rectangular
Primary Sedimentation Tank
• In small tanks scum draw-down facility consisting of a
horizontal, slotted pipe that can be rotated by a lever or screw
can be used
– Limitation - creates large volume of scum liquor
• Transverse rotating helical wiper attached to a shaft can also
be used for scum removal
– Scum is removed from the water surface and moved over an
inclined apron for discharge to a cross-collecting scum trough
Other provisions and facilities
• Tanks may sloping bottom towards the influent end
• Influent end has sludge hoppers or sludge trench
• Scum pit is provided for storing the scum liquid removed
• Sludge pump, piping and tank may be there to remove the collected
sludge from the sludge hopper or trench
Rectangular
Primary Sedimentation Tank
Design of Primary Clarifier
• Overflow rate and hydraulic retention time obtained from the
settling test and settling profile diagram are used to find
surface area and depth of the clarifier
• Safety factors of 1.25 is usually used to take into account
– Inlet and outlet disturbances
– Disturbances created by the rotating mechanism to scrap the
settled sludge and to collect the floating scum
– Wind blow effects
– Temperature variations
– Flow short-circuiting
• Design also takes into account the following:
– Horizontal flow velocity (below the scour velocity)
– Weir overflow rate (below a limit to avoid density currents)
– Weir overflow balancing to avoid short-circuiting problems
– Flooding of collection trough
Detention time 1.5 to 2.5 hours (2.0 hr.)
Overflow rate
Average flow 30-50 m3/m2.day (40) – 24-32 (26)
Peak flow 80-120 m3/m2.day (100) – 48-70 (60)
Weir loading 125-500 m3/m.day (250)
Rectangular tanks
Depth 3-4.9 (4.3)
Length 15-90 (24-40)
Width 3-24 (4.9-9.8)
Flight speed 0.6-1.2 m/min (0.9)
Circular tank
Diameter 3-60 (12-45)
Bottom slope 1 in 16 to 1 in 6 (1 in 12)
Flight speed 0.02-0.05 rpm (0.03)
Primary Sedimentation Tank
Short circuiting and hydraulic stability
• Tracer studies can be used for determining short-circuiting
problems
• Method of influent flow distribution can also affect short circuiting
Temperature difference of 1C between incoming wastewater
and wastewater of the tank can cause density current
Wind blowing across the top of an open sedimentation tank can
cause circulation cell to form – this reduces effective
volumetric capacity of the tank
Surface loading rates (overflow rates)
• There can be regulations prescribing limits to surface loading rates
• Overflow rates must be set low enough to ensure satisfactory
performance at peak rates of flow
Primary Sedimentation Tank
Detention time
• Solids reaching the settling tank are susceptible to flocculation
• Flocculation is aided by eddying motion of fluid within the tank
• Level of flocculation depends on the time elapsed (detention time)
• In cold climates because of increase in water viscosity detention
time required also increases (1.38 time more HRT for 10C water
that when temperature is 20C)
Weir loading rates
• Have little effect on efficiency of primary settlign tanks
Primary sludge scum characteristics and quantities
• Factors influencing are
– Characteristics of untreated water (strength and freshness)
– Period of sedimentation
– Conditions of the deposited solids
– Period between solids removal operations
Primary Sedimentation Tank
Primary Sludge
• Primary clarifier is designed for a specified % removal of TSS
• From knowing the TSS and flow rate of the influent sewage
primary sludge generated can be quantified
• TSS of the sewage is comprised of inorganic TSS, VSS and
Biodegradable VSS
– Biodegradable VSS contributes BOD and this is 50-60% of the
total BOD for municipal sewage
• Primary clarifier through removing the Biodegradable VSS
contributes to BOD removal
– BOD removal in the primary clarifier is typically 35-45%
• If BOD removal in the primary clarifier is known, one can find
out the biodegradable fraction of the primary sludge
– BOD removal can be expressed as BODu removal and BODu
removal as TSS equivalent removal
– The fraction of biodegradable VSS in the TSS is assumed to
remain the same even in the clarified effluent
• If consistency of the primary sludge is known even volume of
the primary sludge can be calculated

More Related Content

What's hot

06 - Neutralisation, Equalisation & Proportioning.pptx
06 - Neutralisation, Equalisation & Proportioning.pptx06 - Neutralisation, Equalisation & Proportioning.pptx
06 - Neutralisation, Equalisation & Proportioning.pptxPRACHI DESSAI
 
Residuals of industrial wastewater treatment
Residuals of industrial wastewater treatmentResiduals of industrial wastewater treatment
Residuals of industrial wastewater treatmentVIJAYA SUBRAMANIAM P R
 
Wastewater engineering info
Wastewater engineering infoWastewater engineering info
Wastewater engineering infoTadviDevarshi
 
2. screen chamber
 2. screen chamber 2. screen chamber
2. screen chambervvsasane
 
Sludge thickening and stabilization processes
Sludge thickening and stabilization processes  Sludge thickening and stabilization processes
Sludge thickening and stabilization processes Natthu Shrirame
 
