4th Itaú BBA LATAM Commodities Conference




 Maria das Graças Silva Foster
 Petrobras’ CEO




September 26th, 2012
DISCLAIMER

                                 FORWARD-LOOKING STATEMENTS

The presentation may contain forward-looking statements about                 We undertake no obligation to publicly update or revise any
future events within the meaning of Section 27A of the Securities Act         forward-looking statements, whether as a result of new
of 1933, as amended, and Section 21E of the Securities Exchange               information or future events or for any other reason. Figures
Act of 1934, as amended, that are not based on historical facts and           for 2012 on are estimates or targets.
are not assurances of future results. Such forward-looking
statements merely reflect the Company’s current views and
estimates of future economic circumstances, industry conditions,              All forward-looking statements are expressly qualified in their
company performance and financial results. Such terms as                      entirety by this cautionary statement, and you should not
"anticipate", "believe", "expect", "forecast", "intend", "plan", "project",   place reliance on any forward-looking statement contained in
"seek", "should", along with similar or analogous expressions, are            this presentation.
used to identify such forward-looking statements. Readers are
cautioned that these statements are only projections and may differ
materially from actual future results or events. Readers are referred         NON-SEC COMPLIANT OIL AND GAS RESERVES:
to the documents filed by the Company with the SEC, specifically the
                                                                              CAUTIONARY STATEMENT FOR US INVESTORS
Company’s most recent Annual Report on Form 20-F, which identify
important risk factors that could cause actual results to differ from         We present certain data in this presentation, such as oil and
those contained in the forward-looking statements, including, among           gas resources, that we are not permitted to present in
other things, risks relating to general economic and business                 documents filed with the United States Securities and
conditions, including crude oil and other commodity prices, refining          Exchange Commission (SEC) under new Subpart 1200 to
margins and prevailing exchange rates, uncertainties inherent in              Regulation S-K because such terms do not qualify as proved,
making estimates of our oil and gas reserves including recently               probable or possible reserves under Rule 4-10(a) of
discovered oil and gas reserves, international and Brazilian political,       Regulation S-X.
economic and social developments, receipt of governmental
approvals and licenses and our ability to obtain financing.
                                                                                                                                                2
Brazil: Economic and Social Development
Consumption Increase
                                                                                                                                                                                    BRAZIL




                                                                                                                                     Unemployment
                                                                                                                                                                                   -5.7 p.p.
                  UNEMPLOYMENT




                                                                                                                                         Rate
                                                                                                                                         (%)
              Jobs generation contributing to increase the wage bill.

                                                                                                                                                                       2002                           2011




                                                                                                                                     Extreme Poverty
                                                                                                                                                                                   -5.5 p.p.




                                                                                                                                      Population in
                  EXTREME POVERTY LEVEL




                                                                                                                                           (%)
              Improvement in income distribution with poverty reduction.
                                                                                                                                                                       2001                           2009
                                                                                                                                                                                 +21.7 p.p.




                                                                                                                                     (% of population)
                  RISE OF SOCIAL CLASSES




                                                                                                                                        A, B and C
                                                                                                                                           Class
              Income level of families is growing leading to social
              mobility.
                                                                                                                                                                       2003                           2011
                                                                                                                                                                                  -8.25 p.p.
                  INTEREST RATE




                                                                                                                                          (% p.y.)
                                                                                                                                           Selic
              Reduction in interest rate stimulating productive
              investment.
                                                                                                                                                                       2000                           2012
                                                                                                                                                                                     +35%
                                                                                                                                     (Kg / hab. year)
                                                                                                                                      Consumption

                  CONSUMPTION PER CAPITA OF
                                                                                                                                       Per Capita

                  THERMOPLASTIC RESINS                                                                                                                                                                 31
                                                                                                                                                                        23
              The consumption evolution is a consequence of the
              economical growth and a higher power of consumption.                                                                                                     2000                           2010
Sources: Banco Central do Brasil, Meta Selic dez/00 e ago/12; Abiquim. http://www.abiquim.org.br/resinastermoplasticas/estatisticas_33.asp - acesso 29/ago/12; Pesquisa Mensal de Emprego, IBGE. Nova série histórica disponível apenas
de março/02 a maio/12; “De Volta ao País do Futuro: Projeções, Crise Européia e a Nova Classe Média”, FGV, março/12.; Comunicados do IPEA nº 63: PNAD 2009 Primeiras Análises: Distribuição de Renda entre 1995 e 2009. Out/10.           3
Brazil: Oil Products Market Grows Above World Average
                                                                         BRAZIL                                          WORLD
Between 2000 and 2011...
                                                                            +49%                                            +15%
   GASOLINE CONSUMPTION




                                        Gasoline
                                        Demand
                                         (kbpd)
     WORLD : +1.3% a.a.                                                                 469                                              22,533
                                                                  315                                            19,616
     BRAZIL: +3.7% a.a.
       • Jan-Aug12 x Jan-Aug11: +23%
                                                                  2000                 2011                       2000                   2011

   DIESEL CONSUMPTION                                                       +43%                                            +29%




                                        Demand
                                         (kbpd)
                                        Diesel
     WORLD : +2.3% a.a.
                                                                  626                   896                      20,220                  26,072
     BRAZIL: +3.3% a.a.
       • Jan-Aug12 x Jan-Aug11: +6,7%
                                                                  2000                 2011                       2000                   2011

   JET FUEL CONSUMPTION                                                     +53%                                             -2%
                                        Demand
                                        Jet Fuel

     WORLD: -0,2% a.a.                   (kbpd)                                         121                       6,506                  6,393
     BRAZIL: +4,0% a.a.                                            79
       • Jan-Aug12 x Jan-Aug11: +7,9%
                                                                  2000                 2011                       2000                   2011

   OIL FUEL CONSUMPTION                                                     -56%                                             -18%
                                          Demand (kbpd)




     WORLD: -1,8% a.a.
                                            Oil Fuel




                                                                  189                                             9,675                  7,958
     BRAZIL: -7,1% a.a.                                                                  84
       • Jan-Aug12 x Jan-Aug11: -5,4%
                                                                  2000                 2011                       2000                   2011
                                                          Sources: Petrobras for Brazil data and Woodmackenzie for international data.            4
Petrobras Today:
Proved Reserves + Potential Recoverable Volumes: 31.5 bi boe
                                       Petrobras’ Proved Reserves : 15.7 bi boe
                                            Potential Growth: + 15.8 bi boe
 Million boe

35,000
35.000
                                                                                                                                                Potential
                                                                                                                                                 Growth
                                                                                                                             Concession – Potential        10.8 bi
30,000
30.000               • 2005-2010: more than 50% of new discoveries around the world were in deep                              Recoverable Volumes          boe
                       water, with Brazil representing 63% of these discoveries. (PFC Energy, jun/11)
                                      19%
25,000
 25.000              • From 2005 to 2012 Petrobras declared 63 discoveries in pre-salt area and
                            49%
                       189 in other areas to ANP. (Petrobras, aug/12)
                                       32%
20,000
20.000                                Brasil                                                                                      Transfer of Rights       5.0 bi
                     • 2030: Brazil should present the highest growth production among the countries
                                      Brasil                                                                                                               boe
                        that are not members of OPEC. (PFC Energy, jun/11)
                                                                                                                                             15.71
15,000
15.000
                                                                                                                                   Ultra-Deep Water 5.3 bi boe
                                                                                                                                          (>1,500m)

10.000
10,000
                                                                                                                                                       7.9 bi boe
                                                                                                                         Deep Water (300-1,500m)
 5,000
 5.000
                                                                                                                             Shallow-Water (0-300m) 1.2 bi boe
                                                                                                                                           Onshore 1.3 bi boe
     0
          1965




                      1970




                                     1975




                                                   1980




                                                              1985




                                                                             1990




                                                                                            1995




                                                                                                        2000




                                                                                                                      2005




                                                                                                                                         2010
                                                                                                                                         2011
    • Added Reserves in 2011 = 1.24 billion boe.          • Pre-Salt Added Reserves: 1 billion boe.   • Reserve/Production Ratio  19.2 year.

                                                                                                                                                               5
Production Increase and Breakdown of Oil and Gas Reserves
     of Major Companies: 2002 to 2011
                                                                                     PETROBRAS




                                    Oil and Natural Gas
                                                            5




                                       (million boe/d)
                                                            4




                                         Production
                                                                                           +45%             2.6
                                                            3
                                                            2                  1.8                                   0.5
                                                                    0.3                   Overseas
                                                            1                  1.5                          2.1
                                                                                            Brazil
                                                            0
                                                                              2002                       2011
                                                       Reserves                          84%                  16%
                                                   Breakdown (2010)
                                                                                          Oil                 Gas


                                             Oil and Natural Gas Production (million boe/d)
                     EXXON MOBIL                                   BP                                         SHELL              CHEVRON
                        +6%
                                                                                                              -19%
                                                                 -2%
                                                                                                                                      +2%




                   2002      2011                   2002                   2011                      2002              2011   2002          2011
Breakdown (2010)
    Reserves




                   47%       53%                          60%               40%                      44%              56%       62%          38%
                   Oil       Gas                          Oil               Gas                      Oil              Gas       Oil          Gas
                                                                Fonte: Evaluate Energy e WoodMackenzie, set/12.                                    6
Our Advantage:
The Value of Our Reserves and the Pre-Salt Reality




                                               Oil and NGL Production (jan-jul/12):
                                               Total Brazil: 2.007 kbpd
                                                   Onshore: 210 kbpd
                                                   Offshore
                                                        • Post-Salt: 1.681 kbpd
                                                        • Pre-Salt: 116 kbpd*
                                                 * Including partners: 148,3 kbpd
                                                   Record (incl. partners): 174,2 kbpd (jul/12)




                                                                                                  7
                                                                                                  7
Fundamentals of Business and Management Plan 2012-2016



                                                                               PRIORITY
                                                         CAPITAL
                                   PERFORMANCE           DISCIPLINE
         Financiability
         Assumptions                                                            • Priority given
                                      • Management
   • Maintenance of Investment                                                   to exploration
                                        focused in
   Grade                                                      • To ensure       and production
                                      accomplishing
   • There is no issuance of new                            expansion with       projects of oil
                                       physical and
   shares                                                    solid financial    and natural gas
                                     financial targets
   • Oil Products Import Price                                 indicators           in Brazil
                                      of each project
   Parity
   • Divestment of existing
   assets abroad




 2012                                                                                              2016
                                                                                                      8
Projects Under Implementation and Projects Under Evaluation

                                                                    Under Implementation                                                                   Under Evaluation
           2012-2016 BP                                     =           Projects with construction
                                                                             already started
                                                                                                                                     +             Projects in Phase I, II and III


           US$ 236.5 Billion                                              US$ 208.7 Billion                                                                US$ 27.8 Billion
                   980 projects                                                          833 projects                                                                   147 projects


                                                                                 CONSTRUCTION
                                     27.7%                                                                  24.8%                                    17% (**)
                                (US$ 65.5 Billion)                                                      US$ 51.7 Billion                          (US$ 4.6 Billion)

                                        28%                                                                                                 7%
                                                                                                                                      (US$ 1.9 Billion)

                                                                                                                                           0%
                                                                         65.8%                                                       (US$ 0.1 Billion)
      60.0%                                                                                                            3.7%                                                                 50%
 (US$ 141.8 Billion)                                               (US$ 137.2 Billion)                           (US$ 7.8 Billion)           5%                                       (US$ 13.9 Billion)
                                                     5.8%                                                                              (US$ 1.3 Billion)
                                                                                                                       1.8%
                                             (US$ 13.8 Billion
                                                                                                                 (US$ 3.7 Billion)
                                                     2.1%
                                                                                                                      1.7%
                                              (US$ 5.0 Billion)
                                                                                                                  (US$ 3.5 Billion)                       21%
                                                     1.5%
                                             (US$ 3.6 Billion)                                                      0.9%                          (US$ 6.0 Billion)
                                          1.6%                                                                 (US$ 1.9 Billion)
                                                                                                         1.4%
                              1.3% (US$ 3.8 Billion)
                                                                                                   (US$ 3.0 Billion)
                          (US$ 3.0 Billion)                                                                                                                           ** E&P abroad


                                          E&P           RTM       G&E        Petrochemical        Distribution             Biofuel           Corporate

