Seminar Report
On
SUPERCRITICAL TECHNOLOGY IN
POWER PLANT
Submitted to
UNIVERSITY OF PUNE
Submitted By
Mr. GANESH VASANT NIRGUDE
DEPARTMENT OF MECHANICAL ENGINEERING
ShriChhatrapatiShivaji College Of Engineering
Shrishivajinagar (Rahuri Factory),
Tal: Rahuri, Dist: Ahmednagar.
Academic Year 2012-2013
II
ShriChhatrapatiShivaji College Of Engineering
Shrishivajinagar (Rahuri Factory),
(Recognized by Pune University)
Department of Mechanical Engineering,
CERTIFICATE
This is to certify that the seminar report entitled
SUPERCRITICAL TECHNOLOGY IN
POWER PLANT
Is submitted as partial fulfillment of curriculum of T.E. Mechanical
Engineering. Conferred by the University of Pune.
By Mr. GANESH VASANT NIRGUDE
Prof . Shelke S.V. Prof. Pandharkar U.J
(Seminar Guide) (Seminar Co-ordinator)
Prof.Dongare A.D.
(Head of department)
III
University of Pune
CERTIFICATE
This is to certify that
Mr. GANESH VASANT NIRGUDE
Student of T.E. Mechanical engineering was examined in the
seminar Presentation entitled
On 23 / 10/ 2012
“SUPERCRITICAL TECHNOLOGY IN
POWER PLANT”
At
Department of Mechanical Engineering,
Shri Chhatrapati Shivaji College Of Engineering.
Prof.Shelke S.V. Prof.Pandharkar. U.J
(SeminarGuide) (Seminar Co-ordinator)
IV
ACKNOWLEDGEMENT
Every orientation work has imprint of many people and this work is no
different. This work gives me an opportunity to express deep gratitude for
the same.
While preparing seminar report I received endless help from number of
people. This report would be incomplete if I don’t convey my sincere
thanks to all those who were involved.
First and foremost I would like to thank my respected guide Prof. .Seminar
coordinator Prof.Pandharkar U.J. and HOD Prof.Dongare A.D.
(Department of Mechanical Engineering) for giving me an opportunity to
present this seminar and there indispensable support, priceless suggestions
and valuable time.
Finally, I wish to thanks my friends and my family for being supportive of
me, without whom this seminar would not have seen the light of day.
Every work is an outcome of full-proof planning, continuous hard work
and organized effort. This work is a combination of all the three put
together sincerely.
Mr. Nirgude Ganesh Vasant
V
LIST OF CONTENENT
SR
NO
TOPIC PAGE
NO
ABSTRACT
1 INTRODUCTION
1-5
1.1Basic rankine cycle
1.2Energy Analysis of the Rankine Cycle
2 SUPERCRITICAL RANKINE CYCYLE
6-82.1Supercritical technology
2.2 Efficiency
2.3 Definition
3 DESIGN AND WORKING
9-10
3.1 Boiler Design
i. Boiler shell
3.2 Working
4 MATERIAL SELECTION
11-134.1 Metallurgical Problems
4.2 Materials used
5 SUPERCRITICAL BOILERS
14-155.1 A typical Supercritical Boilers
5.2 Super and Sub Critical Boilers (comparative study)
6 ADVANCE IN SC TECHNOLGY AND FUTURE IN INDIA
166.1 Natural Gas Production with a Supercritical Geothermal
Power
7 CONCLUSION
17
8 REFERENCES 18
VI
ABSTRACT
This paper reviews the major technical and performance aspects of a coal fired plan using
the supercritical technology. These include the turbine-generator set, the once-through
boiler, and operational issues such as load change, fuel flexibility, and water. Reviewing
the possibilities for the design and manufacture of components for supercritical-fired
plants in developing countries, the paper notes that the differences between sub critical
and supercritical power plants are limited to a relatively small number of components;
primarily the feedwater pumps and the high pressure feedwater train equipment. All of
the remaining components, common both types of plants, can be manufactured in
developing countries. The paper concludes with a review of the Schwarze Pumpe - the
world's largest supercritical lignite fired steam power plant.The primary purpose of the
study is to assess whether supercritical thermalplant technology is a proven and mature
commercial technology and whether .They operate at supercritical pressure. In contrast to
a "subcritical boiler", a supercritical steam generator operates at such a high pressure
(over 3,200 psi or 22 MPa) that actual boiling ceases to occur, the boiler has no liquid
water - steam separation. There is no generation of steam bubbles within the water,
because the pressure is above the critical pressure at which steam bubbles can form. It
passes below the critical point as it does work in a high pressure turbine and enters the
generator's condenser. This results in slightly less fuel use and therefore less greenhouse
gas production. The term "boiler" should not be used for a supercritical pressure steam
generator, as no "boiling" actually occurs in this device.
VII
1 INTRODUCTION
1.1 Basic Rankine Cycle:
The Rankine cycle is the oldest functional heat cycle utilized by man. The
Rankine cycle is the very a basic vapor power cycle which is adopted in all the
thermal power plants. It is a four step process (Figure 1.1) which involves the
heating of the working fluid to its saturation temperature and vaporizing it
isothermally, expanding the vapor on a turbine (work cycle), condensing the
steam isothermally to the liquid phase and pumping it back to the boiler.
Figure 1.1.1 Basic Rankine Cycle
Figure 2 represents the temperature-entropy diagram for the simplest version of
the Rankine cycle. Although this simple version is rarely used it gives a very clear
and simple picture on the working of the cycle.
Process 1-2 is the pumping of the working fliud (water) into the boiler
drum. The power required is derived from the overall power developed. Process
2-3 is the heating of the water upto its saturation temperature (100°C at 1 atm
pressure for water) is reached and then isothermal heating of the water where the
VIII
phase change from liquid to vapor occurs. Points 3 lie on the saturated vapor line.
The steam here is completely dry. Process 3-4 is the adiabatic expansion of the
vapor/steam on the turbine to obtain mechanical work. It is an isentropic process.
The temperature of the steam is reduced and it falls below the saturated vapor
line. The dryness fraction is reduced to less than one and a mixed liquid vapor
phase is present. Process 4-1 is the condensation process. This mixture is
condensed in a condenser isothermally and brought to the liquid phase back to the
pump.
FIGURE 1.1.2 Temperature vs. Entropy diagram for Rankine cycle
The steam is however, usually, superheated so as to obtain more work output.
Increasing the superheat to greater extent would lead to more work output.
However the energy spent in superheating the fuel is also high. The overall effect
is an increase in the thermal efficiency since the average temperature at which the
heat is added increases. Moisture content at the exit of the steam is decreased as
seen in the figure 1.3.
Superheating is usually limited to 620°C owing to metallurgical considerations.
IX
Figure1.1.3 Rankine cycle with superheating
1.2 Energy Analysis of the Rankine Cycle:
All four components in the Rankine Cycle (pump, boiler, turbine and
condenser) are steady flow devices and thus can be analyzed under steady flow
processes. K.E and P.E changes are small compared to work and heat transferred
and is thereby neglected.
Thus the steady flow equation (per unit mass) reduces to:
Q+hini = W+hfinal
Boiler and condenser do not involve any work and pump and turbine are assumed
to be isentropic. The conservation of Energy relation for each device is expressed
as follows:
 Steam turbine:
As the expansion is adiabatic (Q=0) and isentropic (S3=S4), then,
W3-4=Wturbine= (h3-h4) kJ/kg
X
 Condenser:
Heat rejected in the condenser, Q4-1+h4=h1+W4-1
Since W4-1=0, Q4-1=h1-h4
Thus,
Q4-1=-(h4-h1) kJ/kg
 Pump:
Work required to pump water:
Wpump=h1-h2 kJ/kg (-ve work)
 Boiler:
Heat added in boiler:
Q2-3=h3-h2 kJ/kg=h3-h1-Wpump kJ/kg
Thus, the Rankine Efficiency=Work done/Heat added
= (h3-h4-Wp) / (h3-h1-Wp)
Neglecting feed pump work as it is very small compared to other quantities, the
efficiency reduces to:
ηrankine= (h3-h4) / (h3-h1).
1.3 Factors increasing the Rankine Efficiency:
i. Lowering the condenser pressure:
Lowering the condenser pressure would lead to the lowering of
temperature os steam. Thus for the same turbine inlet state, more work is obtained
at lower temperatures.
XI
This method though cannot be extensively used as it reduces the dryness
fraction x of the steam. This is highly undesirable as it decreases the turbine
efficiency is reduced due to excessive erosion of the turbine blades.
ii. Superheating the steam to high temperature:
There is an increase in the work output if superheating of steam is done. It
increases the thermal efficiency as the average temperature at which heat is added
increases.
There is also another benfit of superheating; the steam at the exit of the
turbine is drier than in case of non superheated steam.
iii. Increasing the boiler pressure:
Increasing the boiler pressure raises the average temperature at which heat
is added and thereby increases the theramal efficiency. However the dryness
fraction decreases for the same exit temperature of the boiler. This problem can be
solved by employing reheating procedure. If however the boiler pressure is raised
to supercritical point greater efficiency is obtained as the latent heat absorbed
during phase change is reduced to zero.
XII
2 SUPERCRITICAL RANKINE CYCYLE
2.1 Supercritical technology:
When temperature and pressure of live steam are increased beyond the
critical point of water, the properties of steam will change dramatically. The
critical point of water is at 374 °C and 221.2 bar (218 atm), Figure 2.1, and it is
defined to be the point where gaseous component cannot be liquefied by
increasing the pressure applied to it. Beyond this critical point water does not
experience a phase change to vapor, but it becomes a supercritical fluid.
Supercritical fluid is not a gas or liquid. It is best described to be an intermediate
between these two phases. It has similar solvent power as liquid, but its transport
properties are similar to gases.
Figure 2.1.1 Phase diagram of water
2.2Efficiency:
The Rankine cycle can be greatly improved by operating in the
supercritical region of the coolant. Most modern fossil fuel plants employ the
XIII
supercritical Rankine Steam Cycle which pushes the thermal efficiency of the
plant (see equation 4) into the low to mid 40% range.
ηsupercritical = (h2-h1-h3+h4 )/( h2-h1) -(eqn 4)
2.2 Definition:
Figure 2.2.1 T-S diagram for supercritical Rankine cycle
For water, this cycle corresponds to pressures above 221.2 bar and
temperatures above 374.15°C (647.3 K). The T-S diagram for a supercritical cycle
can be seen in Figure 6. With the use of reheat and regeneration techniques, point
3 in Figure 2.1, which corresponds to the T-S vapor state of the coolant after it has
expanded through a turbine, can be pushed to the right such that the coolant
remains in the gas phase. This simplifies the system by eliminating the need for
steam separators, dryers, and turbines specially designed for low quality steam.
XIV
Material Concerns:
The primary concern with this cycle, at least for water, is the material
limits of the primary and support equipment. The materials in a boiler can be
exposed to temperatures above their limit, within reason, so long as the rate of
heat transfer to the coolant is sufficient to “cool” the material below its given
limit. The same holds true for the turbine materials. With the advent of modern
materials, i.e. super alloys and ceramics, not only are the physical limits of the
materials being pushed to extremes, but the systems are functioning much closer
to their limits. The current super alloys and coatings are allowing turbine inlet
temperatures of up to 700°C (973 K). the fourth generation super alloys with
ruthenium mono-crystal structures promise turbine inlet temperatures up to
1097°C (1370 K). Special alloys like Iconel 740, Haynes 230, CCA617, etc. are
used.
The metallurgical challenges faced and solutions:
 Normal Stainless steel proves of absolutely no use in building SC and USC
Boilers.
 The high temperature and pressure in the boiler induce huge amount of stresses
and fatigue in the materials. Also chances of oxidation are very high at such high
temperature and pressure.
 To resist these stress levels and oxidation different advanced materials and alloys
should be introduced.
 Also they should me machinable and weldable. This is a great metallurgical
challenge.
XV
3 DESIGN AND WORKING
3.1 Boiler Design:
The design of Super and Ultra supercritical boilers (also called as Benson
Boiler) is very critical as the working pressures of these boilers are very high. The
boiler shells, the economizer unit, super heaters, air preheaters are specially
designed. Their location is also of great significance.
i. Boiler shell:
As shown in the figure 3.1 the geometry of the boilers and the
configuration of the inlets determine the recirculation pattern inside boiler. The
intensive recirculation created in the symmetric boiler results in a more uniform
temperature field, lower temperature peaks, moderate oxygen concentration and
complete burnout of the combustible gases and char
Fig 3.1.1 Predicted Recirculation inside the combustion chamber
Table 3.1 lists the peak temperatures and burnout for designs A, B and C. the table also
lists the standard deviations of the predicted temperature and oxygen fields. The lowest
values for C indicate the higher degree of homogeneity. Thus the symmetrical boiler
seems to be the most suitable design.
XVI
ii. Location of burners:
The number of burners in the boiler shell is also of prime importance.
Amongst all of them the downfired boilers are most suitable and advantageous.
Table 3.2 gives a clear idea.
iii. Boiler dimensions:
One of the most important advantages of HTAC applications are high heat
fluxes. Thus, compact combustion chambers can be built and the investment costs
can be lowered. The fourth calculation series was carried out in order to find the
combustion chamber dimensions which can, on one hand, ensure an efficient heat
exchange between combustion gas and water/steam mixture and on the other
hand, ensure high values of firing density. Three different sizes are tested and
they are named in as the small boiler, the medium size boiler and the large boiler
.It has been observed (see Table 3.3) that the small boiler is too short. At the top a
region of high temperatures exists and its enthalpy cannot be efficiently used. On
the contrary, in the large boiler although the heat fluxes areuniform, they are two
times lower than in the medium size boiler. Therefore, the medium size boiler
configuration is chosen for further investigations.
Small boiler Medium size boiler Large boiler
Firing Density
kW/m3
774 238 89
Outlet temperature,
K
1805 1558 1299
Table3.1.1 Results of the boiler size determination
3.2 Working:
As already discussed, the working of Supercritical Boilers is similar to the
working of sub-critical boilers. It works on the supercritical rankine cycle. Most
supercritical boilers are being run at operating pressures above of 235 bars. The
working of ultra supercritical boilers has operating pressures above 273 bars
XVII
4 MATERIAL SELECTION
4.1 Metallurgical Problems:
The available materials today like stainless steel which are usually used
for boiler parts are not suitable for SC and USC boilers. They do not have the
enough creep strength to resist the high pressure. Also there is high rate of
oxidation at such high temperature and pressures which are beyond the capability
of these materials to resist. Capable, qualified materials must be available to the
industry to enable development of steam generators for SC steam conditions.
Major components, such as infurnace tubing for the waterwalls, superheater/
reheater sections, headers, external piping, and other accessories require
advancements in materials technology to allow outlet steam temperature increases
to reach 760°C (1400F). Experiences with projects such as the pioneering Philo
and Eddystone supercritical plants and the problems with the stainless steel steam
piping and superheater fireside corrosion provided a valuable precautionary
lesson for SC development. Industry organizations thus recognized that a
thorough program was required to develop new and improved materials and
protection methods necessary for these high temperature steam conditions.
4.2 Materials used:
The materials used should be sustainable to the very high pressure being
developed and should not get oxidized due to the very high temperature. Different
high temperature materials are being used like 9 to 12% ferritic steels T91/P91,
T92/P92, T112/P122 steel, Advanced Austenitic alloys TP347, HFG, Super 304,
Nickel and chrome-nickel super alloys like Inconel 740.
Table 4.2 gives a very brief idea about the boiler materials used for
different parts of the boiler.
XVIII
Heat surface Tube material Header material
Economiser SA-210 C SA-106 C
Furnace Walls SA-213 T12 SA-106 C
Super
heater/Reheater
SA-213 T12
SA-213 T23
SA-213 TP 304H
SA-213
TP347HFG
SUPER 304H
SA-335 P12
SA-335 P91
SA-335 P911
Steam Piping SA 335 P91
Table 4.2.1 Materials for different boiler parts
The materials for the other parts of the power plant (like turbine) also must be
sustainable for the super critically heated steam. The following table gives a detail idea
on the turbine materials of a plant operating on a supercritical cycle. (Table 4.3)
XIX
Table 4.2.2 Materials for other parts
The following figures show some of the materials used for SC and USC boilers. Iconel
740 is widely used for steam pipings in almost all of them.
Figure 4.1 TP347HFG Figure 4.2 Iconel 740
Component 1,050° F 1,150 °F 1,300° F 1,400 °F
Casings
(shells, valves,
steam chests,
nozzles)
CrMoV (cast)
10CrMoVMb
9–10% Cr (W)
12CrW (Co)
CrMoWVNbN
CF8C-
Plus
CCA617
Inconel
625
Nimonic
263
CCA617
Inconel
740
CF8C-
Plus
Bolting 422
9–12%
CrMoV
Nimonic 80A
9–12% CrMoV
CrMoWVNbN
Nimonic
105
Nimonic
115
Waspaloy
Nimonic
105
Nimonic
115
U700
Rotors/Discs 1CrMoV
12CrMoVNbN
9–12 % CrWCo
12CrMoWVNbN
CCA617
Inconel
625
CCA617
Inconel
740
Nozzles/Blades 422
10CrMoVNbN
9–12% CrWCo
10CrMoVCbN
Wrought
Ni-based
Wrought
Ni-
based
XX
5 SUPERCRITICAL BOILERS
5.1 A typical Supercritical Boilers:
Largest CFB and first supercritical CFB sold to date is the Lagisza 460 MWe
unit Ordered by Poludniowy Koncern Energetyczny SA (PKE) in Poland. The design is
Essentially complete with financial closing expected in the first quarter of 2006 at
which time Fabrication and construction will commence. The largest capacity units in
operation today are the two (2) 300 MWe JEA repowered units which were designed to
fire any Combination of petroleum coke and bituminous coals. The physically largest
Foster Wheeler boilers in operation are the 262 MWe Turow Units 4, 5, and 6 which
were designed to fire a high moisture brown coal. The design and configuration of
these units with Compact solids separators and INTREX™ heat exchangers were used
as the basis for the Lagisza design as well as for this study. The Lagisza design was
adjusted to accommodate a typical bituminous coal and the steam cycle.
Figure 5.1.1 The Lagisza 300 MWe plant in Pola
XXI
5.2 Super and Sub Critical Boilers (comparative study):
There are many advantages of super critical boilers over normal
subcritical boilers, the prime advantage being the increased efficiency and reduced
emissions. There are many more advantages like no need of steam dryers, higher
operating pressures leading to more work output etc.
It is thus very important to have a comparative study of both the
boilers.
Table 5.2.1 Comparison of sub and supercritical boilers
Technology Efficiency (%) Steam
pressure/temperature
Typical emissions
Ultra Supercritical
33–35
>242 bar and
593.33°C
SO2-0.408 kg/MHh
NOx-0.286
kg/MWh
CO2-0.96 T/MWh
Supercritical
36–40
>221.2 bar and
537°C
SO2-0.431 kg/MHh
NOx-0.304
kg/MWh
CO2-1.02 T/MWh
Subritical
42–45
165 bar 537°C SO2-0.445 kg/MHh
NOx-0.31 kg/MWh
CO2-1.02 T/MWh
XXII
6 ADVANCE IN SC TECHNOLGY AND FUTURE IN INDIA
6.2 Supercritical Boilers in India:
There haven’t been any supercritical boilers in use in India so far. The European
countries, USA, Japan have been using supercritical technology since the last two
decades. However, there are upcoming projects to build power plants working under
the supercritical technology in India.
The National Thermal Power Corporation (NTPC) had entrusted a techno
economic study to M/s EPDC for super-critical Vs Sub-critical Boilers for their
proposed Sipat STPS (4x500 MW) in Madhya Pradesh.
M/s EPDC has recommended that a first step to the introduction of super-
critical technology, the most proven steam conditions may be chosen and the most
applicable steam conditions in India shall be 246 kg/cm2
, 538° C/566° C. With these
steam parameters, M/s EPDC has estimated that the capital cost for a supercritical
power station (4x500 MW) shall be about 2% higher than that of sub-critical power
plant but at the same time the plant efficiency shall improve from 38.64% to 39.6%.
Being a pit head thermal power project, the saving in fuel charges is not justified by
increase in fixed charges.
Here are some upcoming projects in India:
 North Karanpura, Jharkhand – 3x660 MW
 Darlipali, Orissa – 4x800 MW
 Lara, Chattisgarh – 5x800 MW
 Marakanam, Tamilnadu – 4x800 MW
 Tanda-II, Uttar Pradesh - 2x660 MW
 Meja, Uttar Pradesh - 2x660 MW
 Sholapur – 2x660 MW
XXIII
 New Nabinagar-3x660 MW
 Many more projects including 800 MW ultra super critical units under
consideration
7 CONCLUSION
The supercritical Rankine cycle, in general, offers an additional 30% relative
improvement in the thermal efficiency as compared to the same system operating in the
subcritical region. The cycle has been successfully utilized in fossil fuel plants but the
current available materials prohibit reliable application of the supercritical cycle to
nuclear applications. There is much work to be done in order to advance materials to
the point where they will be able to reliably withstand the stresses of a supercritical
environment inside a nuclear reactor for a designed life span of 60 years.
Supercritical boiler technology has matured, through advancements in design
and materials. Coal-fired supercritical units supplied around the world over the past
several years have been operating with high efficiency performance and high
availability.
XXIV
REFERENCES
1. “Design Aspects of the Ultra-Supercritical CFB Boiler”; Stephen J.
Goidich, Song Wu, Zhen Fan; Foster Wheeler North America Corp.
2. “Novel conceptual design of a supercritical pulverized coal boiler utilizing
high temperature air combustion (HTAC) technology”; Natalia Schaffel-
Mancini, Marco Mancini, Andrzej Szlek, Roman Weber; Institute of
Energy Process Engineering and Fuel Technology, Clausthal University of
Technology, Agricolastr. 4, 38678 Clausthal-Zellerfeld, Germany; 6
February 2010.
3. “Supercritical (Once Through) Boiler Technology”; J.W. Smith, Babcock
& Wilcox, Barberton, Ohio, U.S.A.; May 1998.
4. “Steam Generator for Advanced Ultra-Supercritical Power Plants 700 to
760°C”; P.S. Weitzel; ASME 2011 Power Conference, Denver, Colorado,
U.S.A; July 12-14, 2011.
5. “Supercritical boiler technology for future market conditions”; Joachim
Franke and Rudolf Kral; Siemens Power Generation; Parsons Conference;
2003.
6. “Steam Turbine Design Considerations for Supercritical Cycles”; Justin
Zachary, Paul Kochis, Ram Narula; Coal Gen 2007 Conference;1-3
August 2007.
7. “Technology status of thermal power plants in India and opportunities in
renovation and modernization”; TERI, D S Block, India Habitat Centre,
Lodi Road, New Delhi – 110003.
8. “Applied Thermodynamics”; Dr. H.N Sawant; January 1992; revised July
2004.
9. “http://en.wikipedia.org/wiki/Boiler#Supercritical_steam_generator”
XXV

