Project Excellence – Cost Management
Muhammad Saeed PMP
March 19, 2014
Cost Management
March 19, 2014
Cost Management
The project excellence competence matrix has 10 competencies:
• Client relationships
• Expanding business
• Commercial acumen
• Commercial risk management
• Leadership
• Project management
• Service delivery
• Meeting statutory requirements
• Design/solution coordination
• Knowledge management
March 19, 2014
Cost Management
• What is Project Cost Management ?
A group of Halcrow processes involved in planning, estimating,
budgeting, and controlling costs so that the project can be completed
within the approved budget.
• Project cost management is primarily concerned with the cost of the
resources needed to complete project schedule activities
March 19, 2014
Cost Management
• Cost Estimating
• Cost Budgeting
• Cost Control
March 19, 2014
Cost Estimating
• Analogous estimating (Top Down estimating): Activity Duration
Estimating.
• 2. Determine Resource Cost Rate: The unit cost rates, such as staff cost
per hour and bulk material cost per cubic yard should be known.
• 3. Bottom-up estimating: This technique involves estimating the cost of
individual activities or work packages, then summarizing or rolling up
the individual estimates to get a project total.
• 4. Parametric Estimating: Is a technique that uses a statistical
relationship between historical data and other variables (e.g. square
footage in construction, lines of code in software development,
required labor hours) to calculate a cost estimate for a schedule
activity resource.).
• 5. Project Management Software: Computerized tools, such as cost
estimating software applications, computerized spreadsheets and
simulation/statistical tools, are widely used to assist with cost
estimating
March 19, 2014
Cost Estimating
• 6. Vendor Bid Analysis.
• 7. Reserve Analysis: Estimates should include reserves, also called
contingencies (estimated costs to be used at the discretion of the
project manager to deal with anticipated, but not certain, events,
(“known unknowns”)
March 19, 2014
Cost Estimating
• Accuracy of Cost Estimates
• Order of Magnitude Estimate
– Cost estimating done during the concept phase.
– The accuracy of estimates made at this time can only be: from
-25% to +75% (AED 10,000 ± = from AED 7,500 to 17,500).
• Budget Estimate
– Cost estimating done during Early Project Planning Phase.
– The accuracy of estimates made at this time can only be: from
-10% to +25% (from AED 9,000 to AED 12,500).
• Definitive Estimate
– Cost estimating done during End of Planning Phase
– The accuracy of estimates made at this time can only be: from
-5% to +10% (from AED 9,500 to AED 11,000).
March 19, 2014
Cost Budgeting
• Cost Budgeting
• . Cost Aggregation: Schedule activity cost estimates are aggregated by
work packages in accordance with the WBS. The work package cost
estimates are then aggregated for the higher component levels of the
WBS, such as control accounts, and ultimately for the entire project.
• 2. Reserve Analysis: Establishes contingency reserves, such as the
management contingency reserve, that are allowances for unplanned,
but potentially required, changes “unkown unkowns”. Project
manager must obtain approval before obligating or spending this
reserve. IT IS NOT PART OF PROJECT COST BASELINE.
• 3. Parametric modeling: Using project characteristics (or parameters) in
a mathematical model to predict total project costs. Models can be
simple or complex. The model is likely to be reliable if:
– The historical information used to develop the model is accurate.
– The parameters used in the model are readily quantifiable.
– The model is scalable such that it works as well for a very large
project as well as a small one.
March 19, 2014
Cost Budgeting
• 4. Funding Limit Reconciliation: Large variations in the periodic
expenditure of funds are usually undesirable for organizational
operations, Therefore, the expenditure of funds is reconciled with the
funding limits set by the customer or performing organization on
disbursement of funds for the project.
March 19, 2014
Cost Control
• Cost Control What is Cost Control?:-
– Influencing the factors that create changes to the cost baseline.
– Ensuring requested changes are agreed upon.
– Assuring that potential cost overruns do not exceed the authorized
funding periodically and in total for the project.
– Monitoring cost performance to detect variances from the cost baseline.
– Recording all appropriate changes accurately against the cost baseline
– Preventing incorrect, inappropriate, or unapproved changes from being
included in the reported cost or resource usage.
– Informing the appropriate stakeholders of approved changes.
– Acting to bring expected cost overruns within acceptable limits.
– Project cost control searches out the causes of positive and negative
variances and is part of Integrated Change Control
March 19, 2014
Cost Control
Cost control
• 1. Cost change control system: Procedures by which the cost baseline
can be changed. It includes:
– Forms
– Documentation
– Tracking system.
– Approval levels necessary for authorizing changes.
– 2. Performance measurement Analysis: Helps to assess the
magnitude of any variances that will invariably occur, in addition to
the cause of the variance, and to decide if the variance requires
corrective action. The Earned Value Technique (EVT) compares the
cumulative value of the budgeted cost of work performed (earned)
at the original allocated budget amount to both the budgeted cost
of work scheduled (planned) and to the actual cost of work
performed (actual).
March 19, 2014
Cost Control
• 4. Project Performance Reviews: Are meetings held to compare cost performance
over time, schedule activities or work packages overrunning and under running
budget (planned values), milestones due, and milestones met. They are used in
conjunction with:
– Variance Analysis: Comparing actual project performance to planned or
expected performance.
– Trend Analysis: Involves examining project performance over time to
determine if performance is improving or deteriorating.
– Earned value technique: Compares planned performance to actual
performance.
• 5. Project Management Software: Such as computerized spreadsheets, is often
used to monitor PV versus AC, and to forecast the effects of changes or
variances.
• 6. Variance Management: The cost management plan describes how cost
variances will be managed, for example, having different responses to major or
minor problems
March 19, 2014
Cost Management
March 19, 2014
Cost Management
Questions?
March 19, 2014
How to join Project Excellence
• Approach someone you know is a PEx mentor directly
Full list of mentors on the PEx Halnet site (recommended approach)
• Speak to your Regional or BG PEx champion or your office PEx leader
and ask them for advice in recommending a mentor.
• Send an e-mail to the projectexcellence@halcrow.com to register your
interest.
Names on this list are passed on to new mentors seeking mentees.
Note that this approach has the least chances of finding a mentor for you
quickly.
March 19, 2014
References
• Halnet
• Project Excellence (PEx) Web site
• Project management Institute (PMI)
1 von 17

