Strategic Planning : The best way to manage EPC Contract Risks 
Pankaj K Sinha Abu Dhabi 17th Nov 2014 
2ND CONTRACTS AND COMMERCIAL MANAGEMENT IN ENERGY CONFERENCE
2 
Risks in the EPC Contracting Process 
1.Project risk is an uncertain event or condition that, if it occurs, has a positive or negative effect on one or more project objectives such as scope, schedule, cost, and quality. : PMBOK Guide 
2.Risk shall be managed, minimized, shared, transferred or accepted. 
3.Appropriate and equitable allocation of a risk from early project life cycle is essential in all contractual arrangements to capitalize on them.
3 
Risk Build Up and Time 
Stage 1 
Stage 2 
Stage 3 
Stage 4 
Operation 
EPC 
FEED 
Feasibility Study 
Stage 2 
Design 
EPC PQ 
Risk Workshop 
Term Sheet 
Pre-bid conference 
RFP 
Stage 1 Business case Risk Workshop Stakeholders’ input Execution Strategy 
Stage 3 Risk Workshop Bidding & Contract Detailed Design Procurement Construction Commissioning
4 
Risks Allocation in the Contracting Process 
• 
The contracting environment is competitive and EPC scopes are complex. 
• 
Often risk allocation is through “aversion” 
• 
Inappropriate entities are often burdened with risks they can’t manage or survive. 
• 
Strategy for appropriate allocation of risks is very important for success for a project. 
Owner 
Contractor 
Subcontractor
5 
Risk- Industry Standards & References 
•ISO 31000:2009 Risk management - Principles and guidelines 
•A Guide to the Project Management Body of Knowledge (PMBOK® Guide) - PMI (ANSI/PMI 99-001-2013) 
•Practice Standard for Project Risk Management - PMI 
•BS 6079-3:2000: Project management. Guide to the management of business related project risk 
•International Project Risk Assessment (IPRA) – CII 
•AACE RP No. 62R-11 : Risk assessment: identification & qualitative analysis
6 
Potential IPRA Application Points 
Program Decision 
Pre-Project 
Planning 
Engineering & Design 
Construction 
Operations 
Secondary 
Primary 
= Potential application points
7 
Risk Management Strategy for EPC Contracts 
1. 
Risk Register as input from Risk Workshop. 
2. 
Finalize bidding strategy. EPC Contractor takes the major risks relating to the Cost , Schedule & Quality 
3. 
Identify risk that can be allocated or transferred to relevant parties and develop a risk matrix 
4. 
Contemplates factors that may diminish the practical effect of the intended risk allocation in the contractual arrangement. 
5. 
Refine the Risk Matrix and identify relevant parties. 
6. 
Develop contract provisions and insurance regimes 
7. 
Execute contract and administer for successful project delivery.
8 
Hot Button Risks (Typical) 
1. 
Site Conditions 
2. 
Joint & several responsibility 
3. 
Review and approvals 
4. 
Liquidated Damages for Delay & Performance 
5. 
Indemnity 
6. 
Insurance Allocation 
7. 
Force Majeure 
8. 
Change Management 
9. 
Nominated Subcontractors 
10. 
Design Responsibility 
11. 
Change in Law/Specifications/Regulations 
12. 
Standard of Care 
13. 
Performance and Acceptance Criteria 
14. 
Dispute Resolution 
Risk Workshop 
Stakeholders’ input on risks/due diligence 
Bid Package 
Contract
9 
Risk Allocation Matrix 
Risk 
Brief Details 
Risk probability 
Mitigation Measures 
Contractor 
Owner 
Insurance 
Site Conditions 
Joint & several responsibility 
Review and approvals 
Liquidated Damages for Delay & Performance 
Indemnity 
Insurance Allocation
10 
Insurance Program 
Risk 
Owner 
Contractor 
1.Construction All Risks 
2.Construction Delay in Start Up 
3.Marine Cargo / Transits 
4.Third Party Liability 
5.Professional Indemnity 
6.Employers Liability 
7.Workmen’s Compensation 
