Regional Project Monitoring and Evaluation System




                       Prepared by the
       National Economic and Development Authority
              Cordillera Administrative Region
                      RPMC Secretariat
Second Quarter CY 2012 RPMES Report

The Regional Project Monitoring and Evaluation System (RPMES) report is published quarterly
to provide an overall view on the status of major programs/projects (P/Ps) in the Cordillera
Administrative Region (CAR). The report is based primarily from the submission of eleven
regional line agencies (RLAs). The detailed report is regularly posted in the RDC-CAR webpage.


CY 2012 Major Programs / Projects

For CY 2012, the RPMES Report contains 46 major P/Ps with an aggregate cost of Php 10.414
Billion. These P/Ps were enrolled in the monitoring system by the eleven RLAs. The projects
are grouped according to sector/ program, namely: Social, Economic, Infrastructure and
Strategic Action Plan (SAP) for the rehabilitation & recovery of disaster-afflicted areas. The
following table shows the total cost and physical accomplishment by sector/ program as of end-
June 2012.
                   Cost and Physical Accomplishment by Sector/ Program, CAR
                                        As of June 2012


                                                          Percentage         Accomplishment
    Sector/ Program            Cost (Php M.)
                                                             Cost             (ao June 2012)
a) Social Sector                 1,788.255                 17.17 %               41.17 %

b) Economic Sector               5,424.533                 52.09 %               26.37 %

c) Infrastructure Sector         2,794.801                 26.83 %               30.61 %

d) Strategic Action Plan          406.722                   3.91 %                96.24%
   (Rehabilitation &
   Recovery Program)
       CAR Total                 10,414.311                 100 %                32.78 %


In terms of cost, Economic Sector has the highest with Php 5.4 B or 52 percent. This is
                                  costing Php 3.1 Billion. Infrastructure Sector follows with Php
2.8 Billion or 26.83 percent. While the Social Sector and SAP have Php 1.8 B. or 17.17 percent
and Php 406.7 M. or barely 4 percent, respectively.


                                               1
Some 7.11 percent, amounting to Php
740.45 M. are carryover projects. The
bulk of these are implemented by DepEd,
DPWH and DOH. While 38.27 percent or
Php 3.99 B. are multiyear projects and
54.62 percent, amounting to Php 5.79
Billion are new projects for the current
year. In terms of fund source, Php 3.34
B. or 32.12 percent are foreign-assisted
while Php 7.07 B or 67.88 % are GOP
funded.


In terms of implementation status, the overall physical accomplishment is 32.78 percent. It is
expected by the second semester, project progress will pick-up due to the improved weather
condition. The SAP which is mostly carryover projects posted 96.24 percent. The SAP projects,
by DPWH and DepEd, are rehabilitation and recovery projects for the disaster-affected areas
particularly Typhoons Juan, Pedring and Quiel.




The Social Sector obtained an accomplishment of 41.17 percent. The sector is dominated by
the          Pantawid Pamilyang Pilipino Program (4Ps), Php 745.5 M.;          Red & Black
School Building Program (Php 266.1 M.);         health facilities (Php 453.1 M.) and water
system projects (Php 184.5 M.).


                                              2
The Infrastructure Sector and Economic Sector achieved 30.61 percent and 26.37 percent,
respectively. The Infrastructure Sector is basically           road and bridge projects.
The large projects in Economic Sector are                                    (Php 1.078
B.),


The relatively low performance of the Economic Sector is largely attributed to the delayed
implementation of the multi-year and ODA-assisted CHARMP 2. This has bearing due to its
large cost and posting an accomplishment of merely 18.66 percent. The project underwent
another NEDA-ICC process for a project reconfiguration to address the concern of LGU
beneficiaries in putting up their cash counterpart.


CY 2012 Priority Sectoral Programs/ Projects

From among the 46 major program/ projects, priority P/Ps were selected by the Sectors based
on the RPMES national forum criteria: (a) foreign-assisted projects (FAP/ODA), (b)
interprovincial, (c) large scale cost, (d) national priority, critical projects by the Office of the
President (OP), and (e) regional priority.


The eight (8) major P/Ps are subject of closer RPMC-CAR monitoring through field validation
and inspection. These major P/Ps have a total cost of Php 5.3 B., to wit:
   1. Second Cordillera Highland Agricultural Resource Management Project (CHARMP 2), Php
      3.08 B;
   2. Pantawid Pamilyang Pilipino Program (4Ps), Php 745.5 M;
   3. Agrarian Reform Infrastructure Support Project, Phase III, Php 903.8 M;
   4. Kabugao-Solsona, Apayao-Ilocos Norte Road, Php 100M;
   5. Kabugao-Pudtol- Luna- Cagayan Boundary Road, Php 58.8 M;
   6. Cordillera-wide Strengthening of Local health System for Effective and Efficient Delivery
      of Maternal and Child Health Services, Php 43 M;
   7. National Greening Program, Php 103.66 M; and
   8. Red and Black Scholl Building Program, Php 266 M.




                                                 3
RPMES 2nd Quarter Report
                                 CY 2012 MAJOR PROGRAMS/PROJECTS
                                           Cordillera Administrative Region
                                                    As of June 2012


                                               IMPLEMENTING         PROJECT COST        FUNDING      STATUS/
          PROGRAM/PROJECT
                                                  AGENCY              (PhP M)            SOURCE      REMARKS

                                                   SOCIAL SECTOR
1. Pantawid Pamilyang Pilipino Program              DSWD                      745.512    Loan              47.09%
   (4Ps)

2. Red and Black School Building                    DepEd          CY 2011:              GOP        CY 2011 fund:
   Program                                                                     50.952                      89.22%
                                                                                                   209 Classrooms

                                                                   CY 2012:                         CY 2012 fund:
                                                                           115.200                          7.69%
                                                                                                   143 Classrooms

3. Cordillera-wide Strengthening of              DOH & LGUs                     43.00     JICA    Project was
   Local Health System for Effective and         Abra Apayao                                      launched on
   Efficient Delivery of Maternal and              Benguet                                        March 13, 2012.
   Child Health Services                                                                          However, the
                                                                                                  project has yet
                                                                                                  to fully take-off
                                                                                                  since JICA has
                                                                                                  yet to procure
                                                                                                  and deliver the
                                                                                                  medical
                                                                                                  equipment for
                                                                                                  the provinces of
                                                                                                  Abra and
                                                                                                  Apayao.