                                                                                                                                                                                                           9
Business and Management Plan 2012-2016: US$ 236.5 Billion

                                                          INVESTMENTS UNDER IMPLEMENTATION
US$ 131.6 billion                   US$ 55.8 billion                                US$ 7.7 billion                                    US$ 6 billion                                  US$ 3.2 billion                           US$ 1.2 billion
          E&P                   Downstream                                          Gas & Power                                        International                                     Distribution                                Biofuels
                                                  4% 1%                                                                                               1%                                                                             1%            3%
                                             5% (2,4) (0,5)                                                                                  1%                                                                                                   (0,03)
                                                                                                                                        4% (0,1)     (0,1)                                                                          (0,01)
                                            (2,9)                                                                                                                                                                                             6%
                                                                                                    6%     10%                         (0,2)      7%                                                    13%
                                                                                                                                    2%                                                                                                       (0,07)
               19%                                                                                 (0,5)   (0,7)                                 (0,4)                                                 (0,42)
                                         9%                                                                                        (0,1)
              (25,4)                                                                   20%
                                        (4,8)                                          (1,5)                                                                                          43%
                                                                                                                                                                                                                                                                         US$
                                +                                               +                                                  +                                          +                                      +                                             =
                                                                        45%                                                24%                                                                                   21%
                        12%                                                                                                (1,9)                                                     (1,39)
                                                                       (24,9)                                                                                                                                   (0,70)
                                    17%
                                                                                                                                                                                                                                                                       208.7 bi
                       (16,3)
                                    (9,4)
  68%
 (89,9)                                                                                                             7%
                                                                                                                                                                                                                   1%
                                                  20%                                          32%                 (0,6)                                     85%
                                                                                                                                                                                                 21%              (0,01)                           90%
                                                                                               (2,5)                                                         (5,1)
                                                 (11,0)                                                                                                                                         (0,67)                                            (1,05)




                                                                                                                                                +
                                                                                                                                       E&P       R&M                 Distribuição
                                                                                                                                       G&E       Petroquímica        Corporativo




                                                        3%                                                                                       3%
                                               7%
                                                       (0,5)                                                                                  (US$ 0,1 Bi)
                                     5%       (1,1)
                                    (0,8)                                                                    15%
                                                                                                                                                                                                                                     21%                   21%
                                                                                                             (0,9)                                                                                                          1%       (0,3)                 (0,3)
                                                                                                                                                                                                                           (0,01)
                                                                                                                                                                                                                                                                        US$
                                                                       41%                                              8%


                                +                                               +                                                  +                                          +                                      +                                             =
                                                                       (6,4)                                           (0,5)                                                                  100%
                                                                                    54%                                                                                                       (0,10)

                                       37%
                                                                                    (3,2)
                                                                                                                     22%
                                                                                                                                                                                                                                                                       27.8 bi
                                       (5,8)                                                                         (1,3)
                                                                8%                                                                                                       97%                                                                     57%
                                                               (1,2)                                                                                                  (US$ 4,6 Bi)                                                               (0,8)


          E&P                   Downstream                                          Gas & Power                                        International
                                                                                                                                       E&P
                                                                                                                                                                                        Distribution                                 Biofuels
          US$ -                     US$ 15.8 billion                                US$ 5.9 billion                                    US$ 4.7 billion
                                                                                                                                       G&E                                             US$ 0.1 billion                          US$ 1.4 billion

                                                                       INVESTMENTS UNDER EVALUATION
                                                                                                                                                                                                                                                                             10
Systematic Approval of Projects and Organizational Learning

                         Projects under Evaluation                                                    Projects under Implamentation       Projects under Operation



               PROJECTS INITIATION AND PLANNING                                       Appproval of                                           Platform P-57
                                                                                        the Basic           Phase IV       Phase V
            PHASE I                    PHASE II                                         EVTE¹ and
                                                                                                              Work         Start up &
                                                              PHASE III               clearance for
           Opportunity                Conceptual                                                            Execution      Operation
                                                             Basic Project              execution
          Identification                Project                                        (work start)


                                                                                                                        RNEST
                                                                                                                                                 GASTAU
           Included at          Approval of          Approval of
            Petrobras           EVTE¹ Phase            EVTE¹
             Portfolio               I               Concptual
         ¹EVTE: Technical and Economic Feasibility Study
                                                                                                        UTE Baixada Fluminense

                                      EXPERTISE ACQUIRED: GATHER KNOWLEDGES IN EACH PHASE OF PROJECTS DEVELOPMENT

                          Normative
                                                       Procedures
                          Documents
                                                                                                                                                    Validation and
  Changes and improvements included in the next project                                               EXPERTISE                                      Approval of
                                                                                                      ACQUIRED                                       Knowledge’s
                           NORTEC                        MAGES                                                               SINAPSE Register,           Items
                       Petrobras Technical              Petrobras
                          Normalization             Management Guide.                                                         Consultation and
SINAPSE: Integrated environment that allows the record learning of workforce. Suports the record process,                       interaction
analyses, consolidation, recovery and, mainly, implementation of learned lessons.                                                                                11
REVAP – São José dos Campos (SP)                                        Site of RNEST – Ago/12
       Inaugurated in 1980: Project by Snamprogetti.                First refinery constructed by Petrobras since 1980.




                                                        Expertise
                                                        Acquired
     Premium I and II – International Metrics
                 Typical Chinese Projects
                                                                 The experience acquired enable the conception of
                                                                new refineries in MA, CE and RJ, within the
                                                                international metrics of price, term and standardized
                                                                technologies.
                                                                 Capacity: 230 kbpd
                                                                 Production of Diesel: 161 kbpd (70%)
                                                                 Current Situation: in construction, 62% physical
                                                                progress
Place: Qinzhou, China          Place: Huizhou, China            Start up: November/2014
Capacity (Mbpd): 200           Capacity (Mbpd): 240              CAPEX: US$ 17 billions.
Construction time: 52 months   Construction time: 46 months
                                                                Jobs Generated: 43,500 jobs
Start up: Sep/2010             Start up: May/2009
                                                                 Local Content: 91%                               12
P-57 – Jubarte Field: Capacity of 180 kbpd
                                                Local Content (LC): 69%


                                                                                                                                                                  Platform P-57 started operation in
                                                                                                                                                                   December 2010, 3 months before
                                                                                                                                                                  contractual term, with 69% of local
                                                                                                                                                                  content and currently is producing
                                                                                                                                                                   138 kbpd (1Q12) at Jubarte Field.


                                                                                                                                               Expertise
                                                                                                                                               Acquired
                                        The Challenge is Huge!                                                                                                            P-62 – Roncador Module IV
                                                                                                                                                                            Start up in Mar/14 - LC 65%
                                                                                                               Franco 4
                                                                                   Lula Alto      Lula Ext.
                                                                                   P-66           Sul P-70     Sul de
                                                                                                               Guará
                                                                                   Lula Central   Iara Horst
Piloto Baúna
                                                                                   P-67           P-71         Júpiter
e Piracaba
(SS-11)                                                                                           NE Tupi      Carcará        Maromba      Espadarte III
                                                         Norte Pq.                 Lula Sul
                                                                                   P-68           P-76         P-73           Bonito       Florim
Cachalote e                                              Baleias (P-58)
Baleia Franca                          Piloto Sapinhoá                                            Carimbé      Sul Pq.        Entorno de
                                                                                   Franco 1
(Capixaba)                             (Cid. São Paulo) Roncador IV                                            Baleias        Iara
                                                        (P-62)                     P-74           Aruanã
Uruguá /                               Piloto Lula NE                                                          Franco 5
                                                        Sapinhoá Norte             Carioca Z2     Iara NW
Tambaú                                 (Cid. Paraty)
                                                        (Cid. Ilhabela)                           P-72         Espadarte I                   4.200
(Cid. Santos)                                                                      Lula Norte
                         Baleia Azul   Papa-Terra
                                                        Iracema Sul                P-69           Franco 3
Piloto Lula   Mexilhão (Cid. Anchieta) (P-61 e P-63)                    Iracema
                                                        (Cid.                      Franco 2       P-77
(Cid. Angra (PMXL-1) Baúna e           Roncador III                     Norte Z1
                                                        Mangaratiba)               P-75
dos Reis)                              (P-55)
              Marlim Sul Piracaba
Jubarte
Jubarte       (P-56)     (Cid. Itajaí)
                                                                                                                             24 btwn 2012 and 2016
                                                                                                  Drilling Rigs
(P-57)
 (P-57)
                                                                                                  LDA > 2.000 m              49 btwn 2012 and 2020
                                                                                     2.500
 2.004          2.022                                                                                                        19 btwn 2012 and 2016
                                                                                                            UEPs
                                                                                                                             38 btwn 2012 and 2020

   2010          2011          2012          2013          2014           2015        2016           2017          2018            2019       2020


                                                                                                                                                           Construction of P-62
                                                                                                                                                           180 kbpd of capacity – Ago/12                  13
Oil and NGL Production Curve in Brazil: 2011 and 2012
Target 2012: 2,022 kbpd (+/- 2%)

   kbpd                                            2011                                                                       2012
2.200                                  2Q11                                                            1Q12                  2Q12
                                   average: 2,018                                                  average: 2,066        average: 1,970
2.150
                                                                                                   2,110
                                                                                           2,084           2,098
2.100
        2,069                                                                      2,061
                          2,040                   2,047
2.050
                  2,020                                                   2,002   2,001                                      1,989
                                  2,003   2,003
2.000                                                                                                        1,993                   1,960
                                                          1,968   1,963                                              1,961                   1,940
1.950
  50      Jan/11 Feb/11 Mar/11 Apr/11 May/11 Jun/11 Jul/11 Aug/11 Sep11 Oct/11 Nov/11 Dec/11 jan/12 fev/12 mar/12 abr/12 mai/12 jun/12 jul/12
            jan/11 fev/11 mar/11 abr/11 mai/11 jun/11 jul/11 ago/11 set/11 out/11 nov/11 dez/11 Jan/12 Feb/12 Mar/12 Apr/12 May/12 Jun/12 Jul/12

     5% decrease in production 2Q12/1Q12 (- 96 kbpd) as a result of:
          • Operational stoppages(-54 kbpd), lower operational efficiency (-18 kbpd) and interruption of Frade (-15 kbpd).
          • Decline of old systems´potential as expected, around 11% p.y. The average rate worldwide for big and giant fields in
             deepwater is between 10% and 15% p.y.
     Start-up of 2 new systems in 2H12:
          • FPSO Cidade de Anchieta (Baleia Azul), 100 kbpd capacity, started on 09/10/12, peak in Feb/13
          • FPSO Cidade de Itajaí (Baúna e Piracaba), 80 kbpd capacity, built in Singapore, postponed from October to
             December.
                    • Authorization to operate production unit SS-11 untill 28/Feb/2013 requested to ANP.
     Maintenance of 2012 oil production target (flat when compared to 2011, +/-2%):
          • Production recovery only in 4Q12 (scheduled stoppages will continue on 3Q12).
                                                                                                                                                     14
PROEF: Initiatives to Recover Operational Efficiency – UO-BC

                               Improve Campos Basin         Increase the oil curve delivery
   PROEF                                                                                                 Improve production
                                  Operational Unit               reliability, provided
  Objectives                                                                                              systems integrity
                                  efficiency levels                in 2012-2016 BP




                                             Campos Basin Operational Efficiency – UO-BC

                                 89                                                                                          90
                                             88                                                                 88
                                                                                          PROEF Targets
 Operational                      Executed
                                                      80                                           81
  efficiency
                         (%)




 targets for                                                                         76
                                                                          74                   PROEF Disbursements:
   Campos                                                       71                              • Well workovers, subsea systems and
 Basin Unit                                                                                       platforms intervention through
                                                                                                  maintenance units: US$ 5.1 Bi (2012-
                                                                                                  16)
                                                                                               PROEF Estimated NPV:
                                                                                                • US$ 1.6 Bn - US$ 3.3 Bn


                                2008     2009      2010        2011      2012       2013         2014           2015       2016
Operational Efficiency
                                                                                              HC / PAD Fields
• Without UO-BC:                                      94%        95%       94%
                                                                                              UO-BC Assets
• E&P Total:                              90%         87%        86%                                                               15
38 Production Units: 2012 – 2020
Production Units: 2012-2013
                                                              Oil Production, Brazil: 2,022 – 4,200 kbpd

