This document summarizes a lecture on project time management. It discusses 6 key processes: 1) plan schedule management, 2) define activities, 3) sequence activities, 4) estimate activity resources, 5) estimate activity durations, and 6) develop schedule. For each process, it outlines the inputs, tools and techniques, and outputs as defined in the Project Management Body of Knowledge. The lecture also provides examples and additional details for several scheduling techniques.
2. Lecture 06 : Project Time Management (2/31)
1.Plan Schedule Management (Planning)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
T i m e M a n a g e m e n t
6.1 Plan Schedule Management
Inputs :
Project Management Plan
Project Charter
Enterprise Environmental Factors
Organizational Process Assets
Tools and Techniques :
Expert Judgment
Analytical Techniques
Meetings
Outputs :
Schedule Management Plan
4. Lecture 06 : Project Time Management (4/31)
1.Plan Schedule Management (Planning)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Scheduling Management Plan:
It’s a component of the project management plan.
It shows how you are going to develop, monitor, and control the schedule.
It can establish the following:
scheduling methodology and the scheduling tool to be used.
Acceptable accuracy of activity duration estimates.
Units of measure (hour / day / week).
Process and frequency to update the status and record progress.
Allowed variance before some action needs to be taken (thresholds).
Rules of performance measurement (Percent complete, EVM).
Formats and frequency for the various schedule reports.
O
5. Lecture 06 : Project Time Management (5/31)
2. Define Activities (Planning)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
T i m e M a n a g e m e n t
6.2 Define Activities
Inputs :
Schedule Management Plan
Scope Baseline
Enterprise Environmental Factors
Organizational Process Assets
Tools and Techniques :
Decomposition
Rolling Wave Planning
Expert Judgment
Outputs :
Activity List
Activity Attributes
Milestone list
6. Lecture 06 : Project Time Management (6/31)
2. Define Activities (Planning)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Rolling Wave Planning :
• The work to be done in the near term is planned in detail. Future work is
planned at a higher level. It is a form of progressive elaboration.
• It’s not excuse for improper planning or ensuring that scope is known.
TT
7. Lecture 06 : Project Time Management (7/31)
2. Define Activities (Planning)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Activity List :
• All activities including product &
project work.
Activity Attributes:
• Includes identification, description,
predecessor, successor, discipline,
area, …etc.
Milestone List :
• Include significant
events through
schedule.
• (Ex: project start,
project end).
O
O
O
8. Lecture 06 : Project Time Management (8/31)
3. Sequence Activities (Planning)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
T i m e M a n a g e m e n t
6.3 Sequence Activities
Inputs :
Schedule Management Plan
Activity List
Activity Attributes
Milestone list
Project scope Statement
Enterprise Environmental Factors
Organizational Process Assets
Tools and Techniques :
Precedence Diagramming Method (PDM)
Dependency Determination
Leads and Lags
Outputs :
Project Schedule Network Diagram
Project document Updates
10. Lecture 06 : Project Time Management (10/31)
3. Sequence Activities (Planning)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Activity on the node:
A
D=2
B
D=3
C
D=5
D
D=4
2
5
7
11
Activity on the Arrow:
A
2 C
5
D
4
B
32
7
7 11
11. Lecture 06 : Project Time Management (11/31)
3. Sequence Activities (Planning)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Applying Leads and Lags : التأخيرات و التعجيالت تطبيق
• Lead : Starting the activity before completing its predecessor
التعجيل أزمنة:له السابق النشاط انهاء قبل النشاط بدء
• Lag : Waiting time between activities
التأخير أزمنة:المتتاليين النشاطين بين انتظار ازمنة عن عبارة
Schedule Network Diagram : الزمني الجدول شبكة مخطط
• Illustrates activities and dependencies between them بينها العالقة و االنشطة توضح
• If duration is added, network can show critical path
للمشروع الحرج المسار بالشبكة يتضح سوف لالنشطة الزمنية المدد اضافة بعد
• If plotted against time , it is called time-scaled schedule network diagram