Lec 1 (wastewater collection system)
Lec 1 (wastewater collection system)Lec 1 (wastewater collection system)
Lec 1 (wastewater collection system)5032683
 
Unit operations; processes in waste water treatment
Unit operations; processes in waste water treatmentUnit operations; processes in waste water treatment
Unit operations; processes in waste water treatmentDuithy George
 
Activated Sludge Process
Activated Sludge ProcessActivated Sludge Process
Activated Sludge ProcessNiaz Memon
 
L 12 contaminent concentration reduction
L 12  contaminent concentration reductionL 12  contaminent concentration reduction
L 12 contaminent concentration reductionDr. shrikant jahagirdar
 
L8- Sedimentation aided with coagulation.pptx
L8- Sedimentation aided with coagulation.pptxL8- Sedimentation aided with coagulation.pptx
L8- Sedimentation aided with coagulation.pptxPRACHI DESSAI
 
L 4 characterization of industrial waste and sampling
L 4 characterization of industrial waste and samplingL 4 characterization of industrial waste and sampling
L 4 characterization of industrial waste and samplingDr. shrikant jahagirdar
 
Operation & maintenance aspects of a Water treatment plant.
Operation & maintenance aspects of a Water treatment plant.Operation & maintenance aspects of a Water treatment plant.
Operation & maintenance aspects of a Water treatment plant.Home
 
Primary waste water treatment powerpointb presntation
Primary waste water treatment powerpointb  presntationPrimary waste water treatment powerpointb  presntation
Primary waste water treatment powerpointb presntationkanchan jadon
 
Characteristics of Waste-Water (Unit-I)
Characteristics of Waste-Water (Unit-I)Characteristics of Waste-Water (Unit-I)
Characteristics of Waste-Water (Unit-I)GAURAV. H .TANDON
 

What's hot (20)

06 - Neutralisation, Equalisation & Proportioning.pptx
06 - Neutralisation, Equalisation & Proportioning.pptx06 - Neutralisation, Equalisation & Proportioning.pptx
06 - Neutralisation, Equalisation & Proportioning.pptx
 
Residuals of industrial wastewater treatment
Residuals of industrial wastewater treatmentResiduals of industrial wastewater treatment
Residuals of industrial wastewater treatment
 
Wastewater engineering info
Wastewater engineering infoWastewater engineering info
Wastewater engineering info
 
2. screen chamber
 2. screen chamber 2. screen chamber
2. screen chamber
 
Sludge thickening and stabilization processes
Sludge thickening and stabilization processes  Sludge thickening and stabilization processes
Sludge thickening and stabilization processes
 
L 8 equalization and proportioning
L  8 equalization and proportioningL  8 equalization and proportioning
L 8 equalization and proportioning
 
Lec 1 (wastewater collection system)
Lec 1 (wastewater collection system)Lec 1 (wastewater collection system)
Lec 1 (wastewater collection system)
 
Module IV Wastewater treatment methods
Module IV Wastewater treatment methodsModule IV Wastewater treatment methods
Module IV Wastewater treatment methods
 
L 17 coagulation and flocculation
L 17 coagulation and flocculationL 17 coagulation and flocculation
L 17 coagulation and flocculation
 
Unit operations; processes in waste water treatment
Unit operations; processes in waste water treatmentUnit operations; processes in waste water treatment
Unit operations; processes in waste water treatment
 
Activated Sludge Process
Activated Sludge ProcessActivated Sludge Process
Activated Sludge Process
 
L 12 contaminent concentration reduction
L 12  contaminent concentration reductionL 12  contaminent concentration reduction
L 12 contaminent concentration reduction
 
L8- Sedimentation aided with coagulation.pptx
L8- Sedimentation aided with coagulation.pptxL8- Sedimentation aided with coagulation.pptx
L8- Sedimentation aided with coagulation.pptx
 
Reverse osmosis
Reverse osmosisReverse osmosis
Reverse osmosis
 
L 4 characterization of industrial waste and sampling
L 4 characterization of industrial waste and samplingL 4 characterization of industrial waste and sampling
L 4 characterization of industrial waste and sampling
 
L 13 grit chamber
L 13 grit chamberL 13 grit chamber
L 13 grit chamber
 
Operation & maintenance aspects of a Water treatment plant.
Operation & maintenance aspects of a Water treatment plant.Operation & maintenance aspects of a Water treatment plant.
Operation & maintenance aspects of a Water treatment plant.
 