4. National Household Targeting System              DSWD                       40.793    GOP,              57.20%
   for Poverty Reduction Program                                                         Loan

5. Rehabilitation of School Building                DepEd          CY 2011:              GOP        CY 2011 Fund:
   including Water Sanitation Facilities                                       21.934                     89.99%

                                                                   CY 2012:                         CY 2012 Fund:
                                                                               29.340                  Waiting for
                                                                                                            SARO
6. Philippine Response to Indigenous                DepEd                       3.978   AusAid               19%

    (PRIME)




                                                          4
RPMES 2nd Quarter Report
                                 CY 2012 MAJOR PROGRAMS/PROJECTS
                                          Cordillera Administrative Region
                                                   As of June 2012


                                              IMPLEMENTING         PROJECT COST        FUNDING        STATUS/
            PROGRAM/PROJECT
                                                 AGENCY              (PhP M)            SOURCE        REMARKS

7. Construction of Various Health                   DOH           CY 2011:               GOP         CY 2011 fund:
   Facility                                                               117.867                          58.55%

                                                                  CY 2012:                           CY 2012 fund:
                                                                          335.179                           6.49%
8. Water Supply System                              DOH                   184.500        GOP               57.98%

Sub-Total                                                                1,788.255                            41.17%
                                                ECONOMIC SECTOR
9. Second Cordillera Highland                       DA                   3,081.862       IFAD,                18.66%
   Agricultural Resource Management                                                    ADB. OFID
   Project (CHARMP2)

10. Agrarian Reform Infrastructure                   DAR          Total Project          Loan                 42.60%
    Support Project Phase III                                     Cost: 903.863          GOP
    (Abra, Apayao, Benguet, Ifugao,
    Kalinga and Mt. Province)                                      CY 2011:
                                                                  (2 projects)
                                                                            16.718

                                                                  CY 2012:
                                                                  (12 projects)
                                                                           167.445

11. National Greening Program (NGP)                 DENR                     103.663     GOP                  48.53%

12. Farm-to-Market Roads                             DA           CY 2011:               Grant     CY 2011:
    (CY 2011 Fund:                                                             53.00                          81.13%
    Abra, Kalinga and Mt. Province)
                                                                  CY 2012:                         CY 2012:
    (CY 2012 Fund:                                                        161.803                             11.56%
    Abra, Baguio City, Benguet, Ifugao,
    Kalinga and Mt. Province)

13. Irrigation Projects                              NIA                1,078.046        GOP                  30.15%
                                                                     (432 projects)

14. One Town One Product Program                     DTI                       2.747     GOP                  84.68%
    (OTOP)




                                                           5
RPMES 2nd Quarter Report
                                  CY 2012 MAJOR PROGRAMS/PROJECTS
                                        Cordillera Administrative Region
                                                 As of June 2012


                                            IMPLEMENTING         PROJECT COST        FUNDING     STATUS/
          PROGRAM/PROJECT
                                               AGENCY              (PhP M)            SOURCE     REMARKS

15. Rural Micro Enterprise Promotion               DTI                       1.800   IFAD with          90%
      Programme (RuMEPP)                                                                GOP
                                                                                      Counter
                                                                                        Part

16. Shared Service Facilities Project              DTI                       8.388    NEDAC      Awarding of
      (SSF)                                                                             Fund        bidding
                                                                                     (National     suppliers
                                                                                       Export
                                                                                     Develop-
                                                                                     ment and
                                                                                     Competi-
                                                                                     tiveness)

17. Small Enterprise Technology                   DOST                      28.673     GOP             100%
      Upgrading Program (SETUP) Core
      and Non-Core Funded Projects

18. Packaging and Labeling                        DOST                      688.00     GOP             100%
                Sub-Total                                              5,424.533                     26.37%
                                          INFRASTRUCTURE SECTOR
Abra
19. Abra-Ilocos Sur Road                         DPWH                      106.195     GOP           33.86%
20. Abra-Kalinga Road, K0467+000-                DPWH                      147.691     GOP            1.44%
    K0474+305
21. Abra-Ilocos Norte, K0436+700-                DPWH                        62.00     GOP            7.17%
    K0439+395
22. Road Upgrading along Abra-                   DPWH                        60.00     GOP            1.03%
    Cervantes Road (Realigned from
    Sto. Tomas-Manabo Bridge)
23. Sto. Tomas-Manabo Bridge                     DPWH                       160.00     GOP           58.62%
24. Abra-Kalinga Road K0410+000-                 DPWH                        50.45     GOP           96.03%
    K0413+810
25. Abra-Kalinga Road K0437+490-                 DPWH                       143.67     GOP              93%
    K0455+890, K0432+000, K0450+800
Apayao
26. Kabugao-Pudtol-Luna-Cagayan                  DPWH                       58.827     GOP           40.70%
    Boundary Road K0661+000-
    K0661+321,K0643+646 - K0645+825
    Gravel to Concrete



                                                         6
RPMES 2nd Quarter Report
                               CY 2012 MAJOR PROGRAMS/PROJECTS
                                     Cordillera Administrative Region
                                              As of June 2012


                                          IMPLEMENTING        PROJECT COST        FUNDING   STATUS/
         PROGRAM/PROJECT
                                             AGENCY             (PhP M)            SOURCE   REMARKS

27. Kabugao, Apayao-Solsona, Ilocos           DPWH                       100.00    GOP           0.50%
    Norte Road
Benguet
28.                                           DPWH                       54.433    GOP           3.22%
    Kennon Road
29. Baguio-Bontoc Road (Pico-Lamtang          DPWH                       98.674    GOP           1.05%
    Rd., Baguio Itogon & Baguio-Bontoc)
30. Baguio-Bontoc Road, K0269+000-            DPWH                      109.332    GOP            15%
    K0275+000 (v.s.)& K0299+000-
    K0300+900 (v.s.) & K0305+000-
    K0308+500 (v.s.) & K0309+000-
    K0311+000 (v.s.), K0317+415-
    K0318+500 (v.s.), & K0323+000
    K0328+000 (v.s.)
31. Gurel-Bokod-Kabayan-Buguias-              DPWH                        98.50    GOP            70%
    Abatan Road
32. Gurel-Bokod-Kabayan-Buguias-              DPWH                       116.50    GOP          88.88%
    Abatan Road K0303+600-
    K03012+000
33.                        -Bokod-            DPWH                       148.00    GOP          21.56%
    Kabayan-Buguias Road including
    RROW
34. Gurel-Bokod-Kabayan-Buguias-              DPWH                       68.921    GOP          24.43%
    Abatan Road, K0345+513-K0359+300
    (vs.)
Ifugao
35. Banaue-Mayoyao-A Lista-Isabela            DPWH                       58.064    GOP           0.50%
    Bdry. Road
36. Nueva Vizcaya-Ifugao-Mt. Province         DPWH                       54.163    GOP            17%
    Road
Kalinga
37. Kalinga-Abra Road, K0470+000-             DPWH                       53.057    GOP          13.05%
    K0472+267
38. Kalinga-Abra Road, K0476+000-             DPWH                       135.27    GOP           0.60%
    K0480+1000, K0480+1000-
    K0482+700 (with exceptions)
39. Balbalan-Pinukpuk Road K0485+000-         DPWH                       100.00    GOP          63.80%
    K0489+000
40. Balbalan-Pinukpuk Road                    DPWH                       245.00    GOP          27.10%
    K0560+1061-K0520+449



