Enhancing project team roles and responsibilities
                        in project cost management
               by Pascal Martin-Daguet, Civil Engineer INSA Rennes (France)
                Freyssinet International and Company (www.freyssinet.com)
                                   pmdaguet@gmail.com
                                 Singapore, 27th May 2009



Introduction
In most construction projects “cost control”, if any, consists of asking an accounting
department to code each invoice using pre-defined cost codes, and to dedicate a quantity
surveyor to sum-up, on a regular basis, the amounts accrued on each of these codes. With
this biased information the project management team (Project Manager and Construction
Manager) are consequently restricted in their ability to attain efficient cost management.


In short this paradigm is “cost following” rather than “cost controlling”


“Project cost management” or “Cost-driven project management” has two main goals:


   1. To secure the projected profitability, success and sustainability of the Project by
        reducing the risks
   2. To find areas of cost optimization in order to further improve profitability


In order to achieve the aforementioned the whole Projects organisation must be
structured, selected, organised but also effectively managed and lead to achieve these
aims.




                             Operations         Financial


                                       Project
                                     Management

                             Customer            Learning
                                                 & growth




                                                                                      1 of 16
Planning the strategy


In order to manage the cost, the organisation has first to set out its strategy. This can be
first formulated in a vision and mission statement. The next step is to develop a
sustainable plan which is communicated and socialised throughout the whole organisation.


Risk management must be one of the fundamentals of this strategy. Risk management is a
systematic approach to minimizing the organisation exposure to risk. A risk management
system includes various policies, plans, procedures and practices that work in unison to
identify, analyse, control, monitor, measure and record risks.


The project management team need will need to prepare the following documents:
   •   Risk Register/Risk Assessment
   •   Safety & Security Policies & Plans & Procedures
   •   Quality Assurance, Quality Control, policy, Plan & Procedures
   •   Administrative policy , plans and procedures
   •   Human Resources , policy , plans and procedures
   •   Crisis/Emergency Management Response Plan and Procedures


Very often, the project management team is rushing to start the project and neglects these
strong pillars of a cost-driven organisation, or delegate them to lower rank staff, often a
trainee. This is a severe mistake as these documents are the architecture of the
organisation. Without them, members of the organisation will not efficiently execute the
strategic plan.


Throughout the life cycle of the project, regular reviews of the strategy must be
undertaken. This will facilitate the continual improvements of the organization as it moves
thought the various phases of the project: For example


   •   Management review : every 6 months
   •   Quality review : every 6 months
   •   Risk register review : every 2 months




                                                                                     2 of 16
The execution of the strategy must also be made measurable as it provides the
organisation with measurements of actual performance against its perceived performance.
These measurements can take various forms and should be kept simple and in graphical
format to be more easily understood.


                    Safety              Number of accidents (AFR)
                                        Severity of accident (ASR)
                    Quality             Non Conformance Reports (NCR)
                    Engineering         Number of documents to be issued,
                                        issued, approved
                    Works               Percentage work done, scheduled; and
                                        any other linear indicator (number of
                                        beams, m3 of concrete...)
                    Financial           Amounts invoiced, paid; cost
                    Cost control        Budget, cost accrued, cost to spend,
                                        works value, cost at completion, daily
                                        running cost
                    HR                  Absenteism



Project team organisation


An organisation that manages cost is an organisation that manages risks. Traditionally,
safety and quality are the two major risks in the construction industry. The corresponding
two departments should therefore have an important position in the organisation chart,
they should be a service to the other departments, and they should be directly connected
to the Project Manager as they are some of his main control levers (other control levers
being: planning, budget/cost control, HR).




                                                                                   3 of 16
Project Manager




                             Safety                             Quality




                                      Contract/QS
         Production   Engineering                    Accounts   Procurement       HR
                                      Cost control


                               Cost-driven project organisation




Traditionally, projects are late from the very first day, and recruitment is done in a rush.
Staffs normally are hired with little know of their qualifications, competency and suitability
to the project (job description, work environment, capability to cope with stress, ethics...).
While most of people adapt well to their new environment, there is usually a small number
of people wrongly selected that don't fit the organisation. In best cases, these people don't
produce the expected results; in worse cases they produce counter-productive results and
damage the entire organisation, limiting the execution of the plan and adding avoidable
costs.


It is therefore important that the whole the organisation be clear on the projects goals,
mission and values. This can be achieved through strategic HR policy where the right
person is selected for the right job, in alignment with the project's goals.


To achieve this important target, the following should be put in place:
   •     Assign/recruit a trained HR manager
   •     Forecast HR requirements for the whole project
   •     Prepare an organisation chart at an early stage of the project, and keep it regularly
         updated
   •     Define the required job positions, do a job analysis in order to clearly define what
         the employee is expected to do.

                                                                                       4 of 16
•   Contact recruitment agencies, advertise in newspapers (although 75% of
       recruitment is usually done through “people who know people who know people”)
   •   Use Human Resource information management systems              to assist in making
       people the most powerful organisation assets [ HRIMS]
   •   Ensure time is built into the plan for regular group or one-on-one worker
       management consultation sessions.
   •   Use performance appraisals and link rewards (bonuses, salary increments) to
       Projects goals.


Job interviews should be conducted not only to verify the competencies of the candidate,
but also to determine whether the candidate will fit the organisation (be in alignment with
the project's goals and values). The interviewer should use pre-defined questionnaires to
assess   the   candidate's   values:   ambition,   assertiveness,   competence,   courtesy,
cheerfulness, dependability, forgiveness, helpfulness, honesty, imagination, independence,
rationality, openness, self-control. Finally, the interviewer could use online tests
(personality, team playing) to ensure that the future staff will be comfortable in the
organisation and produce positive results.




Cost control organisation


Cost control is a tool that must be used by senior management to monitor the profitability
of the project, to report to a corporate level, to make strategic decisions, to get the
production teams to be responsible of their works.


The most important point of an efficient cost controlling system is to have a senior
manager with a good technical knowledge of the project (“what” has to be built) to define
the cost codes. It would be typically the project manager, the construction manager or a
senior engineer. In no cases should the definition of cost codes be left to an accounting
department as they would not have the required big picture.