                                                                                                     P-66         P-70         CO5
                                                                                                     (Lula        (Lula Ext.   (Franco 4)
                                                                                                     High)        South)       CO6
                                                                                                     P-67         P-71         (South of
                                                                                                     (Lula        (Iara Horst) Guará)
                                                                                                     Central)
                                                                                                                  P-76         Júpiter
    Oil and NGL Production Curve (kbpd)




                                                                          P-58                       P-68         (NE Tupi)                     Maromba
                                                                                                                               P-73                         Espadarte III
                                                           Cid. São      (Whales Park               (Lula
                                                                                                                  Afretada     (Carcará)        Bonito
                                                          Paulo           North)                     South)                                                 CO9
                                                          (Piloto de                                              (Carimbé)    Whales           CO8         (Florim)
                                                                          P-62                       P-74
                                                          Sapinhoá)                                               Aruanã       Parq South       (Iara
                                                                          (Roncador                  (Franco 1)
                                                           Cid. Paraty mod. IV)                                  P-72         CO7              Surround)
                                                                                                     Z2
                                                          (Piloto de Lula Cid. Ilhabela                           (Iara NW)    (Franco 5)
                                                                                                     (Carioca)
                                                          NE)             (Sapinhoá                                            Espadarte I
                                                                                                     P-69         P-77
                                                           P-61        North)                       (Lula        (Franco 3)
                                           Cid.
                                                           P-63 (Papa-                              North)
                                          Anchieta                      Cid.               Z1
                                                          Terra)        Mangaratiba
                                          (Baleia Azul)                                    Iracema   P-75
                                                           P-55        (Iracema           North     (Franco 2)
                                           Cid. Itajaí
                                                          (Roncador     South)
                                          (Baúna e
                                                          mod. III)
                                          Piracaba)

                                                                                                                                             23 Already Contracted
                                                                                          Production Units           19 up to 2016
                                                                                                                                                 15 to Contract
                                                                                          Construction               38 up to 2020           (from nov/12 to apr/17)



                                                                                                                                                                            16
FPSO Cidade de Anchieta – Baleia Azul                                           Operating since sep/10/12

  Production Ramp up        Interconnection of
         (bpd)               Producing Wells
   Sep/12       29,700     1st Well    sep/10/12
   Oct/12       52,185     2nd Well    sep/21/12
   Nov/12       52,185     3rd Well    sep/26/12
   Dec/12       72,000     4th Well    nov/12/12
 Peak (100 kbpd): Feb/13   5th Well    nov/13/12




                                                   Local Content - Mandatory: 0% / Forecast Accomplishment : 44%
                                                                                                               17
Baleia Azul Project – FPSO Cidade de Anchieta (1st Oil: Sep/12)
Meeting of Critical Analysis (RAC) Monthly: CEO + E&P Director + Engineering, Technology and Materials Director


             PHYSICAL PROGRESS OF THE PROJECT – S CURVE
                 IMPLEMENTATION LANDMARKS
                 1 - Issuance of Preliminary License (LP) (P:Sep-08 / R:Sep-08)
                 2 – Conclusion of the Opportunity Evaluation Phase (Gate 1) (P:Dec-08 / R:Dec-08) (P: 100% / R: 100%)
                 3 – Conclusion of the Conceptual Project Phase (Gate 2) (P:Jul-09 / R:Jul-09) (P: 100% / R: 100%)
                 4 – Conclusion of the Basic Project Phase (Gate 3) (P:Dez-09 / R:Dez-09) (P: 100% / R: 100%)
                                                            st
                 5 – Beginning of the Construction of the 1 Well (P:Jan-11 / R:Feb-11)
                 6 – Issuance of the Instalation License (LI) (P:Dec-11 / R:Dec-11)
                 7 – Arrival of the Unit in the Local (P:Ago-12 / R:Aug-12)
                                                           st
                 8 – Beginning of Interconnection of the 1 Well (P:Aug-12 / R:Aug-12)
                 9 – Issuance of the Operating License (LO) (P:Aug-12 / R:Sep-12)
                 10 – Interconnection of the Last Well (P:Mar-13 / Proj:Mar-13)




                                  Baseline                                      Baseline 2012-2016 BP                                     Accomplished   Forecast



              Fonte :SAP/PNG 12-16: 30/06/12. Data de Medição pela Diretoria de Exploração & Produção: 13/09/12.
              Linha de Base: EVTE da Fase III, aprovado em 03/12/2009, Ata DE 4.787. / Projetado: Replanejamento realizado em Julho/12.


                                                                                                                                                                    18
Baúna e Piracaba Project – FPSO Cidade de Itajaí (1st Oil: Dec/12)
Meeting of Critical Analysis (RAC) Monthly: CEO + E&P Director + Engineering, Technology and Materials Director


             PHYSICAL PROGRESS OF THE PROJECT – S CURVE
            IMPLEMENTATION LANDMARKS
            1 - Conclusion of the Opportunity Evaluation Phase (Gate 1) (P:Mar-10 / R:Mar-10) (P: 100% / R: 100%)
            2 - Conclusion of the Conceptual Project Phase (Gate 2) (P:May-11 / R:May-11) (P: 100% / R: 100%)
                                                 st
            3- Beginning of Construction of the 1 Well (P:Aug-11 / R:Jul-11)
            4 - Conclusion of the Basic Project Phase (Gate 3) (P:Sep-11 / R:Sep-11) (P: 100% / R: 100%)
            5 -- Issuance of Preliminary License (PL) (P:Jul-12 / Proj:Sep-12)
            6 - Issuance of the Instalation License (LI) (P:Aug-12 / Proj:Sep-12)
            7 - Issuance of the Operating License (OL) (P:Sep-12 / Proj:Nov-12)
            8 - Arrival of the Unit in the Local (P:Sep-12 / R:Dec-12)
                                                       st
            9 - Beginning of Interconnection of the 1 Well Baúna (P:Sep-12 / Proj:Dec-12)
                                                      st
            10 – Beginning of Construction of the 1 Well Piracaba (P:Mar-13 / Proj:Jan-13)
                                                            st
            11 – Beginning of Interconnection of the 1 Well Piracaba (P:Jun-13 / Proj:May-13)
            12 - Interconnection of the Last Well (P:Aug-14 / Proj:Aug-14)




                                                                                                                                                            apr



                                                                                                                                                                    oct



                                                                                                                                                                             apr



                                                                                                                                                                                   oct
                                                                                                                       oct



                                                                                                                                       apr
                                                                                                        apr




                                                                                                                                                      oct
                 apr



                               oct



                                              apr



                                                                 oct



                                                                           apr



                                                                                          oct




                              Baseline                                       Baseline 2012-2016 BP                                     Accomplished               Forecast


           Fonte :SAP/PNG 12-16: 30/06/12. Data de Medição pela Diretoria de Exploração & Produção: 13/09/12.
           Linha de Base: EVTE da Fase III, aprovado em 03/12/2009, Ata DE 4.787. / Projetado: Replanejamento realizado em Julho/12.



Local Content: Mandatory: 60% / Forecast Accomplishment : 81%                                                                                                                            19
FPSO Cidade de São Paulo - Sapinhoá Pilot (1st Oil: Jan/13)
Local Content - Mandatory :30% / Forecast Accomplishment :50%      Hull Conversion - Cosco (China)
                                                                   Modules Construction: AIBEL (Thailand)
                                                                   1. Main Gas Compression A
                                                                   2. Main Gas Compression B
                                                                   3. Gas Treatment - CO2 Removal
                                                                   4. Gas Reinjection
                                                                   5. CO2 Injection
                                                                   6. Oil Processing – High Pressure
                                                                   7. Oil Processing – Low Pressure
                                                                   8. Utilities and Water Injection

                                                                   Modules Construction: BOOMESC (China)
                                                                   9. Energy Generation
                                                                   10. E-House MCC – Panels Room
                                                                   11. Piperack



                                                                    Modules Construction: ENAVAL/VEOLIA – Niterói (RJ)
                                                                   12. Salt Water Treatment




Modules Construction: BrasFels Shipyards– Angra dos Reis (RJ)
13. Arrival Risers Manifolds                                         Enaval - Niteroi (RJ)
14. Operation Cargo Area - 1S                                   Brasfels Shipyard – Angra (RJ)
15. Operation Cargo Area - 5S
16. Flare Chimney

Integration: BrasFels Shipyards – Angra dos Reis (RJ)
Modules Integration from hull 1 to 16



                                                                                                                     20
FPSO - Cidade de São Paulo: Modules Construction and Integration at BrasFels Shipyard



                                                    FPSO Cidade de São Paulo




View of BrasFels Shipyard, in Angra dos Reis – RJ (08//31/12).
                                                                                        21
FPSO Cidade de São Paulo – Sapinhoá Pilot (1st Oil: Jan/13)
Monthly Meeting of Critical Analysis (RAC) : CEO + E&P Director + Engineering, Technology and Materials Director


              PHYSICAL PROJECT MONITORING – ‘S’ CURVE
               IMPLEMENTATION LANDMARKS:
               1 – Beginning of Construction of the 1st Well (P:mar-12 / R:feb-12)                                                      Start-Up Forecast:
               2 – Issuance of Preliminary License (LP) (P:may-12/ R:sep-12)                                                                  Jan/13
               3 – Issuance of the Instalation License (LI) (P:may-12 /Proj:sep-12)
               4 – Basic Design Conclusion (Gate 3) (P:july-12 /Proj:oct-12) (P: 89% / R: 90%)
               5 – Production Unit (PU) in the Site (P:nov-12 /Proj:nov-12)
                                                                                                                                                                 Start-Up
               6 – Operation License Issue (LO) (P:dec-12 /Proj:dec-12)
                                                                                                                                                             BP 12-16: Jan/13
                    st
               7 – 1 Well Interconnection Start (P:dez-12 /Proj:dez-12)
               8 - Exports Gas Pipeline Interconnection (P:aug-13 /Proj:aug-13)
               9 – Last Well Interconection (P:oct-15 /Proj:oct-15)
                                                                                                                                                 Start-Up EVTE:
                                                                                                                                                     Dec/12




            Fonte :SAP/PNG 12-16: 30/06/12. Data de Medição pela Diretoria de Exploração & Produção: 13/09/12.
            Linha de Base: EVTE da Fase III, aprovado em 03/12/2009, Ata DE 4.787. / Projetado: Replanejamento realizado em Julho/12.


                                                                                                                                                                                22
FPSO Cidade de Paraty – Lula NE Pilot (1st Oil: May/13)
Local Content - Mandatory: 30% / Forecast Accomplishment 30%
                                                                                         Hull Conversion: Keppel Shipyard - Singapore

                                                                                         Modules Construction: Keppel Shipyard - Singapore
                                                                                         1. Energy Generation BB
                                                                                         2. Energy Generation BE
                                                                                         3. Local Equipment Room
                                                                                         4. Maintenance and conversion areas, and moorings
                                                                                         5. Helipad
                                                                                         6. Burners



                            Modules Construction: Nuclep Site Construction (EBSE) –
                                                  Itaguaí (RJ)
                          7. Manifold
                          8. Cargo Operation and Chemical Storage                       Modules Construction: ENAVAL/VEOLIA – Niterói (RJ)
                          9. Gas Injection and Compression                              16. Salt Water Treatment
                          10. Gas A Treatment                                           17. Utilities and Water Injection




 Modules Construction: BrasFels Shipyard – Angra dos Reis (RJ)                              Enaval - Niteroi (RJ)
11. Oil A Processing                                                                      Nuclep - Itaguaí (RJ)
12. Oil B Processing                                                                  BrasFels Shipyard - Angra (RJ)
13. Gas A Compression
14. Gas B Compression
15. Gas B Treatment




Integração: Estaleiro BrasFels – Angra dos Reis (RJ)
Modules Integration from hull 1 to 17
                                                                                                                                             23
FPSO - Cidade de Paraty: Modules Construction and Integration at BrasFels Shipyard


                                                                                                                                                              FPSO
                                                                                                                                                          Cid. de Paraty
                                                                       FPSO Cid. de
                                                                       Paraty Modules
                                                               6

