// Achieving the Unachievable
  A Case Study on Aligning a Project with Stakeholder Expectations




               Dr. Dan Patterson, PMP
                CEO & President, Acumen

                    February 2012




                              +1 512 291 6261 // info@projectacumen.com

                                       www.projectacumen.com
Table of Contents
     	
  
  Introduction to the Project ........................................................................................... 3
  S1: The Starting Point .................................................................................................. 4
  S1 > S2: Creating a More Realistic Schedule .............................................................. 4
            Figure 1 – Float Comparison between Original S1, Resolved S2 Schedules ......... 5
  S2 > S3: Understanding the True Risk Exposure .......................................................... 5
            Figure 2 – Team Perception and Reality of True Risk Exposure ............................ 6
  S3 > S4: Establishing an Achievable Acceleration Scenario ........................................ 7
  S4 > S5: Tying it All Together ...................................................................................... 8
  Conclusions ................................................................................................................. 9
            Figure 3 – Summary of S1 S5 Schedule Maturity Dates ...................................... 9
            Figure 4 – P75 Delay from Original Dec 2013 First Gas ..................................... 10




+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                                     2
Achieving the Unachievable
A case study on aligning a project with stakeholder objectives.
This case study describes how a major capital expenditure project was able to achieve
a faster, risk-adjusted and still achievable schedule using a combination of schedule
and risk analytics, based on the Acumen S1>S5™ schedule maturity framework built
into the Fuse project analysis platform.


Through groundbreaking analytics and reporting techniques, what was originally
deemed to be unachievable—a faster, less risky project that would enable a faster-to-
market gas production facility, was achieved. The techniques used reduced the original
project forecasted duration by almost one year, and in parallel, reduced the forecasted
risk exposure, aligning the project to stakeholder expectations and ultimately leading to
a successful, timely sanction and approval of funding.


Introduction to the Project
The project in question was an onshore gas pipeline and facility development project
being built in-country, on a greenfield site. Owned by a company we will refer to as
“GasCom”, the project was in the early FEED stage rapidly headed towards project
sanction and official funding from GasCom’s investment board.


Timely sanction had previously been threatened by numerous delays in Pre-FEED/FEED
activities relating to location of the LNG processing facility and land acquisition
uncertainties. Further, the forecasted completion date developed in a CPM schedule
was out of alignment with the target date being requested by the business development
team at GasCom. In order to try and get the project back on track and proceed to
sanction with an aggressive, yet achievable first gas completion date of December
2013, the GasCom project team conducted a complete schedule and risk review on the
project.




+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       3
S1: The Starting Point
Schedule developed by the project team.
S1 Result: First Gas forecast date of December 2013.


S1 > S2: Creating a More Realistic Schedule
The first step in the alignment process was to conduct a schedule critique. The
schedule review was conducted to ensure that the schedule was of sound basis so that
a realistic forecast could be presented to the sanction board.


The project team adopted the Acumen Fuse Quality Index™, a schedule quality score
comprising multiple schedule metrics accounting for quality of logic, use of constraints,
float analysis and more1. From the schedule critique, the schedule shortcomings, where
appropriate, were corrected (e.g., missing logic added; redundant logic removed;
constraints used only where relevant; long lags converted to true activities; and,
elimination of negative float). The net result of these fixes was a new First Gas
completion date of May 2014, five months later than the originally forecasted date.


This analysis additionally provided insight into how the float in the schedule varied over
time. Prior to the schedule review, the project team perceived there to be a high amount
of float in the early stages of the project. This was viewed as an opportunity to gain
back the previously lost time leading up to sanction and beyond. In reality, once the
schedule corrections had been applied, the float analysis showed a very different
picture. Figure 1 shows how the amount (and distribution over time) of the average float
shifted significantly to the right as a result of the schedule fixes. Therefore, the original
perception of front-end float availability to help regain lost time was flawed, as this float
was not in fact available. Added to this, the order of magnitude of average float
decreased as a result of the schedule fixes—in layman’s terms: the schedule had
become tighter with less opportunity for easy compression or time adjustment through
absorption of float.

1
 For details and descriptions on the metrics included in the Fuse Quality Index™, see the Fuse Metrics &
Descriptions guide at http://www.projectacumen.com/fuse/information/downloads.


+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                            4
Originally percieved opportunity for   Resolved schedule not
                                  making up lost time through float      offering early stage
  60                             absorption in early stage of project   schedule acceleration

  40

   20
    0
        Q1 Q2 Q3
       2011 2011 2011 Q4 Q1 Q2 Q3
                       2011 2012            Q4   Q1
                                 2012 2012            Q2   Q3
                                           2012 2013            Q4   Q1
                                                     2013 2013            Q2   Q3
                                                               2013 2014                         Q4
                                                                         2014 2014
                S1 Average Float                                                                2014

              S2 Average Float




   Figure 1 – Float Comparison between the Original S1 and Resolved S2 Schedules

Following this analysis, the project team concluded that while they now had a much
more realistic schedule (albeit five months late on paper), the opportunity for making up
this lost time without making significant schedule adjustments was no longer possible.


With this key objective still in mind, a risk analysis was firstly needed in order to better
understand the true schedule risk exposure of the project. While the sanction board
wanted an accurate First Gas date, they requested this information in the form of a risk-
adjusted P75 date—in other words, a date that the project team was 75% confident of
achieving or better yet, actually beating. In order to achieve a P75 December 2013 date,
the deterministic schedule would need to be even earlier…


S2 result: a much more accurate, realistic schedule but with a five month later First Gas
forecast date of May 2014.


S2 > S3: Understanding the True Risk Exposure
A risk workshop was then conducted capturing the team’s buy-in to the realism or
aggressiveness of the durations (schedule uncertainty) as well as the identified key risk
events to determine the true P75 date. These two sets of risk inputs were used as the
basis for running a Monte Carlo Risk analysis. Rather than just relying on traditional risk
+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                                5
reporting such as risk histograms and tornado charts, the results of the risk analysis
were dissected using Acumen Fuse® libraries of risk metrics (risk hotspots, average risk
range, etc.) in order to give a more insightful view into exactly where and when the true
risk exposure lay. Pinpointing the drivers of risk is essential in the path to reducing risk
exposure.


Figure 2 shows how the team’s view of highly aggressive activities compared to the
time-phased risk exposure results. It was determined that while the team perceived
most of the risk to be in the early stages of the project, in reality the opposite was true.
A majority of the true risk hotspots™ in the schedule sat well towards the latter end.


