SlideShare ist ein Scribd-Unternehmen logo
1 von 7
Downloaden Sie, um offline zu lesen
Muhammad Raza Hussain
Page 1 of 7
Muhammad Raza Hussain
PROJECT MANAGER (Projects & Turnarounds) 
 
Permanent Address:  
Gate # 01, Street # 1A, Hassan Abad, Khanewal Road, Multan, Pakistan. 
 
Email Address:muhammadrazah@gmail.com 
 
Mobile Phone Number: +92 336 7305023 (Pakistan) 
 
 
OBJECTIVE 
To join a more progressive organization, which enhance my skills and use the skills as a team player for the 
betterment of organization and to grow as a proficient, innovative and committed person. 
 
EXPERIENCE SUMMARY (25Years 08 Months, Major in Project Management / Turnarounds /Maintenance) 
 
Company  Category  Position  Major Responsibilities  From  To 
Descon 
Engineering 
Qatar L.L.C. 
Oil & gas 
Petrochemicals 
Turnarounds 
Construction 
Project 
Manager / 
Turnaround 
Manager 
Served the company for more than 09 years on 
different projects and turnarounds. 
Plan and execute turnaround. 
Coordinate internal resources and third 
parties/vendors for the flawless execution of 
projects / turnaround. 
Lead execution teams. 
Scope verification. 
Integrates all operations, capital and expense 
projects into turnaround planning and execution. 
Accountable for delivering the planning and 
preparation phase as well as the execution phase 
of the turnarounds / projects. 
As a member of the turnaround leadership team 
and even the project group has participated in 
turnaround improvement initiatives, developing 
and sharing of standard work practices. 
Aug‐2006  Sep‐2015 
J‐Ray 
McDermott 
Middle East 
Inc. UAE 
Construction 
In charge 
Piping / 
Mechanical 
Study job specifications to determine appropriate 
construction methods. 
Monitor site progress including installation of 
required equipment against accepted programs 
and 2‐4 week look ahead .Make recommendation 
where extra sources or alternative work 
processes are required to maintain or increase 
performance. 
Ensure the construction schedule is maintained. 
Dec‐1996  Jul‐2006 
Al Tariq 
Construction 
Pvt. Ltd. 
Construction 
Site            
In charge 
Mechanical 
Supervised the work crew for mechanical related 
job at live lines as well as in green fields per 
approved Procedure according to the 
international codes and standards. 
Prepare and implement program of activities and 
allocate manpower to each and finish every job 
and punch list, final finishing to cope up with the 
systems completion schedule and handover to 
client defect free project as per target date. 
Jan‐1990  Nov‐1996 
   
 
 
Muhammad Raza Hussain
Page 2 of 7
 
PROFESSIONAL EXPERIENCE DETAILS  
 
Company      : Descon Engineering Qatar L.L.C. 
Project / Department    : Turnarounds, Large & Medium Scale Projects 
Sector        : Oil & Gas, Petrochemicals 
Role        : Project Manager / Turnaround Manager 
Duration       : Aug – 2006 ~ to date (09 Year 01 Month) 
Responsibilities   : 
 
 Ensuring organizational capability for the turnaround event by facilitating and actively participating as 
a member of the turnaround project. 
 Ensuring proper representation and leading/motivating the core team responsible for planning Team, 
who is ultimately responsible for scope, resources, risk, and readiness and execution and comprised 
of  members  reporting  directly  to  turnaround  project  manager  as  well  as  specialist  from  plant 
organization. 
 Manage contractor teams and ownership of Maintenance objectives. 
 Ensuring  execution  plans  are  developed  and  documented  for  health  and  safety,  environmental, 
facility sitting, logistics and real estate, operations, inspection and quality, security, cost and schedule 
management, change management, documentation, communication, and training. 
 Ensured that all projects are delivered on‐time, within scope and within budget. 
 Assist in the definition of project scope and objectives, involving all relevant stakeholders and 
ensuring technical feasibility. 
 Ensured resource availability and allocation. 
 Developed a detailed project plan to monitor and track progress. 
 Managed changes to the project scope, project schedule, and project costs using appropriate 
verification techniques. 
 Report and escalate to management as needed. 
 Successfully manage the relationship with the client and all stakeholders. 
 Perform risk management to minimize project risks. 
 Establish and maintain relationships with third parties/vendors. 
 Create and maintain comprehensive project documentation. 
 Hire specialized staff. 
 Making budget estimates team. 
 Risk analysis 
 Coordination of internal resources and third parties/vendors for the flawless execution of projects. 
 Accountable for delivering the planning and preparation phase as well as the execution phase of the 
turnaround. 
 Ensure all work activities are carried out in a safe manner implementing the HSE plan. 
 Identify long lead / critical items procurement in sufficient time to comply with the project schedule. 
Muhammad Raza Hussain
Page 3 of 7
Summary of Turnarounds / Projects Executed through Descon Engineering Qatar’s Platform: 
 