Cost codes should be defined so that they provide monitoring of the critical parts of the
project, representing amounts of money that are relatively high or in the same range. It
makes no sense, for example, to create a specific code to monitor purchase of stamps that
would represent 0.002% of the cost of the project.

                                                                                    5 of 16
Cost codes should be of two types, organised in a matrix system, in order to represent the
two different aspects of cost: its destination (which part of the site) and its nature (what
kind of material, equipment or service):


Cost centres : typically one per team so that each foreman is responsible of his own
budget. It is recommended to use letters for cost centres. There should always be a cost
centre for “general items” where all the administrative and running costs (general staff,
office...) can be allocated.
For example, for a bridge construction:


                                  Centre     Activity
                                    A        General items
                                    B        Foundation
                                    C        Columns
                                    D        Piers
                                    E        Beams prefabrication
                                    F        Deck
                                    G        Finishes



Analytical codes (also called, global ledger code, accounting code...) : a series of codes
representing the nature of the cost, defined in main categories and sub-categories. It is
recommended to use 4-digits code, the first two digits for the main category, the following
two for the sub-category. There should no more than 50 to 100 analytical codes.
An example of chart of accounts (sub-categories have been shown here only for the first
category for easy reading):


                          Code          Nature
                          0100          Labour (main category)
                           0101         Direct labour
                           0102         Sub-contracted labour
                           0110         Labour medical expenses
                           0111         Labour transportation
                           0112         Labour other expenses
                          0200          Materials and products
                          0300          Plant and equipment
                          0400          Consumables

                                                                                     6 of 16
0500       Design, Testing, sub
                        0600       Staff
                        0700       Running cost
                        0800       Administrative and financial charges
                        0900       Fixed assets


On smaller projects, cost centres can be omitted as long as analytical codes don't actually
comprise of a mix of cost centres and analytical codes (for example: labour for
foundations, labour for columns...) as this would create confusion in the coding process.


Once the chart of accounts has been created, the first budget can be prepared; each item
of the budget should then be coded according to the charts of accounts, and the cost
displayed in the form of a matrix so that each team (corresponding to each cost centre) is
aware of its available budget in each category:


                A           B          C          D           E           F          G
   0100         -           $          $           $          $           $          $
   0101         -           $          $           $          $           $          $
   0102         -           $          $           $          $           $          $
   0110         -           $          -           $          -           -          -
   0111         -           $          $           $          $           $          $
   0112         -           -          $           -          $           $          -
   0200         -           $          $           -          $           -          -
   0300         -           $          $           $          $           $          $
   0400         -           $          $           $          $           $          -
   0500         -           $          $           $          $           $          $
   0600         $           $          $           $          $           $          $
   0700         $           -          -           -          -           -          -
   0800         $           -          -           -          -           -          -
   0900         -           $          $           -          $           $          -



During the course of the project, each site team will specify ts cost centre on the
requisition for purchase of material, equipment..., and the accounting department will code
each invoice according to the analytical nature of the cost. Purchase orders, delivery notes
and invoices should be input in a computer system, and the cost reconciled in a matrix


                                                                                     7 of 16
form, similar to the budget one, for easy comparison.


On a regular basis (monthly), the cost controller should compare the “cost to date” + “cost
accrued” (spent but not yet paid) to the “works value” (cost that should have been spent
considering the present progress of the works). The budget should be updated at least
every 6 months.


The typical organisation chart for this kind of system should be as follows.


                                  Steering Committee



                                   Project Manager




               Construction Manager                      Commercial Manager



                         Foreman 1                                   Purchaser


                         Foreman 2                                Cost controller


                         Foreman 3                                  Accountant


                                                                   Store keeper




Planning
The Five P rule : “Proper Planning Prevents Poor Performance”


The main program of works should be prepared at the beginning of the project in the form
of a Gantt chart showing the main activities and sub-activities, using a specialised
software. Dates in a Gantt chart should never be fixed except for the first task as futures
modifications of the program would be rendered very difficult. Tasks should be linked to
each other, and the calendar should include rest days, bank holidays and a few days

                                                                                    8 of 16
immobilized for bad weather. The actual progress of works should be checked against the
main program of works on a monthly basis, and the main program of works should be
revised every 6 months.


A “weekly 5 weeks rolling program” should be prepared at the end of each week to show
the activities programmed for the 4 weeks to come, and the actual works done against the
programmed tasks of the past week.


A program of procurement of the main items to be ordered should also be prepared in
accordance with the main program of works and reviewed on a regular basis. This is
particularly important for items that have to be procured from overseas to allow fabrication
time, shipping and custom clearance. Indeed, many project suffer delays because of bad
procurement planning.




                             if you fail to plan, you plan to fail


Finally, a program of staff and labour (in the form of a bar chart) will allow the HR
department to anticipate the recruitment needs.




                                                                                     9 of 16
Leadership


The best way to manage the cost of a project is to make sure that the whole team is
aligned on a same vision, a same goal, so that all the energies are focussed in the same
direction (towards a successful completion of the project) rather than to fight against each
other. It is widely recognized that a team behaves similarly to its leader. Besides finding
the right people for the right job, it is therefore paramount to the team to lead by example
in an environment where each person feels empowered, respected, listened to,
responsible. In such circumstances, no energy is lost in conflicts, everybody works
efficiently which, eventually, helps managing cost (conflicts creating intangible cost).


Creating such an environment is entirely up to the project manager, and it takes years of
practice and a good dose of psychology to achieve it. There are countless books and
training methods available (see in the references section), and here are some of the
qualities that a good leader should develop:




                                                                                       10 of 16
Think big picture                              Set realistic targets
Be completely committed                        Hold effective meetings
Work harder than everybody                     Make meetings fun
Be prepared to sacrifice                       Encourage people
Be mentally tough                              Give credit
Lead with integrity                            Celebrate
Build team spirit                              Fight for your team
Build confidence                               Inspire loyalty
Respect legitimate authority                    Respect individual differences
Be proactive, not reactive                     Listen to ideas from others
Keep it simple                                 Don't always have the last word
Chase perfection                               Be ready to say yes
Learn from mistakes                            Set standards/expectations
Have a plan B, and a plan C                    Be creative
Be flexible and ready to move on               Keep learning
Don't bad-mouth your boss                      Don't bad-mouth your team
Don't play politics                            Don't intimidate
Don't cut corners                              Be in command and take charge



Relationships with Client and subcontractors


Remember why you are working of this project: because of the Client, your customer.
Although the Client has the same goal as the contractor (finishing the project on time, with
the required level of quality, with high safety standards and within its budget) he has
different problems to solve: funding the project, dealing with Authorities or stakeholders,
dealing with the Public...