                                                               5

                                                               4


                                                                   3

                                                                   2

                                                                   1




View of BrasFels Shipyard, in Angra dos Reis – RJ (08/31/12).
FPSO Cidade de Paraty Modules: (1) TS072 – Main Gas B Compressor; (2) TS062 – Oil A Treatment; (3) TS063 – Oil B Treatment; (4) TS071 – Main Gas A Compressor; (5) TS075 – Gas B
Treatment; (6) TS073 –CO2 Compressor; (LC: Full modules package contracted attending 65% of Local Content).                                                                     24
FPSO - Cidade de Paraty: Modules Construction at Nuclep Construction
Canteiro Nuclep - RJ


                                                                                                                                         FPSO Cid. de
                                                                                                                                        Paraty Modules




                                                                                                                                                 2



                                                                                                                                        1




                                                                                                                                            11




View of Nuclep Construction Site, in Angra dos Reis – RJ (08/31/12).
FPSO Cidade de Paraty (Hull – Singapore and Integration BrasFels): (1) Gas Injection and Compression (LC:65%); (2) Manifold (LC:65%).                25
FPSO Cidade de Paraty – Lula NE Pilot (1st Oil: May/13)
  Monthly Meeting of Critical Analysis (RAC) : CEO + E&P Director + Engineering, Technology and Materials Director


                               PHYSICAL PROJECT MONITORING – ‘S’ CURVE
                100
                               IMPLEMENTATION LANDMARKS:
                                                                                                                                                                                                                                                                                      Operational
                                                                                                                                                                                                                                                                                  Entrada em Operação
                 90            1 – Conclusion of Opportunity Evaluation Phase(Gate 1) (P:may-10/R:may-10) (P:100%/R:100%)
                                                                                                                                                                                                                                                                                   Start-Up Forecast
                                                                                                                                                                                                                                                                                     Prevista (EVTE):                                                                                                                         10
                                                                                                                                                                                                                                                                                    (EVTE): May/13
                                                                                                                                                                                                                                                                                         28/05/13
                               2 – Conclusion of Conceptual Project Phase (Gate 2) (P:jul-11/R:jun-11) (P:100%/R:100%)
                 80
                               3 - Beginning of Construction of the 1st Well (P:feb-12 / R:feb-12)
                               4 - Issuance of Preliminary License (LP) (P:aug-12 / R: sep-12)
                 70
                               5 - Basic Design Conclusion (Gate 3) (P:may-12/R:oct-12) (P:100%/R:95%)
                                                                                                                                                                                                                                                                                                                                           Operational
                                                                                                                                                                                                                                                                                                                                            Entrada em
                 60            6 - Issuance of the Instalation License (LI) (P:aug-12 /Proj: oct-12)
                                                                                                                                                                                                                                                       8                                                                                Operação Forecast:
                                                                                                                                                                                                                                                                                                                                        Start-Up Projetada:
% % Acumulado




                               7 - Production Unit (PU) in the Site (P:mar-13 /Proj:mar-13)                                                                                                                                                                                                                                                   May/13
                                                                                                                                                                                                                                                                                                                                             28/05/2013
                                                                                                                                                                                                                                                                            9
  Accrued




                 50            8 - Operation License Issue (LO) (P:mar-13 / Proj:mar-13)                                                                                                                                                                             7
                                        st
                               9 - 1 Well Interconnection Start (P:apr-13 / Proj:apr-13)                                                                                                                                        6
                 40            10 - Last Well Interconection (P:apr-16 / Proj:apr-16)                                                                                                                                                                                                                    Operational
                                                                                                                                                                                                                                                                                                     Entrada em Operação
                                                                                                                                                                                  Justif.2 (A)                                                                                                       Start-Up Forecast:
                                                                                                                                                                                                                                                                                                     Prevista (PNG 12-16):
                                                                                                                                                                                                                                                  5                                                  BP 12-16: May/2013
                 30                                                                                                                                                              Justif.2 (B)                                                                                                             28/05/2013

                                                                                                                                                                                                                                4                                                                                                             Reference: Aug/12
                 20                                                                                                                          2                                                                                                                                                                                                  Referência: agosto/12
                                                                                                                                                                                                                                                                                                                                               MTD     Accrued
                                                                                                                                                                                                                                                                                                                               Forecast BP: No mês Acumulado
                                                                                                                                                                                                                                                                                                                                              1.1%          29.1%
                 10                                                                           1                                                                                                  3                                                                                                                             Accomplished: 1,1%
                                                                                                                                                                                                                                                                                                                                 Previsto PNG: 1.1%     29,1%
                                                                                                                                                                                                                                                                                                                                                            31.8%
                                                                                                                                                                                                                                                                                                                                 Realizado:   1,1%      31,8%

                  0
                                                          set-09




                                                                                                                set-10




                                                                                                                                                                      set-11




                                                                                                                                                                                                                            set-12




                                                                                                                                                                                                                                                                                  set-13




                                                                                                                                                                                                                                                                                                                                        set-14




                                                                                                                                                                                                                                                                                                                                                                                              set-15
                               mar-09
                                        mai-09




                                                                                     mar-10
                                                                                              mai-10




                                                                                                                                           mar-11
                                                                                                                                                    mai-11




                                                                                                                                                                                                 mar-12
                                                                                                                                                                                                          mai-12




                                                                                                                                                                                                                                                       mar-13
                                                                                                                                                                                                                                                                mai-13




                                                                                                                                                                                                                                                                                                             mar-14
                                                                                                                                                                                                                                                                                                                      mai-14




                                                                                                                                                                                                                                                                                                                                                                   mar-15
                                                                                                                                                                                                                                                                                                                                                                            mai-15




                                                                                                                                                                                                                                                                                                                                                                                                                         mar-16
                                                                                                                                                                                                                                                                                                                                                                                                                                  mai-16
                                                 jul-09




                                                                                                       jul-10




                                                                                                                                                             jul-11




                                                                                                                                                                                                                   jul-12




                                                                                                                                                                                                                                                                         jul-13




                                                                                                                                                                                                                                                                                                                               jul-14




                                                                                                                                                                                                                                                                                                                                                                                     jul-15
                      jan-09




                                                                            jan-10




                                                                                                                                  jan-11




                                                                                                                                                                                        jan-12




                                                                                                                                                                                                                                              jan-13




                                                                                                                                                                                                                                                                                                    jan-14




                                                                                                                                                                                                                                                                                                                                                          jan-15




                                                                                                                                                                                                                                                                                                                                                                                                                jan-16
                                                                   nov-09




                                                                                                                         nov-10




                                                                                                                                                                               nov-11




                                                                                                                                                                                                                                     nov-12




                                                                                                                                                                                                                                                                                           nov-13




                                                                                                                                                                                                                                                                                                                                                 nov-14




                                                                                                                                                                                                                                                                                                                                                                                                       nov-15
                                          Baseline
                                          Linha de Base                                                                                          Baseline BP 12-16
                                                                                                                                                 Linha Base - PNG 12-16                                                                                                     Realizado
                                                                                                                                                                                                                                                                            Accomplished                                                                                    Forecast
                                                                                                                                                                                                                                                                                                                                                                            Projetado

                         Fonte :SAP/PNG 12-16: 30/06/12. Data de Medição pela Diretoria de Exploração & Produção: 13/09/12.
                         Linha de Base: EVTE da Fase III, aprovado em 03/12/2009, Ata DE 4.787. / Projetado: Replanejamento realizado em Julho/12.




                                                                                                                                                                                                                                                                                                                                                                                                                                           26
FPSO P-63 – Papa-Terra (1st Oil: Jul/13)
Local Content - Mandatory: 0% / Accomplished Forecast: 65%                          Hull: Conversion - Cosco (China)
                                                                                     Modules: Construction COSCO Shipyard (China)
                                                                                     1. M01 Offices, Accommodations and Helideck
                                                                                     2. M21/M22 Manifolds
                                                                                     3. M81 Utilities System
                                                                                     4. M82 Heaters
                                                                                     5. M32/42 Load and Unload Area
                                                                                     6. M41 Laboratory and Workshop
                                                                                     7. M90 Electric Panels
                                                                                     8. M91/92/93 Electricity Generation Systems
Modules: Construction QUIP Construction Site–Rio Grande Port                        Modules: Construction Tekfen (Turkey)
(RS)                                                                                9. Z90 Piperack
10. EBSE – M11 High Separation System
11. EBSE – M12 Low Separation System
12. NATCO – M13 Oil Treatment
13. SULZER/TSL – M51 – Water Treatment and Injection Systems
14. VEOLIA – M52 – Sulphate Reduction Unit
15. QUIP – M-31 Flare Vases
16. QUIP – Flare Spare
17. SULZER/TSL – M83 Chemical Injection System
18. M60 Natural Gas Compression System




Integration: Rio Grande Port (RS)
Integration of Modules 1 to 18 to the hull


                                                               Rio Grande Port - Rio Grande (RS)
                                                                                                                                    27
P-63 – Modules Construction at Rio Grande Port




                                                                                                                                            6

                                                                                                     5

                                                                                                                                        1




                                                                                                                                                         4
                                                                                          2
                                                                                                                               3




                                                                                                                                                  7




View of the Honório Bicalho Shipyard (QUIP Construction site), in Rio Grande Port – RS (03/sep/12).
P-63 Modules (Hull converted in China will arrive in Brazil in Dec/12): (1) M60 – Compression; (2) M52 – Sulphate removal; (3) M12 – Low pressure separator; (4) M11 – High pressure separator;
(5) M13 – Electrostatic treatment; (6) M51- Water injection and treatment; (7) F30 - P-63 Flare. (LC: Full package contracted with 65% LC).                                                 28
FPSO P-61 – Papa-Terra (1st Oil: Dec/13)
Local Content - Mandatory: 0% / Accomplished: 65%



 Hull Construction: BrasFels Shipyard – Angra dos Reis (RJ)


                                                                Modules Construction: SIEMENS – Indonesia
                                                                1. Electric Modules

                                                                Modules Construction: KeppelFELS - Singapore
                                                                2. Topside Integration




 Integration: BrasFels Shipyard – Angra dos Reis (RJ)         BrasFels Shipyard - Angra (RJ)
 Topside / Hull Integration




                                                                                                               29
4th Itaú BBA LATAM Commodities Conference
4th Itaú BBA LATAM Commodities Conference
4th Itaú BBA LATAM Commodities Conference
4th Itaú BBA LATAM Commodities Conference
4th Itaú BBA LATAM Commodities Conference
4th Itaú BBA LATAM Commodities Conference
4th Itaú BBA LATAM Commodities Conference
4th Itaú BBA LATAM Commodities Conference
4th Itaú BBA LATAM Commodities Conference
4th Itaú BBA LATAM Commodities Conference
4th Itaú BBA LATAM Commodities Conference
4th Itaú BBA LATAM Commodities Conference
4th Itaú BBA LATAM Commodities Conference
4th Itaú BBA LATAM Commodities Conference
4th Itaú BBA LATAM Commodities Conference

Weitere ähnliche Inhalte

Was ist angesagt?