Weitere ähnliche Inhalte

Was ist angesagt?

Supercritical steam generators
Supercritical steam generatorsSupercritical steam generators
Supercritical steam generatorsAshutosh Katti
 
660 mw supercritical boiler
660 mw supercritical boiler660 mw supercritical boiler
660 mw supercritical boilerAshvani Shukla
 
Unit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownUnit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownNitin Mahalle
 
Supercritical boiler ntpc sipat
Supercritical boiler ntpc sipatSupercritical boiler ntpc sipat
Supercritical boiler ntpc sipatpratikguptateddy
 
Turbine cycle heat rate calculation
Turbine  cycle heat rate calculationTurbine  cycle heat rate calculation
Turbine cycle heat rate calculationSHIVAJI CHOUDHURY
 
SUPER-CRITICAL THERMAL POWER PLANT by Tatyaso Kadam
SUPER-CRITICAL THERMAL POWER PLANT by Tatyaso KadamSUPER-CRITICAL THERMAL POWER PLANT by Tatyaso Kadam
SUPER-CRITICAL THERMAL POWER PLANT by Tatyaso Kadamtatyasokadam88
 
Report on Boilers at NTPC Ramagunadam
Report on  Boilers at NTPC RamagunadamReport on  Boilers at NTPC Ramagunadam
Report on Boilers at NTPC RamagunadamAbhinay Angari
 
Boiler commissioning procedure
Boiler commissioning procedureBoiler commissioning procedure
Boiler commissioning procedureABVSAI
 
super critical power plant
super critical power plantsuper critical power plant
super critical power plantsridurga88
 
Hydrogen Purge and Fill
Hydrogen Purge and FillHydrogen Purge and Fill
Hydrogen Purge and FillShad Edwards
 
Air Heater and PF Boiler Performance Indices
Air Heater and PF Boiler Performance IndicesAir Heater and PF Boiler Performance Indices
Air Heater and PF Boiler Performance IndicesManohar Tatwawadi
 
Feedwater heaters in thermal power plants
Feedwater heaters in thermal power plantsFeedwater heaters in thermal power plants
Feedwater heaters in thermal power plantsSHIVAJI CHOUDHURY
 
Boiler Purging-Logic, Importance & Working
Boiler Purging-Logic, Importance & WorkingBoiler Purging-Logic, Importance & Working
Boiler Purging-Logic, Importance & WorkingTahoor Alam Khan
 
A technical overview of thermal power plant
A technical overview of thermal power plantA technical overview of thermal power plant
A technical overview of thermal power plantMirdul Amin Sarkar
 
Boilers and Its Auxiliaries & Plant Overview
Boilers and Its Auxiliaries & Plant OverviewBoilers and Its Auxiliaries & Plant Overview
Boilers and Its Auxiliaries & Plant Overviewseshu seelamsetti
 
Steam Condenser performance and loss diagnostic
Steam Condenser performance and loss diagnosticSteam Condenser performance and loss diagnostic
Steam Condenser performance and loss diagnosticPichai Chaibamrung
 
Coal based power plant
Coal based power plantCoal based power plant
Coal based power plantGaurav Kaushik
 

Was ist angesagt? (20)

Supercritical steam generators
Supercritical steam generatorsSupercritical steam generators
Supercritical steam generators
 
660 mw supercritical boiler
660 mw supercritical boiler660 mw supercritical boiler
660 mw supercritical boiler
 
Unit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownUnit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdown
 
Supercritical boiler ntpc sipat
Supercritical boiler ntpc sipatSupercritical boiler ntpc sipat
Supercritical boiler ntpc sipat
 
Boiler light up & loading
Boiler light up & loadingBoiler light up & loading
Boiler light up & loading
 
Turbine cycle heat rate calculation
Turbine  cycle heat rate calculationTurbine  cycle heat rate calculation
Turbine cycle heat rate calculation
 