Although most contracts contain all the necessary weapons to go to war with the Client (or
vice-versa) this should be envisaged as a last recourse only. All win-loose situations
actually lead to loose-loose situations!


Maintaining good relationships with the Client from the very first day of the project and
more particularly in difficult moments, will be beneficial to both the Client and the
Contractor; in other words to the Project. This requires to work in partnering with the Client
to solve problems as they come, to propose solutions adapted to the problems, to discuss


                                                                                      11 of 16
openly and on a regular basis contractual and commercial issues. In all circumstances,
leaving problems aside until the end of the project, hoping that they will be solved then, is
an open door to endless conflicts and financial losses.


In some cases, Contractors realising that their price offer was too low will start a
contractual battle with the client and produce unreasonable variation orders. They should
rather consider the option of “managing the cost of the project” through the implementation
of an appropriate organisation and opting for cost optimization. Blaming the Client for
everything is, in the end, counter-productive as a lot of energy (and therefore cost) is lost
in the process. It also damaged the image of the company for future projects.
Compromising and opting for a win-win settlement of problems will, once again, avoid
intangible costs.


The same principles apply to sub-contractors that main contractors often tend to
pressurize to “squeeze” cost. Ensure the sub-contractors are selected not only on their
cost both also their ability to align themselves with projects goals. There should be time
allocated to sufficiently orient them to the expectation levels. Early identification of sub-
contractors' weakness through audits and through a formal appraisal system, will guide
these sub-contractors to improve themselves. Not blaming “bad” subcontractors, but
instead helping them to develop, will help create strong and durable relationships between
parties, reducing delays and ultimately cost. Changing sub-contractors “as they are not
good” would again produce intangible costs and is often a result of poor planning and
selection policies.




Training


Most project-based organisations don't see the value of training their project staff. After all,
they will be with the company for only a few months or a few years; so why spending
money for their development?


The first reason for adopting a learning and development policy is to be able to fill the gaps
in people's competencies and make them more efficient in their present position. They
work better, produce better results for the benefit of the project which has the long-term
effect of optimizing the cost of the project.

                                                                                        12 of 16
The second reason is that, thanks to continuous training, people can be internally
promoted to higher levels of responsibilities, which is of great advantage to the company
as there is no need to spend time and money recruiting external staff that could possibly
be unsuitable for the job.


Finally, being exposed to external experiences different from the daily routine job, helps
the team to bond together and to work better together, especially when they are under
pressure.


In conclusion, adopting a learning and development program helps to stabilize the staff,
reduces turnover , improves work efficiency and avoids intangible costs.




Communication


Communication is the giving, receiving, processing and interpretation of information.
Information can be conveyed verbally, non-verbally, actively, passively, formally, informally,
consciously or unconsciously. Effective communication is fundamental to project
management as it helps to gain common understanding (what are the objectives and how
to attain them). Unclear communication can quickly lead to misunderstanding among the
projects team, which can invariably degenerate into friction and conflicts as everybody
may think they have understood the expectations levels when in fact they may have not.


The organisation may also be a multi ethnic team where multiple languages and different
cultural norms exist. If each member is not recognized and understood by the
management, there can be misunderstanding, frustration, conflict and reduction in
efficiency. Ideally all managers should be trained in cultural awareness and effective
communications before they start to work on a project.


In other words, “seek first to understand then to be understood “(Covey, 1989). Effective
communication helps maintaining energy levels and enthusiasm, builds teamwork and
ensures that the organisation is focused towards a common goal which, in turn, reduces
the intangible costs incurred.



                                                                                      13 of 16
My suggestion is to have, at least, one weekly meeting with the management personnel
(15 to 20 participants maximum). This meeting should be held within the office building,
preferably towards the end of the week (my personal experience is that Friday morning
9am is a good time). The meeting should be held in the form of a forum where each
participant is invited to expose the challenges or problems that he faces so that the other
members of the team can actively participate and suggest solutions. The chairman of the
meeting (the Project Manager) should limit the meeting to 1h-1.5h, make it a dynamic and
fun moment and prepare short minutes of meeting in the form of an action list (who does
what by when). A weekly coordination meeting should not be a lengthy, sterile moment
where each participant waits his turn to give a report of what he has done during the week.


I also suggest to have a 2-3 hours meeting with the senior staff only (5 to 10 people) every
6 months, outside of the office (preferably in a hotel or in a restaurant so that it can be
followed by a dinner and a fellowship session) for the Project Manager to remind the
objectives of the project, share the strategy and important information.


Finally, Key Performance Indicators (KPI), newsletters, website, multilingual posters
should be used when appropriate to communicate with the whole team.


Cost optimisation


Once the above-described organisation has been put in place and is working efficiently, a
cost-optimisation exercise can be envisaged. It is pointless, and sometimes counter-
productive, to start a cost-optimisation exercise when the cost-management structure is
not fully-functioning and stable. There are several ways to optimise cost:


   1. Planning optimisation: consist of looking for ways to reduce the project time by
      overlapping tasks, modifying resources on specific tasks, reducing float using the
      Critical Path Method.
   2. Value engineering: is the action of being creative to modify parts of the structure to
      be build, to change methods of construction or materials in order to reduce cost.
      Value engineering usually requires the prior approval of the Client.
   3. Budget optimization: consist of reducing “cost to spend” of specific areas in the
      budget that had been over-estimated. The cost centre / nature of cost matrix
      defined earlier is particularly useful here.