Mirus Credit Market Update112508
Mirus Credit Market Update112508Mirus Credit Market Update112508
Mirus Credit Market Update112508Mirus
 
Iochpe-Maxion - 2Q07 Presentation
Iochpe-Maxion - 2Q07 PresentationIochpe-Maxion - 2Q07 Presentation
Iochpe-Maxion - 2Q07 PresentationIochpe-Maxion
 
Las Vegas Americas Market Beat Industrial Q42011
Las Vegas Americas Market Beat Industrial Q42011Las Vegas Americas Market Beat Industrial Q42011
Las Vegas Americas Market Beat Industrial Q42011Jessica Parrish
 
regions Lehman_2007/09/11
regions Lehman_2007/09/11regions Lehman_2007/09/11
regions Lehman_2007/09/11finance25
 
Tim meeting with investors - sep 2012
Tim   meeting with investors - sep 2012Tim   meeting with investors - sep 2012
Tim meeting with investors - sep 2012TIM RI
 
E2AGP - Country Portfolio
E2AGP - Country PortfolioE2AGP - Country Portfolio
E2AGP - Country Portfolioroxannemiller
 
Msia Economics Monthly - 0711
Msia Economics Monthly - 0711Msia Economics Monthly - 0711
Msia Economics Monthly - 0711nikfauzan
 
World constructionreport 2012
World constructionreport 2012World constructionreport 2012
World constructionreport 2012miguelpmelo
 
Oportunidades Renta Fija Andy Wells, Fidelity, enero 2013
Oportunidades Renta Fija Andy Wells, Fidelity, enero 2013Oportunidades Renta Fija Andy Wells, Fidelity, enero 2013
Oportunidades Renta Fija Andy Wells, Fidelity, enero 2013Finect
 
EP09_18BankofAmerica
EP09_18BankofAmericaEP09_18BankofAmerica
EP09_18BankofAmericafinance49
 
Latvia Looking Ahead - the Remaining Challenges
Latvia Looking Ahead - the Remaining Challenges Latvia Looking Ahead - the Remaining Challenges
Latvia Looking Ahead - the Remaining Challenges Latvijas Banka
 
el paso 09_04LehmanBrothersConference_FINAL
el paso  09_04LehmanBrothersConference_FINALel paso  09_04LehmanBrothersConference_FINAL
el paso 09_04LehmanBrothersConference_FINALfinance49
 
MK Property Forum 27.09.12
MK Property Forum 27.09.12MK Property Forum 27.09.12
MK Property Forum 27.09.12mkpla
 

Was ist angesagt? (14)

Trinidad & Tobago - Trade Profile [UWI's Shridath Ramphal Centre]
Trinidad & Tobago - Trade Profile [UWI's Shridath Ramphal Centre]Trinidad & Tobago - Trade Profile [UWI's Shridath Ramphal Centre]
Trinidad & Tobago - Trade Profile [UWI's Shridath Ramphal Centre]
 
Mirus Credit Market Update112508
Mirus Credit Market Update112508Mirus Credit Market Update112508
Mirus Credit Market Update112508
 
Iochpe-Maxion - 2Q07 Presentation
Iochpe-Maxion - 2Q07 PresentationIochpe-Maxion - 2Q07 Presentation
Iochpe-Maxion - 2Q07 Presentation
 
Las Vegas Americas Market Beat Industrial Q42011
Las Vegas Americas Market Beat Industrial Q42011Las Vegas Americas Market Beat Industrial Q42011
Las Vegas Americas Market Beat Industrial Q42011
 
regions Lehman_2007/09/11
regions Lehman_2007/09/11regions Lehman_2007/09/11
regions Lehman_2007/09/11
 
Tim meeting with investors - sep 2012
Tim   meeting with investors - sep 2012Tim   meeting with investors - sep 2012
Tim meeting with investors - sep 2012
 
E2AGP - Country Portfolio
E2AGP - Country PortfolioE2AGP - Country Portfolio
E2AGP - Country Portfolio
 
Msia Economics Monthly - 0711
Msia Economics Monthly - 0711Msia Economics Monthly - 0711
Msia Economics Monthly - 0711
 
World constructionreport 2012
World constructionreport 2012World constructionreport 2012
World constructionreport 2012
 
Oportunidades Renta Fija Andy Wells, Fidelity, enero 2013
Oportunidades Renta Fija Andy Wells, Fidelity, enero 2013Oportunidades Renta Fija Andy Wells, Fidelity, enero 2013
Oportunidades Renta Fija Andy Wells, Fidelity, enero 2013
 
EP09_18BankofAmerica
EP09_18BankofAmericaEP09_18BankofAmerica
EP09_18BankofAmerica
 
Latvia Looking Ahead - the Remaining Challenges
Latvia Looking Ahead - the Remaining Challenges Latvia Looking Ahead - the Remaining Challenges
Latvia Looking Ahead - the Remaining Challenges
 
el paso 09_04LehmanBrothersConference_FINAL
el paso  09_04LehmanBrothersConference_FINALel paso  09_04LehmanBrothersConference_FINAL
el paso 09_04LehmanBrothersConference_FINAL
 
MK Property Forum 27.09.12
MK Property Forum 27.09.12MK Property Forum 27.09.12
MK Property Forum 27.09.12
 

Mehr von Petrobras

Strategic Plan 2040 || Business and Management Plan 2019-2023
Strategic Plan 2040 || Business and Management Plan 2019-2023Strategic Plan 2040 || Business and Management Plan 2019-2023
Strategic Plan 2040 || Business and Management Plan 2019-2023Petrobras
 
Plano Estratégico 2040 || Plano de Negócios e Gestão 2019-2023
Plano Estratégico 2040 || Plano de Negócios e Gestão 2019-2023Plano Estratégico 2040 || Plano de Negócios e Gestão 2019-2023
Plano Estratégico 2040 || Plano de Negócios e Gestão 2019-2023Petrobras
 
Petrobras Overview - September 2018
Petrobras Overview - September 2018Petrobras Overview - September 2018
Petrobras Overview - September 2018Petrobras
 
Apresentação Investor Day, São Paulo, 2018
Apresentação Investor Day, São Paulo, 2018Apresentação Investor Day, São Paulo, 2018
Apresentação Investor Day, São Paulo, 2018Petrobras
 
Petrobras Investor Day - London 2018
Petrobras Investor Day - London 2018Petrobras Investor Day - London 2018
Petrobras Investor Day - London 2018Petrobras
 
Sustentabilidade 2017
Sustentabilidade 2017Sustentabilidade 2017
Sustentabilidade 2017Petrobras
 
Apresentacao png-2018-2022-webcast-ingles
Apresentacao png-2018-2022-webcast-inglesApresentacao png-2018-2022-webcast-ingles
Apresentacao png-2018-2022-webcast-inglesPetrobras
 
Apresentação PNG 2018-2022
Apresentação PNG 2018-2022Apresentação PNG 2018-2022
Apresentação PNG 2018-2022Petrobras
 
Apresentação de Pedro Parente no Investor Day Nova York
Apresentação de Pedro Parente no Investor Day Nova YorkApresentação de Pedro Parente no Investor Day Nova York
Apresentação de Pedro Parente no Investor Day Nova YorkPetrobras
 
Apresentação de Pedro Parente no Investor Day Londres
Apresentação de Pedro Parente no Investor Day LondresApresentação de Pedro Parente no Investor Day Londres
Apresentação de Pedro Parente no Investor Day LondresPetrobras
 
Apresentação de Pedro Parente no Investor Day São Paulo
Apresentação de Pedro Parente no Investor Day São PauloApresentação de Pedro Parente no Investor Day São Paulo
Apresentação de Pedro Parente no Investor Day São PauloPetrobras
 
Visão Geral 2017 fevereiro
Visão Geral   2017 fevereiro Visão Geral   2017 fevereiro
Visão Geral 2017 fevereiro Petrobras
 
Petrobras General Overview
Petrobras General OverviewPetrobras General Overview
Petrobras General OverviewPetrobras
 
Petrobras at a Glance
Petrobras at a GlancePetrobras at a Glance
Petrobras at a GlancePetrobras
 
Visão Geral Petrobras
Visão Geral PetrobrasVisão Geral Petrobras
Visão Geral PetrobrasPetrobras
 
Strategic Plan and 2017-2021 Business & Management Plan
Strategic Plan and 2017-2021 Business & Management PlanStrategic Plan and 2017-2021 Business & Management Plan
Strategic Plan and 2017-2021 Business & Management PlanPetrobras
 
Plano Estratégico e Plano de Negócios e Gestão 2017-2021
Plano Estratégico e Plano de Negócios e Gestão 2017-2021Plano Estratégico e Plano de Negócios e Gestão 2017-2021
Plano Estratégico e Plano de Negócios e Gestão 2017-2021Petrobras
 
Plano de Negócios e Gestão 2015 – 2019
Plano de Negócios e Gestão 2015 – 2019 Plano de Negócios e Gestão 2015 – 2019
Plano de Negócios e Gestão 2015 – 2019 Petrobras
 
Webcast 1T16
Webcast 1T16Webcast 1T16
Webcast 1T16Petrobras
 
Webcast 1Q16
Webcast 1Q16Webcast 1Q16
Webcast 1Q16Petrobras
 

Mehr von Petrobras (20)

Strategic Plan 2040 || Business and Management Plan 2019-2023
Strategic Plan 2040 || Business and Management Plan 2019-2023Strategic Plan 2040 || Business and Management Plan 2019-2023
Strategic Plan 2040 || Business and Management Plan 2019-2023
 
Plano Estratégico 2040 || Plano de Negócios e Gestão 2019-2023
Plano Estratégico 2040 || Plano de Negócios e Gestão 2019-2023Plano Estratégico 2040 || Plano de Negócios e Gestão 2019-2023
Plano Estratégico 2040 || Plano de Negócios e Gestão 2019-2023
 
Petrobras Overview - September 2018
Petrobras Overview - September 2018Petrobras Overview - September 2018
Petrobras Overview - September 2018
 
Apresentação Investor Day, São Paulo, 2018
Apresentação Investor Day, São Paulo, 2018Apresentação Investor Day, São Paulo, 2018
Apresentação Investor Day, São Paulo, 2018
 
Petrobras Investor Day - London 2018
Petrobras Investor Day - London 2018Petrobras Investor Day - London 2018
Petrobras Investor Day - London 2018
 
Sustentabilidade 2017
Sustentabilidade 2017Sustentabilidade 2017
Sustentabilidade 2017
 
Apresentacao png-2018-2022-webcast-ingles
Apresentacao png-2018-2022-webcast-inglesApresentacao png-2018-2022-webcast-ingles
Apresentacao png-2018-2022-webcast-ingles
 
Apresentação PNG 2018-2022
Apresentação PNG 2018-2022Apresentação PNG 2018-2022
Apresentação PNG 2018-2022
 
Apresentação de Pedro Parente no Investor Day Nova York
Apresentação de Pedro Parente no Investor Day Nova YorkApresentação de Pedro Parente no Investor Day Nova York
Apresentação de Pedro Parente no Investor Day Nova York
 
Apresentação de Pedro Parente no Investor Day Londres
Apresentação de Pedro Parente no Investor Day LondresApresentação de Pedro Parente no Investor Day Londres
Apresentação de Pedro Parente no Investor Day Londres
 
Apresentação de Pedro Parente no Investor Day São Paulo
Apresentação de Pedro Parente no Investor Day São PauloApresentação de Pedro Parente no Investor Day São Paulo
Apresentação de Pedro Parente no Investor Day São Paulo
 
Visão Geral 2017 fevereiro
Visão Geral   2017 fevereiro Visão Geral   2017 fevereiro
Visão Geral 2017 fevereiro
 
Petrobras General Overview
Petrobras General OverviewPetrobras General Overview
Petrobras General Overview
 
Petrobras at a Glance
Petrobras at a GlancePetrobras at a Glance
Petrobras at a Glance
 
Visão Geral Petrobras
Visão Geral PetrobrasVisão Geral Petrobras
Visão Geral Petrobras
 
Strategic Plan and 2017-2021 Business & Management Plan
Strategic Plan and 2017-2021 Business & Management PlanStrategic Plan and 2017-2021 Business & Management Plan
Strategic Plan and 2017-2021 Business & Management Plan
 
Plano Estratégico e Plano de Negócios e Gestão 2017-2021
Plano Estratégico e Plano de Negócios e Gestão 2017-2021Plano Estratégico e Plano de Negócios e Gestão 2017-2021
Plano Estratégico e Plano de Negócios e Gestão 2017-2021
 
Plano de Negócios e Gestão 2015 – 2019
Plano de Negócios e Gestão 2015 – 2019 Plano de Negócios e Gestão 2015 – 2019
Plano de Negócios e Gestão 2015 – 2019
 
Webcast 1T16
Webcast 1T16Webcast 1T16
Webcast 1T16
 
Webcast 1Q16
Webcast 1Q16Webcast 1Q16
Webcast 1Q16
 

Kürzlich hochgeladen

Q1 Quarterly Update - April 16, 2024.pdf
Q1 Quarterly Update - April 16, 2024.pdfQ1 Quarterly Update - April 16, 2024.pdf
Q1 Quarterly Update - April 16, 2024.pdfProbe Gold
 
Collective Mining | Corporate Presentation | April 2024
Collective Mining | Corporate Presentation | April 2024Collective Mining | Corporate Presentation | April 2024
Collective Mining | Corporate Presentation | April 2024CollectiveMining1
 
Q1 Probe Gold Quarterly Update- April 2024
Q1 Probe Gold Quarterly Update- April 2024Q1 Probe Gold Quarterly Update- April 2024
Q1 Probe Gold Quarterly Update- April 2024Probe Gold
 