8.Contractors’ Plant & Equipment 
9.Auto Liability
11 
1. 
Enactment of new Laws or Regulations 
2. 
Force Majeure 
3. 
Currrency Risks 
4. 
Site Acsess 
5. 
Differing Site Conditions 
6. 
Errors, omissions, inconsistencies or discrepancies in the Specifications/Scope 
7. 
Change in Rely-upon Information 
8. 
Acceleration or disrupton by Client 
9. 
Delay or Suspension by Client 
10. 
Special Risks 
11. 
Delayed Approvals 
Contractor’s entitlement for Risk Events
12 
Risk Allocation in FIDIC Silver Book (FSB) 
•Drafted to be used internationally in 1999. Specifically introduced for Project Financed Works for Engineer, Procure, Construct i.e. EPC Contracts 
•Extensively debated in industry forums. 
•The Silver Book is recommended for use on process, power and private-infrastructure projects where a Contractor is to take on full responsibility for the design and execution of a project. Where certainty of final price and often of completion date are of extreme importance. 
•Risks for completion to time, cost and quality are transferred to the Contractor. 
•Employer’s Requirements can also be linked with Performance Specification 
•Substantial Risk transfer to the Contractor 
•Lump Sum Contract Price (adjustments in limited specified cases)
13 
Risk Allocation to Contractor (FSB) 
The risks are mostly allocated to the contractor. The following identify the main risks that have been allocated to the Contractor 
•Design obligations and errors 
•Setting Out risks i.e. errors in the ‘Items of reference’ 
•Unforeseeable Difficulties’ all necessary information as to risks, contingencies and other circumstances which may influence or affect the Works 
•sub-surface and hydrological conditions. The Contractor shall be responsible for verifying and interpreting such data. Owner is having no responsibility for the accuracy, sufficiency or completeness of such data. 
•Any data received does not relieve the contractor from responsibility for the design and execution except for specified rely upon data/information. 
•use or occupation by the Owner of any part of the Permanent Works, except as may be specified in the Contract 
•Indemnity obligations 
•Requirements can be linked with Performance Specification 
•Lump Sum Contract Price (adjustments in limited specified cases)
14 
Risk Allocation to Contractor (FSB) 
• 
war, hostilities (whether war be declared or not), invasion, act of foreign enemies, 
• 
rebellion, terrorism, revolution, insurrection, military or usurped power, or civil war, within the Country, 
• 
riot, commotion or disorder within the Country by persons other than the Contractor's Personnel and other employees of the Contractor and Subcontractors, 
• 
munitions of war, explosive materials, ionizing radiation or contamination by radio-activity, within the Country, except as may be attributable to the Contractor's use of such munitions, explosives, radiation or radio-activity, and 
• 
pressure waves caused by aircraft or other aerial devices travelling at sonic or supersonic speeds.
15 
Way Forward 
1. 
Increasing numbers of mega projects are executed under complex EPC commercial frameworks. Conclusive EPC agreement for a specific project can be a cumbersome but crucial task. It is important that owner and the contractor should be involved in the risk allocation process, which should begin early in the project life cycle. 
2.Use of industry standards & frameworks shall be encouraged. 
3.Appropriate risk allocation will encourage contracting parties to change the adversarial relationships to a more cooperative approach and successfully project delivery.
16 
Thank you Q & A