Schedule Network Diagram Benefits : الشبكة فوائد
• Show dependencies and work flow العمل سير و االعتمادية توضح
• Identify opportunities to compress the schedule الجدول لضغط المتاحة الفرص توضح
12. Lecture 06 : Project Time Management (12/31)
4. Estimate Activity Resources (Planning)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
T i m e M a n a g e m e n t
6.4 Estimate Activity Resources
Inputs :
Schedule Management Plan ▪ Activity List
Activity Attributes ▪ Resource Calendars
Scope Management Plan ▪ Activity Cost Estimates
Enterprise Environmental Factors ▪ Organizational Process Assets
Tools and Techniques :
Expert Judgment
Alternative Analysis
Published Estimating Data
Bottom-up estimating
Project Management Software
Outputs :
Activity Resource Requirements
Resource Breakdown Structure
Project documents Updates
13. Lecture 06 : Project Time Management (13/31)
4. Estimate Activity Resources (Planning)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Resource Calendar : للموارد الزمني التقويم سجل
• This document expresses the availability of resource during the planned
period for each activity للنشاط المخططة الفترة اثناء الموارد توفر مدى
Alternative Analysis : البدائل تحليل
• Various levels of resource capability or skills المكانيات متعددة مستويات/الموارد مهارات
• Different size or type of machines (hand vs. automated) الماكينات احجام و انواع
• Make or buy decisions الشراء ام التصنيع قرار(مقاول خالل من او بالموقع المشغول الحديد)
Bottom-Up Estimation : ألعلى أسفل من التقدير
• Used when you are not able to estimate activity resources التقدير تعذر عند
• Decompose work into more details within the activity ًالتفصي اكثر ألجزاء التفكيك
• Then estimate needs الموارد من االحتياجات تقدير ثم
• Then aggregate estimates االحتياجات تجميع ثم
14. Lecture 06 : Project Time Management (14/31)
4. Estimate Activity Resources (Planning)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Activity Resource requirements : النشاط موارد متطلبات
• [1] Types and [2]Quantity of resources required for each activity.
نشاط لكل المطلوبة الموارد كمية و نوع
Resource Breakdown Structure
• Hierarchical structure of identified resources. تحديدها تم التي للموارد هرمي هيكل
• Can be classified by category ( Labor, material, equipment, supplier)
للنوع ًاطبق تصنيفها يتم ان يمكن(عمالة,مواد,معدات,موردين)
• May include other info like skill, efficiency, ….etc. اخرى معلومات تتضمن ان يمكن
Notes
• Estimates should be based on WBS األعمال تجزئة هيكل على التقديرات تعتمد ان يجب
• Use historical info to improve accuracy السابقة المعلومات استخدم الدقة لتحسين
• PM estimates not just accept constraints بالقيود يقبل فقط ليس و يقدر المشروع مدير
• Estimates can be reduced by reducing risks المخاطر بتقليل التقديرات تقليل يمكن
• PM must meet any agreed-upon estimates
عليها المتفق التقديرات بتحقيق يلتزم ان يجب المشروع مدير
15. Lecture 06 : Project Time Management (15/31)
5. Estimate Activity Duration (Planning)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
T i m e M a n a g e m e n t
6.5 Estimate Activity Duration
Inputs :
Schedule Management Plan ▪ Activity List
Activity Attributes ▪ Activity Resource Requirements
Resource Calendars ▪ Project scope Statement
Risk Register ▪ Resource Breakdown Structure
Enterprise Environmental Factors ▪ Organizational Process Assets
Tools and Techniques :
Expert Judgment
Analogous Estimating
Parametric Estimating
Three-Point Estimates
Group Decision-Making Techniques
Reserve Analysis
Outputs :
Activity Duration Estimates
Project document Updates
16. Lecture 06 : Project Time Management (16/31)
5. Estimate Activity Duration (Planning)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
One Point Estimate : واحدة دفعة التقدير(حسابات أي بدون)
• Based on expert judgment, history, or guessing بالتخمين او سابقة معلومات او بالخبرة
• Used if not required high probable schedule دقيق بيان مطلوب يكن لم اذا يستخدم
• This method forces estimator into padding الحشو على بالتقدير يقوم من تجبر
Padding : الحشو
• Adding extra (time or cost) when no enough information available
المتاحة المعلومات كفاية عدم بسبب التقديرات عمل اثناء تكلفة او وقت زياد عن عبارة الحشو
• PM should provide team with enough information and prevent padding.
الحشو يمنع ان يحاول و الكافية بالبيانات العمل فريق يزود المشروع مدير
• If we had to consider padding, this should be addressed in risk
management process.