Position  Client   Project / Turnaround  Category 
Project Manager   NGL‐3 Turnaround 
Shutdown Maintenance Works for NGL‐3 Plant, Gas 
Operations, Mesaieed 
Oil & Gas 
Project Manager   RLOC Turnaround 
Shutdown Maintenance Works for RLOC Plant, PP Plant, 
RLIC 
PP 
Project Manager  
Chiyoda Technip Joint 
Venture 
Installation of Tie ‐in work for LP/Mp Steam Header 
during TR‐06 Shutdown for RGX LP/MP/HP Steam System 
Reliability Improvement Project 
Oil & Gas 
Project Manager  
Chiyoda Technip Joint 
Venture 
Train 1/2 = 16/26‐X001 & X004, 19/29‐F002, 29‐F003 and 
12‐Y001 stacks Nozzles, Platform, E&I cable tray 
installation and associated works during May 2014 
Shutdown 
Oil & Gas 
Project Manager   Samsung Engineering   T‐07 November ‐2013Shutdown  Oil & Gas 
Project Manager  
Chiyoda Technip Joint 
Venture 
 WC‐2198+2193 SRU Shutdown (Train‐7)   Oil & Gas 
Project Manager  
Chiyoda Technip Joint 
Venture 
RasGas Train‐6 SRU June 2013 Shutdown (WC‐2197 & 
WC‐2161) 
Oil & Gas 
Project Manager  
Chiyoda Technip Joint 
Venture 
RasGas Train‐6 SRU June 2013 Shutdown (WC 2429, 
Completion Package Feed Preheater, Steam Condensate 
System Hammering AKG‐II) 
Oil & Gas 
Project Manager  
Chiyoda Technip Joint 
Venture 
Ras Gas SRU/AKG Pre Shut Down Works  Oil & Gas 
Site Manager   Qatar Chemicals  Q‐CHEM Modification and shutdown 2012  PP 
Project Manager  
Choyida Almana 
Engineering LLC  
(RGP‐536) Train 1& 2 Start‐up Flare reduction Project‐2nd 
Phase Procurement & Construction (RFS‐139) 
Oil & Gas 
Project Manager  
Choyida Almana 
Engineering LLC  
Flare Elimination at stat‐up of train 4 & 5 Long Loop 
Recycle Project (RFS‐131) 
Oil & Gas 
Project Manager  
Qatar Gas Operating 
Company 
EPC FOR FOUR COMBINED PROJECT ( PROJECTS 6, 7, 8, 
10) 
Oil & Gas 
Project Manager  
Qatar Gas Operating 
Company 
EPC WORK FOR RAS LAFFAN AVENUE THIRD LANE 
ENLARGEMENT AT QG TSF AREA 
Oil & Gas 
Project Manager  
Ras laffan Operating 
Company Turnaround 
2015 TURNAROUND WORKS AT RLOC ‐ MAIN CONTRACT  Oil & Gas 
Project Manager  
Choyida Almana 
Engineering LLC  
SECURITY UPGRADE PHASE‐1 FENCING & HVM PROJECT  Oil & Gas 
Project Manager  
Chiyoda Technip Joint 
Venture 
Isolation and By Pass BAHX 665‐E003 and Sales GAS Back 
up TR‐06 Tie‐ins Project 
Oil & Gas 
Project Manager  
Qatar Gas Operating 
Company 
Provision of 2 Combined Projects   Oil & Gas 
Project Manager  
Qatar Gas Operating 
Company 
Replacement of Elbow, Pipe Spool of Line of SC1004 of 
Train‐1 
Oil & Gas 
Project Manager  
Choyida Almana 
Engineering LLC  
Methanol Convertor (V1107) modification of Pipeline 
Support Services for internal installation and construction 
of Civil foundation 
Oil & Gas 
Project Manager  
Qatar Gas Operating 
Company 
Extension of the Drain Line of 6 Berth Spill Basin until the 
Sea 
Oil & Gas 
Project Manager  
Choyida Almana 
Engineering LLC  
(RGCP‐328) LOW NOX Reduction‐Turbine Frame 7 Train 3 
Project (RFS‐020A) 
Oil & Gas 
Project Manager  
Qatar Gas Operating 
Company 
Provision of Seven Combined Projects for Laffan Refinery  Oil & Gas 
Site Manager   Oryx GTL Plant   Repair Service for ATR headers  Oil & Gas 
Muhammad Raza Hussain
Page 4 of 7
Position  Client   Project / Turnaround  Category 
Project Manager  
Choyida Almana 
Engineering LLC  
RFS‐112‐RGCP‐461 Enhanced Continues Emission 
Monitoring System (36‐X001, 36‐X004 32‐Y002 SD 2013 
Works) 
Oil & Gas 
Project Manager  
Qatar Chemical 
Company  
Construction of Nitrogen line and tie‐in to GASAL 
Nitrogen grid 
Oil & Gas 
Project Manager  
Choyida Almana 
Engineering LLC  
Hot Oil Furnace Burner Replacement  Oil & Gas 
Project Manager  
Choyida Almana 
Engineering LLC  
AKG‐1 (197‐F081) CEMS Project "RGCP 461  Oil & Gas 
Project Manager  
Choyida Almana 
Engineering LLC  
Hot Oil Furnace Burner Replacement Additional Works & 
Claim  
Oil & Gas 
Project Manager  
Choyida Almana 
Engineering LLC  
Construction Works for the Qatar Gas early Mechanical 
Tie‐ins Project‐T‐06 
Oil & Gas 
Project Manager   Technip Middle East   Mechanical Tie‐ins Project‐T‐06  Oil & Gas 
Project Manager   Samsung Engineering   HGO Line Works at laffan refinery   Oil & Gas 
Project Manager   Samsung Engineering  
Installation of Reactor Internal including mutil 
thermocouple  
Oil & Gas 
Project Manager  
Choyida Almana 
Engineering LLC  
(RGCP‐328) LOW NOX Reduction‐Turbine Frame 7 Train 3 
Project (RFS‐020A) 
Oil & Gas 
Project Manager  
Qatar Gas Operating 
Company 
Modification of Inlet Separator in QG2 Inlet Facility   Oil & Gas 
Project Manager  
Qatar Gas Operating 
Company 
Provision of Nine Combined QG projects   Oil & Gas 
Site Manager  
Chiyoda Technip Joint 
Venture 
WC‐2212(TR‐6)662‐E007 Feed Preheater, Steam 
Condensate System Hammering  
Oil & Gas 
Site Manager  
Sin hydro Lussail 
Project 
 Electro Mechanical works for Tunnel Ventilation 
Chambers at Lussail  
Oil & Gas 
Site Manager  
Qatar Gas Operating 
Company 
QG 23 Combined Project Phase II  Oil & Gas 
Site Manager   Ras Gas 
Ras Gas Train 3,4,5 Flare up‐gradation & Gantry Crane 
Project 
Oil & Gas 
In charge QA/QC 
Ras Laffan Olifin 
Company (RLOC) 
Olefin Ethylene Cracker  PP 
In charge 
Mechanical 
Dolphin Energy Limited  Dolphin Upstream and Compression Facilities Project  Oil & Gas 
 