The reason for the two highly contrasting curves was the fact that the in-field
construction phase of the project was dependent upon a large number of upstream
schedule paths, including the completion of the pipeline, the gathering field and partial
completion of the LNG facility itself. These converging dependencies (risk hotspots™)
forced the risk profile of the project to be heavily back-end loaded.
This was the first time the project team was able to see that, despite the schedule
aggressiveness early on in the project, the knock-on effect of this accumulation of risk
would not materialize until late in the project, at a time where risk reduction or
mediation would be far too late to be effective.

  70%
                               Team Perception
  60%
                               Actual Risk Hotspots
  50%
  40%
  30%
  20%
  10%
   0%
          Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4                 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
         2011 2011 2011 2011 2012 2012 2012 2012 2013 2013 2013 2013 2014 2014 2014 2014



              Figure 2 – Team Perception and Reality of True Risk Exposure


+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                            6
With very little float available in the early stages of the project and a heavily back-end
loaded risk profile, the outlook for being able to defend an on-time December 2013 First
Gas was very bleak. To make matters worse, the P75 risk-adjusted forecast was
showing October 2014, an additional five-month slip beyond the S2 schedule-resolved
date of May 2014. In total this was 10 months later than the sanction board’s expected
P75 December 2013 completion date.


The turning point in this process was the realization that if the schedule was presented
as it currently stood, the project would, at best, be sanctioned but end up massively
late and, at worst, not even make it through the sanction stage gate, essentially
resulting in an indefinite hold on the project. Having this insight early on with the
numbers to prove it, the project team embarked on a proactive risk-reduced and
accelerated scenario generation exercise…


S3 result: an accurate schedule that carried a high risk profile showing a P75 date of
October 2014, 10 months later than December 2013.


S3 > S4: Establishing an Achievable Acceleration Scenario
A two-prong approach was used to establish an accelerated scenario that would move
closer towards satisfying the December 2013 target S1 date. First, the project team
agreed upon a set of activities that were viable candidates for schedule compression or
acceleration. Then, an aggressive risk mitigation plan was developed, targeting the risk
hotspots in the schedule, reducing their exposure and in turn reducing the P75
schedule slip.


In parallel, specific sets of activities were targeted for acceleration. A proven schedule
acceleration approach offered in Fuse 3602 was adopted.




2
 Fuse 360 is an acceleration and decision support software offered by Acumen. Fuse 360 uses a
simulation technique that iteratively accelerates targeted activities or groups of activities, using user-
defined rules and criteria.


+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                               7
This approach uses a simulation technique that iteratively accelerates targeted activities
on a critical path based on a set of defined rules and criteria. This intelligent means of
schedule acceleration provides a perfect blend of scientific optimization with the insight
and experience of the project team determining which activities to focus on, and give
priority to, during the acceleration exercise.


Consideration was given to incentivizing specific disciplines, accelerating early site
works, adding additional engineering resources to specific high-risk design tasks and
commercial incentives for contractors to complete early. This set of criteria formed the
basis of the rules used during the generation of the accelerated scenario.


By running this simulation, a new accelerated scenario (S4) was established that gave a
forecasted First Gas completion date of August 2013. In absence of risk, this date was
forecasting completion four months prior to the P75 target first gas of December 2013.
Comparing a non-risk adjusted schedule with a First Gas date of August 2013 to a P75
risk-adjusted schedule with a First Gas date of December 2013 date was not a fair
comparison and so the team ran a risk analysis against the accelerated scenario. The
result of the risk analysis on the accelerated scenario was a risk-adjusted P75 S4 date
of February 2014 (mitigation was not included in the calculation of this date). This was
very close to the target December 2013. Reflecting a 6-month P75 risk exposure.


S4 result: an accurate, accelerated schedule showing a first gas date of Aug 2013 with a
corresponding P75 date of February 2014. This reflects a high-risk exposure of six
months.


S4 > S5: Tying it All Together
The final step in the schedule optimization was to obtain and account for team-buy-in
to the proposed mitigation plans. The risk mitigation plan component involved
developing plans that carried both a cost and schedule overhead so that a true ROI
picture could be established. This proved to be incredibly useful when presenting the
scenario to the board, as the project was able to later justify a $500MM additional



+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       8
spend in order to implement the mitigation plans and further reduce the risk exposure
by an additional two months.


S5 result: an accurate, risk-adjusted, accelerated, risk-mitigated, team validated First
Gas production date of August 2013 with a corresponding P75 date of December 2013,
in other words perfectly aligned with the sanction board’s expectations.


Conclusions
The net result of the combined risk reduction and schedule acceleration (S5) was as
follows:
    •   An S5 First Gas risk-adjusted date of December 2013 that fully satisfied the
        board’s expectation of a P75 sanctioned first gas date of December 2013
    •   A fully validated scenario that carried a high degree of realism
    •   A schedule that fully accounted for risk and uncertainty
    •   A schedule that had been accelerated and compressed using intelligence and
        insight from the project team in the form of targeted criteria
    •   A risk exposure profile of only four months (one month less than the risk profile
        of the original plan that forecast a completion date almost a year behind target)
    •   Full team buy-in into the proposed plan
    •   A highly aligned project-team and corporate sanction board.




                     P75 S4: Feb 2014




                   Figure 3 – Summary of S1 S5 Schedule Maturity Dates



+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       9
P75 Schedule Delay From Dec 2013 1st Gas
                                                           10
                                                            9
                                                                                             Resolved, risk-
                                                            8                                  adjusted,
                                                            7                                 accelerated,

                                (months)
                                                            6                                  mitigated
                                                            5                       10
                                                            4
                                                            3            5
                                                            2
                                                            1   0                            2                 0
                                                            0




                                                                             Scenario


                                                     Figure 4 – P75 Delay from Original Dec 2013 First Gas

While a successful project requires both a realistic plan as well as efficient execution,
the establishment of a sound, achievable schedule that accounts for risk and is aligned
with stakeholder expectations is the best foundation a project can hope for leading up
to execution.


Today, owners and contractors alike are using Acumen Fuse on thousands of major
CAPEX projects. Embedded within Fuse is the Acumen S1>S5™ schedule maturity
framework. More information on Acumen’s software and services can be found at
www.projectacumen.com.




+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                                                        10

Weitere ähnliche Inhalte

Was ist angesagt?