Weitere ähnliche Inhalte

Was ist angesagt?

FIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFrancis Ho
 
EPC_EPCM Business process modelling rendition
EPC_EPCM Business process modelling renditionEPC_EPCM Business process modelling rendition
EPC_EPCM Business process modelling renditionJaswin Sood
 
Epc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promoEpc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promoignitetribes
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementASHISH KUMAR SINGH
 
Contract Management
Contract Management Contract Management
Contract Management Dr K M SONI
 
Project Control Practical Way by Herve Baron
Project Control Practical Way by Herve BaronProject Control Practical Way by Herve Baron
Project Control Practical Way by Herve Baronignitetribes
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanAdrias TAN
 

Was ist angesagt? (20)

FIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power Projects
 
EPC Contracts
EPC Contracts EPC Contracts
EPC Contracts
 
EPC_EPCM Business process modelling rendition
EPC_EPCM Business process modelling renditionEPC_EPCM Business process modelling rendition
EPC_EPCM Business process modelling rendition
 
Why EPC
Why EPCWhy EPC
Why EPC
 
Fidic contracts management introduction
Fidic contracts management introductionFidic contracts management introduction
Fidic contracts management introduction
 
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP ContractsFIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
 
Contract Management
Contract ManagementContract Management
Contract Management
 
Construction Claims
Construction ClaimsConstruction Claims
Construction Claims
 
Epc contractor
Epc contractorEpc contractor
Epc contractor
 
Epc overview
Epc  overviewEpc  overview
Epc overview
 
Ppt on fidic claims
Ppt on fidic claimsPpt on fidic claims
Ppt on fidic claims
 
Epc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promoEpc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promo
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
Contract Management
Contract Management Contract Management
Contract Management
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
 
Fidic Form of Contract.
Fidic Form of Contract.Fidic Form of Contract.
Fidic Form of Contract.
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
 
Project Control Practical Way by Herve Baron
Project Control Practical Way by Herve BaronProject Control Practical Way by Herve Baron
Project Control Practical Way by Herve Baron
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
 
FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
 

Andere mochten auch

Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...HIMADRI BANERJI
 
Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)Roland_Nikles
 
Tender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process
 
Tender evaluation procedure
Tender evaluation procedureTender evaluation procedure
Tender evaluation procedureayushida
 
Introduction to programming01
Introduction to programming01Introduction to programming01
Introduction to programming01Nadim Ahmed
 
Fidic flow charts final
Fidic flow charts finalFidic flow charts final
Fidic flow charts finalFitBlar Mit
 
Contract & Tender Management
Contract & Tender ManagementContract & Tender Management
Contract & Tender ManagementAnand Subramaniam
 
Tendering in construction introduction
Tendering in construction introductionTendering in construction introduction
Tendering in construction introductionDaniel Ross
 
Tender processing
Tender processingTender processing
Tender processingdnyandev_d
 

Andere mochten auch (13)

EPC Business Model
EPC Business ModelEPC Business Model
EPC Business Model
 
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...
 
Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)
 
Tender
TenderTender
Tender
 
Tender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement Guide
 
Tender procedure slide
Tender procedure slideTender procedure slide
Tender procedure slide
 
Tender evaluation procedure
Tender evaluation procedureTender evaluation procedure
Tender evaluation procedure
 
Introduction to programming01
Introduction to programming01Introduction to programming01
Introduction to programming01
 
Fidic law1
Fidic law1Fidic law1
Fidic law1
 
Fidic flow charts final
Fidic flow charts finalFidic flow charts final
Fidic flow charts final
 
Contract & Tender Management
Contract & Tender ManagementContract & Tender Management
Contract & Tender Management
 
Tendering in construction introduction
Tendering in construction introductionTendering in construction introduction
Tendering in construction introduction
 
Tender processing
Tender processingTender processing
Tender processing
 

Ähnlich wie Strategic Planning : the best way to manage EPC Contract Risks

Assignment 1 Complete
Assignment 1 CompleteAssignment 1 Complete
Assignment 1 CompleteJohn Ashton
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Gregoire Lesecq
 
Winning tenders / securing tenderers in a competitive construction market - N...
Winning tenders / securing tenderers in a competitive construction market - N...Winning tenders / securing tenderers in a competitive construction market - N...
Winning tenders / securing tenderers in a competitive construction market - N...Browne Jacobson LLP
 
Beyond Engineering: EPC Lessons learnt from a Lenders' Technical and Environm...
Beyond Engineering: EPC Lessons learnt from a Lenders' Technical and Environm...Beyond Engineering: EPC Lessons learnt from a Lenders' Technical and Environm...
Beyond Engineering: EPC Lessons learnt from a Lenders' Technical and Environm...Sailesh Patel
 