SUPER-CRITICAL THERMAL POWER PLANT by Tatyaso Kadam
SUPER-CRITICAL THERMAL POWER PLANT by Tatyaso KadamSUPER-CRITICAL THERMAL POWER PLANT by Tatyaso Kadam
SUPER-CRITICAL THERMAL POWER PLANT by Tatyaso Kadam
 
Report on Boilers at NTPC Ramagunadam
Report on  Boilers at NTPC RamagunadamReport on  Boilers at NTPC Ramagunadam
Report on Boilers at NTPC Ramagunadam
 
Boiler commissioning procedure
Boiler commissioning procedureBoiler commissioning procedure
Boiler commissioning procedure
 
super critical power plant
super critical power plantsuper critical power plant
super critical power plant
 
Hydrogen Purge and Fill
Hydrogen Purge and FillHydrogen Purge and Fill
Hydrogen Purge and Fill
 
Kbr[1] report
Kbr[1] reportKbr[1] report
Kbr[1] report
 
Air Heater and PF Boiler Performance Indices
Air Heater and PF Boiler Performance IndicesAir Heater and PF Boiler Performance Indices
Air Heater and PF Boiler Performance Indices
 
Feedwater heaters in thermal power plants
Feedwater heaters in thermal power plantsFeedwater heaters in thermal power plants
Feedwater heaters in thermal power plants
 
Boiler Purging-Logic, Importance & Working
Boiler Purging-Logic, Importance & WorkingBoiler Purging-Logic, Importance & Working
Boiler Purging-Logic, Importance & Working
 
A technical overview of thermal power plant
A technical overview of thermal power plantA technical overview of thermal power plant
A technical overview of thermal power plant
 
Boilers and Its Auxiliaries & Plant Overview
Boilers and Its Auxiliaries & Plant OverviewBoilers and Its Auxiliaries & Plant Overview
Boilers and Its Auxiliaries & Plant Overview
 
Boiler -Emergency Handling
 Boiler -Emergency Handling Boiler -Emergency Handling
Boiler -Emergency Handling
 
Steam Condenser performance and loss diagnostic
Steam Condenser performance and loss diagnosticSteam Condenser performance and loss diagnostic
Steam Condenser performance and loss diagnostic
 
Coal based power plant
Coal based power plantCoal based power plant
Coal based power plant
 

Andere mochten auch

Job Experience Letter Format
Job Experience Letter FormatJob Experience Letter Format
Job Experience Letter FormatYour HR World
 
Experience Certificate
Experience CertificateExperience Certificate
Experience Certificatesajid hasan
 
Boiler Supporting structure-Steel detailing
Boiler Supporting structure-Steel detailingBoiler Supporting structure-Steel detailing
Boiler Supporting structure-Steel detailingGaurav Kumar
 
Final reprt at ntpc vindhyanagar , singrauli
Final  reprt at ntpc vindhyanagar , singrauliFinal  reprt at ntpc vindhyanagar , singrauli
Final reprt at ntpc vindhyanagar , singrauliDevanshu Yadav
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...haxxo24
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...haxxo24
 
Thermal Power Plants
Thermal Power PlantsThermal Power Plants
Thermal Power Plantspeeyush95
 
Project report format
Project report formatProject report format
Project report formatrohtb2010
 
BUILDING MATERIALS AS A STEEL
BUILDING MATERIALS AS  A STEELBUILDING MATERIALS AS  A STEEL
BUILDING MATERIALS AS A STEELAbhishek Mewada
 

Andere mochten auch (11)

Super critical boiler
Super critical boilerSuper critical boiler
Super critical boiler
 
Job Experience Letter Format
Job Experience Letter FormatJob Experience Letter Format
Job Experience Letter Format
 
Experience Certificate
Experience CertificateExperience Certificate
Experience Certificate
 
Boiler Supporting structure-Steel detailing
Boiler Supporting structure-Steel detailingBoiler Supporting structure-Steel detailing
Boiler Supporting structure-Steel detailing
 
Final reprt at ntpc vindhyanagar , singrauli
Final  reprt at ntpc vindhyanagar , singrauliFinal  reprt at ntpc vindhyanagar , singrauli
Final reprt at ntpc vindhyanagar , singrauli
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Thermal Power Plants
Thermal Power PlantsThermal Power Plants
Thermal Power Plants
 
Project report format
Project report formatProject report format
Project report format
 
BUILDING MATERIALS AS A STEEL
BUILDING MATERIALS AS  A STEELBUILDING MATERIALS AS  A STEEL
BUILDING MATERIALS AS A STEEL
 

Ähnlich wie Seminar report on supercritical thenology

NTPC Project KORBA(SUPER THEMAL POWER PLANT)
NTPC Project KORBA(SUPER THEMAL POWER PLANT)NTPC Project KORBA(SUPER THEMAL POWER PLANT)
NTPC Project KORBA(SUPER THEMAL POWER PLANT)Rajan Kumar Choudhary
 
Thermal Analysis of Steam Turbine Power Plants
Thermal Analysis of Steam Turbine Power PlantsThermal Analysis of Steam Turbine Power Plants
Thermal Analysis of Steam Turbine Power PlantsIOSR Journals
 
thermal project 1
thermal project 1thermal project 1
thermal project 1James Li
 
193411716 study-on-steam-turbines
193411716 study-on-steam-turbines193411716 study-on-steam-turbines
193411716 study-on-steam-turbineshomeworkping3
 
A STUDY ON ROLE OF CONDENSER AND NATURAL DRAFT COOLING TOWER ON THE PERFORMAN...
A STUDY ON ROLE OF CONDENSER AND NATURAL DRAFT COOLING TOWER ON THE PERFORMAN...A STUDY ON ROLE OF CONDENSER AND NATURAL DRAFT COOLING TOWER ON THE PERFORMAN...
A STUDY ON ROLE OF CONDENSER AND NATURAL DRAFT COOLING TOWER ON THE PERFORMAN...Saikat Halder
 
Vapor_power cycles KM.pptx ..
Vapor_power cycles KM.pptx            ..Vapor_power cycles KM.pptx            ..
Vapor_power cycles KM.pptx ..happycocoman
 
vapour-power-cycle h.pptx
vapour-power-cycle                          h.pptxvapour-power-cycle                          h.pptx
vapour-power-cycle h.pptxMahamad Jawhar
 
ME6301 ENGINEERING THERMODYNAMICS SHORT QUESTIONS AND ANSWERS - UNIT III
ME6301 ENGINEERING THERMODYNAMICS SHORT QUESTIONS AND ANSWERS - UNIT IIIME6301 ENGINEERING THERMODYNAMICS SHORT QUESTIONS AND ANSWERS - UNIT III
ME6301 ENGINEERING THERMODYNAMICS SHORT QUESTIONS AND ANSWERS - UNIT IIIBIBIN CHIDAMBARANATHAN
 
Improvement of rankine efficinecy of steam power plants
Improvement of rankine efficinecy of steam power plantsImprovement of rankine efficinecy of steam power plants
Improvement of rankine efficinecy of steam power plantsDhilip Pugalenthi
 
ThermoDynamics (Working of steam power plant and rankine cyle)
ThermoDynamics (Working of steam power plant and rankine cyle)ThermoDynamics (Working of steam power plant and rankine cyle)
ThermoDynamics (Working of steam power plant and rankine cyle)Graphic Era University.
 
Steam Power Cycle and Basics of Boiler
Steam Power Cycle and Basics of BoilerSteam Power Cycle and Basics of Boiler
Steam Power Cycle and Basics of BoilerMulugeta Wotango
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plantRabi Kumar
 
performance analysis of steam power plants using ideal reheat rankin cycle
performance analysis of steam power plants using ideal reheat rankin cycleperformance analysis of steam power plants using ideal reheat rankin cycle
performance analysis of steam power plants using ideal reheat rankin cycleIJAEMSJORNAL
 
steam power plant
steam power plantsteam power plant
steam power plantOmar Qasim
 

Ähnlich wie Seminar report on supercritical thenology (20)

Ganesh final report
Ganesh final reportGanesh final report
Ganesh final report
 
NTPC Project KORBA(SUPER THEMAL POWER PLANT)
NTPC Project KORBA(SUPER THEMAL POWER PLANT)NTPC Project KORBA(SUPER THEMAL POWER PLANT)
NTPC Project KORBA(SUPER THEMAL POWER PLANT)
 
The reheat cycle
The reheat cycleThe reheat cycle
The reheat cycle
 
Thermal Analysis of Steam Turbine Power Plants
Thermal Analysis of Steam Turbine Power PlantsThermal Analysis of Steam Turbine Power Plants
Thermal Analysis of Steam Turbine Power Plants
 
thermal project 1
thermal project 1thermal project 1
thermal project 1
 
Power cycles
Power cyclesPower cycles
Power cycles
 
193411716 study-on-steam-turbines
193411716 study-on-steam-turbines193411716 study-on-steam-turbines
193411716 study-on-steam-turbines
 
A STUDY ON ROLE OF CONDENSER AND NATURAL DRAFT COOLING TOWER ON THE PERFORMAN...
A STUDY ON ROLE OF CONDENSER AND NATURAL DRAFT COOLING TOWER ON THE PERFORMAN...A STUDY ON ROLE OF CONDENSER AND NATURAL DRAFT COOLING TOWER ON THE PERFORMAN...
A STUDY ON ROLE OF CONDENSER AND NATURAL DRAFT COOLING TOWER ON THE PERFORMAN...
 