Recomendados

Curcial Factors that affect Cost Management. von
Curcial Factors that affect Cost Management.Curcial Factors that affect Cost Management.
Curcial Factors that affect Cost Management.Ahmed Al-Senosy Ph.D(cand),MSc,PMP,RMP
3.1K views24 Folien
Project cost control techniques von
Project cost control techniquesProject cost control techniques
Project cost control techniquesWissem Amara
364 views11 Folien
Project cost & control von
Project cost & controlProject cost & control
Project cost & controlAMARAYYA
9.3K views19 Folien
Project cost control von
Project cost controlProject cost control
Project cost controlSourabh Modgil
13.7K views16 Folien
Construction Cost Control von
Construction Cost ControlConstruction Cost Control
Construction Cost ControlSunayana Miglani
5.8K views31 Folien
Project Management 5 Cost Management von
Project Management 5 Cost ManagementProject Management 5 Cost Management
Project Management 5 Cost Managementgrmkslideshare
769 views12 Folien

Más contenido relacionado

Was ist angesagt?

Cost & value management von
Cost & value management Cost & value management
Cost & value management kamariya keyur
843 views15 Folien
Cost management plan von
Cost management planCost management plan
Cost management planJody R Flower
2K views8 Folien
PMBoK, discussion #5: Project Cost Management von
PMBoK, discussion #5: Project Cost ManagementPMBoK, discussion #5: Project Cost Management
PMBoK, discussion #5: Project Cost ManagementOleksandr Lutsaievskyi
3.5K views15 Folien
Project cost management von
Project cost management Project cost management
Project cost management PALLA NARASIMHUDU
1.8K views12 Folien
Project Cost Management von
Project Cost ManagementProject Cost Management
Project Cost ManagementHayat Denzi
6.1K views45 Folien
Project Cost Management von
Project Cost ManagementProject Cost Management
Project Cost ManagementKateri Manglicmot
655 views42 Folien

