Anzeige
Anzeige

Más contenido relacionado

Destacado(20)

Anzeige

Similar a Barry Cutting - Booster fans Angus Place Colliery(20)

Más de NSW Environment and Planning(20)

Anzeige

Último(20)

Barry Cutting - Booster fans Angus Place Colliery

  1. www.centennialcoal.com.au Booster Fans Angus Place Colliery BJ Cutting Manager of Electrical Engineering Angus Place
  2. Centennial Angus Place 2 Scone Rylstone Mudgee Muswellbrook Singleton Maitland Newcastle Lithgow Gosford SYDNEY Katoomba Berrima Wollongong Port Kembla Kiama Moss Vale Angus Place
  3. Introduction 3 • Mine established in 1978 • Mining the Lithgow seam • No history of methane or spontaneous combustion in Lithgow Seam • Currently developing the Angus Place East Area which is an expansion of Angus Place workings to 2031 • Planned production averages 3.5 Mtpa with longwall extraction • New Angus Place East ventilation facilities currently being constructed. • Shaft No.1 due for commissioning in January 2015 • Current ventilation into Angus Place East was not sufficient to support anticipated mining operations.
  4. Process 4 • It was identified that a Booster Fan would be required to provide adequate ventilation to the Angus Place East area until the completion of the new ventilation shaft no.1. • Angus Place investigated what fan options where available within the industry that would suit the Angus Place short term application. (6-9 months) • Identified 5 possible locations where the Booster Fans could be installed. • Ventsim software was used to model the 5 selected Booster Fan locations. • The decision was then made to install the Booster Fan in an intake airway not a return airway like other Booster Fan installations.
  5. Booster Fan Locations Investigated 5 1. At the intake panel entry of 910 (preferred option) 2. In the return outbye in 910 panel 3. At the 910 install road 4. Inbye 910N intake 5. Inbye 910N return 1 2 3 5 4
  6. Mine Plan 6 Current Angus Place Workings Future Angus Place East Workings New Upcast and Downcast Shafts Booster Fan Location
  7. Process • Angus Place conducted a risk assessment to identify the risks associated with a booster fan installation. • Key Outcomes from the Risk Assessment. – Legislative requirements.(Design and Item Registration) – Organise meetings with key stakeholders. • Department of Trade and Investment • Fan Manufacturers – Develop a functional specification for the operation of the Booster Fan. – Short timeframe for the Booster Fan Installation. – Additional work required outside the Booster Fan scope. (ventilation devices) • Visited other mining operations with in service booster fan installations to assist with the equipment selection process. 7
  8. Meeting with Department of Trade and Investment • To obtain an understanding of how the department viewed a Booster Fan Installation in an intake airway and to make the process as smooth as possible. – Could we treat it like a conveyor installation? Not a Booster Fan installation. – Was there a requirement to apply for Design and Item Registration? – Was it a High Risk Activity? – How would the department see the registration process moving forward. – Was there anything that they could see being a show stopper? 8