 
Company      : Ray McDermott Middle East Inc. UAE 
Project / Department    : Construction (Onshore / Offshore) 
Sector        : Oil & Gas 
Role        : In charge Piping /Mechanical 
Duration       : Dec – 1996 to Jul – 2006 (10 Years) 
Responsibilities   : 
 
 Establish and maintain effective team working with project contractors to ensure the construction 
work is executed in accordance with company project procedures and to the agreed schedule. 
 Planning  &  Execution  of  Pre‐Commissioning,  Commissioning,  Start‐up  and  Test  Run  activities  for 
various projects. 
 To study all technical drawings, documents and any revisions thereon. 
Muhammad Raza Hussain
Page 5 of 7
 Raise technical query for any conflict information within the project technical document. 
 Prepare comparison report between tender documents and IFC documents in terms of materials 
quantities, specification and scope of work to commercial department to claim any variations in 
project objectives. 
 Prepare value engineering if required by authorized authorities. 
 Assist Construction Manager in advising on construction methodologies in coordination with other 
disciplines/contractors/ subcontractors prior to construction. 
 Assist Construction Manager in supervising the construction in terms of proper method, material 
reservation and optimum output of labor. 
 Engage with planning department to define project activities within the scope of work. 
 Engage with procurement and planning departments for defining the materials required to execute 
the project and provide the technical support required to select the proper materials. 
 Review the technical submittal of materials and ensure its compliance with project specifications. 
 Supervise preparation of full detailed shop drawings required to execute the project. 
 Follow obtaining of drawings and materials approvals. 
 Give full and extensive instruction to his team. 
 Execute the works according to the latest approved revision of drawings and /or instruction of 
authorized authorities. 
 Follow up of progress planning and arranging all its requirements. 
 Monitoring of Subcontractor’s performance. 
 Ensure that any variations and instructions received from the client are incorporated into the latest 
construction issue drawings and auctioned by the construction team. 
 Ensure that the quantity surveyor is aware of any such changes. 
 Pass all instructions issued to him by the authorized representatives to his manager to handle 
contractually prior to commencement.  
 Analyzing and resolving field problems. 
 Reporting to management. 
 Materials take off from contract drawings. 
 Materials requisition. 
 Maintain an awareness of all potential risks to the company’s day to day objectives and progress of 
the works, this applies to commercial risks due to delays, non‐performing direct labour, sub‐
contractors etc and or delays by others (3rd parties), observing and adhering to company PQP’s and 
QHSE plans. 
 Ensure the Operations & Maintenance manuals as well as handover documents are in line with 
contract specification and requirements. 
 Liaise with site engineers to ensure construction is coordinated and recorded as per plans and ensure 
that efficient and effective communications are maintained between the site team and client. 
 Verification  and  acceptance  of  mechanical  completion  packages  in  line  with  the  agreed  system 
handover schedule. 
Muhammad Raza Hussain
Page 6 of 7
 Monitors and co‐ordinates punch list items resulting from construction activities. 
 Maintain good relations with other disciplines and with the client at all times. 
 Ensure that construction hazards and risks are fully considered by contractors and that the 
appropriate mitigation and actions are implemented during the construction phase. 
 