                                                                                    14 of 16
4. Six Sigma: is a performance based methodology that uses metrics and statistical
       analysis to detect inefficient parts of a working process, to reduce defects, to
       improve performance and productivity, and to ultimately reduce cost. The Six Sigma
       methodology is widely used in the manufacturing industry to drastically improve
       profitability, but is under-used in the construction industry although it is easy to set-
       up and can generate substantial savings (10% and above) as it tackles intangible
       costs : the Cost Of Poor Quality (COPQ). Six Sigma uses the DMAIC concept:
       Define, Measure, Analyse, Improve, Control to produce durable cost savings.




Conclusion


Cost-Managing projects is far more than cost-controlling projects. It relates to cost-driving
projects to tackle the intangible costs by putting in place a strong organisation united
toward a same goal: completing the project safely, on time, with the required quality, in
budget and to the satisfaction of the Client. Cost-managing projects not only helps to
stabilise costs (avoiding cost overrun) but also gives opportunity to improve profitability by
improving productivity and efficiency, therefore further reducing cost. Finally, it enhances
the image of the company, builds sustainability and improves marketability.




                                                                                        15 of 16
References


Association for Project Management (APM), http://apm.org.uk , viewed 12th May 2009


APM Body of Knowledge 5th Edition, 2006, Association for Project Management, UK ,


Covey , S , 1989 , The 7 Habits of Highly Effective People , Simon and Schuster , NY


Free online personality test, http://www.goddessflight.com/per/passess.htm, viewed 12th
May 2009


Free online team player test, http://www.testcafe.com/team/team.html, viewed 12th May
2009


Lombardi , V , 2003, The Lombardi Rules, Mc Graw-Hill, USA


Project management tools : http://www.method123.com/, viewed 12th May 2009


Stone, R, J , 2008 ,Human Resource Management 6th Edition, John Wiley and Sons
Australia Ltd.


Templar, R, 2005, The rules of Management, Pearson Books, Pearson Books , UK


Understanding Six Sigma, Neville Clarke Malaysia Sdn Bhd, www.nevilleclarke.com




                                                                                  16 of 16

More Related Content

What's hot

Introduction of project management
Introduction of project managementIntroduction of project management
Introduction of project managementMeenakshi Gautam
 
Workshop project risk management (29 june 2012)
Workshop   project risk management (29 june 2012)Workshop   project risk management (29 june 2012)
Workshop project risk management (29 june 2012)bfriday
 
Project risk management (pmp)
Project risk management (pmp)Project risk management (pmp)
Project risk management (pmp)Hieu Dang
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk ManagementMauro Jasse
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk ManagementSAJJAD KHUDHUR ABBAS
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk ManagementBiju Nair
 
Inform the selection of 5 efficiency and 8 effectiveness measures. This frame...
Inform the selection of 5 efficiency and 8 effectiveness measures. This frame...Inform the selection of 5 efficiency and 8 effectiveness measures. This frame...
Inform the selection of 5 efficiency and 8 effectiveness measures. This frame...TURKI , PMP
 
Exploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project deliveryExploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project deliveryMECandPMV
 
Risk Management - Business Continuity Planning and Management
Risk Management  - Business Continuity Planning and ManagementRisk Management  - Business Continuity Planning and Management
Risk Management - Business Continuity Planning and ManagementCody Shive
 

What's hot (20)

Project risk management
Project risk managementProject risk management
Project risk management
 
Introduction of project management
Introduction of project managementIntroduction of project management
Introduction of project management
 
043 Integrating Risk Management
043 Integrating Risk Management043 Integrating Risk Management
043 Integrating Risk Management
 
Workshop project risk management (29 june 2012)
Workshop   project risk management (29 june 2012)Workshop   project risk management (29 june 2012)
Workshop project risk management (29 june 2012)
 
Project risk management (pmp)
Project risk management (pmp)Project risk management (pmp)
Project risk management (pmp)
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk Management
 
Strategic Performance Plan
Strategic Performance PlanStrategic Performance Plan
Strategic Performance Plan
 
Planning
PlanningPlanning
Planning
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Project risk management
Project risk managementProject risk management
Project risk management
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Winning Project Work
Winning Project WorkWinning Project Work
Winning Project Work
 
PROJECT MANAGEMENT
PROJECT MANAGEMENT PROJECT MANAGEMENT
PROJECT MANAGEMENT
 
Project Management
Project ManagementProject Management
Project Management
 
Inform the selection of 5 efficiency and 8 effectiveness measures. This frame...
Inform the selection of 5 efficiency and 8 effectiveness measures. This frame...Inform the selection of 5 efficiency and 8 effectiveness measures. This frame...
Inform the selection of 5 efficiency and 8 effectiveness measures. This frame...
 
Exploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project deliveryExploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project delivery
 
Handling risk
Handling riskHandling risk
Handling risk
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Risk Management - Business Continuity Planning and Management
Risk Management  - Business Continuity Planning and ManagementRisk Management  - Business Continuity Planning and Management
Risk Management - Business Continuity Planning and Management
 

Similar to Project Cost Management Paper 27 May09

Project Management Overview
Project Management OverviewProject Management Overview
Project Management OverviewRockon0017i5
 
Cost management
Cost managementCost management
Cost managementshkadry
 
1 ch 1 Project CM.pptx ggggggggggggggggg
1 ch 1 Project CM.pptx ggggggggggggggggg1 ch 1 Project CM.pptx ggggggggggggggggg
1 ch 1 Project CM.pptx gggggggggggggggggadabotor7
 
1. Project Risk Management (25 Points)You have been tasked to.docx
1.  Project Risk Management (25 Points)You have been tasked to.docx1.  Project Risk Management (25 Points)You have been tasked to.docx
1. Project Risk Management (25 Points)You have been tasked to.docxdorishigh
 
IntroductionThe standards of venture risk administration can be .docx
IntroductionThe standards of venture risk administration can be .docxIntroductionThe standards of venture risk administration can be .docx
IntroductionThe standards of venture risk administration can be .docxmariuse18nolet
 
W4N1 Cost Management OverviewCost management is a critical comp.docx
W4N1 Cost Management OverviewCost management is a critical comp.docxW4N1 Cost Management OverviewCost management is a critical comp.docx
W4N1 Cost Management OverviewCost management is a critical comp.docxcelenarouzie
 
significance_of_test_estimating_in_the_software_development.pptx
significance_of_test_estimating_in_the_software_development.pptxsignificance_of_test_estimating_in_the_software_development.pptx
significance_of_test_estimating_in_the_software_development.pptxsarah david
 