Engineering design process 3rd edition haik solutions manual
Engineering design process 3rd edition haik solutions manualEngineering design process 3rd edition haik solutions manual
Engineering design process 3rd edition haik solutions manualSummerfieldTBL
 
Planning A Complex Project
Planning A Complex ProjectPlanning A Complex Project
Planning A Complex ProjectChris Carson
 
An Overview Of Basic Planning & Scheduling Concepts
An Overview Of Basic Planning & Scheduling ConceptsAn Overview Of Basic Planning & Scheduling Concepts
An Overview Of Basic Planning & Scheduling ConceptsShankar Ganesh Radhakrishnan
 
Flood modelling of Periyar basin using SWAT
Flood modelling of Periyar basin using SWAT Flood modelling of Periyar basin using SWAT
Flood modelling of Periyar basin using SWAT RithwikMohan2
 
Teekay LNG Partners Q1-2015 Earnings Presentation
Teekay LNG Partners Q1-2015 Earnings Presentation Teekay LNG Partners Q1-2015 Earnings Presentation
Teekay LNG Partners Q1-2015 Earnings Presentation Teekay LNG Partners L.P.
 
OIL & GAS DRILLING- METHANE & VOCs (EPA White Paper)
OIL & GAS DRILLING- METHANE & VOCs (EPA White Paper)OIL & GAS DRILLING- METHANE & VOCs (EPA White Paper)
OIL & GAS DRILLING- METHANE & VOCs (EPA White Paper)Dr Dev Kambhampati
 

Was ist angesagt? (7)

Engineering design process 3rd edition haik solutions manual
Engineering design process 3rd edition haik solutions manualEngineering design process 3rd edition haik solutions manual
Engineering design process 3rd edition haik solutions manual
 
Modular Construction Conference 2012
Modular Construction Conference 2012Modular Construction Conference 2012
Modular Construction Conference 2012
 
Planning A Complex Project
Planning A Complex ProjectPlanning A Complex Project
Planning A Complex Project
 
An Overview Of Basic Planning & Scheduling Concepts
An Overview Of Basic Planning & Scheduling ConceptsAn Overview Of Basic Planning & Scheduling Concepts
An Overview Of Basic Planning & Scheduling Concepts
 
Flood modelling of Periyar basin using SWAT
Flood modelling of Periyar basin using SWAT Flood modelling of Periyar basin using SWAT
Flood modelling of Periyar basin using SWAT
 
Teekay LNG Partners Q1-2015 Earnings Presentation
Teekay LNG Partners Q1-2015 Earnings Presentation Teekay LNG Partners Q1-2015 Earnings Presentation
Teekay LNG Partners Q1-2015 Earnings Presentation
 
OIL & GAS DRILLING- METHANE & VOCs (EPA White Paper)
OIL & GAS DRILLING- METHANE & VOCs (EPA White Paper)OIL & GAS DRILLING- METHANE & VOCs (EPA White Paper)
OIL & GAS DRILLING- METHANE & VOCs (EPA White Paper)
 

Ähnlich wie Achieving the Unachievable: Aligning a Project with Stakeholder Expectations

Does better scheduling drive execution success ppt
Does better scheduling drive execution success pptDoes better scheduling drive execution success ppt
Does better scheduling drive execution success pptp6academy
 
Initial Project Meeting Agenda PowerPoint Presentation Slides
Initial Project Meeting Agenda PowerPoint Presentation Slides Initial Project Meeting Agenda PowerPoint Presentation Slides
Initial Project Meeting Agenda PowerPoint Presentation Slides SlideTeam
 
Basics of Project Planning
Basics of Project PlanningBasics of Project Planning
Basics of Project PlanningZilicus
 
Why Scheduling Mustn't Be Allowed to Become an Extinct Science
Why Scheduling Mustn't Be Allowed to Become an Extinct ScienceWhy Scheduling Mustn't Be Allowed to Become an Extinct Science
Why Scheduling Mustn't Be Allowed to Become an Extinct ScienceAcumen
 
Kickoff Meeting Powerpoint Presentation Slides
Kickoff Meeting Powerpoint Presentation SlidesKickoff Meeting Powerpoint Presentation Slides
Kickoff Meeting Powerpoint Presentation SlidesSlideTeam
 
Budgeting in SCRUM
Budgeting in SCRUM Budgeting in SCRUM
Budgeting in SCRUM Divante
 
Budgeting in SCRUM
Budgeting in SCRUM Budgeting in SCRUM
Budgeting in SCRUM Mati Polak
 
Kickoff Meeting PowerPoint Presentation Slides
Kickoff Meeting PowerPoint Presentation SlidesKickoff Meeting PowerPoint Presentation Slides
Kickoff Meeting PowerPoint Presentation SlidesSlideTeam
 
Meeting For Starting New Project Powerpoint Presentation Slides
Meeting For Starting New Project Powerpoint Presentation SlidesMeeting For Starting New Project Powerpoint Presentation Slides
Meeting For Starting New Project Powerpoint Presentation SlidesSlideTeam
 
PMI Global 2007 - Urucu/Manaus
PMI Global 2007 - Urucu/ManausPMI Global 2007 - Urucu/Manaus
PMI Global 2007 - Urucu/ManausPeter Mello
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.pptTinotendaChivese
 
Benchmarking Project Schedules
Benchmarking Project SchedulesBenchmarking Project Schedules
Benchmarking Project SchedulesAcumen
 
Kanban for Fixed Price Projects
Kanban for Fixed Price ProjectsKanban for Fixed Price Projects
Kanban for Fixed Price ProjectsSudipta Lahiri
 
Project Kickoff Meeting Agenda PowerPoint Presentation Slides
Project Kickoff Meeting Agenda PowerPoint Presentation SlidesProject Kickoff Meeting Agenda PowerPoint Presentation Slides
Project Kickoff Meeting Agenda PowerPoint Presentation SlidesSlideTeam
 
Work breakdown structure WBS Columbia Southe.docx
Work breakdown structure WBS Columbia Southe.docxWork breakdown structure WBS Columbia Southe.docx
Work breakdown structure WBS Columbia Southe.docxericbrooks84875
 
Baseline Compliance Analysis
Baseline Compliance AnalysisBaseline Compliance Analysis
Baseline Compliance AnalysisAcumen
 
Taming an Unruly Schedule with the 14 Point Schedule Assessment
Taming an Unruly Schedule with the 14 Point Schedule AssessmentTaming an Unruly Schedule with the 14 Point Schedule Assessment
Taming an Unruly Schedule with the 14 Point Schedule AssessmentAcumen
 

Ähnlich wie Achieving the Unachievable: Aligning a Project with Stakeholder Expectations (20)

Does better scheduling drive execution success ppt
Does better scheduling drive execution success pptDoes better scheduling drive execution success ppt
Does better scheduling drive execution success ppt
 
Initial Project Meeting Agenda PowerPoint Presentation Slides
Initial Project Meeting Agenda PowerPoint Presentation Slides Initial Project Meeting Agenda PowerPoint Presentation Slides
Initial Project Meeting Agenda PowerPoint Presentation Slides
 