Capital Project Risk Survey
Capital Project Risk SurveyCapital Project Risk Survey
Capital Project Risk SurveyEric Ho
 
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo
 
2015_0220_HAI_TM1-T6-05_F_cls
2015_0220_HAI_TM1-T6-05_F_cls2015_0220_HAI_TM1-T6-05_F_cls
2015_0220_HAI_TM1-T6-05_F_clsDennis Doherty
 
Managing Technical & Project Risks on Small Renewable Energy Projects (...
Managing Technical & Project Risks on Small Renewable Energy Projects (...Managing Technical & Project Risks on Small Renewable Energy Projects (...
Managing Technical & Project Risks on Small Renewable Energy Projects (...mtingle
 
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...EMLI Indonesia
 
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Rae Davies
 
PPP identification & STRUCTURING Conceptualising
PPP identification & STRUCTURINGConceptualisingPPP identification & STRUCTURINGConceptualising
PPP identification & STRUCTURING ConceptualisingDr. Heera Lal IAS
 
Owner's engineer services - statement of capabilities
Owner's engineer services - statement of capabilitiesOwner's engineer services - statement of capabilities
Owner's engineer services - statement of capabilitiesGensol Engineering Limited
 

Ähnlich wie Strategic Planning : the best way to manage EPC Contract Risks (20)

Assignment 1 Complete
Assignment 1 CompleteAssignment 1 Complete
Assignment 1 Complete
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016
 
Winning tenders / securing tenderers in a competitive construction market - N...
Winning tenders / securing tenderers in a competitive construction market - N...Winning tenders / securing tenderers in a competitive construction market - N...
Winning tenders / securing tenderers in a competitive construction market - N...
 
PROJECT_STEPS
PROJECT_STEPSPROJECT_STEPS
PROJECT_STEPS
 
Beyond Engineering: EPC Lessons learnt from a Lenders' Technical and Environm...
Beyond Engineering: EPC Lessons learnt from a Lenders' Technical and Environm...Beyond Engineering: EPC Lessons learnt from a Lenders' Technical and Environm...
Beyond Engineering: EPC Lessons learnt from a Lenders' Technical and Environm...
 
Capital Project Risk Survey
Capital Project Risk SurveyCapital Project Risk Survey
Capital Project Risk Survey
 
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
 
Pre Bid Risk Assessment
Pre Bid Risk AssessmentPre Bid Risk Assessment
Pre Bid Risk Assessment
 
2015_0220_HAI_TM1-T6-05_F_cls
2015_0220_HAI_TM1-T6-05_F_cls2015_0220_HAI_TM1-T6-05_F_cls
2015_0220_HAI_TM1-T6-05_F_cls
 
Managing Technical & Project Risks on Small Renewable Energy Projects (...
Managing Technical & Project Risks on Small Renewable Energy Projects (...Managing Technical & Project Risks on Small Renewable Energy Projects (...
Managing Technical & Project Risks on Small Renewable Energy Projects (...
 
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
 
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
 
Oman EPC 2015 summary and recommendations
Oman EPC 2015 summary and recommendationsOman EPC 2015 summary and recommendations
Oman EPC 2015 summary and recommendations
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Standard forms lgtf
Standard forms lgtfStandard forms lgtf
Standard forms lgtf
 
PPP identification & STRUCTURING Conceptualising
PPP identification & STRUCTURINGConceptualisingPPP identification & STRUCTURINGConceptualising
PPP identification & STRUCTURING Conceptualising
 
Contracting strategies for_terminal_construction
Contracting strategies for_terminal_constructionContracting strategies for_terminal_construction
Contracting strategies for_terminal_construction
 
Contracting strategies for_terminal_construction
Contracting strategies for_terminal_constructionContracting strategies for_terminal_construction
Contracting strategies for_terminal_construction
 
Owner's engineer services - statement of capabilities
Owner's engineer services - statement of capabilitiesOwner's engineer services - statement of capabilities
Owner's engineer services - statement of capabilities
 