Water softening ce3
Water softening ce3Water softening ce3
Water softening ce3
 
Primary waste water treatment powerpointb presntation
Primary waste water treatment powerpointb  presntationPrimary waste water treatment powerpointb  presntation
Primary waste water treatment powerpointb presntation
 
Characteristics of Waste-Water (Unit-I)
Characteristics of Waste-Water (Unit-I)Characteristics of Waste-Water (Unit-I)
Characteristics of Waste-Water (Unit-I)
 

Viewers also liked

Sewage Treatment: Primary Treatment
Sewage Treatment: Primary TreatmentSewage Treatment: Primary Treatment
Sewage Treatment: Primary TreatmentAkepati S. Reddy
 
water treatment slides
water treatment slideswater treatment slides
water treatment slidesAnand Keshri
 
Primary and secondary wastewater treatment..
Primary and secondary wastewater treatment..Primary and secondary wastewater treatment..
Primary and secondary wastewater treatment..snehalmenon92
 
Industrial wastewater treatment
Industrial wastewater treatmentIndustrial wastewater treatment
Industrial wastewater treatmentMohamed Ramzy
 
Waste water treatment processes
Waste water treatment processesWaste water treatment processes
Waste water treatment processesAshish Agarwal
 
07 coagulation-flocculation-settling
07 coagulation-flocculation-settling07 coagulation-flocculation-settling
07 coagulation-flocculation-settlingAkepati S. Reddy
 
Wastewater treatment
Wastewater treatmentWastewater treatment
Wastewater treatmentRanjan Das
 
Simulation in Action: Fatigue Analysis on 1243 Scraper Tail
Simulation in Action: Fatigue Analysis on 1243 Scraper Tail Simulation in Action: Fatigue Analysis on 1243 Scraper Tail
Simulation in Action: Fatigue Analysis on 1243 Scraper Tail Adaptive Corporation
 
B Tech R-13 Regulation Syllabus of JNTUH 2013
B Tech R-13 Regulation Syllabus of JNTUH 2013B Tech R-13 Regulation Syllabus of JNTUH 2013
B Tech R-13 Regulation Syllabus of JNTUH 2013gouse_1210
 
Sewage Treatment and Recycle Presentation
Sewage Treatment and Recycle PresentationSewage Treatment and Recycle Presentation
Sewage Treatment and Recycle PresentationSuresh Kumar
 
Ag wastewater treatment by ag.pdf 2
Ag wastewater treatment by ag.pdf 2Ag wastewater treatment by ag.pdf 2
Ag wastewater treatment by ag.pdf 2ghildiyal8811
 
Radiation and atmospheric temperature
Radiation and atmospheric temperatureRadiation and atmospheric temperature
Radiation and atmospheric temperatureAkepati S. Reddy
 
Aerobic attached growth systems
Aerobic attached growth systemsAerobic attached growth systems
Aerobic attached growth systemsAkepati S. Reddy
 
Solid waste biomethanation plants
Solid waste biomethanation plantsSolid waste biomethanation plants
Solid waste biomethanation plantsAkepati S. Reddy
 
15 secondary sedimentation
15 secondary sedimentation15 secondary sedimentation
15 secondary sedimentationAkepati S. Reddy
 
Regulatory Requirements of Solid Waste Management, Indian Context
Regulatory Requirements of Solid Waste Management, Indian ContextRegulatory Requirements of Solid Waste Management, Indian Context
Regulatory Requirements of Solid Waste Management, Indian ContextAkepati S. Reddy
 
Biological n and p removal
Biological n and p removalBiological n and p removal
Biological n and p removalAkepati S. Reddy
 
biomass fuels and cook stoves
biomass fuels and cook stovesbiomass fuels and cook stoves
biomass fuels and cook stovesAkepati S. Reddy
 

Viewers also liked (20)

Sewage Treatment: Primary Treatment
Sewage Treatment: Primary TreatmentSewage Treatment: Primary Treatment
Sewage Treatment: Primary Treatment
 
water treatment slides
water treatment slideswater treatment slides
water treatment slides
 
Primary and secondary wastewater treatment..
Primary and secondary wastewater treatment..Primary and secondary wastewater treatment..
Primary and secondary wastewater treatment..
 
Industrial wastewater treatment
Industrial wastewater treatmentIndustrial wastewater treatment
Industrial wastewater treatment
 
Waste water treatment processes
Waste water treatment processesWaste water treatment processes
Waste water treatment processes
 
07 coagulation-flocculation-settling
07 coagulation-flocculation-settling07 coagulation-flocculation-settling
07 coagulation-flocculation-settling
 
Wastewater treatment
Wastewater treatmentWastewater treatment
Wastewater treatment
 
Simulation in Action: Fatigue Analysis on 1243 Scraper Tail
Simulation in Action: Fatigue Analysis on 1243 Scraper Tail Simulation in Action: Fatigue Analysis on 1243 Scraper Tail
Simulation in Action: Fatigue Analysis on 1243 Scraper Tail
 
B Tech R-13 Regulation Syllabus of JNTUH 2013
B Tech R-13 Regulation Syllabus of JNTUH 2013B Tech R-13 Regulation Syllabus of JNTUH 2013
B Tech R-13 Regulation Syllabus of JNTUH 2013
 
Sewage Treatment and Recycle Presentation
Sewage Treatment and Recycle PresentationSewage Treatment and Recycle Presentation
Sewage Treatment and Recycle Presentation
 