Basics of Project Planning
Basics of Project PlanningBasics of Project Planning
Basics of Project Planning
 
CSC-1986.original
CSC-1986.originalCSC-1986.original
CSC-1986.original
 
Why Scheduling Mustn't Be Allowed to Become an Extinct Science
Why Scheduling Mustn't Be Allowed to Become an Extinct ScienceWhy Scheduling Mustn't Be Allowed to Become an Extinct Science
Why Scheduling Mustn't Be Allowed to Become an Extinct Science
 
Kickoff Meeting Powerpoint Presentation Slides
Kickoff Meeting Powerpoint Presentation SlidesKickoff Meeting Powerpoint Presentation Slides
Kickoff Meeting Powerpoint Presentation Slides
 
Budgeting in SCRUM
Budgeting in SCRUM Budgeting in SCRUM
Budgeting in SCRUM
 
Budgeting in SCRUM
Budgeting in SCRUM Budgeting in SCRUM
Budgeting in SCRUM
 
Kickoff Meeting PowerPoint Presentation Slides
Kickoff Meeting PowerPoint Presentation SlidesKickoff Meeting PowerPoint Presentation Slides
Kickoff Meeting PowerPoint Presentation Slides
 
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
 
Meeting For Starting New Project Powerpoint Presentation Slides
Meeting For Starting New Project Powerpoint Presentation SlidesMeeting For Starting New Project Powerpoint Presentation Slides
Meeting For Starting New Project Powerpoint Presentation Slides
 
PMI Global 2007 - Urucu/Manaus
PMI Global 2007 - Urucu/ManausPMI Global 2007 - Urucu/Manaus
PMI Global 2007 - Urucu/Manaus
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
 
Benchmarking Project Schedules
Benchmarking Project SchedulesBenchmarking Project Schedules
Benchmarking Project Schedules
 
Kanban for Fixed Price Projects
Kanban for Fixed Price ProjectsKanban for Fixed Price Projects
Kanban for Fixed Price Projects
 
Monthly Progress Report No.05 - June-2012
Monthly Progress Report No.05 - June-2012Monthly Progress Report No.05 - June-2012
Monthly Progress Report No.05 - June-2012
 
Project Kickoff Meeting Agenda PowerPoint Presentation Slides
Project Kickoff Meeting Agenda PowerPoint Presentation SlidesProject Kickoff Meeting Agenda PowerPoint Presentation Slides
Project Kickoff Meeting Agenda PowerPoint Presentation Slides
 
Work breakdown structure WBS Columbia Southe.docx
Work breakdown structure WBS Columbia Southe.docxWork breakdown structure WBS Columbia Southe.docx
Work breakdown structure WBS Columbia Southe.docx
 
Baseline Compliance Analysis
Baseline Compliance AnalysisBaseline Compliance Analysis
Baseline Compliance Analysis
 
Taming an Unruly Schedule with the 14 Point Schedule Assessment
Taming an Unruly Schedule with the 14 Point Schedule AssessmentTaming an Unruly Schedule with the 14 Point Schedule Assessment
Taming an Unruly Schedule with the 14 Point Schedule Assessment
 

Mehr von Acumen

How Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us DownHow Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us DownAcumen
 
Developing Standards for Enterprise Schedule Quality
Developing Standards for Enterprise Schedule QualityDeveloping Standards for Enterprise Schedule Quality
Developing Standards for Enterprise Schedule QualityAcumen
 
Simplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen riskSimplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen riskAcumen
 
Benchmarking Execution Performance and Earned Value
Benchmarking Execution Performance and Earned ValueBenchmarking Execution Performance and Earned Value
Benchmarking Execution Performance and Earned ValueAcumen
 
Fuse Customer Perspectives: Oil & Gas / Energy
Fuse Customer Perspectives: Oil & Gas / EnergyFuse Customer Perspectives: Oil & Gas / Energy
Fuse Customer Perspectives: Oil & Gas / EnergyAcumen
 
Acumen Fuse World Tour 2012
Acumen Fuse World Tour 2012Acumen Fuse World Tour 2012
Acumen Fuse World Tour 2012Acumen
 
Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Acumen
 
Meet or Exceed Schedule Expectations through Intelligent Acceleration
Meet or Exceed Schedule Expectations through Intelligent AccelerationMeet or Exceed Schedule Expectations through Intelligent Acceleration
Meet or Exceed Schedule Expectations through Intelligent AccelerationAcumen
 
Dr. McNatty Webinar: An Introduction to Acumen 360
Dr. McNatty Webinar: An Introduction to Acumen 360Dr. McNatty Webinar: An Introduction to Acumen 360
Dr. McNatty Webinar: An Introduction to Acumen 360Acumen
 
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise EnvironmentPMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise EnvironmentAcumen
 
Smarter Project Analysis and Improved Project Performance
Smarter Project Analysis and Improved Project PerformanceSmarter Project Analysis and Improved Project Performance
Smarter Project Analysis and Improved Project PerformanceAcumen
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsAcumen
 
Acumen Fuse & Customer Case Study
Acumen Fuse & Customer Case StudyAcumen Fuse & Customer Case Study
Acumen Fuse & Customer Case StudyAcumen
 
Acumen & ARES: Simplified Cost & Schedule Integration
Acumen & ARES: Simplified Cost & Schedule IntegrationAcumen & ARES: Simplified Cost & Schedule Integration
Acumen & ARES: Simplified Cost & Schedule IntegrationAcumen
 
2011 Acumen Annual Summit Keynote
2011 Acumen Annual Summit Keynote2011 Acumen Annual Summit Keynote
2011 Acumen Annual Summit KeynoteAcumen
 
Calgary Breakfast Seminar: Predict and Influence Project Success
Calgary Breakfast Seminar: Predict and Influence Project SuccessCalgary Breakfast Seminar: Predict and Influence Project Success
Calgary Breakfast Seminar: Predict and Influence Project SuccessAcumen
 
Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360Acumen
 
Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0Acumen
 
Successful Dispute Resolution
Successful Dispute ResolutionSuccessful Dispute Resolution
Successful Dispute ResolutionAcumen
 
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™Acumen
 

Mehr von Acumen (20)

How Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us DownHow Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us Down
 
Developing Standards for Enterprise Schedule Quality
Developing Standards for Enterprise Schedule QualityDeveloping Standards for Enterprise Schedule Quality
Developing Standards for Enterprise Schedule Quality
 
Simplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen riskSimplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen risk
 
Benchmarking Execution Performance and Earned Value
Benchmarking Execution Performance and Earned ValueBenchmarking Execution Performance and Earned Value
Benchmarking Execution Performance and Earned Value
 
Fuse Customer Perspectives: Oil & Gas / Energy
Fuse Customer Perspectives: Oil & Gas / EnergyFuse Customer Perspectives: Oil & Gas / Energy
Fuse Customer Perspectives: Oil & Gas / Energy
 
Acumen Fuse World Tour 2012
Acumen Fuse World Tour 2012Acumen Fuse World Tour 2012
Acumen Fuse World Tour 2012
 
Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?
 