                                                    7
RPMES 2nd Quarter Report
                                 CY 2012 MAJOR PROGRAMS/PROJECTS
                                        Cordillera Administrative Region
                                                 As of June 2012


                                            IMPLEMENTING         PROJECT COST        FUNDING      STATUS/
          PROGRAM/PROJECT
                                               AGENCY              (PhP M)            SOURCE      REMARKS

41. Mt. Province Bdry. Calanan-                  DPWH                       209.00    GOP                  38%
    Pinukpuk Abbut Road (Pinukpuk)
    (P209.0 M) K0499+674-K0509+294
    (I.S.)
42. Balbalan-Pinukpuk Road, Abut A of            DPWH                      183.239    GOP       Advertised June
    Baay Bridge+(-18502) to Abut A of                                                              21-25, 2012.
    Baay Bridge+0                                                                                 Scheduled for
                                                                                                 bidding on July
                                                                                                       10, 2012.
Mountain Province
43. Mt. Province Ilocos Sur via Tue Road           DPWH                     81.815      GOP             20.75%
44. Mt. Province-Ilocos Sur via Kayan              DPWH                      92.00      GOP             30.35%
Sub-Total                                                               2,794.801                       30.61%
                                           STRATEGIC ACTION PLAN (SAP)
                            (Rehabilitation and Recovery of Areas Affected by Disasters)
45. Disaster Related Rehabilitation                DPWH                                DRRP
    Project (DRRP)                                                                   Calamity
                                                                                       Fund
                                                                                      CY 2011
    a. Apayao 1st District Engineering                                   74,550.0                       87.73%
        Office (16 projects)
    b. Apayao 2nd District Engineering                                   14,000.0                         100%
        Office (5 projects)
    c. Benguet 1st District Engineering                                  45,469.0                         100%
        Office (15 projects)
    d. Benguet 2nd District Engineering                                  39,279.1                         100%
        Office (6 projects)
    e. Baguio City District Engineering                                      600.0                        100%
        Office (1 project)
    f. Ifugao 1st District Engineering                                     8,580.0                        100%
        Office (2 projects)
    g. Ifugao 2nd District Engineering                                   25,850.0                         100%
        Office (4 projects)
    h. Kalinga District Engineering                                      85,910.5                       95.93%
        Office (9 projects)
    i. Mt. Province District Office                                     102,459.4                         100%
        (28 projects)
Sub-Total                                                                 396.697                       96.81%




                                                       8
RPMES 2nd Quarter Report
                                  CY 2012 MAJOR PROGRAMS/PROJECTS
                                         Cordillera Administrative Region
                                                  As of June 2012


                                              IMPLEMENTING         PROJECT COST       FUNDING   STATUS/
          PROGRAM/PROJECT
                                                 AGENCY              (PhP M)           SOURCE   REMARKS

46. Quick Response Fund (QRF)                      DepEd                               GOP
    a. Cabaroan ES Dolores, Abra                                              1.201                   56%
       (Construction of 1 unit-2
       classroom in Bldg.1)
    b. Cabaroan ES Dolores, Abra                                              1.201                  100%
       (Construction of 1 unit-2
       classroom in Bldg.2)
    c. Cabaroan ES Dolores, Abra                                              318.0                   79%
       (Construction of 3 Seater Toilet
       type III with handwashing)
    d. Cabaroan ES Dolores, Abra                                              219.0                   71%
       (1 classroom repair)
    e. Tonglo Carino PS, Buguias,                                             1.201                   15%
       Benguet
    f. Talubin NHS, Bontoc Mt. Province                                       1.143                   65%
       (Construction of 2cl /
       Replacement of Burned Bldg.)
    g. Tumog Es, Luna, Apayao                                                 1.942                   70%
       (Construction of 1stry 3
       Classroom 7x9 type I)
    h. Lagawe CS, Lagawe, Ifugao                                              1.200                  100%
       (Construction of 2cl /
       Replacement of Burned Bldg.)
    i. Bañacao ES, Bangued West, Abra                                         1.600                  100%
       (Repair of Classrooms /
       Construction of Slope Protection
       /Water System)
Sub-Total                                                                    10.025                 73.44%
SAP Sub-Total                                                               406.722                 96.24%


               CAR Total                                               10,414.311                   32.78%

  Sources: Agencies' RPMES PMC Form I - 2 as of end of June 2011




                                                        9
Priority Sectoral Programs/ Projects, CAR
                                                    As of June 2012

                                                                                                               Status/
                                                                                Cost
    Name of                                                                                 Fund     Imp      Remarks
                                   Description                      Location    (Php)
 Project/Sector                                                                            Source   Entity   As of June
                                                                                  M
                                                                                                                2012

Second             The project has five components:                 Abra,      3,081.862   IFAD,     DA       18.66%
Cordillera                                                          Apayao,                ADB.
                   (1) Community mobilization, participatory
Highland                                                            Benguet,               OFID
                   planning of investments, and land titling; (2)
Agricultural                                                        Ifugao,
                   community watershed conservation (including
Resource                                                            Kalinga,
                   forest management and agro forestry
Management
                   development); (3) agricultural and               Mt.
Project
                   agribusiness development, and promotion of       Province
(CHARMP 2)         income-generating activities; (4) rural
                   infrastructure development; and (5) project
                   management and coordination.


Pantawid           The program addresses the Millennium             Region-    745.512     Loan     DSWD      47.09%
Pamilyang          Development Goals such as reducing of            wide
Pilipino Program   extreme poverty and hunger, achieving
(4Ps)              universal primary education, reducing child
                   mortality, improving maternal health, and
                   promoting gender equality and empowerment
                   of women. The beneficiaries must meet the
                   conditions of the program to avail cash grants
                   and each household beneficiary will receive
                   cash grants for at most five years.


Agrarian Reform    The project involves collaboration among the     Abra,        Total     Loan     DAR       42.60%
Infrastructure     implementing agencies (DAR, DPWH, LGU,           Apayao,     Project    GOP
Support Project    and NIA) and Irrigators Associations. It         Benguet,     Cost:
Phase III          involves construction/rehabilitation of rural    Ifugao,
                                                                               903.863
                                                             1
Priority Sectoral Programs/ Projects, CAR
                                                      As of June 2012

                                                                                                                  Status/
                                                                                     Cost
    Name of                                                                                    Fund     Imp      Remarks
                                     Description                         Location    (Php)
 Project/Sector                                                                               Source   Entity   As of June
                                                                                       M
                                                                                                                   2012
                   infrastructure such as irrigation facilities, farm-   Kalinga,   ( 2011)
                   to-market roads, post-harvest facilities, and         Mt.
                   rural water supply systems, agrarian reform                      16.718
                                                                         Province
                   information and marketing center building,
                   development of coop managed agri-
                   business/rural enterprise/ l                                     (2012)
                   organizations in the ARCs through                                167.445
                   appropriate training and capacity building
                   approaches.