 
 
Company      : Al Tariq Construction Pvt. Ltd. 
Project / Department    : Projects / Construction 
Sector        : Oil & Gas  
Role        : Site In charge Mechanical 
Duration       : Jan – 1990 to Nov – 1996 (06 Years, 11 Months) 
Responsibilities   : 
 
 Preparation, approval and implementation of Quality Control Procedures, Inspection and Test Plans 
and Project Quality Plan. 
 Preparation and approval of Welding Procedures. 
 Carried out Audits to check the conformance of the company systems with ISO 9001, ISO 14001 QCP’s 
and ITP’s. 
 Ensuring that Construction/Manufacturing methods are in line with approved Procedures and are well 
understood by concerned Supervisors in place and focus on Quality cost reduction activities. 
 Maintaining,  updating  and  submitting  the  final  dossier  to  client  as  per  Quality  Control  approved 
Procedures. 
 Communication with Project Manager for any discrepancies, between execution and specifications. 
 Ensuring the proper issuance and follow up of NCR’s. 
 Ensuring that activities like NDT, PWHT and Hydro/Pneumatic Testing are executed as per approved 
Procedures. 
 Responsible for maintaining instrument surveillance for accuracy and calibration by ensuring that all 
IMTE’s under use have calibrated dates. 
 Providing assistance to for all incoming materials inspections, both DESCON purchased and/or Client 
supplied. 
 Preparation and distribution of daily, weekly and monthly reports. 
 Perform  plans;  organizing,  supervising  or  foreman’s  activities  engaged  in  fabrication,  erection  and 
pipefitting  of  pipe  and  spools  in  this  unit,  utilities,  and  offsite  above  ground  piping,  underground 
piping . 
 Coordination with clients for test packs & reinstatements 
 Weld map marking on isometric & support marking 
 Perform line checking as per specification and punch list activities 
 Coordinate to the I/C Piping, Client and inspectors as per specifications and drawing standard. 
 Prepares materials for piping isometric, piping and instrument diagram, mechanical and equipment 
drawings for construction 
Muhammad Raza Hussain
Page 7 of 7
 Prepares as built for piping isometric 
 Assigned  in  the  central  workshop  of  fabrication  of  plant.  Performed  daily  basis  of  the  assigned 
personnel in a safe manner involved in the critical jobs of piping 
 Fabrication & Erection of boiler, pressure vessels, storage tanks, fire water tanks &  exchangers 
 Expert in forming isometrics from plan drawings & vice versa 
 Prepared as built in case of piping isometrics 
 Site data collection, and isometrics & plan drawing formation 
 Ensure work is carried out safely and efficiently and adhere to permit to work system. 
 
EDUCATION 
D.A.E. Mechanical 1993
 
 
PERSONAL INFORMATION 
  Date of Birth       :  July 23, 1970 
  Gender        :  Male 
  Nationality      :  Pakistani 
  Visa Status      :  Citizen 
  Marital Status      :  Married 
  Number of Dependants   :  05 
  Driving License Issued From  :  Pakistan   
 
 
Languages 
 
Urdu, English, Punjabi
 
 
References 
 
References can be furnished on demand. 
 
 
 
 
 
 
_____________________ 
Muhammad Raza Hussain 

Weitere ähnliche Inhalte

Ähnlich wie Muhammad Raza Hussain_Project Manager

Ähnlich wie Muhammad Raza Hussain_Project Manager (20)

Latest Resume
Latest ResumeLatest Resume
Latest Resume
 
Resume
ResumeResume
Resume
 
Tanveer Sr Planning Engineer
Tanveer Sr Planning EngineerTanveer Sr Planning Engineer
Tanveer Sr Planning Engineer
 
Resume of A.H.Sharma (Revised April 14, 2012)
Resume of A.H.Sharma (Revised April 14, 2012)Resume of A.H.Sharma (Revised April 14, 2012)
Resume of A.H.Sharma (Revised April 14, 2012)
 
CV - Emad Fathi PM
CV - Emad Fathi PMCV - Emad Fathi PM
CV - Emad Fathi PM
 
Hitesh Patel Presentation
Hitesh Patel PresentationHitesh Patel Presentation
Hitesh Patel Presentation
 