Brochure PlanningPackage.com
Brochure PlanningPackage.comBrochure PlanningPackage.com
Brochure PlanningPackage.commkhilauria
 
Enterprise 360 degree risk management
Enterprise 360 degree risk managementEnterprise 360 degree risk management
Enterprise 360 degree risk managementInfosys
 
AI in Project Management.pdf
AI in Project Management.pdfAI in Project Management.pdf
AI in Project Management.pdfJamieDornan2
 
significance_of_test_estimating_in_the_software_development.pdf
significance_of_test_estimating_in_the_software_development.pdfsignificance_of_test_estimating_in_the_software_development.pdf
significance_of_test_estimating_in_the_software_development.pdfsarah david
 
Running Head PROJECT PLAN OUTLINE1Project Plan Outline2.docx
Running Head PROJECT PLAN OUTLINE1Project Plan Outline2.docxRunning Head PROJECT PLAN OUTLINE1Project Plan Outline2.docx
Running Head PROJECT PLAN OUTLINE1Project Plan Outline2.docxcharisellington63520
 
R I S K M A N A G E M E N T
R I S K  M A N A G E M E N TR I S K  M A N A G E M E N T
R I S K M A N A G E M E N Tmadhav shirur
 
significance_of_test_estimating_in_the_software_development.pptx
significance_of_test_estimating_in_the_software_development.pptxsignificance_of_test_estimating_in_the_software_development.pptx
significance_of_test_estimating_in_the_software_development.pptxsarah david
 

Similar to Project Cost Management Paper 27 May09 (20)

Project Mangement
Project MangementProject Mangement
Project Mangement
 
Project Management Overview
Project Management OverviewProject Management Overview
Project Management Overview
 
Cost management
Cost managementCost management
Cost management
 
Project Risk management
Project Risk managementProject Risk management
Project Risk management
 
Project mgt
Project mgtProject mgt
Project mgt
 
1 ch 1 Project CM.pptx ggggggggggggggggg
1 ch 1 Project CM.pptx ggggggggggggggggg1 ch 1 Project CM.pptx ggggggggggggggggg
1 ch 1 Project CM.pptx ggggggggggggggggg
 
PMP_Project Cost Management
PMP_Project Cost ManagementPMP_Project Cost Management
PMP_Project Cost Management
 
1. Project Risk Management (25 Points)You have been tasked to.docx
1.  Project Risk Management (25 Points)You have been tasked to.docx1.  Project Risk Management (25 Points)You have been tasked to.docx
1. Project Risk Management (25 Points)You have been tasked to.docx
 
IntroductionThe standards of venture risk administration can be .docx
IntroductionThe standards of venture risk administration can be .docxIntroductionThe standards of venture risk administration can be .docx
IntroductionThe standards of venture risk administration can be .docx
 
W4N1 Cost Management OverviewCost management is a critical comp.docx
W4N1 Cost Management OverviewCost management is a critical comp.docxW4N1 Cost Management OverviewCost management is a critical comp.docx
W4N1 Cost Management OverviewCost management is a critical comp.docx
 
significance_of_test_estimating_in_the_software_development.pptx
significance_of_test_estimating_in_the_software_development.pptxsignificance_of_test_estimating_in_the_software_development.pptx
significance_of_test_estimating_in_the_software_development.pptx
 
Project mngmnt risks3.2
Project mngmnt risks3.2Project mngmnt risks3.2
Project mngmnt risks3.2
 
Brochure PlanningPackage.com
Brochure PlanningPackage.comBrochure PlanningPackage.com
Brochure PlanningPackage.com
 
Enterprise 360 degree risk management
Enterprise 360 degree risk managementEnterprise 360 degree risk management
Enterprise 360 degree risk management
 
AI in Project Management.pdf
AI in Project Management.pdfAI in Project Management.pdf
AI in Project Management.pdf
 
significance_of_test_estimating_in_the_software_development.pdf
significance_of_test_estimating_in_the_software_development.pdfsignificance_of_test_estimating_in_the_software_development.pdf
significance_of_test_estimating_in_the_software_development.pdf
 
Running Head PROJECT PLAN OUTLINE1Project Plan Outline2.docx
Running Head PROJECT PLAN OUTLINE1Project Plan Outline2.docxRunning Head PROJECT PLAN OUTLINE1Project Plan Outline2.docx
Running Head PROJECT PLAN OUTLINE1Project Plan Outline2.docx
 
R I S K M A N A G E M E N T
R I S K  M A N A G E M E N TR I S K  M A N A G E M E N T
R I S K M A N A G E M E N T
 
significance_of_test_estimating_in_the_software_development.pptx
significance_of_test_estimating_in_the_software_development.pptxsignificance_of_test_estimating_in_the_software_development.pptx
significance_of_test_estimating_in_the_software_development.pptx
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 

Recently uploaded

Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...lizamodels9
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Sheetaleventcompany
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwaitdaisycvs
 
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLkapoorjyoti4444
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizharallensay1
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...rajveerescorts2022
 
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableCall Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableSeo
 
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876dlhescort
 
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...Anamikakaur10
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfAdmir Softic
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...amitlee9823
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...Aggregage
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with CultureSeta Wicaksana
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangaloreamitlee9823
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort ServiceMalegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort ServiceDamini Dixit
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...Sheetaleventcompany
 
Whitefield CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
Whitefield CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLWhitefield CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
Whitefield CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLkapoorjyoti4444
 

Recently uploaded (20)

Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
 
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
 
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableCall Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
 
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
 
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort ServiceMalegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
 
Whitefield CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
Whitefield CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLWhitefield CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
Whitefield CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
 