Kabugao,           The road is a major component of the                  Kabugao,    100      GOP      DPWH       0.50%
Apayao-Solsona,    Cordillera Roads Improvement Project (CRIP)           Apayao
Ilocos Norte       as lateral road; it connects Ilocos Region and
Road               the Northern Cordilleras. It traverses the
                   municipalities of Kabugao and Calanasan in
                   Apayao and turns west to Solsona in Ilocos
                   Norte.


Kabugao-Pudtol-    The road is a major component of the             Apayao          58.827    GOP      DPWH      40.70%
Luna-Cagayan       Cordillera Roads Improvement Project (CRIP)
Boundary Road      as the northern tip of the regional backbone. It
K0661+000 -        traverses the municipalities of Kabugao,
K0661+321,         Pudtol and Luna in Apayao and turns east to
K0643+646 -        Abulog in Cagayan.
K0645+825 Gravel
to Concrete

                                                                  2
Priority Sectoral Programs/ Projects, CAR
                                                      As of June 2012

                                                                                                                   Status/
                                                                                    Cost
    Name of                                                                                   Fund     Imp        Remarks
                                      Description                       Location    (Php)
 Project/Sector                                                                              Source   Entity     As of June
                                                                                      M
                                                                                                                    2012

Cordillera-wide                                                         Abra,        43      JICA     DOH &     Project was
Strengthening of     condition health condition particularly of         Apayao                         LGUs     launched on
Local Health         women and children through the delivery of                                        Abra     March 13,
System for           effective and efficient Maternal and Child                                       Apayao    2012.
Effective and        Health (MCH) services.                                                           Benguet   However, the
Efficient Delivery                                                                                              project has yet
                     The project seeks to: (a) strengthen the local
of Maternal and                                                                                                 to fully take-off
                     health systems in all the CAR Provinces; and
Child Health                                                                                                    since JICA
                     (b) improve the quality of health services.
Services                                                                                                        has yet to
                                                                                                                procure and
                                                                                                                deliver the
                                                                                                                medical
                                                                                                                equipments
                                                                                                                for the
                                                                                                                provinces of
                                                                                                                Abra and
                                                                                                                Apayao.


National             An administration priority program (Executive      Region-    103.663   GOP      DENR          48.53%
Greening             Order No. 26) that seeks to attain a               wide
Program (NGP)        sustainable human development, economic
                     and ecological security through the planting of
                     1.5 billion trees in around 1.5 million hectares
                     of public land within six years from year 2011
                     to 2016.

                     The NGP also aims to ensure food security,
                     biodiversity conservation and address climate
                                                                 3
Priority Sectoral Programs/ Projects, CAR
                                                    As of June 2012

                                                                                                                Status/
                                                                                  Cost
    Name of                                                                                  Fund     Imp      Remarks
                                   Description                       Location     (Php)
 Project/Sector                                                                             Source   Entity   As of June
                                                                                    M
                                                                                                                 2012
                  change.

                  In the Cordillera, the target for CY 2012 is 7.5
                  million trees covering 15,000 hectares.

Red and Black     The Regular School Building Program                Region-    (CY 2011) GOP        DepEd    (CY 2011)
School Building   specifically targets schools which are             wide                                      89.22%
                                                                                 150.952
Program           categorized under the Red Zone or those
                  which have a ratio of 56 or more students to
                                                                                (CY 2012)                     (CY 2012)
                  one classroom: and the Black Zone, or                                                         7.69%
                  schools which make use of makeshift                            115.200
                  classrooms and facilities.
                  The standard DepEd design is 7m x 9m
                  classroom for rural areas with a classroom-
                  student ratio of 1:45. This standard also
                  applies to all public secondary schools,
                  regardless of location and class size.


TOTAL:                                                                          5,302.879                      28.84%




                                                              4

Weitere ähnliche Inhalte

Ähnlich wie 2nd qtr rpmes 2012

2nd qtr major program projects
2nd qtr major program projects2nd qtr major program projects
2nd qtr major program projectsRdc Cordillera
 
Summary of programs and projects as of first quarter 2012
Summary of programs and projects as of first quarter 2012Summary of programs and projects as of first quarter 2012
Summary of programs and projects as of first quarter 2012Rdc Cordillera
 
Red and Black School Building Program
Red and Black School Building ProgramRed and Black School Building Program
Red and Black School Building ProgramRdc Cordillera
 
Doh local health system 2nd_qtr_f
Doh local health system 2nd_qtr_fDoh local health system 2nd_qtr_f
Doh local health system 2nd_qtr_fRdc Cordillera
 
Dar arisp iii 2nd qtr_f
Dar arisp iii 2nd qtr_fDar arisp iii 2nd qtr_f
Dar arisp iii 2nd qtr_fRdc Cordillera
 
Dep ed red & black school buildngs_2nd qtr_f
Dep ed red & black school buildngs_2nd qtr_fDep ed red & black school buildngs_2nd qtr_f
Dep ed red & black school buildngs_2nd qtr_fRdc Cordillera
 
LECTURE-1 Introduction to Project Concept, Lifecycle .pptx
LECTURE-1 Introduction to Project Concept, Lifecycle .pptxLECTURE-1 Introduction to Project Concept, Lifecycle .pptx
LECTURE-1 Introduction to Project Concept, Lifecycle .pptxmansoor584949
 
dilg-memocircular-2022-026_SGLG.pdf
dilg-memocircular-2022-026_SGLG.pdfdilg-memocircular-2022-026_SGLG.pdf
dilg-memocircular-2022-026_SGLG.pdfFrancisCoronelJr
 
Jica seminar
Jica seminarJica seminar
Jica seminarkutmdoc
 
IFAD Biogas support Mission in Rwanda
IFAD Biogas support Mission in RwandaIFAD Biogas support Mission in Rwanda
IFAD Biogas support Mission in Rwandacopppldsecretariat
 
2. COSOP results review mtr 2016
2. COSOP results review mtr 20162. COSOP results review mtr 2016
2. COSOP results review mtr 2016ifadseahub
 
Ifad west africa hub compile case studies 2019-en
Ifad west africa hub compile case studies 2019-enIfad west africa hub compile case studies 2019-en
Ifad west africa hub compile case studies 2019-enBenoît THIERRY
 
Annex 4 Paper NZ
Annex 4 Paper NZAnnex 4 Paper NZ
Annex 4 Paper NZnaziazakir
 

Ähnlich wie 2nd qtr rpmes 2012 (20)