Meet or Exceed Schedule Expectations through Intelligent Acceleration
Meet or Exceed Schedule Expectations through Intelligent AccelerationMeet or Exceed Schedule Expectations through Intelligent Acceleration
Meet or Exceed Schedule Expectations through Intelligent Acceleration
 
Dr. McNatty Webinar: An Introduction to Acumen 360
Dr. McNatty Webinar: An Introduction to Acumen 360Dr. McNatty Webinar: An Introduction to Acumen 360
Dr. McNatty Webinar: An Introduction to Acumen 360
 
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise EnvironmentPMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
 
Smarter Project Analysis and Improved Project Performance
Smarter Project Analysis and Improved Project PerformanceSmarter Project Analysis and Improved Project Performance
Smarter Project Analysis and Improved Project Performance
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance Standards
 
Acumen Fuse & Customer Case Study
Acumen Fuse & Customer Case StudyAcumen Fuse & Customer Case Study
Acumen Fuse & Customer Case Study
 
Acumen & ARES: Simplified Cost & Schedule Integration
Acumen & ARES: Simplified Cost & Schedule IntegrationAcumen & ARES: Simplified Cost & Schedule Integration
Acumen & ARES: Simplified Cost & Schedule Integration
 
2011 Acumen Annual Summit Keynote
2011 Acumen Annual Summit Keynote2011 Acumen Annual Summit Keynote
2011 Acumen Annual Summit Keynote
 
Calgary Breakfast Seminar: Predict and Influence Project Success
Calgary Breakfast Seminar: Predict and Influence Project SuccessCalgary Breakfast Seminar: Predict and Influence Project Success
Calgary Breakfast Seminar: Predict and Influence Project Success
 
Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360
 
Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0
 
Successful Dispute Resolution
Successful Dispute ResolutionSuccessful Dispute Resolution
Successful Dispute Resolution
 
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
 

Kürzlich hochgeladen

Guard Your Investments- Corporate Defaults Alarm.pdf
Guard Your Investments- Corporate Defaults Alarm.pdfGuard Your Investments- Corporate Defaults Alarm.pdf
Guard Your Investments- Corporate Defaults Alarm.pdfJasper Colin
 
Role of Information and technology in banking and finance .pptx
Role of Information and technology in banking and finance .pptxRole of Information and technology in banking and finance .pptx
Role of Information and technology in banking and finance .pptxNarayaniTripathi2
 
NO1 Certified Amil Baba In Lahore Kala Jadu In Lahore Best Amil In Lahore Ami...
NO1 Certified Amil Baba In Lahore Kala Jadu In Lahore Best Amil In Lahore Ami...NO1 Certified Amil Baba In Lahore Kala Jadu In Lahore Best Amil In Lahore Ami...
NO1 Certified Amil Baba In Lahore Kala Jadu In Lahore Best Amil In Lahore Ami...Amil baba
 
Uae-NO1 Rohani Amil In Islamabad Amil Baba in Rawalpindi Kala Jadu Amil In Ra...
Uae-NO1 Rohani Amil In Islamabad Amil Baba in Rawalpindi Kala Jadu Amil In Ra...Uae-NO1 Rohani Amil In Islamabad Amil Baba in Rawalpindi Kala Jadu Amil In Ra...
Uae-NO1 Rohani Amil In Islamabad Amil Baba in Rawalpindi Kala Jadu Amil In Ra...Amil baba
 
Economic Risk Factor Update: April 2024 [SlideShare]
Economic Risk Factor Update: April 2024 [SlideShare]Economic Risk Factor Update: April 2024 [SlideShare]
Economic Risk Factor Update: April 2024 [SlideShare]Commonwealth
 
PMFBY , Pradhan Mantri Fasal bima yojna
PMFBY , Pradhan Mantri  Fasal bima yojnaPMFBY , Pradhan Mantri  Fasal bima yojna
PMFBY , Pradhan Mantri Fasal bima yojnaDharmendra Kumar
 
Amil Baba In Pakistan amil baba in Lahore amil baba in Islamabad amil baba in...
Amil Baba In Pakistan amil baba in Lahore amil baba in Islamabad amil baba in...Amil Baba In Pakistan amil baba in Lahore amil baba in Islamabad amil baba in...
Amil Baba In Pakistan amil baba in Lahore amil baba in Islamabad amil baba in...amilabibi1
 
Overview of Inkel Unlisted Shares Price.
Overview of Inkel Unlisted Shares Price.Overview of Inkel Unlisted Shares Price.
Overview of Inkel Unlisted Shares Price.Precize Formely Leadoff
 
Uae-NO1 Kala Jadu specialist Expert in Pakistan kala ilam specialist Expert i...
Uae-NO1 Kala Jadu specialist Expert in Pakistan kala ilam specialist Expert i...Uae-NO1 Kala Jadu specialist Expert in Pakistan kala ilam specialist Expert i...
Uae-NO1 Kala Jadu specialist Expert in Pakistan kala ilam specialist Expert i...Amil baba
 
Uae-NO1 Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
Uae-NO1 Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...Uae-NO1 Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
Uae-NO1 Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...Amil baba
 
Financial Preparation for Millennia.pptx
Financial Preparation for Millennia.pptxFinancial Preparation for Millennia.pptx
Financial Preparation for Millennia.pptxsimon978302
 
Unveiling Poonawalla Fincorp’s Phenomenal Performance Under Abhay Bhutada’s L...
Unveiling Poonawalla Fincorp’s Phenomenal Performance Under Abhay Bhutada’s L...Unveiling Poonawalla Fincorp’s Phenomenal Performance Under Abhay Bhutada’s L...
Unveiling Poonawalla Fincorp’s Phenomenal Performance Under Abhay Bhutada’s L...beulahfernandes8
 
Market Morning Updates for 16th April 2024
Market Morning Updates for 16th April 2024Market Morning Updates for 16th April 2024
Market Morning Updates for 16th April 2024Devarsh Vakil
 