Was ist angesagt?(19)

Project Cost Management von Hayat Denzi
Project Cost ManagementProject Cost Management
Project Cost Management
Hayat Denzi6.1K views
Project Management C8 -cost_estimation_and_budgeting von Izah Asmadi
Project Management C8  -cost_estimation_and_budgetingProject Management C8  -cost_estimation_and_budgeting
Project Management C8 -cost_estimation_and_budgeting
Izah Asmadi4.4K views
Project Cost Management - PMP preparation course von Vladimir Vujovic
Project Cost Management - PMP preparation courseProject Cost Management - PMP preparation course
Project Cost Management - PMP preparation course
Vladimir Vujovic866 views
Project Cost Management - PMP/CAPM von Mudassir Iqbal
Project Cost Management - PMP/CAPMProject Cost Management - PMP/CAPM
Project Cost Management - PMP/CAPM
Mudassir Iqbal29 views
Professional project cost management von Muthu Kumar
Professional project cost managementProfessional project cost management
Professional project cost management
Muthu Kumar487 views
Vijay Prasad’S Views On Earned Value Management In Project von destination
Vijay Prasad’S Views On Earned Value Management In ProjectVijay Prasad’S Views On Earned Value Management In Project
Vijay Prasad’S Views On Earned Value Management In Project
destination274 views
Melbourne streamlining earned value with hd published von InSync Conference
Melbourne streamlining earned value with hd publishedMelbourne streamlining earned value with hd published
Melbourne streamlining earned value with hd published
InSync Conference275 views

Similar a P ex cost management-1

P ex cost management-1 von
P ex cost management-1P ex cost management-1
P ex cost management-1AHMED NADIM JILANI
485 views17 Folien
Preparing cost estimation von
Preparing cost estimationPreparing cost estimation
Preparing cost estimationSomashekar S.M
94 views24 Folien
A brief on project cost management von
A brief on project cost managementA brief on project cost management
A brief on project cost managementImran Jamil
2.2K views29 Folien
PMP Module 4 - Cost von
PMP Module 4 - CostPMP Module 4 - Cost
PMP Module 4 - CostCybrary
619 views24 Folien
7 cost managmenet von
7 cost managmenet7 cost managmenet
7 cost managmenetAla Ibrahim
131 views49 Folien
Project Management Ch 14.ppt von
Project Management Ch 14.pptProject Management Ch 14.ppt
Project Management Ch 14.pptUjalaBatool7
33 views17 Folien

Similar a P ex cost management-1(20)

A brief on project cost management von Imran Jamil
A brief on project cost managementA brief on project cost management
A brief on project cost management
Imran Jamil2.2K views
PMP Module 4 - Cost von Cybrary
PMP Module 4 - CostPMP Module 4 - Cost
PMP Module 4 - Cost
Cybrary619 views
Project Management Ch 14.ppt von UjalaBatool7
Project Management Ch 14.pptProject Management Ch 14.ppt
Project Management Ch 14.ppt
UjalaBatool733 views
Project Accounting.pptx von KSureshBabu9
Project Accounting.pptxProject Accounting.pptx
Project Accounting.pptx
KSureshBabu9346 views
Online PMP Training Material for PMP Exam - Cost Management Knowledge Area von GlobalSkillup
Online PMP Training Material for PMP Exam - Cost Management Knowledge AreaOnline PMP Training Material for PMP Exam - Cost Management Knowledge Area
Online PMP Training Material for PMP Exam - Cost Management Knowledge Area
GlobalSkillup1K views
L4_Cost Management.ppt von MUST
L4_Cost Management.pptL4_Cost Management.ppt
L4_Cost Management.ppt
MUST11 views
Using Earned Value Management Concepts to Improve Commercial Project Performance von LewisFowlerLLC
Using Earned Value Management Concepts to Improve Commercial Project PerformanceUsing Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project Performance
LewisFowlerLLC587 views
Program and Project Financial Management in Project Online von Mike Otranto
Program and Project Financial Management in Project OnlineProgram and Project Financial Management in Project Online
Program and Project Financial Management in Project Online
Mike Otranto1.4K views