Ag wastewater treatment by ag.pdf 2
Ag wastewater treatment by ag.pdf 2Ag wastewater treatment by ag.pdf 2
Ag wastewater treatment by ag.pdf 2
 
Atmospheric Water
Atmospheric WaterAtmospheric Water
Atmospheric Water
 
Radiation and atmospheric temperature
Radiation and atmospheric temperatureRadiation and atmospheric temperature
Radiation and atmospheric temperature
 
Aerobic attached growth systems
Aerobic attached growth systemsAerobic attached growth systems
Aerobic attached growth systems
 
Solid waste biomethanation plants
Solid waste biomethanation plantsSolid waste biomethanation plants
Solid waste biomethanation plants
 
Anaerobic ponds
Anaerobic pondsAnaerobic ponds
Anaerobic ponds
 
15 secondary sedimentation
15 secondary sedimentation15 secondary sedimentation
15 secondary sedimentation
 
Regulatory Requirements of Solid Waste Management, Indian Context
Regulatory Requirements of Solid Waste Management, Indian ContextRegulatory Requirements of Solid Waste Management, Indian Context
Regulatory Requirements of Solid Waste Management, Indian Context
 
Biological n and p removal
Biological n and p removalBiological n and p removal
Biological n and p removal
 
biomass fuels and cook stoves
biomass fuels and cook stovesbiomass fuels and cook stoves
biomass fuels and cook stoves
 

Similar to Primary sedimentation

14 stokes law and grit separators
14 stokes law and grit separators14 stokes law and grit separators
14 stokes law and grit separatorsAkepati S. Reddy
 
1. Onsite sanitation system and disposal of sludge slide series (1) septic tank
1. Onsite sanitation system and disposal of sludge slide series (1) septic tank1. Onsite sanitation system and disposal of sludge slide series (1) septic tank
1. Onsite sanitation system and disposal of sludge slide series (1) septic tankvvsasane
 
UNIT -II Treatment of water- aeration and sedimentation.ppt
UNIT -II  Treatment of water- aeration and sedimentation.pptUNIT -II  Treatment of water- aeration and sedimentation.ppt
UNIT -II Treatment of water- aeration and sedimentation.pptmadhukarjadhav10
 
SEDIMENTATION
SEDIMENTATIONSEDIMENTATION
SEDIMENTATIONErika Joy
 
Treatment of water
Treatment of waterTreatment of water
Treatment of waterdhavalsshah
 
Presentation for safegard septic tank
Presentation for safegard septic tankPresentation for safegard septic tank
Presentation for safegard septic tankkalyanmaji
 
Excavation and Ground water control1.pptx
Excavation and Ground water control1.pptxExcavation and Ground water control1.pptx
Excavation and Ground water control1.pptxssusercbae26
 
Coagulation and flocculation
 Coagulation and flocculation Coagulation and flocculation
Coagulation and flocculationHarshada Vispute
 
Unit III Quality and Treatment
Unit  III Quality and TreatmentUnit  III Quality and Treatment
Unit III Quality and TreatmentMadhukarJadhav8
 
Sewage Treatment: Priliminary Treatment
Sewage Treatment: Priliminary TreatmentSewage Treatment: Priliminary Treatment
Sewage Treatment: Priliminary TreatmentAkepati S. Reddy
 

Similar to Primary sedimentation (20)

08 filtration
08 filtration08 filtration
08 filtration
 
05 water supply system
05 water supply system05 water supply system
05 water supply system
 
sedimentation
sedimentationsedimentation
sedimentation
 
Pumping Stations
Pumping StationsPumping Stations
Pumping Stations
 
14 stokes law and grit separators
14 stokes law and grit separators14 stokes law and grit separators
14 stokes law and grit separators
 
Plain sedimentation
Plain sedimentationPlain sedimentation
Plain sedimentation
 
1. Onsite sanitation system and disposal of sludge slide series (1) septic tank
1. Onsite sanitation system and disposal of sludge slide series (1) septic tank1. Onsite sanitation system and disposal of sludge slide series (1) septic tank
1. Onsite sanitation system and disposal of sludge slide series (1) septic tank
 
UNIT -II Treatment of water- aeration and sedimentation.ppt
UNIT -II  Treatment of water- aeration and sedimentation.pptUNIT -II  Treatment of water- aeration and sedimentation.ppt
UNIT -II Treatment of water- aeration and sedimentation.ppt
 
Low Cost Sanitation Systems
Low Cost Sanitation SystemsLow Cost Sanitation Systems
Low Cost Sanitation Systems
 
SEDIMENTATION
SEDIMENTATIONSEDIMENTATION
SEDIMENTATION
 
Wwwe
WwweWwwe
Wwwe
 
Treatment of water
Treatment of waterTreatment of water
Treatment of water
 
ASP.pptx
ASP.pptxASP.pptx
ASP.pptx
 
Activated Sludge process
Activated Sludge processActivated Sludge process
Activated Sludge process
 
