VIETNAM – SOLAR POWER – AMAZING BREAKING NEWS – THE VERY FIRST SOLAR LAW - GOVERNMENT’S SUPPORTING REGIME FOR SOLAR POWER PROJECTS IN VIETNAM FINALLY OUT
VIETNAM – SOLAR POWER – AMAZING BREAKING NEWS – THE VERY FIRST SOLAR LAW - GOVERNMENT’S SUPPORTING REGIME FOR SOLAR POWER PROJECTS IN VIETNAM FINALLY OUT
Feed in-tariff regulations and getting wind power projects done (en)
Ähnlich wie VIETNAM – SOLAR POWER – AMAZING BREAKING NEWS – THE VERY FIRST SOLAR LAW - GOVERNMENT’S SUPPORTING REGIME FOR SOLAR POWER PROJECTS IN VIETNAM FINALLY OUT
VIETNAM – SOLAR POWER - MOIT PUBLISHES DRAFT CIRCULAR ON PROJECT DEVELOPMENT ...Dr. Oliver Massmann
Ähnlich wie VIETNAM – SOLAR POWER – AMAZING BREAKING NEWS – THE VERY FIRST SOLAR LAW - GOVERNMENT’S SUPPORTING REGIME FOR SOLAR POWER PROJECTS IN VIETNAM FINALLY OUT (20)
citizenship in the Philippines as to the laws applicable
VIETNAM – SOLAR POWER – AMAZING BREAKING NEWS – THE VERY FIRST SOLAR LAW - GOVERNMENT’S SUPPORTING REGIME FOR SOLAR POWER PROJECTS IN VIETNAM FINALLY OUT
1. VIETNAM – SOLAR POWER – AMAZING BREAKING NEWS – THE VERY FIRST
SOLAR LAW - GOVERNMENT’S SUPPORTING REGIME FOR SOLAR POWER
PROJECTS IN VIETNAM FINALLY OUT
On 11 April 2017, the Prime Minister officially approved the issuance of Decision No.
11/2017/QD-TTg on supporting regime for the development of solar power projects in Vietnam.
We note below some major points in this Decision:
Feed-in-tariff (FIT) rate
EVN is responsible for buying the whole electric output from on-grid solar power projects with
the electric buying price at the point of electricity receipt to be 2,086 Vietnamese dong/kWh
(equivalent to 9.35 UScents/kWh) (VAT excluded). This FIT only applies for on-grid projects
with capacity of solar cell being over 16% or of solar module being over 15%.
There is no FIT for rooftoop solar power projects if such projects are not grid-connected. This is
one of the differences compared with the previous Draft Solar Decision which sets a seperate
FIT for rooftop projects when they are connected to the grid.
The FIT is based on the VND/USD exchange rate issued by the State Bank of Vietnam on 10
April 2017 (USD 1 = VND22,316). This FIT will be adjusted according to the fluctuation of the
VND/USD exchange rate as specified in the standard Power Purchase Agreement (PPA) to be
issued by the Ministry of Industry and Trade. We note that the solar PPA will have a term of 20
years from the commercial operation date of the solar plant and can be extended/ renewed based
on regulations in effect at that time.
Investment incentives
Investment capital: Investors may mobilize capital from domestic or overseas organizations and
individuals to invest in solar power projects.
Import duty: Solar power projects are exempted from import duty on goods imported to create
fixed assets of the projects; components, materials and semi-finished products which are not
available at home for the project’s operation.
Corporate income tax: solar power projects will also enjoy the same corporate income tax
exemption and reduction as projects in sectors receiving investment incentives according to the
current regulations on taxation. For example, corporate income tax rate of 10% will be applied
for 15 years, tax exemptions within 4 years and tax reduction by 50% in the next 9 years.
Land: Solar power projects, lines and transformer stations connected to the national grid enjoy
the same exemptions and reductions in land use, land rental as projects being entitled for
preferential investment treatment. Such incentives, among other things, include exemption of
land rental within 3 years from the operation date of the project.
Projects included in the Power Master Plan
The Power Master Plan, whether it is national or provincial, only applies for on-grid solar
projects.
2. Projects of 50MW or below will be approved by the Ministry of Industry and Trade to be
included in the Power Master Plan, while those of more than 50MW will be approved by the
Prime Minister.
Thus, it could be understood that off-grid and rooftop projects do not have to be included in the
Power Master Plan. This will save the investors the hassle of negotiating the PPA with EVN.
The Decision has effect from 01 June 2017 to 30 June 2019.
***
Please do not hesitate to contact Oliver Massmann under omassmann@duanemorris.com if you
have any questions or want to know more details on the above. Oliver Massmann is the General
Director of Duane Morris Vietnam LLC.