Resume - Sunil M. Birajdar 2
Resume - Sunil M. Birajdar 2Resume - Sunil M. Birajdar 2
Resume - Sunil M. Birajdar 2
 
avinash chandrashekar-CV
avinash chandrashekar-CVavinash chandrashekar-CV
avinash chandrashekar-CV
 
Resume
ResumeResume
Resume
 
Resume 2016
Resume 2016Resume 2016
Resume 2016
 
MOHAMED AHMED HAMAD
MOHAMED AHMED HAMADMOHAMED AHMED HAMAD
MOHAMED AHMED HAMAD
 
Baba TODAI - Cover Letter
Baba TODAI - Cover LetterBaba TODAI - Cover Letter
Baba TODAI - Cover Letter
 
Baba TODAI - Resume
Baba TODAI - ResumeBaba TODAI - Resume
Baba TODAI - Resume
 
Planner's Resume
Planner's ResumePlanner's Resume
Planner's Resume
 
Copy of Senior Manager
Copy of Senior ManagerCopy of Senior Manager
Copy of Senior Manager
 
Senior Manager
Senior ManagerSenior Manager
Senior Manager
 
Vageesh Presentation
Vageesh PresentationVageesh Presentation
Vageesh Presentation
 
CP Proj Coordinator
CP Proj CoordinatorCP Proj Coordinator
CP Proj Coordinator
 
Zuhair Alshawaf - Resume as of May 2015
Zuhair Alshawaf - Resume as of May 2015Zuhair Alshawaf - Resume as of May 2015
Zuhair Alshawaf - Resume as of May 2015
 
Mohamad Abd ElRahman
Mohamad Abd ElRahman Mohamad Abd ElRahman
Mohamad Abd ElRahman
 

Mehr von Muhammad Raza Hussain

Mehr von Muhammad Raza Hussain (6)

Auditors course
Auditors courseAuditors course
Auditors course
 
DevelDeveloping ledadership skills
DevelDeveloping ledadership skillsDevelDeveloping ledadership skills
DevelDeveloping ledadership skills
 
Hse for line managers
Hse for line managersHse for line managers
Hse for line managers
 
Developing effecitve communication skills
Developing effecitve communication skillsDeveloping effecitve communication skills
Developing effecitve communication skills
 
Project manager RLOC qATAR shutdown
Project manager RLOC qATAR shutdownProject manager RLOC qATAR shutdown
Project manager RLOC qATAR shutdown
 
NGL shutdown manager
NGL shutdown managerNGL shutdown manager
NGL shutdown manager
 