  9. Equipment Selection 9 • 3 x 110 kW Clemcorp axial fans in parallel • Ability to run either 2 or 3 fans in parallel due to fitment of self closing doors in each fan duct – Eliminates recirculation in the event of a single fan failure •Fans used extensively in underground metalliferous mines as booster fans. •Nickel Brass alloy impellers and mild steel ducting. •Modular design ensures quick and simple installation.
  10. Existing Fan Installation in a Metaliferous Mine 10
  11. Brass Nickel Impeller 11
  12. Positives - Preferred Option • Reduced risk compared to an installation in a return airway. •Legislation requirements. –Less departmental requirements ? (was the thought process) •Easier installation –Access restricted in the belt road. –Parallel Installation. –No loss of production. •Reduced pressure across the coffin seal. 12
  13. Negatives - Preferred Option • Restricted access around Booster Fans – Vehicle access through double ventilation doors. – Process to get larger pieces of equipment through double doors. – People and machine movement around and past Booster Fans. •Airborne dust – Along 910 travelling road. – Migrating into 1000 district production units. 13
  14. Functional Specification • If the main vent fan stops the booster fan is to stop immediately. • If any fan selected to run stops, all other booster fans stop. • If the booster fans stop the C910 conveyor is to be inhibited. • Environmental monitoring of CH4 and CO, if levels are detected above the pre-set values all booster fans stop. • Any failure of ventilation inbye or outbye of the booster fan installation, will cause all booster fans to stop. – Stopping Failure – Access or by-pass doors not in their correct position. • If ventilation pressures are outside of the intended tolerances all booster fan are to stop. • If the booster fans stop all power inbye of booster fans is turned off. 14
  15. Functional Safety Assessment 15
  16. Booster Fan Setup • Bypass Doors open if the Booster Fans are stopped – Proximity sensors to monitor position of bypass doors and machine access doors. • Vibration and Temperature monitoring on all fans • CO and CH4 monitoring inbye and outbye of fans • Differential pressure monitoring across – Fan Bulkhead – Coffin Seal – 19C/T 303 District • Fans set to trip on any one failure of system components • Monitoring alarms in control room 16
  17. Booster Fan Setup 17 BYPASS DOORS D D Belt Road Return Road PNEUMATIC ACCESS DOORS COFFIN SEAL
  18. Booster Fan Monitoring 18 PROXIMITY SENSORS D D Belt Road Return Road PRESSURE MONITORING CO & CH4 MONITORING
  19. Fans Installed at Angus Place 19
  20. Bulkhead Self Closing Fan Doors 20
  21. Bypass Doors & Pneumatic Machine Access Doors 21 PNEUMATIC MACHINES ACCESS DOORS VENTILATION BYPASS DOORS
  22. Potential Hazards Identified in Risk Assessment 22 • Booster Fan not turning off when Main Fan stops • Inability to conduct maintenance caused by insufficient access around Booster Fan • Fire on Booster Fan • Damage to Bypass Doors • Insufficient air reaching Booster Fan due to failure of Ventilation Control Device outbye of 910N • Complete failure of Booster Fan • Partial failure of Booster Fan • Increased dust caused by increased air velocity in 910N • Noise generated from booster fans
  23. Citect Display / Remote Monitoring 23
  24. Booster Fan Starter 24
  25. Booster Fan Starter 25