Más de AHMED NADIM JILANI

Scaffolding by vn prabhu source facebook group survey & engineering de... von
Scaffolding  by  vn prabhu source facebook group survey  & engineering de...Scaffolding  by  vn prabhu source facebook group survey  & engineering de...
Scaffolding by vn prabhu source facebook group survey & engineering de...AHMED NADIM JILANI
656 views24 Folien
Nanotechnology in civil engineering0 von
Nanotechnology in civil engineering0Nanotechnology in civil engineering0
Nanotechnology in civil engineering0AHMED NADIM JILANI
1.1K views21 Folien
Staadpresentation1 159 von
Staadpresentation1 159Staadpresentation1 159
Staadpresentation1 159AHMED NADIM JILANI
6.2K views21 Folien
Pres staadpro von
Pres staadproPres staadpro
Pres staadproAHMED NADIM JILANI
887 views99 Folien
Corenet montreal 2_13_08_nanotech_materials von
Corenet montreal 2_13_08_nanotech_materialsCorenet montreal 2_13_08_nanotech_materials
Corenet montreal 2_13_08_nanotech_materialsAHMED NADIM JILANI
600 views67 Folien
DESIGN OF STEEL STRUCTURE von
DESIGN OF STEEL STRUCTUREDESIGN OF STEEL STRUCTURE
DESIGN OF STEEL STRUCTUREAHMED NADIM JILANI
25.6K views23 Folien

Más de AHMED NADIM JILANI(20)

Scaffolding by vn prabhu source facebook group survey & engineering de... von AHMED NADIM JILANI
Scaffolding  by  vn prabhu source facebook group survey  & engineering de...Scaffolding  by  vn prabhu source facebook group survey  & engineering de...
Scaffolding by vn prabhu source facebook group survey & engineering de...
AHMED NADIM JILANI656 views