2nd qtr rpmes report
2nd qtr rpmes report2nd qtr rpmes report
2nd qtr rpmes report
 
2nd qtr major program projects
2nd qtr major program projects2nd qtr major program projects
2nd qtr major program projects
 
3rd qtr rpmes report
3rd qtr rpmes report3rd qtr rpmes report
3rd qtr rpmes report
 
Summary of programs and projects as of first quarter 2012
Summary of programs and projects as of first quarter 2012Summary of programs and projects as of first quarter 2012
Summary of programs and projects as of first quarter 2012
 
2012 yearend report
2012 yearend report2012 yearend report
2012 yearend report
 
2nd qtr rpmes 2013
2nd qtr rpmes 20132nd qtr rpmes 2013
2nd qtr rpmes 2013
 
Da charmp 2 2nd qtr_f
Da charmp 2 2nd qtr_fDa charmp 2 2nd qtr_f
Da charmp 2 2nd qtr_f
 
Red and Black School Building Program
Red and Black School Building ProgramRed and Black School Building Program
Red and Black School Building Program
 
Doh local health system 2nd_qtr_f
Doh local health system 2nd_qtr_fDoh local health system 2nd_qtr_f
Doh local health system 2nd_qtr_f
 
Dar arisp iii 2nd qtr_f
Dar arisp iii 2nd qtr_fDar arisp iii 2nd qtr_f
Dar arisp iii 2nd qtr_f
 
Dep ed red & black school buildngs_2nd qtr_f
Dep ed red & black school buildngs_2nd qtr_fDep ed red & black school buildngs_2nd qtr_f
Dep ed red & black school buildngs_2nd qtr_f
 
Planning in india
Planning in indiaPlanning in india
Planning in india
 
LECTURE-1 Introduction to Project Concept, Lifecycle .pptx
LECTURE-1 Introduction to Project Concept, Lifecycle .pptxLECTURE-1 Introduction to Project Concept, Lifecycle .pptx
LECTURE-1 Introduction to Project Concept, Lifecycle .pptx
 
dilg-memocircular-2022-026_SGLG.pdf
dilg-memocircular-2022-026_SGLG.pdfdilg-memocircular-2022-026_SGLG.pdf
dilg-memocircular-2022-026_SGLG.pdf
 
1st qtr rpmes 2013
1st qtr rpmes 20131st qtr rpmes 2013
1st qtr rpmes 2013
 
Jica seminar
Jica seminarJica seminar
Jica seminar
 
IFAD Biogas support Mission in Rwanda
IFAD Biogas support Mission in RwandaIFAD Biogas support Mission in Rwanda
IFAD Biogas support Mission in Rwanda
 
2. COSOP results review mtr 2016
2. COSOP results review mtr 20162. COSOP results review mtr 2016
2. COSOP results review mtr 2016
 
Ifad west africa hub compile case studies 2019-en
Ifad west africa hub compile case studies 2019-enIfad west africa hub compile case studies 2019-en
Ifad west africa hub compile case studies 2019-en
 
Annex 4 Paper NZ
Annex 4 Paper NZAnnex 4 Paper NZ
Annex 4 Paper NZ
 

Mehr von Rdc Cordillera

Search for cordillera champions
Search for cordillera championsSearch for cordillera champions
Search for cordillera championsRdc Cordillera
 
Dpwh kabugao pudtol_2nd qtr_f
Dpwh kabugao pudtol_2nd qtr_fDpwh kabugao pudtol_2nd qtr_f
Dpwh kabugao pudtol_2nd qtr_fRdc Cordillera
 
Dpwh kabugao solsona_2nd qtr_f
Dpwh kabugao solsona_2nd qtr_fDpwh kabugao solsona_2nd qtr_f
Dpwh kabugao solsona_2nd qtr_fRdc Cordillera
 
State of the Nation Address 2012
State of the Nation Address 2012State of the Nation Address 2012
State of the Nation Address 2012Rdc Cordillera
 
State of the region address cordillera administrative region
State of the region address   cordillera administrative regionState of the region address   cordillera administrative region
State of the region address cordillera administrative regionRdc Cordillera
 
Red and black schoolbuilding program inspection report
Red and black schoolbuilding program inspection reportRed and black schoolbuilding program inspection report
Red and black schoolbuilding program inspection reportRdc Cordillera
 
National greening program inspection report
National greening program inspection reportNational greening program inspection report
National greening program inspection reportRdc Cordillera
 
ARISP III Inspection Report
ARISP III Inspection ReportARISP III Inspection Report
ARISP III Inspection ReportRdc Cordillera
 
2012 rpmc inspection reports
2012 rpmc inspection reports2012 rpmc inspection reports
2012 rpmc inspection reportsRdc Cordillera
 

Mehr von Rdc Cordillera (16)

Search for cordillera champions
Search for cordillera championsSearch for cordillera champions
Search for cordillera champions
 
Nomination form
Nomination formNomination form
Nomination form
 
Vacaciesjan2012 1
Vacaciesjan2012 1Vacaciesjan2012 1
Vacaciesjan2012 1
 
2nd qtr rpmes 2012
2nd qtr rpmes 20122nd qtr rpmes 2012
2nd qtr rpmes 2012
 
Dpwh kabugao
Dpwh kabugaoDpwh kabugao
Dpwh kabugao
 
Dpwh kabugao pudtol_2nd qtr_f
Dpwh kabugao pudtol_2nd qtr_fDpwh kabugao pudtol_2nd qtr_f
Dpwh kabugao pudtol_2nd qtr_f
 
Dpwh kabugao solsona_2nd qtr_f
Dpwh kabugao solsona_2nd qtr_fDpwh kabugao solsona_2nd qtr_f
Dpwh kabugao solsona_2nd qtr_f
 
Dswd 4 ps_2nd qtr_f
Dswd 4 ps_2nd qtr_fDswd 4 ps_2nd qtr_f
Dswd 4 ps_2nd qtr_f
 
Denr ngp 2nd qtr_f
Denr ngp 2nd qtr_fDenr ngp 2nd qtr_f
Denr ngp 2nd qtr_f
 
State of the Nation Address 2012
State of the Nation Address 2012State of the Nation Address 2012
State of the Nation Address 2012
 
State of the region address cordillera administrative region
State of the region address   cordillera administrative regionState of the region address   cordillera administrative region
State of the region address cordillera administrative region
 
Red and black schoolbuilding program inspection report
Red and black schoolbuilding program inspection reportRed and black schoolbuilding program inspection report
Red and black schoolbuilding program inspection report
 
National greening program inspection report
National greening program inspection reportNational greening program inspection report
National greening program inspection report
 
ARISP III Inspection Report
ARISP III Inspection ReportARISP III Inspection Report
ARISP III Inspection Report
 
2012 rpmc inspection reports
2012 rpmc inspection reports2012 rpmc inspection reports
2012 rpmc inspection reports
 