  26. Commissioning 26 Electrical Commissioning Sheet 0 Fans 1 Fan 2 Fans 3 Fans Settings (3 Fans Opperational) Reading Expected Actual Expected Actual Expected Actual Expected Actual Setting Type Setting Value Bypass Doors Open Open Closed Closed Closed Closed Closed Closed Access Door 1 (outbye) Closed Closed Closed Closed Closed Closed 1 of 3 Closed Closed Access Door 2 (middle) Open Open Open Open Open Open Open Access Door 3 (inbye) Closed Closed Closed Closed Closed Closed Closed Coffin Seal Pressure 1148 1270 780 784 350 490 Trip/Alarm Low Alarm/Trip High 300/400 900/1000 19 c/t, 303 Stopping Pressure 1727 1750 1500 1409 1255 1240 Trip/Alarm Low Alarm/Trip High 400/500 1600/1700 Booster Fan Pressure 0 0 890 1240 2010 2020 Trip/Alarm Low Alarm/Trip High 900/1000 2400/2500 Gas Sensor- CO inbye 0 0.2 0 0.2 0 0.2 Alarm Trip 15 ppm 25ppm Gas Sensor- CO outbye 0 0.2 0 0.2 0 0.2 Alarm Trip 15 ppm 25ppm Gas Sensor- CH4 inbye 0 0 0 0 0 0 Alarm Trip 0.25% 0.50% Gas Sensor- CH4 outbye 0 0 0 0 0 0 Alarm Trip 0.25% 0.50% Bypass Timer (minutes for pressurisation) 5 mins 5 mins 5 mins 5 mins Timer Values (T1/T2) 6 mins 6 mins Fan 1 Axial Vibration Sensor 1.01 mm/s Alarm Trip 6 mm/s 8 mm/s Radial Vibration Sensor 1.02 mm/s Alarm Trip 6 mm/s 8 mm/s DE Bearing Temperature Sensor 41 ᵒC Alarm Trip 60 ᵒC 80 ᵒC NDE Bearing Temperature Sensor 45 ᵒC Alarm Trip 60 ᵒC 80 ᵒC Winding Temperature Sensor 1 61 ᵒC Alarm Trip 85 ᵒC 120 ᵒC Winding Temperature Sensor 2 62 ᵒC Alarm Trip 85 ᵒC 120 ᵒC Winding Temperature Sensor 3 60 ᵒC Alarm Trip 85 ᵒC 120 ᵒC Fan 2 Axial Vibration Sensor 1.02 mm/s Alarm Trip 6 mm/s 8 mm/s Radial Vibration Sensor 0.90 mm/s Alarm Trip 6 mm/s 8 mm/s DE Bearing Temperature Sensor 44 ᵒC Alarm Trip 60 ᵒC 80 ᵒC NDE Bearing Temperature Sensor 44 ᵒC Alarm Trip 60 ᵒC 80 ᵒC Winding Temperature Sensor 1 59 ᵒC Alarm Trip 85 ᵒC 120 ᵒC Winding Temperature Sensor 2 60 ᵒC Alarm Trip 85 ᵒC 120 ᵒC Winding Temperature Sensor 3 60 ᵒC Alarm Trip 85 ᵒC 120 ᵒC Fan 3 Axial Vibration Sensor 1.03 mm/s Alarm Trip 6 mm/s 8 mm/s Radial Vibration Sensor 0.99 mm/s Alarm Trip 6 mm/s 8 mm/s DE Bearing Temperature Sensor 42 ᵒC Alarm Trip 60 ᵒC 80 ᵒC NDE Bearing Temperature Sensor 44 ᵒC Alarm Trip 60 ᵒC 80 ᵒC Winding Temperature Sensor 1 61 ᵒC Alarm Trip 85 ᵒC 120 ᵒC Winding Temperature Sensor 2 60 ᵒC Alarm Trip 85 ᵒC 120 ᵒC Winding Temperature Sensor 3 62 ᵒC Alarm Trip 85 ᵒC 120 ᵒC Noise Level (dBA) (Starter/Fan Guarding) 83/95 83/95
  27. Ventilation Survey 27 LocationVentsim QVensim PMeasured VMeasured QMeasured PVentsim QVensim PMeasured VMeasured QMeasured PVentsim QVensim PMeasured VMeasured QMeasured P910N 4 - 6 C/T14.9865113962.78771600912250910N 16 - 17C/T166169059750 @ 17 C/T729704.673.611108513624.8577.61260910N 35-36 C/T15.5498345100 @ 35 C/T581173.655.8125691653.960.45150910 0-1C/T 3 hdg15.3678118874895.990.6241026.295.232910N Regulator9.68278.7929.894.081041096910N Coffin Seal9114812707780770535049082918901290111201020201900 7 - 8 C/T15.517146071.3400 @ 8C/t663954.163.591350603203.8559.7135270LW Face343229303 19C/T172717501500140012551240Main Fan220223227303 regulator77960970740700No Fans Bypass Open2 Fans Running3 Fans RunningFan Bulkhead (D/D Closed) Fan Bulkhead (D/D Open)
  28. Item Registration 28
  29. Plant Registration - Exemption 29
  30. Start-up Sequence 30
  31. Acknowledgements • Shane McClure & Scott Wyborn - Centennial Coal. • Clemcorp Australia. •Simon Fulton & Grant Waring – ATF. •Mike Taylor – Advitech. •Marcus Punch. 31
  32. www.centennialcoal.com.au Thank You
Anzeige