Project Cost Management Paper 27 May09

  • 1. Enhancing project team roles and responsibilities in project cost management by Pascal Martin-Daguet, Civil Engineer INSA Rennes (France) Freyssinet International and Company (www.freyssinet.com) pmdaguet@gmail.com Singapore, 27th May 2009 Introduction In most construction projects “cost control”, if any, consists of asking an accounting department to code each invoice using pre-defined cost codes, and to dedicate a quantity surveyor to sum-up, on a regular basis, the amounts accrued on each of these codes. With this biased information the project management team (Project Manager and Construction Manager) are consequently restricted in their ability to attain efficient cost management. In short this paradigm is “cost following” rather than “cost controlling” “Project cost management” or “Cost-driven project management” has two main goals: 1. To secure the projected profitability, success and sustainability of the Project by reducing the risks 2. To find areas of cost optimization in order to further improve profitability In order to achieve the aforementioned the whole Projects organisation must be structured, selected, organised but also effectively managed and lead to achieve these aims. Operations Financial Project Management Customer Learning & growth 1 of 16
  • 2. Planning the strategy In order to manage the cost, the organisation has first to set out its strategy. This can be first formulated in a vision and mission statement. The next step is to develop a sustainable plan which is communicated and socialised throughout the whole organisation. Risk management must be one of the fundamentals of this strategy. Risk management is a systematic approach to minimizing the organisation exposure to risk. A risk management system includes various policies, plans, procedures and practices that work in unison to identify, analyse, control, monitor, measure and record risks. The project management team need will need to prepare the following documents: • Risk Register/Risk Assessment • Safety & Security Policies & Plans & Procedures • Quality Assurance, Quality Control, policy, Plan & Procedures • Administrative policy , plans and procedures • Human Resources , policy , plans and procedures • Crisis/Emergency Management Response Plan and Procedures Very often, the project management team is rushing to start the project and neglects these strong pillars of a cost-driven organisation, or delegate them to lower rank staff, often a trainee. This is a severe mistake as these documents are the architecture of the organisation. Without them, members of the organisation will not efficiently execute the strategic plan. Throughout the life cycle of the project, regular reviews of the strategy must be undertaken. This will facilitate the continual improvements of the organization as it moves thought the various phases of the project: For example • Management review : every 6 months • Quality review : every 6 months • Risk register review : every 2 months 2 of 16
  • 3. The execution of the strategy must also be made measurable as it provides the organisation with measurements of actual performance against its perceived performance. These measurements can take various forms and should be kept simple and in graphical format to be more easily understood. Safety Number of accidents (AFR) Severity of accident (ASR) Quality Non Conformance Reports (NCR) Engineering Number of documents to be issued, issued, approved Works Percentage work done, scheduled; and any other linear indicator (number of beams, m3 of concrete...) Financial Amounts invoiced, paid; cost Cost control Budget, cost accrued, cost to spend, works value, cost at completion, daily running cost HR Absenteism Project team organisation An organisation that manages cost is an organisation that manages risks. Traditionally, safety and quality are the two major risks in the construction industry. The corresponding two departments should therefore have an important position in the organisation chart, they should be a service to the other departments, and they should be directly connected to the Project Manager as they are some of his main control levers (other control levers being: planning, budget/cost control, HR). 3 of 16
  • 4. Project Manager Safety Quality Contract/QS Production Engineering Accounts Procurement HR Cost control Cost-driven project organisation Traditionally, projects are late from the very first day, and recruitment is done in a rush. Staffs normally are hired with little know of their qualifications, competency and suitability to the project (job description, work environment, capability to cope with stress, ethics...). While most of people adapt well to their new environment, there is usually a small number of people wrongly selected that don't fit the organisation. In best cases, these people don't produce the expected results; in worse cases they produce counter-productive results and damage the entire organisation, limiting the execution of the plan and adding avoidable costs. It is therefore important that the whole the organisation be clear on the projects goals, mission and values. This can be achieved through strategic HR policy where the right person is selected for the right job, in alignment with the project's goals. To achieve this important target, the following should be put in place: • Assign/recruit a trained HR manager • Forecast HR requirements for the whole project • Prepare an organisation chart at an early stage of the project, and keep it regularly updated • Define the required job positions, do a job analysis in order to clearly define what the employee is expected to do. 4 of 16
  • 5. Contact recruitment agencies, advertise in newspapers (although 75% of recruitment is usually done through “people who know people who know people”) • Use Human Resource information management systems to assist in making people the most powerful organisation assets [ HRIMS] • Ensure time is built into the plan for regular group or one-on-one worker management consultation sessions. • Use performance appraisals and link rewards (bonuses, salary increments) to Projects goals. Job interviews should be conducted not only to verify the competencies of the candidate, but also to determine whether the candidate will fit the organisation (be in alignment with the project's goals and values). The interviewer should use pre-defined questionnaires to assess the candidate's values: ambition, assertiveness, competence, courtesy, cheerfulness, dependability, forgiveness, helpfulness, honesty, imagination, independence, rationality, openness, self-control. Finally, the interviewer could use online tests (personality, team playing) to ensure that the future staff will be comfortable in the organisation and produce positive results. Cost control organisation Cost control is a tool that must be used by senior management to monitor the profitability of the project, to report to a corporate level, to make strategic decisions, to get the production teams to be responsible of their works. The most important point of an efficient cost controlling system is to have a senior manager with a good technical knowledge of the project (“what” has to be built) to define the cost codes. It would be typically the project manager, the construction manager or a senior engineer. In no cases should the definition of cost codes be left to an accounting department as they would not have the required big picture. Cost codes should be defined so that they provide monitoring of the critical parts of the project, representing amounts of money that are relatively high or in the same range. It makes no sense, for example, to create a specific code to monitor purchase of stamps that would represent 0.002% of the cost of the project. 5 of 16