Eo no. 78 2012
Eo no. 78 2012Eo no. 78 2012
Eo no. 78 2012
 

2nd qtr rpmes 2012

  • 1. Regional Project Monitoring and Evaluation System Prepared by the National Economic and Development Authority Cordillera Administrative Region RPMC Secretariat
  • 2. Second Quarter CY 2012 RPMES Report The Regional Project Monitoring and Evaluation System (RPMES) report is published quarterly to provide an overall view on the status of major programs/projects (P/Ps) in the Cordillera Administrative Region (CAR). The report is based primarily from the submission of eleven regional line agencies (RLAs). The detailed report is regularly posted in the RDC-CAR webpage. CY 2012 Major Programs / Projects For CY 2012, the RPMES Report contains 46 major P/Ps with an aggregate cost of Php 10.414 Billion. These P/Ps were enrolled in the monitoring system by the eleven RLAs. The projects are grouped according to sector/ program, namely: Social, Economic, Infrastructure and Strategic Action Plan (SAP) for the rehabilitation & recovery of disaster-afflicted areas. The following table shows the total cost and physical accomplishment by sector/ program as of end- June 2012. Cost and Physical Accomplishment by Sector/ Program, CAR As of June 2012 Percentage Accomplishment Sector/ Program Cost (Php M.) Cost (ao June 2012) a) Social Sector 1,788.255 17.17 % 41.17 % b) Economic Sector 5,424.533 52.09 % 26.37 % c) Infrastructure Sector 2,794.801 26.83 % 30.61 % d) Strategic Action Plan 406.722 3.91 % 96.24% (Rehabilitation & Recovery Program) CAR Total 10,414.311 100 % 32.78 % In terms of cost, Economic Sector has the highest with Php 5.4 B or 52 percent. This is costing Php 3.1 Billion. Infrastructure Sector follows with Php 2.8 Billion or 26.83 percent. While the Social Sector and SAP have Php 1.8 B. or 17.17 percent and Php 406.7 M. or barely 4 percent, respectively. 1
  • 3. Some 7.11 percent, amounting to Php 740.45 M. are carryover projects. The bulk of these are implemented by DepEd, DPWH and DOH. While 38.27 percent or Php 3.99 B. are multiyear projects and 54.62 percent, amounting to Php 5.79 Billion are new projects for the current year. In terms of fund source, Php 3.34 B. or 32.12 percent are foreign-assisted while Php 7.07 B or 67.88 % are GOP funded. In terms of implementation status, the overall physical accomplishment is 32.78 percent. It is expected by the second semester, project progress will pick-up due to the improved weather condition. The SAP which is mostly carryover projects posted 96.24 percent. The SAP projects, by DPWH and DepEd, are rehabilitation and recovery projects for the disaster-affected areas particularly Typhoons Juan, Pedring and Quiel. The Social Sector obtained an accomplishment of 41.17 percent. The sector is dominated by the Pantawid Pamilyang Pilipino Program (4Ps), Php 745.5 M.; Red & Black School Building Program (Php 266.1 M.); health facilities (Php 453.1 M.) and water system projects (Php 184.5 M.). 2
  • 4. The Infrastructure Sector and Economic Sector achieved 30.61 percent and 26.37 percent, respectively. The Infrastructure Sector is basically road and bridge projects. The large projects in Economic Sector are (Php 1.078 B.), The relatively low performance of the Economic Sector is largely attributed to the delayed implementation of the multi-year and ODA-assisted CHARMP 2. This has bearing due to its large cost and posting an accomplishment of merely 18.66 percent. The project underwent another NEDA-ICC process for a project reconfiguration to address the concern of LGU beneficiaries in putting up their cash counterpart. CY 2012 Priority Sectoral Programs/ Projects From among the 46 major program/ projects, priority P/Ps were selected by the Sectors based on the RPMES national forum criteria: (a) foreign-assisted projects (FAP/ODA), (b) interprovincial, (c) large scale cost, (d) national priority, critical projects by the Office of the President (OP), and (e) regional priority. The eight (8) major P/Ps are subject of closer RPMC-CAR monitoring through field validation and inspection. These major P/Ps have a total cost of Php 5.3 B., to wit: 1. Second Cordillera Highland Agricultural Resource Management Project (CHARMP 2), Php 3.08 B; 2. Pantawid Pamilyang Pilipino Program (4Ps), Php 745.5 M; 3. Agrarian Reform Infrastructure Support Project, Phase III, Php 903.8 M; 4. Kabugao-Solsona, Apayao-Ilocos Norte Road, Php 100M; 5. Kabugao-Pudtol- Luna- Cagayan Boundary Road, Php 58.8 M; 6. Cordillera-wide Strengthening of Local health System for Effective and Efficient Delivery of Maternal and Child Health Services, Php 43 M; 7. National Greening Program, Php 103.66 M; and 8. Red and Black Scholl Building Program, Php 266 M. 3
  • 5. RPMES 2nd Quarter Report CY 2012 MAJOR PROGRAMS/PROJECTS Cordillera Administrative Region As of June 2012 IMPLEMENTING PROJECT COST FUNDING STATUS/ PROGRAM/PROJECT AGENCY (PhP M) SOURCE REMARKS SOCIAL SECTOR 1. Pantawid Pamilyang Pilipino Program DSWD 745.512 Loan 47.09% (4Ps) 2. Red and Black School Building DepEd CY 2011: GOP CY 2011 fund: Program 50.952 89.22% 209 Classrooms CY 2012: CY 2012 fund: 115.200 7.69% 143 Classrooms 3. Cordillera-wide Strengthening of DOH & LGUs 43.00 JICA Project was Local Health System for Effective and Abra Apayao launched on Efficient Delivery of Maternal and Benguet March 13, 2012. Child Health Services However, the project has yet to fully take-off since JICA has yet to procure and deliver the medical equipment for the provinces of Abra and Apayao. 4. National Household Targeting System DSWD 40.793 GOP, 57.20% for Poverty Reduction Program Loan 5. Rehabilitation of School Building DepEd CY 2011: GOP CY 2011 Fund: including Water Sanitation Facilities 21.934 89.99% CY 2012: CY 2012 Fund: 29.340 Waiting for SARO 6. Philippine Response to Indigenous DepEd 3.978 AusAid 19% (PRIME) 4