المخاطر ادارة عمليات في ذلك يذكر ان يجب الحشو الستخدام االضطرار عند
17. Lecture 06 : Project Time Management (17/31)
5. Estimate Activity Duration (Planning)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Analogous Estimate : التناظري التقدير(السابقة البيانات خالل من)
• Using information from similar previous projects سابقة مشاريع من بيانات باستخدام
• Used when there is a limited amount of info. المعلومات من محدود قدر وجود عند
• Less time/cost consuming but less accurate دقة االقل لكن و التكلفة و الوقت في األقل
• EX: we will use 3 days for activity duration because in the last two times it
took 3 days. أي ثالثة في السابقتين المرتين بتنفيذه قمنا ألننا أيام بثالثة النشاط مدة تقدير تمام
Parametric Analysis : البارامتري التقدير(المستنتجة العالقات او بالمعدالت)
• Deduction of mathematical relationship between historical data then use it
to calculate an estimate. التقدي لحساب استخدامها ثم السابقة البيانات من حسابية عالقة استنتاجر
• Ex: Painting one square meter takes two hours, or design takes 15% of
total project duration. التصميم او ساعتين يستهلك المسطح المتر دهان15%المشروع مدة من
• Results of this method are heuristic and called “rule of thumb”.
استرشادية تكون الطريقة هذه من النتائج
18. Lecture 06 : Project Time Management (18/31)
5. Estimate Activity Duration (Planning)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Three-Point Estimate : الثالثة النقاط تقدير
• Also called PERT (Program Evaluation and Review Technique)
• O : Optimistic duration المتفائل الزمن(فيه النشاط انجاز تم زمن أقل)
• P : Pessimistic duration المتشائم الزمن(فيه النشاط انجاز تم زمن أكبر)
• M : Most likely duration األفضل الزمن(ًاحدوث األكثر و المعتاد الزمن)
• EAD : Expected activity duration = (P+4M+O) / 6 النشاط النجاز المتوقعة المدة
• SD : Standard Deviation SD = (P-O) / 6 المعياري االنحراف
• V : Variance V = (SD)2 االنحراف
• R : Range = (EAD-SD : EAD+SD ) المدي
Reserve Analysis : االحتياطي تحليل
• Connect estimation to risk management process المخاطر ادارة بعمليات التقدير يربط
• There are two types of reserve: لالحتياطي نوعان يوجد
1. Contingency Reserve : For remaining risks after planning risk responses
الطوارئ احتياطي:المخاطر تخطيط بعد المتبقية للمخاطر
2. Management Reserve : For unforeseen risks. االدارة احتياطي:معروفة الغير للمخاطر
19. Lecture 06 : Project Time Management (19/31)
6. Develop Schedule (Planning)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
T i m e M a n a g e m e n t
6.6 Develop Schedule
Inputs :
Schedule Management Plan ▪ Activity List
Activity Attributes ▪ Project Schedule Network Diagram
Activity Resource Requirements ▪ Resource Calendars
Activity Duration Estimates ▪ Project scope Statement
Risk Register ▪ Project Staff Assignments
Resource Breakdown Structure ▪ Enterprise Environmental Factors
Organizational Process Assets
Tools and Techniques :
Schedule Network Analysis ■ Critical Path Method
Critical Chain Method ■ Resource Optimization Techniques
Modeling Techniques ■ Leads and Lags
Schedule Compression ■ Scheduling Tool
Outputs :
Schedule Baseline ■ Project Schedule
Schedule Data ■ Project Calendars
Project Management Plan Updates ■ Project document Updates
20. Lecture 06 : Project Time Management (20/31)
6. Develop Schedule (Planning)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Schedule Network Analysis : الزمني الجدول شبكة تحليل
• A technique that generate schedule (activity start and finish dates).
الزمني الجدول لعمل يستخدم شبكي اسلوب(االنشطة نهاية و بداية تواريخ)
• It employs various analytical techniques like critical path method, critical
chain method, what-if analysis, and resource leveling.
ماذا و الحرجة السلسلة و الحرج المسار مثل متعددة تحليلية تقنيات بتوظيف يقوم-الموارد تسوية و لو
Critical Path method : الحرج المسار طريقة
• This method calculates start and finish dates without regard for any
resource limitation by performing forward and backward pass analysis.
خلفي و امامي مشوارين تحليل طريق عن الموارد في عجز اي اعتبار بدون االنشطة أزمنة بحساب تقوم
• Critical path normally characterized by zero total float.