Vapor_power cycles KM.pptx ..
Vapor_power cycles KM.pptx            ..Vapor_power cycles KM.pptx            ..
Vapor_power cycles KM.pptx ..
 
vapour-power-cycle h.pptx
vapour-power-cycle                          h.pptxvapour-power-cycle                          h.pptx
vapour-power-cycle h.pptx
 
Chapter 10 lecture
Chapter 10 lectureChapter 10 lecture
Chapter 10 lecture
 
Power plant cycle
Power plant cyclePower plant cycle
Power plant cycle
 
ME6301 ENGINEERING THERMODYNAMICS SHORT QUESTIONS AND ANSWERS - UNIT III
ME6301 ENGINEERING THERMODYNAMICS SHORT QUESTIONS AND ANSWERS - UNIT IIIME6301 ENGINEERING THERMODYNAMICS SHORT QUESTIONS AND ANSWERS - UNIT III
ME6301 ENGINEERING THERMODYNAMICS SHORT QUESTIONS AND ANSWERS - UNIT III
 
Improvement of rankine efficinecy of steam power plants
Improvement of rankine efficinecy of steam power plantsImprovement of rankine efficinecy of steam power plants
Improvement of rankine efficinecy of steam power plants
 
ThermoDynamics (Working of steam power plant and rankine cyle)
ThermoDynamics (Working of steam power plant and rankine cyle)ThermoDynamics (Working of steam power plant and rankine cyle)
ThermoDynamics (Working of steam power plant and rankine cyle)
 
Steam Power Cycle and Basics of Boiler
Steam Power Cycle and Basics of BoilerSteam Power Cycle and Basics of Boiler
Steam Power Cycle and Basics of Boiler
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Rnakine reheat regen
Rnakine reheat regenRnakine reheat regen
Rnakine reheat regen
 
performance analysis of steam power plants using ideal reheat rankin cycle
performance analysis of steam power plants using ideal reheat rankin cycleperformance analysis of steam power plants using ideal reheat rankin cycle
performance analysis of steam power plants using ideal reheat rankin cycle
 
steam power plant
steam power plantsteam power plant
steam power plant
 

Kürzlich hochgeladen

6 ways Samsung’s Interactive Display powered by Android changes the classroom
6 ways Samsung’s Interactive Display powered by Android changes the classroom6 ways Samsung’s Interactive Display powered by Android changes the classroom
6 ways Samsung’s Interactive Display powered by Android changes the classroomSamsung Business USA
 
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 - I-LEARN SMART WORLD - CẢ NĂM - CÓ FILE NGHE (BẢN...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 - I-LEARN SMART WORLD - CẢ NĂM - CÓ FILE NGHE (BẢN...BÀI TẬP BỔ TRỢ TIẾNG ANH 8 - I-LEARN SMART WORLD - CẢ NĂM - CÓ FILE NGHE (BẢN...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 - I-LEARN SMART WORLD - CẢ NĂM - CÓ FILE NGHE (BẢN...Nguyen Thanh Tu Collection
 
Congestive Cardiac Failure..presentation
Congestive Cardiac Failure..presentationCongestive Cardiac Failure..presentation
Congestive Cardiac Failure..presentationdeepaannamalai16
 
ClimART Action | eTwinning Project
ClimART Action    |    eTwinning ProjectClimART Action    |    eTwinning Project
ClimART Action | eTwinning Projectjordimapav
 
Satirical Depths - A Study of Gabriel Okara's Poem - 'You Laughed and Laughed...
Satirical Depths - A Study of Gabriel Okara's Poem - 'You Laughed and Laughed...Satirical Depths - A Study of Gabriel Okara's Poem - 'You Laughed and Laughed...
Satirical Depths - A Study of Gabriel Okara's Poem - 'You Laughed and Laughed...HetalPathak10
 
Unraveling Hypertext_ Analyzing Postmodern Elements in Literature.pptx
Unraveling Hypertext_ Analyzing  Postmodern Elements in  Literature.pptxUnraveling Hypertext_ Analyzing  Postmodern Elements in  Literature.pptx
Unraveling Hypertext_ Analyzing Postmodern Elements in Literature.pptxDhatriParmar
 
Shark introduction Morphology and its behaviour characteristics
Shark introduction Morphology and its behaviour characteristicsShark introduction Morphology and its behaviour characteristics
Shark introduction Morphology and its behaviour characteristicsArubSultan
 
MS4 level being good citizen -imperative- (1) (1).pdf
MS4 level   being good citizen -imperative- (1) (1).pdfMS4 level   being good citizen -imperative- (1) (1).pdf
MS4 level being good citizen -imperative- (1) (1).pdfMr Bounab Samir
 
An Overview of the Calendar App in Odoo 17 ERP
An Overview of the Calendar App in Odoo 17 ERPAn Overview of the Calendar App in Odoo 17 ERP
An Overview of the Calendar App in Odoo 17 ERPCeline George
 
BIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptx
BIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptxBIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptx
BIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptxSayali Powar
 
4.11.24 Poverty and Inequality in America.pptx
4.11.24 Poverty and Inequality in America.pptx4.11.24 Poverty and Inequality in America.pptx
4.11.24 Poverty and Inequality in America.pptxmary850239
 
BÀI TẬP BỔ TRỢ TIẾNG ANH 11 THEO ĐƠN VỊ BÀI HỌC - CẢ NĂM - CÓ FILE NGHE (GLOB...
BÀI TẬP BỔ TRỢ TIẾNG ANH 11 THEO ĐƠN VỊ BÀI HỌC - CẢ NĂM - CÓ FILE NGHE (GLOB...BÀI TẬP BỔ TRỢ TIẾNG ANH 11 THEO ĐƠN VỊ BÀI HỌC - CẢ NĂM - CÓ FILE NGHE (GLOB...
BÀI TẬP BỔ TRỢ TIẾNG ANH 11 THEO ĐƠN VỊ BÀI HỌC - CẢ NĂM - CÓ FILE NGHE (GLOB...Nguyen Thanh Tu Collection
 
Scientific Writing :Research Discourse
Scientific  Writing :Research  DiscourseScientific  Writing :Research  Discourse
Scientific Writing :Research DiscourseAnita GoswamiGiri
 
PART 1 - CHAPTER 1 - CELL THE FUNDAMENTAL UNIT OF LIFE
PART 1 - CHAPTER 1 - CELL THE FUNDAMENTAL UNIT OF LIFEPART 1 - CHAPTER 1 - CELL THE FUNDAMENTAL UNIT OF LIFE
PART 1 - CHAPTER 1 - CELL THE FUNDAMENTAL UNIT OF LIFEMISSRITIMABIOLOGYEXP
 
Q-Factor General Quiz-7th April 2024, Quiz Club NITW
Q-Factor General Quiz-7th April 2024, Quiz Club NITWQ-Factor General Quiz-7th April 2024, Quiz Club NITW
Q-Factor General Quiz-7th April 2024, Quiz Club NITWQuiz Club NITW
 
Objectives n learning outcoms - MD 20240404.pptx
Objectives n learning outcoms - MD 20240404.pptxObjectives n learning outcoms - MD 20240404.pptx
Objectives n learning outcoms - MD 20240404.pptxMadhavi Dharankar
 
Q-Factor HISPOL Quiz-6th April 2024, Quiz Club NITW
Q-Factor HISPOL Quiz-6th April 2024, Quiz Club NITWQ-Factor HISPOL Quiz-6th April 2024, Quiz Club NITW
Q-Factor HISPOL Quiz-6th April 2024, Quiz Club NITWQuiz Club NITW
 

Kürzlich hochgeladen (20)

6 ways Samsung’s Interactive Display powered by Android changes the classroom
6 ways Samsung’s Interactive Display powered by Android changes the classroom6 ways Samsung’s Interactive Display powered by Android changes the classroom
6 ways Samsung’s Interactive Display powered by Android changes the classroom
 
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 - I-LEARN SMART WORLD - CẢ NĂM - CÓ FILE NGHE (BẢN...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 - I-LEARN SMART WORLD - CẢ NĂM - CÓ FILE NGHE (BẢN...BÀI TẬP BỔ TRỢ TIẾNG ANH 8 - I-LEARN SMART WORLD - CẢ NĂM - CÓ FILE NGHE (BẢN...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 - I-LEARN SMART WORLD - CẢ NĂM - CÓ FILE NGHE (BẢN...
 
Congestive Cardiac Failure..presentation
Congestive Cardiac Failure..presentationCongestive Cardiac Failure..presentation
Congestive Cardiac Failure..presentation
 
Introduction to Research ,Need for research, Need for design of Experiments, ...
Introduction to Research ,Need for research, Need for design of Experiments, ...Introduction to Research ,Need for research, Need for design of Experiments, ...
Introduction to Research ,Need for research, Need for design of Experiments, ...
 