  • 6. RPMES 2nd Quarter Report CY 2012 MAJOR PROGRAMS/PROJECTS Cordillera Administrative Region As of June 2012 IMPLEMENTING PROJECT COST FUNDING STATUS/ PROGRAM/PROJECT AGENCY (PhP M) SOURCE REMARKS 7. Construction of Various Health DOH CY 2011: GOP CY 2011 fund: Facility 117.867 58.55% CY 2012: CY 2012 fund: 335.179 6.49% 8. Water Supply System DOH 184.500 GOP 57.98% Sub-Total 1,788.255 41.17% ECONOMIC SECTOR 9. Second Cordillera Highland DA 3,081.862 IFAD, 18.66% Agricultural Resource Management ADB. OFID Project (CHARMP2) 10. Agrarian Reform Infrastructure DAR Total Project Loan 42.60% Support Project Phase III Cost: 903.863 GOP (Abra, Apayao, Benguet, Ifugao, Kalinga and Mt. Province) CY 2011: (2 projects) 16.718 CY 2012: (12 projects) 167.445 11. National Greening Program (NGP) DENR 103.663 GOP 48.53% 12. Farm-to-Market Roads DA CY 2011: Grant CY 2011: (CY 2011 Fund: 53.00 81.13% Abra, Kalinga and Mt. Province) CY 2012: CY 2012: (CY 2012 Fund: 161.803 11.56% Abra, Baguio City, Benguet, Ifugao, Kalinga and Mt. Province) 13. Irrigation Projects NIA 1,078.046 GOP 30.15% (432 projects) 14. One Town One Product Program DTI 2.747 GOP 84.68% (OTOP) 5
  • 7. RPMES 2nd Quarter Report CY 2012 MAJOR PROGRAMS/PROJECTS Cordillera Administrative Region As of June 2012 IMPLEMENTING PROJECT COST FUNDING STATUS/ PROGRAM/PROJECT AGENCY (PhP M) SOURCE REMARKS 15. Rural Micro Enterprise Promotion DTI 1.800 IFAD with 90% Programme (RuMEPP) GOP Counter Part 16. Shared Service Facilities Project DTI 8.388 NEDAC Awarding of (SSF) Fund bidding (National suppliers Export Develop- ment and Competi- tiveness) 17. Small Enterprise Technology DOST 28.673 GOP 100% Upgrading Program (SETUP) Core and Non-Core Funded Projects 18. Packaging and Labeling DOST 688.00 GOP 100% Sub-Total 5,424.533 26.37% INFRASTRUCTURE SECTOR Abra 19. Abra-Ilocos Sur Road DPWH 106.195 GOP 33.86% 20. Abra-Kalinga Road, K0467+000- DPWH 147.691 GOP 1.44% K0474+305 21. Abra-Ilocos Norte, K0436+700- DPWH 62.00 GOP 7.17% K0439+395 22. Road Upgrading along Abra- DPWH 60.00 GOP 1.03% Cervantes Road (Realigned from Sto. Tomas-Manabo Bridge) 23. Sto. Tomas-Manabo Bridge DPWH 160.00 GOP 58.62% 24. Abra-Kalinga Road K0410+000- DPWH 50.45 GOP 96.03% K0413+810 25. Abra-Kalinga Road K0437+490- DPWH 143.67 GOP 93% K0455+890, K0432+000, K0450+800 Apayao 26. Kabugao-Pudtol-Luna-Cagayan DPWH 58.827 GOP 40.70% Boundary Road K0661+000- K0661+321,K0643+646 - K0645+825 Gravel to Concrete 6
  • 8. RPMES 2nd Quarter Report CY 2012 MAJOR PROGRAMS/PROJECTS Cordillera Administrative Region As of June 2012 IMPLEMENTING PROJECT COST FUNDING STATUS/ PROGRAM/PROJECT AGENCY (PhP M) SOURCE REMARKS 27. Kabugao, Apayao-Solsona, Ilocos DPWH 100.00 GOP 0.50% Norte Road Benguet 28. DPWH 54.433 GOP 3.22% Kennon Road 29. Baguio-Bontoc Road (Pico-Lamtang DPWH 98.674 GOP 1.05% Rd., Baguio Itogon & Baguio-Bontoc) 30. Baguio-Bontoc Road, K0269+000- DPWH 109.332 GOP 15% K0275+000 (v.s.)& K0299+000- K0300+900 (v.s.) & K0305+000- K0308+500 (v.s.) & K0309+000- K0311+000 (v.s.), K0317+415- K0318+500 (v.s.), & K0323+000 K0328+000 (v.s.) 31. Gurel-Bokod-Kabayan-Buguias- DPWH 98.50 GOP 70% Abatan Road 32. Gurel-Bokod-Kabayan-Buguias- DPWH 116.50 GOP 88.88% Abatan Road K0303+600- K03012+000 33. -Bokod- DPWH 148.00 GOP 21.56% Kabayan-Buguias Road including RROW 34. Gurel-Bokod-Kabayan-Buguias- DPWH 68.921 GOP 24.43% Abatan Road, K0345+513-K0359+300 (vs.) Ifugao 35. Banaue-Mayoyao-A Lista-Isabela DPWH 58.064 GOP 0.50% Bdry. Road 36. Nueva Vizcaya-Ifugao-Mt. Province DPWH 54.163 GOP 17% Road Kalinga 37. Kalinga-Abra Road, K0470+000- DPWH 53.057 GOP 13.05% K0472+267 38. Kalinga-Abra Road, K0476+000- DPWH 135.27 GOP 0.60% K0480+1000, K0480+1000- K0482+700 (with exceptions) 39. Balbalan-Pinukpuk Road K0485+000- DPWH 100.00 GOP 63.80% K0489+000 40. Balbalan-Pinukpuk Road DPWH 245.00 GOP 27.10% K0560+1061-K0520+449 7
  • 9. RPMES 2nd Quarter Report CY 2012 MAJOR PROGRAMS/PROJECTS Cordillera Administrative Region As of June 2012 IMPLEMENTING PROJECT COST FUNDING STATUS/ PROGRAM/PROJECT AGENCY (PhP M) SOURCE REMARKS 41. Mt. Province Bdry. Calanan- DPWH 209.00 GOP 38% Pinukpuk Abbut Road (Pinukpuk) (P209.0 M) K0499+674-K0509+294 (I.S.) 42. Balbalan-Pinukpuk Road, Abut A of DPWH 183.239 GOP Advertised June Baay Bridge+(-18502) to Abut A of 21-25, 2012. Baay Bridge+0 Scheduled for bidding on July 10, 2012. Mountain Province 43. Mt. Province Ilocos Sur via Tue Road DPWH 81.815 GOP 20.75% 44. Mt. Province-Ilocos Sur via Kayan DPWH 92.00 GOP 30.35% Sub-Total 2,794.801 30.61% STRATEGIC ACTION PLAN (SAP) (Rehabilitation and Recovery of Areas Affected by Disasters) 45. Disaster Related Rehabilitation DPWH DRRP Project (DRRP) Calamity Fund CY 2011 a. Apayao 1st District Engineering 74,550.0 87.73% Office (16 projects) b. Apayao 2nd District Engineering 14,000.0 100% Office (5 projects) c. Benguet 1st District Engineering 45,469.0 100% Office (15 projects) d. Benguet 2nd District Engineering 39,279.1 100% Office (6 projects) e. Baguio City District Engineering 600.0 100% Office (1 project) f. Ifugao 1st District Engineering 8,580.0 100% Office (2 projects) g. Ifugao 2nd District Engineering 25,850.0 100% Office (4 projects) h. Kalinga District Engineering 85,910.5 95.93% Office (9 projects) i. Mt. Province District Office 102,459.4 100% (28 projects) Sub-Total 396.697 96.81% 8