Presentation for safegard septic tank
Presentation for safegard septic tankPresentation for safegard septic tank
Presentation for safegard septic tank
 
Sewer Appurtanances
Sewer AppurtanancesSewer Appurtanances
Sewer Appurtanances
 
Excavation and Ground water control1.pptx
Excavation and Ground water control1.pptxExcavation and Ground water control1.pptx
Excavation and Ground water control1.pptx
 
Coagulation and flocculation
 Coagulation and flocculation Coagulation and flocculation
Coagulation and flocculation
 
Unit III Quality and Treatment
Unit  III Quality and TreatmentUnit  III Quality and Treatment
Unit III Quality and Treatment
 
Sewage Treatment: Priliminary Treatment
Sewage Treatment: Priliminary TreatmentSewage Treatment: Priliminary Treatment
Sewage Treatment: Priliminary Treatment
 

More from Akepati S. Reddy

More from Akepati S. Reddy (20)

PH,acidity and alkanity
PH,acidity and alkanityPH,acidity and alkanity
PH,acidity and alkanity
 
Td sand tss
Td sand tssTd sand tss
Td sand tss
 
Asr wastewater characteristics
Asr wastewater characteristicsAsr wastewater characteristics
Asr wastewater characteristics
 
Asr flow measurement
Asr  flow measurementAsr  flow measurement
Asr flow measurement
 
Asr= nutrients
Asr= nutrientsAsr= nutrients
Asr= nutrients
 
Asr mp ntest
Asr mp ntestAsr mp ntest
Asr mp ntest
 
02b priliminary treatment
02b priliminary treatment02b priliminary treatment
02b priliminary treatment
 
02d secondary treatment
02d secondary treatment02d secondary treatment
02d secondary treatment
 
Wastewater characteristics
Wastewater characteristicsWastewater characteristics
Wastewater characteristics
 
Chapter2activestudge process
Chapter2activestudge processChapter2activestudge process
Chapter2activestudge process
 
acticated sluge process
acticated sluge processacticated sluge process
acticated sluge process
 
Atmospheric Pressure and Winds
Atmospheric Pressure and WindsAtmospheric Pressure and Winds
Atmospheric Pressure and Winds
 
Atmosphere: Composition and Strucutre
Atmosphere: Composition and StrucutreAtmosphere: Composition and Strucutre
Atmosphere: Composition and Strucutre
 
Biological sludge digestion
Biological sludge digestionBiological sludge digestion
Biological sludge digestion
 
Geothermal energy technologies
Geothermal energy technologiesGeothermal energy technologies
Geothermal energy technologies
 
UASB reactors
UASB reactorsUASB reactors
UASB reactors
 
Activated sludge process
Activated sludge processActivated sludge process
Activated sludge process
 
Scrubbing Systems
Scrubbing SystemsScrubbing Systems
Scrubbing Systems
 
biomass gasification
biomass gasificationbiomass gasification
biomass gasification
 
Sewerage System
Sewerage SystemSewerage System
Sewerage System
 

Recently uploaded

Call Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...SUHANI PANDEY
 
Get Premium Hoskote Call Girls (8005736733) 24x7 Rate 15999 with A/c Room Cas...
Get Premium Hoskote Call Girls (8005736733) 24x7 Rate 15999 with A/c Room Cas...Get Premium Hoskote Call Girls (8005736733) 24x7 Rate 15999 with A/c Room Cas...
Get Premium Hoskote Call Girls (8005736733) 24x7 Rate 15999 with A/c Room Cas...MOHANI PANDEY
 
Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...
Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...
Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...rajputriyana310
 
Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur Escorts
Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur EscortsCall Girl Nagpur Roshni Call 7001035870 Meet With Nagpur Escorts
Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
VVIP Pune Call Girls Vishal Nagar WhatSapp Number 8005736733 With Elite Staff...
VVIP Pune Call Girls Vishal Nagar WhatSapp Number 8005736733 With Elite Staff...VVIP Pune Call Girls Vishal Nagar WhatSapp Number 8005736733 With Elite Staff...
VVIP Pune Call Girls Vishal Nagar WhatSapp Number 8005736733 With Elite Staff...SUHANI PANDEY
 
$ Love Spells 💎 (310) 882-6330 in Pennsylvania, PA | Psychic Reading Best Bla...
$ Love Spells 💎 (310) 882-6330 in Pennsylvania, PA | Psychic Reading Best Bla...$ Love Spells 💎 (310) 882-6330 in Pennsylvania, PA | Psychic Reading Best Bla...
$ Love Spells 💎 (310) 882-6330 in Pennsylvania, PA | Psychic Reading Best Bla...PsychicRuben LoveSpells
 
VIP Model Call Girls Wagholi ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Wagholi ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Wagholi ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Wagholi ( Pune ) Call ON 8005736733 Starting From 5K to ...SUHANI PANDEY
 