Muhammad Raza Hussain_Project Manager

  • 1. Muhammad Raza Hussain Page 1 of 7 Muhammad Raza Hussain PROJECT MANAGER (Projects & Turnarounds)    Permanent Address:   Gate # 01, Street # 1A, Hassan Abad, Khanewal Road, Multan, Pakistan.    Email Address:muhammadrazah@gmail.com    Mobile Phone Number: +92 336 7305023 (Pakistan)      OBJECTIVE  To join a more progressive organization, which enhance my skills and use the skills as a team player for the  betterment of organization and to grow as a proficient, innovative and committed person.    EXPERIENCE SUMMARY (25Years 08 Months, Major in Project Management / Turnarounds /Maintenance)    Company  Category  Position  Major Responsibilities  From  To  Descon  Engineering  Qatar L.L.C.  Oil & gas  Petrochemicals  Turnarounds  Construction  Project  Manager /  Turnaround  Manager  Served the company for more than 09 years on  different projects and turnarounds.  Plan and execute turnaround.  Coordinate internal resources and third  parties/vendors for the flawless execution of  projects / turnaround.  Lead execution teams.  Scope verification.  Integrates all operations, capital and expense  projects into turnaround planning and execution.  Accountable for delivering the planning and  preparation phase as well as the execution phase  of the turnarounds / projects.  As a member of the turnaround leadership team  and even the project group has participated in  turnaround improvement initiatives, developing  and sharing of standard work practices.  Aug‐2006  Sep‐2015  J‐Ray  McDermott  Middle East  Inc. UAE  Construction  In charge  Piping /  Mechanical  Study job specifications to determine appropriate  construction methods.  Monitor site progress including installation of  required equipment against accepted programs  and 2‐4 week look ahead .Make recommendation  where extra sources or alternative work  processes are required to maintain or increase  performance.  Ensure the construction schedule is maintained.  Dec‐1996  Jul‐2006  Al Tariq  Construction  Pvt. Ltd.  Construction  Site             In charge  Mechanical  Supervised the work crew for mechanical related  job at live lines as well as in green fields per  approved Procedure according to the  international codes and standards.  Prepare and implement program of activities and  allocate manpower to each and finish every job  and punch list, final finishing to cope up with the  systems completion schedule and handover to  client defect free project as per target date.  Jan‐1990  Nov‐1996         
  • 2. Muhammad Raza Hussain Page 2 of 7   PROFESSIONAL EXPERIENCE DETAILS     Company      : Descon Engineering Qatar L.L.C.  Project / Department    : Turnarounds, Large & Medium Scale Projects  Sector        : Oil & Gas, Petrochemicals  Role        : Project Manager / Turnaround Manager  Duration       : Aug – 2006 ~ to date (09 Year 01 Month)  Responsibilities   :     Ensuring organizational capability for the turnaround event by facilitating and actively participating as  a member of the turnaround project.   Ensuring proper representation and leading/motivating the core team responsible for planning Team,  who is ultimately responsible for scope, resources, risk, and readiness and execution and comprised  of  members  reporting  directly  to  turnaround  project  manager  as  well  as  specialist  from  plant  organization.   Manage contractor teams and ownership of Maintenance objectives.   Ensuring  execution  plans  are  developed  and  documented  for  health  and  safety,  environmental,  facility sitting, logistics and real estate, operations, inspection and quality, security, cost and schedule  management, change management, documentation, communication, and training.   Ensured that all projects are delivered on‐time, within scope and within budget.   Assist in the definition of project scope and objectives, involving all relevant stakeholders and  ensuring technical feasibility.   Ensured resource availability and allocation.   Developed a detailed project plan to monitor and track progress.   Managed changes to the project scope, project schedule, and project costs using appropriate  verification techniques.   Report and escalate to management as needed.   Successfully manage the relationship with the client and all stakeholders.   Perform risk management to minimize project risks.   Establish and maintain relationships with third parties/vendors.   Create and maintain comprehensive project documentation.   Hire specialized staff.   Making budget estimates team.   Risk analysis   Coordination of internal resources and third parties/vendors for the flawless execution of projects.   Accountable for delivering the planning and preparation phase as well as the execution phase of the  turnaround.   Ensure all work activities are carried out in a safe manner implementing the HSE plan.   Identify long lead / critical items procurement in sufficient time to comply with the project schedule. 