  • 10. RPMES 2nd Quarter Report CY 2012 MAJOR PROGRAMS/PROJECTS Cordillera Administrative Region As of June 2012 IMPLEMENTING PROJECT COST FUNDING STATUS/ PROGRAM/PROJECT AGENCY (PhP M) SOURCE REMARKS 46. Quick Response Fund (QRF) DepEd GOP a. Cabaroan ES Dolores, Abra 1.201 56% (Construction of 1 unit-2 classroom in Bldg.1) b. Cabaroan ES Dolores, Abra 1.201 100% (Construction of 1 unit-2 classroom in Bldg.2) c. Cabaroan ES Dolores, Abra 318.0 79% (Construction of 3 Seater Toilet type III with handwashing) d. Cabaroan ES Dolores, Abra 219.0 71% (1 classroom repair) e. Tonglo Carino PS, Buguias, 1.201 15% Benguet f. Talubin NHS, Bontoc Mt. Province 1.143 65% (Construction of 2cl / Replacement of Burned Bldg.) g. Tumog Es, Luna, Apayao 1.942 70% (Construction of 1stry 3 Classroom 7x9 type I) h. Lagawe CS, Lagawe, Ifugao 1.200 100% (Construction of 2cl / Replacement of Burned Bldg.) i. Bañacao ES, Bangued West, Abra 1.600 100% (Repair of Classrooms / Construction of Slope Protection /Water System) Sub-Total 10.025 73.44% SAP Sub-Total 406.722 96.24% CAR Total 10,414.311 32.78% Sources: Agencies' RPMES PMC Form I - 2 as of end of June 2011 9
  • 11. Priority Sectoral Programs/ Projects, CAR As of June 2012 Status/ Cost Name of Fund Imp Remarks Description Location (Php) Project/Sector Source Entity As of June M 2012 Second The project has five components: Abra, 3,081.862 IFAD, DA 18.66% Cordillera Apayao, ADB. (1) Community mobilization, participatory Highland Benguet, OFID planning of investments, and land titling; (2) Agricultural Ifugao, community watershed conservation (including Resource Kalinga, forest management and agro forestry Management development); (3) agricultural and Mt. Project agribusiness development, and promotion of Province (CHARMP 2) income-generating activities; (4) rural infrastructure development; and (5) project management and coordination. Pantawid The program addresses the Millennium Region- 745.512 Loan DSWD 47.09% Pamilyang Development Goals such as reducing of wide Pilipino Program extreme poverty and hunger, achieving (4Ps) universal primary education, reducing child mortality, improving maternal health, and promoting gender equality and empowerment of women. The beneficiaries must meet the conditions of the program to avail cash grants and each household beneficiary will receive cash grants for at most five years. Agrarian Reform The project involves collaboration among the Abra, Total Loan DAR 42.60% Infrastructure implementing agencies (DAR, DPWH, LGU, Apayao, Project GOP Support Project and NIA) and Irrigators Associations. It Benguet, Cost: Phase III involves construction/rehabilitation of rural Ifugao, 903.863 1
  • 12. Priority Sectoral Programs/ Projects, CAR As of June 2012 Status/ Cost Name of Fund Imp Remarks Description Location (Php) Project/Sector Source Entity As of June M 2012 infrastructure such as irrigation facilities, farm- Kalinga, ( 2011) to-market roads, post-harvest facilities, and Mt. rural water supply systems, agrarian reform 16.718 Province information and marketing center building, development of coop managed agri- business/rural enterprise/ l (2012) organizations in the ARCs through 167.445 appropriate training and capacity building approaches. Kabugao, The road is a major component of the Kabugao, 100 GOP DPWH 0.50% Apayao-Solsona, Cordillera Roads Improvement Project (CRIP) Apayao Ilocos Norte as lateral road; it connects Ilocos Region and Road the Northern Cordilleras. It traverses the municipalities of Kabugao and Calanasan in Apayao and turns west to Solsona in Ilocos Norte. Kabugao-Pudtol- The road is a major component of the Apayao 58.827 GOP DPWH 40.70% Luna-Cagayan Cordillera Roads Improvement Project (CRIP) Boundary Road as the northern tip of the regional backbone. It K0661+000 - traverses the municipalities of Kabugao, K0661+321, Pudtol and Luna in Apayao and turns east to K0643+646 - Abulog in Cagayan. K0645+825 Gravel to Concrete 2
  • 13. Priority Sectoral Programs/ Projects, CAR As of June 2012 Status/ Cost Name of Fund Imp Remarks Description Location (Php) Project/Sector Source Entity As of June M 2012 Cordillera-wide Abra, 43 JICA DOH & Project was Strengthening of condition health condition particularly of Apayao LGUs launched on Local Health women and children through the delivery of Abra March 13, System for effective and efficient Maternal and Child Apayao 2012. Effective and Health (MCH) services. Benguet However, the Efficient Delivery project has yet The project seeks to: (a) strengthen the local of Maternal and to fully take-off health systems in all the CAR Provinces; and Child Health since JICA (b) improve the quality of health services. Services has yet to procure and deliver the medical equipments for the provinces of Abra and Apayao. National An administration priority program (Executive Region- 103.663 GOP DENR 48.53% Greening Order No. 26) that seeks to attain a wide Program (NGP) sustainable human development, economic and ecological security through the planting of 1.5 billion trees in around 1.5 million hectares of public land within six years from year 2011 to 2016. The NGP also aims to ensure food security, biodiversity conservation and address climate 3
  • 14. Priority Sectoral Programs/ Projects, CAR As of June 2012 Status/ Cost Name of Fund Imp Remarks Description Location (Php) Project/Sector Source Entity As of June M 2012 change. In the Cordillera, the target for CY 2012 is 7.5 million trees covering 15,000 hectares. Red and Black The Regular School Building Program Region- (CY 2011) GOP DepEd (CY 2011) School Building specifically targets schools which are wide 89.22% 150.952 Program categorized under the Red Zone or those which have a ratio of 56 or more students to (CY 2012) (CY 2012) one classroom: and the Black Zone, or 7.69% schools which make use of makeshift 115.200 classrooms and facilities. The standard DepEd design is 7m x 9m classroom for rural areas with a classroom- student ratio of 1:45. This standard also applies to all public secondary schools, regardless of location and class size. TOTAL: 5,302.879 28.84% 4