Kürzlich hochgeladen

Triangulation survey (Basic Mine Surveying)_MI10412MI.pptx
Triangulation survey (Basic Mine Surveying)_MI10412MI.pptxTriangulation survey (Basic Mine Surveying)_MI10412MI.pptx
Triangulation survey (Basic Mine Surveying)_MI10412MI.pptxRomil Mishra
 
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMSHigh Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMSsandhya757531
 
Python Programming for basic beginners.pptx
Python Programming for basic beginners.pptxPython Programming for basic beginners.pptx
Python Programming for basic beginners.pptxmohitesoham12
 
Introduction to Artificial Intelligence: Intelligent Agents, State Space Sear...
Introduction to Artificial Intelligence: Intelligent Agents, State Space Sear...Introduction to Artificial Intelligence: Intelligent Agents, State Space Sear...
Introduction to Artificial Intelligence: Intelligent Agents, State Space Sear...shreenathji26
 
AntColonyOptimizationManetNetworkAODV.pptx
AntColonyOptimizationManetNetworkAODV.pptxAntColonyOptimizationManetNetworkAODV.pptx
AntColonyOptimizationManetNetworkAODV.pptxLina Kadam
 
ADM100 Running Book for sap basis domain study
ADM100 Running Book for sap basis domain studyADM100 Running Book for sap basis domain study
ADM100 Running Book for sap basis domain studydhruvamdhruvil123
 
Detection&Tracking - Thermal imaging object detection and tracking
Detection&Tracking - Thermal imaging object detection and trackingDetection&Tracking - Thermal imaging object detection and tracking
Detection&Tracking - Thermal imaging object detection and trackinghadarpinhas1
 
Artificial Intelligence in Power System overview
Artificial Intelligence in Power System overviewArtificial Intelligence in Power System overview
Artificial Intelligence in Power System overviewsandhya757531
 
Novel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending ActuatorsNovel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending ActuatorsResearcher Researcher
 
Secure Key Crypto - Tech Paper JET Tech Labs
Secure Key Crypto - Tech Paper JET Tech LabsSecure Key Crypto - Tech Paper JET Tech Labs
Secure Key Crypto - Tech Paper JET Tech Labsamber724300
 
Theory of Machine Notes / Lecture Material .pdf
Theory of Machine Notes / Lecture Material .pdfTheory of Machine Notes / Lecture Material .pdf
Theory of Machine Notes / Lecture Material .pdfShreyas Pandit
 
Module-1-(Building Acoustics) Noise Control (Unit-3). pdf
Module-1-(Building Acoustics) Noise Control (Unit-3). pdfModule-1-(Building Acoustics) Noise Control (Unit-3). pdf
Module-1-(Building Acoustics) Noise Control (Unit-3). pdfManish Kumar
 
22CYT12 & Chemistry for Computer Systems_Unit-II-Corrosion & its Control Meth...
22CYT12 & Chemistry for Computer Systems_Unit-II-Corrosion & its Control Meth...22CYT12 & Chemistry for Computer Systems_Unit-II-Corrosion & its Control Meth...
22CYT12 & Chemistry for Computer Systems_Unit-II-Corrosion & its Control Meth...KrishnaveniKrishnara1
 
KCD Costa Rica 2024 - Nephio para parvulitos
KCD Costa Rica 2024 - Nephio para parvulitosKCD Costa Rica 2024 - Nephio para parvulitos
KCD Costa Rica 2024 - Nephio para parvulitosVictor Morales
 
70 POWER PLANT IAE V2500 technical training
70 POWER PLANT IAE V2500 technical training70 POWER PLANT IAE V2500 technical training
70 POWER PLANT IAE V2500 technical trainingGladiatorsKasper
 
The Satellite applications in telecommunication
The Satellite applications in telecommunicationThe Satellite applications in telecommunication
The Satellite applications in telecommunicationnovrain7111
 