صفر تساوي اجمالية سماح فترة لها سكون عادة الحرج المسار على االنشطة
• Many critical path in the project will increase risk
المخاطر يزيد سوف بالمشروع حرج مسار من اكثر تواجد
21. Lecture 06 : Project Time Management (21/31)
6. Develop Schedule (Planning)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Critical Path Method (Definitions)
ES : Early Start المبكرة البداية EF: Early Finish المبكرة النهاية
LS : Late Start المتأخرة البداية LF : Late Finish المتأخرة النهاية
TF : Total Float : الكلية السماح فترة(المشروع تأخر دون يتأخرها ان للنشاط يمكن التي)
TFA = ( LFA – EFA ) = ( LSA – ESA )
FF : Free Float : الحر السماح فترة(التالي للنشاط المبكرة البداية تأخر دون النشاط يتأخرها ان يمكن)
FFA = ESB - EFA
TF
ES EF
LS LF
A
B
A B
FF=0
TF
A
B
A
B
FF=X
22. Lecture 06 : Project Time Management (22/31)
6. Develop Schedule (Planning)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Critical Path Method (Example 1)
8
A
Example for Activity
Form
ES D EF
Activity Name
LS TF LF
5
B
2
C
3
D
6
E
4
F
9
G
7
HStart End
Activity
D
(Days)
Dependency
A 8 Start
B 5 Start
C 2 Start
D 3 A
E 6 A, B
F 4 C
G 9 D
H 7 D, E
Consider all relationships are FS=0
23. Lecture 06 : Project Time Management (23/31)
6. Develop Schedule (Planning)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Critical Path Method (Example 1 Solution)
0 8 8
A
0 0 8
Example for Activity
Form
ES D EF
Activity Name
LS TF LF
0 5 5
B
3 3 8
0 2 2
C
15 15 17
8 3 11
D
9 1 12
8 6 14
E
8 0 14
2 4 6
F
17 15 21
11 9 20
G
12 1 21
14 7 21
H
14 0 21
Start End
21
21
0
0
Notes :
• Critical Path is : A – E – H
• FFB = 3
Activity
D
(Days)
Dependency
A 8 Start
B 5 Start
C 2 Start
D 3 A
E 6 A, B
F 4 C
G 9 D
H 7 D, E
Consider all relationships are FS=0
24. Lecture 06 : Project Time Management (24/31)
6. Develop Schedule (Planning)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Critical Path Method (Example 2)
8
A
5
B
2
C
3
D
6
E
4
F
9
G
7
HStart End
SS=1
Activity
D
(Days)
Dependency
A 8 Start : FS=0
B 5 Start : FS=0
C 2 Start : FS=0
D 3 A : FS=0
E 6
A : FS=0
B : FS=0
F 4 C : FS=0
G 9 D : FS=0
H 7
D : FS=0
E : SS=1
25. Lecture 06 : Project Time Management (25/31)
6. Develop Schedule (Planning)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Critical Path Method (Example 2 Solution)
0 8 8
A
0 0 8
0 5 5
B
7 7 12
0 2 2
C
14 14 16
8 3 11
D
8 0 11
8 6 14
E
12 4 18
2 4 6
F
16 14 20
11 9 20
G
11 0 20
11 7 18
H
13 2 20
Start End
SS=1
Activity
D
(Days)
Dependency
A 8 Start : FS=0
B 5 Start : FS=0
C 2 Start : FS=0
D 3 A : FS=0
E 6
A : FS=0
B : FS=0
F 4 C : FS=0
G 9 D : FS=0
H 7
D : FS=0
E : SS=1
Notes :
• Critical Path is : A – D – G
• FFB = 0
26. Lecture 06 : Project Time Management (26/31)
6. Develop Schedule (Planning)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Critical Chain Method : الحرجة السلسلة طريقة
• After developing the critical path, resource availability is entered to create a
resource-constrained critical path known as critical chain
الحرجة السلسلة لتنتج الجدول على الموارد اتاحة مدى ادخال يتم الحرج بالمسار الزمني الجدول انشاء بعد
• Critical chain method adds duration buffers to manage uncertainty.
زمنية مدد اضافة يتم(حماية آلية)التأكد عدم الدارة(الشك)
• Project Buffer : Placed at the end of the critical chain to protect finish date
المشروع حماية آلية:المشروع انتهاء تاريخ لحماية المشروع نهاية في اضافتها يتم زمنية مدة
• Feeding Buffers : Placed when non-critical chain feeds into critical chain.
التغذية حماية آلية:الحرجة السلسلة الى حرجة غير سلسلة تغذية عند اضافتها يتم زمنية مدة
Resource Leveling : الموارد تسوية
• Leveling the peaks and valleys of resource usage الموارد بمخطط والقيعان القمم تسوية
• Leveling causes schedule slippage and cost increase to response for
resource constraints. الموارد على للقيود استجابة التكاليف زيادة و الجدول النزالق تؤدي التسوية
27. Lecture 06 : Project Time Management (27/31)
6. Develop Schedule (Planning)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
What-If scenario : االفتراضي السيناريو تحليل
• Performed to compute different scenarios such as delaying a major
component delivery or a drop in currency exchange rate.