Mandalay Resources 2024 April IR Presentation
Mandalay Resources 2024 April IR PresentationMandalay Resources 2024 April IR Presentation
Mandalay Resources 2024 April IR PresentationMandalayResources
 
Corporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfCorporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfProbe Gold
 
Collective Mining | Corporate Presentation - April 2024
Collective Mining | Corporate Presentation - April 2024Collective Mining | Corporate Presentation - April 2024
Collective Mining | Corporate Presentation - April 2024CollectiveMining1
 
Corporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfCorporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfProbe Gold
 
Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024
Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024
Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024Osisko Gold Royalties Ltd
 
slideshare_2404_presentation materials_en.pdf
slideshare_2404_presentation materials_en.pdfslideshare_2404_presentation materials_en.pdf
slideshare_2404_presentation materials_en.pdfsansanir
 
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...USDAReapgrants.com
 
the 25 most beautiful words for a loving and lasting relationship.pdf
the 25 most beautiful words for a loving and lasting relationship.pdfthe 25 most beautiful words for a loving and lasting relationship.pdf
the 25 most beautiful words for a loving and lasting relationship.pdfFrancenel
 

Kürzlich hochgeladen (12)

Q1 Quarterly Update - April 16, 2024.pdf
Q1 Quarterly Update - April 16, 2024.pdfQ1 Quarterly Update - April 16, 2024.pdf
Q1 Quarterly Update - April 16, 2024.pdf
 
Collective Mining | Corporate Presentation | April 2024
Collective Mining | Corporate Presentation | April 2024Collective Mining | Corporate Presentation | April 2024
Collective Mining | Corporate Presentation | April 2024
 
Q1 Probe Gold Quarterly Update- April 2024
Q1 Probe Gold Quarterly Update- April 2024Q1 Probe Gold Quarterly Update- April 2024
Q1 Probe Gold Quarterly Update- April 2024
 
Mandalay Resources 2024 April IR Presentation
Mandalay Resources 2024 April IR PresentationMandalay Resources 2024 April IR Presentation
Mandalay Resources 2024 April IR Presentation
 
Corporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfCorporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdf
 
Collective Mining | Corporate Presentation - April 2024
Collective Mining | Corporate Presentation - April 2024Collective Mining | Corporate Presentation - April 2024
Collective Mining | Corporate Presentation - April 2024
 
Corporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfCorporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdf
 
Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024
Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024
Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024
 
slideshare_2404_presentation materials_en.pdf
slideshare_2404_presentation materials_en.pdfslideshare_2404_presentation materials_en.pdf
slideshare_2404_presentation materials_en.pdf
 
Korea District Heating Corporation 071320 Algorithm Investment Report
Korea District Heating Corporation 071320 Algorithm Investment ReportKorea District Heating Corporation 071320 Algorithm Investment Report
Korea District Heating Corporation 071320 Algorithm Investment Report
 
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
 
the 25 most beautiful words for a loving and lasting relationship.pdf
the 25 most beautiful words for a loving and lasting relationship.pdfthe 25 most beautiful words for a loving and lasting relationship.pdf
the 25 most beautiful words for a loving and lasting relationship.pdf
 