  • 6. Cost codes should be of two types, organised in a matrix system, in order to represent the two different aspects of cost: its destination (which part of the site) and its nature (what kind of material, equipment or service): Cost centres : typically one per team so that each foreman is responsible of his own budget. It is recommended to use letters for cost centres. There should always be a cost centre for “general items” where all the administrative and running costs (general staff, office...) can be allocated. For example, for a bridge construction: Centre Activity A General items B Foundation C Columns D Piers E Beams prefabrication F Deck G Finishes Analytical codes (also called, global ledger code, accounting code...) : a series of codes representing the nature of the cost, defined in main categories and sub-categories. It is recommended to use 4-digits code, the first two digits for the main category, the following two for the sub-category. There should no more than 50 to 100 analytical codes. An example of chart of accounts (sub-categories have been shown here only for the first category for easy reading): Code Nature 0100 Labour (main category) 0101 Direct labour 0102 Sub-contracted labour 0110 Labour medical expenses 0111 Labour transportation 0112 Labour other expenses 0200 Materials and products 0300 Plant and equipment 0400 Consumables 6 of 16
  • 7. 0500 Design, Testing, sub 0600 Staff 0700 Running cost 0800 Administrative and financial charges 0900 Fixed assets On smaller projects, cost centres can be omitted as long as analytical codes don't actually comprise of a mix of cost centres and analytical codes (for example: labour for foundations, labour for columns...) as this would create confusion in the coding process. Once the chart of accounts has been created, the first budget can be prepared; each item of the budget should then be coded according to the charts of accounts, and the cost displayed in the form of a matrix so that each team (corresponding to each cost centre) is aware of its available budget in each category: A B C D E F G 0100 - $ $ $ $ $ $ 0101 - $ $ $ $ $ $ 0102 - $ $ $ $ $ $ 0110 - $ - $ - - - 0111 - $ $ $ $ $ $ 0112 - - $ - $ $ - 0200 - $ $ - $ - - 0300 - $ $ $ $ $ $ 0400 - $ $ $ $ $ - 0500 - $ $ $ $ $ $ 0600 $ $ $ $ $ $ $ 0700 $ - - - - - - 0800 $ - - - - - - 0900 - $ $ - $ $ - During the course of the project, each site team will specify ts cost centre on the requisition for purchase of material, equipment..., and the accounting department will code each invoice according to the analytical nature of the cost. Purchase orders, delivery notes and invoices should be input in a computer system, and the cost reconciled in a matrix 7 of 16
  • 8. form, similar to the budget one, for easy comparison. On a regular basis (monthly), the cost controller should compare the “cost to date” + “cost accrued” (spent but not yet paid) to the “works value” (cost that should have been spent considering the present progress of the works). The budget should be updated at least every 6 months. The typical organisation chart for this kind of system should be as follows. Steering Committee Project Manager Construction Manager Commercial Manager Foreman 1 Purchaser Foreman 2 Cost controller Foreman 3 Accountant Store keeper Planning The Five P rule : “Proper Planning Prevents Poor Performance” The main program of works should be prepared at the beginning of the project in the form of a Gantt chart showing the main activities and sub-activities, using a specialised software. Dates in a Gantt chart should never be fixed except for the first task as futures modifications of the program would be rendered very difficult. Tasks should be linked to each other, and the calendar should include rest days, bank holidays and a few days 8 of 16
  • 9. immobilized for bad weather. The actual progress of works should be checked against the main program of works on a monthly basis, and the main program of works should be revised every 6 months. A “weekly 5 weeks rolling program” should be prepared at the end of each week to show the activities programmed for the 4 weeks to come, and the actual works done against the programmed tasks of the past week. A program of procurement of the main items to be ordered should also be prepared in accordance with the main program of works and reviewed on a regular basis. This is particularly important for items that have to be procured from overseas to allow fabrication time, shipping and custom clearance. Indeed, many project suffer delays because of bad procurement planning. if you fail to plan, you plan to fail Finally, a program of staff and labour (in the form of a bar chart) will allow the HR department to anticipate the recruitment needs. 9 of 16
  • 10. Leadership The best way to manage the cost of a project is to make sure that the whole team is aligned on a same vision, a same goal, so that all the energies are focussed in the same direction (towards a successful completion of the project) rather than to fight against each other. It is widely recognized that a team behaves similarly to its leader. Besides finding the right people for the right job, it is therefore paramount to the team to lead by example in an environment where each person feels empowered, respected, listened to, responsible. In such circumstances, no energy is lost in conflicts, everybody works efficiently which, eventually, helps managing cost (conflicts creating intangible cost). Creating such an environment is entirely up to the project manager, and it takes years of practice and a good dose of psychology to achieve it. There are countless books and training methods available (see in the references section), and here are some of the qualities that a good leader should develop: 10 of 16
  • 11. Think big picture Set realistic targets Be completely committed Hold effective meetings Work harder than everybody Make meetings fun Be prepared to sacrifice Encourage people Be mentally tough Give credit Lead with integrity Celebrate Build team spirit Fight for your team Build confidence Inspire loyalty Respect legitimate authority Respect individual differences Be proactive, not reactive Listen to ideas from others Keep it simple Don't always have the last word Chase perfection Be ready to say yes Learn from mistakes Set standards/expectations Have a plan B, and a plan C Be creative Be flexible and ready to move on Keep learning Don't bad-mouth your boss Don't bad-mouth your team Don't play politics Don't intimidate Don't cut corners Be in command and take charge Relationships with Client and subcontractors Remember why you are working of this project: because of the Client, your customer. Although the Client has the same goal as the contractor (finishing the project on time, with the required level of quality, with high safety standards and within its budget) he has different problems to solve: funding the project, dealing with Authorities or stakeholders, dealing with the Public... Although most contracts contain all the necessary weapons to go to war with the Client (or vice-versa) this should be envisaged as a last recourse only. All win-loose situations actually lead to loose-loose situations! Maintaining good relationships with the Client from the very first day of the project and more particularly in difficult moments, will be beneficial to both the Client and the Contractor; in other words to the Project. This requires to work in partnering with the Client to solve problems as they come, to propose solutions adapted to the problems, to discuss 11 of 16