ClimART Action | eTwinning Project
ClimART Action    |    eTwinning ProjectClimART Action    |    eTwinning Project
ClimART Action | eTwinning Project
 
Satirical Depths - A Study of Gabriel Okara's Poem - 'You Laughed and Laughed...
Satirical Depths - A Study of Gabriel Okara's Poem - 'You Laughed and Laughed...Satirical Depths - A Study of Gabriel Okara's Poem - 'You Laughed and Laughed...
Satirical Depths - A Study of Gabriel Okara's Poem - 'You Laughed and Laughed...
 
Unraveling Hypertext_ Analyzing Postmodern Elements in Literature.pptx
Unraveling Hypertext_ Analyzing  Postmodern Elements in  Literature.pptxUnraveling Hypertext_ Analyzing  Postmodern Elements in  Literature.pptx
Unraveling Hypertext_ Analyzing Postmodern Elements in Literature.pptx
 
Shark introduction Morphology and its behaviour characteristics
Shark introduction Morphology and its behaviour characteristicsShark introduction Morphology and its behaviour characteristics
Shark introduction Morphology and its behaviour characteristics
 
MS4 level being good citizen -imperative- (1) (1).pdf
MS4 level   being good citizen -imperative- (1) (1).pdfMS4 level   being good citizen -imperative- (1) (1).pdf
MS4 level being good citizen -imperative- (1) (1).pdf
 
An Overview of the Calendar App in Odoo 17 ERP
An Overview of the Calendar App in Odoo 17 ERPAn Overview of the Calendar App in Odoo 17 ERP
An Overview of the Calendar App in Odoo 17 ERP
 
BIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptx
BIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptxBIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptx
BIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptx
 
4.11.24 Poverty and Inequality in America.pptx
4.11.24 Poverty and Inequality in America.pptx4.11.24 Poverty and Inequality in America.pptx
4.11.24 Poverty and Inequality in America.pptx
 
BÀI TẬP BỔ TRỢ TIẾNG ANH 11 THEO ĐƠN VỊ BÀI HỌC - CẢ NĂM - CÓ FILE NGHE (GLOB...
BÀI TẬP BỔ TRỢ TIẾNG ANH 11 THEO ĐƠN VỊ BÀI HỌC - CẢ NĂM - CÓ FILE NGHE (GLOB...BÀI TẬP BỔ TRỢ TIẾNG ANH 11 THEO ĐƠN VỊ BÀI HỌC - CẢ NĂM - CÓ FILE NGHE (GLOB...
BÀI TẬP BỔ TRỢ TIẾNG ANH 11 THEO ĐƠN VỊ BÀI HỌC - CẢ NĂM - CÓ FILE NGHE (GLOB...
 
Scientific Writing :Research Discourse
Scientific  Writing :Research  DiscourseScientific  Writing :Research  Discourse
Scientific Writing :Research Discourse
 
Plagiarism,forms,understand about plagiarism,avoid plagiarism,key significanc...
Plagiarism,forms,understand about plagiarism,avoid plagiarism,key significanc...Plagiarism,forms,understand about plagiarism,avoid plagiarism,key significanc...
Plagiarism,forms,understand about plagiarism,avoid plagiarism,key significanc...
 
PART 1 - CHAPTER 1 - CELL THE FUNDAMENTAL UNIT OF LIFE
PART 1 - CHAPTER 1 - CELL THE FUNDAMENTAL UNIT OF LIFEPART 1 - CHAPTER 1 - CELL THE FUNDAMENTAL UNIT OF LIFE
PART 1 - CHAPTER 1 - CELL THE FUNDAMENTAL UNIT OF LIFE
 
Q-Factor General Quiz-7th April 2024, Quiz Club NITW
Q-Factor General Quiz-7th April 2024, Quiz Club NITWQ-Factor General Quiz-7th April 2024, Quiz Club NITW
Q-Factor General Quiz-7th April 2024, Quiz Club NITW
 
Objectives n learning outcoms - MD 20240404.pptx
Objectives n learning outcoms - MD 20240404.pptxObjectives n learning outcoms - MD 20240404.pptx
Objectives n learning outcoms - MD 20240404.pptx
 
Paradigm shift in nursing research by RS MEHTA
Paradigm shift in nursing research by RS MEHTAParadigm shift in nursing research by RS MEHTA
Paradigm shift in nursing research by RS MEHTA
 
Q-Factor HISPOL Quiz-6th April 2024, Quiz Club NITW
Q-Factor HISPOL Quiz-6th April 2024, Quiz Club NITWQ-Factor HISPOL Quiz-6th April 2024, Quiz Club NITW
Q-Factor HISPOL Quiz-6th April 2024, Quiz Club NITW
 