Indian Tradition, Culture & Societies.pdf
Indian Tradition, Culture & Societies.pdfIndian Tradition, Culture & Societies.pdf
Indian Tradition, Culture & Societies.pdfalokitpathak01
 
tourism-management-srs_compress-software-engineering.pdf
tourism-management-srs_compress-software-engineering.pdftourism-management-srs_compress-software-engineering.pdf
tourism-management-srs_compress-software-engineering.pdfchess188chess188
 
Analysis and Evaluation of Dal Lake Biomass for Conversion to Fuel/Green fert...
Analysis and Evaluation of Dal Lake Biomass for Conversion to Fuel/Green fert...Analysis and Evaluation of Dal Lake Biomass for Conversion to Fuel/Green fert...
Analysis and Evaluation of Dal Lake Biomass for Conversion to Fuel/Green fert...arifengg7
 

Kürzlich hochgeladen (20)

Triangulation survey (Basic Mine Surveying)_MI10412MI.pptx
Triangulation survey (Basic Mine Surveying)_MI10412MI.pptxTriangulation survey (Basic Mine Surveying)_MI10412MI.pptx
Triangulation survey (Basic Mine Surveying)_MI10412MI.pptx
 
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMSHigh Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
 
Python Programming for basic beginners.pptx
Python Programming for basic beginners.pptxPython Programming for basic beginners.pptx
Python Programming for basic beginners.pptx
 
Introduction to Artificial Intelligence: Intelligent Agents, State Space Sear...
Introduction to Artificial Intelligence: Intelligent Agents, State Space Sear...Introduction to Artificial Intelligence: Intelligent Agents, State Space Sear...
Introduction to Artificial Intelligence: Intelligent Agents, State Space Sear...
 
AntColonyOptimizationManetNetworkAODV.pptx
AntColonyOptimizationManetNetworkAODV.pptxAntColonyOptimizationManetNetworkAODV.pptx
AntColonyOptimizationManetNetworkAODV.pptx
 
ADM100 Running Book for sap basis domain study
ADM100 Running Book for sap basis domain studyADM100 Running Book for sap basis domain study
ADM100 Running Book for sap basis domain study
 
Detection&Tracking - Thermal imaging object detection and tracking
Detection&Tracking - Thermal imaging object detection and trackingDetection&Tracking - Thermal imaging object detection and tracking
Detection&Tracking - Thermal imaging object detection and tracking
 
Designing pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptxDesigning pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptx
 
Artificial Intelligence in Power System overview
Artificial Intelligence in Power System overviewArtificial Intelligence in Power System overview
Artificial Intelligence in Power System overview
 
Novel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending ActuatorsNovel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending Actuators
 
Secure Key Crypto - Tech Paper JET Tech Labs
Secure Key Crypto - Tech Paper JET Tech LabsSecure Key Crypto - Tech Paper JET Tech Labs
Secure Key Crypto - Tech Paper JET Tech Labs
 
Theory of Machine Notes / Lecture Material .pdf
Theory of Machine Notes / Lecture Material .pdfTheory of Machine Notes / Lecture Material .pdf
Theory of Machine Notes / Lecture Material .pdf
 
Module-1-(Building Acoustics) Noise Control (Unit-3). pdf
Module-1-(Building Acoustics) Noise Control (Unit-3). pdfModule-1-(Building Acoustics) Noise Control (Unit-3). pdf
Module-1-(Building Acoustics) Noise Control (Unit-3). pdf
 
22CYT12 & Chemistry for Computer Systems_Unit-II-Corrosion & its Control Meth...
22CYT12 & Chemistry for Computer Systems_Unit-II-Corrosion & its Control Meth...22CYT12 & Chemistry for Computer Systems_Unit-II-Corrosion & its Control Meth...
22CYT12 & Chemistry for Computer Systems_Unit-II-Corrosion & its Control Meth...
 