  • 12. openly and on a regular basis contractual and commercial issues. In all circumstances, leaving problems aside until the end of the project, hoping that they will be solved then, is an open door to endless conflicts and financial losses. In some cases, Contractors realising that their price offer was too low will start a contractual battle with the client and produce unreasonable variation orders. They should rather consider the option of “managing the cost of the project” through the implementation of an appropriate organisation and opting for cost optimization. Blaming the Client for everything is, in the end, counter-productive as a lot of energy (and therefore cost) is lost in the process. It also damaged the image of the company for future projects. Compromising and opting for a win-win settlement of problems will, once again, avoid intangible costs. The same principles apply to sub-contractors that main contractors often tend to pressurize to “squeeze” cost. Ensure the sub-contractors are selected not only on their cost both also their ability to align themselves with projects goals. There should be time allocated to sufficiently orient them to the expectation levels. Early identification of sub- contractors' weakness through audits and through a formal appraisal system, will guide these sub-contractors to improve themselves. Not blaming “bad” subcontractors, but instead helping them to develop, will help create strong and durable relationships between parties, reducing delays and ultimately cost. Changing sub-contractors “as they are not good” would again produce intangible costs and is often a result of poor planning and selection policies. Training Most project-based organisations don't see the value of training their project staff. After all, they will be with the company for only a few months or a few years; so why spending money for their development? The first reason for adopting a learning and development policy is to be able to fill the gaps in people's competencies and make them more efficient in their present position. They work better, produce better results for the benefit of the project which has the long-term effect of optimizing the cost of the project. 12 of 16
  • 13. The second reason is that, thanks to continuous training, people can be internally promoted to higher levels of responsibilities, which is of great advantage to the company as there is no need to spend time and money recruiting external staff that could possibly be unsuitable for the job. Finally, being exposed to external experiences different from the daily routine job, helps the team to bond together and to work better together, especially when they are under pressure. In conclusion, adopting a learning and development program helps to stabilize the staff, reduces turnover , improves work efficiency and avoids intangible costs. Communication Communication is the giving, receiving, processing and interpretation of information. Information can be conveyed verbally, non-verbally, actively, passively, formally, informally, consciously or unconsciously. Effective communication is fundamental to project management as it helps to gain common understanding (what are the objectives and how to attain them). Unclear communication can quickly lead to misunderstanding among the projects team, which can invariably degenerate into friction and conflicts as everybody may think they have understood the expectations levels when in fact they may have not. The organisation may also be a multi ethnic team where multiple languages and different cultural norms exist. If each member is not recognized and understood by the management, there can be misunderstanding, frustration, conflict and reduction in efficiency. Ideally all managers should be trained in cultural awareness and effective communications before they start to work on a project. In other words, “seek first to understand then to be understood “(Covey, 1989). Effective communication helps maintaining energy levels and enthusiasm, builds teamwork and ensures that the organisation is focused towards a common goal which, in turn, reduces the intangible costs incurred. 13 of 16
  • 14. My suggestion is to have, at least, one weekly meeting with the management personnel (15 to 20 participants maximum). This meeting should be held within the office building, preferably towards the end of the week (my personal experience is that Friday morning 9am is a good time). The meeting should be held in the form of a forum where each participant is invited to expose the challenges or problems that he faces so that the other members of the team can actively participate and suggest solutions. The chairman of the meeting (the Project Manager) should limit the meeting to 1h-1.5h, make it a dynamic and fun moment and prepare short minutes of meeting in the form of an action list (who does what by when). A weekly coordination meeting should not be a lengthy, sterile moment where each participant waits his turn to give a report of what he has done during the week. I also suggest to have a 2-3 hours meeting with the senior staff only (5 to 10 people) every 6 months, outside of the office (preferably in a hotel or in a restaurant so that it can be followed by a dinner and a fellowship session) for the Project Manager to remind the objectives of the project, share the strategy and important information. Finally, Key Performance Indicators (KPI), newsletters, website, multilingual posters should be used when appropriate to communicate with the whole team. Cost optimisation Once the above-described organisation has been put in place and is working efficiently, a cost-optimisation exercise can be envisaged. It is pointless, and sometimes counter- productive, to start a cost-optimisation exercise when the cost-management structure is not fully-functioning and stable. There are several ways to optimise cost: 1. Planning optimisation: consist of looking for ways to reduce the project time by overlapping tasks, modifying resources on specific tasks, reducing float using the Critical Path Method. 2. Value engineering: is the action of being creative to modify parts of the structure to be build, to change methods of construction or materials in order to reduce cost. Value engineering usually requires the prior approval of the Client. 3. Budget optimization: consist of reducing “cost to spend” of specific areas in the budget that had been over-estimated. The cost centre / nature of cost matrix defined earlier is particularly useful here. 14 of 16
  • 15. 4. Six Sigma: is a performance based methodology that uses metrics and statistical analysis to detect inefficient parts of a working process, to reduce defects, to improve performance and productivity, and to ultimately reduce cost. The Six Sigma methodology is widely used in the manufacturing industry to drastically improve profitability, but is under-used in the construction industry although it is easy to set- up and can generate substantial savings (10% and above) as it tackles intangible costs : the Cost Of Poor Quality (COPQ). Six Sigma uses the DMAIC concept: Define, Measure, Analyse, Improve, Control to produce durable cost savings. Conclusion Cost-Managing projects is far more than cost-controlling projects. It relates to cost-driving projects to tackle the intangible costs by putting in place a strong organisation united toward a same goal: completing the project safely, on time, with the required quality, in budget and to the satisfaction of the Client. Cost-managing projects not only helps to stabilise costs (avoiding cost overrun) but also gives opportunity to improve profitability by improving productivity and efficiency, therefore further reducing cost. Finally, it enhances the image of the company, builds sustainability and improves marketability. 15 of 16
  • 16. References Association for Project Management (APM), http://apm.org.uk , viewed 12th May 2009 APM Body of Knowledge 5th Edition, 2006, Association for Project Management, UK , Covey , S , 1989 , The 7 Habits of Highly Effective People , Simon and Schuster , NY Free online personality test, http://www.goddessflight.com/per/passess.htm, viewed 12th May 2009 Free online team player test, http://www.testcafe.com/team/team.html, viewed 12th May 2009 Lombardi , V , 2003, The Lombardi Rules, Mc Graw-Hill, USA Project management tools : http://www.method123.com/, viewed 12th May 2009 Stone, R, J , 2008 ,Human Resource Management 6th Edition, John Wiley and Sons Australia Ltd. Templar, R, 2005, The rules of Management, Pearson Books, Pearson Books , UK Understanding Six Sigma, Neville Clarke Malaysia Sdn Bhd, www.nevilleclarke.com 16 of 16