Proposed Amendments to Chapter 15, Article X: Wetland Conservation Areas
Proposed Amendments to Chapter 15, Article X: Wetland Conservation AreasProposed Amendments to Chapter 15, Article X: Wetland Conservation Areas
Proposed Amendments to Chapter 15, Article X: Wetland Conservation Areas💥Victoria K. Colangelo
 
Call On 6297143586 Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...
Call On 6297143586  Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...Call On 6297143586  Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...
Call On 6297143586 Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...tanu pandey
 
Call Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance Bookingtanu pandey
 
VIP Model Call Girls Viman Nagar ( Pune ) Call ON 8005736733 Starting From 5K...
VIP Model Call Girls Viman Nagar ( Pune ) Call ON 8005736733 Starting From 5K...VIP Model Call Girls Viman Nagar ( Pune ) Call ON 8005736733 Starting From 5K...
VIP Model Call Girls Viman Nagar ( Pune ) Call ON 8005736733 Starting From 5K...SUHANI PANDEY
 
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...SUHANI PANDEY
 
Types of Pollution Powerpoint presentation
Types of Pollution Powerpoint presentationTypes of Pollution Powerpoint presentation
Types of Pollution Powerpoint presentationmarygraceaque1
 
Alandi Road ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready ...
Alandi Road ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready ...Alandi Road ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready ...
Alandi Road ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready ...tanu pandey
 
Book Sex Workers Available Pune Call Girls Kondhwa 6297143586 Call Hot India...
Book Sex Workers Available Pune Call Girls Kondhwa  6297143586 Call Hot India...Book Sex Workers Available Pune Call Girls Kondhwa  6297143586 Call Hot India...
Book Sex Workers Available Pune Call Girls Kondhwa 6297143586 Call Hot India...Call Girls in Nagpur High Profile
 
DENR EPR Law Compliance Updates April 2024
DENR EPR Law Compliance Updates April 2024DENR EPR Law Compliance Updates April 2024
DENR EPR Law Compliance Updates April 2024itadmin50
 
CSR_Tested activities in the classroom -EN
CSR_Tested activities in the classroom -ENCSR_Tested activities in the classroom -EN
CSR_Tested activities in the classroom -ENGeorgeDiamandis11
 

Recently uploaded (20)

Call Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance Booking
 
VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...
 
Get Premium Hoskote Call Girls (8005736733) 24x7 Rate 15999 with A/c Room Cas...
Get Premium Hoskote Call Girls (8005736733) 24x7 Rate 15999 with A/c Room Cas...Get Premium Hoskote Call Girls (8005736733) 24x7 Rate 15999 with A/c Room Cas...
Get Premium Hoskote Call Girls (8005736733) 24x7 Rate 15999 with A/c Room Cas...
 
Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...
Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...
Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...
 
Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur Escorts
Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur EscortsCall Girl Nagpur Roshni Call 7001035870 Meet With Nagpur Escorts
Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...
 
VVIP Pune Call Girls Vishal Nagar WhatSapp Number 8005736733 With Elite Staff...
VVIP Pune Call Girls Vishal Nagar WhatSapp Number 8005736733 With Elite Staff...VVIP Pune Call Girls Vishal Nagar WhatSapp Number 8005736733 With Elite Staff...
VVIP Pune Call Girls Vishal Nagar WhatSapp Number 8005736733 With Elite Staff...
 
$ Love Spells 💎 (310) 882-6330 in Pennsylvania, PA | Psychic Reading Best Bla...
$ Love Spells 💎 (310) 882-6330 in Pennsylvania, PA | Psychic Reading Best Bla...$ Love Spells 💎 (310) 882-6330 in Pennsylvania, PA | Psychic Reading Best Bla...
$ Love Spells 💎 (310) 882-6330 in Pennsylvania, PA | Psychic Reading Best Bla...
 
VIP Model Call Girls Wagholi ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Wagholi ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Wagholi ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Wagholi ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
Proposed Amendments to Chapter 15, Article X: Wetland Conservation Areas
Proposed Amendments to Chapter 15, Article X: Wetland Conservation AreasProposed Amendments to Chapter 15, Article X: Wetland Conservation Areas
Proposed Amendments to Chapter 15, Article X: Wetland Conservation Areas
 
Call On 6297143586 Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...
Call On 6297143586  Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...Call On 6297143586  Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...
Call On 6297143586 Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...
 
Call Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance Booking
 
Sustainable Packaging
Sustainable PackagingSustainable Packaging
Sustainable Packaging
 
VIP Model Call Girls Viman Nagar ( Pune ) Call ON 8005736733 Starting From 5K...
VIP Model Call Girls Viman Nagar ( Pune ) Call ON 8005736733 Starting From 5K...VIP Model Call Girls Viman Nagar ( Pune ) Call ON 8005736733 Starting From 5K...
VIP Model Call Girls Viman Nagar ( Pune ) Call ON 8005736733 Starting From 5K...
 
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
 
Types of Pollution Powerpoint presentation
Types of Pollution Powerpoint presentationTypes of Pollution Powerpoint presentation
Types of Pollution Powerpoint presentation
 
Alandi Road ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready ...
Alandi Road ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready ...Alandi Road ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready ...
Alandi Road ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready ...
 