Seminar report on supercritical thenology

  • 1. I Seminar Report On SUPERCRITICAL TECHNOLOGY IN POWER PLANT Submitted to UNIVERSITY OF PUNE Submitted By Mr. GANESH VASANT NIRGUDE DEPARTMENT OF MECHANICAL ENGINEERING ShriChhatrapatiShivaji College Of Engineering Shrishivajinagar (Rahuri Factory), Tal: Rahuri, Dist: Ahmednagar. Academic Year 2012-2013
  • 2. II ShriChhatrapatiShivaji College Of Engineering Shrishivajinagar (Rahuri Factory), (Recognized by Pune University) Department of Mechanical Engineering, CERTIFICATE This is to certify that the seminar report entitled SUPERCRITICAL TECHNOLOGY IN POWER PLANT Is submitted as partial fulfillment of curriculum of T.E. Mechanical Engineering. Conferred by the University of Pune. By Mr. GANESH VASANT NIRGUDE Prof . Shelke S.V. Prof. Pandharkar U.J (Seminar Guide) (Seminar Co-ordinator) Prof.Dongare A.D. (Head of department)
  • 3. III University of Pune CERTIFICATE This is to certify that Mr. GANESH VASANT NIRGUDE Student of T.E. Mechanical engineering was examined in the seminar Presentation entitled On 23 / 10/ 2012 “SUPERCRITICAL TECHNOLOGY IN POWER PLANT” At Department of Mechanical Engineering, Shri Chhatrapati Shivaji College Of Engineering. Prof.Shelke S.V. Prof.Pandharkar. U.J (SeminarGuide) (Seminar Co-ordinator)
  • 4. IV ACKNOWLEDGEMENT Every orientation work has imprint of many people and this work is no different. This work gives me an opportunity to express deep gratitude for the same. While preparing seminar report I received endless help from number of people. This report would be incomplete if I don’t convey my sincere thanks to all those who were involved. First and foremost I would like to thank my respected guide Prof. .Seminar coordinator Prof.Pandharkar U.J. and HOD Prof.Dongare A.D. (Department of Mechanical Engineering) for giving me an opportunity to present this seminar and there indispensable support, priceless suggestions and valuable time. Finally, I wish to thanks my friends and my family for being supportive of me, without whom this seminar would not have seen the light of day. Every work is an outcome of full-proof planning, continuous hard work and organized effort. This work is a combination of all the three put together sincerely. Mr. Nirgude Ganesh Vasant
  • 5. V LIST OF CONTENENT SR NO TOPIC PAGE NO ABSTRACT 1 INTRODUCTION 1-5 1.1Basic rankine cycle 1.2Energy Analysis of the Rankine Cycle 2 SUPERCRITICAL RANKINE CYCYLE 6-82.1Supercritical technology 2.2 Efficiency 2.3 Definition 3 DESIGN AND WORKING 9-10 3.1 Boiler Design i. Boiler shell 3.2 Working 4 MATERIAL SELECTION 11-134.1 Metallurgical Problems 4.2 Materials used 5 SUPERCRITICAL BOILERS 14-155.1 A typical Supercritical Boilers 5.2 Super and Sub Critical Boilers (comparative study) 6 ADVANCE IN SC TECHNOLGY AND FUTURE IN INDIA 166.1 Natural Gas Production with a Supercritical Geothermal Power 7 CONCLUSION 17 8 REFERENCES 18
  • 6. VI ABSTRACT This paper reviews the major technical and performance aspects of a coal fired plan using the supercritical technology. These include the turbine-generator set, the once-through boiler, and operational issues such as load change, fuel flexibility, and water. Reviewing the possibilities for the design and manufacture of components for supercritical-fired plants in developing countries, the paper notes that the differences between sub critical and supercritical power plants are limited to a relatively small number of components; primarily the feedwater pumps and the high pressure feedwater train equipment. All of the remaining components, common both types of plants, can be manufactured in developing countries. The paper concludes with a review of the Schwarze Pumpe - the world's largest supercritical lignite fired steam power plant.The primary purpose of the study is to assess whether supercritical thermalplant technology is a proven and mature commercial technology and whether .They operate at supercritical pressure. In contrast to a "subcritical boiler", a supercritical steam generator operates at such a high pressure (over 3,200 psi or 22 MPa) that actual boiling ceases to occur, the boiler has no liquid water - steam separation. There is no generation of steam bubbles within the water, because the pressure is above the critical pressure at which steam bubbles can form. It passes below the critical point as it does work in a high pressure turbine and enters the generator's condenser. This results in slightly less fuel use and therefore less greenhouse gas production. The term "boiler" should not be used for a supercritical pressure steam generator, as no "boiling" actually occurs in this device.
  • 7. VII 1 INTRODUCTION 1.1 Basic Rankine Cycle: The Rankine cycle is the oldest functional heat cycle utilized by man. The Rankine cycle is the very a basic vapor power cycle which is adopted in all the thermal power plants. It is a four step process (Figure 1.1) which involves the heating of the working fluid to its saturation temperature and vaporizing it isothermally, expanding the vapor on a turbine (work cycle), condensing the steam isothermally to the liquid phase and pumping it back to the boiler. Figure 1.1.1 Basic Rankine Cycle Figure 2 represents the temperature-entropy diagram for the simplest version of the Rankine cycle. Although this simple version is rarely used it gives a very clear and simple picture on the working of the cycle. Process 1-2 is the pumping of the working fliud (water) into the boiler drum. The power required is derived from the overall power developed. Process 2-3 is the heating of the water upto its saturation temperature (100°C at 1 atm pressure for water) is reached and then isothermal heating of the water where the
  • 8. VIII phase change from liquid to vapor occurs. Points 3 lie on the saturated vapor line. The steam here is completely dry. Process 3-4 is the adiabatic expansion of the vapor/steam on the turbine to obtain mechanical work. It is an isentropic process. The temperature of the steam is reduced and it falls below the saturated vapor line. The dryness fraction is reduced to less than one and a mixed liquid vapor phase is present. Process 4-1 is the condensation process. This mixture is condensed in a condenser isothermally and brought to the liquid phase back to the pump. FIGURE 1.1.2 Temperature vs. Entropy diagram for Rankine cycle The steam is however, usually, superheated so as to obtain more work output. Increasing the superheat to greater extent would lead to more work output. However the energy spent in superheating the fuel is also high. The overall effect is an increase in the thermal efficiency since the average temperature at which the heat is added increases. Moisture content at the exit of the steam is decreased as seen in the figure 1.3. Superheating is usually limited to 620°C owing to metallurgical considerations.
  • 9. IX Figure1.1.3 Rankine cycle with superheating 1.2 Energy Analysis of the Rankine Cycle: All four components in the Rankine Cycle (pump, boiler, turbine and condenser) are steady flow devices and thus can be analyzed under steady flow processes. K.E and P.E changes are small compared to work and heat transferred and is thereby neglected. Thus the steady flow equation (per unit mass) reduces to: Q+hini = W+hfinal Boiler and condenser do not involve any work and pump and turbine are assumed to be isentropic. The conservation of Energy relation for each device is expressed as follows:  Steam turbine: As the expansion is adiabatic (Q=0) and isentropic (S3=S4), then, W3-4=Wturbine= (h3-h4) kJ/kg
  • 10. X  Condenser: Heat rejected in the condenser, Q4-1+h4=h1+W4-1 Since W4-1=0, Q4-1=h1-h4 Thus, Q4-1=-(h4-h1) kJ/kg  Pump: Work required to pump water: Wpump=h1-h2 kJ/kg (-ve work)  Boiler: Heat added in boiler: Q2-3=h3-h2 kJ/kg=h3-h1-Wpump kJ/kg Thus, the Rankine Efficiency=Work done/Heat added = (h3-h4-Wp) / (h3-h1-Wp) Neglecting feed pump work as it is very small compared to other quantities, the efficiency reduces to: ηrankine= (h3-h4) / (h3-h1). 1.3 Factors increasing the Rankine Efficiency: i. Lowering the condenser pressure: Lowering the condenser pressure would lead to the lowering of temperature os steam. Thus for the same turbine inlet state, more work is obtained at lower temperatures.
  • 11. XI This method though cannot be extensively used as it reduces the dryness fraction x of the steam. This is highly undesirable as it decreases the turbine efficiency is reduced due to excessive erosion of the turbine blades. ii. Superheating the steam to high temperature: There is an increase in the work output if superheating of steam is done. It increases the thermal efficiency as the average temperature at which heat is added increases. There is also another benfit of superheating; the steam at the exit of the turbine is drier than in case of non superheated steam. iii. Increasing the boiler pressure: Increasing the boiler pressure raises the average temperature at which heat is added and thereby increases the theramal efficiency. However the dryness fraction decreases for the same exit temperature of the boiler. This problem can be solved by employing reheating procedure. If however the boiler pressure is raised to supercritical point greater efficiency is obtained as the latent heat absorbed during phase change is reduced to zero.
  • 12. XII 2 SUPERCRITICAL RANKINE CYCYLE 2.1 Supercritical technology: When temperature and pressure of live steam are increased beyond the critical point of water, the properties of steam will change dramatically. The critical point of water is at 374 °C and 221.2 bar (218 atm), Figure 2.1, and it is defined to be the point where gaseous component cannot be liquefied by increasing the pressure applied to it. Beyond this critical point water does not experience a phase change to vapor, but it becomes a supercritical fluid. Supercritical fluid is not a gas or liquid. It is best described to be an intermediate between these two phases. It has similar solvent power as liquid, but its transport properties are similar to gases. Figure 2.1.1 Phase diagram of water 2.2Efficiency: The Rankine cycle can be greatly improved by operating in the supercritical region of the coolant. Most modern fossil fuel plants employ the
  • 13. XIII supercritical Rankine Steam Cycle which pushes the thermal efficiency of the plant (see equation 4) into the low to mid 40% range. ηsupercritical = (h2-h1-h3+h4 )/( h2-h1) -(eqn 4) 2.2 Definition: Figure 2.2.1 T-S diagram for supercritical Rankine cycle For water, this cycle corresponds to pressures above 221.2 bar and temperatures above 374.15°C (647.3 K). The T-S diagram for a supercritical cycle can be seen in Figure 6. With the use of reheat and regeneration techniques, point 3 in Figure 2.1, which corresponds to the T-S vapor state of the coolant after it has expanded through a turbine, can be pushed to the right such that the coolant remains in the gas phase. This simplifies the system by eliminating the need for steam separators, dryers, and turbines specially designed for low quality steam.
  • 14. XIV Material Concerns: The primary concern with this cycle, at least for water, is the material limits of the primary and support equipment. The materials in a boiler can be exposed to temperatures above their limit, within reason, so long as the rate of heat transfer to the coolant is sufficient to “cool” the material below its given limit. The same holds true for the turbine materials. With the advent of modern materials, i.e. super alloys and ceramics, not only are the physical limits of the materials being pushed to extremes, but the systems are functioning much closer to their limits. The current super alloys and coatings are allowing turbine inlet temperatures of up to 700°C (973 K). the fourth generation super alloys with ruthenium mono-crystal structures promise turbine inlet temperatures up to 1097°C (1370 K). Special alloys like Iconel 740, Haynes 230, CCA617, etc. are used. The metallurgical challenges faced and solutions:  Normal Stainless steel proves of absolutely no use in building SC and USC Boilers.  The high temperature and pressure in the boiler induce huge amount of stresses and fatigue in the materials. Also chances of oxidation are very high at such high temperature and pressure.  To resist these stress levels and oxidation different advanced materials and alloys should be introduced.  Also they should me machinable and weldable. This is a great metallurgical challenge.