P ex cost management-1

  • 1. March 19, 2014 Project Excellence – Cost Management Muhammad Saeed PMP
  • 2. March 19, 2014 Cost Management
  • 3. March 19, 2014 Cost Management The project excellence competence matrix has 10 competencies: • Client relationships • Expanding business • Commercial acumen • Commercial risk management • Leadership • Project management • Service delivery • Meeting statutory requirements • Design/solution coordination • Knowledge management
  • 4. March 19, 2014 Cost Management • What is Project Cost Management ? A group of Halcrow processes involved in planning, estimating, budgeting, and controlling costs so that the project can be completed within the approved budget. • Project cost management is primarily concerned with the cost of the resources needed to complete project schedule activities
  • 5. March 19, 2014 Cost Management • Cost Estimating • Cost Budgeting • Cost Control
  • 6. March 19, 2014 Cost Estimating • Analogous estimating (Top Down estimating): Activity Duration Estimating. • 2. Determine Resource Cost Rate: The unit cost rates, such as staff cost per hour and bulk material cost per cubic yard should be known. • 3. Bottom-up estimating: This technique involves estimating the cost of individual activities or work packages, then summarizing or rolling up the individual estimates to get a project total. • 4. Parametric Estimating: Is a technique that uses a statistical relationship between historical data and other variables (e.g. square footage in construction, lines of code in software development, required labor hours) to calculate a cost estimate for a schedule activity resource.). • 5. Project Management Software: Computerized tools, such as cost estimating software applications, computerized spreadsheets and simulation/statistical tools, are widely used to assist with cost estimating
  • 7. March 19, 2014 Cost Estimating • 6. Vendor Bid Analysis. • 7. Reserve Analysis: Estimates should include reserves, also called contingencies (estimated costs to be used at the discretion of the project manager to deal with anticipated, but not certain, events, (“known unknowns”)
  • 8. March 19, 2014 Cost Estimating • Accuracy of Cost Estimates • Order of Magnitude Estimate – Cost estimating done during the concept phase. – The accuracy of estimates made at this time can only be: from -25% to +75% (AED 10,000 ± = from AED 7,500 to 17,500). • Budget Estimate – Cost estimating done during Early Project Planning Phase. – The accuracy of estimates made at this time can only be: from -10% to +25% (from AED 9,000 to AED 12,500). • Definitive Estimate – Cost estimating done during End of Planning Phase – The accuracy of estimates made at this time can only be: from -5% to +10% (from AED 9,500 to AED 11,000).
  • 9. March 19, 2014 Cost Budgeting • Cost Budgeting • . Cost Aggregation: Schedule activity cost estimates are aggregated by work packages in accordance with the WBS. The work package cost estimates are then aggregated for the higher component levels of the WBS, such as control accounts, and ultimately for the entire project. • 2. Reserve Analysis: Establishes contingency reserves, such as the management contingency reserve, that are allowances for unplanned, but potentially required, changes “unkown unkowns”. Project manager must obtain approval before obligating or spending this reserve. IT IS NOT PART OF PROJECT COST BASELINE. • 3. Parametric modeling: Using project characteristics (or parameters) in a mathematical model to predict total project costs. Models can be simple or complex. The model is likely to be reliable if: – The historical information used to develop the model is accurate. – The parameters used in the model are readily quantifiable. – The model is scalable such that it works as well for a very large project as well as a small one.
  • 10. March 19, 2014 Cost Budgeting • 4. Funding Limit Reconciliation: Large variations in the periodic expenditure of funds are usually undesirable for organizational operations, Therefore, the expenditure of funds is reconciled with the funding limits set by the customer or performing organization on disbursement of funds for the project.
  • 11. March 19, 2014 Cost Control • Cost Control What is Cost Control?:- – Influencing the factors that create changes to the cost baseline. – Ensuring requested changes are agreed upon. – Assuring that potential cost overruns do not exceed the authorized funding periodically and in total for the project. – Monitoring cost performance to detect variances from the cost baseline. – Recording all appropriate changes accurately against the cost baseline – Preventing incorrect, inappropriate, or unapproved changes from being included in the reported cost or resource usage. – Informing the appropriate stakeholders of approved changes. – Acting to bring expected cost overruns within acceptable limits. – Project cost control searches out the causes of positive and negative variances and is part of Integrated Change Control
  • 12. March 19, 2014 Cost Control Cost control • 1. Cost change control system: Procedures by which the cost baseline can be changed. It includes: – Forms – Documentation – Tracking system. – Approval levels necessary for authorizing changes. – 2. Performance measurement Analysis: Helps to assess the magnitude of any variances that will invariably occur, in addition to the cause of the variance, and to decide if the variance requires corrective action. The Earned Value Technique (EVT) compares the cumulative value of the budgeted cost of work performed (earned) at the original allocated budget amount to both the budgeted cost of work scheduled (planned) and to the actual cost of work performed (actual).
  • 13. March 19, 2014 Cost Control • 4. Project Performance Reviews: Are meetings held to compare cost performance over time, schedule activities or work packages overrunning and under running budget (planned values), milestones due, and milestones met. They are used in conjunction with: – Variance Analysis: Comparing actual project performance to planned or expected performance. – Trend Analysis: Involves examining project performance over time to determine if performance is improving or deteriorating. – Earned value technique: Compares planned performance to actual performance. • 5. Project Management Software: Such as computerized spreadsheets, is often used to monitor PV versus AC, and to forecast the effects of changes or variances. • 6. Variance Management: The cost management plan describes how cost variances will be managed, for example, having different responses to major or minor problems
  • 14. March 19, 2014 Cost Management
  • 15. March 19, 2014 Cost Management Questions?
  • 16. March 19, 2014 How to join Project Excellence • Approach someone you know is a PEx mentor directly Full list of mentors on the PEx Halnet site (recommended approach) • Speak to your Regional or BG PEx champion or your office PEx leader and ask them for advice in recommending a mentor. • Send an e-mail to the projectexcellence@halcrow.com to register your interest. Names on this list are passed on to new mentors seeking mentees. Note that this approach has the least chances of finding a mentor for you quickly.
  • 17. March 19, 2014 References • Halnet • Project Excellence (PEx) Web site • Project management Institute (PMI)

Hinweis der Redaktion

  1. Enter the name of your presentation, sub title and the date. Text should be Arial 24pt Bold for the main title. Subtitles are in Arial 18pt Bold. Font colour should be white.