AnyConv.com__FSS Advance Retail & Distribution - 15.06.17.ppt
AnyConv.com__FSS Advance Retail & Distribution - 15.06.17.pptAnyConv.com__FSS Advance Retail & Distribution - 15.06.17.ppt
AnyConv.com__FSS Advance Retail & Distribution - 15.06.17.pptPriyankaSharma89719
 
Unit 4.1 financial markets operations .pdf
Unit 4.1 financial markets operations .pdfUnit 4.1 financial markets operations .pdf
Unit 4.1 financial markets operations .pdfSatyamSinghParihar2
 
NO1 Certified kala jadu karne wale ka contact number kala jadu karne wale bab...
NO1 Certified kala jadu karne wale ka contact number kala jadu karne wale bab...NO1 Certified kala jadu karne wale ka contact number kala jadu karne wale bab...
NO1 Certified kala jadu karne wale ka contact number kala jadu karne wale bab...Amil baba
 
INTERNATIONAL TRADE INSTITUTIONS[6].pptx
INTERNATIONAL TRADE INSTITUTIONS[6].pptxINTERNATIONAL TRADE INSTITUTIONS[6].pptx
INTERNATIONAL TRADE INSTITUTIONS[6].pptxaymenkhalfallah23
 
NO1 Certified Black Magic Specialist Expert In Bahawalpur, Sargodha, Sialkot,...
NO1 Certified Black Magic Specialist Expert In Bahawalpur, Sargodha, Sialkot,...NO1 Certified Black Magic Specialist Expert In Bahawalpur, Sargodha, Sialkot,...
NO1 Certified Black Magic Specialist Expert In Bahawalpur, Sargodha, Sialkot,...Amil baba
 
The AES Investment Code - the go-to counsel for the most well-informed, wise...
The AES Investment Code -  the go-to counsel for the most well-informed, wise...The AES Investment Code -  the go-to counsel for the most well-informed, wise...
The AES Investment Code - the go-to counsel for the most well-informed, wise...AES International
 

Kürzlich hochgeladen (20)

Guard Your Investments- Corporate Defaults Alarm.pdf
Guard Your Investments- Corporate Defaults Alarm.pdfGuard Your Investments- Corporate Defaults Alarm.pdf
Guard Your Investments- Corporate Defaults Alarm.pdf
 
Role of Information and technology in banking and finance .pptx
Role of Information and technology in banking and finance .pptxRole of Information and technology in banking and finance .pptx
Role of Information and technology in banking and finance .pptx
 
NO1 Certified Amil Baba In Lahore Kala Jadu In Lahore Best Amil In Lahore Ami...
NO1 Certified Amil Baba In Lahore Kala Jadu In Lahore Best Amil In Lahore Ami...NO1 Certified Amil Baba In Lahore Kala Jadu In Lahore Best Amil In Lahore Ami...
NO1 Certified Amil Baba In Lahore Kala Jadu In Lahore Best Amil In Lahore Ami...
 
Uae-NO1 Rohani Amil In Islamabad Amil Baba in Rawalpindi Kala Jadu Amil In Ra...
Uae-NO1 Rohani Amil In Islamabad Amil Baba in Rawalpindi Kala Jadu Amil In Ra...Uae-NO1 Rohani Amil In Islamabad Amil Baba in Rawalpindi Kala Jadu Amil In Ra...
Uae-NO1 Rohani Amil In Islamabad Amil Baba in Rawalpindi Kala Jadu Amil In Ra...
 
Economic Risk Factor Update: April 2024 [SlideShare]
Economic Risk Factor Update: April 2024 [SlideShare]Economic Risk Factor Update: April 2024 [SlideShare]
Economic Risk Factor Update: April 2024 [SlideShare]
 
PMFBY , Pradhan Mantri Fasal bima yojna
PMFBY , Pradhan Mantri  Fasal bima yojnaPMFBY , Pradhan Mantri  Fasal bima yojna
PMFBY , Pradhan Mantri Fasal bima yojna
 
Amil Baba In Pakistan amil baba in Lahore amil baba in Islamabad amil baba in...
Amil Baba In Pakistan amil baba in Lahore amil baba in Islamabad amil baba in...Amil Baba In Pakistan amil baba in Lahore amil baba in Islamabad amil baba in...
Amil Baba In Pakistan amil baba in Lahore amil baba in Islamabad amil baba in...
 
Overview of Inkel Unlisted Shares Price.
Overview of Inkel Unlisted Shares Price.Overview of Inkel Unlisted Shares Price.
Overview of Inkel Unlisted Shares Price.
 
Uae-NO1 Kala Jadu specialist Expert in Pakistan kala ilam specialist Expert i...
Uae-NO1 Kala Jadu specialist Expert in Pakistan kala ilam specialist Expert i...Uae-NO1 Kala Jadu specialist Expert in Pakistan kala ilam specialist Expert i...
Uae-NO1 Kala Jadu specialist Expert in Pakistan kala ilam specialist Expert i...
 
Uae-NO1 Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
Uae-NO1 Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...Uae-NO1 Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
Uae-NO1 Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
 
Financial Preparation for Millennia.pptx
Financial Preparation for Millennia.pptxFinancial Preparation for Millennia.pptx
Financial Preparation for Millennia.pptx
 
Unveiling Poonawalla Fincorp’s Phenomenal Performance Under Abhay Bhutada’s L...
Unveiling Poonawalla Fincorp’s Phenomenal Performance Under Abhay Bhutada’s L...Unveiling Poonawalla Fincorp’s Phenomenal Performance Under Abhay Bhutada’s L...
Unveiling Poonawalla Fincorp’s Phenomenal Performance Under Abhay Bhutada’s L...
 
Q1 2024 Newsletter | Financial Synergies Wealth Advisors
Q1 2024 Newsletter | Financial Synergies Wealth AdvisorsQ1 2024 Newsletter | Financial Synergies Wealth Advisors
Q1 2024 Newsletter | Financial Synergies Wealth Advisors
 
Market Morning Updates for 16th April 2024
Market Morning Updates for 16th April 2024Market Morning Updates for 16th April 2024
Market Morning Updates for 16th April 2024
 
AnyConv.com__FSS Advance Retail & Distribution - 15.06.17.ppt
AnyConv.com__FSS Advance Retail & Distribution - 15.06.17.pptAnyConv.com__FSS Advance Retail & Distribution - 15.06.17.ppt
AnyConv.com__FSS Advance Retail & Distribution - 15.06.17.ppt
 
Unit 4.1 financial markets operations .pdf
Unit 4.1 financial markets operations .pdfUnit 4.1 financial markets operations .pdf
Unit 4.1 financial markets operations .pdf
 
NO1 Certified kala jadu karne wale ka contact number kala jadu karne wale bab...
NO1 Certified kala jadu karne wale ka contact number kala jadu karne wale bab...NO1 Certified kala jadu karne wale ka contact number kala jadu karne wale bab...
NO1 Certified kala jadu karne wale ka contact number kala jadu karne wale bab...
 