Book Sex Workers Available Pune Call Girls Kondhwa 6297143586 Call Hot India...
Book Sex Workers Available Pune Call Girls Kondhwa  6297143586 Call Hot India...Book Sex Workers Available Pune Call Girls Kondhwa  6297143586 Call Hot India...
Book Sex Workers Available Pune Call Girls Kondhwa 6297143586 Call Hot India...
 
DENR EPR Law Compliance Updates April 2024
DENR EPR Law Compliance Updates April 2024DENR EPR Law Compliance Updates April 2024
DENR EPR Law Compliance Updates April 2024
 
CSR_Tested activities in the classroom -EN
CSR_Tested activities in the classroom -ENCSR_Tested activities in the classroom -EN
CSR_Tested activities in the classroom -EN
 

Primary sedimentation

  • 1. Primary Sedimentation Dr. Akepati S. Reddy School of Energy and Environment Thapar University, Patiala PUNJAB, INDIA
  • 2. Flocculent Particle Settling • Particles do not settle as discrete particles – instead during sedimentation they coalesce and flocculate • Extent of coalescence or flocculation depend on – Overflow rate – Depth of settling basin – Velocity gradients in the system – Concentration of particles – Range of particle sizes • Settling characteristics of a suspension of flocculent particles can be obtained by a settling column test • Settling column – Height: equal to the depth of the proposed settling tank – Diameter can be anything – influences of the wall should be taken care off – sample required should be small enough – Provided with sampling ports
  • 3. • Settling column test – To begin with ensure uniform distribution of particle size from top to bottom of the column – Duration of test should be equal to the settling time in the proposed tank – Draw samples from the ports at various time intervals, analyze for TSS and compute % removal – Plot % removal against time and depth and construct curves of equal % removal – Overflow rates for various settling are determined by noting where the curve intersect the x-axis Flocculent Particle Settling                   2 (%) 1 1 nn n h n RR H h R
  • 4. Settling Column Settling Profile Graph
  • 5.
  • 6. Primary Sedimentation Tank • Purpose is removal of readily settleable solids and floating material from wastewater • Usually give 50-70% suspended solids removal efficiency and 25-40% BOD removal (for municipal sewage) • Rectangular or circular sedimentation tanks are used – Two or more cylindrical or rectangular sedimentation tanks may be used for allowing maintenance and repair – Multiple rectangular tanks require less land area than multiple circular tanks and common walls reduce construction cost • Sedimentation tanks should include – Inlet section and Outlet section – Facilities and provisions for the settled sludge scrapping, collection and removal – Facilities and provisions for the floating material entrapment, skimming, collection and removal • Sedimentation tank can be considered to include Settling zone and Sludge zone
  • 7. Flow pattern is radial with central feed arrangement • Has a center well of 15-20% of the tank diameter and 1.0 to 2.5 m depth is used • Center well has a tangential energy dissipating inlet • wastewater is discharged into the well within the upper 0.5-0.7 m at 0.3 to 0.45 m/sec flow velocity Solids removal mechanisms • Smaller tanks have hopper bottom with >45 inclination with the horizontal • 3.6-9.0 m diameter tanks have solids removal equipment supported on beams spanning the tank • Larger diameter tanks have a central pier supporting the mechanism and is reached by a walkway or bridge • Bottom of the tank is sloped at 1 in 12 to 64 or lesser • Solids are scrapped to the center and removed Clarified liquid is skimmed off over weirs into a collection trough Circular Primary Sedimentation Tank
  • 8.
  • 9. Clarified sewage Collection trough Scum retaining baffle Distribution baffle of central well Scrapper arm Skimmer bladeCentral well Central pier Influent pipe Sludge draw-off pipe Central rotating equipment Sludge trough Tangential openings in the pier for the distribution of the influent Slope 1 in 12 Side wall of clarifier 0.5m 0.3m 0.3m 0.3m 0.6m Central pier Sludge trough 0.5 m 1.5 m 0.5 m Sludge draw-off pipe Influent pipe Primary clarifier Section to show side wall with clarified sewage collection trough Bottom sludge trough and outlet 3.0 m
  • 10. Inlet • Full width inlet channels with inlet weirs – can introduce vertical velocity component spreading into the sludge hoppers (provided at the inlet end) • Inlets with submerged ports/orifices (velocities in the ports/orifices are in the range of 3-9 m/min.) • Inlet channels with wide gates and slotted baffles • Inlet baffles can be used to reduce high initial velocities and distribute flow width wise – usually extend from 150 mm below and 300 mm above the water surface Outlet • Clarified effluent is collected into a collection trough through an overflow weir • Floating material or settled suspended solids should not be washed out with the clarified effluent • Floating material retaining or entrapping baffle is provided • Weir length is designed to avoid washout out of sludge Rectangular Primary Sedimentation Tanks