4th Itaú BBA LATAM Commodities Conference

  • 1. 4th Itaú BBA LATAM Commodities Conference Maria das Graças Silva Foster Petrobras’ CEO September 26th, 2012
  • 2. DISCLAIMER FORWARD-LOOKING STATEMENTS The presentation may contain forward-looking statements about We undertake no obligation to publicly update or revise any future events within the meaning of Section 27A of the Securities Act forward-looking statements, whether as a result of new of 1933, as amended, and Section 21E of the Securities Exchange information or future events or for any other reason. Figures Act of 1934, as amended, that are not based on historical facts and for 2012 on are estimates or targets. are not assurances of future results. Such forward-looking statements merely reflect the Company’s current views and estimates of future economic circumstances, industry conditions, All forward-looking statements are expressly qualified in their company performance and financial results. Such terms as entirety by this cautionary statement, and you should not "anticipate", "believe", "expect", "forecast", "intend", "plan", "project", place reliance on any forward-looking statement contained in "seek", "should", along with similar or analogous expressions, are this presentation. used to identify such forward-looking statements. Readers are cautioned that these statements are only projections and may differ materially from actual future results or events. Readers are referred NON-SEC COMPLIANT OIL AND GAS RESERVES: to the documents filed by the Company with the SEC, specifically the CAUTIONARY STATEMENT FOR US INVESTORS Company’s most recent Annual Report on Form 20-F, which identify important risk factors that could cause actual results to differ from We present certain data in this presentation, such as oil and those contained in the forward-looking statements, including, among gas resources, that we are not permitted to present in other things, risks relating to general economic and business documents filed with the United States Securities and conditions, including crude oil and other commodity prices, refining Exchange Commission (SEC) under new Subpart 1200 to margins and prevailing exchange rates, uncertainties inherent in Regulation S-K because such terms do not qualify as proved, making estimates of our oil and gas reserves including recently probable or possible reserves under Rule 4-10(a) of discovered oil and gas reserves, international and Brazilian political, Regulation S-X. economic and social developments, receipt of governmental approvals and licenses and our ability to obtain financing. 2
  • 3. Brazil: Economic and Social Development Consumption Increase BRAZIL Unemployment -5.7 p.p. UNEMPLOYMENT Rate (%) Jobs generation contributing to increase the wage bill. 2002 2011 Extreme Poverty -5.5 p.p. Population in EXTREME POVERTY LEVEL (%) Improvement in income distribution with poverty reduction. 2001 2009 +21.7 p.p. (% of population) RISE OF SOCIAL CLASSES A, B and C Class Income level of families is growing leading to social mobility. 2003 2011 -8.25 p.p. INTEREST RATE (% p.y.) Selic Reduction in interest rate stimulating productive investment. 2000 2012 +35% (Kg / hab. year) Consumption CONSUMPTION PER CAPITA OF Per Capita THERMOPLASTIC RESINS 31 23 The consumption evolution is a consequence of the economical growth and a higher power of consumption. 2000 2010 Sources: Banco Central do Brasil, Meta Selic dez/00 e ago/12; Abiquim. http://www.abiquim.org.br/resinastermoplasticas/estatisticas_33.asp - acesso 29/ago/12; Pesquisa Mensal de Emprego, IBGE. Nova série histórica disponível apenas de março/02 a maio/12; “De Volta ao País do Futuro: Projeções, Crise Européia e a Nova Classe Média”, FGV, março/12.; Comunicados do IPEA nº 63: PNAD 2009 Primeiras Análises: Distribuição de Renda entre 1995 e 2009. Out/10. 3
  • 4. Brazil: Oil Products Market Grows Above World Average BRAZIL WORLD Between 2000 and 2011... +49% +15% GASOLINE CONSUMPTION Gasoline Demand (kbpd) WORLD : +1.3% a.a. 469 22,533 315 19,616 BRAZIL: +3.7% a.a. • Jan-Aug12 x Jan-Aug11: +23% 2000 2011 2000 2011 DIESEL CONSUMPTION +43% +29% Demand (kbpd) Diesel WORLD : +2.3% a.a. 626 896 20,220 26,072 BRAZIL: +3.3% a.a. • Jan-Aug12 x Jan-Aug11: +6,7% 2000 2011 2000 2011 JET FUEL CONSUMPTION +53% -2% Demand Jet Fuel WORLD: -0,2% a.a. (kbpd) 121 6,506 6,393 BRAZIL: +4,0% a.a. 79 • Jan-Aug12 x Jan-Aug11: +7,9% 2000 2011 2000 2011 OIL FUEL CONSUMPTION -56% -18% Demand (kbpd) WORLD: -1,8% a.a. Oil Fuel 189 9,675 7,958 BRAZIL: -7,1% a.a. 84 • Jan-Aug12 x Jan-Aug11: -5,4% 2000 2011 2000 2011 Sources: Petrobras for Brazil data and Woodmackenzie for international data. 4
  • 5. Petrobras Today: Proved Reserves + Potential Recoverable Volumes: 31.5 bi boe Petrobras’ Proved Reserves : 15.7 bi boe Potential Growth: + 15.8 bi boe Million boe 35,000 35.000 Potential Growth Concession – Potential 10.8 bi 30,000 30.000 • 2005-2010: more than 50% of new discoveries around the world were in deep Recoverable Volumes boe water, with Brazil representing 63% of these discoveries. (PFC Energy, jun/11) 19% 25,000 25.000 • From 2005 to 2012 Petrobras declared 63 discoveries in pre-salt area and 49% 189 in other areas to ANP. (Petrobras, aug/12) 32% 20,000 20.000 Brasil Transfer of Rights 5.0 bi • 2030: Brazil should present the highest growth production among the countries Brasil boe that are not members of OPEC. (PFC Energy, jun/11) 15.71 15,000 15.000 Ultra-Deep Water 5.3 bi boe (>1,500m) 10.000 10,000 7.9 bi boe Deep Water (300-1,500m) 5,000 5.000 Shallow-Water (0-300m) 1.2 bi boe Onshore 1.3 bi boe 0 1965 1970 1975 1980 1985 1990 1995 2000 2005 2010 2011 • Added Reserves in 2011 = 1.24 billion boe. • Pre-Salt Added Reserves: 1 billion boe. • Reserve/Production Ratio  19.2 year. 5
  • 6. Production Increase and Breakdown of Oil and Gas Reserves of Major Companies: 2002 to 2011 PETROBRAS Oil and Natural Gas 5 (million boe/d) 4 Production +45% 2.6 3 2 1.8 0.5 0.3 Overseas 1 1.5 2.1 Brazil 0 2002 2011 Reserves 84% 16% Breakdown (2010) Oil Gas Oil and Natural Gas Production (million boe/d) EXXON MOBIL BP SHELL CHEVRON +6% -19% -2% +2% 2002 2011 2002 2011 2002 2011 2002 2011 Breakdown (2010) Reserves 47% 53% 60% 40% 44% 56% 62% 38% Oil Gas Oil Gas Oil Gas Oil Gas Fonte: Evaluate Energy e WoodMackenzie, set/12. 6
  • 7. Our Advantage: The Value of Our Reserves and the Pre-Salt Reality Oil and NGL Production (jan-jul/12):  Total Brazil: 2.007 kbpd  Onshore: 210 kbpd  Offshore • Post-Salt: 1.681 kbpd • Pre-Salt: 116 kbpd* * Including partners: 148,3 kbpd Record (incl. partners): 174,2 kbpd (jul/12) 7 7
  • 8. Fundamentals of Business and Management Plan 2012-2016 PRIORITY CAPITAL PERFORMANCE DISCIPLINE Financiability Assumptions • Priority given • Management • Maintenance of Investment to exploration focused in Grade • To ensure and production accomplishing • There is no issuance of new expansion with projects of oil physical and shares solid financial and natural gas financial targets • Oil Products Import Price indicators in Brazil of each project Parity • Divestment of existing assets abroad 2012 2016 8
  • 9. Projects Under Implementation and Projects Under Evaluation Under Implementation Under Evaluation 2012-2016 BP = Projects with construction already started + Projects in Phase I, II and III US$ 236.5 Billion US$ 208.7 Billion US$ 27.8 Billion 980 projects 833 projects 147 projects CONSTRUCTION 27.7% 24.8% 17% (**) (US$ 65.5 Billion) US$ 51.7 Billion (US$ 4.6 Billion) 28% 7% (US$ 1.9 Billion) 0% 65.8% (US$ 0.1 Billion) 60.0% 3.7% 50% (US$ 141.8 Billion) (US$ 137.2 Billion) (US$ 7.8 Billion) 5% (US$ 13.9 Billion) 5.8% (US$ 1.3 Billion) 1.8% (US$ 13.8 Billion (US$ 3.7 Billion) 2.1% 1.7% (US$ 5.0 Billion) (US$ 3.5 Billion) 21% 1.5% (US$ 3.6 Billion) 0.9% (US$ 6.0 Billion) 1.6% (US$ 1.9 Billion) 1.4% 1.3% (US$ 3.8 Billion) (US$ 3.0 Billion) (US$ 3.0 Billion) ** E&P abroad E&P RTM G&E Petrochemical Distribution Biofuel Corporate 9
  • 10. Business and Management Plan 2012-2016: US$ 236.5 Billion INVESTMENTS UNDER IMPLEMENTATION US$ 131.6 billion US$ 55.8 billion US$ 7.7 billion US$ 6 billion US$ 3.2 billion US$ 1.2 billion E&P Downstream Gas & Power International Distribution Biofuels 4% 1% 1% 1% 3% 5% (2,4) (0,5) 1% (0,03) 4% (0,1) (0,1) (0,01) (2,9) 6% 6% 10% (0,2) 7% 13% 2% (0,07) 19% (0,5) (0,7) (0,4) (0,42) 9% (0,1) (25,4) 20% (4,8) (1,5) 43% US$ + + + + + = 45% 24% 21% 12% (1,9) (1,39) (24,9) (0,70) 17% 208.7 bi (16,3) (9,4) 68% (89,9) 7% 1% 20% 32% (0,6) 85% 21% (0,01) 90% (2,5) (5,1) (11,0) (0,67) (1,05) + E&P R&M Distribuição G&E Petroquímica Corporativo 3% 3% 7% (0,5) (US$ 0,1 Bi) 5% (1,1) (0,8) 15% 21% 21% (0,9) 1% (0,3) (0,3) (0,01) US$ 41% 8% + + + + + = (6,4) (0,5) 100% 54% (0,10) 37% (3,2) 22% 27.8 bi (5,8) (1,3) 8% 97% 57% (1,2) (US$ 4,6 Bi) (0,8) E&P Downstream Gas & Power International E&P Distribution Biofuels US$ - US$ 15.8 billion US$ 5.9 billion US$ 4.7 billion G&E US$ 0.1 billion US$ 1.4 billion INVESTMENTS UNDER EVALUATION 10
  • 11. Systematic Approval of Projects and Organizational Learning Projects under Evaluation Projects under Implamentation Projects under Operation PROJECTS INITIATION AND PLANNING Appproval of Platform P-57 the Basic Phase IV Phase V PHASE I PHASE II EVTE¹ and Work Start up & PHASE III clearance for Opportunity Conceptual Execution Operation Basic Project execution Identification Project (work start) RNEST GASTAU Included at Approval of Approval of Petrobras EVTE¹ Phase EVTE¹ Portfolio I Concptual ¹EVTE: Technical and Economic Feasibility Study UTE Baixada Fluminense EXPERTISE ACQUIRED: GATHER KNOWLEDGES IN EACH PHASE OF PROJECTS DEVELOPMENT Normative Procedures Documents Validation and Changes and improvements included in the next project EXPERTISE Approval of ACQUIRED Knowledge’s NORTEC MAGES SINAPSE Register, Items Petrobras Technical Petrobras Normalization Management Guide. Consultation and SINAPSE: Integrated environment that allows the record learning of workforce. Suports the record process, interaction analyses, consolidation, recovery and, mainly, implementation of learned lessons. 11
  • 12. REVAP – São José dos Campos (SP) Site of RNEST – Ago/12  Inaugurated in 1980: Project by Snamprogetti.  First refinery constructed by Petrobras since 1980. Expertise Acquired Premium I and II – International Metrics Typical Chinese Projects  The experience acquired enable the conception of new refineries in MA, CE and RJ, within the international metrics of price, term and standardized technologies.  Capacity: 230 kbpd  Production of Diesel: 161 kbpd (70%)  Current Situation: in construction, 62% physical progress Place: Qinzhou, China Place: Huizhou, China Start up: November/2014 Capacity (Mbpd): 200 Capacity (Mbpd): 240  CAPEX: US$ 17 billions. Construction time: 52 months Construction time: 46 months Jobs Generated: 43,500 jobs Start up: Sep/2010 Start up: May/2009  Local Content: 91% 12
  • 13. P-57 – Jubarte Field: Capacity of 180 kbpd Local Content (LC): 69% Platform P-57 started operation in December 2010, 3 months before contractual term, with 69% of local content and currently is producing 138 kbpd (1Q12) at Jubarte Field. Expertise Acquired The Challenge is Huge! P-62 – Roncador Module IV Start up in Mar/14 - LC 65% Franco 4 Lula Alto Lula Ext. P-66 Sul P-70 Sul de Guará Lula Central Iara Horst Piloto Baúna P-67 P-71 Júpiter e Piracaba (SS-11) NE Tupi Carcará Maromba Espadarte III Norte Pq. Lula Sul P-68 P-76 P-73 Bonito Florim Cachalote e Baleias (P-58) Baleia Franca Piloto Sapinhoá Carimbé Sul Pq. Entorno de Franco 1 (Capixaba) (Cid. São Paulo) Roncador IV Baleias Iara (P-62) P-74 Aruanã Uruguá / Piloto Lula NE Franco 5 Sapinhoá Norte Carioca Z2 Iara NW Tambaú (Cid. Paraty) (Cid. Ilhabela) P-72 Espadarte I 4.200 (Cid. Santos) Lula Norte Baleia Azul Papa-Terra Iracema Sul P-69 Franco 3 Piloto Lula Mexilhão (Cid. Anchieta) (P-61 e P-63) Iracema (Cid. Franco 2 P-77 (Cid. Angra (PMXL-1) Baúna e Roncador III Norte Z1 Mangaratiba) P-75 dos Reis) (P-55) Marlim Sul Piracaba Jubarte Jubarte (P-56) (Cid. Itajaí) 24 btwn 2012 and 2016 Drilling Rigs (P-57) (P-57) LDA > 2.000 m 49 btwn 2012 and 2020 2.500 2.004 2.022 19 btwn 2012 and 2016 UEPs 38 btwn 2012 and 2020 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 Construction of P-62 180 kbpd of capacity – Ago/12 13
  • 14. Oil and NGL Production Curve in Brazil: 2011 and 2012 Target 2012: 2,022 kbpd (+/- 2%) kbpd 2011 2012 2.200 2Q11 1Q12 2Q12 average: 2,018 average: 2,066 average: 1,970 2.150 2,110 2,084 2,098 2.100 2,069 2,061 2,040 2,047 2.050 2,020 2,002 2,001 1,989 2,003 2,003 2.000 1,993 1,960 1,968 1,963 1,961 1,940 1.950 50 Jan/11 Feb/11 Mar/11 Apr/11 May/11 Jun/11 Jul/11 Aug/11 Sep11 Oct/11 Nov/11 Dec/11 jan/12 fev/12 mar/12 abr/12 mai/12 jun/12 jul/12 jan/11 fev/11 mar/11 abr/11 mai/11 jun/11 jul/11 ago/11 set/11 out/11 nov/11 dez/11 Jan/12 Feb/12 Mar/12 Apr/12 May/12 Jun/12 Jul/12  5% decrease in production 2Q12/1Q12 (- 96 kbpd) as a result of: • Operational stoppages(-54 kbpd), lower operational efficiency (-18 kbpd) and interruption of Frade (-15 kbpd). • Decline of old systems´potential as expected, around 11% p.y. The average rate worldwide for big and giant fields in deepwater is between 10% and 15% p.y.  Start-up of 2 new systems in 2H12: • FPSO Cidade de Anchieta (Baleia Azul), 100 kbpd capacity, started on 09/10/12, peak in Feb/13 • FPSO Cidade de Itajaí (Baúna e Piracaba), 80 kbpd capacity, built in Singapore, postponed from October to December. • Authorization to operate production unit SS-11 untill 28/Feb/2013 requested to ANP.  Maintenance of 2012 oil production target (flat when compared to 2011, +/-2%): • Production recovery only in 4Q12 (scheduled stoppages will continue on 3Q12). 14