INTERNATIONAL TRADE INSTITUTIONS[6].pptx
INTERNATIONAL TRADE INSTITUTIONS[6].pptxINTERNATIONAL TRADE INSTITUTIONS[6].pptx
INTERNATIONAL TRADE INSTITUTIONS[6].pptx
 
NO1 Certified Black Magic Specialist Expert In Bahawalpur, Sargodha, Sialkot,...
NO1 Certified Black Magic Specialist Expert In Bahawalpur, Sargodha, Sialkot,...NO1 Certified Black Magic Specialist Expert In Bahawalpur, Sargodha, Sialkot,...
NO1 Certified Black Magic Specialist Expert In Bahawalpur, Sargodha, Sialkot,...
 
The AES Investment Code - the go-to counsel for the most well-informed, wise...
The AES Investment Code -  the go-to counsel for the most well-informed, wise...The AES Investment Code -  the go-to counsel for the most well-informed, wise...
The AES Investment Code - the go-to counsel for the most well-informed, wise...
 

Achieving the Unachievable: Aligning a Project with Stakeholder Expectations

  • 1. // Achieving the Unachievable A Case Study on Aligning a Project with Stakeholder Expectations Dr. Dan Patterson, PMP CEO & President, Acumen February 2012 +1 512 291 6261 // info@projectacumen.com www.projectacumen.com
  • 2. Table of Contents   Introduction to the Project ........................................................................................... 3 S1: The Starting Point .................................................................................................. 4 S1 > S2: Creating a More Realistic Schedule .............................................................. 4 Figure 1 – Float Comparison between Original S1, Resolved S2 Schedules ......... 5 S2 > S3: Understanding the True Risk Exposure .......................................................... 5 Figure 2 – Team Perception and Reality of True Risk Exposure ............................ 6 S3 > S4: Establishing an Achievable Acceleration Scenario ........................................ 7 S4 > S5: Tying it All Together ...................................................................................... 8 Conclusions ................................................................................................................. 9 Figure 3 – Summary of S1 S5 Schedule Maturity Dates ...................................... 9 Figure 4 – P75 Delay from Original Dec 2013 First Gas ..................................... 10 +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 2
  • 3. Achieving the Unachievable A case study on aligning a project with stakeholder objectives. This case study describes how a major capital expenditure project was able to achieve a faster, risk-adjusted and still achievable schedule using a combination of schedule and risk analytics, based on the Acumen S1>S5™ schedule maturity framework built into the Fuse project analysis platform. Through groundbreaking analytics and reporting techniques, what was originally deemed to be unachievable—a faster, less risky project that would enable a faster-to- market gas production facility, was achieved. The techniques used reduced the original project forecasted duration by almost one year, and in parallel, reduced the forecasted risk exposure, aligning the project to stakeholder expectations and ultimately leading to a successful, timely sanction and approval of funding. Introduction to the Project The project in question was an onshore gas pipeline and facility development project being built in-country, on a greenfield site. Owned by a company we will refer to as “GasCom”, the project was in the early FEED stage rapidly headed towards project sanction and official funding from GasCom’s investment board. Timely sanction had previously been threatened by numerous delays in Pre-FEED/FEED activities relating to location of the LNG processing facility and land acquisition uncertainties. Further, the forecasted completion date developed in a CPM schedule was out of alignment with the target date being requested by the business development team at GasCom. In order to try and get the project back on track and proceed to sanction with an aggressive, yet achievable first gas completion date of December 2013, the GasCom project team conducted a complete schedule and risk review on the project. +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 3
  • 4. S1: The Starting Point Schedule developed by the project team. S1 Result: First Gas forecast date of December 2013. S1 > S2: Creating a More Realistic Schedule The first step in the alignment process was to conduct a schedule critique. The schedule review was conducted to ensure that the schedule was of sound basis so that a realistic forecast could be presented to the sanction board. The project team adopted the Acumen Fuse Quality Index™, a schedule quality score comprising multiple schedule metrics accounting for quality of logic, use of constraints, float analysis and more1. From the schedule critique, the schedule shortcomings, where appropriate, were corrected (e.g., missing logic added; redundant logic removed; constraints used only where relevant; long lags converted to true activities; and, elimination of negative float). The net result of these fixes was a new First Gas completion date of May 2014, five months later than the originally forecasted date. This analysis additionally provided insight into how the float in the schedule varied over time. Prior to the schedule review, the project team perceived there to be a high amount of float in the early stages of the project. This was viewed as an opportunity to gain back the previously lost time leading up to sanction and beyond. In reality, once the schedule corrections had been applied, the float analysis showed a very different picture. Figure 1 shows how the amount (and distribution over time) of the average float shifted significantly to the right as a result of the schedule fixes. Therefore, the original perception of front-end float availability to help regain lost time was flawed, as this float was not in fact available. Added to this, the order of magnitude of average float decreased as a result of the schedule fixes—in layman’s terms: the schedule had become tighter with less opportunity for easy compression or time adjustment through absorption of float. 1 For details and descriptions on the metrics included in the Fuse Quality Index™, see the Fuse Metrics & Descriptions guide at http://www.projectacumen.com/fuse/information/downloads. +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 4
  • 5. Originally percieved opportunity for Resolved schedule not making up lost time through float offering early stage 60 absorption in early stage of project schedule acceleration 40 20 0 Q1 Q2 Q3 2011 2011 2011 Q4 Q1 Q2 Q3 2011 2012 Q4 Q1 2012 2012 Q2 Q3 2012 2013 Q4 Q1 2013 2013 Q2 Q3 2013 2014 Q4 2014 2014 S1 Average Float 2014 S2 Average Float Figure 1 – Float Comparison between the Original S1 and Resolved S2 Schedules Following this analysis, the project team concluded that while they now had a much more realistic schedule (albeit five months late on paper), the opportunity for making up this lost time without making significant schedule adjustments was no longer possible. With this key objective still in mind, a risk analysis was firstly needed in order to better understand the true schedule risk exposure of the project. While the sanction board wanted an accurate First Gas date, they requested this information in the form of a risk- adjusted P75 date—in other words, a date that the project team was 75% confident of achieving or better yet, actually beating. In order to achieve a P75 December 2013 date, the deterministic schedule would need to be even earlier… S2 result: a much more accurate, realistic schedule but with a five month later First Gas forecast date of May 2014. S2 > S3: Understanding the True Risk Exposure A risk workshop was then conducted capturing the team’s buy-in to the realism or aggressiveness of the durations (schedule uncertainty) as well as the identified key risk events to determine the true P75 date. These two sets of risk inputs were used as the basis for running a Monte Carlo Risk analysis. Rather than just relying on traditional risk +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 5