KCD Costa Rica 2024 - Nephio para parvulitos
KCD Costa Rica 2024 - Nephio para parvulitosKCD Costa Rica 2024 - Nephio para parvulitos
KCD Costa Rica 2024 - Nephio para parvulitos
 
70 POWER PLANT IAE V2500 technical training
70 POWER PLANT IAE V2500 technical training70 POWER PLANT IAE V2500 technical training
70 POWER PLANT IAE V2500 technical training
 
The Satellite applications in telecommunication
The Satellite applications in telecommunicationThe Satellite applications in telecommunication
The Satellite applications in telecommunication
 
Indian Tradition, Culture & Societies.pdf
Indian Tradition, Culture & Societies.pdfIndian Tradition, Culture & Societies.pdf
Indian Tradition, Culture & Societies.pdf
 
tourism-management-srs_compress-software-engineering.pdf
tourism-management-srs_compress-software-engineering.pdftourism-management-srs_compress-software-engineering.pdf
tourism-management-srs_compress-software-engineering.pdf
 
Analysis and Evaluation of Dal Lake Biomass for Conversion to Fuel/Green fert...
Analysis and Evaluation of Dal Lake Biomass for Conversion to Fuel/Green fert...Analysis and Evaluation of Dal Lake Biomass for Conversion to Fuel/Green fert...
Analysis and Evaluation of Dal Lake Biomass for Conversion to Fuel/Green fert...
 