  • 15. XV 3 DESIGN AND WORKING 3.1 Boiler Design: The design of Super and Ultra supercritical boilers (also called as Benson Boiler) is very critical as the working pressures of these boilers are very high. The boiler shells, the economizer unit, super heaters, air preheaters are specially designed. Their location is also of great significance. i. Boiler shell: As shown in the figure 3.1 the geometry of the boilers and the configuration of the inlets determine the recirculation pattern inside boiler. The intensive recirculation created in the symmetric boiler results in a more uniform temperature field, lower temperature peaks, moderate oxygen concentration and complete burnout of the combustible gases and char Fig 3.1.1 Predicted Recirculation inside the combustion chamber Table 3.1 lists the peak temperatures and burnout for designs A, B and C. the table also lists the standard deviations of the predicted temperature and oxygen fields. The lowest values for C indicate the higher degree of homogeneity. Thus the symmetrical boiler seems to be the most suitable design.
  • 16. XVI ii. Location of burners: The number of burners in the boiler shell is also of prime importance. Amongst all of them the downfired boilers are most suitable and advantageous. Table 3.2 gives a clear idea. iii. Boiler dimensions: One of the most important advantages of HTAC applications are high heat fluxes. Thus, compact combustion chambers can be built and the investment costs can be lowered. The fourth calculation series was carried out in order to find the combustion chamber dimensions which can, on one hand, ensure an efficient heat exchange between combustion gas and water/steam mixture and on the other hand, ensure high values of firing density. Three different sizes are tested and they are named in as the small boiler, the medium size boiler and the large boiler .It has been observed (see Table 3.3) that the small boiler is too short. At the top a region of high temperatures exists and its enthalpy cannot be efficiently used. On the contrary, in the large boiler although the heat fluxes areuniform, they are two times lower than in the medium size boiler. Therefore, the medium size boiler configuration is chosen for further investigations. Small boiler Medium size boiler Large boiler Firing Density kW/m3 774 238 89 Outlet temperature, K 1805 1558 1299 Table3.1.1 Results of the boiler size determination 3.2 Working: As already discussed, the working of Supercritical Boilers is similar to the working of sub-critical boilers. It works on the supercritical rankine cycle. Most supercritical boilers are being run at operating pressures above of 235 bars. The working of ultra supercritical boilers has operating pressures above 273 bars
  • 17. XVII 4 MATERIAL SELECTION 4.1 Metallurgical Problems: The available materials today like stainless steel which are usually used for boiler parts are not suitable for SC and USC boilers. They do not have the enough creep strength to resist the high pressure. Also there is high rate of oxidation at such high temperature and pressures which are beyond the capability of these materials to resist. Capable, qualified materials must be available to the industry to enable development of steam generators for SC steam conditions. Major components, such as infurnace tubing for the waterwalls, superheater/ reheater sections, headers, external piping, and other accessories require advancements in materials technology to allow outlet steam temperature increases to reach 760°C (1400F). Experiences with projects such as the pioneering Philo and Eddystone supercritical plants and the problems with the stainless steel steam piping and superheater fireside corrosion provided a valuable precautionary lesson for SC development. Industry organizations thus recognized that a thorough program was required to develop new and improved materials and protection methods necessary for these high temperature steam conditions. 4.2 Materials used: The materials used should be sustainable to the very high pressure being developed and should not get oxidized due to the very high temperature. Different high temperature materials are being used like 9 to 12% ferritic steels T91/P91, T92/P92, T112/P122 steel, Advanced Austenitic alloys TP347, HFG, Super 304, Nickel and chrome-nickel super alloys like Inconel 740. Table 4.2 gives a very brief idea about the boiler materials used for different parts of the boiler.
  • 18. XVIII Heat surface Tube material Header material Economiser SA-210 C SA-106 C Furnace Walls SA-213 T12 SA-106 C Super heater/Reheater SA-213 T12 SA-213 T23 SA-213 TP 304H SA-213 TP347HFG SUPER 304H SA-335 P12 SA-335 P91 SA-335 P911 Steam Piping SA 335 P91 Table 4.2.1 Materials for different boiler parts The materials for the other parts of the power plant (like turbine) also must be sustainable for the super critically heated steam. The following table gives a detail idea on the turbine materials of a plant operating on a supercritical cycle. (Table 4.3)
  • 19. XIX Table 4.2.2 Materials for other parts The following figures show some of the materials used for SC and USC boilers. Iconel 740 is widely used for steam pipings in almost all of them. Figure 4.1 TP347HFG Figure 4.2 Iconel 740 Component 1,050° F 1,150 °F 1,300° F 1,400 °F Casings (shells, valves, steam chests, nozzles) CrMoV (cast) 10CrMoVMb 9–10% Cr (W) 12CrW (Co) CrMoWVNbN CF8C- Plus CCA617 Inconel 625 Nimonic 263 CCA617 Inconel 740 CF8C- Plus Bolting 422 9–12% CrMoV Nimonic 80A 9–12% CrMoV CrMoWVNbN Nimonic 105 Nimonic 115 Waspaloy Nimonic 105 Nimonic 115 U700 Rotors/Discs 1CrMoV 12CrMoVNbN 9–12 % CrWCo 12CrMoWVNbN CCA617 Inconel 625 CCA617 Inconel 740 Nozzles/Blades 422 10CrMoVNbN 9–12% CrWCo 10CrMoVCbN Wrought Ni-based Wrought Ni- based
  • 20. XX 5 SUPERCRITICAL BOILERS 5.1 A typical Supercritical Boilers: Largest CFB and first supercritical CFB sold to date is the Lagisza 460 MWe unit Ordered by Poludniowy Koncern Energetyczny SA (PKE) in Poland. The design is Essentially complete with financial closing expected in the first quarter of 2006 at which time Fabrication and construction will commence. The largest capacity units in operation today are the two (2) 300 MWe JEA repowered units which were designed to fire any Combination of petroleum coke and bituminous coals. The physically largest Foster Wheeler boilers in operation are the 262 MWe Turow Units 4, 5, and 6 which were designed to fire a high moisture brown coal. The design and configuration of these units with Compact solids separators and INTREX™ heat exchangers were used as the basis for the Lagisza design as well as for this study. The Lagisza design was adjusted to accommodate a typical bituminous coal and the steam cycle. Figure 5.1.1 The Lagisza 300 MWe plant in Pola
  • 21. XXI 5.2 Super and Sub Critical Boilers (comparative study): There are many advantages of super critical boilers over normal subcritical boilers, the prime advantage being the increased efficiency and reduced emissions. There are many more advantages like no need of steam dryers, higher operating pressures leading to more work output etc. It is thus very important to have a comparative study of both the boilers. Table 5.2.1 Comparison of sub and supercritical boilers Technology Efficiency (%) Steam pressure/temperature Typical emissions Ultra Supercritical 33–35 >242 bar and 593.33°C SO2-0.408 kg/MHh NOx-0.286 kg/MWh CO2-0.96 T/MWh Supercritical 36–40 >221.2 bar and 537°C SO2-0.431 kg/MHh NOx-0.304 kg/MWh CO2-1.02 T/MWh Subritical 42–45 165 bar 537°C SO2-0.445 kg/MHh NOx-0.31 kg/MWh CO2-1.02 T/MWh
  • 22. XXII 6 ADVANCE IN SC TECHNOLGY AND FUTURE IN INDIA 6.2 Supercritical Boilers in India: There haven’t been any supercritical boilers in use in India so far. The European countries, USA, Japan have been using supercritical technology since the last two decades. However, there are upcoming projects to build power plants working under the supercritical technology in India. The National Thermal Power Corporation (NTPC) had entrusted a techno economic study to M/s EPDC for super-critical Vs Sub-critical Boilers for their proposed Sipat STPS (4x500 MW) in Madhya Pradesh. M/s EPDC has recommended that a first step to the introduction of super- critical technology, the most proven steam conditions may be chosen and the most applicable steam conditions in India shall be 246 kg/cm2 , 538° C/566° C. With these steam parameters, M/s EPDC has estimated that the capital cost for a supercritical power station (4x500 MW) shall be about 2% higher than that of sub-critical power plant but at the same time the plant efficiency shall improve from 38.64% to 39.6%. Being a pit head thermal power project, the saving in fuel charges is not justified by increase in fixed charges. Here are some upcoming projects in India:  North Karanpura, Jharkhand – 3x660 MW  Darlipali, Orissa – 4x800 MW  Lara, Chattisgarh – 5x800 MW  Marakanam, Tamilnadu – 4x800 MW  Tanda-II, Uttar Pradesh - 2x660 MW  Meja, Uttar Pradesh - 2x660 MW  Sholapur – 2x660 MW
  • 23. XXIII  New Nabinagar-3x660 MW  Many more projects including 800 MW ultra super critical units under consideration 7 CONCLUSION The supercritical Rankine cycle, in general, offers an additional 30% relative improvement in the thermal efficiency as compared to the same system operating in the subcritical region. The cycle has been successfully utilized in fossil fuel plants but the current available materials prohibit reliable application of the supercritical cycle to nuclear applications. There is much work to be done in order to advance materials to the point where they will be able to reliably withstand the stresses of a supercritical environment inside a nuclear reactor for a designed life span of 60 years. Supercritical boiler technology has matured, through advancements in design and materials. Coal-fired supercritical units supplied around the world over the past several years have been operating with high efficiency performance and high availability.
  • 24. XXIV REFERENCES 1. “Design Aspects of the Ultra-Supercritical CFB Boiler”; Stephen J. Goidich, Song Wu, Zhen Fan; Foster Wheeler North America Corp. 2. “Novel conceptual design of a supercritical pulverized coal boiler utilizing high temperature air combustion (HTAC) technology”; Natalia Schaffel- Mancini, Marco Mancini, Andrzej Szlek, Roman Weber; Institute of Energy Process Engineering and Fuel Technology, Clausthal University of Technology, Agricolastr. 4, 38678 Clausthal-Zellerfeld, Germany; 6 February 2010. 3. “Supercritical (Once Through) Boiler Technology”; J.W. Smith, Babcock & Wilcox, Barberton, Ohio, U.S.A.; May 1998. 4. “Steam Generator for Advanced Ultra-Supercritical Power Plants 700 to 760°C”; P.S. Weitzel; ASME 2011 Power Conference, Denver, Colorado, U.S.A; July 12-14, 2011. 5. “Supercritical boiler technology for future market conditions”; Joachim Franke and Rudolf Kral; Siemens Power Generation; Parsons Conference; 2003. 6. “Steam Turbine Design Considerations for Supercritical Cycles”; Justin Zachary, Paul Kochis, Ram Narula; Coal Gen 2007 Conference;1-3 August 2007. 7. “Technology status of thermal power plants in India and opportunities in renovation and modernization”; TERI, D S Block, India Habitat Centre, Lodi Road, New Delhi – 110003. 8. “Applied Thermodynamics”; Dr. H.N Sawant; January 1992; revised July 2004. 9. “http://en.wikipedia.org/wiki/Boiler#Supercritical_steam_generator”