  • 6. reporting such as risk histograms and tornado charts, the results of the risk analysis were dissected using Acumen Fuse® libraries of risk metrics (risk hotspots, average risk range, etc.) in order to give a more insightful view into exactly where and when the true risk exposure lay. Pinpointing the drivers of risk is essential in the path to reducing risk exposure. Figure 2 shows how the team’s view of highly aggressive activities compared to the time-phased risk exposure results. It was determined that while the team perceived most of the risk to be in the early stages of the project, in reality the opposite was true. A majority of the true risk hotspots™ in the schedule sat well towards the latter end. The reason for the two highly contrasting curves was the fact that the in-field construction phase of the project was dependent upon a large number of upstream schedule paths, including the completion of the pipeline, the gathering field and partial completion of the LNG facility itself. These converging dependencies (risk hotspots™) forced the risk profile of the project to be heavily back-end loaded. This was the first time the project team was able to see that, despite the schedule aggressiveness early on in the project, the knock-on effect of this accumulation of risk would not materialize until late in the project, at a time where risk reduction or mediation would be far too late to be effective. 70% Team Perception 60% Actual Risk Hotspots 50% 40% 30% 20% 10% 0% Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2011 2011 2011 2011 2012 2012 2012 2012 2013 2013 2013 2013 2014 2014 2014 2014 Figure 2 – Team Perception and Reality of True Risk Exposure +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 6
  • 7. With very little float available in the early stages of the project and a heavily back-end loaded risk profile, the outlook for being able to defend an on-time December 2013 First Gas was very bleak. To make matters worse, the P75 risk-adjusted forecast was showing October 2014, an additional five-month slip beyond the S2 schedule-resolved date of May 2014. In total this was 10 months later than the sanction board’s expected P75 December 2013 completion date. The turning point in this process was the realization that if the schedule was presented as it currently stood, the project would, at best, be sanctioned but end up massively late and, at worst, not even make it through the sanction stage gate, essentially resulting in an indefinite hold on the project. Having this insight early on with the numbers to prove it, the project team embarked on a proactive risk-reduced and accelerated scenario generation exercise… S3 result: an accurate schedule that carried a high risk profile showing a P75 date of October 2014, 10 months later than December 2013. S3 > S4: Establishing an Achievable Acceleration Scenario A two-prong approach was used to establish an accelerated scenario that would move closer towards satisfying the December 2013 target S1 date. First, the project team agreed upon a set of activities that were viable candidates for schedule compression or acceleration. Then, an aggressive risk mitigation plan was developed, targeting the risk hotspots in the schedule, reducing their exposure and in turn reducing the P75 schedule slip. In parallel, specific sets of activities were targeted for acceleration. A proven schedule acceleration approach offered in Fuse 3602 was adopted. 2 Fuse 360 is an acceleration and decision support software offered by Acumen. Fuse 360 uses a simulation technique that iteratively accelerates targeted activities or groups of activities, using user- defined rules and criteria. +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 7
  • 8. This approach uses a simulation technique that iteratively accelerates targeted activities on a critical path based on a set of defined rules and criteria. This intelligent means of schedule acceleration provides a perfect blend of scientific optimization with the insight and experience of the project team determining which activities to focus on, and give priority to, during the acceleration exercise. Consideration was given to incentivizing specific disciplines, accelerating early site works, adding additional engineering resources to specific high-risk design tasks and commercial incentives for contractors to complete early. This set of criteria formed the basis of the rules used during the generation of the accelerated scenario. By running this simulation, a new accelerated scenario (S4) was established that gave a forecasted First Gas completion date of August 2013. In absence of risk, this date was forecasting completion four months prior to the P75 target first gas of December 2013. Comparing a non-risk adjusted schedule with a First Gas date of August 2013 to a P75 risk-adjusted schedule with a First Gas date of December 2013 date was not a fair comparison and so the team ran a risk analysis against the accelerated scenario. The result of the risk analysis on the accelerated scenario was a risk-adjusted P75 S4 date of February 2014 (mitigation was not included in the calculation of this date). This was very close to the target December 2013. Reflecting a 6-month P75 risk exposure. S4 result: an accurate, accelerated schedule showing a first gas date of Aug 2013 with a corresponding P75 date of February 2014. This reflects a high-risk exposure of six months. S4 > S5: Tying it All Together The final step in the schedule optimization was to obtain and account for team-buy-in to the proposed mitigation plans. The risk mitigation plan component involved developing plans that carried both a cost and schedule overhead so that a true ROI picture could be established. This proved to be incredibly useful when presenting the scenario to the board, as the project was able to later justify a $500MM additional +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 8
  • 9. spend in order to implement the mitigation plans and further reduce the risk exposure by an additional two months. S5 result: an accurate, risk-adjusted, accelerated, risk-mitigated, team validated First Gas production date of August 2013 with a corresponding P75 date of December 2013, in other words perfectly aligned with the sanction board’s expectations. Conclusions The net result of the combined risk reduction and schedule acceleration (S5) was as follows: • An S5 First Gas risk-adjusted date of December 2013 that fully satisfied the board’s expectation of a P75 sanctioned first gas date of December 2013 • A fully validated scenario that carried a high degree of realism • A schedule that fully accounted for risk and uncertainty • A schedule that had been accelerated and compressed using intelligence and insight from the project team in the form of targeted criteria • A risk exposure profile of only four months (one month less than the risk profile of the original plan that forecast a completion date almost a year behind target) • Full team buy-in into the proposed plan • A highly aligned project-team and corporate sanction board. P75 S4: Feb 2014 Figure 3 – Summary of S1 S5 Schedule Maturity Dates +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 9
  • 10. P75 Schedule Delay From Dec 2013 1st Gas 10 9 Resolved, risk- 8 adjusted, 7 accelerated, (months) 6 mitigated 5 10 4 3 5 2 1 0 2 0 0 Scenario Figure 4 – P75 Delay from Original Dec 2013 First Gas While a successful project requires both a realistic plan as well as efficient execution, the establishment of a sound, achievable schedule that accounts for risk and is aligned with stakeholder expectations is the best foundation a project can hope for leading up to execution. Today, owners and contractors alike are using Acumen Fuse on thousands of major CAPEX projects. Embedded within Fuse is the Acumen S1>S5™ schedule maturity framework. More information on Acumen’s software and services can be found at www.projectacumen.com. +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 10