  • 3. Muhammad Raza Hussain Page 3 of 7 Summary of Turnarounds / Projects Executed through Descon Engineering Qatar’s Platform:    Position  Client   Project / Turnaround  Category  Project Manager   NGL‐3 Turnaround  Shutdown Maintenance Works for NGL‐3 Plant, Gas  Operations, Mesaieed  Oil & Gas  Project Manager   RLOC Turnaround  Shutdown Maintenance Works for RLOC Plant, PP Plant,  RLIC  PP  Project Manager   Chiyoda Technip Joint  Venture  Installation of Tie ‐in work for LP/Mp Steam Header  during TR‐06 Shutdown for RGX LP/MP/HP Steam System  Reliability Improvement Project  Oil & Gas  Project Manager   Chiyoda Technip Joint  Venture  Train 1/2 = 16/26‐X001 & X004, 19/29‐F002, 29‐F003 and  12‐Y001 stacks Nozzles, Platform, E&I cable tray  installation and associated works during May 2014  Shutdown  Oil & Gas  Project Manager   Samsung Engineering   T‐07 November ‐2013Shutdown  Oil & Gas  Project Manager   Chiyoda Technip Joint  Venture   WC‐2198+2193 SRU Shutdown (Train‐7)   Oil & Gas  Project Manager   Chiyoda Technip Joint  Venture  RasGas Train‐6 SRU June 2013 Shutdown (WC‐2197 &  WC‐2161)  Oil & Gas  Project Manager   Chiyoda Technip Joint  Venture  RasGas Train‐6 SRU June 2013 Shutdown (WC 2429,  Completion Package Feed Preheater, Steam Condensate  System Hammering AKG‐II)  Oil & Gas  Project Manager   Chiyoda Technip Joint  Venture  Ras Gas SRU/AKG Pre Shut Down Works  Oil & Gas  Site Manager   Qatar Chemicals  Q‐CHEM Modification and shutdown 2012  PP  Project Manager   Choyida Almana  Engineering LLC   (RGP‐536) Train 1& 2 Start‐up Flare reduction Project‐2nd  Phase Procurement & Construction (RFS‐139)  Oil & Gas  Project Manager   Choyida Almana  Engineering LLC   Flare Elimination at stat‐up of train 4 & 5 Long Loop  Recycle Project (RFS‐131)  Oil & Gas  Project Manager   Qatar Gas Operating  Company  EPC FOR FOUR COMBINED PROJECT ( PROJECTS 6, 7, 8,  10)  Oil & Gas  Project Manager   Qatar Gas Operating  Company  EPC WORK FOR RAS LAFFAN AVENUE THIRD LANE  ENLARGEMENT AT QG TSF AREA  Oil & Gas  Project Manager   Ras laffan Operating  Company Turnaround  2015 TURNAROUND WORKS AT RLOC ‐ MAIN CONTRACT  Oil & Gas  Project Manager   Choyida Almana  Engineering LLC   SECURITY UPGRADE PHASE‐1 FENCING & HVM PROJECT  Oil & Gas  Project Manager   Chiyoda Technip Joint  Venture  Isolation and By Pass BAHX 665‐E003 and Sales GAS Back  up TR‐06 Tie‐ins Project  Oil & Gas  Project Manager   Qatar Gas Operating  Company  Provision of 2 Combined Projects   Oil & Gas  Project Manager   Qatar Gas Operating  Company  Replacement of Elbow, Pipe Spool of Line of SC1004 of  Train‐1  Oil & Gas  Project Manager   Choyida Almana  Engineering LLC   Methanol Convertor (V1107) modification of Pipeline  Support Services for internal installation and construction  of Civil foundation  Oil & Gas  Project Manager   Qatar Gas Operating  Company  Extension of the Drain Line of 6 Berth Spill Basin until the  Sea  Oil & Gas  Project Manager   Choyida Almana  Engineering LLC   (RGCP‐328) LOW NOX Reduction‐Turbine Frame 7 Train 3  Project (RFS‐020A)  Oil & Gas  Project Manager   Qatar Gas Operating  Company  Provision of Seven Combined Projects for Laffan Refinery  Oil & Gas  Site Manager   Oryx GTL Plant   Repair Service for ATR headers  Oil & Gas 
  • 4. Muhammad Raza Hussain Page 4 of 7 Position  Client   Project / Turnaround  Category  Project Manager   Choyida Almana  Engineering LLC   RFS‐112‐RGCP‐461 Enhanced Continues Emission  Monitoring System (36‐X001, 36‐X004 32‐Y002 SD 2013  Works)  Oil & Gas  Project Manager   Qatar Chemical  Company   Construction of Nitrogen line and tie‐in to GASAL  Nitrogen grid  Oil & Gas  Project Manager   Choyida Almana  Engineering LLC   Hot Oil Furnace Burner Replacement  Oil & Gas  Project Manager   Choyida Almana  Engineering LLC   AKG‐1 (197‐F081) CEMS Project "RGCP 461  Oil & Gas  Project Manager   Choyida Almana  Engineering LLC   Hot Oil Furnace Burner Replacement Additional Works &  Claim   Oil & Gas  Project Manager   Choyida Almana  Engineering LLC   Construction Works for the Qatar Gas early Mechanical  Tie‐ins Project‐T‐06  Oil & Gas  Project Manager   Technip Middle East   Mechanical Tie‐ins Project‐T‐06  Oil & Gas  Project Manager   Samsung Engineering   HGO Line Works at laffan refinery   Oil & Gas  Project Manager   Samsung Engineering   Installation of Reactor Internal including mutil  thermocouple   Oil & Gas  Project Manager   Choyida Almana  Engineering LLC   (RGCP‐328) LOW NOX Reduction‐Turbine Frame 7 Train 3  Project (RFS‐020A)  Oil & Gas  Project Manager   Qatar Gas Operating  Company  Modification of Inlet Separator in QG2 Inlet Facility   Oil & Gas  Project Manager   Qatar Gas Operating  Company  Provision of Nine Combined QG projects   Oil & Gas  Site Manager   Chiyoda Technip Joint  Venture  WC‐2212(TR‐6)662‐E007 Feed Preheater, Steam  Condensate System Hammering   Oil & Gas  Site Manager   Sin hydro Lussail  Project   Electro Mechanical works for Tunnel Ventilation  Chambers at Lussail   Oil & Gas  Site Manager   Qatar Gas Operating  Company  QG 23 Combined Project Phase II  Oil & Gas  Site Manager   Ras Gas  Ras Gas Train 3,4,5 Flare up‐gradation & Gantry Crane  Project  Oil & Gas  In charge QA/QC  Ras Laffan Olifin  Company (RLOC)  Olefin Ethylene Cracker  PP  In charge  Mechanical  Dolphin Energy Limited  Dolphin Upstream and Compression Facilities Project  Oil & Gas      Company      : Ray McDermott Middle East Inc. UAE  Project / Department    : Construction (Onshore / Offshore)  Sector        : Oil & Gas  Role        : In charge Piping /Mechanical  Duration       : Dec – 1996 to Jul – 2006 (10 Years)  Responsibilities   :     Establish and maintain effective team working with project contractors to ensure the construction  work is executed in accordance with company project procedures and to the agreed schedule.   Planning  &  Execution  of  Pre‐Commissioning,  Commissioning,  Start‐up  and  Test  Run  activities  for  various projects.   To study all technical drawings, documents and any revisions thereon. 