هبوط او هامة توريدات تأخر مثل تحدث قد التي المختلفة السيناريوهات تأثير لدراسة زمني تحليل اجراء يتم
العملة الصرف سعر.
• This technique is used to assess the feasibility of the schedule under
different conditions and also for preparing contingency plans.
الطوارئ خطط اعداد في ايضا و المختلفة الظروف تحت الزمني البرنامج جدوى تقييم في يستخدم
• The most common technique is Monte Carlo Analysis
كارلو مونت اسلوب هو التحليل هذا الجراء شيوعا األكثر االسلوب
Schedule compression : الزمني الجدول ضغط
• 1- Fast Track : Performing activities in parallel السريع التعاقب:التوازي على التنفيذ
• 2- Crashing : A time and cost trade-off is done to obtain the most
compression for the least cost.
(Ex: Working over time , adding resources, or paying to expedite delivery)
التعجيل:كلفة اقل مقابل زمني انظغاط اكبر على للحصول التكاليف و الوقت بين الموازنة.
28. Lecture 06 : Project Time Management (28/31)
6. Develop Schedule (Planning)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Project Schedule : الزمني الجدول
• The main output for this process, it can be graphically represented in
different formats such as: milestone chart, bar chart, or network diagram.
الهامة المخرجات احد الزمني الجدول يعد,الشريطية المخططات او األهداف بمخططات تمثيله يمكن و
الشبكية المخططات او
ID Activity Name Duration Oct Nov Dec Jan
10 Substructure 0
20 Superstructure 0
30 Finish Work 0
ID Activity Name Duration Oct Nov Dec Jan
10 Substructure 30
20 Superstructure 45
30 Finish Work 60
Milestone Chart
Bar Chart
29. Lecture 06 : Project Time Management (29/31)
6. Develop Schedule (Planning)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Schedule Baseline : الزمني الجدول أساس خط
• A version of the time schedule that is approved as the baseline and will
never change except for formally approved changes.
األساس خط ليكون والمعتمد الزمني الجدول اصدارات احد,ًارسمي المعتمدة التغيير بأوامر اال يتغير وال
• During the execution, the actual work will be compared against the
baseline to calculate the variance. االنحراف لحساب االساس بخط الفعلي مقارنة يتم
• Note : Milestone report to senior management. Bar chart report to team
• Note : Estimate then Preliminary Schedule then Compress & Risk Mgmt
then Finalize Schedule.
ID Activity Name D Oct Nov Dec Jan Feb
10 Substructure 30
20 Superstructure 45
30 Finish Work 60
30. Lecture 06 : Project Time Management (30/31)
7. Control Schedule (M/C)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
T i m e M a n a g e m e n t
6.7 Control Schedule
Inputs :
Project Management Plan ■ Project Schedule
Work Performance Data ■ Project Calendars
Schedule Data ■ Organizational Process Assets
Tools and Techniques :
Performance reviews ■ Project Management Software
Resource Optimization Techniques ■ Modeling Techniques
Leads and Lags ■ Schedule Compression
Scheduling Tool
Outputs :
Work Performance Information
Schedule Forecasts
Change Requests
Project Management Plan Updates
Project Document Updates
Organizational Process Assets Updates
31. Lecture 06 : Project Time Management (31/31)
7. Control Schedule (M/C)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Performance Reviews : األداء مراجعات
• Measure, compare, and analyze performance (Dates, percent complete,
remaining duration). األداء تحليل و مقارنة و قياس(التواريخ,االنجاز نسبة,المتبقية المدة)
• Decide if corrective or preventive action is required تصحيحي او وقائي اجراء احتياج
Variance Analysis : االنحراف تحليل
• Assess the magnitude of variation to the original schedule baseline.
األصلي بالجدول مقارنة التغيير قيمة(األساس خط)
• Determine the cause & degree of the variance and whether corrective or
preventive action is required. وقائي او تصحيحي اجراء يستوجب وهل االنحراف سبب تحديد
Re-estimating : التقدير اعادة
• Estimation is done in planning, but it’s difficult to estimate well through this
phase. It’s a standard practice to re-estimate the entire remaining part of
the project at least once over project life to ensure that you can meet the
end dates, budget, and other objectives.
المرحلة هذه في دقيقة تقديرات على الحصول الصعب من لكن و التخطيط مرحلة في التقدير عملية تتم.
مازال انه من للتأكد المشروع عمر خالل أخرى مرة االقل على تقدير اعادة عمل القياسية الممارسات من
لها المخطط بالميزانية موعده في المشروع انجاز ًاممكن