Strategic Planning : the best way to manage EPC Contract Risks

  • 1. Strategic Planning : The best way to manage EPC Contract Risks Pankaj K Sinha Abu Dhabi 17th Nov 2014 2ND CONTRACTS AND COMMERCIAL MANAGEMENT IN ENERGY CONFERENCE
  • 2. 2 Risks in the EPC Contracting Process 1.Project risk is an uncertain event or condition that, if it occurs, has a positive or negative effect on one or more project objectives such as scope, schedule, cost, and quality. : PMBOK Guide 2.Risk shall be managed, minimized, shared, transferred or accepted. 3.Appropriate and equitable allocation of a risk from early project life cycle is essential in all contractual arrangements to capitalize on them.
  • 3. 3 Risk Build Up and Time Stage 1 Stage 2 Stage 3 Stage 4 Operation EPC FEED Feasibility Study Stage 2 Design EPC PQ Risk Workshop Term Sheet Pre-bid conference RFP Stage 1 Business case Risk Workshop Stakeholders’ input Execution Strategy Stage 3 Risk Workshop Bidding & Contract Detailed Design Procurement Construction Commissioning
  • 4. 4 Risks Allocation in the Contracting Process • The contracting environment is competitive and EPC scopes are complex. • Often risk allocation is through “aversion” • Inappropriate entities are often burdened with risks they can’t manage or survive. • Strategy for appropriate allocation of risks is very important for success for a project. Owner Contractor Subcontractor
  • 5. 5 Risk- Industry Standards & References •ISO 31000:2009 Risk management - Principles and guidelines •A Guide to the Project Management Body of Knowledge (PMBOK® Guide) - PMI (ANSI/PMI 99-001-2013) •Practice Standard for Project Risk Management - PMI •BS 6079-3:2000: Project management. Guide to the management of business related project risk •International Project Risk Assessment (IPRA) – CII •AACE RP No. 62R-11 : Risk assessment: identification & qualitative analysis
  • 6. 6 Potential IPRA Application Points Program Decision Pre-Project Planning Engineering & Design Construction Operations Secondary Primary = Potential application points
  • 7. 7 Risk Management Strategy for EPC Contracts 1. Risk Register as input from Risk Workshop. 2. Finalize bidding strategy. EPC Contractor takes the major risks relating to the Cost , Schedule & Quality 3. Identify risk that can be allocated or transferred to relevant parties and develop a risk matrix 4. Contemplates factors that may diminish the practical effect of the intended risk allocation in the contractual arrangement. 5. Refine the Risk Matrix and identify relevant parties. 6. Develop contract provisions and insurance regimes 7. Execute contract and administer for successful project delivery.
  • 8. 8 Hot Button Risks (Typical) 1. Site Conditions 2. Joint & several responsibility 3. Review and approvals 4. Liquidated Damages for Delay & Performance 5. Indemnity 6. Insurance Allocation 7. Force Majeure 8. Change Management 9. Nominated Subcontractors 10. Design Responsibility 11. Change in Law/Specifications/Regulations 12. Standard of Care 13. Performance and Acceptance Criteria 14. Dispute Resolution Risk Workshop Stakeholders’ input on risks/due diligence Bid Package Contract
  • 9. 9 Risk Allocation Matrix Risk Brief Details Risk probability Mitigation Measures Contractor Owner Insurance Site Conditions Joint & several responsibility Review and approvals Liquidated Damages for Delay & Performance Indemnity Insurance Allocation
  • 10. 10 Insurance Program Risk Owner Contractor 1.Construction All Risks 2.Construction Delay in Start Up 3.Marine Cargo / Transits 4.Third Party Liability 5.Professional Indemnity 6.Employers Liability 7.Workmen’s Compensation 8.Contractors’ Plant & Equipment 9.Auto Liability
  • 11. 11 1. Enactment of new Laws or Regulations 2. Force Majeure 3. Currrency Risks 4. Site Acsess 5. Differing Site Conditions 6. Errors, omissions, inconsistencies or discrepancies in the Specifications/Scope 7. Change in Rely-upon Information 8. Acceleration or disrupton by Client 9. Delay or Suspension by Client 10. Special Risks 11. Delayed Approvals Contractor’s entitlement for Risk Events
  • 12. 12 Risk Allocation in FIDIC Silver Book (FSB) •Drafted to be used internationally in 1999. Specifically introduced for Project Financed Works for Engineer, Procure, Construct i.e. EPC Contracts •Extensively debated in industry forums. •The Silver Book is recommended for use on process, power and private-infrastructure projects where a Contractor is to take on full responsibility for the design and execution of a project. Where certainty of final price and often of completion date are of extreme importance. •Risks for completion to time, cost and quality are transferred to the Contractor. •Employer’s Requirements can also be linked with Performance Specification •Substantial Risk transfer to the Contractor •Lump Sum Contract Price (adjustments in limited specified cases)
  • 13. 13 Risk Allocation to Contractor (FSB) The risks are mostly allocated to the contractor. The following identify the main risks that have been allocated to the Contractor •Design obligations and errors •Setting Out risks i.e. errors in the ‘Items of reference’ •Unforeseeable Difficulties’ all necessary information as to risks, contingencies and other circumstances which may influence or affect the Works •sub-surface and hydrological conditions. The Contractor shall be responsible for verifying and interpreting such data. Owner is having no responsibility for the accuracy, sufficiency or completeness of such data. •Any data received does not relieve the contractor from responsibility for the design and execution except for specified rely upon data/information. •use or occupation by the Owner of any part of the Permanent Works, except as may be specified in the Contract •Indemnity obligations •Requirements can be linked with Performance Specification •Lump Sum Contract Price (adjustments in limited specified cases)
  • 14. 14 Risk Allocation to Contractor (FSB) • war, hostilities (whether war be declared or not), invasion, act of foreign enemies, • rebellion, terrorism, revolution, insurrection, military or usurped power, or civil war, within the Country, • riot, commotion or disorder within the Country by persons other than the Contractor's Personnel and other employees of the Contractor and Subcontractors, • munitions of war, explosive materials, ionizing radiation or contamination by radio-activity, within the Country, except as may be attributable to the Contractor's use of such munitions, explosives, radiation or radio-activity, and • pressure waves caused by aircraft or other aerial devices travelling at sonic or supersonic speeds.
  • 15. 15 Way Forward 1. Increasing numbers of mega projects are executed under complex EPC commercial frameworks. Conclusive EPC agreement for a specific project can be a cumbersome but crucial task. It is important that owner and the contractor should be involved in the risk allocation process, which should begin early in the project life cycle. 2.Use of industry standards & frameworks shall be encouraged. 3.Appropriate risk allocation will encourage contracting parties to change the adversarial relationships to a more cooperative approach and successfully project delivery.
  • 16. 16 Thank you Q & A