  • 11. Facilities and provisions for the settled sludge scrapping, collection and removal • Settled sludge is collected at the inlet end • Chain and flight solids collectors – Have a pair of endless conveyor chains – Scraper flights of wood or fiberglass, running full width of the tank and attached to the chains at 3 m interval – The settled solids are scrapped • to solids hoppers In case of small tanks – multiple hoppers are used in larger tanks • to a transverse trough in case of large tanks - troughs in turn have cross collectors Rectangular Primary Sedimentation Tank
  • 12. Traveling bridge type collectors – Travel up and down the tank on rubber wheels or on rails supported on the sidewalls – Scrapper blades are suspended from the bridge (returning scraper blades lifted free of the solids blanket) Facilities and provisions for floating material entrapment, skimming, collection and removal • Floating scum is collected at the effluent end • Floating scum is skimmed and carried to the effluent end and entrapped for avoiding overflow into the clarified effluent trough – Flights returning at the liquid surface can be used – Water showers can be used to push forward the floating scum – Baffle is provided in front of the overflow weir for the scum entrapment until removed Rectangular Primary Sedimentation Tank
  • 13. • In small tanks scum draw-down facility consisting of a horizontal, slotted pipe that can be rotated by a lever or screw can be used – Limitation - creates large volume of scum liquor • Transverse rotating helical wiper attached to a shaft can also be used for scum removal – Scum is removed from the water surface and moved over an inclined apron for discharge to a cross-collecting scum trough Other provisions and facilities • Tanks may sloping bottom towards the influent end • Influent end has sludge hoppers or sludge trench • Scum pit is provided for storing the scum liquid removed • Sludge pump, piping and tank may be there to remove the collected sludge from the sludge hopper or trench Rectangular Primary Sedimentation Tank
  • 14.
  • 15. Design of Primary Clarifier • Overflow rate and hydraulic retention time obtained from the settling test and settling profile diagram are used to find surface area and depth of the clarifier • Safety factors of 1.25 is usually used to take into account – Inlet and outlet disturbances – Disturbances created by the rotating mechanism to scrap the settled sludge and to collect the floating scum – Wind blow effects – Temperature variations – Flow short-circuiting • Design also takes into account the following: – Horizontal flow velocity (below the scour velocity) – Weir overflow rate (below a limit to avoid density currents) – Weir overflow balancing to avoid short-circuiting problems – Flooding of collection trough
  • 16. Detention time 1.5 to 2.5 hours (2.0 hr.) Overflow rate Average flow 30-50 m3/m2.day (40) – 24-32 (26) Peak flow 80-120 m3/m2.day (100) – 48-70 (60) Weir loading 125-500 m3/m.day (250) Rectangular tanks Depth 3-4.9 (4.3) Length 15-90 (24-40) Width 3-24 (4.9-9.8) Flight speed 0.6-1.2 m/min (0.9) Circular tank Diameter 3-60 (12-45) Bottom slope 1 in 16 to 1 in 6 (1 in 12) Flight speed 0.02-0.05 rpm (0.03) Primary Sedimentation Tank
  • 17. Short circuiting and hydraulic stability • Tracer studies can be used for determining short-circuiting problems • Method of influent flow distribution can also affect short circuiting Temperature difference of 1C between incoming wastewater and wastewater of the tank can cause density current Wind blowing across the top of an open sedimentation tank can cause circulation cell to form – this reduces effective volumetric capacity of the tank Surface loading rates (overflow rates) • There can be regulations prescribing limits to surface loading rates • Overflow rates must be set low enough to ensure satisfactory performance at peak rates of flow Primary Sedimentation Tank
  • 18. Detention time • Solids reaching the settling tank are susceptible to flocculation • Flocculation is aided by eddying motion of fluid within the tank • Level of flocculation depends on the time elapsed (detention time) • In cold climates because of increase in water viscosity detention time required also increases (1.38 time more HRT for 10C water that when temperature is 20C) Weir loading rates • Have little effect on efficiency of primary settlign tanks Primary sludge scum characteristics and quantities • Factors influencing are – Characteristics of untreated water (strength and freshness) – Period of sedimentation – Conditions of the deposited solids – Period between solids removal operations Primary Sedimentation Tank
  • 19. Primary Sludge • Primary clarifier is designed for a specified % removal of TSS • From knowing the TSS and flow rate of the influent sewage primary sludge generated can be quantified • TSS of the sewage is comprised of inorganic TSS, VSS and Biodegradable VSS – Biodegradable VSS contributes BOD and this is 50-60% of the total BOD for municipal sewage • Primary clarifier through removing the Biodegradable VSS contributes to BOD removal – BOD removal in the primary clarifier is typically 35-45% • If BOD removal in the primary clarifier is known, one can find out the biodegradable fraction of the primary sludge – BOD removal can be expressed as BODu removal and BODu removal as TSS equivalent removal – The fraction of biodegradable VSS in the TSS is assumed to remain the same even in the clarified effluent • If consistency of the primary sludge is known even volume of the primary sludge can be calculated