  • 15. PROEF: Initiatives to Recover Operational Efficiency – UO-BC Improve Campos Basin Increase the oil curve delivery PROEF Improve production Operational Unit reliability, provided Objectives systems integrity efficiency levels in 2012-2016 BP Campos Basin Operational Efficiency – UO-BC 89 90 88 88 PROEF Targets Operational Executed 80 81 efficiency (%) targets for 76 74 PROEF Disbursements: Campos 71 • Well workovers, subsea systems and Basin Unit platforms intervention through maintenance units: US$ 5.1 Bi (2012- 16) PROEF Estimated NPV: • US$ 1.6 Bn - US$ 3.3 Bn 2008 2009 2010 2011 2012 2013 2014 2015 2016 Operational Efficiency HC / PAD Fields • Without UO-BC: 94% 95% 94% UO-BC Assets • E&P Total: 90% 87% 86% 15
  • 16. 38 Production Units: 2012 – 2020 Production Units: 2012-2013 Oil Production, Brazil: 2,022 – 4,200 kbpd P-66 P-70 CO5 (Lula (Lula Ext. (Franco 4) High) South) CO6 P-67 P-71 (South of (Lula (Iara Horst) Guará) Central) P-76 Júpiter Oil and NGL Production Curve (kbpd) P-58 P-68 (NE Tupi) Maromba P-73 Espadarte III  Cid. São (Whales Park (Lula Afretada (Carcará) Bonito Paulo North) South) CO9 (Piloto de (Carimbé) Whales CO8 (Florim) P-62 P-74 Sapinhoá) Aruanã Parq South (Iara (Roncador (Franco 1)  Cid. Paraty mod. IV) P-72 CO7 Surround) Z2 (Piloto de Lula Cid. Ilhabela (Iara NW) (Franco 5) (Carioca) NE) (Sapinhoá Espadarte I P-69 P-77  P-61 North) (Lula (Franco 3)  Cid.  P-63 (Papa- North) Anchieta Cid. Z1 Terra) Mangaratiba (Baleia Azul) Iracema P-75  P-55 (Iracema North (Franco 2)  Cid. Itajaí (Roncador South) (Baúna e mod. III) Piracaba) 23 Already Contracted Production Units 19 up to 2016 15 to Contract Construction 38 up to 2020 (from nov/12 to apr/17) 16
  • 17. FPSO Cidade de Anchieta – Baleia Azul Operating since sep/10/12 Production Ramp up Interconnection of (bpd) Producing Wells Sep/12 29,700 1st Well sep/10/12 Oct/12 52,185 2nd Well sep/21/12 Nov/12 52,185 3rd Well sep/26/12 Dec/12 72,000 4th Well nov/12/12 Peak (100 kbpd): Feb/13 5th Well nov/13/12 Local Content - Mandatory: 0% / Forecast Accomplishment : 44% 17
  • 18. Baleia Azul Project – FPSO Cidade de Anchieta (1st Oil: Sep/12) Meeting of Critical Analysis (RAC) Monthly: CEO + E&P Director + Engineering, Technology and Materials Director PHYSICAL PROGRESS OF THE PROJECT – S CURVE IMPLEMENTATION LANDMARKS 1 - Issuance of Preliminary License (LP) (P:Sep-08 / R:Sep-08) 2 – Conclusion of the Opportunity Evaluation Phase (Gate 1) (P:Dec-08 / R:Dec-08) (P: 100% / R: 100%) 3 – Conclusion of the Conceptual Project Phase (Gate 2) (P:Jul-09 / R:Jul-09) (P: 100% / R: 100%) 4 – Conclusion of the Basic Project Phase (Gate 3) (P:Dez-09 / R:Dez-09) (P: 100% / R: 100%) st 5 – Beginning of the Construction of the 1 Well (P:Jan-11 / R:Feb-11) 6 – Issuance of the Instalation License (LI) (P:Dec-11 / R:Dec-11) 7 – Arrival of the Unit in the Local (P:Ago-12 / R:Aug-12) st 8 – Beginning of Interconnection of the 1 Well (P:Aug-12 / R:Aug-12) 9 – Issuance of the Operating License (LO) (P:Aug-12 / R:Sep-12) 10 – Interconnection of the Last Well (P:Mar-13 / Proj:Mar-13) Baseline Baseline 2012-2016 BP Accomplished Forecast Fonte :SAP/PNG 12-16: 30/06/12. Data de Medição pela Diretoria de Exploração & Produção: 13/09/12. Linha de Base: EVTE da Fase III, aprovado em 03/12/2009, Ata DE 4.787. / Projetado: Replanejamento realizado em Julho/12. 18
  • 19. Baúna e Piracaba Project – FPSO Cidade de Itajaí (1st Oil: Dec/12) Meeting of Critical Analysis (RAC) Monthly: CEO + E&P Director + Engineering, Technology and Materials Director PHYSICAL PROGRESS OF THE PROJECT – S CURVE IMPLEMENTATION LANDMARKS 1 - Conclusion of the Opportunity Evaluation Phase (Gate 1) (P:Mar-10 / R:Mar-10) (P: 100% / R: 100%) 2 - Conclusion of the Conceptual Project Phase (Gate 2) (P:May-11 / R:May-11) (P: 100% / R: 100%) st 3- Beginning of Construction of the 1 Well (P:Aug-11 / R:Jul-11) 4 - Conclusion of the Basic Project Phase (Gate 3) (P:Sep-11 / R:Sep-11) (P: 100% / R: 100%) 5 -- Issuance of Preliminary License (PL) (P:Jul-12 / Proj:Sep-12) 6 - Issuance of the Instalation License (LI) (P:Aug-12 / Proj:Sep-12) 7 - Issuance of the Operating License (OL) (P:Sep-12 / Proj:Nov-12) 8 - Arrival of the Unit in the Local (P:Sep-12 / R:Dec-12) st 9 - Beginning of Interconnection of the 1 Well Baúna (P:Sep-12 / Proj:Dec-12) st 10 – Beginning of Construction of the 1 Well Piracaba (P:Mar-13 / Proj:Jan-13) st 11 – Beginning of Interconnection of the 1 Well Piracaba (P:Jun-13 / Proj:May-13) 12 - Interconnection of the Last Well (P:Aug-14 / Proj:Aug-14) apr oct apr oct oct apr apr oct apr oct apr oct apr oct Baseline Baseline 2012-2016 BP Accomplished Forecast Fonte :SAP/PNG 12-16: 30/06/12. Data de Medição pela Diretoria de Exploração & Produção: 13/09/12. Linha de Base: EVTE da Fase III, aprovado em 03/12/2009, Ata DE 4.787. / Projetado: Replanejamento realizado em Julho/12. Local Content: Mandatory: 60% / Forecast Accomplishment : 81% 19
  • 20. FPSO Cidade de São Paulo - Sapinhoá Pilot (1st Oil: Jan/13) Local Content - Mandatory :30% / Forecast Accomplishment :50% Hull Conversion - Cosco (China) Modules Construction: AIBEL (Thailand) 1. Main Gas Compression A 2. Main Gas Compression B 3. Gas Treatment - CO2 Removal 4. Gas Reinjection 5. CO2 Injection 6. Oil Processing – High Pressure 7. Oil Processing – Low Pressure 8. Utilities and Water Injection Modules Construction: BOOMESC (China) 9. Energy Generation 10. E-House MCC – Panels Room 11. Piperack Modules Construction: ENAVAL/VEOLIA – Niterói (RJ) 12. Salt Water Treatment Modules Construction: BrasFels Shipyards– Angra dos Reis (RJ) 13. Arrival Risers Manifolds Enaval - Niteroi (RJ) 14. Operation Cargo Area - 1S Brasfels Shipyard – Angra (RJ) 15. Operation Cargo Area - 5S 16. Flare Chimney Integration: BrasFels Shipyards – Angra dos Reis (RJ) Modules Integration from hull 1 to 16 20
  • 21. FPSO - Cidade de São Paulo: Modules Construction and Integration at BrasFels Shipyard FPSO Cidade de São Paulo View of BrasFels Shipyard, in Angra dos Reis – RJ (08//31/12). 21
  • 22. FPSO Cidade de São Paulo – Sapinhoá Pilot (1st Oil: Jan/13) Monthly Meeting of Critical Analysis (RAC) : CEO + E&P Director + Engineering, Technology and Materials Director PHYSICAL PROJECT MONITORING – ‘S’ CURVE IMPLEMENTATION LANDMARKS: 1 – Beginning of Construction of the 1st Well (P:mar-12 / R:feb-12) Start-Up Forecast: 2 – Issuance of Preliminary License (LP) (P:may-12/ R:sep-12) Jan/13 3 – Issuance of the Instalation License (LI) (P:may-12 /Proj:sep-12) 4 – Basic Design Conclusion (Gate 3) (P:july-12 /Proj:oct-12) (P: 89% / R: 90%) 5 – Production Unit (PU) in the Site (P:nov-12 /Proj:nov-12) Start-Up 6 – Operation License Issue (LO) (P:dec-12 /Proj:dec-12) BP 12-16: Jan/13 st 7 – 1 Well Interconnection Start (P:dez-12 /Proj:dez-12) 8 - Exports Gas Pipeline Interconnection (P:aug-13 /Proj:aug-13) 9 – Last Well Interconection (P:oct-15 /Proj:oct-15) Start-Up EVTE: Dec/12 Fonte :SAP/PNG 12-16: 30/06/12. Data de Medição pela Diretoria de Exploração & Produção: 13/09/12. Linha de Base: EVTE da Fase III, aprovado em 03/12/2009, Ata DE 4.787. / Projetado: Replanejamento realizado em Julho/12. 22
  • 23. FPSO Cidade de Paraty – Lula NE Pilot (1st Oil: May/13) Local Content - Mandatory: 30% / Forecast Accomplishment 30% Hull Conversion: Keppel Shipyard - Singapore Modules Construction: Keppel Shipyard - Singapore 1. Energy Generation BB 2. Energy Generation BE 3. Local Equipment Room 4. Maintenance and conversion areas, and moorings 5. Helipad 6. Burners Modules Construction: Nuclep Site Construction (EBSE) – Itaguaí (RJ) 7. Manifold 8. Cargo Operation and Chemical Storage Modules Construction: ENAVAL/VEOLIA – Niterói (RJ) 9. Gas Injection and Compression 16. Salt Water Treatment 10. Gas A Treatment 17. Utilities and Water Injection Modules Construction: BrasFels Shipyard – Angra dos Reis (RJ) Enaval - Niteroi (RJ) 11. Oil A Processing Nuclep - Itaguaí (RJ) 12. Oil B Processing BrasFels Shipyard - Angra (RJ) 13. Gas A Compression 14. Gas B Compression 15. Gas B Treatment Integração: Estaleiro BrasFels – Angra dos Reis (RJ) Modules Integration from hull 1 to 17 23
  • 24. FPSO - Cidade de Paraty: Modules Construction and Integration at BrasFels Shipyard FPSO Cid. de Paraty FPSO Cid. de Paraty Modules 6 5 4 3 2 1 View of BrasFels Shipyard, in Angra dos Reis – RJ (08/31/12). FPSO Cidade de Paraty Modules: (1) TS072 – Main Gas B Compressor; (2) TS062 – Oil A Treatment; (3) TS063 – Oil B Treatment; (4) TS071 – Main Gas A Compressor; (5) TS075 – Gas B Treatment; (6) TS073 –CO2 Compressor; (LC: Full modules package contracted attending 65% of Local Content). 24
  • 25. FPSO - Cidade de Paraty: Modules Construction at Nuclep Construction Canteiro Nuclep - RJ FPSO Cid. de Paraty Modules 2 1 11 View of Nuclep Construction Site, in Angra dos Reis – RJ (08/31/12). FPSO Cidade de Paraty (Hull – Singapore and Integration BrasFels): (1) Gas Injection and Compression (LC:65%); (2) Manifold (LC:65%). 25
  • 26. FPSO Cidade de Paraty – Lula NE Pilot (1st Oil: May/13) Monthly Meeting of Critical Analysis (RAC) : CEO + E&P Director + Engineering, Technology and Materials Director PHYSICAL PROJECT MONITORING – ‘S’ CURVE 100 IMPLEMENTATION LANDMARKS: Operational Entrada em Operação 90 1 – Conclusion of Opportunity Evaluation Phase(Gate 1) (P:may-10/R:may-10) (P:100%/R:100%) Start-Up Forecast Prevista (EVTE): 10 (EVTE): May/13 28/05/13 2 – Conclusion of Conceptual Project Phase (Gate 2) (P:jul-11/R:jun-11) (P:100%/R:100%) 80 3 - Beginning of Construction of the 1st Well (P:feb-12 / R:feb-12) 4 - Issuance of Preliminary License (LP) (P:aug-12 / R: sep-12) 70 5 - Basic Design Conclusion (Gate 3) (P:may-12/R:oct-12) (P:100%/R:95%) Operational Entrada em 60 6 - Issuance of the Instalation License (LI) (P:aug-12 /Proj: oct-12) 8 Operação Forecast: Start-Up Projetada: % % Acumulado 7 - Production Unit (PU) in the Site (P:mar-13 /Proj:mar-13) May/13 28/05/2013 9 Accrued 50 8 - Operation License Issue (LO) (P:mar-13 / Proj:mar-13) 7 st 9 - 1 Well Interconnection Start (P:apr-13 / Proj:apr-13) 6 40 10 - Last Well Interconection (P:apr-16 / Proj:apr-16) Operational Entrada em Operação Justif.2 (A) Start-Up Forecast: Prevista (PNG 12-16): 5 BP 12-16: May/2013 30 Justif.2 (B) 28/05/2013 4 Reference: Aug/12 20 2 Referência: agosto/12 MTD Accrued Forecast BP: No mês Acumulado 1.1% 29.1% 10 1 3 Accomplished: 1,1% Previsto PNG: 1.1% 29,1% 31.8% Realizado: 1,1% 31,8% 0 set-09 set-10 set-11 set-12 set-13 set-14 set-15 mar-09 mai-09 mar-10 mai-10 mar-11 mai-11 mar-12 mai-12 mar-13 mai-13 mar-14 mai-14 mar-15 mai-15 mar-16 mai-16 jul-09 jul-10 jul-11 jul-12 jul-13 jul-14 jul-15 jan-09 jan-10 jan-11 jan-12 jan-13 jan-14 jan-15 jan-16 nov-09 nov-10 nov-11 nov-12 nov-13 nov-14 nov-15 Baseline Linha de Base Baseline BP 12-16 Linha Base - PNG 12-16 Realizado Accomplished Forecast Projetado Fonte :SAP/PNG 12-16: 30/06/12. Data de Medição pela Diretoria de Exploração & Produção: 13/09/12. Linha de Base: EVTE da Fase III, aprovado em 03/12/2009, Ata DE 4.787. / Projetado: Replanejamento realizado em Julho/12. 26
  • 27. FPSO P-63 – Papa-Terra (1st Oil: Jul/13) Local Content - Mandatory: 0% / Accomplished Forecast: 65% Hull: Conversion - Cosco (China) Modules: Construction COSCO Shipyard (China) 1. M01 Offices, Accommodations and Helideck 2. M21/M22 Manifolds 3. M81 Utilities System 4. M82 Heaters 5. M32/42 Load and Unload Area 6. M41 Laboratory and Workshop 7. M90 Electric Panels 8. M91/92/93 Electricity Generation Systems Modules: Construction QUIP Construction Site–Rio Grande Port Modules: Construction Tekfen (Turkey) (RS) 9. Z90 Piperack 10. EBSE – M11 High Separation System 11. EBSE – M12 Low Separation System 12. NATCO – M13 Oil Treatment 13. SULZER/TSL – M51 – Water Treatment and Injection Systems 14. VEOLIA – M52 – Sulphate Reduction Unit 15. QUIP – M-31 Flare Vases 16. QUIP – Flare Spare 17. SULZER/TSL – M83 Chemical Injection System 18. M60 Natural Gas Compression System Integration: Rio Grande Port (RS) Integration of Modules 1 to 18 to the hull Rio Grande Port - Rio Grande (RS) 27
  • 28. P-63 – Modules Construction at Rio Grande Port 6 5 1 4 2 3 7 View of the Honório Bicalho Shipyard (QUIP Construction site), in Rio Grande Port – RS (03/sep/12). P-63 Modules (Hull converted in China will arrive in Brazil in Dec/12): (1) M60 – Compression; (2) M52 – Sulphate removal; (3) M12 – Low pressure separator; (4) M11 – High pressure separator; (5) M13 – Electrostatic treatment; (6) M51- Water injection and treatment; (7) F30 - P-63 Flare. (LC: Full package contracted with 65% LC). 28
  • 29. FPSO P-61 – Papa-Terra (1st Oil: Dec/13) Local Content - Mandatory: 0% / Accomplished: 65% Hull Construction: BrasFels Shipyard – Angra dos Reis (RJ) Modules Construction: SIEMENS – Indonesia 1. Electric Modules Modules Construction: KeppelFELS - Singapore 2. Topside Integration Integration: BrasFels Shipyard – Angra dos Reis (RJ) BrasFels Shipyard - Angra (RJ) Topside / Hull Integration 29