  • 5. Muhammad Raza Hussain Page 5 of 7  Raise technical query for any conflict information within the project technical document.   Prepare comparison report between tender documents and IFC documents in terms of materials  quantities, specification and scope of work to commercial department to claim any variations in  project objectives.   Prepare value engineering if required by authorized authorities.   Assist Construction Manager in advising on construction methodologies in coordination with other  disciplines/contractors/ subcontractors prior to construction.   Assist Construction Manager in supervising the construction in terms of proper method, material  reservation and optimum output of labor.   Engage with planning department to define project activities within the scope of work.   Engage with procurement and planning departments for defining the materials required to execute  the project and provide the technical support required to select the proper materials.   Review the technical submittal of materials and ensure its compliance with project specifications.   Supervise preparation of full detailed shop drawings required to execute the project.   Follow obtaining of drawings and materials approvals.   Give full and extensive instruction to his team.   Execute the works according to the latest approved revision of drawings and /or instruction of  authorized authorities.   Follow up of progress planning and arranging all its requirements.   Monitoring of Subcontractor’s performance.   Ensure that any variations and instructions received from the client are incorporated into the latest  construction issue drawings and auctioned by the construction team.   Ensure that the quantity surveyor is aware of any such changes.   Pass all instructions issued to him by the authorized representatives to his manager to handle  contractually prior to commencement.    Analyzing and resolving field problems.   Reporting to management.   Materials take off from contract drawings.   Materials requisition.   Maintain an awareness of all potential risks to the company’s day to day objectives and progress of  the works, this applies to commercial risks due to delays, non‐performing direct labour, sub‐ contractors etc and or delays by others (3rd parties), observing and adhering to company PQP’s and  QHSE plans.   Ensure the Operations & Maintenance manuals as well as handover documents are in line with  contract specification and requirements.   Liaise with site engineers to ensure construction is coordinated and recorded as per plans and ensure  that efficient and effective communications are maintained between the site team and client.   Verification  and  acceptance  of  mechanical  completion  packages  in  line  with  the  agreed  system  handover schedule. 
  • 6. Muhammad Raza Hussain Page 6 of 7  Monitors and co‐ordinates punch list items resulting from construction activities.   Maintain good relations with other disciplines and with the client at all times.   Ensure that construction hazards and risks are fully considered by contractors and that the  appropriate mitigation and actions are implemented during the construction phase.        Company      : Al Tariq Construction Pvt. Ltd.  Project / Department    : Projects / Construction  Sector        : Oil & Gas   Role        : Site In charge Mechanical  Duration       : Jan – 1990 to Nov – 1996 (06 Years, 11 Months)  Responsibilities   :     Preparation, approval and implementation of Quality Control Procedures, Inspection and Test Plans  and Project Quality Plan.   Preparation and approval of Welding Procedures.   Carried out Audits to check the conformance of the company systems with ISO 9001, ISO 14001 QCP’s  and ITP’s.   Ensuring that Construction/Manufacturing methods are in line with approved Procedures and are well  understood by concerned Supervisors in place and focus on Quality cost reduction activities.   Maintaining,  updating  and  submitting  the  final  dossier  to  client  as  per  Quality  Control  approved  Procedures.   Communication with Project Manager for any discrepancies, between execution and specifications.   Ensuring the proper issuance and follow up of NCR’s.   Ensuring that activities like NDT, PWHT and Hydro/Pneumatic Testing are executed as per approved  Procedures.   Responsible for maintaining instrument surveillance for accuracy and calibration by ensuring that all  IMTE’s under use have calibrated dates.   Providing assistance to for all incoming materials inspections, both DESCON purchased and/or Client  supplied.   Preparation and distribution of daily, weekly and monthly reports.   Perform  plans;  organizing,  supervising  or  foreman’s  activities  engaged  in  fabrication,  erection  and  pipefitting  of  pipe  and  spools  in  this  unit,  utilities,  and  offsite  above  ground  piping,  underground  piping .   Coordination with clients for test packs & reinstatements   Weld map marking on isometric & support marking   Perform line checking as per specification and punch list activities   Coordinate to the I/C Piping, Client and inspectors as per specifications and drawing standard.   Prepares materials for piping isometric, piping and instrument diagram, mechanical and equipment  drawings for construction 
  • 7. Muhammad Raza Hussain Page 7 of 7  Prepares as built for piping isometric   Assigned  in  the  central  workshop  of  fabrication  of  plant.  Performed  daily  basis  of  the  assigned  personnel in a safe manner involved in the critical jobs of piping   Fabrication & Erection of boiler, pressure vessels, storage tanks, fire water tanks &  exchangers   Expert in forming isometrics from plan drawings & vice versa   Prepared as built in case of piping isometrics   Site data collection, and isometrics & plan drawing formation   Ensure work is carried out safely and efficiently and adhere to permit to work system.    EDUCATION  D.A.E. Mechanical 1993     PERSONAL INFORMATION    Date of Birth       :  July 23, 1970    Gender        :  Male    Nationality      :  Pakistani    Visa Status      :  Citizen    Marital Status      :  Married    Number of Dependants   :  05    Driving License Issued From  :  Pakistan        Languages    Urdu, English, Punjabi     References    References can be furnished on demand.              _____________________  Muhammad Raza Hussain